Environmental and Social Management...
-
Upload
hoangnguyet -
Category
Documents
-
view
215 -
download
0
Transcript of Environmental and Social Management...
1
INSTITUTIONAL STRENGTHENING FOR IMPROVED VILLAGE
SERVICE DELIVERY PROJECT
Environmental and Social Management Framework
MINISTRY OF HOME AFFAIRS
and
MINISTRY OF VILLAGES, DISADVANTAGED AREAS AND TRANSMIGRATION
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
3
TABLE OF CONTENTS
Table of Contents 3
List of Tables 5
List of Figures 5
List of Annexes 5
List of Abbreviations 6
1. Strategic Context 7
2. Project Description 17
2.1 Theory of Change 17
2.2 Project Development Objectives 20
2.3 Project Components 21
2.4 Project Beneficiaries 25
3. Potential Environmental and Social Impacts and Risks and Potential
Mainstreaming of Environmental and Social Sustainability 26
3.1 Potential Impacts and Strengthening Areas 26
3.2 Institutional Capacity 32
4. Objectives of the Environmental and Management Social Framework (ESMF) 33
5. Environmental and Social Sustainability Aspects in the Current Implementation
of the Village Law and Direction Towards Strengthening 33
6. Framework for Mainstreaming Environmental and Social Sustainability Aspects
in the Capacity Building and Institutional Strengthening of the Implementation
of the Village Law 36
7. Environmental and Social Management Framework for Component 3 and E-Waste 41
7.1 Principles, Screening and Safeguards instruments 43
7.2 Protocol for E-Waste Disposal 46
8. Indigenous Peoples Planning Framework (IPPF) 48
8.1 Objective 48
8.2 Specific Objectives of this Framework 48
8.3 National Regulations and Institutional Arrangements Pertaining to IPs 49
8.4 Objectives and Requirements of OP 4.10 52
8.5 Application of OP 4.10 in Project Component 1, 2, and Component 4 52
8.6 Criteria of Indigenous Peoples 53
8.7 Screening of IPs 54
8.8 Assessment of IPs as beneficiaries or affected by an activity 54
8.9 Indigenous Peoples Plan (IPP) and Sub-Project Design 54
9. Public Consultations and Disclosures 55
10. Grievance Redress Mechanisms (GRM) 56
11. Institutional Arrangements for Implementing the Environmental and Social
Sustainability Aspects 58
12. Capacity Building Plan 60
13. Monitoring and Evaluation 62
14. Budget to Implement the ESMF 63
4
LIST OF TABLES
Table 1: Expected GoI Contributions to Project Activities (2019-2024) 21
Table 2: Project Costing by Component 25
Table 3: Indicative Key Strengthening Areas 39
Table 4: Responsible Agencies for Mainstreaming and Strengthening the ESS Aspects 58
Table 5: Proposed Capacity Building Plan for Mainstreaming and Strengthening 61
the ESS Aspects
Table 6: Cost Components and Responsible Agencies to Provide Budget for the Implementation 65
of the Mainstreaming and Safeguards in Component 3 as Specified in this ESMF
LIST OF FIGURES
Figure 1: Annual Government Expenditures for Village Law (2018) 12
Figure 2: Overall Project Results Chain 18
Figure 3: Project Theory of Change 19
Figure 4: Organizational Structure of the Institutional Strengthening for Improved
Village Service Delivery Project 26
Figure 5: E-Waste Management Procedures 48
LIST OF ANNEXES
Annex 1: Project Implementation Structure and Arrangement 66
Annex 2: Some of the Ongoing Capacity Building Activities in the Ministry of Village and the
Ministry of Home Affairs for the Implementation of Village Law 76
Annex 3: Some of the Ongoing Capacity Building Activities in the Ministry of Home Affairs
for the Implementation of Village Law 78
Annex 4: E-Waste Management 79
Annex 5: Report on Environmental Screening 82
Annex 6: Suggested Screening Form (Generic) 83
Annex 7: Format of Environmental Management Plan and Environmental Monitoring
Plan (UKL/UPL) 84
Annex 8: Format of Statement of Assurance For UKL/UPL Implementation 87
Annex 9: SOP for Environmental Management 88
Annex 10: Format of the “Statement of Commitment to Implement Environmental
Management and Monitoring” (SPPL) 89
Annex 11: Typical Subproject Impacts and Mitigation Measures 90
Annex 12: Environmental Codes of Practices (ECOPs) 91
Annex 13. Form Check List Environmental Code of Practice (ECOPs) 93
Annex 14: Social Assessment of Indigenous Peoples 97
Annex 15: Format of Indigenous Peoples Plan (IPP) 98
Annex 16: Minutes of Consultation Meeting with IPs 100
Annex 17: Notes on Free, Prior and Informed Consultations (FPIC) 101
Annex 18: List of Districts that Potentially Have Indigenous Peoples Presence 104
Annex 19: Chance Finds Procedures 105
Annex 20: Notes from Public Consultations of the ESMF 106
5
LIST OF ABBREVIATIONS
APBD Local Government Annual Budget/ Local Budget
APBDes Village Government Annual Budget/ Village Budget
APBN National Government Annual Budget/ Central Budget
AMDAL Analisis Mengenai Dampak Lingkungan (Environmental Impact Assessment)
B3 Bahan Beracun Berbahaya (hazardous and toxic waste material)
BAPPENAS Badan Perencanaan Pembangunan Nasional (National Development Planning Board)
BAPPEDA Badan Perencanaan Pembangunan Daerah (Local Development Planning Agency)
BKM or LKM Badan/Lembaga Keswadayaan Masyarakat (Community Board of Trustees)
BPS Badan Pusat Statistik (National Statistical Bureau)
BPKP Badan Pengawasan Keuangan dan Pembangunan (National Internal Auditor)
Bupati Head of Regency/ District
CDD Community Driven Development
CPIU Central Project Implementation Unit
DAK Dana Alokasi Khusus (Special Allocation Fund)
DED Detailed Engineering Design
DG Directorate General
EA Environmental Assessment
EMP Environmental Management Plan
ESIA Environmental and Social Impact Assessment
ESS Environmental and Social Sustainability
ESMF Environment and Social Management Framework
ESMP Environment and Social Management Plan
E-Waste Electronic Waste
GOI Government of Indonesia
GRM Grievance Redress Mechanism
IBRD International Bank for Reconstruction and Development
IPs Indigenous Peoples
IPP Indigenous Peoples Plan
IPPF Indigenous Peoples Planning Framework
KAT Kelompok Adat Terasing (Isolated Indigenous Community)
Kecamatan Sub District
Kelurahan Urban Ward
Keppres Keputusan Presiden (Presidential Decree)
KSM Kelompok Swadaya Masyarakat (Community Self-help Group)
KPMD Kader Pemberdayaan Masyarakat Desa (Village Cadre for Community
Empowerment)
LG Local Government
LGDP Local Government Development Program
M&E Monitoring and Evaluation
MA Masyarakat Adat (Customary Community)
MHA Masyarakat Hukum Adat (Customary Law Community)
MIS Management Information System
MoHA Ministry of Home Affairs
MoV Ministry of Village
NGO Non-Government Organization
NMC National Management Consultant
6
OHS Occupational Health and Safety
OP Operational Policy
PAD Project Appraisal Document
PAP Project Affected People
PCR Physical Cultural Resources
PD Pendamping Desa (village facilitator)
PD-P Pendamping Desa Pemberdayaan (village facilitator for empowerment)
PD-TI Pendamping Desa Teknis Infrastruktur (village facilitator for infrastructure)
PDO Project Development Objective
PIU Project Implementation Unit
PMU Project Management Unit
Pokja Kelompok Kerja (National Task Force)
PTPD Pendamping Teknis Pemerintahan Desa (Technical Assistant for Village Governance)
RPJMN Rencana Pembangunan Jangka Menengah Nasional (National Medium Term
Development Plan)
RPJMD Rencana Pembangunan Jangka Menengah Daerah (Regional Medium Term
Development Plan)
RPJMDes Rencana Pembangunan Jangka Menengah Desa (Village Medium Term
Development Plan)
RKPDes Rencana Kerja Pembangunan Desa (Village Development Work Plan)
SA Social Assessment
SMS Short-text Messaging Services
SOP Standard Operational Procedure
SPPL Surat Pernyataan Kesanggupan Pengelolaan dan Pemantauan Lingkungan (Letter of
Environmental Management and Monitoring)
TA Tenaga Ahli (Expert)
TMC Technical Management Consultant
TOR Terms of Reference
TPK Tim Pelaksana Kegiatan (Implementing Unit)
UKL/UPL Upaya Pengelolaan Lingkungan/ Upaya Pemantauan Lingkungan (Environmental
Management and Monitoring Plan)
7
1. STRATEGIC CONTEXT
A. Country Context
1. Indonesia is the world’s largest archipelagic state, fourth most populous nation, tenth-
largest economy in purchasing power parity terms and is one of the most socially,
economically and culturally diverse countries in the world. Indonesia has a population of more
than 261 million, with 300 distinct ethnic groups and over 700 languages and dialects spread across
around 6,000 inhabited islands spanning 1.9 million kilometers squared from Aceh in the Indian
Ocean to Papua on the edge of the Pacific. The country has witnessed rapid urbanization since the
1970s. However, with approximately 45 percent of the population or 118.9 million living in rural
areas, it remains less urbanized than most middle-income countries.
2. Indonesia continues to make progress on reducing poverty and has begun to reverse
inequality, with the poverty rate falling to a single digit for the first time in 2018 and the Gini
coefficient declining. Indonesia made large gains in poverty reduction since 1999, cutting the
poverty rate by more than half to 10.6 percent in 2017.1 However, most of the progress happened
before 2012, with poverty rates declining by 4.6 percentage points between 2007 and 2011,
compared to a 2.1 percentage point reduction since 2012. Inequality increased over this period,
rising from a Gini coefficient of 30 in 2000 to 41 in 2010. More recently, both poverty and
inequality have begun to decline. The national poverty rate fell to 9.8 percent in 2018 and the Gini
coefficient to 38.9.
3. Poverty is significantly higher in Indonesia’s rural and lagging regions, and the rural
poor are particularly vulnerable to sliding back into poverty. The rural poverty rate is about 14
percent, compared to 7.7 percent in urban areas. This means that close to 60 percent of the poor
reside in rural areas, where poverty reduction has tended to be slower. From 2014 to 2017 the rural
poverty rate declined by only 0.3 percentage points, from 14.2 to 13.9 percent, compared 0.6
percentage points, from to 8.3 to 7.7 percent, in urban areas. Households living in predominantly
rural districts also lag on several other human development indicators. For example, only 86
percent of births are attended by a skilled health worker and 62 percent have access to safe drinking
water in predominantly rural districts, compared to 98 percent and 83 percent in predominantly
urban districts. Likewise, socioeconomic outcomes are lower, with household heads in
predominantly rural districts attaining lower levels of education (8.5 years vs. 10.0 years in urban
districts), being much more reliant on agricultural employment (49 percent vs. 11 percent in urban
districts) and informal employment (66 percent vs. 38 percent in rural districts).2 Overall, rural
Indonesians remain vulnerable to poverty, and lack the economic security to transition to the middle
class, which is crucial to Indonesia’s future growth.
4. The rural poor are also exposed to shocks from natural disasters and climate change,
threatening their livelihood security and contributing to trapping them in poverty. As the
largest archipelago nation in the world, Indonesia is highly vulnerable to the negative impacts of
climate change. Hydrometeorological events such as floods and droughts, which currently make
1 World Development Indicators for Indonesia, (updated November 14, 2018), World Bank. 2 SUSENAS 2017 data.
8
up 80 percent of disaster occurrences in the country, are projected to increase with climate change.3
In the long run, Indonesia is also anticipating impacts from slow-onset events, namely sea level
rise (SLR), increasing temperatures, and shifting rainfall patterns.4 The poor populations in the
rural and lagging regions are expected to face the negative impacts of climate change through
multiple channels, including increased disaster damage to village infrastructure, water shortage,
reduced agricultural yields, increased food insecurity, more prevalence of climate-sensitive
diseases (such as diarrhea, dengue and malaria), etc. Java, Bali and Sumatra islands face high and
very high risks from climate change compared to other regions, due to their higher concentration
of population and infrastructure. Villages in Eastern Indonesia are also particularly prone to more
droughts.
5. Indonesia’s dynamic digital economy, driven in part by its young tech-savvy
population, together with its infrastructure investments in reducing internet costs and
expanding the fiber backbone to all regions, provides a unique opportunity to bridge the
“digital divide” between urban and rural areas as well as the poor and non-poor. Indonesia is
rapidly digitizing; however, it is concentrated in urban areas despite recent government efforts to
expand access to internet services in rural areas and remote regions. In only five years, the total
number of internet users in Indonesia spiked from roughly 63 million in 2013 to 143 million people
in 2017.5 This rapid growth in internet users is consistent with decreasing mobile data costs. From
2014 to 2018, the cost of one gigabyte in Indonesia decreased from roughly 2 percent of GNI per
capita to less than 0.8 percent, making data costs in Indonesia as low as 50 percent of the cost paid
in neighboring ASEAN countries.6 While in urban areas 72.4 percent of the population had internet
access, for rural areas internet penetration stood at 48.3 percent. To improve connectivity
throughout Indonesia, the government is undertaking an ambitious country-wide infrastructure
investment, the Palapa Ring Project, spanning 67,887 kilometers of broadband fiber-optic cable
over sea and land. The Palapa Ring Project will connect all districts across Indonesia, providing
equality of service to even the most remote locations to boost digital inclusion.
B. Sectoral and Institutional Context
Sectoral Context
6. In 2014, the Government of Indonesia passed the Village Law (2014/6), significantly
increasing fiscal resources for development and community empowerment in Indonesia’s
75,000 rural villages (desa). Between 2015 and 2018, fiscal transfers to villages increased from
IDR 78 trillion (US$5.6 billion) to IDR 119 trillion (US$8.4 billion). The new Village Law, which
was enacted in early 2014, also expanded the roles and responsibilities for villages, including for
village administration, development, basic service delivery and community empowerment. The
fiscal transfers are large and in 2018 they account for approximately six percent of the national
budget, and around 0.5 percent of GDP. On average, a village now receives approximately IDR 1.6
3 Government of Indonesia (2016), Indonesia’s First Nationally Determined Contributions submitted to the
UNFCCC. 4 Government of Indonesia (2013), National Action Plan for Climate Change Adaptation (RAN API): Synthesis
Report. 5 Association for Internet Service Providers in Indonesia (APJII) 6 Google and TEMASEK, e-Conomy SEA 2018, Southeast Asia’s Internet Economy Hits an Inflection Point,
2018.
9
billion ($113,500) every year, although the amount on a per capita basis varies widely because the
allocation formula includes a large fixed allocation and village population sizes vary from an
average of 2,500 to less than 500 people and well above 5,500 people.7
7. The increased financial resources and the new institutional framework offer new
opportunities for villages to invest in larger, multi-year and multi-sectoral development
activities and strategies in alignment with village needs and local district and regional
development priorities. To access and use these financial resources the Village Head and the
village administrative apparatus are required to prepare six-year Village Medium-Term
Development Plans (RPJMDes),8 annual Village Development Plans (RKPDes), annual Village
Budgets (APBDes) and annual financial reports in consultation with community members. The
district government is also required to review and endorse the annual village budget. In contrast to
previous village development activities, which were fragmented across multiple sector programs
and/or tended to by-pass local government planning processes, the Village Law enables villages
to: (a) make larger multi-year investments—for example, instead of one-off sub-projects of around
IDR 150-200 million (US$10,000-15,000), villages can plan larger multi-year activities; (b)
address development problems that require investments across multiple sectors—for example, the
National Strategy for Accelerating Stunting Prevention supports villages to invest in the health
(maternal health and community growth promotion activities), water and sanitation, early child
education services as well as strengthens village leadership and capacity to oversee convergence
of these multi-sectoral services;9 (c) finance a wider variety of investment types—in additional to
infrastructure investment, villages have more scope to inject capital into village-owned enterprises
and manage village assets for village development purposes; (d) align village investments with
local district and regional development priorities; and (e) ensure synergies across a wider variety
of activities.
8. These investment opportunities have opened new “pathways” for villages to address
Indonesia’s gaps in rural infrastructure, jobs and human capital as well as rural connectivity
and digital inclusion, and thereby contribute to poverty reduction and future economic
growth. For addressing remaining infrastructure gaps, improving local services to reduce stunting,
managing natural resources and disaster risks, or improving local economic development, villages
occupy the key position where government meets the community. Playing this role effectively
depends on how well villages can identify their priority needs, and then convert increased financing
into investments and services that effectively meet those needs. In turn, this depends on the capacity
and incentives of the village government to work with the community, as well as with higher levels
of government, to plan, budget and implement village development. Village government capacity,
accountability, and incentives to perform will be a key determinant of the Village Law’s impact.
These still relatively early days of Village Law implementation are a key window of opportunity
7 An average village in Indonesia has around 2,500 people or 500-600 households. However, about one-third of
villages have less than 500 people or 100 households (generally in Eastern Indonesia and other more remote
locations) and about one-third have more than 5,500 people or 1,000 households. 8 The six-year RPJMDes is aligned with the Village Head election cycle; that is, Village Heads are required to
prepare the development plan within one year of their election (or re-election). Village Heads must be a resident
in the village and can be re-elected three times for a total 18 years. 9 See results area 4 of the Investing in Nutrition in Early Years (P164686)
10
for national government to set policies and make large-scale investments to strengthen villages –
both governments and communities – to use their expanded transfers effectively.
9. There are some early signs that some villages are taking advantage of these new
opportunities with the number of “independent villages”10 increasing from 2,894 (3.9 percent)
to 5,559 villages (7.6 percent) and the number of “left-behind villages” declining from 19,750
(26.8 percent) to 13,232 villages (17.9 percent) between 2014 and 2018.11 The government
Village Development Index (IPD) is one attempt to measure village development progress
holistically, albeit one that is imperfect and requires improvements.12 The index consists of five
core components and is based on 42 composite indicators from the Village Potential (PODES)
survey, which is a village census that the Central Statistical Agency (BPS) conducts every 3-4
years. The five components are basic service delivery facilities, village infrastructure conditions,
transportation and accessibility, general services and village administration. The overall index
score increased from 55.7 to 59.4, with most gains coming from improvement to village
infrastructure conditions and village administration. Unsurprisingly, the majority of “left-behind
villages”, which score low on the index, are in Papua, Maluku and Kalimantan as well as pockets
of Sumatra, Sulawesi and NTT.
10. There are also tentative signs that rural poverty reduction is accelerating after three
years of stagnation, although it is too early to know whether this will be sustained, and it is
difficult to directly link this to village investments. The official government statistics on poverty
concluded that rural poverty declined only marginally from 14.2 percent in 2014 to 13.9 percent in
2017. However, as noted above, in March 2018 it recorded the largest year-on-year decline since
March 2011 with the poverty rate for the first time decreasing faster in rural than urban areas. This
is partly the results of a recent expansion in social assistance programs and buoyant labor market
conditions, and some in government have argued that increased financial resources for villages,
which reached the full allocation in 2017, contributed to the decline rural areas.13 Box 1 below
illustrates how one village took advantage of the new village funds to dramatically improve its
ranking on the index and reduce poverty in the village.
11. However, most evidence indicates that most villages have stuck with “typical”
investment strategies that will only contribute marginal improvements to their IPD score and
are unlikely to create new economic opportunities, increase human capital and transform
livelihoods. The Village Public Expenditure Review (ViPER), which the World Bank conducted
in 2016, found that villages spent almost 40 percent of their budget on village administration, 38
percent on village infrastructure, and very little on health, education and livelihoods.14 The
10 The Government of Indonesia has developed a Village Development Index, classifying villages as
“independent”, or advanced development, “developing”, and “lagging”. The index is updated annually, and draws
on 42 composite indicators, with 117 specific indicators, including measurements on five dimensions: basic
services, infrastructure, transportation, public services and governance. 11 The survey was conducted in May 2018, and therefore it covers three effective years of increased financial
resources for villages, i.e. 2015, 2016 and 2017. Villages usually receive the first tranche of fiscal transfers around
March-April and most activities occur in the second half of the year. 12 FN on our views on its general robustness. 13 Santoso & Sandy Maulana (2017) On Constructing Village Fund Impact Evaluation Model (Paper presented at
FKP seminar session– Article 33). 14 World Bank, 2016 Village Expenditure Review (ViPER), 25 August 2017.
11
government’s monitoring data indicates similar patterns in more recent years. The Ministry of
Villages reported that in 2017 spending on village administration had declined to around 30
percent, village infrastructure had increased to almost 60 percent, and spending on human capital
and economic empowerment remained very low.15 Furthermore, systematic qualitative research
indicates that although the quality of individual infrastructure sub-projects are satisfactory overall,
villages tend to simply divide up development spending relatively evenly between hamlets within
a village.16 This results in small and fragmented investments (e.g., small-scale infrastructure sub-
projects or, worse, “beautification” sub-projects), which have little impact on economic growth and
poverty reduction.
12. Villages have not yet realized the potential of the Village Law because of variation in
village leadership, participation and citizen engagement, management and technical capacity,
and incentives to take advantage of the new investment opportunities. Global empirical
research and operational experience relating to local governance and community-driven
development (CDD) emphasize that capacity building through incentives for public sector workers,
improved selection processes and top-down and bottom-up accountability mechanisms are
effective in improving local governance and strengthening development outcomes. Community
participation and citizen engagement can also play a contributing role. Across potential
interventions costs of implementation should be weighed against evidence of impact, with attention
given to lowering investments in less proven interventions.17 For example, reducing investments
in traditional capacity building face-to-face training and education that have variable impact-
records. As summarized in Box 1 below, these factors are all relevant to understanding village use
of the new funds and community development outcomes more generally. Many villages are unable
to envisage and oversee more complex village investment plans, because they lack the requisite
capacity for comprehensive planning, lack basic information on village needs as well as more
complex information on regional development plans, lack access to technical service providers that
15 Ministry of Villages, Program Achievements: Village Development 2014-2018, 5 March 2018. 16 On infrastructure quality, see World Bank, Indonesia Village Law: Evaluation of Infrastructure Built with
Village Funds, October 2018; on village planning, see Sentinel Villages study. 17 World Bank, Building Village Governance Capacity: Literature Review, November 2018.
Box 1: The potential for villages to use the village funds to make transformative investments – the
experience Panjalu village in West Java
Panjalu Village in Ciamis, West Java, which has a population of 12,600, transformed its infrastructure, services
and livelihoods over the past seven years. In 2011 the village was classified as “disadvantaged” but by 2018 it
was classified “independent, with most of the gains coming in the past years with the increased village financial
resources.
To achieve this the village adopted a multi-year development plan that directed the village funds to implement
various fields of development that are mutually supportive: infrastructure for education, health, economy, tourism,
and increasing human resources as well as addressing horizontal conflict among villages and creating
opportunities for village youth.
The village collaborated with neighboring villages and other stakeholders in economic activities, especially in
managing forest and agriculture to maintain spring water for local bathing, washing, latrines, and to upgrade the
tourism and market facilities. With this multi-year planning system, the village succeeded in generating additional
revenue, which now stands at IDR 1.4 billion (US$96,550) and is more than twice what the village receives from
the central government village transfer.
12
could help them implement the plans if they wanted, and lack incentives and community demand
to embark on more ambitious development plans.
13. The challenges of enabling villages to invest effectively is compounded by the scale of
the country and variation in the situation of Indonesia’s 75,000 villages. Given the size and
variation across Indonesia’s 75,000 villages, approaches to support villages must be adaptable,
flexible and demand driven. Current systems of support are often “one size fits all” and supply
driven, addressing village needs with a uniform approach. This not only creates a gap in the services
for village development, but also results in inefficiencies in government expenditures towards
villages. There is no uniform solution that will resolve all problems and ensure all villages take full
advantage of their new investment opportunities in accordance with their local needs and priorities.
For some villages, the challenge will be leadership and not technical capacity, for other
administrative capacity and not incentives, and for others the problem may not be village itself but
the sub-district or district government.
Institutional Context
14. The central government as well as provincial and district governments realize villages
require support and have since 2015 financed various programs and systems to improve
coordination, village administration, village development and community empowerment, and
increase accountability. As summarized in Figure 1 below, the government spends approximately
IDR 9.6 trillion (US$715 million) per year on support to, and oversight of, villages. This is spread
across three levels of government. The central government spends approximately IDR 3.2 trillion
(US$239 million) or 33 percent of the total amount, although most of this is executed by provincial
governments via deconcentrated financing (Dekon). Provincial and district governments spend an
estimated IDR 1.9 trillion (US$141 million) and IDR 4.5 trillion (US$335 million) respectively,
which works out to be about (US$4.1 million) per provincial government and IDR 11.2 billion
($770,000) per district government. These sums are significant and amount to approximately
US$9,000 per village or approximately 10 percent of the amount villages themselves are spending
on village administration and investment.
Figure 1: Annual Government Expenditures for Village Law (2018)
13
Box 2: Local Governance and Community Development –A Summary
Capability Global Literature & Indonesia Assessments
Capacity-
building via
selection and
screening
Selection and delegation of tasks to higher-skilled workers at the village level can
create significant improvements in governance outcomes (Casey et al 2018).
Selecting more skilled, competent, and motivated individuals, governance outcomes
can be improved significantly (Finan 2017).
Designing selection methods that attract officials with higher intrinsic motivation is
a promising approach to improving governance outcomes (World Bank Group WDR
2017)
Capacity-
building via
training
(Indirect evidence via community) The 2017 World Development Report lists some
examples of research on the training of members of the community but lacks evidence
about training of government employees or service providers: Duflo et al found that
schools in Kenya could reduce capture (by civil service teachers) by training parents
in the community (Duflo et al 2015).
Ex post evaluations of capacity-building efforts supported by development partners
have been very critical, especially with regard to a focus on training relative to other
dimensions of capacity” (World Bank, 2017).
Performance-
based
Management via
Incentives
Financial incentives are important for improving governance outcomes, despite
consistent concerns among experts that higher financial incentives could discourage
performance by selecting against intrinsically motivated workers (Finan 2017).
Consider tools that provide incentives, such as pay-for-performance schemes.
Randomized evaluations of these schemes in the context of the frontline provision of
public services find that the performance of public officials in fulfilling their tasks
improves” (WDR 2017).
In Indonesia, incentive-based block grants delivered to villages based on performance
in health and education indicators led to significant on health indicators (.04 standard
deviations) – especially malnutrition rates – and bigger gains for those villages that
started worse off (they report no gains in education and muted gains in health over time)
(Olken, Onishi, Wong 2014)
Top-down
Accountability
Examples, such as inspections by higher subnational agencies, has mixed but mostly
positive evidence in its support. Monitoring can improve outcomes via multiple
channels: (i) Monitoring can enable performance-based management (rewards or
punishments based on observable outcomes); (ii) Monitoring can act as a deterrent; (iii)
Monitoring by higher agencies can deter officials from colluding in policy capture
and generate useful information for third parties interested in preventing capture.
When results from top-down monitoring are made available to the public, it enables
important bottom-up accountability via citizen pressure. (WDR 2017, Finan 2017)
The WDR adds that despite the strong evidence for results from effective monitoring,
that monitors themselves are not immune to capture.
Audits, for example, have been shown to reduce leakage in village-level public
investment programs (Olken 2007)
Bottom-up
Accountability
via Community
Monitoring,
Participation and
Citizen
Engagement
(evidence from
Indonesia and
India)
A cautious approach toward the use and interpretation of score card initiatives is also
recommended, as these attempt to employ citizen satisfaction as a close proxy for
actual quality of services, in nonrandom samples, and without controlling for other
factors. (Lewis and Pattinasarany 2009).
Participants in civic activities tend to be wealthier, more educated, of higher social status
(by caste and ethnicity), male, and more politically connected than nonparticipants
(Mansuri and Rao 2013).
At some point, the opportunity cost of participation must surely eclipse its
instrumental and intrinsic value. Finding that participation is a tax and associated
quotas for the poorest and most marginalized make it a particularly regressive one
(Casey 2017).
Technology In quasi-experimental evidence from India and Indonesia, electronic procurement
leads to quality improvements in infrastructure provision by facilitating entry from
more diverse and higher-quality contractors (though notably they did not find reduced
costs) (Lewis-Faupel et al 2016).
14
15. The quality of these support systems has improved over the past four years, however,
they are costly, their effectiveness is mixed and their efficiency is low. There are four core
areas—village administration, village development and community empowerment, inter-village
development and accountability—which are the responsibility of three main ministries: the
Ministry Home Affairs (MoHA), the Ministry of Villages, Disadvantaged Areas and
Transmigration (MoV) and the Ministry of Finance (MoF):
a. Administrative capacity support. MoHA, via the Directorate General for Village
Government Guidance, is responsible for village government and administration,
including village elections, village boundaries, village administration, village financial
and asset management, and village oversight. It implemented a large-scale cascading
training program for villages in 2015 and 2016 that trained almost all 75,000 villages
on core government tasks, including village elections and village administration as well
as village planning, budgeting and reporting for the increased village funds. The
approach was one-size-fits-all and used a traditional cascading delivery model, which
was arguably justified in the first years of Village Law implementation given the need
to provide basic information to all villages. More recently, the Directorate General has
focused on capacity building for sub-districts offices, although of implementation has
been weak because of limited resources. The Directorate General, like MoHA more
generally, tends towards a legalistic and technocratic approach to capacity building—
setting rules, explaining the rules, and demanding compliance—and focused on core
capacities to hold elections, disburse village funds, and account for financial inputs. It
has focused little attention on leadership and the “soft skills” of village government,
performance-based management and results-based accountability.
b. Village development and community empowerment support. MoV, via the
Directorate General of Village Development and Community Empowerment, is
responsible for Various programs, one-size-fits-all. Its flagship program is the Village
Development and Community Empowerment Program (P3MD), which built on the
CDD facilitation structure of the World Bank-supported PNPM project.18 At a cost of
approximately IDR 2.7 trillion (US$201 million) per year19, the central government
finances via provinces, the provision of 2,484 district-level technical advisers, 15,305
sub-district-level village facilitators (which includes 5,577 technical village facilitators
with engineering qualifications) as well as 19,851 local village facilitators that support
villages to prepare plans, budgets and reports. P3MD deploys traditional approaches to
implementation that focus more on augmenting capacity than building capacity. The
one-size-fits-all approach means there is often a misalignment between village
technical capacity needs and the support available. More recently, MoV has adopted
more innovative and less traditional approaches to capacity building. With support
from the World Bank, it launched a peer-to-peer learning and results-focused
knowledge exchange platform, the Village Innovation Program, which uses video and
knowledge exchange hubs to inspire, incentivize and empower villages to innovate in
18 The government’s Village Law to PNPM Transition Strategy, which ran from 2015 to 2016, saw inter alia
approximately 14,000 district, empowerment and technical facilitators transition from PNPM to supporting
villages to prepare village plans and budgets. 19 Based on 2016 budget allocations
15
how they use their villages funds for infrastructure and human capital. MoV has also
recently established Village Academy 4.0, which it aims to develop as an online
learning platform for courses on village business development.
c. Inter-village development support. MoV is also responsible for inter-village
development, via the Directorate General for Inter-Village Development, and with
some programming for villages dispersed within other Directorate Generals. These
DGs have smaller, more niche programs focused on piloting methods and approaches
to encouraging inter-village development cooperation and aligning village
development plans with regional development priorities.
d. Accountability systems and support. MoHA, MoF and the Supreme Audit Agency
(BPK) as well as district governments all play important roles in the village
accountability system. BPK has ultimate audit authority but has narrowed its focus to
the disbursement of the fiscal transfers from district to villages, MoHA supports
district-level Inspectorates to conduct financial audit of villages and supports
accountability via its role in village elections, and MoF accounts for use of the fiscal
transfer to villages from the central government (Dana Desa). These accountability
systems are heavily input-oriented and there has been relatively little focus on results.
That began to change after the President as well as Parliament begun to demand
information on how the village funds were being used, questions that the input-oriented
reporting and audit systems could not answer. This prompted both MoF and MoV to
establish systems for the collection and compilation of village output data.20 However,
both systems have tended to focus on pulling data up to Jakarta for central government
accountability purposes (i.e. to cabinet and parliament). And there has been little focus
on enabling districts and village—let alone the general public—to access and use this
data for public accountability and local planning purposes.
16. One overall weakness of the support systems is that they make little use of new
technologies for teaching, knowledge sharing and accountability. The administrative approach
to capacity building is overall reliant on expensive and ineffective top-down cascade training
systems. New opportunities in technology-based innovations, coupled with Indonesia’s rapid
digital infrastructure expansion, present potential to expand more flexible, adaptive and demand
driven service delivery. The Village Innovation Program, although innovative and operating at a
scale rarely seen, is still reliant on face-to-face knowledge exchange and learning, and does not
fully maximize online peer-to-peer knowledge platforms. Despite MoV’s “market place approach”
to technical service provision, it has yet to tap the potential of online platforms for matching the
demand and supply of technical service needs. Similarly, the approach to accountability is strictly
hierarchical and focuses on extremely “long paths” of accountability rather than “short path” direct
accountability. These online and digital systems can support a more cost-effective and efficient
system of connecting villages in innovation exchanges and to access services.
20 MoF also recently incorporated a results-oriented scorecard in relation to the National Strategy to Accelerate
Stunting Prevention into its latest ministerial regulation on Dana Desa Reporting (PMK /2018). This was a
Disbursement-Linked Result (DLR) for the Investing in Nutrition and Early Years (P164686) PforR Program.
