Environmental Effects Report Pty Ltd, Asphalt Plant... · Postal Address PO Box 651 Burnie TAS 7320...
Transcript of Environmental Effects Report Pty Ltd, Asphalt Plant... · Postal Address PO Box 651 Burnie TAS 7320...
ABN: 97 107 517 144 ACN: 107 517 144 80 Minna Road PO Box 651 Heybridge TAS 7316 Burnie TAS 7320 Ph: (03) 6431 2999 www.esandd.com.au
Environmental
Effects Report
Roadways Bridgewater
Project No: 7092
Date: August 2020
Document Control
Prepared & Published by: ES&D
Version: Review
File: 7092
Contact: Rod Cooper
Phone No: (03) 6431 2999
Prepared For: Roadways Pty Ltd
Version: Date:
DRAFT 1 M Atkinson ES&D 3/04/2020
REVIEW R Cooper ES&D 8/04/2020
DRAFT 2 M. Atkinson ES&D 14/04/2020
REVIEW B Harpley ES&D 17/06/2020
FINAL M. Atkinson ES&D 25/06/2020
FINAL V2 M. Atkinson ES&D 23/07/2020
This report has been prepared, based on information generated by Environmental Service and Design Pty Ltd from
a wide range of sources. If you believe that Environmental Service and Design Pty Ltd has misrepresented or
overlooked any relevant information, it is your responsibility to bring this to the attention of Environmental Service
and Design Pty Ltd before implementing any of the report’s recommendations. In preparing this report, we have
relied on information supplied to Environmental Service and Design Pty Ltd, which, where reasonable,
Environmental Service and Design Pty Ltd has assumed to be correct. Whilst all reasonable efforts have been made
to substantiate such information, no responsibility will be accepted if the information is incorrect or inaccurate.
This report is prepared solely for the use of the client to whom it is addressed and Environmental Service and Design
Pty Ltd will not accept any responsibility for third parties. In the event that any advice or other services rendered by
Environmental Service and Design Pty Ltd constitute a supply of services to a consumer under the Competition and
Consumer Act 2010 (as amended), then Environmental Service and Design Pty Ltd’s liability for any breach of any
conditions or warranties implied under the Act shall not be excluded but will be limited to the cost of having the
advice or services supplied again. Nothing in this Disclaimer affects any rights or remedies to which you may be
entitled under the Competition and Consumer Act 2010 (as amended). Each paragraph of this disclaimer shall be
deemed to be separate and severable from each other. If any paragraph is found to be illegal, prohibited or
unenforceable, then this shall not invalidate any other paragraphs.
Contents
Executive Summary ............................................................................................................... 1
1 PART A - Proponent Information ..................................................................................... 2
2 PART B- Project Description ............................................................................................ 3
Description of Project ............................................................................................................ 3
Map and site plan .................................................................................................................. 5
Proposal location ................................................................................................................... 6
2.3.1 Climate details .......................................................................................................... 7
2.3.2 Zoning........................................................................................................................ 8
2.3.3 Geology ..................................................................................................................... 8
Rationale and Alternatives .................................................................................................... 9
Planning information ............................................................................................................. 9
Existing activity ...................................................................................................................... 9
3 PART C - Potential Environmental Effects ...................................................................... 10
Air Quality ............................................................................................................................ 10
Water Quality ...................................................................................................................... 12
Noise Emissions ................................................................................................................... 15
Solid Wastes ........................................................................................................................ 15
Environmentally Hazardous Substances ............................................................................. 16
Natural Values ..................................................................................................................... 16
Weeds, Pests and Pathogens .............................................................................................. 18
Greenhouse Gas Emissions and Climate Change ................................................................ 18
Site Contamination .............................................................................................................. 18
Other Off-site impacts ......................................................................................................... 18
Environmental Impacts of Traffic ........................................................................................ 18
Monitoring ........................................................................................................................... 19
Decommissioning and Rehabilitation .................................................................................. 19
4 PART D - Management Commitments ........................................................................... 19
5 PART E - Public Consultation ......................................................................................... 20
Appendix 1 – Stack Test ................................................................................................................ 1
Appendix 2 – Hazardous Chemical Register ................................................................................... 3
Appendix 3 – Traffic Management Plan ......................................................................................... 5
List of Tables Table 1 – Proponent information ................................................................................................................ 2
Table 2 – Consultant Details ......................................................................................................................... 2
List of Figures Figure 1 Site map .......................................................................................................................................... 6
Figure 2 Average wind rose for Hobart ......................................................................................................... 7
Figure 3 Zoning .............................................................................................................................................. 8
Figure 4 Stack location ................................................................................................................................ 11
Figure 5 - Typical liquid effluent ................................................................................................................. 13
Figure 6 Contour drain and settling ponds ................................................................................................. 14
Figure 7 TasVeg 3.0 ..................................................................................................................................... 17
7092 Roadways Bridgewater EER 1
Executive Summary
Roadways Pty Ltd are applying to increase the production of their asphalt plant located in
Bridgewater. The current permit allows 50,000 tons of asphalt to be produced per year and the
applicant is seeking to increase production to 70,000 tons per year.