16
17. It is also critical that the support systems more systematically help districts to do
capacity building and empowerment differently. In general, government entities involved in
implementing the Law include: (i) DPMD, under the MoV, which is responsible for village support
and supervision at both the provincial and district levels; (ii) the District Finance Office (Badan
Keuangan dan Asset Daerah, BKAD) which is responsible for disbursing Dana Desa to villages;
(iii) the district-level Local Inspector, which is overseen by MoHA; and (iv) the District Planning
Agency (Badan Perencanaan dan Pembangunan Daerah, BAPPEDA). At the sub district
(kecamatan) level, the Technical Guides for Village Government (Pembina Teknis Pemerintahan
Desa, PTPD) play a coordinating role in village governance and development. One key challenge
for districts is that, while roles and responsibilities vis-à-vis villages have increased with the
introduction of the Village Law, districts have not seen a commensurate increase in budget or fiscal
transfers to effectively manage these responsibilities.21
18. Finally, national coordination of the support system is weak. Currently, Kemenko PMK
plays a coordinating role between institutions and ministries related to the Village Law. This brings
together relevant line ministries to regularly discuss policies, regulations, and issues related to
implementation of their respective Village Law functions. Despite effectively bringing together
ministries, however, the coordinating function is ad hoc, and lacks the institutional mandate to
effectively enforce decisions reached as a part of the coordination meetings. This issue is
exacerbated by the fact that several key line ministries to not fall under the coordinating mandate
of Kemenko PMK (e.g. MoHA). BAPPENAS’s planning functions related to Village Law are well
structured and oversees both MoHA and MoV under a single department, but this lacks the
analytical and technical capacity needed to effectively oversee and monitor implementation of key
activities related to Village Law. Finally, there are currently no systematic engagement with the
private sector, which has an important role to play in supporting villages with technical services at
the local level.
C. Relevance to Higher Level Objectives
19. The proposed Project contributes to the World Bank Group’s Country Partnership
Framework (CPF) for the period 2016-2020. The 2016-2020 CPF identifies three pathways for
poverty reduction and shared prosperity: job creation; service delivery and opportunities for all;
and natural resource management. The CPF is structured around six Engagement Areas and two
Supporting Beams. The proposed operation supports Engagement Area 4: Delivery of Local
Services and Infrastructure, and Supporting Beam II: Shared Prosperity, Equality and Inclusion.
Under Engagement Area 4, it is consistent with Pillar 1: Strengthening the decentralization
framework to improve local service delivery, and Pillar 2: Supporting the delivery of quality
education and health services, water and sanitation in rural areas to directly address inequality of
opportunity. Under Pillar 1, the proposed operation is consistent with several of the pillar’s
strategies, including strengthening the capacity of central government to support and oversee local
governments, strengthening the capacity and functions of local governments to deliver local
services, supporting citizens to monitor local service delivery, and establishing a performance-
based fiscal transfer system. Under Pillar 2, the proposed operation is consistent with the Bank’s
21 District Assessment; District expenditure review
17
approach to supporting local implementation of national programs, such as the Village Law of
2014.
20. The proposed operation also supports the government’s National Medium-Term
Development Plan (Rencana Pembangunan Jangka Menengah Nasional, RPJMN) 2015-2019,
and contributes to the Government’s Nawa Cita Strategy that aims to narrow the gaps in
poverty and development in Indonesia’s lagging regions. The Government’s Nawa Cita
Strategy (the administration’s mission statement) and RPJMN 2015- 2019 identify priorities and
goals for reducing poverty and inequality. Nawa Cita includes a strong emphasis on developing
Indonesia’s lagging regions and on improving governance and accountability in the public sector.
Transfers to villages, as mandated by the Village Law, are one of the major instruments through
which the GoI is pursuing the administration’s vision of “building Indonesia from the periphery.”
The RPJMN aims to boost overall development with specific emphasis on achieving a competitive
economy that is based on quality human capital, optimum natural resources management, and
improved technological capacity. The plan sets out national targets for achieving stable economic
growth (with a growth target of 6-8 percent per year), accelerating poverty reduction (with a
poverty rate target of 6-8 percent by 2019), and reducing disparities and inequality (with a Gini
coefficient target of 0.36 by 2019). The RPJMN includes three pillars: (i) developing a national
social protection system, (ii) improving service delivery for the poor and vulnerable, and (iii)
promoting sustainable livelihoods for the poor.
21. The proposed operation also supports the Government’s climate policy objective of
strengthening social resilience to climate change at the village level. Adapting to the impacts of
climate change is a high priority of the GoI. The country’s first Nationally Determined
Contributions (NDC) document articulates a clear climate policy objective of reducing risks from
climate change on all development sectors by 2030 through local capacity strengthening, improved
knowledge management, convergent policy on climate change adaptation and disaster risks
reduction, and application of adaptive technology.22 As climate change impacts are experienced
locally, achieving these policy objectives calls for strong engagement of local governments and
villages. The proposed operation will contribute to achieving these objectives at the local level by
promoting climate-resilient village development planning and spending, facilitating peer-to-peer
exchange of climate-resilient village innovations, and building climate awareness and preparedness
of systems for service delivery to villages in climate-sensitive regions.
2. PROJECT DESCRIPTION
2.1 Theory of Change
22. The Project will support GoI to develop and roll out new and reformed systems of
implementation support for village institutional strengthening, with the objective of improving the
quality of village spending and thereby contribute to an accelerate in rural poverty reduction and
village development. The overall results chain from project inputs to the higher-level objectives is
summarized in Figure 2 (below). It consists of three parts: first, how the project components will
22 Government of Indonesia (2016), Indonesia’s First Nationally Determined Contributions submitted to the
UNFCCC
18
change the village support system; second, how an improved village support system will lead to
better village investment outcomes; and finally, on the pathways through which village investments
can contribute to poverty reductions and economic growth.
Figure 2: Overall Project Results Chain
23. The project investments will focus on developing and supporting the roll out of more
adaptable village support systems that strengthens village governance and development in
according with local institutional needs and development opportunities. The Project will focus
on reforming and improving systems through investments in four sets of activities:
a. National results-oriented leadership and coordination. The Project will strengthen
national leadership and coordination through investments in consolidating, analyzing
and using data to drive national policy making relating to the Village Law and its
support systems.
i. Technology-driven delivery systems. The Project will leverage technology to
reform business processes and improve support systems that promote
innovative and cost-effective learning, in particularly by that will (i) change
accountability in the delivery model; (ii) better match supply of support
services with village demands and needs; and (iii) collect and better use data.
Box 2 below summarizes how the Project will use innovative digital solutions
to drive improvements in the support system and establish a village-focused
platform for transforming rural service delivery (for more details see Annex 1).
b. Roll-out support in priority locations. The Project will also support the phased roll-
out of these new support systems and services in a phase manner in priority districts
(see below for more information on the project phases and priority locations.
c. Performance incentives. The project will also invest in designing, testing and rollout
out village performance system that strengthens villages incentives to adopt and realize
these new adaptive support systems.
Strategic investments in
leadership, technology, roll-
out and performance
incentives
Adaptable village support systems aligned
with village needs
Villages realize improved quality of spending
Greater rural poverty
reduction
19
24. As summarized in Figure 3 (below), these the development and rollout of these systems are
expected to improve cost effectiveness in supporting village institutions and development and
realize efficiency gains in government spending.
Figure 3: Project Theory of Change
Box 3: Driving innovation in service delivery through digital solutions
Indonesia is currently undergoing a digital transformation, with rapidly expanding information and
communication technologies (ICTs). In 2017, Indonesia recorded 143.26 million internet users1, or 53 percent
of the population, representing a 30 percent increase since 2015. As digital infrastructure and connectivity
continues to improve, there will be growing opportunities to harness digital solutions to improve service
delivery. For example, digitizing back end service delivery—such as integrating e-learning systems or
digitizing human resource management functions—has the potential to improve efficiencies, cut costs, and
improve oversight within government systems. Further innovations in digitally based solutions can also
empower citizens and communities.
Global innovations to link end users with services through a platform-based approach, whereby the
government acts as a facilitator or a coordinator of citizen-to-market, or peer-to-peer interactions, allows for
citizens and communities to connect directly with the people or services that they need. Given the size and
scale of solutions needed to effectively cater to the needs of Indonesia’s 75,000 village institutions, digital
solutions have the potential to provide effective support to villages. Digital systems and approaches will be
pilot tested under the Project, with a view to learn and scale up, and with significant resources in place to
support villages, districts and provinces to best adapt to and adopt these solutions.
20
25. With support systems and fiscal transfer systems aligned, villages will be able to
realize improved quality of spending. Improving the quality of spending at the village level
depends on four factors: institutional capacity, timely information; adequate fiscal resources, and
incentives to encourage good spending. The project’s interventions will lead to improved
institutional capacity, including core administrative capacity of village governments for more
efficient and sophisticated planning, and necessary technical and capacity support to villages in
line with village needs. Information systems will be integrated and strengthened, and innovative
platforms for knowledge and innovation exchanges will further strengthen improving information
flows, ideas, inspiration and the enabling environment. Incentives and results will be strengthened
as a result of investments to improve support systems for participation, accountability and
improving knowledge and will pilot test performance grants for village governments. Thus,
systems improvements will help to align with significant fiscal resources to improve quality of
spending at the village level.
26. Improved quality of spending is expected to improve village investments resulting in
contributions to rural poverty reduction. Three types of typical village investments could
contribute to poverty reduction. First, improved capacity and accountability of village institutions
would result in decisions over infrastructure investments that better align with village needs.
Strategic infrastructure investments also have the potential to unlock local economic development,
align better with district level planning and investments to maximize impacts, and support
community labour for direct poverty benefits. Second, village investments in human capital would
support closing urban-rural gaps in access to early education and health services and create
economic value for villages through investments in skills and knowledge. Finally, improving
quality of spending is expected to result in investments in physical and digital connectivity, that
have the potential to drive economic empowerment and reduce poverty.
2.2 Project Development Objectives
PDO Statement
27. The proposed Project Development Objective (PDO) is to “strengthen Institutional
capacity for improved quality of spending in participating villages”. This will be achieved through
investments that improve and modernize support systems that build capacity of village institutions,
enhancements to and integration of information systems, and aligning these to increase with fiscal
transfers to focus on performance and results.
PDO Level Indicators
• Village institutional capacity for improved transparency and accountability is
strengthened (percentage)
• Beneficiaries feel that village investments meet their needs (percentage, by gender)
• Village governments participating in the performance-based incentive see improvements
in quality of spending (number)
21
2.3 Project Components
27. Project approach. The Project will support the GoI to develop and roll out new systems
of implementation support for village institutions, with the objective of improving the quality of
village development plans and programs. This will be achieved by: (i) supporting the design of new
systems and approaches for capacity building, knowledge sharing, technical assistance, and
learning that are adaptable and demand driven; (ii) focusing on aligning results in improved
performance with incentive mechanisms; and (iii) strengthening the village information and data
systems through digital solutions that improve monitoring and evaluation of village performance
(including procurement and payment transactions), as well as promoting the use of data in planning
and budgeting at the village level. Taken together, these interventions will support village
institutions to better access the support systems they need to improve quality of spending.
28. Project financing vis-a-vis government expenditures. With the enactment of Village
Law in 2014, village governments have seen significant increases in budget allocations, as well as
expanded roles and responsibilities for local development. In 2018, fiscal transfers to villages
amounted to around US$8.4 billion. In addition, the GoI supports the implementation of Village
Law through various line ministries and Government programs with an estimated US$715 million
annually. However, these existing support services are currently not leading to high quality
planning or village government expenditures that fulfil higher level objectives of poverty reduction,
and pro-poor, impactful and climate resilient village development. The Project will target
investments of US$350 million over five years to improve the GoI’s implementation support
systems and processes to become more flexible and adaptable to the varied needs of its villages, as
well as more efficient, cost-effective, and demand driven. This support is expected to transform
support to villages by better linking village institutions with capacity support structures and
information systems, and to align these with the right incentive mechanisms. The Project will
leverage expected GoI expenditures on capacity building programs through designated line
ministries of around US$403 million over the project period (see table below). These contributions
are expected based on existing expenditure patterns and government programs for improved village
capacity. In addition, the Project is expected to influence the broader support system to villages,
and interventions under the project would support development of systems that would positively
enhance and improve village planning and spending. All told, the Project will influence an
estimated US$42.5 billion in GoI spending over the project period.
Table 1: Expected GoI Contributions to Project Activities (2019-2024)
IDR (billion) USD (million)
National Budget (ABPN) 2,610.0 180.0 (*)
Provincial Budget (ABPD 1) 145.0 10.0
District Budgets (APBD) 1,087.5 75.0
Sub-district 217.5 15.0
Village Government 1,740.0 120.0 (**)
TOTAL 5,800.0 403.0
Estimated expenditures are based on existing budget allocation patterns and are calculated as those that
are directly relevant to the project’s activities, including capacity building activities and training programs
that exist already and could be leveraged as a part of the project activities. These estimates do not include
government staff salaries, or operational costs for government departments.
(*) including the portion of the national budget currently used to fund village facilitators (TPD) and
experts in districts and sub-districts for community empowerment, an estimate of the portion of the TPD
for capacity development assistance, of which 15% is used for capacity building assistance (**) Village
22
APBDesa portion used for capacity building activities are estimated at less than 1% of all village APBDes
values.
29. Project Components. The Project is organized in four components, which together
comprehensively support the development of systems and approaches, as well as their roll out and
adoption, for improved Village Law implementation. Implementation of these systems and
approaches are expected to lead to improved efficiencies in government expenditures These will
improve delivery systems for institutional strengthening, strengthen mechanisms of oversight and
coordination, and align incentives for improved quality of spending. MoHA, with a mandate for
supporting sub-national government institutions, will be the lead executing agency for the Project,
and will be directly responsible for Components 1 and 3 of the Project. These components will
focus on improving institutional strengthening systems for village governments, as well as pilot
testing incentive mechanisms for improved village government performance. MoV, with a mandate
to support village development, will participate in the Project by overseeing Component 2, which
aims to strengthen community empowerment and improve social accountability within village
development processes. The Ministry of National Development Planning/ National Development
Planning Agency (Badan Perencanaan dan Pembangunan Nasional, BAPPENAS) will implement
Component 4 of the Project, with the objective of improving coordination, monitoring and
oversight of the implementation of the Village Law.
30. Component 1: Strengthening Village Government Institutions (IBRD US$185
million). The objective of this component is to improve the institutional strengthening system for
village governments (apparat) within MoHA, and to support the rollout and adoption of these new
tools and approaches. This will be achieved by supporting the development of a capacity building
platform for village governments that is flexible and adaptable, to address the varied capacity needs
of village governments. This component will also support the rollout of this platform through the
sub-national government institutions, providing an opportunity to leverage existing support
systems and further strengthening and aligning these to better support village governments. The
Project will finance (i) the design of a digital learning platform within MoHA to integrate content
and deliver cost effective and efficient capacity building support to villages; (ii) the development
of expanded content and tools (e.g. animation videos, e-learning, blended learning, distance
learning, and other tools), as well as technical manuals, guidelines, modules and supporting
instruments to bolster administrative capacity; (iii) rollout of a revised institutional strengthening
program through sub-national governments, including support to adoption and transition of these
systems, improved coordination and oversight, and alignment with sub-national spending and
programs on capacity building; and (iv) support to upgrading MoHA’s village level data systems,
management information systems (MIS) and integration of monitoring and performance
measurement systems. This component also provides an opportunity to improve the quality of
village planning and development by mainstreaming training, capacity building, and technical
guidelines to improve social and environmental standards, awareness of climate change hotspots
and impacts on village livelihoods and potential responses to be integrated in village plans,
strengthening inclusion and participation in planning and budgeting, and upgrading and supporting
best practice in procurement systems. This component will also support village financial
management through strengthening current reporting systems and supporting capacity building for
oversight and supervision functions of the district and sub-district through the learning platform.
23
31. Component 2: Promoting Participatory Village Development (IBRD US$95 million).
The objective of this component is to strengthen systems of capacity support and village
development within MoV. Strengthening these systems will leverage the existing facilitator
structure under MoV, which currently supports around 37,000 facilitators, including 14,000 field
level facilitators, across the country, as well as several other programs within MoV to support
community empowerment and village development. These programs will be supported to be more
flexible and adaptable to better respond to needs, and to facilitate innovation and cross learning for
community capacity. This component will also put in place systems to improve support for
improving participatory planning and strengthening social accountability mechanisms. The Project
will finance: (i) improvements to community learning systems that aim to build capacity (e.g.
Akademi Desa 4.0), and peer to peer exchanges, such as village innovation forums (Bursa Innovasi
Desa), including creating and curating content and improving systems to better access and
distribute knowledge; (ii) digitization of the oversight and management systems for village
facilitators (P3MD), and integration of village level feedback on performance for improved
resource deployment; (iii) development of a digital platform (GoDesa) to integrate digital solutions
more effectively within MoV, and support to develop, upgrade and improve digital applications,
hardware and software systems (including a citizen portal with access to comparative information
and statistics about villages (e.g. poverty, health, nutrition, exposure to floods, droughts etc.); (iv)
digital marketplaces for technical service providers, and interactive chat portals (RuangDesa),
among others); and (v) testing of different innovations in village development, including digital or
smart villages, participatory tracking systems, etc.. Social accountability and participatory planning
systems will be strengthened through upgrading training content and guidelines for facilitators to
better support community participation in decision-making, and to ensure the contestability of
different fora for deliberation (e.g. facilitate MusDes, BPD, village meetings, needs assessments,
etc.). Technical assistance to support the development, testing and rollout of these systems will be
provided, as well as support to subnational management of facilitators for the first two years of the
Project. The subnational technical assistance will help monitor results more closely during
implementation to identify adjustments, as needed. The Project will not finance facilitator salaries,
incremental operating costs, training costs for facilitators, or travel and supervision costs.
32. Component 3: Strengthening Village Government Performance (IBRD US$50
million). The objective of this component is to pilot test a performance grant system that would
reward village governments according to key performance metrics of good governance. While
investments in Components 1 and 2 focuses on strengthening the institutional capacity of village
institutions (including village governments and communities), and in improving their capacity for
better governance, component 3 matches these supply side interventions by pilot testing a program
to measure and reward improved outcomes in village governance and quality of spending. A
performance assessment system will be established in Year 1 of the Project to capture simplified
metrics for village government performance; annual assessments will be carried out for
participating village governments, through a combination of a web-based system and in person
assessments. A proposed set of metrics, which will assess if and how village plans address issues
such as local economic development, exposure to and preparedness for climate and disaster risks,
and social and environmental standards etc., is provided in Annex 2 of PAD. This list includes
measurements to capture improvements in the quality of planning (i.e. more inclusive,
participatory, and climate-resilient), capture improvements in output and budget reporting, and
promote transparency and accountability. Participating village governments will be assessed in
24
Year 2 of the Project and will be evaluated against the agreed performance metrics and criteria.
Assessments would be conducted by the National Government Internal Auditor (Badan
Pengawasan Keuangan dan Pembangunan, BPKP), who would recommend qualifying village
governments to MoHA; MoHA would in turn work with the Directorate General of Fiscal Balance
(Direktorat Jenderal Perimbangan Keuangan, DJPK) under the Ministry of Finance, to release the
performance transfer to village government accounts via district governments. The performance
grant system will be pilot tested in 50 districts, or around 8,500- 9,000 villages.
33. Component 4: National Coordination, Monitoring and Supervision (IBRD US$20
million). The objective of this component is to improve and strengthen national coordination,
harmonization of regulations, monitoring, and supervision of village development. This will be
achieved through the establishment of an integrated information management system that offers
real time incorporation of key metrics for village development under a single information system
(InfoDesa). This information management system will draw on existing data collected through a
variety of government agencies, and will integrate these into a single platform, accessible via a
dashboard where data can be visualized by different levels of government through web and
application-based interfaces. Data to be integrated in this platform may relate to village poverty
status, income, health, nutrition, education, existing infrastructure, exposure to disasters and
climate-related hazards (e.g. droughts, floods, storms, coastal inundation, etc.), and community
assets at risk, land and forest fire hotspots and related greenhouse gas emissions, etc. Linkages to
existing real-time data bases (e.g. for disaster early warning, weather forecasts) and indexes (e.g.
climate vulnerability and food security indexes), which are relevant for village-level planning, will
be explored. The Project will finance the hardware, systems and technical assistance required to
establishing this integrated information system and will also ensure that the system contains the
data needed for decision making processes. This component would also finance the formal
establishment of a National Coordination Platform for Village Development. This platform would
be chaired by Coordinating Ministry for Human Development and Cultural Affairs (Kementerian
Koordinator Bidang Pembangunan Manusia dan Kebudayaan, Kemenko PMK), and would be
supported by a Secretariat under BAPPENAS, who would oversee the management and
coordination efforts, and the integrated information system. Finally, this component would support
evaluations, including impact evaluations, of the program’s interventions.
Project Cost and Financing
34. The total project costs are estimated at about US$ 753 million, which is to be financed
through an IBRD Loan of US$350 million. The GoI will contribute equivalent costs of an estimated
US$403 million in the form of expected budget allocations during the project period. These
contributions will be in form of incremental operating costs, cost of capacity building activities,
facilitator staff and management costs, and fiscal transfers to village governments.
25
Table 2. Project Costing by Component
Project Components Project cost IBRD
Financing % Financing
1.Strengthening Village Government Institutions
2.Promoting Participatory Village Development
3.Strengthing Village Government Performance
4. National Coordination, Monitoring and
Supervision
Total Costs
320.0
360.0
50.0
23.0
185.0
95.0
50.0
20.0
100%
100%
100%
100%
Total Project Costs
Front end fees
Total Financing Required
753.0
-
753.0
350.0
-
350.0
2.4 Project Beneficiaries
35. The Project is expected to primarily benefit communities across Indonesia’s75,000
villages. Investments in improved support services and capacity, coupled with community
empowerment and development, are expected to further strengthen participation in village
governance; and better serve the poor, marginalized, or groups that are otherwise excluded at the
village level. The Project is also expected to benefit village governments (apparatus) and
institutions (including village councils), by strengthening their capacity to execute their core
functions, thus leading to improved spending and service delivery at the village level. The Project
will also benefit local governments, especially subdistricts (kecamatan) and district governments,
by strengthening their capacity to support and supervise villages and village governments more
effectively. Nationally, the Project will directly benefit line ministries involved in providing
support to village governments, through improved regulations and systems, as well as through
improved coordination and oversight functions that will help better direct government resources
and spending towards villages. The Project is expected to cover all 75,000 of Indonesia’s village
governments over the five years of implementation.
36. The Project organizational structure is presented in Diagram 1 below, and the details are
presented in Annex 1. Chaired by BAPPENAS, the Project has a Steering Committee comprises of
various ministries and agencies at the national level. Main implementing agencies are MoHA and
MoV at the national level, and there are PIUs and Working Group at the provincial and district
levels. A Consultant team will assist the PIUs at the national level, provincial and district level.
Detail explanation of the project organizational structure and implementation arrangements is
presented in Annex 1.
37. The mainstreaming and strengthening of environmental and social sustainability
(ESS) aspects in the Project will be part of the activities of the project organizational
structure and implementation arrangements. For instance, strengthening the current manuals
and guidelines for the village apparatus on ESS aspects will be the responsibilities of the MoHA
(PIU), as MoHA has been responsible for such manuals and guidelines. Similarly, improvement of
the ESS aspects in the manuals, guidelines and training for the village community and village
facilitators will be in the MoV (PIU). Structure of responsibilities of ESS strengthening and
26
improvement will follow the current responsibility structure between the MoHA, MoV, the
provincial and district governments of the relevant tasks.
Figure 4: Organizational Structure of the Institutional Strengthening for
Improved Village Service Delivery Project
3. POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS AND RISKS AND
POTENTIAL MAINSTREAMING OF ENVIRONMENTAL AND SOCIAL
SUSTAINABILITY
3.1 Potential Impacts and Strengthening Areas
38. Given the nature of the activities explained above, Component 1, 2, and 4 will not
involve any physical investment or preparation of any plans that would lead to the
implementation of physical investment or activities involving downstream environmental and
social impacts and risks. Most Project activities involve establishment of a digitalized, IT-based
tools, development of e-platform and e-services for learning, capacity building, market place for
capacity services, knowledge management, harmonization and simplification of regulations,
oversight and monitoring, and integrated information and data-system management. Anticipated
potential environmental impacts would be in the form of electronic waste as consequences of the
expansion of the existing and/or purchase of information and communication infrastructure
required including hardware, software, design, and upgrading data centers. Expansion of the
existing and/or new installation of IT hardware would take place in the PIUs. With the introduction
of the digitalization using the information technology, the Project will promote social
transformation in the implementation system of the Village Law. This would be a challenge for all
stakeholders involved in the Village Law implementation, including the village communities and
apparatus, consultants, facilitators, sub-districts, districts, provincial and MoHA as well as MoV.
Table 3 (Indicative Key Strengthening Areas) provides the elements of mainstreaming
environmental and social sustainability aspects in the capacity building and institutional
strengthening system.
27
39. Although Component 1, 2 and 4 do not involve any physical investment or preparation of
any plans that would lead to the implementation of physical investment or activities involving
downstream environmental and social impacts and risks, the Project will ensure that improved
capacity of village government include awareness and capacity to implement environmental and
social sustainability (ESS) considerations, through mainstreaming the objectives, key principles
and requirements for environmental and social sustainability in reference to relevant Indonesian
laws and regulations and applicable World Bank Safeguards Policies as well as EHS Guidelines.
This would include among others, improvement of stakeholder engagements, inclusion of
vulnerable groups, Indigenous Peoples community, and gender as well as complaint handling
system into the new and improved village plan, village annual budget plan, guidelines, training
modules, terms of references for the facilitators and monitoring and supervisory team/unit.
World Bank Operational Polices applicable to the Project: objectives, key principles and
requirements
40. The following paragraphs describe the objectives, key principles and requirements to the
World Bank safeguards policies applicable to the Project along with the objectives and key
principles and requirements of the relevant Indonesian laws and regulations, which would be taken
into consideration to the extent possible as elements for the mainstreaming within the activities of
Component 1, 2 and 4 as specified in Section 5 and 6. Applicable World Bank safeguards policies
to the Project are OP 4.01 on Environmental Assessment, OP 4.04 on Natural Habitat, OP 4.36 on
Forest, OP 4.11 on Physical Cultural Resources, OP 4.10 on Indigenous Peoples and OP 4.12 on
Involuntary Resettlement.
41. Environmental Assessment (OP 4.01) - The purpose of Environmental Assessment (EA)
is to improve decision making, to ensure that project options under consideration are sound and
sustainable, and that potentially affected people have been properly consulted. EA is a process
whose breadth, depth, and type of analysis depend on the nature, scale, and potential environmental
impact of the proposed project. EA evaluates a project's potential environmental risks and impacts
in its area of influence; examines project alternatives; identifies ways of improving project
selection, siting, planning, design, and implementation by preventing, minimizing, mitigating, or
compensating for adverse environmental impacts and enhancing positive impacts; and includes the
process of mitigating and managing adverse environmental impacts throughout project
implementation. The Bank favors preventive measures over mitigatory or compensatory measures,
whenever feasible.
42. EA takes into account the natural environment (air, water, and land); human health and
safety; social aspects (involuntary resettlement, Indigenous Peoples, and physical cultural
resources); and transboundary and global environmental aspects. EA considers natural and social
aspects in an integrated way. The objectives, key principles and requirements of the ESS which are
governed under OP 4.01 serve as an umbrella policy for other safeguards policies applicable to this
Project, i.e., OP 4.04, OP 4.36, OP 4.11, OP 4.10 and OP 4.12. The policy also takes into account
the variations in project and country conditions; the findings of country environmental studies;
national environmental action plans; the country's overall policy framework, national legislation,
and institutional capabilities related to the environment and social aspects; and obligations of the
28
country, pertaining to project activities, under relevant international environmental treaties and
agreements. The Bank does not finance project activities that would contravene such country
obligations, as identified during the EA. EA is initiated as early as possible in project processing
and is integrated closely with the economic, financial, institutional, social, and technical analyses
of a proposed project.
43. Natural Habitats (OP 4.04) – This policy seeks to ensure that World Bank-supported
infrastructure and other development projects take into account the conservation of biodiversity, as
well as the numerous environmental services and products which natural habitats provide to human
society. This policy requires the conservation of natural habitats and specifically prohibits the
support of a project that involve significant conversion or degradation of critical natural habitats
which are either legally protected, officially proposed for protection, or unprotected but of known
high conservation value. In other (non-critical) natural habitats, Bank supported projects can cause
significant loss or degradation only when (i) there are no feasible alternatives to achieve the
project's substantial overall net benefits; and (ii) acceptable mitigation measures, such as
compensatory protected areas, are included within the project. The policy further requires the
environmental assessment to identify impacts on biodiversity and species and to determine
endemism, endangered species and to determine project impacts on these species and to propose
acceptable mitigation and monitoring measures.
44. Forests (OP 4.36) – The objective of this policy is to assist borrowers to reduce
deforestation, promote afforestation, harness the potential of forests to reduce poverty in a
sustainable manner, integrate forests effectively into sustainable economic development, and
protect the vital local and global environmental services and values of forests. Bank’s supported
project must not damage critical forests, should avoid or minimize damage to other forests and if
damage to non-critical forests is necessary and justified, it must be adequately mitigated, typically
through compensatory protected areas under the same project.
45. This policy applies to the following types of Bank-financed investment projects: (a)
projects that have or may have impacts on the health and quality of forests; (b) projects that affect
the rights and welfare of people and their level of dependence upon or interaction with forests; and
(c) projects that aim to bring about changes in the management, protection, or utilization of natural
forests or plantations, whether they are publicly, privately, or communally owned. The Bank does
not finance projects that, in its opinion, would involve significant conversion or degradation of
“critical forest areas,” or related critical natural habitats (CNH). As determined by the Bank, if
affected forest areas are “non-critical” the Bank may finance such a project if: (a) no feasible
alternatives to the project or site; (b) “overall benefits substantially outweigh environmental costs”;
and (c) project incorporates “appropriate mitigation measures.” The Bank does not finance projects
that “contravene applicable international environmental agreements.”
46. Physical Cultural Resources (OP 4.11) – This objective of this policy is to avoid adverse
impacts on physical cultural resources or to mitigate such impacts. This policy seeks to avoid the
disturbance and or destruction of PCR as defined by the policy by the projects’ activities. PCR
includes places of worship, buried artifacts, cemeteries and archeological assets, etc. The policy
further requires (i) an environmental assessment to pre-identify and locate PCR’s in the project
29
influence area, (ii) environmental management plan to propose management measures and (iii) to
include chance find clauses in civil works contracts during construction and maintenance stages.
On-site investigations and consultation with the people who value the physical cultural resources
are essential.
47. Indigenous Peoples (OP 4.10) – The objective of this policy is to ensure that development
process fully respects the dignity, human rights, economies and cultures of Indigenous Peoples
(IPs). The policy aims at providing culturally appropriate benefits and gender and
intergenerationally inclusive for the IPs. The policy requires the project to avoid potential adverse
effects on IPs and when avoidance is not feasible, minimize, mitigate or compensate for such
impacts. The policy requires the Government to engage in a process of free, prior and informed
consultations that results in broad community supports for the project in situations where IPs are
present in, or have collective attachment to, the project area and are affected (positive and negative)
by the project and for the preparation of an Indigenous Peoples Plan (IPP) including Social
Assessment (SA) and/or Indigenous Peoples Planning Framework (IPPF).
48. Special attention will also be given for IPs community under OP 4.10. Social sustainability
for Component 1, 2 and 4 will also include measures to enhance the inclusion of benefits to IP and
the delivery of culturally appropriate benefits through the strengthening of the existing systems and
tools (for instance, concerning training, capacity building, knowledge management, manual or
guideline, and M&E). The Project will consider include a more pro-active approach to IP inclusion
and development benefits through a more pro-active targeting of IP communities, additional
support (TA/PD) in areas with IPs, a broader menu of eligible investments for IPs, monitoring and
evaluation of IPs participation and benefits during project implementation. Results of Project
monitoring and evaluation will be used to improve the capacity building delivery (such as for the
PDs and village apparatus) and/or manuals tailored to the needs to increase IPs participation and
benefits.
49. Involuntary Resettlement (OP 4.12) – the overall objectives of this policy are: (a)
involuntary resettlement should be avoided where feasible, or minimized, exploring all viable
alternative project designs; (b) where it is not feasible to avoid resettlement, resettlement activities
should be conceived and executed as sustainable development programs, providing sufficient
investment resources to enable the persons displaced by the project to share in project benefits.
Displaced persons should be meaningfully consulted and should have opportunities to participate
in planning and implementing resettlement programs. Displaced persons should be assisted in their
efforts to improve their livelihoods and standards of living or at least to restore them, in real terms,
to pre-displacement levels or to levels prevailing prior to the beginning of project implementation,
whichever is higher.
50. This policy addresses direct economic and social impacts from the projects’ activities that
will cause (a) involuntary taking of land resulting in (i) relocation or loss of shelter, (ii) loss of
assets or access to assets or (iii) loss of income sources or livelihoods and (b) involuntary restriction
of access to legally designated parks and protected areas resulting in adverse impacts on the
livelihoods of the displaced persons. The policy requires siting of project infrastructure so to be
chosen to avoid these impacts altogether or to minimize them to the extent possible. Where these
cannot be avoided, the policy requires the preparation of either or both of these instruments (i)
30
resettlement policy Framework, (ii) Resettlement Action Plan, and for meaningful consultations
with potentially affected people. The policy prohibits community donations of lands for location-
specific infrastructure.
51. Environmental and social sustainability for Components 1, 2 and 4 will also include
among others, aspects of climate-resilience village, disaster management, labor and gender-
based violence management as well as the World Bank Guidelines on Environment, Health
and Safety. Principles and provisions of these aspects will be mainstreamed in the improvement
of the capacity building and institutional strengthening system of the Project, such as manuals,
guidelines, training modules, training delivery system, terms of references for TA, consultants
and/or facilitators.
52. Component 3, villages that are assessed to have met performance standards will
receive the incentives, which will be provided through on-granting mechanism to districts
currently estimated at about $10,000 per village. The eligibility for villages receiving the grants
is for (1) any sub-project that was not already financed but approved in the village development
plan; and (2) any sub-project that does not trigger anything from a negative list. The negative list
includes exclusion of any sub-project requiring land or assets attached to land, those affecting
physical and cultural resources, natural habitats or forests (refer to Section 7.1 on the detail of
negative list). The activities will be separate from other activities funded in the village plan (not
blended with the village budget), in other words, the grants will be used exclusively for activities
that will be financed only by the grants and will not co-finance any activities financed by other
source of financing in the APBDes.
53. Type of small scale activities at village level which is eligible to be financed under the
incentive mechanism will be an open menu against the negative list, among others: innovative
activity to strengthen local economic development, women empowerment of productivity, small
scale physical infrastructure (with negative list), small-scale innovative technology of water supply
facilities, disability inclusive facilities for school and early childhood center, and so on. The list of
proposed activities must be included in the annual work plan of a village (or Rencana Kerja
Pemerintah Desa), be consulted with communities and local institutions. The small-scale physical
investments, such as improvement and rehabilitation of existing community roads and bridges,
water supply, sanitation, drainage, as well as health and education facilities will be community-
based and community self-built and/or community’s-contractor built.
54. The project triggers OP 4.01 on Environmental Assessment for the activities to be financed
under Component 1, 2 and 4 for potential e-waste, and for Component 3 that might have potential
E&S impacts, however potential environmental and social impacts are insignificant, site-specific,
non-cumulative, non-irreversible, and can be managed by the community with some guidance by
the facilitators with the improved guidance and practical training that have mainstreamed
environmental and social sustainability aspects. Impacts are mainly taking place during
construction such as dust, placement of construction materials, generation of construction wastes,
water flow blockage, etc. Annex 9 SOP for Environmental Management serves as references for
environmental management of these types of civil works.
31
55. Although the performance grants will finance specific investments separate from other
village investments, the Project will identify any potential linkages to other village investments
and/or potential environmental and social impacts at the village level. Cumulative impact is not
envisaged. This will be identified during the sub-project screening and appropriate measures which
will be developed during the preparation of sub-project design to avoid or minimize impacts or to
address impacts.
56. It is clearly defined in the negative list of the Project (see Section 7.1) that sub-projects
under Component 3 shall not be undertaken in prohibited, critical natural habitats (including critical
forest, coastal and marine habitats), nor will it result in the significant conversion of natural
habitats. The activities will not affect the health/quality of forest or involve any forest management.
Identification of potential impacts with respect to impacts for instance, to natural habitats, pollution
events of aquifers, fatalities and injuries and loss of livelihood, etc. will be done during the sub-
project screening and avoidance will be addressed by the designs and alternative sites. The previous
experience with PNPM Rural and from the recent missions revealed that the location of the
proposed small-scale activities can be changed or rerouted should there are any concerns with
forestry and natural habitat aspects.
57. The list of proposed activities to be financed by the performance grants must be included
in the annual work plan and annual budget plan of a village (or Rencana Kerja Pemerintah Desa
and APBDes respectively). Local community who are consulted during the preparation of any
village plans (such as RPJMDes, RKPDes and APBDes) should be aware of the needs to consider
the negative list for the performance grants (which is part of the Guidance for the Performance
grants). The BPD who reviews and approves these plans should include the negative list for the
performance grants as parts of its considerations. District Environmental Agency (DEA) will have
to provide guidance to the village government and community on the negative list for the
performance grants during the preparation and implementation of the village plans particularly for
activities financed by the performance grants. In addition, the DEA should provide awareness and
capacity training to the PTPD (at the sub-district level) who guides the village governments in
preparing and implementing the village plans.
58. As the Project will cover villages in the districts that are geographically dispersed, IPs
presence and/or beneficiaries in some of the villages is anticipated. The Project expects that IPs
would be part of the village community who will benefit from the Project, particularly under
Component 3. Inclusion of IPs group to participate and benefit from the strengthening of capacity
building and institutional strengthening system by the Project under Component 1, 2, 4 will also
follow the provisions of the relevant Indonesian laws and regulations and World Bank OP 4.10 on
Indigenous Peoples.
Labor and Gender-Based Violence
59. The proposed Project Development Objective of the Institutional Strengthening for
Improved Village Service Delivery Project is to “improve the quality of village spending through
better village governance and development performance”. Financing for this project is expected
to help improve and strengthen institutional capacity, information systems and incentives to
improve the quality of village level spending.
32
60. The World Bank has specific guidelines for the protection of workers, prevention of
gender-based violence (GBV) and standards to manage poor labor conditions, and also prevent
child and/or forced adult labor. These guidelines include definitions of what are worker categories;
what are the labor standards to follow (safety, fair treatment, worker protection) among others.
Likewise, for gender-based violence, Bank guidelines define conditions under which women and
girls are likely to face harm due to project interventions. These are mainly, but not restricted to,
circumstances which arise from large civil works requiring labor influx (either from other countries
or other regions in a country). Large-scale civil works are known to increase GBV risks and
prevention measures must be established.
61. Given that the proposed Project is focused on capacity building and institutional
strengthening to improve local Government’s ability to plan, budget, and implement village
development activities; strengthen Government coordination to implement the village law; and to
improve the data collection, monitoring and evaluation systems, and also the Project only involves
small-scale activities financed by the village performance grants implemented through community-
based scheme, it is not expected that issues related to harmful labor practices nor risk of GBV
apply. To capture a wide range of grievances, the Project’s Grievance Redressal Mechanism will
be tailored to ensure a safe modality of communicating sensitive information using a variety of
methods. Attention to local cultural conditions including on gender norms will be given to ensure
the GRM in place is appropriate and resolution oriented. In addition, the Project will ensure that
improved capacity of village government includes awareness raising on inclusion of vulnerable
groups and gender and that such awareness programming is mainstreamed in learning modules,
village annual plans, guidelines, training modules, and terms of references for the facilitators and
monitoring and supervisory team/unit.
3.2 Institutional Capacity
62. The Implementing Agencies of the Project (PIUs of MoHA and MoV) are responsible to
ensure that environmental and social sustainability is mainstreamed in the Project23. Both agencies
have involved in the PNPM-Rural and are aware of the importance of environmental and social
sustainability aspects in the implementation of the Village Law. Nonetheless, capacity still needs
to be strengthened to ensure that environmental and social sustainability aspects as specified in
various manuals, guidelines, and training modules are consistently implemented. A World Bank
Study on the Evaluation of Infrastructure Built with Village Funds (2018) suggested that 74% of
the sampled sub-projects had been implemented using appropriate environmental safeguards
practices, but only 34% of the sampled sub-projects had correctly followed the social safeguards
mechanisms as stipulated in the Village Development Guidelines24.
63. To address the above situation, in addition to training provided to the PTPD and PD as well
as to the village apparatus with modules and training delivery that have mainstreamed
environmental and social sustainability (ESS), the Project intends to (1) strengthen the monitoring
and supervision activities by including monitoring indicators representing the inclusion of ESS
23 See Annex 1: Project Implementation Arrangements and Support Plan. 24 Peraturan Menteri Dalam Negeri No. 114/2014 on the Village Development Guidelines.
33
sustainability; (2) include the district environmental agency (DEA) to provide awareness and
capacity training to the district inspectorate, PTPD (at the sub-district level) on the ESS; (3) provide
guidance to the village government and community on the ESS and the negative list for the village
grants during the preparation and implementation of the village plans particularly for activities
financed by the performance grants; (4) include the ESS sustainability aspects in the monitoring
and supervision activities to villages carried out by the PTPD; and/or (5) include the ESS and the
negative list as part of the criteria for the performance grants.
4. OBJECTIVES OF THE ENVIRONMENTAL AND SOCIAL MANAGEMENT
FRAMEWORK (ESMF)
64. The objective of this Environmental and Social Management Framework (ESMF) is to
provide reference and guidance for the Project management and Project implementation staff at
national, provincial, district, sub-district and village levels, as well as consultants, facilitators and
community groups participating in the implementation of Village Law on
a. strengthening the objectives, principles and the requirements of the environmental and
social sustainability appropriately into the new and current instruments and approaches for
capacity building and institutional frameworks system such as guidelines, manuals, training
modules and deliveries for planning, budgeting, implementation, monitoring and
supervision of village sub-projects.
b. screening and identifying potential environmental and social safeguards impacts of the
physical investment financed by the village performance grants, type of instruments for
mitigation measures or documentation of the mitigation measures;
c. institutional arrangements for implementing the environmental and social sustainability
aspects in the Project; and
d. GRM, public consultations, disclosures, and capacity building plan
e. Monitoring
65. This ESMF is prepared with reference to the relevant Indonesia Laws and Regulations on
environmental and social sustainability, World Bank OP 4.01 on Environmental Assessment, OP
4.04 on Natural Habitat, OP 4.36 on Forests, OP 4.11 on Physical Cultural Resources, OP 4.10 on
Indigenous Peoples and OP 4.12 on Involuntary Resettlement as well as WBG Environmental,
Health and Safety Guidelines. This ESMF also outlines the Indonesian protocols and practices to
manage e-wastes.
5. ENVIRONMENTAL AND SOCIAL SUSTAINABILITY ASPECTS IN THE
CURRENT IMPLEMENTATION OF THE VILLAGE LAW AND DIRECTION
TOWARDS STRENGTHENING
66. Law No. 6/2014 and its implementing regulations stipulate the responsibility and authority
of the village among others, to develop and maintain infrastructure and environment in accordance
with its capacity and available local resources; to carry out environmental management of the
village; to promote inclusive development (including the poor, women, local culture, tradition,
customary community – including IPs) through participatory planning and monitoring; and to
promote disclosure and manage complaints.
34
67. Manuals and training modules. The implementation of the Village Law is guided by
various guidelines, manuals and training modules, issued by the MoHA and the MoV. Relevant to
environmental and social sustainability aspects are:
Guidelines:
a. MoHA Regulation No. 114/2014 on Village Development Guidelines
b. MoHA Regulation No. 20/2018 on Village Financial Management
c. MoV Regulation No. 2/2015 on Guidelines for Decision Making Procedures and
Mechanisms in Village Consultations
d. MoV Regulation No. 3/2015 on Village Mentoring
e. MoV Regulation 16/2018 on the Priority for the Utilization of Dana Desa 2019.
68. Amongst the above-listed guidelines, environmental and social sustainability aspects have
been explicitly stipulated in the Village Development Guidelines, notably in the preparation and
implementation of the Medium-term Village Development Plan (RPJMDes) and Village Annual
Work Plan (RKPDes). For RKPDes, Article 62, 67 and 68 stipulate that the Implementor of the
Activity (Tim Pelaksana Kegiatan = TPK) should prepare documentation for the land and assets
that need to be acquired for the sub-project or activity (voluntary land donation or direct purchase),
prepare a report on the assessment of potential environmental and social impacts, ensure that
documentation of land transfers are properly prepared; ensure that poor households are properly
compensated for their acquired land and assets by the APBDes. Furthermore, the Guidelines also
stipulate the mechanisms for inclusive public consultations (for RPJMDes, Article 25; for RKPDes,
Article 46, including women, poor community); complaint handling (Article 78), monitoring and
supervision of the village community during the planning and implementation of the village
development (Article 85). The Guidelines state that information disclosures of the RKPDes,
APBDes and Work Plan are carried out through public consultations at various levels in the village,
web-based village information system, information board, and other available venues.
69. The MoV Regulation 16/2018 on the Priority for the Utilization of Dana Desa (DD) 2019
stipulates that DD can be used for village development and community village empowerment.
Across these two development areas, it promotes sustainable village development, environmental
preservation, disaster management, also provide special attention for vulnerable groups including
women, the poor families, disabled and stunting. The regulation also requires public consultations
and development of information and communication management through various media. Further,
the regulation stipulates that priority of the utilization of the DD should be discussed in the
preparation of the preparation of the RKPDes through public consultations.
70. Based on the brief reviews of the above-said regulations, the Project is planning to
strengthen the environmental and social sustainability aspects, either in the new and/or each of the
above-listed regulation or by developing a Technical Guidelines for Environmental and Social
Sustainability for the implementation of the Village Law, to the extent relevant and applicable. The
strengthening action will follow the relevant Indonesian laws and regulations and the World Bank
safeguards policies applicable to this Project as explained in Section 3 above, i.e. the objectives,
key principles and requirements of OP 4.01 (Environmental Assessment), OP 4.04 (Natural
Habitat), OP 4.36 (Forest), OP 4.11 (Physical Cultural Resources), OP 4.10 (Indigenous Peoples)
and OP 4.12 (Involuntary Resettlement). Refer also to Section 6 on how the objectives, key
35
principles and requirements of the applicable OPs as well as the Bank’s Guidelines for
Environment, Health and Safety will inform the elements of mainstreaming in the Component 1, 2
and 4 of the Project. A negative list for this Project (see Section 7.1) will be taken into consideration
as element of mainstreaming.
71. Strengthening of the environmental and social sustainability aspect is particularly needed
during the preparation and implementation of RPJMDes and RKPDes; preparation and
implementation of APBDes and design of sub-projects (during the preparation of the Rencana
Kegiatan) to be financed by the APBDes, as well as the monitoring and supervision of the
implementation of these plans. Strengthening areas may include detail guidance of: (1) sub-projects
negative list; (2) identification of potential environmental and social impacts/issues; (3) preparation
of mitigation measures instruments; (4) documentation of the implemented instruments; (5)
meaningful consultation; (6) disclosures; (7) budgeting the preparation and implementation of the
instruments; and (8) monitoring and supervision of the implementation of the RPJMDes, RKPDes,
APBDes and Work/Activity Plan (Rencana Kegiatan).
72. In addition, social sustainability includes measures to enhance the inclusion of benefits to
IP and the delivery of culturally appropriate benefits through the strengthening of the existing
guidelines/manuals, training modules, and training delivery. The Project will include a more pro-
active approach to IPs inclusion and development benefits during the preparation and
implementation of RPJMDes, RKPDes, APBDes and design of sub-projects.
73. The Project is planning to use lessons learned and leverage the relevant materials that have
been developed in the PNPM-Rural Project’s environmental and social safeguards operational
technical guidelines.
Training Modules:
a. Pre-assignment training modules for village facilitator for infrastructure (PD-TI)
b. Pre-assignment training modules for village facilitator for empowerment (PD-P)
c. Pre-assignment training modules for local village facilitator (PLD)
d. Training modules for village apparatus in preparing the RPJMDes, RKPDes and APBDes
(not yet available).
74. Amongst the first three of the above-listed training modules, environmental and social
sustainability aspects is only covered in the pre-assignment training modules for village facilitator
for infrastructure (PD-TI). It covers brief principles on land acquisition, IPs, timber management,
and resettlement, screening criteria, outcome indicators for environmental and social safeguards
management, the roles of PLD and village cadres in ensuring the implementation of environmental
and social safeguards; evaluation and environmental management (physical and social), and
strategy for reducing and mitigating impacts due to disasters. The module also includes the format
for voluntary land donation, identification of potential environmental impacts, and a format on the
commitment for operation and maintenance of the infrastructure. Some of the ongoing capacity
building activities carried out by MoHA and MOV are presented in Annex 2 and Annex 3.
75. Capacity and current practices. Overall, awareness and capacity of the stakeholders
involved in implementing the village law on the environmental and social sustainability (ESS) are
36
limited, including at the central level (MoHA and MoV), provincial, district, sub-district and village
level. Some of the MoHA staff who were involved in the PNPM-Rural are aware of the
environmental and social sustainability. Further, village facilitators who had been involved in the
PNPM-Rural have some awareness and understanding on environmental and social sustainability
and used their knowledge during their facilitation to the village community. However, in general,
facilitators (Village Facilitator (PD: PD-P and PD-TI) and Local Village Facilitator (PLD)) have
a very limited awareness and capacity on environmental and social sustainability.
76. Awareness and capacity of the village apparatus in environmental and social sustainability
aspect for the physical investment financed by the APBDes is very limited. Environmental
mitigation measures were not planned during the sub-project design but implemented based on
needs identified during the construction. Consistent with the findings of the World Bank Study on
the Evaluation of Infrastructure Built with Village Funds (2018) mentioned above, field visit to
villages (such as Kabupaten Aceh Utara) revealed that voluntary land donation was rarely
documented, although the village apparatus agreed that it is important to avoid conflict in the future.
The PTPD (Pendamping Teknis Pemerintahan Desa) who oversees and advices the village in
preparing the RKPDes and APBDes have also limited awareness and knowledge in environmental
and social sustainability aspect, similarly with the PD and the PLD.
77. As explained in Section 3.2, to address the above situation, in addition to training provided
to the PTPD and PD as well as to the village apparatus with modules and training delivery that
have mainstreamed ESS’ objectives, principles and requirements, the Project intends to (1)
strengthen the monitoring and supervision activities by including monitoring indicators
representing the inclusion of ESS sustainability; (2) include the district environmental agency
(DEA) to provide awareness and capacity training to the district inspectorate, PTPD (at the sub-
district level) on the ESS; (3) provide guidance to the village government and community on the
ESS and the negative list for the performance grants during the preparation and implementation of
the village plans particularly for activities financed by the performance grants; (4) include the ESS
sustainability aspects in the monitoring and supervision activities to villages carried out by the
PTPD; and/or (5) include the ESS and negative list as part of the criteria for the performance grants.
6. FRAMEWORK FOR MAINSTREAMING ENVIRONMENTAL AND SOCIAL
SUSTAINABILITY ASPECTS IN THE CAPACITY BUILDING AND
INSTITUTIONAL STRENGTHENING OF THE IMPLEMENTATION OF THE
VILLAGE LAW
78. While the Project supports the implementation of the Village Law through the
establishment and use of digital information technology (internet and off-line), the assessment
presented in the Section 3 and Section 5 above suggest that strengthening areas for environmental
and social sustainability aspects is needed to ensure that ultimately the planning and
implementation process, the various plans and their implementation at the village level ensures
sustainable development that benefits all population segments. The system strengthening is
expected to promote a more effective and sustainable spending of the APBDes as avoidance and
impact mitigation measures will have been planned upstream at the RKPDes, APBDes and activity
design stage.
37
79. The strengthening will follow the relevant Indonesian laws and regulations and the World
Bank safeguards policies applicable to this Project as explained in Section 3.1 and Section 5 above,
i.e. the objectives, key principles and requirements of OP 4.01 (Environmental Assessment), OP
4.04 (Natural Habitat), OP 4.36 (Forest), OP 4.11 (Physical Cultural Resources), OP 4.10
(Indigenous Peoples) and OP 4.12 (Involuntary Resettlement).
80. In addition, the underpinning objectives, key principles and requirements of the ESS which
are governed under OP 4.01 that serve as an umbrella policy for other safeguards policies applicable
to this Project, i.e., OP 4.04, OP 4.36, OP 4.11, OP 4.10 and OP 4.12. will inform the mainstreaming
to the Component 1, 2, and 4. As relevant, this includes:
a. Avoidance, and if it is not possible, minimize environmental and social impacts of a
sub-project; to the extent feasible, preventive measures are preferable over mitigatory
or compensatory measures
b. Screen, identify and assess potential environmental and social impacts using screening
check list25, thresholds requirements, and potential associated risks, if any;
c. Determine tangible measures to prevent, minimize, mitigate or compensate for these
adverse impacts;
d. Mitigate environmental and social impacts through the adjustment of sub-project
design, planning, sites and/or through the preparation of appropriate instruments;
e. Implement the instruments prior to, during and after construction of a sub-projects as
applicable; the instrument includes a set of mitigation, monitoring and institutional
measures to be taken during the design, implementation and operations phases of a
sub-project;
f. Process of environmental and social assessment will involve consultations with the
project affected persons and the public (in this Project with the village community) as
applicable;
g. Disclosure of the environmental and social safeguards instruments to the public (in this
Project with the village community), particularly the project affected persons;
h. Monitor and evaluate the implementation of the instruments ensuring that the sub-
project is environmentally and socially sustainable.
81. Mainstreaming objectives, key principles and requirements of OP 4.04 in Component 1, 2
and 4 includes among others, screening to identify potential natural habitats presence such as
wetland, peatland, forest boundaries, protected forest, and developing a system in preventing
natural habitats from conversion and degradation. The negative list specifies the types and
characteristics of natural habitats which need to be avoided e.g. wetland, peatland, grass land and
outline specific prohibition measures to prevent indirect or induced adverse impacts, such as from
the small-scale access road development toward forest boundaries by allowing only small-scale
road rehabilitation/development in residential areas or surrounding public facilities.
25 Public Works Ministerial Regulation No. 10/PRT/M/2008 on Type of Public Works Activities that need a UKL-
UPL. Requirements for activities that need UKL-UPL are also specified in the Regulation of the Ministry of
Environment No. 5/2012 on the Type of Activities that Require an AMDAL. See also Regulation of the Ministry
of Environment and Forestry No. 26/MENLHK/SETJEN/KUM.1/7/2018 on the Guidelines for Defining
Activities that Require an UKL-UPL and a Statement Letter of Commitment to Manage and Monitor the
Environment (SPPL).
38
82. On OP 4.36, to the extent relevant to the Project, mainstreaming will include among others
the need to identify forest types and boundaries and its functions including services provided to the
villagers. Further, the screening of sub-project will exclude the villages which part of their areas
are forests and villages that are located in the surrounding forests area to prevent potential indirect
impacts from the forbidden of the small-scale road development leading to forest boundaries (road
rehab/development are only allowed for residential areas or public facilities for this village
category).
83. On OP 4.11, to the extent relevant, the mainstreaming will cover among others, screening
that identify potential physical cultural resources in the village during the preparation of a sub-
project, avoid the disturbance or impacts to the PCR through re-design or re-route or choose another
sub-project site. Any civil works contract or community civil works contract will include chance
finds clauses to avoid or manage impacts in the case that during construction the village community
happens to find PCR which were unknown prior to the sub-project design. Chance finds procedures
will be included in the manuals, guidance and/or training modules in the Project.
84. On OP 4.10, mainstreaming of the objective, key principles and requirements of this policy
to Component 1, 2 and 4 will include among others, screening and verification of IPs, provisions
of a free, prior, informed consultations that lead to broad supports of the IPs community to a
subproject, social assessment, preparation of an Indigenous Peoples Plan (IPP) in reference to the
IPPF in this ESMF.
85. Special attention for mainstreaming the objectives, key principles and requirements of OP
4.10 in Component 1, 2 and 4 will also include measures to enhance the inclusion of benefits to IP
and the delivery of culturally appropriate benefits through the strengthening of the existing systems
and tools (for instance, concerning training, capacity building, knowledge management, manual
and guideline, and M&E). The Project will consider include a more pro-active approach to IP
inclusion and development benefits through a more pro-active targeting of IP communities,
additional support (TA/PD) in areas with IPs, a broader menu of eligible investments for IPs,
monitoring and evaluation of IPs participation and benefits during project implementation. Results
of Project monitoring and evaluation will be used to improve the capacity building delivery (such
as for the PDs and village apparatus) and/or manuals tailored to the needs to increase IPs
participation and benefits.
86. To the extent possible, the mainstreaming of the objectives, key principles and
requirements of OP 4.12 into Component 1, 2 and 4 includes among others, (a) avoidance of
involuntary resettlement where feasible either through alternative sub-project designs, change the
sub-project site or re-route; (b) address impacts due to resettlement if avoidance is not possible,
prepare a resettlement action plan through meaningful consultations with the affected persons; (c)
assist the affected persons to improve their livelihoods and standards of living or at least restore
them; (d) disclose the resettlement action plan, etc. Refer to Section 3.1.
87. A negative list for this Project (see Section 7.1) will be taken into consideration as element
in the mainstreaming and the Project will also apply the Bank’s Guidelines for Environmental,
Health and Safety.
39
88. The Project manuals, guidelines, training modules and TORs for facilitators etc. will
include the elements explained above paragraphs as part of the mainstreaming. In addition, other
indicative key strengthening areas on ESS sustainability aspects as presented in Table 3 below
include:
a. aspects of climate-resilience village, disaster management, labor and gender-based
violence management;
b. provisions for managing potential environmental and social impacts, and improvement of
stakeholder engagements, inclusion of vulnerable groups, Indigenous Peoples community,
and gender as well as complaint handling system; in the new and existing manuals,
guidelines, training modules, awareness training, integrated data-base management, and
training delivery system, terms of references for TA, consultants and/or facilitators and
monitoring and supervisory team/unit.
89. The key strengthening areas as summarized in Table 3 will be elaborated and confirmed in
the first year of Project implementation as mainstreaming environmental and social sustainability
aspects in the capacity building and institutional strengthening system will be developed based on
needs.
Table 3: Indicative Key Strengthening Areas26
Manuals/Guidelines/ Training Modules Element of strengthening areas27
- Village Development Guidelines Improvement of the existing environmental and
social sustainability aspects, e.g. screening and
impact identification; disaster management and
climate change; potential natural habitats
presence; forest types and boundaries and its
functions including services provided to the
villagers; potential physical cultural resources;
labor and gender-based violence management; Indigenous Peoples; safeguards instruments;
information disclosures; budgeting, monitoring
and supervision for safeguards instruments.
- Village Financial Management Add environmental and social sustainability
aspects, e.g. screening and impact identification;
disaster management and climate change;
safeguards instruments; information disclosures;
budgeting, monitoring and supervision for
safeguards instruments.
- Guidelines for Decision Making Procedures
and Mechanisms in Village Consultations
Add environmental and social sustainability
aspects, e.g. information disclosures; meaningful
consultation, grievance redress mechanism.
➢ Village Mentoring Add environmental and social sustainability
tasks, particularly the PLD, e.g. provisions for
managing potential environmental and social
impacts, stakeholder engagements, inclusion
of vulnerable groups, Indigenous Peoples
community, and gender as well as complaint
26 Element of strengthening areas will be elaborated and confirmed during the first year of Project implementation. 27 Improvement or additional of the elements of the environmental and social sustainability aspects vary among
these guidelines/training modules depending on the users/target groups.
40
Manuals/Guidelines/ Training Modules Element of strengthening areas27
handling system
➢ Priority for the Utilization of Dana Desa
2019
Add environmental and social sustainability
aspects, e.g. screening and impact identification;
disaster management and climate change;
potential natural habitats presence; forest types
and boundaries and its functions including
services provided to the villagers; potential
physical cultural resources; labor and gender-
based violence management; Indigenous
Peoples; safeguards instruments; information
disclosures; budgeting, monitoring and
supervision for safeguards instruments.
➢ Or, develop new Technical Guidelines on
Environmental and Social Sustainability for the
Implementation of Village Law
As relevant, leverage lessons learned and the
PNPM-Rural Technical Operational Guidelines
Training Modules
Through Akademi Desa 4.0
➢ Pre-assignment training modules for
village facilitator for infrastructure (PD-TI)
Improvement or add of the existing
environmental and social sustainability aspects,
e.g. screening and impact identification; disaster
management and climate change; potential
natural habitats presence; forest types and
boundaries and its functions including services
provided to the villagers; potential physical
cultural resources; labor and gender-based
violence management; Indigenous Peoples;
safeguards instruments; information disclosures;
budgeting, monitoring and supervision for
safeguards instruments.
➢ Pre-assignment training modules for
village facilitator for empowerment (PD-P)
➢ Pre-assignment training modules for
local village facilitator (PLD)
➢ Training modules for village apparatus
and village community group (LKM, KPMD,
etc.) in preparing the RPJMDes, RKPDes and
APBDes
Add environmental and social sustainability
aspects, e.g. screening and impact identification;
disaster management and climate change;
potential natural habitats presence; forest types
and boundaries and its functions including
services provided to the villagers; potential
physical cultural resources; labor and gender-
based violence management; Indigenous
Peoples; safeguards instruments; information
disclosures; budgeting, monitoring and
supervision for safeguards instruments..
Awareness Training
- Awareness training modules for the preparation
and implementation of RPJMDes, RKPDes for the
TAPMD (esp. TA-ID), PTPD, officials of DPMD,
and District Inspectorate (new), provincial satker.
Develop new modules - substance of
environmental and social sustainability are
mainstreamed
Integrated Data-based Management/ InfoDesa Develop attributes related to information on the
environmental and social sustainability aspects,
e.g. information on natural habitats; forest types
and its boundaries; Indigenous Peoples, disaster
management and climate change, physical
cultural resources.
41
Manuals/Guidelines/ Training Modules Element of strengthening areas27
Terms of References – Through Market Place
1. TAPMD (esp. TA-ID)
2. PD-TI
3. PD-P
4. PLD
Add tasks for providing oversight and/or
mentoring in ensuring environmental and social
sustainability aspects are considered in the
RPJMDes, RKPDes, APBDes, Activity Design,
e.g. provisions for managing potential
environmental and social impacts, stakeholder
engagements, inclusion of vulnerable groups,
Indigenous Peoples community, and gender as
well as complaint handling system
Performance Criteria Include ESS aspect as relevant
Socialization of the Performance Criteria to the
villages, sub-districts, and districts
Socialization and training for the BPKP
on the performance criteria
Integrated data-based management Include attributes related to ESS aspects, such as
information on natural resource development,
good practices on environmental and social
sustainability, etc.
7. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK FOR
COMPONENT 3 AND E-WASTE
90. This section is specifically prepared for ensuring that environmental and social
sustainability aspects are implemented for the Project Component-3 (strengthening village
government performance) on which will pilot test a performance incentive grant to village
governments demonstrating improvements in pre-determined result criteria, as well as
strengthening systems of verification and outcome monitoring. As explained earlier, the
performance grants will be recorded in the APBDes and will be used for activities that are solely
financed by the grants. The grants will not co-finance any other activities.
91. Type of small scale activities at village level which is eligible to be financed under the
incentive mechanism will be an open menu against the negative list, among others: innovative
activity to strengthen local economic development, women empowerment of productivity, small
scale physical infrastructure (with negative list), small-scale innovative technology of water supply
facilities, disability inclusive facilities for school and early childhood center, and so on. As
suggested by the Viper Study and PNPM-Rural, the typical small-scale physical investments would
be improvement and rehabilitation of existing community roads and bridges, water supply,
sanitation, drainage, as well as health and education facilities. Mostly will be community self-built
or utilizing small local contractors hired by the village (Tim Pelaksana Kegiatan). The list of
proposed activities must be included in the RKPDes and in the APBDes, be consulted with
communities and local institutions and approved by the BPD as well.
92. While under project component 1, 2 and 4, the likely impacts have already been identified
in terms of potential electronic waste as consequences of the introduction of a digitalized, IT-based
tools, development of e-platform and e-services for learning, capacity building, knowledge
management, harmonization of regulations, oversight and monitoring, and integrated information
42
and data management. Component 1, 2 and 4 will not involve any physical or preparation of any
plans that would led to the implementation of physical investment or activities involving
downstream environmental and social impacts and risks. The measures for preventing the
environmental impacts of the e-waste to the environment and human health seems quite straight
forward and will follow a procedures or protocol for e-waste disposal which developed by the
Government. However, awareness program and capacity building will need to be arranged, to
educate people and whole community on issue of e-waste, its potential impact and how to manage
the risks. The procedure is described below under section 7.2.
93. The ESMF for Component 3 and e-waste disposal is an instrument that examines the issues
and impacts associated when a project consists of a program and /or series of sub-projects, and the
impacts cannot be determined until the program or subproject activities details have been identified.
The ESMF set out the principles, rules, guidelines, instruments and procedures to assess the
environment and social impacts. It contains measures and plans to reduce, mitigate and/or offset
adverse impacts and enhance positive impacts. Costs for preparing and implementing the
safeguards instruments for component 3 will be covered by the village budget (APBDes) and for
the e-waste disposal management by the PIUs of MoHA and MOV (also refer to Section 14).
94. Overall responsibility for implementing the ESMF under this section 7 belongs to the PIUs
of the MoHA and MoV. The village government or Tim Pelaksana Kegiatan (TPK) will be
responsible to screen the proposed sub-project using screening check list, negative list and identify
potential environment impact as well as prepare mitigation measures. The proposed activities to be
financed by the performance grants will be reviewed by the district PIU with the assistance of the
PTPD of the sub-district. Provincial PIU will review the consolidated proposed activities from all
districts in a particular province and submit the results of the review to the PIUs in MoHA. MoHA
will then submit the approved proposed activities to be financed by the grants to the MoF. With
assistance of NMC, the PIUs in coordination with the provincial and district PIU will monitor the
overall compliance of the activities financed by the performance grants with the ESMF under
section 7.
95. The PIU of MoHA and MoV, with the assistance of the consultants will provide training to
the village governments, PTPD in the sub-district, and facilitators on the screening (including
negative list), identification and assessment of potential impacts, preparation of appropriate
instruments, consultations with the villagers and affected persons, etc. The Project plans to provide
such training in the year 1 of Project implementation. The training will be part of the overall training
modules as specified in Section 12.