The asphalt is produced on a supply and demand basis and is therefore likely to have peaks of
production when large batches are required.
The plant does not require upgrade to be able to meet increased demand and production. The
plant is located adjacent to an existing quarry and between 1.3km and 1.7km to residential
sensitive receptors making it an appropriate location for the intensification to occur.
The intensification of the use will not alter potential environmental issues. The intensification
requires the site operate for a longer period of time, not at a higher rate of production. Potential
environmental issues will be managed by the current management systems.
7092 Roadways Bridgewater EER 2
1 PART A - Proponent Information
Table 1 – Proponent information
Entity of proponent Ian Harrington Group
Name of proponent Roadways Pty Ltd
Registered Address 134 Midlands Highway, Bridgewater, 7030
Postal Address P.O. Box 303 Glenorchy 7010
ABN number 28 009 485 812
CAN Number N/A
Site Contact Syd Prickett
Telephone number 0437 104 970/03 6271 3500
Email [email protected]
Environmental Service and Design were engaged to prepare this Environmental Effects Report
(EER). Details are provided in Table 2.
Table 2 – Consultant Details
Organisation Environmental Service & Design
Consultants R. Cooper, M. Atkinson
Address 74 Minna Road Heybridge TAS 7316
Postal Address PO Box 651 Burnie TAS 7320
Contact R. Cooper
Phone 0407 421 486
Email [email protected]
7092 Roadways Bridgewater EER 3
2 PART B- Project Description
Description of Project
The proposal is an increase in production for the existing asphalt batch plant on the Midlands
Highway near Bridgewater.
The operation of the plant is as follows:
• The hotmix plant is fed from stockpiles of aggregates via a conveyor from cold feed bins located on the south side of the plant.
• The aggregates pass through a natural gas dryer and stored in hot bins before being weighed into batches for the production of asphalt.
• The bituminous products are introduced to a hopper and blended with the base media (aggregates) and the product is then ready for delivery.
• The trucks are loaded with the hotmix (asphalt blend) and transported off site to the road/worksite for use. Trucks arriving on site to be loaded with hotmix will line their trays with vegetable oils to improve the unloading procedure at the site they deliver to.
On occasion one of the following lists of material is added to the hotmix on client request
• lime,
• sassawax,
• fine ground limestone (different to lime),
• pelletised cellulose fibre,
• modified polymer,
• crumbed rubber and
• crushed glass can be added into the hotmix on clients request.
The lime and crushed glass are the only items stored on site.
7092 Roadways Bridgewater EER 4
The increase in production does not result in an increase in noise output as the plant rate does
not increase. The increase in production is achieved by an increase in production hours. Similarly,
the wastewater generation rate does not increase, only the time period and so treatment
systems will not suffer shock loads or a decrease in efficiency.
The plant has an existing wet scrubber in place to eliminate a significant amount of potential
pollutants from air emissions.
As the plant is already in operation the timeframe for increased production is dependent upon
the issue of the relevant permits and future production demands.
Applicable acts associated with the plant
• Land Use Planning and Approvals Act 1993
• Environmental Management and Pollution Control Act 1994
• Mineral Resources Development Act 1995
• Water Management Act 1999
• Water Management Regulations 2009
• Weed Management Act 1999
• Weed Management Regulations 2007
• Threatened Species Protection Act 1999
• Aboriginal Heritage Act 1975
• State Policy on Water Quality Management 1997
• Environment Protection Policy (Air Quality) 2004
• Environment Protection Policy (Noise) 2009
• National Greenhouse and Energy Reporting Act 2007
• Weed and Disease Planning and Hygiene Guidelines 2015
The activity is currently a level 2 under EMPCA and the increased production to 70,000 tons will
keep the activity to a level 2 under EMPCA.
The current permit allows 50,000 tons of asphalt to be produced per year. The applicant is
seeking to increase production to 70,000 tons per year. The asphalt will be produced on a supply
and demand basis and is therefore likely to have peaks of production when large volumes are
required.
Operating hours of the site will generally be within 0630 – 1600 hours on each day of the week.
On occasion when a large batch is ordered increased production time will be required. The nature
7092 Roadways Bridgewater EER 5
of the ordering of batches means it is difficult to say how often increased production time will be
required.
The site can operate 24 hours a day Monday to Sunday, depending on the volume of hotmix that
is required, so it will be a rare occurrence. The noise requirements stated in EPN 8061-1 are
complied with at all operating times.
The maximum production rate is 120 tons of hotmix per hour however, the plant does not always
produce at this rate.
It must be noted that the increase in production is demand driven by customer volume and time
requirements. The rate of production remains constant whilst the hours of production expand
to meet increased demand.