7.1 Principles, Screening and Safeguards Instruments
96. Principles
a. Subprojects should avoid, and if unavoidable, should minimize negative environmental and
social impacts, including land acquisition and IPs affected, and the village government
should have explored viable alternative location and/or designs to minimize any such
negative environmental and social impacts;
43
b. Sub-project should not make affected persons worse off in terms of environmental
conditions, income, livelihoods as well as other social and cultural aspects. The sub-
projects are expected to generate positive impacts for affected persons.
c. Should such negative impacts be unavoidable, it is necessary to ensure that mitigation
measures are developed to minimize such negative impacts and/or restore to original
conditions, either during the planning, preparation or implementation stage. Any subproject
entailing a negative environmental and social impact should be accompanied by a plan to
mitigate and address such impacts;
d. Environmental management, land acquisition and the management of IPs should be carried
out based on the principles of transparency, public participation and consultation with the
affected persons using adequate information which is to be provided as early as possible,
and involve relevant stakeholders, not limited to Local Government, but also from local
NGOs, academic institutions, and the public.
e. Aspirations and recommendations identified as a result of the public consultation with
affected persons which minimize the negative impact of the sub-project or may maximize
its positive impact must be considered in the design, implementation, operation and
maintenance of the said sub-project.
f. The process of public consultation, results of the agreement and revised plan on the
environmental management, land acquisition the IPs Plan should be publicly disclosed to
the public through available local media and in public facilities accessible to all community
members.
g. The consultation process, agreements, plans and implementation of environmental
management plans, land acquisition as well IPs Plans must be properly documented and
integrated into the proposed sub-projects and in the village report of APBDes
implementation.
h. Subprojects should be in specified in the approved RKPDes and APBDes and avoid
protected areas designated by the Ministry of Environment and Forestry;
i. The subprojects will not trigger World Bank OP 4.04 Natural Habitat, OP 4.36 Forest and
OP 4.11 Physical Cultural Resources. It has been defined in the negative list of
infrastructure/physical investment in Component 3 that the project will not finance sub-
projects to be undertaken in prohibited, critical natural habitats (including critical forest,
coastal and marine habitats), nor will it result in the significant conversion of natural
habitats. The activities will not affect the health/quality of forest or involve any forest
management. The activities will not adversely affect any sites with archaeological,
paleontological, historical, religious or of unique natural value as defined under the policy.
97. Screening
a. The village government or the Tim Pelaksana Kegiatan (TPK) in particular will screen the
proposed sub-projects using screening checklist (see Annex 5 Report on Environment
Screening and Annex 6 on Screening Format for Generic Sub-project)28 and identify
potential environmental impacts, the land need (refer to the negative list), and check
whether IPs or Masyarakat Adat (MA) community are presence in the sub-project area. If
28 Annex 5 and 6 will be expanded during the preparation of the Program Implementation Guidelines in year 1 of Project
implementation.
44
MA presence, identify whether they are part or the sole beneficiaries of the sub-projects or
they will be potentially affected (positively or negatively).
b. Identify the type and intensity of potential environmental impacts; location, amount and
number of land plots, number of land owners, number of occupants/users of land that will
be needed by the sub-project. Verify the IPs presence, benefitted and/or impacted through
meaningful consultations, involving MA leaders, village leaders;
c. Identify linkage and/or potential impacts of the sub-project and inform the person who is
in charge of preparing the sub-project design.
98. Negative list
a. Sub-projects eligible for financing should not include activities with significant, sensitive,
complex, irreversible and unprecedented potential adverse environmental and social
impacts requiring a full environmental assessment to manage and mitigate such impacts in
accordance with Ministry of Environment Regulation No. 5, 2012, Ministry of Public
Works and Housing Regulation No. 10, 2008. Should there be a subproject identified
otherwise, the project will not finance it.
b. Sub-projects involving the following are ineligible for financing under the village
performance grants:
(1) Using material which depletes ozone layer in the atmosphere, tobacco or any products
containing tobacco, and pesticide.
(2) Using asbestos as construction material.
(3) Using raw material and hazardous & toxic waste (B3). The project cannot finance any
project activity which uses, produces, stores or transports raw material and hazardous
& toxic waste such as toxic substance, material which may cause rush or explosion
and any other materials categorized as B3 under Indonesian law.
(4) Carry out sub-project or activity within, traversing or adjacent to forests. The Project
cannot finance any sub-project or activity that is located within, traversing or adjacent to
forests, including conservation forests (natural parks, natural reservation forest,
conservation forest, and hunting parks)29, production forests and protection forests. Some
village infrastructure that are located near forests is allowed if they only involve quality
improvement of existing infrastructure and is necessary for the benefit of IPs, however,
the other ineligibility criteria specified in this negative list shall apply.
(5) Protected and sensitive areas, natural habitat and critical natural habitat. The Project
cannot finance any sub-project of activity that is located within, adjacent to or
traversing protected areas and sensitive areas such as natural conservation areas etc.
or any sub-project or activity which may alter the function or effectiveness of
protected and sensitive areas. Additionally, the Project cannot finance any sub-project
or activity which causes significant conversion and/ or degradation of the natural
habitat or any critical natural habitat environment including those of terrestrial, coastal
and marine ecosystems.
(6) Destroys cultural conservation area. The Project must not finance any project which
degrades or destroys cultural value of a cultural conservation area, not only limited to
29 Based on Government Regulation no. 22 of 2001 on Forest Management and Forest Management Planning, Forest
Utilization and Forest Area.
45
artefact and cultural structure, but also locations considered sacred or having high
spiritual value for local people. In the contract agreement with the contractor, there
must be provisions and guideline concerning what measures must be taken if these
artefacts and structures are found within the project site. Measures should follow the
Chance Finds Procedure as presented in Annex 19.
(7) Those need land or need to acquire assets attached to land
(8) Using timber from illegal logging. The Project must not finance infrastructure related
to or support illegal logging.
(9) The Project must not finance new or rehabilitation irrigation construction in wetland
areas.
99. The PIU of MoHA will have to ensure that one of the eligibility criteria of the performance
grants is the negative list. The district PIU will make the first review of the proposals of the winning
villages to be financed by the grants, which will be then reviewed by the PIU of MoHA. PIU of
MoHA and District PIU will monitor the implementation of the negative list in the activities
financed by the performance grants. The list of proposed activities to be financed by the
performance grants must be included in the annual work plan and annual budget plan of a village
(or Rencana Kerja Pemerintah Desa and APBDes, respectively). Local community who are
consulted during the preparation of any village plans (such as RPJMDes, RKPDes and APBDes)
should be aware of the needs to consider the negative list for the performance grants (which is part
of the Guidance for the Performance grants). The BPD who reviews and approves these plans
should include the negative list for the performance grants as parts of its considerations. District
Environmental Agency (DEA) will have to provide guidance to the village government and
community on the negative list for the performance grants during the preparation and
implementation of the village plans particularly for activities financed by the performance grants.
The DEA should provide awareness and capacity training to the PTPD (at the sub-district level)
who guides the village governments in preparing and implementing the village plans.
100. Environmental and social safeguards instruments
a. Once the sites, delineation of impacts areas, type of impacts and intensity of impacts are
identified, the TPK will select the appropriate instruments. Formats for UKL-UPL (Annex
7 and 8), SPPL (Annex 10) and SOP for environmental management (Annex 9); Typical of
sub-project impacts and mitigation measures is provided in Annex 11. Annex 12 and 13
describes generic format for Environmental Codes of Practices (ECOPs) that are based on
good environmental management practices. More explicit requirements on construction
practices in rural areas based on the main typologies of community investments that can be
adopted during sub-project preparation and implementation under Component 3 is Manual
of “The DOs and DON’Ts: Environmental Management: General Considerations-Site
Screening-Construction Site Management, Roads, Water Supply, Sanitation, Solid Waste
Management, Markets, Rivers” prepared by the PNPM-Rural Project30. The Institutional
30 This Guidance Book, English version can be accessed through
http://documents.worldbank.org/curated/en/925701495170561883/The-dos-and-the-donts-environmental-management-
general-considerations-site-screening-construction-site-management-roads-water-supply-sanitation-solid-waste-
46
Strengthening for Improved Village Service Delivery Project civil work activities should
use these practices to minimize the negative environmental impacts. These good practices
are provided as examples, but measures are not limited to the ones described here, some
measures will be locally specific and can be adapted using the best locally available
technology.
b. The TPK will prepare the appropriate safeguards instruments in consultations with the
affected persons. Consultations, agreements and disagreements should be documented. If
agreement was not reached, the design or location of sub-project has to be changed.
c. The safeguards instruments should be verified by the PLD and PD-TI and approved by the
PTPD. The instruments have to be disclosed by the TPK in the venue and in a way that
villagers can easily access the information.
d. The approved safeguards instruments should be part of the sub-project proposal or plan.
Details on the institutional arrangements at the village level for preparation, review and approval
of the screening process and environmental and social safeguards instruments are provided in
Section 11.
7.2 Protocol for E-Waste Disposal
101. The proposed project activities will not involve any physical investment or preparation of
any plans that would lead to the implementation of physical investment or activities involving
downstream environmental and social impacts and risks. However, likely activities relevant to
establishment or development of e-platform for facilitation services and e-learning platform as well
as strengthening data base system might involve investment in digital/electronic equipment or
hardware, e.g., computers and other electronic equipment. Subsequently, the World Bank’s
Safeguards Policies OP 4.01 on environment assessment will be triggered due to its potential of
electronic waste (e-waste). E-waste is any electronic items or equipment which no longer needed
(whether still functioning or broken) and which intended to be discarded. This type of waste is
categorized as hazardous waste due to its contains of various hazardous and toxic materials such
as lead, mercury, arsenic, cadmium, selenium and chrome. Hazardous waste included e-waste is a
specific waste which need special treatment. Without a proper disposal management, this e-waste
can cause negative impact to the human health and environment. Detail of e-waste management is
presented in Annex 4.
102. The following are a list of some electrical and electronic equipment relevant to Information
Technology (IT) and Telecommunications equipment which subject to e-waste disposal
management:
• Centralized data processing systems: mainframes, mini computer
• Personal computing:
o Personal computer (Central Processing Unit with input and output devices)
o Laptop (Central Processing Unit with input and output devices)
o Notebook computers
management-markets-and-rivers. This Guidance Book, Bahasa Indonesia version can be accessed through
http://documents.worldbank.org/curated/en/188631468042887318/Baik-and-buruk-pengelolaan-lingkungan.
47
o Notepad computers
• Printer including cartridge
• Copying equipment
• Electrical and electronic typewriter
• User terminal and systems
• Facsimile
• Telephones
103. The government is responsible for hazardous waste management. The Law no 32/2009 on
Protection and Management of the Environment and the Law no 18/2008 on Solid Waste
Management cover in general the need to manage hazardous waste from all sources. Government
Regulation No 101 Year 2014 on management of hazardous waste, specifically regulate how to
determine, reduce, storage, collection up to dumping and transboundary movement of hazardous
waste as well as emergency response. The government need to ensure that the e-waste is handled
properly while community/individual must participate in reducing, separating and bringing this
waste to the dropping point or Temporary Collection Facility for further collection by certified
waste collector company.
104. Procedures for e-waste disposal activities from the source of household, commercial, and
government office:
• Separate the e-waste from other waste.
• Place the e-waste in “Dropbox” or other proper container
• Transport e-waste to the E-Waste Shelter: Dropping Point/Temporary Collection Facility31
Other options for removing e-waste:
• “Trade in”. Prior arrangement need to be made during procurement of the electronic
equipment;
• Collection by third party/ certified waste collector company
Diagram 2 below shows the procedures of the e-waste management.
Figure 5: E-Waste Management
31 The disposal of the used IT and other electronic equipment/e-wastes (which part of state assets) should follow removal
procedure of assets/goods belong to the state (Min of Finance Regulation no 96/PMK 06/2007) before transport to E-Waste
Shelter or Temporary Collection Facility or other eligible options for removing the e-wastes.
48
8. INDIGENOUS PEOPLES PLANNING FRAMEWORK (IPPF)
8.1 Objective
105. The main objective of this IPPF is to help ensure that any sub-project activity (including
physical investment) financed by the village performance grants is designed and implemented in a
way that fosters full respect for Indigenous Peoples (IPs)’ identity, dignity, human rights, livelihood
systems, and cultural uniqueness as defined by the IPs themselves to enable them (i) to receive
culturally appropriate social and economic benefits; (ii) not to suffer adverse impacts as a result of
the sub-project activity; and (iii) can participate actively in the activity. This IPPF safeguards the
rights of IPs to participate and equitably receive culturally appropriate benefits from the activities
financed by village performance grants.
8.2 Specific Objectives of this Framework
106. The specific objectives of this framework are to:
a. Ensure that IPs participate in and benefit from any activities in the Project;
b. Avoid or minimize potentially adverse effects on IPs, and if it is unavoidable, develop
and implement mitigation measures based on Free, Prior, and Informed Consultation
(FPIC – see Annex 17) resulting in broad supports from the impacted IPs communities;
c. Maximize the potential positive effects of the project on the IPs, based on FPIC with the
IPs ensuring that the design and implementation of the any activity incorporate
aspirations and needs of the IPs.
8.3 National Regulations and Institutional Arrangements Pertaining to IPs
49
107. The Government acknowledges the presence of Masyarakat Hukum Adat and their rights,
provided that these groups meet eligibility requirements and have obtained legal recognition from
their provincial or district governments (further elaborated in the Minister of Home Affairs’
Regulation No. 52/2014). Such legal recognition serves as a precondition for further recognition of
land rights and natural resources within customary territories. In May 2013 the Constitutional
Court ruled that Hutan Adat are not part of the State forest (hutan negara). This Court decision
modified Hutan Adat from falling under the category of state forest (hutan negara), to the category
of private forest (hutan hak) This decision further implied that Adat forests, wherever legally
recognized, would be assumed to be the collectively owned forests of Indigenous Peoples.
108. The Indonesian legal framework generally refers to Indigenous Peoples as Masyarakat
Hukum Adat (customary law communities).32 Identification criteria of such communities and
protection of their rights to land and natural resources can be found in various legislations. The
following Indonesia laws and regulations recognize the specific rights of IPs:
▪ Indonesian’s Constitution Article 18(B) recognizes the rights of Masyarakat Hukum
Adat;
▪ Basic Agrarian Law No. 5/1960: Apart from defining types of land rights of private
individuals and other entities, the law recognises land rights over customary territories (hak
ulayat) and customary law (adat law) as long as it is not in conflict with the national
interest;
▪ Law No. 39/1999 on Human Rights: Article 6 of the law states that the needs of
Masyarakat Hukum Adat need to be recognised and protected by the law, society, and the
government;
▪ Law No. 6/2014 on Villages: The law acknowledges the existence and rights of
Masyarakat Hukum Adat. The communities can establish adat villages with their own
institutional structures and authority although this law suffers from the lack of guiding
regulations and institutional mandates to make such provisions operational. The Law grants
a desa adat (customary village) the authority to conduct adat-based public administration.
Once recognized, Adat villages are legal entities entitled to village funds (dana desa) and
guaranteed unprecedented levels of autonomy to set up governance structures and manage
the commons. Law 6/2014 has reinforced the rights of IP and adat communities and an
additional route for claiming their rights.
▪ Law No. 23/2014 on Local Government: This Law recognizes the existence of adat
institutions (lembaga adat) by giving them rights to “empowerment”. Second, the Law
32 Relevant regulatory frameworks include Law No. 32/2009 on Environmental Protection and Management, Law
No.41/ 1999 (further revised to Law No 19/2004) on Forestry, Law no 18/2013 on Prevention and Abolition of
Forests Destructions, Presidential Instruction No 88/2017 on Land Tenure Settlements in Forest Areas, and
Ministerial Regulation of the Ministry of Home Affairs No 52/2014 on the Guidelines for the Recognition and
Protection of Adat Community and most recently the Presidential Regulation No 88/2017 on Land Tenure
Settlements in Forest Areas.
50
determines that adat law is an additional rule for purposes such as village elections. Third,
the Law makes adat or adat law the basis upon which to conduct local development, or as
a parameter to measure social cohesiveness;
▪ Law No. 11/2010 on Cultural Heritage: This law recognises Masyarakat Adat as owners
of their cultural heritage and grants them authority to manage it. The law requires
observation and data collection on cultural heritage sites that may be affected by project
activities; and
▪ Forestry Law No. 41/1999: Primarily, the law divides forests into different legal categories
and provides criteria for the recognition of Hutan Adat rights. The law has been amended
by Constitutional Court Decision No. 35/2012 which established that adat forests are not
state forest area but collectively owned private land. The clarification of Article 67 (2) of
Law 41/1999 lists five conditions, based on which the government will recognize a
customary community as Masyarakat Hukum Adat:
o In the people’s daily life, it still is a communal society (paguyuban);
o The community has adat institutions and adat leaders;
o The community has clear boundaries;
o The community has well–functioning customary law institutions, particularly
an adat judicial system; and
o The community still collects forest products for its subsistence.
109. Below the level of national laws, a number of ministerial regulations further define
Masyarakat Hukum Adat and point out the legal procedures for the legal recognition of Masyarakat
Hukum Adat and the recognition of Hutan Adat or other customary land rights. Communal land
rights in the non-forest estates is regulated under Ministerial Regulation of ATR/BPN.
110. Ministry of Home Affairs regulation (Permendagri) No. 52/2014 define Masyarakat Adat
as follows:
a. Customary law communities (Masyarakat Hukum Adat) are groups of Indonesian citizens
who have distinctive characteristics, live in groups harmoniously according to their
customary law, have ties to ancestral origins and or similarities in living, have strong
relationships with land and the environment, and dispose of a distinct value system and
economic, political, social, cultural, legal institutions33;
b. Customary Territory (Wilayah Adat) is customary land in the form of land, water, and / or
waters along with natural resources on top of it with certain boundaries, owned, and
preserved for presence and future generations and utilized in a sustainable manner in order
to meet the needs of the community as inheritance from their ancestors or ownership claims
in the form of ulayat land or customary forests; and
33 Alternatively, The Minister of Agrarian Affairs/National Land Agency (Ministerial Regulation No. 10/2016) defines these
communities as “groups of people bound by their customary law arrangements as members of a group allied by their place of
residence or hereditary base.”
51
c. Customary Law is a set of norms or rules, both written and unwritten, that live and apply
to regulate human behavior that are based on Indonesian cultural values, inherited from
generation to generation, which are always adhered to and respected for justice and public
order and has legal consequences or sanctions.
111. Following Constitutional Court Decision No. 35/2012, several ministerial regulations were
passed that provide further details on how the government can recognize Masyarakat Hukum Adat
and their land rights. The central government (MoEF or MoATR/BPN) can only adat land rights if
there already is a regional form of government recognition. There are two options for the
recognition of Hutan Adat:
a. A regional regulation (Peraturan Daerah or Perda) as stipulated in Article 67 (2) of
Forestry Law 41/1999; and
b. A district head/governor decree (Keputusan Kepala Daerah). Ministerial Regulation of the
Minister of Home Affairs No. 52/2014 concerning Guidelines on the Recognition and
Protection of Masyarakat Hukum Adat, grants district heads/mayors the authority to issue
a decree on recognition based on recommendations from special committees (Panitia
Masyarakat Hukum Adat kabupaten/kota) (Article 6 (2)). These are appointed by the
district head/mayor (Article 3 (1)). They consist of: the regional secretary, the regional
working unit head, the district head of legal affairs and the sub-district head. Article 4
stipulates that the committee has the task to verify the identification (identifikasi),
validation (validasi) and determination (determinasi) of the adat law community involved.
112. After regional recognition has been realized, the following step for Indigenous Peoples to
secure their Hutan Adat rights is recognition by the MoEF. The MoEF has issued a ministerial
regulation on this procedure with regard to the recognition of Hutan Adat rights. This procedure
only appertains to the Forest Estate and not to state land under the jurisdiction of the MoATR/BPN.
Ministerial Regulation 32/2015 concerning Private Forest Rights (hutan hak) regulates the
procedural steps to be taken. A ministerial decree (keputusan menteri) can designate Hutan Adat
and hence, change its from state forest into private forest.
113. Article 6 of the Ministerial Regulation provides the following conditions for the Minister
to recognize adat forests by ministerial decree:
a. An Adat law community or right to avail (hak ulayat) has been recognized by a regional
government through a regional legal decision (produk hukum daerah);
b. There is an Adat territory that is partly or wholly located inside a forest; and
c. There is a formal request from an Adat law community to designate the Adat forest
114. Besides Hutan Adat rights and the other Social Forestry schemes, there are two other legal
options available for communities to secure land rights in the Forest Estate:
a. Hak Komunal (communal rights). This right pertains both to Forest Estate areas and state
land (tanah negara) and was established in Ministerial Regulation No. 10/2016 concerning
Procedures to Determine Communal Rights of Masyarakat Hukum Adat and Communities
in a Specific Zone, by the Minister of ATR/BPN. The Ministerial Regulation provides the
possibility for both Masyarakat Hukum Adat and other communities to obtain communal
52
ownership rights in the Forest Estate or state land. It refers to these communities as
‘communities in a Specific Zone’ (masyarakat dalam Kawasan Tertentu). Special Zone
refers to a Forest Area or to a plantation concession. For communities to obtain hak
komunal, a request has to be filed with their district heads. These shall then form an
inventory team called Tim IP4T.34 After the Tim IP4T verifies the communal land right, the
land in question shall be released either from the state forest or from the plantation
concession. If the land is located inside a Forest Area, the Tim IP4T will hand over its
results to the MoEF, which should then release the land from the Forest Area (Article 11).
If the land is located inside a plantation concession, the holder of the concession rights shall
be requested to exclude the plot of land from its concession (Article 13 (1) b). After the
Tim IP4T has given its approval to the particular district head/governor, a district head
decree or governor decree shall be issued, which shall then be sent to either the Ministry of
ATR/BPN or MoEF (Article 18 (2)) who will be asked to exclude it from their jurisdiction.
b. Land ownership certificate (sertipikat atas tanah). Presidential Regulation No. 88/2017 on
Settling Land Tenure within Forest Estate Areas (PPTKH) put in place procedures to
address issues related to land status and resource conflict within the Forest Estate (kawasan
hutan). According to this regulation, individuals or communities can obtain land ownership
certificates if they have cultivated a parcel of land located in the Forest Estate for more than
20 years (article 20 e). After inspection and verification, this land parcel shall then be
released from the Forest Estate.
8.4 Objectives and Requirements of OP 4.1035
115. OP 4.10 contributes to the Bank’s mission of poverty reduction and sustainable
development by ensuring that the development process fully respects the dignity, human rights,
economies and cultures of Indigenous Peoples. For all projects that are proposed for Bank financing
and affect Indigenous Peoples, the Bank requires the borrower36 to engage in a process of free,
prior, and informed consultation (FPIC). The Bank provides project financing only where free,
prior, and informed consultation (FPIC) results in broad community support to the project by the
affected Indigenous Peoples. Such Bank-financed projects include measures to (a) avoid potentially
adverse effects on the Indigenous Peoples’ communities; or (b) when avoidance is not feasible,
minimize, mitigate, or compensate for such effects. Bank-financed projects are also designed to
ensure that the Indigenous Peoples receive social and economic benefits that are culturally
appropriate and gender and intergenerationally inclusive.
8.5 Application of OP 4.10 in Project Component 1, 2, and Component 4
116. The Project will follow the principles and requirements of the Indonesian laws and
34 IP4T stands for Inventarisasi Penguasaan, Pemilikan, Penggunaan dan Pemanfaatan Tanah (Inventory of control,
ownership, use and benefit of land). 35 Taken from the World Bank OP 4.10 on Indigenous Peoples. 36 In this Project, the MoHA (as Executing Agency and CPIU) and the MOV (as CPIU) will be responsible to ensure that
principles and provisions for Indigenous Peoples are mainstreamed in the Component 1, 2, 4 and IPPF is consistently followed
for Component 3.
53
regulations and OP 4.10 on Indigenous Peoples to ensure that IPs community will have the
opportunity to participate in the planning and implementation process and have culturally
appropriate benefit from the Project with principles that fully respects their dignity, human rights,
economies and cultures. As already specified in the Section 5 on the indicative key strengthening
areas, provisions to enhance the inclusion of benefits to IP and the delivery of culturally appropriate
benefits will be included in the in the new and existing manuals, guidelines, training modules,
awareness training, integrated data-base management, and training delivery system, terms of
references for TA, consultants and/or facilitators and monitoring and supervisory team/unit.
117. In addition, the Project intends to:
a. engage in a more pro-active approach to IP inclusion and development benefits, such as
pro-active targeting of IP communities during the preparation of the RPJMDes, RKPDes,
APBDes and Work Plan/Activity Plan as well as sub-project design;
b. as needed provide additional support (TA/facilitators/consultants) in areas with IPs;
c. as much as possible provide a broader menu of eligible investments for IPs tailored to their
needs; and/or
d. include key provisions of IPs as part of the Project monitoring indicators and evaluation,
perhaps also include IPs to actively monitor the implementation of sub-projects.
8.6 Criteria of Indigenous Peoples
118. There is no universally accepted definition of IPs. In different countries IPs may refer to
by such terms as “indigenous ethnic minorities,” “aboriginals,” “hill tribes,” “minority
nationalities,” “scheduled tribes,” or “tribal groups.” In this IPPF, the term “Indigenous Peoples”
is used in a generic sense to refer to a distinct social and cultural group possessing the following
characteristics in varying degrees:
a. Self-identification as members of a distinct indigenous cultural group and recognition of
this identity by others;
b. Collective attachment to geographically distinct habitats or ancestral territories in the
physical investment area and to the natural resources in these habitats and territories;
c. Customary cultural, economic, social, or political institutions that are separate from those
of the dominant society and culture;
d. An indigenous language, often different from the official language of the country or region.
119. The term “Indigenous Peoples” is often associated with “Masyarakat Hukum Adat” (or
MHA—Customary Law Communities), or “Masyarakat Adat” (or Customary Communities), or
“Masyarakat Tradisional” (or Traditional Communities) which is common terminology used in
Indonesian laws and regulations to describe groups of people with similar characteristics as those
IPs specified above. Ascertaining whether a particular group is considered as Indigenous Peoples,
one should use the above criteria, and for the purpose of this IPPF, may require professional
judgement. This document will use the term “Masyarakat Adat” for IPs with the above 4 (four)
criteria.
8.7 Screening of IPs
54
120. As the Project will ultimately cover all villages in the country, IPs presence in some of the
villages is anticipated. The Project expects that IPs would be part of the village community who
will benefit from the Project. Initial screening of the potential IPs presence will be done using the
World Bank IPs Screening Study 201037. Further screening/verification will be done at the village
level:
a. based on the above four criteria of IPs;
b. confirmation from the village apparatus and TPK on the presence of IPs;
c. confirmation from the village apparatus and TPK whether the IPs are part of the
beneficiaries or only affected (positively and negatively) by the activity;
d. a-c above will have to be verified by the PTPD, PD and the PLD during the review of the
draft RKPDes and APBDes.
8.8 Assessment of IPs as beneficiaries or affected by an activity
121. Once the IPs presence in a village is confirmed, the village government has to carry out the
following:
a. village apparatus and TPK will assess whether the IPs will be part of the beneficiaries of
the activity or will be the sole beneficiaries of the activity, or will only be affected
(positively or negatively) by an activity;
b. a free, prior, informed consultation (FPIC, see Annex 17) with the affected IPs and seek
and agree on the potential impacts and/or benefits for the IPs, and their aspirations and
needs for addressing the adverse impacts or to maximize the benefits.
c. documentation of the consultations process, agreements and aspiration and needs of the
consulted IPs community with a format of Social Assessment (SA). An example of the SA
format is presented in Annex 14, and a sample format for documentation of the consultation
process are provided in Annex 16.
8.9 Indigenous Peoples Plan (IPP) and Sub-Project Design
122. In the case that a sub-project affects the IPs, the village government or TPK will prepare
an Indigenous Peoples Plan (IPP) based on the results of the Social Assessment. Example of the
IPP format is presented in Annex 15. The TPK will have to carry out FPIC for the preparation of
the IPP, to agree on the types, intensity, timing, target groups, and resources of the measures that
will address the adverse impacts and/or that will accommodate the aspirations and needs of the
affected IPs. The PLD will facilitate the consultations. The draft IPP should be agreed by both the
affected IPs community and by the village government or TPK, should be reviewed by the PTPD,
PD and PLD and approved by the PIUs and World Bank.
123. In the case that IPs community is part or the sole beneficiaries of the sub-project, the village
government or TPK will include the aspirations and needs of the IPs beneficiaries in the sub-project
design. The sub-project design should be consulted (FPIC) with the IPs beneficiaries. The village
government or TPK, with the facilitation of the PD-TI or consultant who assist the village
government in designing the sub-project should carry out such consultation.
37 Refer to Annex 20 for the potential IPs presence, based on the World Bank IPs Screening Study (2010)
55
124. IPP and sub-project design should be disclosed at the community level prior to the start of
construction (see also Section 9 on public consultations and disclosures).
125. As mentioned in Sections 3, 5 and 6, elements described in Section 8.7, 8.8 and 8.9 above
will inform the mainstreaming of the Component 1, 2, and 4.
9. PUBLIC CONSULTATIONS AND DISCLOSURES
Public consultations and disclosures of the ESMF
126. The Project (PIU of MoHA and PIU of MoV) carried out public consultations during
January 14-15, 2019 on the Draft ESMF to obtain constructive inputs from the relevant
stakeholders to strengthen the design of the mainstreaming environmental and social sustainability
in the Project. Draft ESMF (in English and Bahasa) was disclosed in
http://binapemdes.id/informasi prior to the public consultation.
127. Public consultation was attended by representatives of DPMD from 33 provinces and 39
districts, as well as five NGOs. One of the important feedbacks received was that on the
practicability of the implementation of the mainstreamed objectives, key principles and
requirements of the environmental and social sustainability in various manuals, guidelines and
training modules, and the implementation of the safeguards instruments at the village level, given
the nature of the subprojects that are relatively small investments. Details of discussions during
public consultations and list of participants are presented in Annex 20. The draft final ESMF will
be uploaded in the MoHA and MoV’s websites (English and Bahasa) and the Bank’s Infoshop
(English) prior to appraisal.
Public consultations and disclosures of the implementation of Component 1, 2 and 3
128. PIUs of MoHA and MoV will consult relevant stakeholders including provincial
governments, district governments, sub-districts and village governments as well as facilitators and
representatives of IPs during the preparation of the improved manuals, guidelines and training
modules so that these documents will reflect the real situation and needs, also test their applicability
on the ground. At the village level, as required by various manuals and guidelines issued by the
MoHA and MoV, all plans (RPJMDes, RKPDes, APBDes, Work Plan of Activity and sub-project
design) will have to be prepared and implemented in consultations with the villagers and these
documents will have to be disclosed through various venues, such as community boards, local
media, website (as available), etc.
129. Manuals, guidelines and training modules will be disclosed in the MoHA and MoV’s
websites and through the digitalized system so that they will be accessible for public including
relevant stakeholders involved in the Village Law implementation. The learning management
system will include e-learning system whereby improved learning modules will be easily accessed
by the villagers and facilitators.
56
130. The preparation of the environmental and safeguards instruments for Component 3, such
as the UKL-UPL, SPPL, ECOPs (as relevant)38, as well as identification of IPs, and IPP will be
done during the preparation of the sub-project design of the activities financed by the performance
grants. The TPK will consult the villagers especially the affected persons during the preparation
and implementation of the UKL-UPL, SPPL, ECOPs, IPP. These instruments will be disclosed in
the village offices or other venues accessible to the villagers and affected persons along with the
sub-project design.
10. GRIEVANCE REDRESS MECHANISMS (GRM)
131. These days, an individual or group or community can file complaints or request for
information or submit an inquiry about the implementation of Village Law through various venues,
that is open to public, fast and relatively without cost. At the central level, the Project provides at
least three channels for public to file complaints and receive responses. These are managed by the
MoHA, MoV and the Ministry of State Apparatus Empowerment (KemenPAN). While at the
village level, villagers are provided complaint handling system managed by the village apparatus
as required by the regulations and/or during the public consultations for the preparation of the
RPJMDes, RKPDes and APBDes. PIU of MoHA and PIU of MoV will work together with the staff
in charge of complaint handling system in each of the Ministry and monitor the status and as needed
will provide the necessary follow-up. The MIS of the Project will also record complaints
documented at the village level. Detail explanation is presented below:
132. MoHA (Executing Agency and CPIU of the Project) operates a GRM through application
for complaints and aspirations called “SAPA”. Public can access the system through
http://www.sapa.kemendagri.go.id. This application is integrated with the GRM system in each of
the district’s website (www.name of district.go.id), which allow one-stop service for complaint
handling. SAPA application is also available in mobile phone (at the moment, it is only available
from play store for Android). Public complaints and aspirations will be forwarded to relevant
agencies including districts. The person in charge of managing the GRM will monitor the follow-
up process of the incoming complaints, and the complainants also can monitor the progress of the
follow-up through the system. The system seems to be using real time and provides information on
the types of complaints (i.e. those related to regulation, permit, area boundary and land,
bribery/corruption, misused of authority, violation, village government, regional development, and
others). Information on the status of complaints (received, being followed-up, and completed) and
on the satisfaction levels (satisfy, not satisfy) of the complainants is available.
133. The MOV (CPIU of this Project) has a GRM system with various venues to receive
complaints, questions and aspirations. One system, called “Village Complaints”, uses call center
38 For various types of village infrastructure, see practical Manual of “The DOs and DON’Ts: Environmental Management:
General Considerations-Site Screening-Construction Site Management, Roads, Water Supply, Sanitation, Solid Waste
Management, Markets, Rivers” prepared by the PNPM-Rural Project. This Guidance Book, English version can be accessed
through http://documents.worldbank.org/curated/en/925701495170561883/The-dos-and-the-donts-environmental-
management-general-considerations-site-screening-construction-site-management-roads-water-supply-sanitation-solid-
waste-management-markets-and-rivers. This Guidance Book, Bahasa Indonesia version can be accessed through
http://documents.worldbank.org/curated/en/188631468042887318/Baik-and-buruk-pengelolaan-lingkungan.
57
(1500040) and short message numbers (081288990040 and 0877 8899 0040), twitter and face book.
Complainants can also come in person to the PPID in the Ministry Office. Another channel for
filing complaints is an application called “LAPOR”, initiated by the President Office and now
managed by the Ministry of State Apparatus Empowerment (KemenPAN). In addition, the MOV
has just launched application for complaint handling accessible in its website. Shor-text Messages
(SMS) is the most popular venue for complaints. The GRM is managed by the Office for
Information and Complain Service (IPP) that records complaints, forwarded complaints to relevant
directorate general offices, and monitor and records the follow-up. In 2017, about 78.5% of the
complaints/inquiries/aspirations received related to the issues under the domain of Directorate
General for Village Development and Empowerment (DG PPMD). Popular issues were about
village funds.
134. At the village level, Permendagri No. 114/2014 stipulated that the village should have a
complaint handling management system. The head of the village is responsible for managing and
processing, as well as in following-up the complaints, and in documenting the complaints as well.
Villagers may also file complaints during the public consultations for preparing village plans,
namely, RPJMDes, RKPDes, and APBDes. This complaint handling management system will
benefit the planning process that includes the ESS aspects.
Bank Grievance Redress System (GRS)
135. Communities and individuals who believe that they are adversely affected by a World Bank
(WB) supported project may submit complaints to existing project-level grievance redress
mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints
received are promptly reviewed in order to address project-related concerns. Project affected
communities and individuals may submit their complaint to the WB’s independent Inspection Panel
which determines whether harm occurred, or could occur, as a result of WB non-compliance with
its policies and procedures. Complaints may be submitted at any time after concerns have been
brought directly to the World Bank's attention, and Bank Management has been given an
opportunity to respond. Grievance received for activities that are not financed by the performance
grants financed by the Project under Component 3 are not eligible under the Bank’s GRS.
Verification on the complaints submitted to the Bank’s GRS will be done prior to the follow-up.
For information on how to submit complaints to the World Bank’s corporate Grievance Redress
Service (GRS), please visit http://www.worldbank.org/en/projects-operations/products-and-
services/grievance-redress-service. For information on how to submit complaints to the World
Bank Inspection Panel, please visit www.inspectionpanel.org.
11. INSTITUTIONAL ARRANGEMENTS FOR IMPLEMENTING THE
ENVIRONMENTAL AND SOCIAL SUSTAINABILITY ASPECTS
136. As explained in the Section 1.4 above, the structure of responsibilities of ESS capacity
building and institutional system strengthening and improvement will follow the current
responsibility structure between the MoHA, MoV, the provincial and district governments of the
58
relevant tasks in the implementation of the Village Law (see also Section 5 and 6; and Annex 1).
A summary of the proposed arrangements are as follows39:
Table 4: Responsible Agencies for Mainstreaming and Strengthening the ESS Aspects
Manuals/Guidelines/ Training
Modules
Elements of
strengthening areas40
PIU MoHA
(and assisted
by the
national
consultant)
PIU MoV
(and assisted
by the
national
consultant) - Village Development Guidelines Improvement of the
existing environmental and
social sustainability
aspects
X
- Village Financial Management Add environmental and
social sustainability
aspects
X
- Guidelines for Decision Making
Procedures and Mechanisms in Village
Consultations
Add environmental and
social sustainability
aspects
X
➢ Village Mentoring Add environmental and
social sustainability tasks,
particularly the PLD
X
➢ Priority for the Utilization of Dana Desa
2019
Add environmental and
social sustainability
aspects
X
➢ Or, develop new Technical Guidelines
on Environmental and Social
Sustainability for the Implementation of
Village Law
As relevant, leverage
lessons learned and the
PNPM-Rural Technical
Operational Guidelines
X X
Training Modules
➢ Pre-assignment training modules for
village facilitator for infrastructure (PD-
TI)
Improvement of the
existing environmental
and social sustainability
aspects
X
➢ Pre-assignment training modules for
village facilitator for empowerment (PD-
P)
Add environmental and
social sustainability
aspects
X
➢ Pre-assignment training modules for
local village facilitator (PLD)
Add environmental and
social sustainability
aspects
➢ Training modules for village apparatus
and village community group (LKM,
KPMD, etc.) in preparing the RPJMDes,
RKPDes and APBDes
Add environmental and
social sustainability
aspects
X,
Provincial
and/or District
DPMD,
Provincial
Balai
X,
Provincial
DPMD and/or
District
DPMD,
Provincial
Balai
Awareness Training
- Awareness training modules for the
preparation and implementation of
RPJMDes, RKPDes for the TAPMD (esp.
TA-ID), PTPD, officials of DPMD, and
District Inspectorate (new), provincial
Develop new modules -
substance of
environmental and social
sustainability are
mainstreamed
X X,
Provincial
DPMD
39 Refer to Table 3 on the detail elements of strengthening areas in Section 6. 40 Improvement or additional of the elements of the environmental and social sustainability aspects vary among
these guidelines/training modules depending on the users/target groups.
59
Manuals/Guidelines/ Training
Modules
Elements of
strengthening areas40
PIU MoHA
(and assisted
by the
national
consultant)
PIU MoV
(and assisted
by the
national
consultant) satker
Integrated Data-based Management/
InfoDesa
Develop attributes related
to information on the
environmental and social
sustainability aspects
X and MOF X and MOF
Terms of References
137. TAPMD (esp. TA-ID)
138. PD-TI
139. PD-P
140. PLD
Add tasks for providing
oversight and/or
mentoring in ensuring
environmental and social
sustainability aspects are
considered in the
RPJMDes, RKPDes,
APBDes, Activity Design
X
X
X
X
Performance Criteria Include ESS aspect as
relevant
X X
Socialization of the Performance Criteria to
the villages, sub-districts, and districts
X X
Socialization and training for the BPKP
on the performance criteria
X X
Integrated data-based management Include attributes related
to ESS aspects, such as
information on IPs, natural
resource development, etc.
X X
137. At the village level, the proposed institutional arrangements for the sub-project financed by
the performance grants are summarized as follows:
a. Sub-project screening and potential impacts identification will be done by the TPK
b. TPK will have to ensure that documentation of the screening and instruments (such as
SPPL, VLD, IPP as relevant, etc.) are prepared in consultations with the affected persons.
Consultations, agreements and disagreements should be documented and well-kept.
c. PD-TI will assist the TPK in ensuring that the sub-project design accommodates the
recommendations of the safeguards instruments, ECOPs41, SPPL, aspirations and needs of
the IPs community, etc.
d. The safeguards instruments should be verified by the PLD and PD-TI. PTPD will review
the screening and instruments prepared and provide inputs and approval for instrument that
does not need approval from the relevant local agencies. The head of the village will have
41 For various types of village infrastructure, see practical Manual of “The DOs and DON’Ts: Environmental Management:
General Considerations-Site Screening-Construction Site Management, Roads, Water Supply, Sanitation, Solid Waste
Management, Markets, Rivers” prepared by the PNPM-Rural Project. This Guidance Book, English version can be accessed
through http://documents.worldbank.org/curated/en/925701495170561883/The-dos-and-the-donts-environmental-
management-general-considerations-site-screening-construction-site-management-roads-water-supply-sanitation-solid-
waste-management-markets-and-rivers. This Guidance Book, Bahasa Indonesia version can be accessed through
http://documents.worldbank.org/curated/en/188631468042887318/Baik-and-buruk-pengelolaan-lingkungan
60
to agree on the screening and mitigation measures as specified in the safeguards
instruments (SPPL, IPP, ECOPs42 etc.)
e. Approved safeguards instruments should be part of the sub-project proposal or plan.
f. The instruments have to be disclosed by the TPK in the venue and in a way that villagers
can easily access the information.
g. Budget for the mitigation measures should be part of the overall sub-project costs.
h. PD-TI will supervise the implementation of the activities or physical investments, and
PTPD will have to monitor and provide advice to the TPK or community groups who are
implementing the activities or physical investment
i. The local environmental agency and the relevant local agency (such as public works for
sub-project on road for instance) will have to review the safeguards instruments
(particularly the SPPL) and mitigation measures whether technically sound and appropriate
in accordance with the type and intensity of impacts.
12. CAPACITY BUILDING PLAN
138. The mainstreaming and strengthening of the ESS aspects in the Implementation of the
Village Law will be carried out gradually and continuously along with the digitalization or
development of the e-system of the capacity building and training deliveries, market place,
harmonization of regulations and integrated data base management. The proposed capacity
building plan is presented in the Table 5.
139. The national consultant team will assist the PIU MoHA and PIU MoV to strengthen the
manuals, guidelines, training materials and providing ToTs to the provincial PIUs (or Pokjas) and
provincial consultant teams (refer also to Section 5 and 6 for the elements of mainstreaming, and
Annex 1 on the Project Implementation Structure and Arrangements). Subsequently, the provincial
PIUs and consultant teams will provide TOTs to the district DPMDs and consultant teams, as well
as the TAPMDs. The DPMDs of the districts with the assistance of the consultant teams will then
train the village apparatus, PDs and PLDs. The timing of the training at various levels can be
parallel depending on the readiness of each level.
140. The costs for the capacity building related to mainstreaming and strengthening of the ESS
aspects will be borne by the APBN Rupiah Murni as part of the MoHA and MoV budgets for
capacity building, monitoring and supervising the implementation of the Village Law. As needed,
additional budget needs could be financed by the Project.
Table 5:
Proposed Capacity Building Plan for Mainstreaming and Strengthening the ESS Aspects
42 For various types of village infrastructure, see practical Manual of “The DOs and DON’Ts: Environmental Management:
General Considerations-Site Screening-Construction Site Management, Roads, Water Supply, Sanitation, Solid Waste
Management, Markets, Rivers” prepared by the PNPM-Rural Project. This Guidance Book, English version can be accessed
through http://documents.worldbank.org/curated/en/925701495170561883/The-dos-and-the-donts-environmental-
management-general-considerations-site-screening-construction-site-management-roads-water-supply-sanitation-solid-
waste-management-markets-and-rivers. This Guidance Book, Bahasa Indonesia version can be accessed through
http://documents.worldbank.org/curated/en/188631468042887318/Baik-and-buruk-pengelolaan-lingkungan
61
Manuals/Guidelines/ Training
Modules
Elements43 of
strengthening areas44
Target Year
- Village Development Guidelines Improvement of the
existing environmental and
social sustainability
aspects
PIU of MoHA 1 - 2
- Village Financial Management Add environmental and
social sustainability
aspects
PIU of MoHA 1-2
- Guidelines for Decision Making
Procedures and Mechanisms in Village
Consultations
Add environmental and
social sustainability
aspects
PIU of MoV 1-2
➢ Village Mentoring Add environmental and
social sustainability tasks,
particularly the PLD
PIU of MoV 1-2
➢ Priority for the Utilization of Dana Desa
2019
Add environmental and
social sustainability
aspects
PIU of MoV 1-2 (also for
utilization for
Dana Desa
2020)
➢ Or, develop new Technical Guidelines
on Environmental and Social
Sustainability for the Implementation of
Village Law
As relevant, leverage
lessons learned and the
PNPM-Rural Technical
Operational Guidelines
PIU of MoHA
and PIU of
MoV
1
Training Modules
➢ Pre-assignment training modules for
village facilitator for infrastructure (PD-
TI)
Improvement of the
existing environmental
and social sustainability
aspects
PD-TI Training, year-
1 onwards
➢ Pre-assignment training modules for
village facilitator for empowerment (PD-
P)
Add environmental and
social sustainability
aspects
PD-P Training, year-
1 onwards
➢ Pre-assignment training modules for
local village facilitator (PLD)
Add environmental and
social sustainability
aspects
PLD Training, year-
1 onwards
➢ Training modules for village apparatus
and village community group (LKM,
KPMD, etc.) in preparing the RPJMDes,
RKPDes and APBDes
Add environmental and
social sustainability
aspects
MoHA, MoV
Provincial
and/or District
DPMD,
Provincial
Balai of MoHA
and MoV)
1-2;
Training, year-
1 onwards
Awareness Training
- Awareness training modules for the
TAPMD (esp. TA-ID), PTPD, officials of
DPMD, and District Inspectorate (new),
provincial satker as well as for the Tim
Pelaksana Kegiatan (Activity Implementor
Team) at the village level on the
environmental and social sustainability
aspects in the preparation and
implementation of the RPJMDes,
RPKPDes, APBDes, and activity design
Develop new modules -
substance of
environmental and social
sustainability are
mainstreamed
Provincial
DPMD, PTPD,
officials of
DPMD, and
District
Inspectorate
(new),
provincial
satker
1-2;
Training,
year-1 onwards
Integrated Data-based Management/
InfoDesa
Develop attributes related
to information on the
X and MoF 1-2
43 Refer to Table 3 in Section 6 on the details of elements of strengthening areas. 44 Improvement or additional of the elements of the environmental and social sustainability aspects vary among
these guidelines/training modules depending on the users/target groups.
62
Manuals/Guidelines/ Training
Modules
Elements43 of
strengthening areas44
Target Year
environmental and social
sustainability aspects
Terms of References
141. TAPMD (esp. TA-ID)
142. PD-TI
143. PD-P
144. PLD
Add tasks for providing
oversight and/or
mentoring in ensuring
environmental and social
sustainability aspects are
considered in the
RPJMDes, RKPDes,
APBDes, Activity Design
PIU of MoV 1
Performance Criteria Include ESS aspect as
relevant
PIU of MoHA
and PIU of
MoV
1-2
Socialization of the Performance Criteria to
the villages, sub-districts, and districts
PIU of MoHA
and PIU of
MoV
2
Socialization and training for the BPKP
on the performance criteria
BPKP 2
Integrated data-based management Include attributes related
to ESS aspects, such as
information on IPs, natural
resource development, etc.
PIU of MoHA
PIU of MoV
1-3
13. MONITORING AND EVALUATION
141. Monitoring and evaluation of the implementation of the ESMF will be part of the overall
monitoring and evaluation of the Project. Indicators of mainstreamed ESS provisions will be part
of the Results Framework and Monitoring of the Project (for details refer to Project Appraisal
Document Chapter VI), particularly the Intermediate Results Indicators (monitored annually),
among others as follows:
a. E-learning platform for needs-based capacity building for village apparatus and institutions
established and fully operational
b. Villages where women representatives trained on village development-related core
modules (participatory planning, budgeting, monitoring)
c. Village allocate budget for needs-based village aparatus and BPD capacity building plan.
142. Monitoring for the implementation of activities supported by the performance grants will
be done by the district PIU and the PTPD. As needed the district environmental agency (DEA) and
PTPD will guide the village apparatus particularly the Tim Pelaksana Kegiatan in preparing and
implementing the safeguards instruments. Monitoring of the implementation of the safeguards
instruments will be done periodically along with the completion of each disbursement stage of the
performance grants.
143. Results of evaluation will be used to adjust the ESS mainstreaming in the capacity building
and institutional system strengthening system.
14. BUDGET TO IMPLEMENT THE ESMF
63
144. It is obvious that the implementation of the ESMF elements will be integrated into the
overall Project implementation (refer to Section 5 and 6 on the elements of mainstreaming, and
Annex 1 on Project Implementation Structure and Arrangements). Budget to implement the ESMF
will be part of the costs of the activities under each component as ESS will be mainstreamed in
such activities. The Project will have to ensure that the activities related to the implementation of
ESMF below are properly included in the budget for implementing the activities under each
component:
Component 1 (MoHA):
a. Consultants to strengthen the manuals on Village Development and guidelines on Village
Financial Management
b. Workshops during the development of manuals and guidelines
c. Socialization of the improved manuals and guidelines to provinces, districts, sub-districts and
villages
d. Consultants for the website designer who include the updated manuals and guidelines especially
the ESS elements
e. Consultants to develop training modules for village apparatus in preparing the RPJMDes,
RKPDes and APBDes
f. Resource persons and logistics to implement the training modules for village apparatus in
preparing the RPJMDes, RKPDes and APBDes (provincial and/or district DPMD and provincial
Balai may contribute to the costs)
g. Implementation of awareness training modules for the TAPMD (esp. TA-ID), PTPD, officials
of DPMD, and District Inspectorate (new), provincial satker as well as for the Tim Pelaksana
Kegiatan (Activity Implementor Team) at the village level
h. Consultants to develop integrated data base management
i. Monitoring and supervision of CPIU, DPIU and District PIU
j. Consultants, pre-test and implementation of the development of digitalized tools, learning
management system, and e-learning etc., particularly the inclusion of the ESMF elements
Component 2 (MoV):
a. Consultants to improve the Guidelines for Decision Making Procedures and Mechanisms in
Village Consultations
b. Workshops in preparing the Guidelines for Decision Making Procedures and Mechanisms in
Village Consultations
c. Socialization of the Guidelines for Decision Making Procedures and Mechanisms in Village
Consultations to villages
d. Consultants to improve the Guidelines for Village Mentoring
e. Workshops in preparing the Guidelines for Village Mentoring
f. Socialization and training of the Guidelines for Village Mentoring for the facilitators
g. Consultants to improve the Guidelines for Priority for the Utilization of Dana Desa
h. Workshops in preparing the Guidelines for Priority for the Utilization of Dana Desa
i. Socialization of the Guidelines for Priority for the Utilization of Dana Desa
j. Consultants for improving the pre-assignment training modules for village facilitator for
infrastructure (PD-TI)
64
k. Consultants for improving the pre-assignment training modules for village facilitator for
empowerment (PD-P)
l. Consultants for improving the pre-assignment training modules for local village facilitator (PLD)
m. Resource persons and logistics to deliver the training modules for village community group
(LKM, KPMD, etc.) in preparing the RPJMDes, RKPDes and APBDes (provincial and/or
district DPMD and provincial Balai may contribute to the costs)
n. Resource persons and logistics to deliver the training modules for the PD-TI, PD-P and PLD
o. Implementation of awareness training modules for the TAPMD (esp. TA-ID), PTPD, officials
of DPMD, and District Inspectorate (new), provincial satker as well as for the Tim Pelaksana
Kegiatan (Activity Implementor Team) at the village level
p. Consultants to develop Terms of References for TAPMD, PD-TI, PD-P and PLD
q. Consultants to develop integrated data base management
r. Monitoring and supervision of CPIU, Provincial PIU and District PIU
s. Consultants, pre-test and implementation of the development of digitalized tools and market
place, learning management system, e-learning etc., particularly the inclusion of the ESMF
elements.
Component 3 (MoHA):
a. Consultants to develop the performance criteria whereby negative list is part of
b. Socialization of the performance criteria
c. Resource persons and logistics for delivering training for BPKP on the performance criteria
d. Consultants and BPKP to implement the performance criteria during the village selection
e. Consultants, PIU of MoHA, and/or District PIUs to monitor the implementation of the negative
list
Component 3 (Villages):
a. Prepare and implement environmental and social instruments
b. Prepare sub-project design
c. Specific training as needed
Component 4 (BAPPENAS and/or MoF):
a. Consultants for developing the InfoDesa related to ESMF elements
b. Coordination, monitoring and supervision for the implementation of ESMF
145. The Project estimates that for implementing the ESMF elements roughly it would cost US$
1 million. This initial rough estimation will be contributed by the Project funds and Rupiah Murni,
namely, APBN, provincial and district governments and village budget. Below is the summary of
activities and responsible parties for providing the needed budget that should be included in the
overall Project financing.
Table 6:
Cost Components and Responsible Agencies to Provide Budget for the Implementation of the
Mainstreaming and Safeguards in Component 3 as Specified in this ESMF
Manuals/Guidelines/ Training Modules PIU MoHA
(Budget Component 1)
PIU MoV
(Budget Component 2)
- Village Development Guidelines X
65
Manuals/Guidelines/ Training Modules PIU MoHA
(Budget Component 1)
PIU MoV
(Budget Component 2) - Village Financial Management X
- Guidelines for Decision Making Procedures
and Mechanisms in Village Consultations
X
➢ Village Mentoring X
➢ Priority for the Utilization of Dana Desa
2019
X
➢ Or, develop new Technical Guidelines on
Environmental and Social Sustainability for
the Implementation of Village Law
X X
Training Modules
➢ Pre-assignment training modules for village
facilitator for infrastructure (PD-TI)
X
➢ Pre-assignment training modules for village
facilitator for empowerment (PD-P)
X
➢ Pre-assignment training modules for local
village facilitator (PLD)
X
➢ Training modules for village apparatus and
village community group (LKM, KPMD,
etc.) in preparing the RPJMDes, RKPDes
and APBDes
X,
Provincial and/or District
DPMD,
Provincial Balai
X,
Provincial DPMD and/or District
DPMD,
Provincial Balai
Awareness Training
- Awareness training modules for the TAPMD
(esp. TA-ID), PTPD, officials of DPMD, and
District Inspectorate (new), provincial satker
as well as for the Tim Pelaksana Kegiatan
(Activity Implementor Team) at the village
level on the ESS aspects in the preparation and
implementation of the RPJMDes, RPKPDes,
APBDes, and activity design
X X,
Provincial DPMD
Integrated Data-based Management/
InfoDesa
X and MOF X and MOF
Terms of References
145. TAPMD (esp. TA-ID)
146. PD-TI
147. PD-P
148. PLD
X
X
X
X
Performance Criteria X X
Socialization of the Performance Criteria to the
villages, sub-districts, and districts
X X
Socialization and training for the BPKP
on the performance criteria
X X
Integrated data-based management X X
Village level
Specific training needs APBDes
Prepare and implement environmental and
social instruments
APBDes
Prepare sub-project design APBDes
66
ANNEX 1: PROJECT IMPLEMENTATION STRUCTURE AND ARRANGEMENT
Overview
1. Key objective. A key objective of the project is to strengthen and support the Government’s
own implementation structure for Village Law funding, in order to put in place a sustainable and long-
term system for improved village development. As such, the project looks first to the systems, processes
and institutions in place to support villages, and aims to strengthen and transform these to be more cost
effective, efficient and adaptive to the varied needs of villages. The project will develop new systems
for the delivery of capacity building support to village governments, as well as for learning and capacity
building for communities, and expanding service delivery options through marketplace models.
Project Coordination and Collaboration
2. National Coordination Platform. The project will support formalizing the existing
coordination mechanism currently functioning under Kemenko PMK, that brings together relevant
agencies involved in implementing programs at the village level. The National Coordination Platform
(NCP) will bring together Bappenas, MoHA, MoV, MoF, the National Statistical Bureau (BPS), and
BPKP, and would be chaired by Kemenko PMK. A Secretariat would be established under Bappenas
to support the NCP, preparing reviews or documents as needed. The NCP will be responsible for Project
coordination at the central level and will: discuss and resolve issues that require inter-ministerial
decisions, support policy developments, and monitor achievement of national targets for village
development. In addition, the NCP will have a role in ensuring that the project reaches the PDO, that
incentive mechanisms are developed, and that there is consistency among the policies adopted by
central PIUs. The NCP will act as the Steering Committee for the project.
3. Project Coordination at Provincial and Municipality/District Levels. At the sub-national
level, working groups (Kelompok Kerja/Pokja), or an existing committee with similar functions will be
identified that would serve to strengthen coordination and oversight at each level. These would draw
on strengthening existing mechansims, where relevant, and would support coordination of local policies
relevant to village development and capacity building, and foster collaboration among institutions and
sectors.
Project Implementation Structure
4. Executing Agency and Implementing Unit. The Executing Agency of the Project will be
positioned at the Directorate General of Village Government (Direktorat Jendral Bina Pemerintahan
Desa) within MoHA. Two Central Project Implementation Units (CPIUs) will be established and led
by an Echelon 2 under MoHA’s Directorate General of Village Government (Direktorat Jendral Bina
Pemerintahan Desa) and MoV’s Directorate General of Village Development and Empowerment
(Direktorat Jendral Pembangunan dan Pemberdayaan Masyarakat Desa). Central PIUs will be
supported by technical, financial and administrative staff in each implementing agency, ensuring sound
financial, procurement, contract management, safeguards and overall project implementation conform
with the World Bank policies. Central PIUs will also be responsible for ensuring achievement of the
PDO and KPIs, improving relevant policies and regulation, and ensuring that expenditures are
consistent with the intended activities and outputs. The CPIU within MoHA will manage Components
1 and 3, and the CPIU within MoV will manage Component 2. In each central PIU, a secretariat will
be established with participation of directorates within the respective DGs.
67
5. Secretariat for Program Coordination and Collaboration. Under the National Coordination
Platform, a Secretariat will be established under BAPPENAS, to ensure that coherent policies are
adopted by central PIUs, establish collaborative technical support and a joint monitoring mechanism,
monitor achievement of target KPIs and implementation of the work plan, and recommend performance
grants for village governments. The Secretariat will support the functioning of the National
Coordination Platform, which, in turn, will ensure participation of various central ministries involved
in village development and capacity building activities.
Table 1: Roles and Responsibilities of Each Ministry and Central Institution
Institutions Roles and Responsibility
BAPPENAS Overall program coordination and collaboration, and responsible for
implementing Component 4: National Coordination, Monitoring and
Supervision
Kemenko PMK Coordination of policies and regulations, and together with BAPPENAS,
support to the implementation of Component 4: National Coordination,
Monitoring and Supervision
MoF Support to the budget release for village governments, disbursement of loans,
and rupiah murni funds, as well as support to the timely release of incentive
grants to village governments
MoHA Implementation of Components 1: Strengthening Village Government
Institutions and 3: Strengthening Village Government Performance, as well
as administrative coordination to consolidate and prepare annual project
financial reports and quarterly IFRs.
MoV Implementation of Component 2: Promoting Participatory Village
Development, and support to the implementation of Component 3:
Strengthening Village Government Performance
BPKP Support outputs verification of performance-based grants under Component 3
BPS Support data provision under the integrated information management system
led by the Secretariat
Note: The above roles and responsibility include those of specified in Section 5, 6, 11 and 12 of this ESMF.
6. Provincial PIUs. PIUs will be established at the provincial level to: (a) mobilize technical
support, (b) establish partnerships with provincial-based institutions and sectors, (c) produce training
modules in line with regional development policies and priorities, (d) review and provide clearance to
annual work plans for CB submitted by the municipality/district, (e) recommend districts to receive
grants based on performance, (f) carry out regular supervision, monitoring and evaluation by utilizing
the web-based and mobile integrated information system, (g) undertake quality control and provide
support and coaching to districts in CB activities, and (h) allocate Provincial APBD for CB activities
specifically relevant to provincial priorities.
7. District PIUs. District PIUs will be in charge of project implementation at the district level.
Their roles include: (a) monitoring the implementation of activities and budget allocation, and
achievement of KPIs; (b) establishing PTPDs and coaching clinics; (c) establishing partnerships with
district-based institutions and sectors, (d) managing CB for villages (both for apparatus and
communities) at district level; (e) carrying out supervision and monitoring to PTPD performance and
68
CB delivery by utilizing the web-based and mobile integrated information system; (f) ensuring the
quality of CB delivery (i.e. quality control, feedback mechanism, etc.); (g) supervising PTPD in
implementing village CB plans; (h) organizing assessment of village CB needs; (i) producing training
modules in line with district development policies and priorities, and (j) reviewing the performance of
villages in CB, and proposing incentives accordingly.
8. Subdistrict PTPDs. At the subdistrict level, PTPDs will be established based on a Decree of
the Bupati/Mayor, as part of the village CB program. PTPD will be responsible, among other tasks, for:
(a) carrying out needs assessments, and verifying village proposals for CB; (b) developing annual work
programs for CB at village and subdistrict level; (c) arranging the delivery of the training at subdistrict
and village level; (d) coordinating peer-learnings and identifying sectoral and technical support needs;
and (e) managing supervision, monitoring, evaluation and feedback at the subdistrict level, locally in
each subdistrict.
9. Village Governments and Institutions. Village governments and institutions are responsible
for: (a) identifying the CB needs and submitting proposals for learning, (b) allocating APBDesa for
attending the trainings, printing the training materials and providing the adequate instruments
(smartphones or tablet), and (c) managing CB activities at the village level, including establishing a
learning forum (or kelompok belajar) and selecting champions for learning at the village level.
Advisory and Technical Support
10. Advisory Support. Advisory support will be deployed to support the Secretariat under
BAPPENAS and Kemenko PMK. This will support the central institution in drafting relevant
regulations and guidance for improving the mechanisms for budget transfers, creating incentives for
villages to improve their budgetary performance, developing sectoral support as needed, advising
institutional strengthening activities, etc.
Figure 1. Organizational Structure of the Project
11. National Management Consultant (NMC). The NMC team will be mobilized at the central
level to support both CPIUs within MoHA and MoV. The NMC will be responsible for daily overall
program management, including strengthening the technical and institutional capacities; carrying-out
Project supervision, monitoring, spot-checks, and evaluation of outputs and outcomes; strengthening
sustainability of Project outcomes, and managing the web and mobile based CB. The NMC will include
69
various technical experts across a range of disciplines. Members of the NMC team will serve central
PIUs during the life of the Project contingent on their annual performance.
12. Provincial and District Consultant Teams, and Subdistrict Facilitators. These teams will
be contracted at the provincial level, and will operate at the provincial, district and subdistrict levels.
The recruitment will be jointly managed by central and provincial PIUs through the establishment of a
joint recruitment committee. The joint recruitment committee will develop selection criteria, which will
be used as part of the annual performance review of the teams. All recruitment processes will be
managed and recorded through the web-based integrated information system. Teams will be mobilized
to service for three years, contingent on annual performance.
Implementation Arrangements and Stages
13. Project Cycle. Project management will follow annual cycles, and will involve the
stakeholders depicted in Figure 1. The annual cycle will include the following activities:
a. Planning activities will include needs assessments; annual work-planning and budget
allocation; organizing communities, local institutions and village government apparatus
(including key champions); and learning events at the village, subdistrict or district levels.
b. Implementation activities include training of trainers (if applicable), socialization of the
learning events, distribution of training modules and supplemental tools and instruments, and
registration and recording of the learning events.
c. Feedback and evaluation and learning performance reviews include: review of the contents of
trainings, instruments used, delivery methodology and training duration,
attendees’/participants’ feedback, and the trainer/learning facilitators performance. All
feedback and training evaluation will be submitted through a web-based system. The learning
performance review (for district, subdistrict and village levels) will be carried out against pre-
determined criteria.
d. Follow-up activities conducted after the CB is implemented and reviewed, i.e. coaching clinics,
visits to selected villages for refresher learning/trainings, community or village apparatus
knowledge sharing activities (kelompok belajar), and peer-learning activities among villages.
These activities will be managed by PTPDs and subdistrict facilitators.
e. Outcome performance review. An outcome performance review will be carried out annually; it
will target learning participants based on surveys submitted through the web-based system.
Findings of the review will be used to revise the substance of the learning materials, types of
delivery, instruments used, schedule, tariff, the focus on behavior change, etc. Feedback from
the performance review will also be used by central PIUs and partner institutions for improving
and upgrading training modules and management, as well as further guidance and regulations.
Project Implementation Phases
14. The Project will be implemented in three phases. During the first year (or year and a half),
Project implementation will lay a solid foundation and begin to put in place and socialize the required
systems. During the middle years (years 2 and 3), the Project will pilot innovative modules and
instruments that are more solutions-oriented to encourage peer learning; it will also pilot performance-
based incentive mechanisms. In the longer-term (years 4 and 5), the Project will aim to maintain the
CB management system, improving/upgrading relevant policies and guidelines, and upgrading the
substance of trainings to suit recent local development needs, and bringing successful pilots and good
practices to scale, formalizing and institutionalizing them.
70
a. Short-term (Year 1): activities to be implemented in Year 1 include the following:
i. Development of basic national curriculum and expected competencies, preparation and
modification of mandatory and selected modules on compliance (on procedure,
accountability, performance, and others) and its supporting instruments (i.e.
promotional materials: flyer, video, posters).
ii. Development of program implementation guidelines and operation procedures.
iii. Mobilization of the management and support system, including identification of partner
institutions, training of trainers (to facilitate the learning process), etc.
iv. Development of a web-based integrated information system and e-learning mechanism.
v. Pilot of web-based system for mandatory training modules.
vi. Strengthening the roles of participating institutions at central, provincial, and district
levels, as well as collecting letters of interest from districts for participating in Project
activities.
b. Medium term (Years 2 and 3): activities to be implemented in Years 2 and 3 include the
following:
i. Development of expanded modules, including those provided by provincial and district
levels, and its supporting materials.
ii. Full utilization of the web-based integrated information management system.
iii. Scaling up the modules and CB delivery mechanism, including expanding the use of
partner institutions.
iv. Adoption of a structured supervision, monitoring and feedback, integrated with the
web-based information management system.
c. Longer-term (Years 4 and 5): activities to be implemented in Years 4 and 5 might include the
following
i. Strengthening the institutions for sustainable use of the web-based information
management system.
ii. Formal guidance provided for partnerships and service delivery.
iii. Abolishment of the face-to-face or facilitated training delivery, to rely only on remote
training delivery (with the exception of lagging/disadvantaged areas with limited
internet connection).
iv. National scale-up and institutionalization or formalization of changes introduced.
Phasing in of target areas
15. The project will use a phased approach during implementation. The project will begin with
implementation in 100 districts, with a view to expand into additional districts as per the sequencing
provided in the table below.
Table 2: Phasing of selected districts in the project
Administrative Units (total)/ Year Year 1 Year 2 Year 3 Year 4 Year 5
Provinces 11 19 19 33 33
Districts 100 180 250 330 380
Villages 16,773 34,137 47,038 58,502 66,496
71
16. Given that the project will use a phased implementation approach, three key criteria will
be used as conditions for entry. Interested provinces and districts must submit a letter of interest with
the following elements:
a. Establishment of Project institutions (PIUs, PTPD, and Pokja)
b. Allocation of adequate staff and budget for Project activities (including for monitoring and
supervision), and selection of self-managed CB activities
c. Commitment to comply with the Project’s operational guidelines
17. During Years 1 and 2, the number of participating districts will be limited to 180, in line
with criteria agreed jointly between BAPPENAS, MoHA and MoV. Selection criteria could include,
inter alia: (a) index of village development (Indeks Pembangunan Desa), (b) APBD allocation for CB
activities, and (c) timeliness of transfers of village funds. The Project will scale up the number of
participating villages and districts based on the capacity of PIUs to maintain and operate the web-based
systems for CB (i.e. provision of adequate modules, partnership with at least two national institutions,
and the regular use of the web-based programs by the existing participating districts).