Map and site plan
The facility is located on the northern corner of 314 Midland Highway with a property of ID of
3411200 and title reference of 170481/1. It is on a shared site with a Boral quarry located in Figure 1
below.
The landowner is Boral with whom the Ian Harrington Group (Roadways) have a lease agreement
with.
7092 Roadways Bridgewater EER 6
Figure 1 Site map
Proposal location
The asphalt plant is an existing activity operating on the northern corner of the Boral quarry at
Bridgewater (Figure 1). To the north is the Jordan River which forms the northern boundary of
the site and flows into the Derwent River to the south.
There is farmland on the northern side of the Jordan River. Figure 1 shows that the nearest
sensitive receptors (residences) to the site are 1350m to the north east and 1700m to the south.
7092 Roadways Bridgewater EER 7
The current use of the site includes the existing asphalt plant. No intensification or plant upgrade
is required to achieve the proposed production increase which results in no change to the existing
visual or environmental impacts.
2.3.1 Climate details
Figure 2 Average wind rose for Hobart
Average annual rainfall for the Hobart area is 612mm with average annual temperature
maximum of 17.0 oC and minimum of 8.4 oC. The positioning of the site to sensitive receptors
shows that the only potential risk could occur during a 1 in 20-year storm event impacting the
Jordan River and Derwent estuary. Measures are put in place discussed in section 3.2 to cover
any risk.
7092 Roadways Bridgewater EER 8
2.3.2 Zoning
Figure 3 Zoning
Site zoning from the Tasmanian Interim Planning Scheme shows that site is within the General
Industrial zone. Adjoining land is within the General Industrial and Rural Resource zones.
Dwellings, and residentially intended land zones are over 500m distance in all directions. No
other sensitive uses are located nearby
2.3.3 Geology
The MRT geological map shows that the area is underlain with consolidated and unconsolidated
tertiary sediments. There is an erosional line between the Jordan River and the site.
7092 Roadways Bridgewater EER 9
Rationale and Alternatives
The rationale for the increased production on the existing site is to meet future demand for road
construction materials in Tasmania. Roadways Pty Ltd has undertaken extensive consultation
with local councils and state government and are aware of multiple large-scale roadworks
planning. The demand for the asphalt is expected to increase beyond the current permit limit of
50,000 tons within a short period of time.
The impacts of asphalt plants are reduced by increasing production at the existing plant due to
the proximity to the Boral quarry. The carbon footprint of the current and expanded plant is
significantly lower than relocation or construction of a second plant.
No alternative sites with access to the main distribution road network, remoteness from sensitive
receptors and the existing supply of essential materials such as sand and aggregate have been
able to be identified.
Planning information
CT170481/1 is located within the General Industrial Zone. The proposal is for intensification of
an existing land use, Manufacturing and Processing (asphalt plant – Level 1 to Level 2 operation).
The proposal is subject to the discretionary assessment process under the Brighton Interim
Planning Scheme.
The site is covered by the Brighton Industrial Precinct Overlay. The site also contains sections of
land to which the Bridgewater Quarry overlay is applicable and some areas of low landslip risk.
The area to be developed is not within the overlay mapping for the Waterway and Coastal
Protection Code.
Existing activity
The site is currently regulated via EPN 8061/1 which was updated in 2012. Roadways commit to
reviewing the current environmental management plan in line with any updated conditions of
the EPN.
7092 Roadways Bridgewater EER 10
There are have been no public complaints recorded in the current register and no known
breaches or contraventions of the current EPN or environmental law.
3 PART C - Potential Environmental Effects
Air Quality
The existing wet scrubber system is the correct size for the proposed increase production and
has the capacity to scrub for the additional time required. Air emissions from the site have not
had a negative impact on the surrounding vegetation (as seen in section 3.6) which is
predominantly farmland, grassland, and the Boral quarry. An increase in the hours of production
to meet increased demand coupled with the capacity of the existing scrubber is very unlikely to
have a negative impact.
Due to the plants location and distance to sensitive receptors the air emissions from the site are
very unlikely to have a negative effect.
The activity has a point discharge, scrubber which is located on Figure 4.
7092 Roadways Bridgewater EER 11
Figure 4 Stack location
The asphalt plant is using high grade raw materials that produce less air emissions that low-grade
materials. The emissions are scrubbed with storm/wastewater from the sediment ponds and
discharged through the stack.
In accordance with the Environment Protection Policy (Air Quality) 2004, the site is following the
waste avoidance hierarchy by firstly avoiding air emissions where possible, treating what can be
treated and as a final option disposal.
A stack emissions test conducted in 2010 by Millen EMS, shows that the emissions from the stack
are, on average, less than 100 mg/m3 and meet the requirements of the Environment Protection
Policy (Air Quality) 2004. The stack test is attached as Appendix 1
The impact of dust emissions is mitigated by the wet scrubber. The stack is a single point
discharge where dust is likely to be produced. There is also potential for dust emissions from the
stockpiles on site during windy days.