18. Conditions for Implementation of Village CB Activities. The project will provide specific
guidance for the CB management, which will include mechanisms for:
a. Rolling out systems for improved capacity building (at village, at subdistrict, and at district
levels). Depending on the needs assessments and quality of materials, the PTPD, District PIUs
and Provincial PIUs may determine that a learning event be held in groups and accounted for
as contribution from the village, subdistrict, or district, without additional costs being borne by
the Project.
b. Delivery type: face-to-face and online (web-based) learnings. The Project will strongly
encourage the use of web-based systems, except for the first years. A waiver will be provided
for remote and lagging areas. The definition of remote and lagging areas will be based on: (a)
limited accessibility (i.e. accessible by only one mode of transport or taking more than 8 hours
of travel time), and (b) geographical conditions (i.e. island based, and border areas).
c. Type of learning: self-learning, facilitated discussions, peer learning, on the job training, and
coaching and forums (kelompok belajar).
Partnership Arrangements
19. Partnerships with national, provincial and district levels institutions will be initiated by
the Project. Partnerships will aim to strengthen the delivery of CB, improve the quality of learning
materials and its supporting instruments, encourage local ownership (from village governments and
local institutions), and support the sustainability of CB mechanisms.
20. Partnership at the national level will be managed by MoHA through the establishment of
Memoranda of Understanding, while partnerships at provincial and district levels will be
facilitated by Provincial PIUs. Selection of partner institutions will be based on competencies and will
consider a variety of services: (a) development of modules, (b) delivery of training/events, (c) provision
of trainers/co-trainers, and (d) coaching and evaluation.
21. Registration of trainers and partner institutions. Registration and verification of partner
institutions will be made through the web system, with approval by MoHA.
72
Village Performance Based Incentive Mechanism (Component 3)
22. The project will pilot test a performance-based grant to qualifying villages who meet
agreed metrics aimed to determine the performance of village governments in improving quality
of planning, budgeting and supervision. Up to fifty (50) districts will be selected to participate in the
performance-based grant program in Year 1 of the project, with all villages within their jurisdiction
having the opportunity to opt into the program. Year 1 of the program will help to finalize the selection
of the villages, and to put in place a system of assessments and reporting for the performance grant. In
Year 2 of the project, village governments will be assessed based on the agreed metrics. Those found
to qualify against quality of governance measures will be recommended to receive the grant, which
would first be disbursed at the start of Year 3 budget cycle (January). The participating villages would
be assessed each year subsequently and would receive the performance grant based on the achievement
of agreed quality metrics.
23. Districts will play a key role in the monitoring and disbursements of performance grants.
The performance-grant fund disbursement process will closely mirror village funds in that they will be
disbursed to districts, and then forwarded on to qualifying village governments for use against agreed
expenditures. The district will play a key role in signing on to the performance grant program, and will
act as the first stop to collect information on village performance to be forwarded on for assessment by
BPKP. Once the final list of villages are recommended, funds would be disbursed to the district, to on-
grant to village governments.
24. Eligible activities. As the performance-based grant is a pilot program, it will look to pilot test
different options for fund usage at the village level, to better understand what best motivates and
rewards good performance. The types of activities that could be eligible for financing under the
performance-based grant include (i) village level investments; (ii) capacity building programs for
village governments; and (iii) performance allowances for village governments. Village level
investments could include innovative activities to strengthen local economic development, women
empowerment, productivity, investment in physical infrastructure, small-scale innovative technology
for water supply, disability inclusive facilities for schools and early childhood centers, digital
infrastructure to promote connectivity, etc. There will be a brief negative list of prohibited infrastructure
types. The list of proposed activities must be included in the annual work plan of a village (or Rencana
Kerja Pemerintah Desa), and it must be consulted with and agreed by communities and local
institutions. MoHA and MoV will develop guidelines to further elaborate the criteria and transfer
mechanism for the incentives.
25. Role of BPKP. BPKP will have a role in sampling villages to verify the outputs. Eligible
outputs will be reported to MoHA and MoV, who will in turn provide recommendations to BAPPENAS
and MoF for granting the funds to the respective districts.
Monitoring and Evaluation Arrangements
26. To improve overall GoI’s capacity to collect and use data to track village development
performance, the Project will develop an integrated village data platform (InfoDesa) that will
compile key village performance data to monitor/track village capacity and development
performance. The Project has identified several village level information systems that can be used to
monitor village governance and development outcomes. These include the Prodeskel (Village Basic
Data), Siskeudes (Village FM), Sipades (Village Assets), Sipede (Village Budget and Outputs) and OM-
SPAN (Village Fund disbursement and outputs). In addition, data on basic health and education service
provisions are available from administrative data of of the Ministry of Health and the Ministry of
Education and Culture. InfoDesa will enable the GoI to pull data from these various sources and use it
73
to monitor village performance. The Project will also help strengthen existing key systems (such as
Prodeskel and Siskeudes) to ensure data availability and quality. The Project will also support
BAPPENAS and BPS to analyze data and results from InfoDesa and utilize the data to inform village
development policies and strategies.
27. The following data sources have been identified to be integrated into an integrated data
platform:
Ministries Data System Information/Variables
Ministry of Home Affair
1. Bina Pemdes Prodeskel Village Data covers:
- Village government capacity
- Population
- Resource
- Agriculture
- Basic Services
2. Dukcapil Civil Registration - Basic information on family
member and background
- Individual background
3. BPKP and District Siskeudes - Village budget
Ministry of Village SIPEDE - Village budget
- Village fund output
Ministry of Finance OMSPAN - District budget
- Village budget
Ministry of Education School - School basic information
- Student examination result
Ministry of Health
1. Basic Service Puskesmas - Puskesmas services
- Medical Staff in puskesmas
- Puskesmas Coverage
2. Balitbangkes Risfaskes - Health facility information
- Medical Staff in each health
facility
- Coverage
3. Balitbangkes Riskesdas - Health status of household
- Basic information about the
household background
Ministry of Social Affair Poverty data - The poor households
background
Geospatial Information Agency Digital Map - Border area of villages
- Agriculture map
BPS
Podes - Village basic information
- Resource
- Population and demographic
- Village government
background
- Basic services
- Agriculture
Population Census - Basic Information of
Population
Agriculture Census - Detail information about
agriculture business
74
Ministries Data System Information/Variables
Economy Census - Detail information about
business, in small to large
scale
Susenas - Household information data
in detail, including access to
education, health, finance,
and poverty program, health
status, consumption, access to
sanitation and clean water, etc
Village digital map - Village border area
Bappenas SEPAKAT - Poverty website for district
28. The integrated data portal (InfoDesa) will integrate data systems into a single portal that will
be able to update on indicators in real time. The project will also develop data dashboards for different
levels of government and to be able to filter and layer different data inputs. This data system will be
publicly available.
Figure 2. Integrated Village Data Platform (InfoDesa)
29. The Project will utilize the PIUs and TA at subdistrict/district levels to collect basic data on
activities and inputs. Data will be compiled at district and province levels and submitted to the National
Management Consultant for quarterly financial and progress reports. The Project’s PIUs will conduct
bi-annual supervision missions together with Bank’s Task Team.
30. The Project will use various mechanisms for evaluation and oversight, such as:
a. E-platform for community monitoring (SmartVillage app), an app that will enable communities
to monitor the use of village funds and their outputs
b. Village audit with BPKP
75
c. Verification protocol with BPKP to assess village performance; this will be done as part of
piloting the performance-based grant transfers to villages
d. Annual PODES (village census). The Project will support and pilot test implementation of
annual PODES with BPS to help verify some village performance indicators
e. Baseline and end line data collection, as needed
f. Mid-term and final evaluations of key Project outcomes
g. Modern electronic system for recording/monitoring procurement, payment transactions and
performance
31. In addition, the Project will conduct an impact evaluations, studies and analyses of project
investments to best capture learning under the project.
76
ANNEX 2: SOME OF THE ONGOING CAPACITY BUILDING ACTIVITIES IN THE MINISTRY OF
VILLAGE AND THE MINISTRY OF HOME AFFAIRS FOR THE IMPLEMENTATION OF
VILLAGE LAW
No. Target Group Module / curricula Duration
TRAINING FOR PROFESSIONAL FACILITATORS IN THE IMPLEMENTATION OF VILLAGE
INNOVATION PROGRAM
1. Experts of Community
Empowerment at District
level (TAPM)
Debriefing training to mentor the Working
Group of PPID and Working Group of P2KTD
5 days
2. Experts of Community
Empowerment at village
level (TAPMD)
Training to mentor the District Innovation
Team (TIK) and Village Innovation
Implementation Team (TPID) in the activities
of capturing innovation
5 days
3. District Facilitator (PD) Training to facilitate the TPID during the
implementation of PPID in the sub-district
2 days
4. Village Facilitator (PLD) Training to facilitate the village on the
innovative village plan
2 days
TRAINING ON INSTITUTIONAL DEVELOPMENT FOR VILLAGE INNOVATION PROGRAM
1. District Innovation Team
(TIK): Working Group
(WG) of Knowledge
Management (PPID); WG of
Providers of Village
Technical Capacity
Strengthening (P2KTD);
Secretary of TIK/Head of
TIK
Orientation training program to promote the
utilization of the Dana Desa for innovative
program through a well-planned and
systematic knowledge management
3-5 days
2. Village Innovation
Implementation Team
(TPID)
Debriefing training to implement the activities
of PPID in the subdistrict and village,
including the financial management of DOK-
TPID
3 days
TRAINING FOR PROVIDERS OF VILLAGE TECHNICAL CAPACITY STRENGTHENING (P2KTD)
1. Provider of Village
Technical Capacity
Strengthening (P2KTD)
Training on planning and implementation of
PEL and entrepreneurship
5 days
2. Provider of Village
Technical Capacity
Strengthening (P2KTD)
Training on planning and implementation of
village infrastructure
5 days
3. Provider of Village
Technical Capacity
Strengthening (P2KTD)
Training on planning and implementation of
human resource development
5 days
TRAINING PIID-PEL
1. Team of Implementing
Partnership Activities
(TPKK)
Management of Financial Administration for
PIID-PEL
3 days
2. Team of Implementing
Partnership Activities
(TPKK)
Procurement for PIID-PEL
3 days
BALAI BESAR LATIHAN MASYARAKAT YOGYAKARTA (MOV)
1. Village Cadre for
Community Empowerment
(KPMD)
• Hydroponic agriculture
• Batik making
• Agriculture product processing
• Fish cultivation
• Decorative plants
77
No. Target Group Module / curricula Duration
2. BUMDes (Village-owned
Enterprise)
Management BUMDes
Entrepreneurship
Village tourism
78
ANNEX 3: SOME OF THE ONGOING CAPACITY BUILDING ACTIVITIES IN THE MINISTRY OF
HOME AFFAIRS FOR THE IMPLEMENTATION OF VILLAGE LAW
No. Target Group Module/Curricula Duration
1. Village apparatus Training PKAD
2. Village apparatus ToMT PKAD
3. Village apparatus ToT PKAD
4. Village Representative Body
(BPD)
Training
BALAI PEMERINTAHAN DESA (MoHA) YOGYAKARTA
1. Village apparatus and Village
Community Organization
(LKD)
Village arrangement; RPJMDes and RKPDes
Village administration
Preparation of APBDes
Management of Village Funds
2. LPMD Preparation of village planning documents
3. LP3 - PKK
4. Neighborhood Association
(RT)
5. Village Representative Body
(BPD)
Institutional and village partnerships
6. Management and Controller
of BUMDes
Control and development of BUMDes
79
ANNEX 4: E-WASTE MANAGEMENT
I. E-Waste Management in Indonesia
1. E-waste is a relatively a new issue in Indonesia. Its physical existence, except used batteries, is not being
so real yet, especially within the chain of waste management. Disposal of e- waste can be processed through
recycling and/or exporting to other countries (for further process). In some area, particularly in Java, e-waste
recovery and handling such as dismantling, segregation of parts, refurbishments of old products and recovery of
metals are done by informal sectors. It handles almost 90% of the total waste generated, particularly from
household, office, commercial areas, recovering materials and refurbishing products. These recyclers use
processes and practices such as open burning, acid baths and heating of circuit boards, resulting in emissions and
release of toxic elements (included brominated flame retardant) into environment. Therefore, the government need
to regulate this practice to prevent the negative impact to environment and human health.
2. Interest regarding hazardous wastes in Indonesia had emerged since 1990s, especially after the
intensified industrial activities. The hazardous wastes management in Indonesia refers to the principles and
guidelines for sustainable development as stipulated in Law No. 4/1982 on Basic Provisions for Managing the
Living Environment. The amendment of this Law has been issued by Law No. 23/1997 on Management of Living
Environment. This Law was amended in 2009 and issued as Law 32/2009 on Protection and Management of the
Environment. Article 59 of this Law refers to hazardous waste management on which mandating that further detail
to be described in the Government Regulation.
3. Below is the national regulations on E-waste in Indonesia:
a. Ratification of Basel Convention by Presidential Decree No. 61 Year 1993 Based on Basel Convention,
Annex VIII: A1080 and A1180;
b. E-waste from household and municipal waste, under the Law no 18/ 2008 on Solid Waste Management,
are categorized as specific municipal solid waste.
c. Government Regulation No. 101 /2014 concerning Hazardous Waste Management
• Based on Annex I, Table 1 List of Hazardous Waste from Not Specific Source: Given Code is B107d
for Electronic Waste including CRT, fluorescent lamp, PCB and wire rubber; and A111d for used
refrigerant from electronic equipment.
• Based on Annex I, Table 3 List of Hazardous Waste from General Specific Source, activity 28:
Electronic manufacturing or electronic equipment; and activity 29: Recondition and
Remanufacturing of Electronic Equipment.
More specific e-waste regulation will be developed under Minister of Environment and Forestry Decree. This
Ministerial Decree for Indonesia National Municipal E-Waste Management from households and municipal
sources, including office is currently being developed. Below is number of industries which has the activity on
collection and dismantling of e-waste in some areas:
Location Number of Industries Kind of collection
Batam Island 1 Rejected small parts of electronic component,
plastic, e-waste, used PCBs, Computer monitor,
and electronic parts (only dismantling, and the
waste produced uses as raw material in smelter
industries)
Central Java 2 Dry cell batteries collection and smelters
West Java 5 All e-waste material (only collection, the waste
goes for export, smelter industries in Batam, and
other smelter industries in Jakarta area)
Tangerang 1 All e waste (only collection) and export
Central Java 1 Recondition of LED monitor, for sale in local and
aboard
80
II. Municipal E-Waste Management
5. According to Law no 32/2009 on Protection and Management of the Environment, the hazardous waste
management as a series of activities related to reducing, storage, transporting, utilization, processing and/or
dumping of hazardous waste, where in each step need permit and reporting. Under the law, indeed, everyone
should be prohibited to dispose the hazardous waste to the environment. Further details on hazardous management
is regulated by Government Regulation no 101/2014 (PP 101/2014). This PP, the management of the hazardous
waste starting from the sources, within temporary collection Facility/dropping point and further e-waste
management by certified companies.
6. The sources of e-waste are from (i) municipal waste (including household, commercial activities and
offices), and (ii) industry. For the later, EPR (extended producer responsibility) is applied where the producer is
responsible to monitor distribution of product and handling of their hazardous waste as mandated in Law 18/2008
on solid waste management.
7. The e-waste management is also involved (i) the consumer and distributor who need to bring their e-
waste to the collection facility, (ii) collector, make cooperation with producer and local government to facilitate
the collection facility sites; and (iii) recondition industry that make recondition and responsible for managing their
waste from the production process.
8. Procedures or protocol for e-waste management in Indonesia, are shown in the following diagram. The
e-waste from the household, commercial activities and offices are transported to the dropping point/temporary
collection facilities. This dropping point can be “trade-in location”, “Waste Bank/Bank sampah” or other
location/site, determined by collector and/or local government. From this e-waste shelter, the e-waste will be
transported to Recycling Center for reused, or to be exported to other countries. Finally, the remaining items
which cannot be reused will be disposed in an authorized dumping area or through other options such as
incinerator.
III. Application of E-Waste Management
9. Below is a good example of e-waste management in the city of Jakarta introduced in May 2017 which
may inspire other cities/districts to do the same. This program has helped the Jakarta resident to reduce their email
through bringing the e-waste to dropping point located in the office of Jakarta Environmental Agency/Dinas
Lingkungan Hidup as well as in several office buildings in Jakarta. Dropping point is also available in Jl. Sudirman
only during ‘car free days.’ Another option that the resident can have pick-up services if the e-waste is amounting
more than 5 Kg.
81
Jakarta starts e-waste collection service in cooperation with PT Prasadha Pamunah Limbah Industri
After long ignoring the issue of the correct disposal of electronic goods, the Jakarta Sanitation Agency has
launched a new initiative for treating the dangerous garbage, involving deploying special trucks to collect it in
cooperation with a private waste-treatment company.
On May 2017, the Jakarta Provincial Government signed a Cooperation Agreement with PT Prasadha Pamunah
Limbah Industri (PT. PPLI) regarding the Program of Managing Electronic Waste Specific for Used Handphones.
The company had treated only industrial waste in the past but was open to working with the administration. It had
actually already looked into treating electronic waste, or e-waste, but had found it difficult to collect.
The Jakarta Provincial Government plans to help the company collect e-waste while it pays compensation to the
garbage facilities. E-waste such as computers, refrigerators, batteries and other broken electronic devices still had
value, so residents could receive compensation. The Environment Agency of Jakarta Provincial Government
would use two ways to collect the e-waste. The first one is residents can actively submit their e-waste through
their local garbage facilities; the second one is consumers could try to return broken devices to producers. Some
producers have 'trade in' programs when you can submit broken or used electronic devices to get some cash.
The agency also conducts the following activities to start in relation to the collection of e-waste in Jakarta, such
as: (i) Socialization and education to the program’s target of collecting Electronic waste; (ii) Placing e--‐waste
drop boxes: (iii) Picking up and transporting e-waste.
82
ANNEX 5: REPORT ON ENVIRONMENTAL AND SOCIAL SCREENING
(Example from a Road Project)
A. SUB-PROJECT ACTIVITY PLAN
1. Name of sub-project activity …………………………………………………………………….
2. Length of Road ………….. km
3. Width of Road
a. Existing width
b. Planned width
c. Existing surface
d. Planned surface
a. ……… m
b. ……… m
c. ……… m
d. ……… m
4. Location
a. City
b. District
c. Province
a. ……………………………………………
b. ……………………………………………
c. ……………………………………………
5. Road Status National/Province/District/City
6. City Status Metropolitan/Big/Medium/Small
7. Project Type Construction/Maintenance
8. Land Acquisition Size ………….. Ha
9. Average Traffic Flow
a. Existing
b. Planned
a. ………………. Vehicles/day
b. ………………. Vehicles/day
10. Project Status Pre-feasibility study/Feasibility study
B. RESULT OF ENVIRONMENTAL SCREENING ON PROTECTED AREA AND OTHER SENSITIVE
AREAS
1. Type of Land Use
a. Type / name of the protected area
b. Location of the road in protected areas
a. ………………..
b. Pass through/share boundary with/close to/far from.…..
2. Other Environmental Components that are
sensitive to changes (if any)
IPs / Vulnerable peoples/ Dense Settlement / Commercial Area /
Cultural Heritage Area / Steep terrain
3. Physiographic conditions of land:
a. Steep terrain (> 40%)
b. Unstable land
c. Other information
1. ………… km
2. ………… km
3. …………. (please mention)
4. Evaluation of Major Impacts Major/Minor
C. CONCLUSIONS (please select one)
1. Must have AMDAL45 Rationale: ……………………
2. Must have UKL/UPL Rationale: ……………………
3. Need LARAP (not applied) Rationale: ……………………
4. Need IPP Rationale……………………
5. Need IPs needs incorporated in the sub-project
design
Rationale ……………………
6. No AMDAL or UKL and UPL needed (only
requires SOP)
Rationale: ……………………
a. BUDGET ESTIMATE FOR STUDY OF
UKL/UPL, SPPL, SOP, LARAP (not
applied), IPP, etc.
Rp…………………………………….
45 Not eligible for financing
83
ANNEX 6: SUGGESTED SCREENING FORM (GENERIC)
Yes No ESMF
Guidance
A. Environment – Will sub-projects during construction and operational phase:
1. Risk causing the contamination of drinking water?
2. Cause poor water drainage and increase the risk of water related
diseases such as malaria?
3. Harvest or exploit a significant amount of natural resources such as
trees, mangroves, fuel wood, fish, or water?
4. Be located within or nearby environmentally sensitive areas (e.g.
intact natural forests, mangroves, coral reefs, wetlands) or threatened
species?
5. Create a risk of increased oil degradation or erosion?
6. Create a risk/potential of landslides?
7. Create a risk of increasing soil salinity?
8. Produce or increase the production of solid or liquid wastes (e.g.
water, medical, domestic or construction wastes)?
9. Affect the quantity or quality of surface waters (e.g. sea, rivers,
streams, wetlands) or groundwater (e.g. wells)?
10. Result in the production of solid or liquid waste, or result in an
increase in waste production, during construction or operation?
If the answer to any of the questions 1-10 is “Yes”, please include an Environmental and
Social Management Plan (ESMP) or SPPL with the sub-project application.
Annex 13
ESMP,
SPPL.
B. Indigenous Peoples:
11. Any there social-cultural groups present in or use the project area
who may be considered as “indigenous peoples”/”ethnic minorities”
/tribal groups” in the project area
12. Any of community member of the indigenous groups in the area
who will get the benefit or impacts from the project?
13. Do such groups self-identify as being part of a distinct social and
cultural group?
14. Do such groups have a close attachment to ancestral territories and
to the natural resources in the project area?
15. Do such groups use indigenous languages that different from the
national language or language used by the majority in project area?
16. Do such groups have customary cultural, economic, social, or
political institutions?
17. Has such groups been historically, socially and economically
marginalized, disempowered, excluded, and/or discriminated?
18. Are such groups represented in any formal decision-making bodies
in the national or local levels?
If the answer to any of the questions 19-26 is “Yes”, please consult the ESMF and, if needed,
prepare an Indigenous Peoples Plan (IPP) with the activity/sub-project application.
IPPF
84
ANNEX 7: FORMAT OF ENVIRONMENTAL MANAGEMENT PLAN AND ENVIRONMENTAL
MONITORING PLAN (UKL/UPL)
The following form is the Format for the Environmental Management Plan (UKL) and Environmental Monitoring
Plan (UPL). It describes the impact of the planned activities on the environment and how it will be managed. As
an integral part of the UKL/UPL, the Statement of Assurance for Implementation of UKL/UPL will be attached
using the template example shown in this annex. This format complies with the Regulation of the Minister of
Environment No. 16/2012 which can be referred to for further guidance.
Title of Chapter/Sub-
Chapter
Content/Remarks
Statement Letter from Project Management
a. The statement letter from project management will state their accountability
to ensure that the Environmental Management Plan (UKL) and
Environmental Monitoring Plan (UPL) will be done. This statement Letter
should be signed on a stamp duty acknowledged by the Head of Bapedalda,
(local environmental agency) and the Head of Local Government
(Governor/Bupati/Mayor).
b. Project management consists of those parties who prepare and implement the
Project Activities, those parties who are responsible for the operations and
maintenance of the Project Activities, and other parties responsible for
environmental management and monitoring.
I. DESCRIPTION OF PROJECT MANAGEMENT
1.1 Company/Village
Name
……………………………….
1.2 Name of Project
Management Entity
Name of project management entity and their job description at each stage of the
Project Activities, which should include:
a. Agency or office responsible for the preparation and implementation of
Project Activities.
b. Agency or office responsible for the operations and maintenance of the
Project Activities after the work is completed.
c. Agency or office responsible for environmental management and
monitoring.
1.3 Address, Number
Phone and Fax,
Website and Email
Clear address of the named agencies or offices related to the Project Activities in
accordance to the point 1.1 above.
II. DESCRIPTION OF PROJECT ACTIVITIES AND ITS IMPACT
2.1 Project Activities
Name
Name of Project Activities in a clear and complete manner.
2.2 Project Activities
Location
a. Location of the Project Activities in a clear and complete manner:
Kelurahan/Village, District/city, and Province where the Project Activities
and its components take place.
b. Location of the Project Activities should be drawn in a map using an adequate
scale (for example, 1:50.000, accompanied with latitude and longitude of the
location).
2.3 Scale of the Project
Activities
An estimation of the scale and type of Project Activities (using accepted units of
measurement). For example: the construction of a market of certain capacity may
need to be accompanied by supporting facilities in line with the Environmental
Management Plan that must mention the type of component as well as the scale.
2.4 Component of
Project Activities in
brief outline
A brief and clear explanation on any component of the Project Activities which
have potential environmental impacts. Work components should be divided based
on stages as follows:
85
Title of Chapter/Sub-
Chapter
Content/Remarks
a. Pre-construction, for example: mobilization of workforce and materials,
transportation, etc.
b. Construction, for example the use of ground water, laying out of utility pipes,
etc.
c. Operations and Maintenance: Post-construction, for example: clearing of
excavated waste material, etc.
Also, attach the flowchart/diagram to explain the flow of work to be done, if
applicable.
III POTENTIAL
ENVIRONMENTAL
IMPACT
Explain in a brief and clear manner about any Project Activities with potential
environmental impacts, type of impacts which might occur, magnitude of impacts,
and other matters needed to describe any potential environmental impacts on the
natural and social environment. Such descriptions can be presented in tabulation,
with each column representing each of the aspects. A description of the size or
magnitude of the impacts should be accompanied with measurement units based
on applicable laws and regulations or specific scientific analysis.
IV. ENVIRONMENTAL MANAGEMENT AND MONITORING PROGRAM
4.1 Environmental
Management Plan
b. The Environmental Management Plan(UKL) consists of the plan itself, as
well as the party in charge, frequency of interventions, implementation
schedule, and types of mechanisms (e.g.: procedures for management,
methods, etc.) in order to mitigate the environmental impacts identified
Section III above.
c. The plan can be presented in a table format, which at minimum contains the
following columns: type of impact, source, magnitude, threshold,
management plan, and frequency of interventions, party in charge, and other
remarks.
4.2 Environmental
Monitoring Plan
a. The Environmental Monitoring Plan (UPL) consists of the plan itself, party
in charge, frequency of interventions, implementation schedule, and types of
mechanisms (e.g.: procedures for monitoring, methods, etc.) in order to
monitor the environmental management plan described in section 4.1 above.
b. The plan can be presented in a table format, which at minimum contains the
following columns: type of impact, source, magnitude, threshold,
management plan, and frequency of interventions, party in charge, and other
remarks. In this monitoring plan, the thresholds should comply with the
prevailing laws and regulations which are applicable according to the
environmental impacts as already identified in Section III above.
V. SIGNATURE AND
OFFICE SEAL
After the UKL/UPL document is prepared and complete, the TPK should sign and
put an official seal on the document.
VI. REFERENCE Insert various references used in the preparation of UKL/UPL.
VII. ATTACHMENTS Attach any relevant documents or information to the UKL/UPL, e.g. tables
displaying the monitoring results, and others.
86
ANNEX 8: FORMAT OF STATEMENT OF ASSURANCE FOR UKL/UPL IMPLEMENTATION
STATEMENT OF ASSURANCE FOR UKL/UPL IMPLEMENTATION
NO: …………………….
In an effort to prevent, minimize and/or address the potential environmental impacts from the Construction Work
of.............................., in the District/Province of.............. as well as in accordance to the duty and authority of the
Village ................, of the District/Province of shall carry out an Environmental Management Plan (UKL) and
Environmental Monitoring Plan (UPL) and include the recommendations from UKL/UPL into the Detailed
Design.
For the next stage, which is the physical work, implementation of the recommendations from UKL/UPL shall be
done by the party in charge for the physical work, which is “TPK Village..................... of the
District/Province..................”.
This statement is duly made, as confirmation to support the Environmental Management Plan (UKL) and
Environmental Monitoring Plan (UPL) on the Construction Work for the Construction of ......................., in the
District/Province of..............,
Location,.........................., Date…..………..
VILLAGE…………….………………............
DISTRICT/PROVINCE OF .......................
Head of Village
NAME .................................
NIP.......................................
87
ANNEX 9: SOP FOR ENVIRONMENTAL MANAGEMENT
1. Roads and Bridges:
a. General Guidelines for Environmental Management (1)- No 008/BM/2009
b. Guidelines for Planning of Environmental Management (2)-No 009/BM/2009, which includes,
among others:
i. General Guidelines for Environmental Management of Sensitive Areas. See Annex 2 of the
Guideline No. 009/BM/2009.
ii. Guidelines for Environmental Management in Forested Areas.
iii. Procedures for obtaining a Use Permit (Leasehold) for Forested Areas.
iv. Implementation Manual for Construction in Forested Areas.
v. Manual for Mitigating Development Impacts on Flora and Fauna in Forested Areas (14
pages), including:
• Methods of Land Clearing;
• Environmental Impact Management Plans for Roads Traversing National Parks.
vi. Guidelines on Environmental Management in Protected Zones Outside of Forested Areas.
See Annex 3 of the Guideline No. 009/BM/2009.
vii. Manual for Mitigating Construction Impacts on Flora and Fauna in Forested Areas.
viii. Manual for Mitigating Development Impacts on Water Resources.
ix. General Environmental Management Guidelines for Protection of Heritage Areas.
x. Manual for Mitigating Air-quality and Noise Pollution from Traffic.
xi. Environmental Screening Procedures for Road Projects. See Annex 4 of the Guideline No.
009/BM/2009.
c. Guidelines for Implementation of Environmental Management Plans (3) - No 010/BM/2009, which
includes, among others:
i. Sample Clauses for Specific Work, related to environmental impact mitigation measures.
See Annex 1 of the Guideline No. 010/BM/2009.
ii. Mitigation Guidelines for Construction Standards (e.g. traffic, construction base-camps,
stockpiles, collecting the material in the quarry, waste management, erosion and
sedimentation, interference of vegetation, handling utilities). See Annex 2 of the Guideline
No. 010/BM/2009.
d. Guidelines for Monitoring of Environmental Management (4) –No 011 /BM/2009.
2. Water Supply:
a. The Regulation of Ministry of Public Works and Housing (MPWH), No. 18/PRT/M/2007, on Water
Supply System Management, which includes among others:
• Guidelines for Master Plan Development, Feasibility Study Preparation, Construction Phase.
b. Guidelines for Simplified Water Supply System Management (SPAM sederhana):
• Guidelines for the construction of water intakes, broncaptering, underground water wells,
simplified water treatment plants, public hydrants, piping installations, and operations and
maintenance.
3. Irrigation:
a. Guidelines for rehabilitation/improvement of irrigation systems, to prevent adverse downstream
effects. Please refer to Regulation of MPWH No 15/PRT/M/2010, Section III.3.2.2 and III.3.3.2.
b. Please follow the MPWH Guidelines for environmental management during construction
(10/BM/2009), as per stipulated in the Regulation of MPWH No 15/PRT/M/2010. Refer to
Appendix 2 - Article III.1.
c. Guidelines for the On-site Agricultural Education for Integrated Pest Management (IPM).
i. Book 1 for Farmers
ii. Book 2 for Extension Workers
iii. Book 3 for Follow Up Actions
4. Sanitation. Can refer to Implementation Guideline of DAK Community Based Sanitation (SLBM)
issued in 2014 by DG of Human Settlements, MPWH.
88
ANNEX 10: FORMAT OF THE “STATEMENT OF COMMITMENT TO IMPLEMENT
ENVIRONMENTAL MANAGEMENT AND MONITORING” (SPPL)
(For activity plan not requiring any UKL/UPL – based on the Regulation of the Minister of Environment No.
16/2012)
We, the undersigned below:
Name :
Job position :
Address :
Ph Number :
As party in charge of the environmental management of:
Company Name/Business :
Address company/Business :
Ph Number of the Company :
Type of Business :
Production Capacity :
Permit already obtained :
Purpose :
Amount of Capital :
Hereinafter, we confirm that we are capable and committed to:
(1) Maintain the public order and always maintain good relations with the neighbouring community.
(2) Maintain the hygiene, cleanliness, and order of the project site.
(3) Be responsible for any environmental damage and/or pollution caused by the business and/or the project
activity.
(4) Be willing to be monitored for environmental impacts of our business and/or project activity by the
authorized officer.
(5) Take the responsibility according to prevailing laws and regulation, if we fail to comply with
commitments stated above.
Remarks:
Environmental impacts already taking place:
1.
2.
3. etc
Measures that will be taken to manage environmental impacts:
1.
2.
3. etc.
This SPPL shall be effective from the date of its issuance, up to the completion of our business and/or project
activity. If the project undergoes any change of location, design, process, type of raw materials and/or
supporting materials, this SPPL must be revised.