The process of heating bitumen can create an odour. However, it is not considered to be able to
impact on the closest sensitive receptor due the distance (over 500m as shown in section 2.3.2).
Stack
7092 Roadways Bridgewater EER 12
Water Quality
The Jordan River forms the boundary of the site to the north as shown in figure 1. The Jordan
River flows into the River Derwent in a south east direction. The Jordan River is approximately
70m North There are no other surface waters, natural wetlands, or estuaries within 1000m of
site.
The plant is existing on the site and is a previously approved activity. The increase in production
volume will have minimal effect as controls are in place under the current EMP and regulated
under the current EPN.
Water required to fill the settlement ponds is sourced from the Boral mains supply. Once
settlement ponds are filled the system is then a ‘closed loop’ only needing to be topped up as
required from the Boral main as water evaporates.
There is little liquid effluent coming from the site. Figure 5 below shows the typical liquid effluent
produced during the operating period. The rate of liquid effluent leaving the plant will not
increase, however the duration of liquid effluent will increase. This will help ensure that the
wetland system is not overloaded with additional effluent.
It is unlikely there will be impacts of the ecology of the river as it is extremely unlikely there will
be water entering the system.
7092 Roadways Bridgewater EER 13
Figure 5 - Typical liquid effluent leaving site
Figure 6 shows a contour drain constructed between the asphalt plant and the Jordan River to
collect any wastewater of effluent. The drain is designed and constructed to cope with winter
rain events and directs all run-off water to the settling ponds before the water is re-routed to use
in the scrubbers of the stack system. The sediment at the bottom of the ponds is re-used by the
Boral quarry which is a substantial reduce reuse strategy.
7092 Roadways Bridgewater EER 14
Figure 6 Contour drain and settling ponds
The Derwent Estuary Program indicates the site is in the middle reaches of the Derwent Estuary.
Information from the Derwent Estuary program suggests that the main potential source of
contamination from this site is stormwater runoff.
The settling ponds have a capacity of 160m3, 216m3, 112m3 and 500m3. This is a combined total
holding capacity of 988m3.
The existing settling ponds have sufficient capacity to cope with a 1 in 20-year rain event. Data
from the Bureau of Meteorology shows that the rainfall intensity of the area for a 24-hour storm
is 3.21 mm/hour. The site is approximately 1000m2 so over a 24-hour period there would be
77.04 m3 of water going into the settling ponds from the roadways site. This is considerably under
the size of the settling ponds capacity.
In the case of above average rainfall the settling ponds are checked for discharge. If there is water
discharging from the ponds to the Joran River a check sample is taken to ensure that a high
sediment load is not impacting the Derwent Estuary.
7092 Roadways Bridgewater EER 15
Monitoring of the settlement ponds is undertaken by Boral. They monitor pH, particulate matter,
and hydrocarbons.
Noise Emissions
A noise assessment has not been conducted for the site nor has one been requested by the EPA.
There have not been any cases of noise complaints from the public during over 28 years of
production at the asphalt plant. The only case a noise assessment is to be undertaken is if the
Director of the EPA requests it.
The operating hours off the site are typically within 0630 - 1600 hours every day. On occasion
when a large batch is ordered increased production time will be required. These hours are less
than the nearby Boral quarry who operate under the Quarry Code of Practice.
The major noise sources on the site are from the following
• Dust fan – 104.4 dB
• Gas burner 100.2 dB
• Asphalt loading bay 97.2 dB
• Dryer 94.6 dB
• Lab marshall compactor 94.8 dB
With over 1000m to the nearest residence the combined noise emissions will be less than 46dB (Noisetools.net). This is unlikely to have an impact on the nearest residences.
Solid Wastes
The production of solid waste cannot be avoided during the asphalt process. The only solid waste
produced is from the settling ponds, which is solids collected during the wet scrubbing process,
and this will increase because of the increased production. All solid waste from the settling ponds
is recycled and re-used by the Boral quarry.
7092 Roadways Bridgewater EER 16
Additionally, Roadways clean out the scrubber each day using a mixture of aggregates consisting
of 7mm, 14mm and 20mm as well as dust. This mixture is placed into a pile with the intent to be
re-used.
Environmentally Hazardous Substances
The site has some environmentally hazardous substances in use. The quantity and type stored on
site is found in Appendix 2.
Spill kits are located on site with all employees receiving training in their use. In the event of a
spill the person finding the spill carries out the following actions:
• Alert site management that there has been a spill and the estimated volume.
• In the event of a minor spill the employee will clean up and place the contaminated material in the designated clean up bag.
• The material is removed from site by a suitably qualified waste contractor.
• In the event of a larger spill the employee is to bund the spill to prevent further exposure to the environment.
• A suitably qualified waste disposal company is contacted to clean up and remove the contaminated material
The only controlled waste that could occur at this site is contaminated soil from a spillage of environmentally hazardous material.
Each employee undertakes spill management training specific for the Bridgewater site.
All spills are recorded in the environmental incident register.