Date, Month, Year
Village Head,
(Name/NIP)
Registry number from the local environment agency
Date
Receiver
Stamp duty of Rp, 6,000 Signature Company seal
89
ANNEX 11: TYPICAL SUBPROJECT IMPACTS AND MITIGATION MEASURES
The typical subprojects that will be supported under Component 3 with the potential negative impacts and
mitigation measures are summarized in the following table:
Potential Negative Impacts Mitigation Measures
Roads, Bridge and Drainage subprojects
Erosion from fresh road cuts and fills
and temporary sedimentation of
natural drainage ways
- Limit earth moving to dry periods
- Protection of most susceptible soil surfaces with mulch
- Protection of drainage channels with berms, or fabric
barriers/geo-textile
- Installation of sedimentation basins, seeding or planting of
erodible surfaces as soon as possible
- Selection an alignment that reduces environmental disturbances
- Undertaking maintenance and repairs in a timely fashion
Creation of stagnant water bodies in
borrow pits, quarries, etc. suited to
mosquito breeding and other disease
vectors
Employ measures to avoid creating habitats (e.g. improved
landscaping, re-vegetation, filing or drainage)
Roads/bridges located in critical lands
that are sensitive to erosion and
landslides
- Changing the alignment to reduce steep grades when possible
- Building civil works to stabilize side slopes – terracing or
retaining wall installation
- Using vegetative treatments to stabilize side slopes or prevent
erosion
- Using special treatments to overcome ground water problems,
such as drains
- Regular monitoring and inventory of risks for erosion
Blocked drains (due to design and
maintenance) stop the flow of water
and impact public health
- O&M work must clean the block drains periodically
- Stone masonry or concrete ditch are preferred as water is quickly
transported away (earth ditches drain but they need much more
space and are less stable, earth ditches also need a lot more
maintenance)
- Use of natural slope as it holds up well against erosion
Public Toilets, Sanitation, and Water Supply – Health Risks on the following activities:
Water level of the dug well almost the
same as the soak away, well too close
to the toilets and septic tank
- Check the direction of groundwater flow; the well should be
placed upstream
- Build the soak away as far as possible away from the dug well
(minimum 10 m)
- - Build the proper drainage system to keep the waste water away
of the dug well
A well in the toilet: this is not
acceptable due to high risk of
contamination
- Build a basin in each toilet room and fill them from the well by
pipe channel or container
- - Keep the toilets clean and separate from the well
The sewer pipe laid on the ground
surface may become brittle from the
sun’s UV rays and could also be
damaged by people stepping on it or
other impact
- Burry the sewer pipe all the way to the septic tank
- Install a ventilation pipe and a manhole access in the septic tank
Incomplete septic tank structures Minimum equipment for a septic tank consists of:
1. Access manhole with a lockable cover
2. Inlet pipe
3. Dividing wall of baffle
4. Overflow pipe
5. Ventilation pipe
(To comply with SNI - 2398 – 2002 on septic tank system)
Incomplete public MCK structures
(Mandi/bath, Cuci/wash,
Kakus/toilets)
All essential elements of an MCK need to be included:
1. Toilet (s)
2. Toilet ventilation
90
Potential Negative Impacts Mitigation Measures
3. Water basin with faucet and bottom outlet
4. Slab with raised edge for public washing area
5. Faucets to fill buckets
6. Notch to ditch for surplus water and flow directly to the existing
ditch/drains
Sewage which contains human waste
carries pathogens and must be treated
before discharge into the ground or an
open water course
- A sewer carrying human waste should discharge to a treatment
plant or a septic tank
- A septic tank or other type of settling tank will also partially treat
sewage
Leachate and odor from temporary
domestic solid waste management
must be treated so it will not pollute
the ground or surface water course
- Conduct solid waste segregation to separate the organic and
inorganic waste
- Contain the leachate in cemented bundling floor and channeled to
settling tank before discharged
- Cover organic waste for faster composting and prevent odor
91
ANNEX 12: ENVIRONMENTAL CODES OF PRACTICES46
A. Other Special
Requirements
General responsibility
1. Comply with all relevant regulatory requirements in Indonesia (PerMen PU
No. 45/2007; No. 29/2006 concerning building technical guidelines; and No.
05/2014 on OHS management system).
2. Employ and train suitable qualified staff to be responsible for OHS.
3. During construction, if historical or ancient objects are found, they must be
reported to the directors / leaders.
4. Always keep the construction area free of things that endanger workers and the
surrounding environment.
5. Comply with all rules of safety and security in building design. Example:
ventilation, evacuation routes, evacuation marks, installation of waste
management/ WWTP, pathways for people with disabilities, etc.
Prohibition
1. Cut down trees outside the agreed construction area.
2. Take historical objects found in the construction area.
3. Throw away garbage or construction waste carelessly.
4. Dispose of pollutants such as oil, paint, diesel fuel, in the environment (soil,
waterways).
5. Burn waste and/ or remaining plants from cleared land.
6. Use material containing asbestos.
7. Use wood with unclear origin for construction.
8. Timber that may be used is only timber that is legal/ completed by SKAU.
Dust and pollution
1. The contractor uses water at certain intervals to wet a dusty area, especially
when it is dry and windy.
2. The generator set used does not produce black/ thick smoke.
3. Use proper vehicle (license/ KIR still valid).
Noise
1. Strive to reduce and control noise.
2. Construction activities are only scheduled in the morning (8am to 6pm).
3. Work carried out after working hours must be notified in advance to the
community around the project at least one week before.
Waste Management
1. Provision of temporary trash shelter and daily cleaning at the project site.
2. Accumulated rubbish must be disposed of at an official landfill (evidence or
landfill location must be reported).
3. Oil waste and other hazardous waste (including contaminated soil and oil
spills) must be kept closed and separated from other wastes. This type of waste
must be transported by licensed transporters to a licensed disposal facility.
4. After the work is completed, all debris and the rest of the construction materials
must be removed from the project site/ cleaned.
5. Worker's waste: leftovers, toilets must be managed properly.
46 For various types of village infrastructure, see practical Manual of “The DOs and DON’Ts: Environmental
Management: General Considerations-Site Screening-Construction Site Management, Roads, Water Supply, Sanitation,
Solid Waste Management, Markets, Rivers” prepared by the PNPM-Rural Project. This Guidance Book, English version
can be accessed through http://documents.worldbank.org/curated/en/925701495170561883/The-dos-and-the-donts-
environmental-management-general-considerations-site-screening-construction-site-management-roads-water-supply-
sanitation-solid-waste-management-markets-and-rivers. This Guidance Book, Bahasa Indonesia version can be accessed
through http://documents.worldbank.org/curated/en/188631468042887318/Baik-and-buruk-pengelolaan-lingkungan.
92
Occupational Health and Safety (OHS)
1. The contractor complies with all applicable regulations in Indonesia and the
applicable SOPs for workers.
2. All workers are equipped with adequate personal protective equipment, namely
protective helmets (hard hat), work clothes/ vests, boots, gloves, eye protection,
and others according to the type of work performed.
3. Requirements for workers and visitors on site to use safety/ protective
equipment that meets the standards.
4. The contractor must maintain equipment that can endanger work safety.
5. The contractor must routinely conduct formal and informal OHS inspection
activities.
6. The contractor provides OHS equipment such as stacking stairs, safety fences,
fire extinguishers, OHS equipment, OHS signs
7. A safety fence is built around the construction site.
8. If a work accident / disaster occurs, it must be reported to the directors / leaders
and documentation.
B. Environmental
Management and
Monitoring
Implementation of environmental management and monitoring:
1. The environmental and social impact management / mitigation plan that has
been prepared and used as the basis for the implementation of construction can
be operational and effective in accordance with the Environmental and Social
Management and Monitoring Plan.
2. Meet environmental and social requirements.
3. Complete all check list and reports and evaluate the Environmental Code of
Practices / ECOP determined by the Project Proponent.
4. Implementation of management of environmental and social impacts of
construction work in accordance with the Environmental and Social
Management and Monitoring Plan.
5. Monthly report on construction work and implementation of management of
environmental and social impacts carried out by the construction implementer.
6. Implementation of management of environmental and social impacts of
construction works in accordance with the matrix taken from UKL-UPL or
SPPL documents or other Environmental Management Documents.
93
ANNEX 13: FORM CHECK LIST ENVIRONMENTAL CODE OF PRACTICE (ECOP47)
Working Unit : ...........................................................................................
Title of Activity : ...........................................................................................
Location of Activity : ............................................................................................
A. ENVIRONMENTAL RESPONSIBILITIES FOR CONTRACTORS
1. GENERAL
No. Criteria Yes No Not necessary Recommendations
given
a. Has it complied with all relevant regulatory
requirements in Indonesia (PerMen PU No.
45/2007; No. 29/2006 concerning building
technical guidelines; and No. 05/2014 on OHS
management system)
b. Is there an Information Board for Construction
Activities that contains information on Project
Name, Implementing Contractor Company Name,
Job Type, Job Execution Period, Supervision
Consultant Company Name and Contact Number
contacted to submit a complaint
c. Have you implemented the Environmental and
Social Management Plan (ESMP) for the duration
of the construction period?
d. Monitor the effectiveness of ESMP
implementation and store monitoring data
e. Make a monthly report on data from the results of
monitoring on the implementation of
environmental management to Project Proponents
f. Employ and train suitable qualified staff to be
responsible for OSH
g. During construction, historical objects must be
reported to the head of the Project Proponent
h. Comply with all rules of safety and security
regulations in building design. Example: there is
ventilation, evacuation routes, evacuation marks,
installation of waste management/ WWTP,
pathways for people with disabilities, etc.
i. If there are significant environmental and social
impacts and no mitigation action conducted, the
Contractor stops construction activities after
receiving instructions from the Project Proponent,
and if needed, proposes and carries out repairs
47 For various types of village infrastructure, see practical Manual of “The DOs and DON’Ts: Environmental
Management: General Considerations-Site Screening-Construction Site Management, Roads, Water Supply, Sanitation,
Solid Waste Management, Markets, Rivers” prepared by the PNPM-Rural Project. This Guidance Book, English version
can be accessed through http://documents.worldbank.org/curated/en/925701495170561883/The-dos-and-the-donts-
environmental-management-general-considerations-site-screening-construction-site-management-roads-water-supply-
sanitation-solid-waste-management-markets-and-rivers. This Guidance Book, Bahasa Indonesia version can be accessed
through http://documents.worldbank.org/curated/en/188631468042887318/Baik-and-buruk-pengelolaan-lingkungan.
94
and implements alternative construction methods
to minimize their environmental and social
impacts.
B. ENVIRONMENTAL MONITORING
Ensuring that work activities performed in a way that does not damage the environment and maintain
the environment.
1. PROHIBITION
No. Criteria Yes No Not
necessary
Recommendations
given
a. Cut down trees outside the agreed
construction area.
b. Take historical objects found in the
construction area.
c. Throw away garbage or construction waste
carelessly.
d. Dispose of pollutants such as oil, paint, diesel
fuel, in the environment (soil, waterways).
e. Burn waste and/ or remaining plants from
cleared land.
2. POLUTION AND DUSK
No. Criteria Yes No Not
necessary
actions
Recommendations
given
a. Use of water at certain intervals to wet a
dusty area, especially when it is dry and
windy
b Use of generator that does not produce
thick/ black smoke
c. Storage of diesel/ diesel for generator sets
uses tanks/ drums with secondary
containment to prevent the impact of spills/
spills on the ground
d. Use proper vehicle (license/ KIR still
vaild)
3. NOISE
No. Criteria Yes No Not
necessary
Recommendations
given
a. Construction activities are only scheduled
in the morning (8am to 6pm).
95
b. Work carried out after working hours must
be notified in advance to the community
around the project at least one week
before.
4. WASTE MANAGEMENT
No. Criteria Yes No Not
necessary
Recommendations
given
a. Provision of temporary trash shelter and
daily cleaning at the project site.
b Accumulated rubbish must be disposed of at
an official landfill (evidence or landfill
location must be reported).
d. Oil waste and other hazardous waste
(including contaminated soil and oil spills)
must be kept closed and separated from
other wastes. This type of waste must be
transported by licensed transporters to a
licensed disposal facility.
d. After the work is completed, all debris and
the rest of the construction materials must
be removed from the project site/ cleaned.
e Worker's waste: leftovers, toilets must be
managed properly.
5. OCCUPATIONAL HEALTH AND SAFETY (OHS)
No. Criteria Yes No Not
necessary
Recommendations
given
a. The contractor complies with all applicable
regulations in Indonesia and the SOP
according to the ESMP for workers
b. All staff are equipped with appropriate
personal protection equipment, namely
protective helmets (hard hats) and security
clothing (high visibility clothing)
c A safety fence has been built around the
construction site
6. AVAILABILITY AND USE OF SAFETY EQUIPMENT
No. Criteria Yes No Not necessary Recommendations
given
Legal basis:
Minister of Manpower instruction No. 2 / M /
BW / BK / 1984, concerning ratification of
personal protective equipment
96
a. Work safety equipment: personal protective
equipment: work clothes/ vests, boots, helmets,
gloves, eye protection etc., available
b. The requirement for workers and visitors on site
to use safety/ protective equipment that meets
the standards
c. Is maintenance for equipment that can endanger
work safety carried out?
d. Does the company carry out inspection
activities on OSH implementation both formally
and informally regularly?
e. Are there available environmental equipment
such as stacking stairs, safety fences, fire
extinguishers, OSH equipment, OHS signs?
f. Does the company conduct activities/ meetings/
briefings related to the implementation of OSH?
g Does the Company have a system for
measuring, monitoring and evaluating the
performance of the Safety Management System
Occupational Health and the results
analyzed to determine success or to identify
corrective actions?
h. What approach does the company take to
increase awareness about OHS, for example:
with OHS posters (safety), slogan motivation to
work safely, reward and punishment?
i If a work accident / disaster occurs, it must be
reported to the board of directors and
documentation is made?
Note: Each monitoring item must be equipped with the appropriate photo / documentation
7. SANCTIONS:
If the contractor is proven to have committed a violation of this SOP, a written warning will be given up to 3
times and if the violation is repeated then the project activity can be stopped and the contract can be terminated.
Reported by Supervision Consultant
Name : Signature :
Cellphone :
E-mail :
Acknowledged by Director of Construction Works
Name : Signature :
Cellphone :
E-mail :
97
ANNEX 14: SOCIAL ASSESSMENT OF INDIGENOUS PEOPLES
1. Objectives. The purpose of Social Assessment (SA) is to evaluate the sub-project’s potential
positive and adverse effects on the Indigenous Peoples in the case that Indigenous Peoples are present in, or
have collective attachment to the project area (based on the screening in accordance with the four criteria as
specified in the World Bank OP 4.10 and criteria on Masyarakat Adat and/or local values), and to examine
sub-project alternatives where adverse effects may be significant. The breadth, depth, and type of analysis in
the SA are proportional to the nature and scale of the proposed sub-project’s potential effects on the
Indigenous Peoples, whether such effects are positive or adverse. In carrying out an SA, the village
government will have to be assisted by the PD, a consultant team or individuals who are social scientist whose
qualifications, experience, and terms of reference are acceptable to the PIU or Pokja of the district. Experts
from local universities or local NGOs who have worked and have experienced in working with the IPs are
encouraged to assist the village government.
2. Outline of the SA. The SA will at least cover the following:
a. Description of sub-project Activity
b. Information about the Subproject Activity’s site and condition of the cultural community
c. Social Economic Characteristics of the affected Indigenous Peoples’ community
i. General Characteristics of IPs
ii. Specific characteristics of IPs
• Cultural Social Institutions
• Economic Condition and Source of livelihood for villagers
• Cultural practices
• Etc.
iii. Stakeholders assessments
d. Consultation process during the Social Assessment reflecting a free, prior and informed
consultation that leads to broad support from the affected IPs community on the proposed sub-
project activity.
e. Findings and potential sub-project activity’s impacts (positive and adverse).
i. Any potential negative (give examples)
• Economic domination by outsiders
• Transfer of ulayat rights
• …
ii. Proposed Mitigation (give example)
• Mitigation related to domination by outsiders
• …
iii. Potential positive impacts and efforts to maximize these impacts
f. Proposed Action Plans in form of a Table containing (to be included in the Draft IPP):
i. Plan to maximize the positive impacts
ii. Negative issues as findings from the study which needs mitigation
iii. The mitigation measures
iv. Subproject Activities within the mitigation framework
v. Location where the impact and mitigation are going to be done
vi. Consultation framework for preparing and implementing IPP
vii. Institution in charge for preparing and implementing IPP
viii. Schedule for implementation
ix. Budget
x. Source of budget
xi. Remarks (other matters that need to be put in the report)
98
ANNEX 15: FORMAT OF INDIGENOUS PEOPLES PLAN (IPP)
The following template presents the outline of an IPP. The template can be further developed based on field
conditions and as per characteristics of the Project Activity.
Title of Chapter/Sub-
Chapter
Content/Remarks
1. DESCRIPTION OF THE PROJECT
Summary Description of sub-project activity (concerning area boundary, location, type of
occupation, area size, area of influence, etc.)
2. SUMMARY OF SOCIAL ASSESMENT
2.1. Baseline Data on IPs
• Baseline information on the demographic, social, cultural, and political characteristic of the IPs
community, the land and territories traditionally owned or customarily used or occupied and the
natural resources that they depend
• Identification of key project stakeholders and elaboration of culturally appropriate process for
consulting with the IPs at each stage of project cycle
2.2. Summary of results of the free, prior, and informed consultations with the affected
Indigenous Peoples’ communities that was carried out during Project Activity’s preparation
and led to broad community support for the Project Activity
• Identification of potential adverse and positive effects of sub-project activity of the affected IPs
within the sub-project activity’s area of influence
• Development of measures necessary to avoid adverse effects or identification of measures to
minimize, mitigate, or compensate for such effects and ensure that IPs receive culturally
appropriate benefits from the sub-project activity
• Mechanism to prepare and implement the public consultation with the Indigenous People
(consultation concerning the draft sub-project activity plan, etc. as relevant), to include:
determination of location and schedule of consultation, information dissemination /invitation,
etc.
• Public consultation process
• Result/resolution and mutual agreement obtained during consultation meeting.
• Number and representative of organization/institution presented by participants in the said
consultation meeting.
2.3. A framework for ensuring the free, prior, and informed consultations with the affected
IPs communities during project implementation
3. ACTION PLAN (INPUTS FROM THE RESULTS OF THE SOCIAL ASSESSMENT)
3.1. Activities for IPs to receive social and economic benefits
3.2. Activities to avoid, minimize, mitigate, or compensate for adverse effects
3.3. Measures to Enhance the Capacity of the Project Management
3.4. Consultation with the affected IPs on the Draft IPP
4. COST ESTIMATE AND FINANCING PLAN
In form of table containing information about: type of activity, party in charge, timeline/milestones,
cost, funding source, and remarks.
5. INSTITUTIONAL ARRANGEMENT TO IMPLEMENT IPP
• Agencies responsible for managing the implementation of the Indigenous Peoples Plan
• Agencies (such as TPK) responsible for reporting and monitoring on the implementation of the
Indigenous Peoples Plan
• Arrangements for monitoring of the implementation of the Indigenous Peoples Plan by the
affected IPs
6. GRIEVANCE REDRESS MECHANISM ACCESSIBLE TO THE AFFECTED IPs
99
Title of Chapter/Sub-
Chapter
Content/Remarks
• Mechanism for managing grievances as suggested by the results of the Social Assessment
results
7. PROJECT MONITORING, EVALUATION, AND REPORTING OF IPP
IMPLEMENTATION
Includes arrangement for free, prior, and informed consultation with the affected IPs
• Explaining the Work Plan for monitoring implementation of IPs and Reporting Mechanism.
• Monitoring on progress implementation of IPP
• Monitoring on process implementation of IPP
• Reporting on implementation of (report to whom, which format to use, and deadline for
submission of the report).
ATTACHMENT
Attach original or copy of documents as relevant to IPP, for example:
• Information about the sub-project activity (Map)
• Table containing Baseline Data of IPs
• Minutes of Dissemination and Consultation Meetings
• Minutes of Agreement on Compensation Plan (if any) based on the consultations
• Other relevant documentation
100
ANNEX 16: MINUTES OF CONSULTATION MEETING WITH IPs
Name of sub-project activity :
Date/ Month/ year :
Time :
Place :
Socialization/Dissemination of information about Project Activity
• Project Management should carry out information dissemination to the IPs concerning the objective and benefit of
the sub-project activity in detail and including any potential positive and negative impacts, physical and non-physical
due to the sub-project activity. The territorial boundary for such scope of impact in particular, should be defined.
• Project Management should inform the IPs of the IPP.
• Project Management should provide maps, designs and other related materials for sub-project activity.
• It is recommended that socialization and consultation are done in a manner that is culturally acceptable by the IPs
community and local language is used, as appropriate.
Consultation
• The village government of TPK should encourage IPs to actively participate in the discussions during the
consultation meetings.
• The overall question-and-answer and recommendation/conclusions should be recorded in this Minutes of Meeting.
Summary of the meeting:
• …….
• ……
Representatives agreed on the Minutes
No
Name of the
Community
members
Job position Signature
1 Head of Tribe
2 Head of Village
3 Head of Hamlet
4
5
Attachment
• Full attendance list
• Photo documentation
101
ANNEX 17: NOTES ON FREE, PRIOR AND INFORMED CONSULTATIONS (FPIC)
2. Indigenous Peoples or Masyarakat Adat (Customary Communities) may be vulnerable to the loss of,
alienation/resettlement from or exploitation to natural and cultural resources. IPs communities are often among the
poorest of the poor in the community and closely tied to their settlements, lands and related natural resources upon which
the sustenance of their livelihoods depends. Frequently, these lands and settlements are traditionally owned or under
customary use and often not legally recognized by national laws. In recognition of this vulnerability, interventions
introduced through this project with the objectives to improve land administration and address informal settlements may
potentially alienate and/or displace IPs if the mechanisms for Free, Prior and Informed Consultations (FPICs) to obtain
broad support are not built into project design and implementation.
3. Objective. The extent, frequency and degree of engagement required by the consultation process should
commensurate with the identified project risks and adverse impacts and with the concerns raised by affected IPs. FPICs
are built on mutually accepted process between affected communities and project actors. FPICs serve at least two
purposes:
a. Provide a platform to undertake a process of consultations in good faith and in a manner that provides
affected IPs with opportunities to express their concerns and views on the sharing of development benefits,
risks, impacts, and mitigation measures and explore ways to leverage culturally and socially acceptable
benefits.
b. Provide a two-way mechanism for village apparatus especially the TPK to engage with IPs and their
organizations, including Adat councils, community groups to consider and respond to the views and concerns
expressed by affected IPs prior to project execution.
4. Procedures. FPICs should be orientated towards obtaining broad community support and by which, broad
community support consists of a collection of expressions by affected community members and/or their recognized
representatives in support of the proposed project/sub-project activities. Although FPICs do not necessarily require
unanimity and in some instances, decisions may be achieved even individuals or groups within the community disagree,
FPICs lay out organized and iterative processes through which decisions and measures adopted by the project incorporate
the views of the affected IPs on matters that affect them directly.
5. The Community Participation Framework needs to be built on gender-sensitive and inter-generationally
inclusive approaches. Effective FPICs are built upon two-way processes that should:
a. Involve members of affected communities and their recognized representative bodies and organizations in
good faith.
b. Capture the views and concerns of men, women and vulnerable community segments including the elderly,
youth, displaced persons, children, people with special needs, etc. about impacts, mitigation mechanisms,
and benefits where appropriate as reflected in sub-project design. If necessary, separate forums or
engagements need to be conducted based on their preferences.
c. Begin early in the process of identification of environmental and social risks and impacts and continue on
an ongoing basis as risks and impacts arise.
d. Be based on the prior disclosure and dissemination/socialization of relevant, transparent, objective,
meaningful, and easily accessible information which is in a culturally appropriate language(s) and format
and is understandable to affected IPs. In designing consultation methods and use of media, a special
attention needs to be paid to include the concerns of Indigenous women, youth, and children and their
access to development opportunities and benefits.
e. Focus on inclusive engagement on those directly affected than those not directly affected;
f. Ensure that the consultation processes are free of external manipulation, interference, coercion and/or
intimidation. The ways the consultations are designed should create enabling environments for meaningful
participation, where applicable. In addition to the language(s) and media used, the timing, venues,
participation composition need to be carefully thought through to ensure everyone could express their
views without repercussions.
g. Be documented
6. In deciding whether to proceed with the sub-project, the PTPD, PD and PLD ascertains on the basis of social
assessment and FPICs whether affected IPs provide their broad support to the project. Where there is such a support, the
TPK should prepare:
a. Documented evidence of FPICs as well as measures taken to avoid and minimize risks to and adverse
impacts of the affected IPs. This includes list of participants, meeting minutes and other documentation
(e.g. photos, video, etc.);
102
b. Additional measures, including project design modification, alternative locations, and where applicable
compensations to address adverse effects on affected IPs and to provide them with culturally and socially
appropriate benefits;
c. Action plan and recommendations for FPICs during project implementation, monitoring, and evaluation,
and
d. Any formal agreements reached with affected IPs and/or their representative organizations.
7. The PIUs and the World Bank will review the process and the outcome of the consultation carried out by the
village apparatus and TPK with supervision from the facilitators (PD and PLD) to confirm that the affected IPs have
provided their broad support to the project. The PIU will not recommend the village or TPK to proceed further with
project processing if it is unable to ascertain that such support exists.
8. Requirements. To ensure that FPICs can be ascertained, the following requirements are needed to determine
whether:
a. The level of engagement in a way that enables informed participation of affected IPs is acceptable;
b. The level of support and dissent among affected IPs for the project is taken into account into decision
making and development of mitigation measures.
Consideration Requirements
Project’s strategy and principles on
engagement
- Community Participation Framework to mainstream FPIC;
- Project Operational Manuals on FPICs;
- Budget and personnel provisions;
- Consultation schedules and other supporting documentation.
Stakeholder identification and
analysis - Stakeholder analysis as part of the Social Assessment;
Community Engagement - Consultation plan, public consultation and disclosure plan, and
stakeholder engagement plan;
- Schedule and record of community engagement including discussions
and consultations with community members and their representatives.
Information disclosure - Disclosure plan, including schedules
- Materials prepared for disclosure and consultations;
- Record/minutes of discussions/consultations with community members
and their representatives
Free, Prior, and Informed
Consultations
- Record/minutes of discussions/consultations with community members
and their representatives;
- Documentation of measures taken to avoid/minimize risks to and
adverse impacts on affected IPs based on community feedback;
- Draft of Action Plan;
Consultations with vulnerable
groups
- Engagement and public consultation plan
- Record/minutes of discussions/consultations with members and
representatives of vulnerable groups
- Documentation of measures taken to avoid/minimize risks to and
adverse impacts on vulnerable groups based on community feedback
- Draft of Action Plan
Grievance redress mechanism - Organizational structure and responsibilities and procedures to manage
grievances;
- Record of grievances received, including expressions of support or
dissent;
- Record/minutes of discussions with community members or
representatives with regards to grievance redress.
Feedback to affected IPs (to
demonstrate that concerns and
recommendations have been
accommodated in the project and
rationale why recommendations
have not been accommodated)
- Documentation of risk mitigation measures
- Record/minutes of discussions with community members and their
representatives;
- On-going reporting on implementation of Action plan;
- Revisions in project/sub-project activities and Action Plan;
- Surveys/interview records of affected IPs.
Formal expressions of support or
dissent
- Record/minutes of meetings/public consultations with community
members and their representatives;
103
Consideration Requirements
- Formal letters/written petitions of support/objection submitted by the
community and/or their representatives;
Informal expressions of support or
objection - Photographs, media reports, personal letters or third-party accounts
(NGOs, CBOs, etc.)
Evidence of good faith
consultations
- Face-to-face interviews with community members/representatives in the
consultations;
- Agreements reached with affected IPs (e.g. MoU, Letters of Intent, Joint
Statements, etc.)
- Action plan, e.g. benefit sharing, development plan, etc.
104
ANNEX 18: LIST OF DISTRICTS WITH POTENTIAL IPS PRESENCE
No. Provinces Districts with Potential Indigenous Peoples Presence
1 Central
Kalimantan
Barito Selatan, Barito Timur, Barito Utara, Gunung Mas, Kapuas, Katingan, Kotawaringin
Barat, Kotawaringin Timur, Lamandau, Murung Raya, Sukamara
2 North Maluku Halmahera Barat, Halmahera Selatan, Halmahera Timur, Halmahera Utara, Kepulauan Sula
3 East Java Banyuwangi, Bojonegoro, Bondowoso, Magetan, Ponorogo, Sumenep. Trenggalek,
Tulungagung
4 Jambi Bungo, Merangin, Muaro Jambi, Sarolangun, Tanjung Jabung Timur, Tebo
5 West Sulawesi Majene, Mamasa, Mamuju Utara, Mamuju
6 Lampung No identified IPs
7 Bengkulu Bengkulu Selatan, Bengkulu Utara, Kaur, Lebong, Seluma
8 West Java Ciamis, Cianjur, Garut, Majalengka, Sukabumi, Sumedang, Tasikmalaya
9 Central Java Cilacap, Demak, Pati, Semarang
10 West
Kalimantan
Bengkayang, Kapuas Hulu, Landak, Melawi, Pontianak, Sambas, Sanggau, Sekadau,
Sintang
11 North Sulawesi Bolaang Mongondow, Kep. Sangihe, Kep. Talaud, Minahasa Selatan, Minahasa Utara
12 South Sulawesi Bantaeng, Barru, Bulukumba, Enrekang, Luwu Utara, Luwu, Maros, Palopo, Sidenreng
Rappang, Soppeng, Tanah Toraja, Wajo
13 West Nusa
Tenggara
Bima, Dompu, Lombok Barat, Sumbawa Barat, Sumbawa
14 East Nusa
Tenggara
Alor, Belu, Ende, Flores Timur, Kupang, Lembata, Manggarai Barat, Sikka, Sumba Barat,
Sumba Timur, Timor Tengah Selatan, Timor Tengah Utara
15 Bali Bangli, Karangasem
16 Bangka
Belitung
Bangka Barat, Bangka Selatan, Bangka Tengah, Bangka Timur, Belitung
17 Banten Lebak, Pandeglang
18 Gorontalo Boalemo, Bone Bolango, Gorontalo
19 South
Kalimantan
Balangan, Banjar, Hulu Sungai Selatan, Hulu Sungai Tengah, Kota Baru, Tabalong, Tanah
Bumbu, Tanah Laut, Tapin
20 East
Kalimantan
Berau, Kutai Barat, Kutai Kertanegara, Kutai Timur, Pasir
21 Riau Islands Bintan, Karimun, Lingga
22 Maluku Buru, Kepulauan Aru, Maluku Tengah, Maluku Tenggara Barat, Seram Bagian Barat
23 Riau Bengkalis, Indragiri Hilir, Indragiri Hulu, Kep. Meranti, Pelalawan, Rokan Hilir, Rokan
Hulu, Siak
24 Central
Sulawesi
Banggai Kepulauan, Banggai, Donggala, Morowali, Parigi Moutong, Poso, Tojo Una-Una,
Toli-Toli
25 South East
Sulawesi
Bombana, Buton, Kolaka Utara, Kolaka, Konawe Selatan, Konawe, Muna, Wakatobi
26 West Sumatera Kepulauan Mentawai, Lima Puluh Koto, Pasaman
27 South Sumatera Banyuasin, Lahat, Muara Enim, Musi Banyuasin, Musi Rawas, Ogan Ilir, Ogan Komering
Ilir, Ogan Komering Ulu, OKU Selatan
28 North Sumatera Deli Serdang, Humbang Hasundutan, Langkat, Mandailing Natal, Nias Selatan, Pakpak
Bharat, Serdang Bedagai, Simalungun, Tapanuli Selatan, Tapanuli Tengah, Tapanuli Utara,
Toba Samosir
29 DI Yogyakarta No identified IPs
30 North
Kalimantan
Nunukan, Bulungan, Malinau
*) List of names and locations of IPs in the village level is included in the World Bank Study on IPs Screening (2010)
105
ANNEX 19: CHANCE FINDS PROCEDURES
1. Definition. A chance find is archaeological, historical, cultural, and remain material encountered unexpectedly
during project construction or operation. A chance find procedure is a project-specific procedure which will be followed
if previously unknown cultural heritage is encountered during project activities. Such procedure generally includes a
requirement to notify relevant authorities of found objects or sites by cultural heritage experts; to fence off the area of
finds or sites to avoid further disturbance; to conduct an assessment of found objects or sites by cultural heritage experts;
to identify and implement actions consistent with the requirements of the World Bank and Indonesian law; and to train
project personnel and project workers on chance find procedures. In the contract agreement with the contractor, there
must be provisions and guideline concerning what measures must be taken if these artefacts and structures are found
within the sub-project site.
2. Objectives.
a. To protect physical cultural resources from the adverse impacts of project activities and support its preservation.
b. To promote the equitable sharing of benefits from the use of PCR.
3. Procedure. If the subproject activity discovers archeological sites, historical sites, remains and objects,
including graveyards and/or individual graves during excavation or construction, shall:
a. Halt the construction activities in the area of the chance find;
b. Delineate and fence the discovered site or area;
c. Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities or sensitive
remains, a night guard shall be arranged until the responsible local authorities or the District/Provincial Department
of Culture, or the local Institute of Archaeology if available to take over;
d. Forbid any take of the objects by the workers or other parties;
e. Notify all subproject personnel (i.e. sub-project workers, Tim Pelaksana Kegiatan or TPK, local agency responsible
for the protection of physical cultural resources) of the finding and take the preliminary precaution of protection;
f. Record the chance find objects and the preliminary actions;
g. Notify the responsible local authorities and the relevant Institute of Archaeology immediately (within 24 hours or
less);
h. Responsible local authorities would be in charge of protecting and preserving the site before deciding on subsequent
appropriate procedures. This would require a preliminary evaluation of the findings to be performed by the local
Institute of Archaeology. The significance and importance of the findings should be assessed according to the various
criteria relevant to cultural heritage; those include the aesthetic, historic, scientific or research, social and economic
values;
i. Decisions on how to handle the finding shall be taken by the responsible authorities. This could include changes in
the subproject layout (such as when finding an irremovable remain of cultural or archeological importance)
conservation, preservation, restoration and salvage;
j. Implementation for the authority decision concerning the management of the finding shall be communicated in
writing by relevant local authorities;
k. The mitigation measures could include the change of subproject design/layout, protection, conservation, restoration,
and/or preservation of the sites and/or objects;
l. Construction work at the site could resume only after permission is given from the responsible local authorities
concerning safeguard of the heritage; and
m. The subproject proponent responsible to cooperate with the relevant local authorities to monitor all construction
activities and ensure that the adequate preservation actions already taken and hence the heritage sites protected.