Natural Values
TasVeg 3.0 (Figure 7) shows that the site is entirely covered by extra urban miscellaneous
vegetation. There are no endangered species within 2 km of the site.
7092 Roadways Bridgewater EER 17
Figure 7 TasVeg 3.0
The proposed increase in production does not require clearing of vegetation for extra plant or
machinery.
There will be increased traffic movements stemming from the increased production. This has the
potential to increase the risk to animals on the road network within and external to the site.
There are incidents of noted fauna located on roadways that are likely to be impacted by the
intensification of the site. Species of fauna found on these roads are the eastern barred
bandicoot, the Tasmanian devil, the masked owl, and eastern quoll. All incidents were reported
prior to 16/01/2018 and are available to view on TheLIST.
The increased traffic movements from the site will be at a maximum of 23 extra trucks per day
(as per appendix 3). This is a minor increase in total traffic of the area and the increase in risk to
associated fauna is negligible.
There are no known natural or geoconservation values within 1000m the site, hence the increase
in production will have no detrimental effect.
Site
7092 Roadways Bridgewater EER 18
Weeds, Pests and Pathogens
The only risk of weeds, pests or pathogens is from the wheels of the trucks that enter and exit
the site to transport the product. Trucks are washed down on site as per EPN8061/1 with all wash
down waste going into the settlement ponds. Due to the nature of asphalt production process
and the product produced on site there is no requirement for a phytophthora management plan.
Greenhouse Gas Emissions and Climate Change
This process uses best practice environmental management. By locating within an existing quarry
operation this minimises traffic movements to and from site for raw materials and reduces the
carbon footprint. This significantly reduces distance a vehicle must travel to bring sand and gravel
to the site which in turn reduces the CO2 discharged when travelling. This is in conjunction with
the proponent using modern, well maintained vehicles for offsite transport of the final product.
The site uses natural gas as the main energy source which again lowers the CO2 discharge that
other energy sources can produce.
Roadways Pty Ltd are committed to reducing transport emissions by minimizing travel distances
and using modern efficient plant and equipment throughout the life of the operation. Which
meets the relevant points in Tasmania’s climate change action plan 2017-2021.
Site Contamination
There are no known historic site contamination issues.
Other Off-site impacts
There are no other off-site impacts.
Environmental Impacts of Traffic
A traffic impact assessment was undertaken by Mr. Chris Martin of CSE Tasmania. He states that
the increase in production has the potential to increase the vehicle movements to the site by
40%. However, there is a new and high standard road infrastructure in the vicinity of the asphalt
plant. Due to this the increased vehicle movements will not have a detrimental effect on safety
or the road network.
7092 Roadways Bridgewater EER 19
Traffic Impact Assessment Report is attached as Appendix 3.
Monitoring
Currently no monitoring is required by the current EPN. However, Boral conduct monitoring of
the settlement ponds under their monitoring program for pH, particulates, and hydrocarbons.
Decommissioning and Rehabilitation
Decommissioning of the site will include the removal of all infrastructure associated with the
asphalt plant. Rehabilitation of the site will be in line with the Boral Quarry rehabilitation where
the plant is located.
4 PART D - Management Commitments
Number Commitment Reference Completion
Date Person
Responsible
1
Undertake annual audits of Workplace Health and Safety Act
1995 and the Workplace Health and Safety Regulations 1998 and the
“Requirements for onsite personnel.”
Section 2.1 Ongoing S. Prickett
2 EPN, EMP and existing systems to
checked for suitability Section 3.1 At approval S. Prickett/EPA
3 Organise a noise assessment to be if
requested. Section 3.3
30 days after initial late operation
S. Prickett
4 Ensure spill kits are on site and
stocked. Section 3.5 Ongoing H Allwright
5 Spill management training is undertaken by all employees
Section 3.5 During
employee site induction
H. Allwright
6 Record all spill in an environmental
incident register Section 3.5
At time of incident
H. Allwright
7 The DRP will conform with the Boral
quarry decommissioning plan Section 3.13
30 days before closure
S. Prickett
7092 Roadways Bridgewater EER 20
5 PART E - Public Consultation
Consultation has occurred with both local and state government regarding impending roadworks.
The projected roadworks will require larger volumes of asphalt than can be produced under the
current permit limit and therefore an increase in output is requested.
Public consultation has not yet been conducted will occur as part of the DA process.