4. Requirements. The TPK should include the chance finds procedure in the Work Plan or community’s contract.
106
ANNEX 20: NOTES FROM PUBLIC CONSULTATIONS OF THE ESMF
Public Consultation on Draft Environmental and Social Management Framework
Institutional Strengthening for Improved Village Service Delivery Project (P3PD)
14 – 15 January 2019
Day 1, 14 January 2019
Talk Show Session: Strengthening the Village Government and Development towards an Increased Quality of Village
Expenditures
Resource Persons:
1. Deputy for Regional Development, Bappenas
2. Director General of Village Development, Ministry of Home Affairs (represented by the Secretary of the
Directorate General)
3. Director General of Village Community Development and Empowerment, Ministry of Village, Development of
Disadvantaged Regions and Transmigration
Q&A and Discussion:
1. DPMD Barito Kuala Regency (Batola)
- In the learning of modules for village facilitators, the principles of equality and openness including gender
equality and partiality for the poor, have been applied. This must be strengthened by technical instruments up
to the level of planning and implementation of the village development program.
2. DPMD Central Kalimantan Province
- The village development programs that include physical investment should be able to consider environmental
and social aspects. We agree with the aim of integrating environmental and social management framework in
all village development guidelines and modules.
- Through this program, capacity building must be measurable and sustainable. If this program is completed, it is
expected that the trained human resources will be able to transfer their knowledge to other village facilitators
and village communities in general.
107
Day 2, 15 January 2018
SESSION 1 - Explanation of Components of the P3PD Activities Program
Materials:
1. Strengthening of Village Government Institutions and Strengthening of Village Government Performance by
the Director of Facilitation of Capacity Development for Village Apparatus, Ministry of Home Affairs (MoHA)
2. Promoting Participatory Village Development by the Director of Village Community Development, Ministry of
Village (MOV)
3. National Level Coordination, Supervision and Monitoring by the Director of Disadvantaged Regions,
Transmigration, and Rural Areas, Bappenas
Resource Persons:
1. Mr. Endang Basuni (MoHA)
2. Ms. Evi (MoV)
3. Mr. Sumedi (Bappenas)
Moderator: Ms. Lily (World Bank)
Mr. Endang Basuni (Ministry of Home Affairs): P3PD Component 1
- There are 62 selected districts participating in this consultation. It is important for all parties to understand what
is and what are the objectives of environmental and social management and to subsequently integrate them into
the program.
- There are 4 components of P3PD, as follow:
1. Strengthening village government institutions.
2. Promoting participatory village development.
3. Improving village performance.
4. National monitoring coordination and supervision.
- Components 1 and 3 P3PD are to be managed by Ministry of Home Affairs’ DPMD, Component 2 by MOV,
and Component 3 by BAPPENAS. Some of the objectives of the P3PD Program are:
1. How to improve the performance of the government and village apparatus through capacity building
systems based on demand and needs.
2. Improvement of community assistance system.
3. Management of a performance-based incentive transfer system.
4. Technology-based village governance information system to improve village performance.
- In the end, it is hoped that the P3PD can help improve the quality of village spending as expected to improve
the quality of life of the community.
- Related regulations have been established including: Village Law UU No. 6, Government Regulation PP No.
43 that has been revised to PP No. 47, Ministry of Village Regulation that oversees village development, and
there is also the Regulation of Head of LKPP regarding the execution of APBDes implementation process.
- Portrait of the day, from almost 75,000 villages, not all of them have prepared RPJMDes properly as a base for
APBDes allocation for the village development program implementation. MoHA Regulation No. 66/2014 is to
support village governments to be able to exercise their authority. This will affect the planning process of the
RPJMDes and RKPDes into the village budgeting process. At present, there are still many villages that carry
108
out activities that are not within their authority. Many of the districts have not responded to the order of Regent
Regulation (Perbup) regarding village authority.
- The P3PD program is expected to address such matters. It is hoped that in the future all districts will immediately
establish a list of village authorities so that the village can follow up with village regulations towards an
accountable APBDes. Especially considering the funding sources provided to the villages that reaches the
amount of IDR 450 trillion. This must be accompanied by the readiness of adequate capacity of the village
apparatus.
- Three challenges in village governance:
1. Regulations that are not aligned, and the roles and responsibilities of stakeholders that are not integrated
have an impact on well-structured and measurable patterns of guidance and supervision.
2. Village Government human resources in carrying out the functions of:
– Planning and budgeting, implementation, reporting and accountability,
– Results in village expenditure that has not been able to contribute optimally to the four areas of
authority in the village.
3. Development and supervision that have not been optimally implemented by the village authorities or
supra desa.
- Many cases were found where the village did not conduct a development and supervision or binwas due to
unavailability of budget. There has been a revision of Permendagri No. 38/2018, which regulates the budget for
developing village administration. The role of binwas is to guard. Capacity in sub-districts will be strengthened
through the role of village technical facilitators in the sub-districts.
Ms. Evi (Ministry of Village): P3PD Component 2
- Current conditions, of the 500 districts/cities not half of them have established the regulation of Perbup regarding
the List of Village Authorities. As part of capacity building, this will be facilitated through technical guidance
and training.
- The Ministry of Village's specific activity in the P3PD Component 2 is to encourage a participatory village
development. The village consultative forum (Musyawarah Desa or Musdes) and village development planning
forum (Musyawarah Perencanaan Pembangunan or Musrenbang) does not only involve the village government,
but also the village representative council (Badan Permusyawaratan Desa or BPD) and community elements.
How to increase the capacity of these elements in synergy and balance.
- The unavailability of budget allocation from the Provincial or District Budget for training of the BPD. This is a
big homework and is still has a long way to go. It is expected that the program activities can address this issue.
- The general objective of Component 2 is to build the capacity of village community and community groups to
be able to improve the quality of achievements of village development. In order to achieve quality development,
achievements must be measurable.
- We have comprehensive data regarding the use of village funds. Most village funds are used for infrastructure.
The problem is, can the results of this utilization show an increase in the progress of the village development?
To measure the village development progress, we need to have reliable data and information regarding the social
and economic conditions in the village. The Component 2 will also help to address this issue.
- Specific objectives of Component 2 are to strengthen systems of capacity support and village development
within MoV. This will be achieved by revamping and supporting programs within MoV to be more flexible and
adaptable to better respond to the needs, and to facilitate innovation and cross learning for community capacity.
This component is divided into the following sub-components.
- Specific objectives of Sub-component 2A are:
1. Improving the village support service by building the competency of village facilitators using digital
tracking systems, improving learning media, and adopting digitally-based applications (GoDesa);
2. Encouraging the simplification of village development guidelines and regulations to strengthen the
implementation of participatory development in villages
109
- Activities under Sub-component 2A includes:
1. Technical assistance to support to the design and development of the GoDesa PLD digital application
for facilitator management.
2. Updating and digitizing capacity building modules and programs for village facilitator training.
3. Monitoring the performance of delivery systems for capacity building, facilitator support, etc.
4. Supporting technical assistance for harmonization of regional regulations.
- The specific objectives of Sub-component 2B is to improve the quality of community participation and social
accountability in village development governance. Activities under this subcomponent will focus on improving
the performance of community cadres and the development of community learning centers.
- Activities under Sub-component 2B includes:
1. Improving the performance of community cadres and the development of community learning centers.
Strengthening of village cadres, or community volunteers, with a view to reactivate their role in village
development.
2. Continued technical support to Community Learning Centers, including development of peer-to-peer
exchanges, “people’s schools” (Sekolah Rakyat), joint learning activities and facilitated interactions.
These programs were developed under the Village Innovation Program and would be further supported
and replicated across all participating villages.
3. Develop social accountability monitoring mechanisms that, alongside the reactivation of cadres, is
expected to improve the quality of participation and accountability in village governance
All activities in subcomponent 2B will be digitally integrated in stages through the community learning system
Akademi Desa 4.0, which will be developed under component 2C.
- Subcomponent 2C focuses on the development and deployment of digital systems for improved village
innovation and development.
- Activities under Sub-component 2C includes:
1. Establish a digital community learning platform (Akademi Desa 4.0).
2. Develop a smart village digital system as a platform to accommodate and disseminate learning
materials and knowledge to village communities.
3. Develop and implement a modern electronic system for recording/monitoring procurement, payment
transactions and performance.
- There are 8 locations for training centers so far, and although the trainings have been carried out throughout
during 2015-2018, the target has not been achieved, it has only reached 1,360 villages out of the entire villages
in Indonesia. Through the Akademi Desa, the capacity building of community and facilitators in all villages will
be faster.
- Specific Objectives of Sub-component 2D are:
1. To manage the integration of work plans and realization of annual activities, based on proposals from
each directorate involved in Component 2.
2. To ensure the roles, functions and responsibilities of each directorate to carry out Component 2
activities in accordance with the responsibilities and work plan.
3. To ensure the availability of budget allocations and technical assistance needed by each directorate in
carrying out their activities, including the availability of Rupiah murni.
4. To integrate input into required reporting, both in Management Information Systems (SIM) and other
reports, for example Interim Financial Report (IFR).
110
- The program structure of Component 2 is as follows:
Mr. Sumedi (Bappenas): P3PD Component 4
- Village development is part of socio-economic and cultural transformation. In this transformation, it is important
for us to push for a change from comparative advantage into a competitive advantage.
- The objective of the Component 4 is to improve and strengthen national coordination, harmonization of
regulations, monitoring, and supervision of village development. This will be achieved through the
establishment of a National Coordination Platform under the project. This platform would be chaired by the
Coordinating Ministry for Human Development and Cultural Affairs (Kementerian Koordinator Bidang
Pembangunan Manusia dan Kebudayaan, Kemenko PMK), and would be supported by a Secretariat under
BAPPENAS, who would oversee the management and coordination efforts, and the integrated information
system.
- Component 4 will provide for the development of an Integrated Data and Information Systems on Villages
(InfoDesa), including the provision of technical assistance, procurement of hardware and software, preparation
of procedures for collecting, verifying and integrating various village data systems, and data analysis by various
stakeholders (i.e. a dashboard). Detailed descriptions of InfoDesa will be developed in the General Guidelines
and the Project’s Technical Guidelines.
- The current challenge is basic services and public services that still need to be addressed. Bappenas will
encourage transformation through:
1. Improvement and simplification of regulations, for example the village financial report into just one
sheet that covers reporting on what outputs have been achieved, what is used for, etc.
2. Development of integrated data and information systems. The latest BPS data, the 2018 Podes, shows
some improvements. The basic service performance index has improved, infrastructure also increased
by 4% even though it is still below 50%, transportation has been above 50%, and public services have
only increased slightly but have also been above 50%, village administration has shown improvements.
3. Knowledge is also important to manage, in addition to data and information.
4. Improvement of basic infrastructure.
5. Strengthening the role of the sub-district. For example, in Japan, sub-districts are the spearhead of
development. It is hoped that improvements can be realized through this program cooperation with the
World Bank.
6. Capacity building of the apparatus, how to strengthen village and sub-district officials as part of the
changes.
111
- Our task is to manage these changes from the village to grow and then become independent. Once they have
become independent villages, the challenge of the next 5-10 years is whether the village will remain a village
or become a village characterized by a city with the development of facilities and infrastructure.
- This component would also finance the formal establishment of a National Coordination Platform for Village
Development. This platform would be chaired by Coordinating Ministry for Human Development and Cultural
Affairs (Kementerian Koordinator Bidang Pembangunan Manusia dan Kebudayaan, Kemenko PMK), and
would be supported by a Secretariat under BAPPENAS, who would oversee the management and coordination
efforts, and the integrated information system. Finally, this component would support evaluations, including
impact evaluations, of the program’s interventions.
Q&A and Discussion:
1. DPMP Kabupaten Kupang, Bapak Yohanes
- The role of facilitation and supervision: internal supervision (inspectorate) is still inadequate and the scope of
the audit is very broad, includes all OPDs, schools, health centers, sub-districts, and the 160 villages spread
across 24 sub-districts in Kupang District. Auditors are still very limited, compared with the village budget that
needs to be audited. Many villages have not been audited for several years, unless there is a special request. If
there is no request, it is considered as operating well without problems.
- Sub-district facilitators: there are verification team and assistance team but there are still limitations in terms of
capacity, facilities and infrastructure, so that improvements are needed.
- Digitizing the village: this is a big problem because the telecommunications network in Kupang is not all over
reliable.
- Village facilitators: the capacity of recruited facilitators is inadequate, especially in regards to knowledge about
environmental and social management. In addition to the quality of human resources, quantity is still very
insufficient. It is very difficult to reach villages in Kupang with the current ratio of 1: 3 or 1: 4 between
facilitators and villages. It would be very good if the village facilitators could be multiplied and the ratio
increased to 1 per village. Suggestions for nomenclature modification related to Experts (Tenaga Ahli or TA) in
the district to become Faskab or District Facilitators. The expenditure on TA is quite large but the impact to date
is not comparable.
- Until now, village facilitators and technical facilitators have been trained more on data collection than providing
facilitation or facilitating participatory deliberations. Directions are on track but in terms of implementation still
need improvement.
2. DPMD Kabupaten Badung, Bapak Sridana
- The village apparatus and facilitators were overwhelmed with technological innovations which make them quite
confused. Various kinds of regulations issued by the Ministry of Home Affairs and Ministry of Village also
created confusion due to overlapping of authorities in the villages.
- These 4 P3PD Project Components – Component 1 and 3 (Ministry of Home Affairs), Component 2 (Ministry
of Village), and Component 4 (Bappenas) – if not managed properly would have the potential to create more
confusions for the villages.
- Village data must be strengthened: existing village profiles can be improved, so no need to make new ones.
3. DPMD Sumatera Selatan, Bapak Tabrani
- It is important to explore the village's potential. The community and village apparatus must be trained.
Facilitation to apparatus, village facilitators and community must be carried out consequently and consistently.
The Village Head is a policy maker and political apparatus, not a bureaucratic apparatus.
- Akademi Desa must be close to the region. It would be good if the Akademi Desa was built in each province.
Indeed, there will be consequences of budget costs, but this academy will produce a group of people with a
common vision and mission and have a well understanding on the village development program planning and
implementation.
112
4. DPMD Kabupaten Sumbawa, Bapak M. Ikhsan
- Facilitation must be consistent (facilitation to the facilitators and community in the villages). In agreement on
the Akademi Desa, but should be close to the region, there should be an Akademi Desa in each province for
village development cadres.
- In agreement with the concept of developing digital-based villages. Through village digital-based development,
updating and processing data will become easier.
- Back to the village's main task in accordance with Law No. 6/2014: governance, development, community and
empowerment. Prioritized use of village funds should not be determined by just one institution but shall be
because of the synergy of various related institutions.
- Status of village development, we need to synchronize one index that can describe village development status up
to the independent village level.
- To strengthen the villages, the strengthening of the BPD should always be carried out in the development of rural
areas.
Response from Resource Persons:
1. Bappenas
Regarding the data, it has been agreed with the Ministry of Home Affairs and Ministry of Village to determine one village
index for the basis of the preparation of development policies and strategies on village development, which will later be
incorporated into the RPJMN 2020-2024 and will be measured annually. With this accurate database there will be 1 data
and 1 map. Coordinate-based village maps will be sought, but beforehand the village boundaries issues must be addressed
first. Institutions must be reorganized. Bappenas as the coordinator will ensure synchronization before the Ministry of
Home Affairs, Ministry of Education and Ministry of Religion issue regulations.
2. Ministry of Home Affairs
All components of the activity program will be utilized to the maximum extent possible for activities in the villages.
Synchronization of regulations based on Joint Decree (Surat Keputusan Bersama or SKB) between 4 Ministries and
coordination are important for the success of all activity components of the program. The program context is so that as
many benefits are received by the village government.
Facilitation is part of the role of binwas. The Ministry of Home Affairs will play a role in the sub-district, village
government and BPD.
3. Ministry of Village
This program will maximize the existing guidelines, technical guidelines or modules, and will not make new instruments.
The environmental and social management aspects will be strengthened through guidelines, technical guidance or
existing learning modules.
The capacity of facilitators is currently inadequate. It is hoped that this P3PD can answer that problem.
Based on PP No. 43 the village's main facilitator is OPD. Despite the availability of professional facilitators, the OPD
facilitators shall not be forgotten. Knowledge transfer will be able to address the issue of current capacity or regulation,
113
SESSION 2 – Integrating the Environmental and Social Management Framework into the P3PD program
Resource Persons:
1. Mr. Beni, Head of Sub Directorate of Capacity Standards, Directorate of Facilitation of Capacity Development
for Village Apparatus, Village Government, Ministry of Home Affairs
2. Mr. Marwoto, Head of Planning Division, Planning Bureau, Ministry of Village
3. Ms. Hindun, Head of Sub-Directorate of Rural Affairs, Bappenas
Moderator: Ms. Indira Dharmapatni (World Bank)
Moderator
This program is an opportunity for stakeholders of the Ministry of Home Affairs, Ministry of Village, Bappenas,
provinces, districts and villages to further strengthen the aspects of environmental and social management into all
program components.
Mr. Beni (Ministry of Home Affairs)
- Regarding the Environmental and Social Management Framework or ESMF, there are 12 main issues, from the
Ministry of Home Affairs side. We will focus on 2 main issues: mainstreaming and integrating the environmental
and social management framework in implementing and achieving the objectives of the P3PD.
- Ministry of Home Affairs is responsible for the implementation of Components 1 and 3. The structure of program
implementing organizations includes PIUs at Bappenas, Ministry of Home Affairs, and Ministry of Village,
which will be supported by management consultants at the national level. Then there is the PIU at the district
level, then Experts at the provincial, district, and sub-district levels, and the Steering Committee that will guide
and provide program direction.
- This ESMF concept framework will not only be a reference and guide at the central level but will also at the
provincial, district, sub-district and village level. The substance of the program will be carried out in each layer
of government. Capacity building will be carried out at all central, provincial, district, sub-district and village
levels.
- The objective of the ESMF development is to provide references and guidance for project management staff at
national, provincial, district, sub-district and village levels, as well as consultants, facilitators, and community
groups involved in the implementation of the Village Law to:
1. Strengthen and integrate environmental and social sustainability appropriately into new instruments
and approaches, such as guidelines, manuals, training modules, etc. This is not new, we have done this
and have considered environmental and social management in the implementation of the development
program so far. For example, in Bali that is very concerned about environmental and social issues,
indigenous peoples, etc. We will integrate this into the instruments that are being prepared in the P3PD
program.
114
2. Screen and identify the potential impacts of environmental and social safeguards from physical
investments financed by village incentives, types of instruments for mitigation measures.
3. Conduct institutional arrangements and capacity building for integrating the environmental and social
sustainability aspects into the project implementation; and
4. Ensure public consultation, disclosure, grievance redress mechanisms are to be disclosed, so that the
public are informed and understand, and can channel complaints regarding environmental and social
issues.
5. Capacity building plan.
6. Monitoring and evaluation.
- If these ESMF aspects along with regulations, guidelines, modules are not integrated and are not understood by
village officials, there are potential risk impacts including planning that is not environmentally friendly, lack of
attention to aspects of disaster/climate change in the planning and implementation of the village development
program. Through this P3PD, we will improve this, so that the environment and social management are integrated
in the regulations, guidelines or modules that will be used for village officials and facilitators.
- The Ministry of Home Affairs as PIU at the central level, the DG of PMD and the balai team have prepared the
relevant regulations and guidelines. Also, in the regions there are regional regulations, guidelines, training
modules in each province, which are expected to accommodate environmental and social issues. Through the
P3PD, the the environment and social management aspects will be integrated into the existing regulations at the
central or regional level.
- There have been efforts to accommodate these issues in central and regional level. Several regulations to ensure
environmental and social sustainability in village development, including Law No. 6, Permendagri No. 114 and
No. 20, training modules, and TOT which have begun to include environmental and social issues in them. Then
also the RPJMDes, RKPDes. We need to encourage all actors in the program planning and implementation to
consider and integrate environmental and social sustainability aspects, so we will be able to reduce the potential
for environmental and social impacts.
- Another issue that needs to be accommodated is planning and budget documents. Does the RPJMDes have the
sense and spirit to strengthen the village community, what about the issues of indigenous peoples, women,
children, people with disabilities, climate change and disaster risk management. Laws relating to indigenous
peoples are being discussed. We must encourage these so that this complements the regulations, training modules,
and all documents to strengthen the capacity of village and institutional apparatus.
- Specifically, Component 1 will include the proposed strengthening of the following elements:
1. Minister of Home Affairs Regulation No. 114/2014 – Village Development Guidelines
Strengthening environmental and social sustainability aspects in the regulations and guidelines, such
as consideration of disaster risk/ climate change mitigation; inclusion of persons with disabilities within
the community; inclusion of indigenous peoples.
2. Minister of Home Affairs Regulation No. 20/2018 – Village Financial Management Guidelines
There are already environmental and social sustainability aspects in the details of the budget, but
specific activities need to be specified that are in accordance with environmental and social
management needs.
3. Training modules for village officials in preparing the RPJMDes, RKPDes and APBDes. Improvement
of environmental and social sustainability aspects, for example: identification and screening of
potential environmental and social impacts/ problems; aspects of disaster and climate change; aspects
of indigenous peoples; preparation of required environmental and social management instruments;
disclosure of information; budgeting for preparation and implementation of the instruments;
monitoring and supervision of the program implementation.
4. It could be also developing a new Technical Guidelines on Environmental and Social Sustainability for
the Implementation of the Village Law by utilizing voluntary learning obtained from the experience of
PNPM-Rural Technical Operational Guidelines implementation.
- Component 3 will be related to the incentive system, including: innovative activities to strengthen regional
economic development, women's empowerment in productivity, small-scale physical infrastructure (with a
115
negative list), innovative technology in small-scale water supply facilities, disability inclusive facilities for
schools and early childhood education centers. We will pay attention and we will assess and measure the
performance of the village and then provide more incentives. Then we will also pay attention to the negative list
in the program instruments, such as the prohibition on the use of hazardous materials (tobacco, pesticides,
asbestos, etc.). This list was also previously used on the PNPM negative list.
- Regarding indigenous peoples, we agree to concentrate on maintaining the existence of indigenous peoples and
we intend for them to get added value and benefits from this program.
- Some general provisions of the ESMF regarding Governance:
1. The responsibility for implementing the entire ESMF is in the Ministry of Home Affairs and Ministry
of Village.
2. The NMC will assist the PIU in screening compliance with the proposed activities and assess impacts
and appropriate mitigation measures. The NMC will discuss these with PIU in the Central and Regional
level.
3. The village government or Activity Implementing Team (Tim Pelaksana Kegiatan or TPK) will be
responsible for screening project proposals by using screening checklists and identifying potential
environmental impacts and mitigation measures.
4. Components 1, 2 and 4 will not involve physical or preparation of any plan that will lead to the
implementation of physical investment but focus on mainstreaming and integrating the environment
and social aspect into the existing guidelines and modules of village development program. Measures
to prevent the environmental impact of electronic waste on the environment and human health can
follow procedures or protocols for electronic waste disposal developed by the Government.
- Some general provisions of the ESMF related to the Principle:
1. Avoid or minimize negative impacts.
2. If negative impacts cannot be avoided, mitigation measures must be taken to minimize the impacts that
transpire.
3. Environmental management, management of indigenous peoples must be based on the principles of
transparency, participation and public consultation not limited to the Regional Government, but also
from local NGOs, academic institutions, and the community.
- Some of the environment and social management instruments are describes in the ESMF and can be used and
adjusted with the local context. We hope that these instruments can be considered by the facilitators in both the
village and the local areas through coordination with technical and village facilitators.
- There is a SAPA complaint handling system in the Ministry of Home Affairs related to issues relevant to the
Ministry of Home Affairs, there was other complaint mechanism system in the past adopted under the PNPM.
Mr. Marwoto (Ministry of Village)
- This Draft of ESMF is the initial concept or initial framework of the P3PD. Suggestions and inputs are highly
expected to make this framework better.
- It is important to know the quality of utilization of village funds. Output can be made but what are the significant
benefits? We must be able to see the gaps. This capacity has not been maximized and must be observed more
profoundly. How can the output and outcome of village funds be maximized? There are other funding sources
and through collaboration with relevant Ministries/Institutions and the World Bank we optimize synergy.
- Village innovation so far has been quite successful. But then, how can the apparatus absorb knowledge from
other villages that are quite successful with regard to village innovation.
- Ministry of Village is responsible for Component 2 of the P3PD. How can we promote participatory process in
the village development? For example, through digital info on GoDesa; digital market technical service provider;
Akademi Desa 4.0; community learning centers; interactive chat portal – such effective 2 directions between the
central and the province can establish communication on village development planning; and Smart Village -
community learning system related to village innovation.
116
- Regarding mainstreaming environmental and social management aspects, for example related to the GoDesa
village digital info platform, how to add information about the environment and social activities including
disaster, indigenous peoples and other matters that have not been previously considered will influence the process
of preparing village development program.
- Akademi Desa 4.0 will consider also environmental and social management aspects, among others, by identifying
potential environmental and soial impacts and problems, include disaster risk management and climate change
aspects into consideration in preparing village development program. There are also community learning centers,
interactive portal that can function as a knowledge-sharing tools.
- We also integrate environmental and social sustainability aspects into the current technical guideline, modules
and as well as other references for priority decision making.
- But the essence of all this is not the module, but how environmental and social management aspects
mainstreaming is included in the module content. So far, environmental and social management aspects have not
been a concern in village development.
Ms. Hindun (Bappenas)
- Component 4 aims to improve and strengthen national coordination, harmonization of regulations, monitoring,
and supervision of village development.
- This will be achieved through the establishment of an integrated information management system that offers real
time incorporation of key metrics for village development under a single information system (InfoDesa). This
information management system will draw on existing data collected through a variety of government agencies,
and will integrate these into a single platform, accessible via a dashboard where data can be visualized by
different levels of government through web and application-based interfaces. Data to be integrated in this
platform may relate to village poverty status, income, health, nutrition, education, existing infrastructure,
exposure to disasters and climate-related hazards (e.g. droughts, floods, storms, coastal inundation, etc.), and
community assets at risk, land and forest fire hotspots and related greenhouse gas emissions, etc. Linkages to
existing real-time data bases (e.g. for disaster early warning, weather forecasts) and indexes (e.g. climate
vulnerability and food security indexes), which are relevant for village-level planning, will be explored.
- Integrated data management system related to digital platforms, Akademi Desa 4.0, InfoDesa. Environment and
Social Sustainability is expected to be included in the central and regional development systems.
- The ESMF implementation should not hamper potential dynamics. It is hoped that the social dynamics of the
government will be managed well to bring forth new innovations in village activities. So that with this dynamic,
environmental mainstreaming can be done in the sustainable development corridor.
Key Notes:
1. Capacity Building is a concern of all parties. This is the key to the 5-year of Village Law Implementation.
2. Mainstreaming of environment and social management aspects is expected not to hamper but instead to improve
the quality of village development. The implementation of the administration on managing or integrating
environment and social management aspects should not be complicated, must be practicable and there must be
standards applicable for all villages.
3. Support is also needed from Bappenas – allocation of funds to each component. Mainstreaming is not only about
methods or instruments, there is also a need for budget allocation to mainstream for strengthen environmental
and social aspects into the relevant regulations, guidelines and modules.
4. These are just the first steps. Detailed technical guidelines in integrating environment and social management
aspects into the village development program require further consultations in the field.
Q&A and Discussion:
1. Balai Pemerintahan Desa Provinsi Lampung, Bapak Effendi
- The lack of social justice in village development still occurs, especially in relation to village spending. There
are tasks that cannot be implemented due to the rules regarding the prioritized use of village funds.
117
- Monitoring and evaluation for the implementation of village development in accordance with the mandate of
the Village Law must be carried out.
2. Pusdatin of Ministry of Village, Bapak Arif
- Based on the MCA-Indonesia project experience, there are three levels of ESMF at MCA-Indonesia (policies,
guidelines and implementation/ instrument). This ESMF will be a binding document through the later
implementation in the field. During the MCA-Indonesia project, farmers in Tanjung Jabung Timur who intended
to build canal blocks must follow the requirements of the ESMF document that had been prepared. Based on the
experiences, preparing SPPL requires a much more expensive cost than the value of the project. The USD 10,000
incentive per village needs to be reviewed more carefully so as not to cause problems related to regulation later,
reflecting on the MCA-Indonesia experience where there are no specific regulations to cover small projects so
that the treatment applied was equated with large- scale projects.
- Matters governing. In agreement with the aim to maximize benefits for indigenous peoples. There have been
several recent regulations that have opened up access for indigenous peoples to forest management. Please
include the regulations in the environmental and social management framework and conduct further review of
the ESMF instrument pertaining to the indigenous peoples.
- Bappeda and Environment Affairs Agency in the regional level must be included in integrating the
environmental and social management aspects into the programs and learning modules.
3. Provinsi Banten, Ibu Enong
- There must be a synergy over the 4 components. The many rules and regulations often create confusion.
- Coordination with OPD. The village should now be able to foster as they have become independent village.
Village is now no longer an object but the subject of development. The role of the province is related to guidance,
coordination and evaluation. We strongly encourage to clearly define village authority, it is hoped that there will
be no overlap between district and village authorities.
- Need to involve the Ministry of Environment in this matter.
4. Asosiasi Pemerintah Desa Indonesia Provinsi Gorontalo, Bapak Habibullah
- Learning from PNPM there was a simpler mechanism, where there was only a list of exceptions for activities
that may not be carried out, the rest can be carried out in accordance with Musdes.
- Environmental issues exist if there is a disaster, it is necessary to include environmental and social management
aspects in developing capacity for village apparatus, village facilitators and village communities, especially
disaster risk management issues.
Response from Resource Persons:
1. Ministry of Home Affairs
Participants agreed to mainstream environmental and social management, but the implementation of mainstreaming shall
not complicate the implementation of the program. There must be environmental and social management instruments
that are adapted to the local context and field conditions in the regions.
Capacity building is important for village officials, village facilitators and village communities. This has been done since
2015 but the target has not been achieved as expected and also requires substantial funds.
Ministry of Home Affairs and Ministry of Village will conduct more technical consultations and discussions with NGOs
or local actors engaged in the environment and social management.
The capacity building modules have considered social aspects including equality and openness. The Ministry of Home
Affairs has also coordinated and invited technical institutions (such as BNPB for disaster aspects, Ministry of ATR/BPN
for land acquisition, etc.) to jointly develop the guidelines and modules.
118
2. Ministry of Village
The preparation of capacity development modules will be done in coordination with governments and actors at the local
level.
3. Bappenas
Bappenas will support coordination at the central level and ensure the integrating environmental and social management
aspects into this program can be carried out by various stakeholders at the central and regional levels.
119
Summary of Results of Public Consultation
Public Consultation on Draft Environmental and Social Management Framework
Institutional Strengthening for Improved Village Service Delivery Project (P3PD)
14 – 15 January 2019
Mr. Imran, Head of Planning Division, Directorate of Village Development, Ministry of Home Affairs
➢ In order to ensure a successful implementation of the Institutional Strengthening for Improved Village Service
Delivery Project (P3PD), the Government of Indonesia prepares an Environmental and Social Management
Framework that refers to the applicable environmental and social management laws and policies in Indonesia.
➢ This public consultation was designed as a participatory process to receive input from stakeholders: relevant
Ministries/Agencies, regional governments, non-governmental organizations, village development practitioners,
observers, and academics in fine-tuning the draft of Environmental and Social Management Framework document
that will serve as guidelines in implementing or integrating the environmental and social management aspects in the
P3PD.
➢ Some of the inputs and suggestions that have been discussed include:
o This environmental and social management framework document is the property of the Government of
Indonesia, which must be carried out as mandated by applicable laws and regulations, especially on aspects
of environmental and social management in village development.
o This program will maximize existing guidelines, technical guidelines or learning modules, and will not
make new instruments. Environmental and social management aspects will be strengthened and integrated
into technical guidelines or learning modules for village apparatus, village facilitators and village
communities.
o It is important to be aware of the practicability of the implementation of the mainstreamed objectives and
principles of the environmental and social sustainability in various manuals, guidelines and training
modules, and the implementation of the safeguards instruments at the village level, given the nature of the
subprojects that are relatively small investments.
o The concept of digital-based village development is impressive. Village profiles and information already
exist but they still cannot be accessed or further processed. This program is expected to facilitate the actors
and beneficiaries to access and process village information digitally, both from the central level to the
regions, to the communities in the village. There is a need to provide environment and social informations
into the digital-based village information.
o The involvement of indigenous peoples in village development is important. There are already several
regulations that regulate in detail the involvement of village community in village development. This must
be included in the technical guidelines and learning modules and their implementation.
➢ Coordination, synchronization and harmonization at the central level will continue to be improved and through the
P3PD program, there have been several components that focus on increasing coordination and synchronization
among stakeholders.
➢ Mainstreaming environmental and social management in technical guidelines or learning modules is important, but
implementation shall not make the implementation of the program complicated. There must be environmental and
social management instruments that are adapted to the local context and field conditions in the regions.
➢ Ministry of Home Affairs and Ministry of Village will conduct more technical consultations and discussions with
NGOs or local actors engaged in environmental and social management and informed of the conditions in the field
to improve environmental and social management instruments that will be implemented in this program.
➢ In the draft ESMF document, there is a statement letter about the willingness of the Regional Government to
implement environmental and social management. The process of discussion related to the agreement of the Regional
Government’s must commence in advance. The draft of this document must be shared to all relevant agencies in the
Regional Government so that it can be understood comprehensively in its implementation.
120
➢ It is hoped that participants attending this first public consultation can attend the next consultations to ensure
continuous delivery of information related to the ESMF through the implementation of the program later.
➢ Suggestions and input (written) regarding the draft ESMF document are highly expected from all participants. The
draft ESMF can be accessed through http://binapemdes.id/informasi
======================================
121
DOCUMENTATION
122
LIST OF ATTENDANCE
123
LIST OF ATTENDANCE
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141