6 Refences
Noise tools calculator accessed from http://noisetools.net/noisecalculator
Appendices
Appendix 1 – Previous Stack Test
SUMMARY REPORT ON ENVIRONMENTAL MONITORING
STACK EMISSION MONITORINGBridgewater Depot
March 2010
for
Roadways Pty Ltd
MILLIN EMS PTY LTDABN 35 090 618 241
1st Floor 5 Morrison Street Hobart TAS 7000PO Box 83 Battery Point TAS 7004T: 03 6231 9690 F: 03 6231 9695
Roadways Pty LtdRDWDep02 - Bridgewater
Millin EMS/ RDWDep02 January 2010 Page 1 of 5
TABLE OF CONTENTS
1.0 Introduction ...........................................................................................22.0 Scope of Works.....................................................................................23.0 Works Carried Out ................................................................................34.0 Background Information ........................................................................3
4.1 Sources of Air Pollution .....................................................................34.2 Operation of the Hotmix Plant............................................................3
5.0 Results ..................................................................................................46.0 Conclusion and Recommendations.......................................................5
Attachment 1: Report on Atmospheric Emissions Scrubber Stack, Roadways Bridgewater by LEC Environmental
Roadways Pty LtdRDWDep02 - Bridgewater
Millin EMS/ RDWDep02 January 2010 Page 2 of 5
1.0 Introduction
This summary report has been prepared in response to a request from Roadways Pty Ltd for environmental monitoring at their Bridgewater Depot.
Roadways Pty Ltd operates from three principal depot sites in Tasmania, including a mixed use depot at Wivenhoe near Burnie in the north of the State. The mixed use depot has a range of activities that potentially impact on air, noise, water quality and soils and groundwater, as well as potentially impacting on the social amenity of surrounding areas, including nuisance noise, odours, lighting, traffic movements and the like.
Millin EMS was previously engaged to inspect each of the three depot sites, to review the licence and approvals and to consider an outline of monitoring requirements likely to address future environmental monitoring requirements of the sites. This review was presented in a report of June 2009.
Further to our report and discussions during mid-2009, Millin EMS was commissioned to arrange for an investigation of air quality at the Bridgewatersite. The objective of the assessment was to determine the concentration of particulates from the scrubber stack with respect to emission limit guideline values.
LEC Environmental were engaged to conduct stack emission testing. This summary report presents the results of this testing. Detailed measurements can be found in LEC Environmental ‘Report on Atmospheric Emissions Scrubber Stack, Bridgewater Depot’ dated 3 March 2010, included in Attachment 1.
2.0 Scope of Works
The scope of works for this report includes results of Hotmix scrubber stack emission monitoring at Bridgewater and comprised the following tasks:
Monitoring stack emissions under two plant operating conditions for:o Total Particulates, and Moisture (in duplicate) (i.e. 4 tests total)o Oxygen, Carbon Dioxide measurements by instrument during
the total particulates testso Nitrogen Oxide, Nitrogen Dioxide, Sulphur Dioxide & Carbon
Monoxide measurements by instrumento Temperature measurements during the total particulates testso Gas Velocity & Volume Flow Rate Calculations (based on one
set of measurements) Report detailing methods, procedures and results.
Roadways Pty LtdRDWDep02 - Bridgewater
Millin EMS/ RDWDep02 January 2010 Page 3 of 5
The test is for total particulates, recovered on a glass fibre filter paper, using Advantec GC50. Particles retention is less than 0.6 micron (no differentiationbetween total particulates and PM10 as the larger particles are expected to be removed in the scrubber).
3.0 Works Carried Out
Stack emissions testing was conducted at Bridgewater on the morning of 16 February 2010. Testing was conducted in accordance with Australian Standards and Victorian EPA methods.
Two tests were conducted, for each test the following measurements were taken:
Velocity of gases in the stack; Particulate measurements; Moisture measurements; Stack temperature; Gas concentrations (CO2%, O2%, COppm, NOppm, NO2ppm
No measurements for sulphur dioxide were reported.
4.0 Background Information
4.1 Sources of Air Pollution
Air pollution issues (i.e. beyond the boundary of the premises) from bitumen operations include coarse dust, fine particles, gaseous pollutants and odours, detailed as follows:
Potential coarse dust and fine particulate sources include vehicle movements, wind-blown from site and materials storage, materials handling, screening, aggregate drying (usually subject to emission control), and truck loading.
Potential gaseous pollutant emission sources include drying, bitumen storage, mixing and truck loading.
Potential odour sources include truck loading and gas leaks.
4.2 Operation of the Hotmix Plant
The hotmix plant is fed from stockpiles of gravel via a conveyor from bins located on the south side of the plant. Bituminous products are introduced to
Roadways Pty LtdRDWDep02 - Bridgewater
Millin EMS/ RDWDep02 January 2010 Page 4 of 5
a hopper and blended base media for supply of product. The hot air stream is drawn off via a wet scrubber prior to discharge to the atmosphere via a stack. The water supply for the wet scrubber is a two stage system of settlement basins located adjacent to the plant. Water is introduced to the scrubber via a recirculation pump.
The return water with entrained fines from the scrubber enters the first settlement basin before entering the pump well located at the far corner of the basin.
5.0 Results
Details of the stack emission testing are outlined in the attached report by LEC Environmental (Attachment 1).
Results indicate that the total particulate concentration of stack emissions was 100.1 mg/m3 and 92.2 mg/m3 for Test 1 and Test 2, respectively. These tests were carried out under normal operating conditions using recycled water from the wet scrubber.
Comparison of results of the two tests with guidelines indicated that the particulate emissions from the scrubber stack was close to the 100mg/m3
guideline level provided by the Environment Protection Policy (Air Quality) 2004 for in-stack concentrations. The averaged result was within the guideline concentration value.
Roadways Pty LtdRDWDep02 - Bridgewater
Millin EMS/ RDWDep02 January 2010 Page 5 of 5
6.0 Conclusion and Recommendations
Under normal operating conditions, the stack emissions were at about the guideline levels for in-stack concentrations (Environment Protection Policy (Air Quality) 2004).
It is likely that there would be variation in concentrations of particulates for varying operational conditions, which could result in the emission limit guideline value being exceeded.
Given that the measured emissions were close to or equal to the guideline value for particulate emissions, it would be prudent to:
Carry out investigations of scrubber operation to assess potential for improved performance;
implement measures for improved fines settlement in the water recirculation system.
Yours Faithfully
Signed: …………………………………………
Philip Millin FEIANZ, MAIGB.Sc (Hons) GDipNatRes
Dated: …………………………………………
For MILLIN EMS PTY LTDABN 35 090 618 241
ATTACHMENT 1: Report on Atmospheric Emissions Scrubber Stack, Roadways Burnie by LEC Environmental
Appendix 2 – Hazardous Goods Register
DG Manifest Roadways Bridgewater Asphalt Plant Revision 3.1
Re-issued May 2020
DANGEROUS GOODS MANIFEST Asphalt Plant (located at Boral Quarry)
1 Parkholme Drive, BridgewaterTas. 7030
Emergency Contacts
Name Position Contact
Bill Abbott Chief Executive Officer Work 03-62713500 A/H 0429 848 182
Henry Allright
Maurice Bradley
Asphalt Plant Manager
Technical Manager Radiation Safety Officer
Work 03 62637784 A/H 0409 817 557
Work & A/H 0400 914 935
(1) Bulk Storage & Packaged Dangerous goods
Location Tank ID. Name Class UN No.
PG Type Capacity
Southside of Control room
BR 1 BR 2
Elevated Temperature Liquid, N.O.S
9 3257 III Above ground
(ag)
89,930 L
“ “
Southside Control room
BR 3
Diesel
Hydrated Lime
C1
8
1202
3262
III
Steel tank
a/g
Wood boxes 10k
bags
5,000 L
10,000 kg
Workshop
Acetylene 2.1 1001 Cylinder 70 L
Workshop
Oxygen 2.2 1072 Cylinder 70 L
Flammable goods Store
LPG Gas 2.1 1978 Cylinders 370 L
Flammable goods Store
Packaged flammable
liquids
3 II & III
Various container
s Tin &
plastic
400 L
DG Manifest Roadways Bridgewater Asphalt Plant Revision 3.1
Re-issued May 2020
NUCLEAR DENSITY GAUGE Troxler 4640B thin lift Asphalt Nuclear Density Gauge
Gauge Source Location Legislation Class 7
Type A Package
Radiation Source
Material Cs-137
Activity 0.3GBq
Southern side of Asphalt
Plant next to shipping
container
Australian Radiation
Protection and Nuclear
Safety Regulations 1999
ARPANSA Code of
Practice & Transport
Safety Guide
Appendix 3 – Traffic Impact Assessment
134 Midlands Highway Roadways
Bridgewater Asphalt Plant Expansion
Parkholme Drive
Traffic Impact Assessment
PREPARED BY CHRIS MARTIN FIEAust, NPER3. Senior Civil Engineer CSE Tasmania Pty Ltd Tasmanian Building Act Accreditation Number: CC4109 V.
DATE 5/6/20
2 Parkholme Drive Asphalt Plant Expansion Traffic Assessment CSE Tasmania Pty Ltd
INDEX 1 Introduction & Background........................................................................ 3
1.1 Statement of Qualifications and Experience ....................................... 4
1.2 Project Scope ..................................................................................... 4
2 Assessment Criteria .................................................................................. 5
3 Existing Condition Site Investigation/Survey ............................................. 5
3.3 Road Safety Performance ................................................................... 6
3.4 Sight Distances ................................................................................... 6
3.5 Intersection Geometry......................................................................... 6
3.6 Impact on the Road Network .............................................................. 6
4 Traffic Generation ..................................................................................... 7 5 Discussion ................................................................................................ 7
6 Recommendation ...................................................................................... 7
3 Parkholme Drive Asphalt Plant Expansion Traffic Assessment CSE Tasmania Pty Ltd
1 Introduction & Background The following report contains the Traffic Impact Assessment (TIA) for the Bridgewater Roadways Asphalt plant expansion, located off Parkholme Drive. The site is looking to expand current extraction rates from 50,000 cubic metres per annum to 70,000 cubic meters per annum.
Fig 1 Excerpt from Google Earth showing location of intersection.
Intersection Location
Asphalt Plant site
4 Parkholme Drive Asphalt Plant Expansion Traffic Assessment CSE Tasmania Pty Ltd
1.1 Statement of Qualifications and Experience This TIA has been prepared by an experienced and qualified Civil Engineer with significant experience in Traffic Impact Assessments and Road Safety Audits in accordance with the requirements of Council’s Planning Scheme and The Department of State Growth’s, A Framework for Undertaking Traffic Impact Assessments, September 2007. This TIA was prepared by Chris Martin. Chris’s experience and qualifications are briefly outlined as follows:
• Bachelor of Civil Engineering with Honours, University of Tasmania 1992
• 28 years professional experience as a Civil Engineer in infrastructure design
• Master of Business Administration (Technology Management) Latrobe University 2007
• Career experience includes design of many subdivisions, 2.5 years Council Engineer, 16 years in civil and structural consulting and 6 years in major infrastructure engineering positions.
1.2 Project Scope The project scope of this TIA is:-
• Review of the existing road environment in the vicinity of the site and the traffic conditions on the road network.
• Provision of information on the proposed development and its expected traffic movements and activity.
• Identification of the traffic generation potential and review of the impact of the increase in traffic on the road network capacity.
• Traffic implications of the proposal with respect to the external road network in terms of traffic efficiency and road safety.
5 Parkholme Drive Asphalt Plant Expansion Traffic Assessment CSE Tasmania Pty Ltd
2 Assessment Criteria With the access road shared with Boral Quarries coming direct onto a roundabout built with the Midlands Highway upgrade the usual assessment criteria do not apply. This asphalt plant has a high standard road junction in place design by DSG engineers during the highway upgrade.
3 Existing Condition Site Investigation/Survey The site inspection was performed by Chris Martin from CSE Tasmania Pty Ltd on the 9th of June 2020.
Parkholme drive commencing at the Bluemetal Drive roundabout – view to the east
Parkholme drive view from inside the gates to the west towards the roundabout.
6 Parkholme Drive Asphalt Plant Expansion Traffic Assessment CSE Tasmania Pty Ltd
3.3 Road Safety Performance Crash data provides valuable information on road safety performance. Existing road safety deficiencies can be highlighted through the examination of crash data, which can assist in determining whether traffic generation from the proposed development may exacerbate any identified issues. The Department of State Growth DSG accident database collects all accident data in the state from 2003. Crash data revealed that two heavy vehicles have collided at the roundabout on during daylight hours at 5pm on 6th of Dec 2019. First aid was required for the heavy vehicle occupants. The description of cause was classified as “cross traffic” suggesting that there was a failure of a vehicle to give way. This one instant is insufficient to indicate any design flaws with the roundabout.
3.4 Sight Distances As the asphalt plant is at the end of Parkholme Drive and it intersects with an existing roundabout sight distances are not an issue.
3.5 Intersection Geometry The Parkholme Drive/Bluemetal Drive intersection was constructed with the highway upgrade. There are no concerns with the geometery of the roundabout.
3.6 Impact on the Road Network Parkholme Drive and its intersections are of new construction. There are no concerns for impact on the road network or beyond as the vehicles join the highway at the relatively new interchange.
7 Parkholme Drive Asphalt Plant Expansion Traffic Assessment CSE Tasmania Pty Ltd
4 Traffic Generation
The operating hours of the asphalt plant are typically from 0700 – 1900hrs
Monday to Friday and 0800 – 1600hrs on Saturdays with some variations
depending on demand.
The asphalt plant expansion will result in an increased number of class 4 (i.e.
10m3, three axle trucks) and class 9 (i.e. 10m3, three axle trucks with an
additional 10m3 trailer) utilizing Parkholme Road. The proposal will see the
existing production rates of 50 000m3 per annum increased to 70 000m3 per
annum, thus resulting in up to 7000 class 4 vehicles, or 3500 class 9 vehicles
leaving this asphalt plant per annum. Predominant use of truck and trailer
combinations will see approx. 3500 truckloads out of the site each year.
It is likely that the product will be shifted from the site in campaigns assuming
about 25 truck and trailer loads removed in a day. This equates to 140 days
at 25 trucks per day. In reality the frequency of trucks could be controlled by
the loading rate – say 1 truck every 10 minutes when there is a major project
requiring asphalt. This could increase frequency to 48 trucks per day.
The predominant direction of truck movements will be to the south of the
asphalt plant access into the greater Hobart market with some larger
campaigns directing asphalt to Midlands Highway upgrades.
5 Discussion Increasing the tonnage output of Bridgewater Roadways Asphalt plant has the potential to increase truck movements by 40%.
Due to the new and high standard of road infrastructure in the vicinity of the
asphalt plant this proposed increase in use will not have a detrimental affect
on safety or the road network.
6 Recommendation The increase in truck movements will not affect recognized safety standards at the intersection or extending further afield on the network. The Traffic Impact Assessment does not identify grounds that would prevent the upgrade in tonnage from this operation.