Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General...

82
Environmental and Social Management Framework: Yemen Emergency Crisis Response Project (ECRP) 29 March 2019

Transcript of Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General...

Page 1: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

Environmental and Social Management Framework: Yemen Emergency Crisis Response Project (ECRP)

29 March 2019

Page 2: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

Table of Contents

Acronyms ................................................................................................................................................................ 1

Executive Summary ................................................................................................................................................ 1

1 Introduction .................................................................................................................................................... 5

2 Project Description ......................................................................................................................................... 5

2.1 Description of Baseline Environmental and Socioeconomic Conditions ........................................... 6

2.2 Summary of Key Results and Activities ............................................................................................... 7

2.2.1 PWP Project Component (1.2) ........................................................................................................ 7

2.2.2 SFD Project Components (1.1 and 1.3)........................................................................................... 8

3 Legal and Regulatory Framework .................................................................................................................. 9

3.1 National Legislation, Policies and Regulations .................................................................................... 9

3.1.1 National Environmental Action Plan ............................................................................................... 9

3.1.2 National Biodiversity Strategy and Action Plan .............................................................................. 9

3.1.3 National Water Sector Strategy and Investment Program ............................................................ 9

3.1.4 Water Law ........................................................................................................................................ 9

3.1.5 Environmental Protection Law ...................................................................................................... 10

3.1.6 Labour Law ..................................................................................................................................... 10

3.1.7 PWP and SFD Operating Procedures ............................................................................................ 11

3.2 International Agreements and Protocols .......................................................................................... 11

3.3 UNDP’s Social and Environmental Standards ................................................................................... 11

3.4 World Bank Requirements ................................................................................................................. 12

4 Social and Environmental Impacts .............................................................................................................. 13

4.1 Conflict ................................................................................................................................................ 15

4.1.1 Activities That May Result in Conflict Risks .................................................................................. 15

4.1.2 Management Measures ................................................................................................................ 16

4.2 Gender and Social Inclusion............................................................................................................... 17

4.2.1 Activities That May Result in Gender and Social Inclusion Impacts or Risks .............................. 17

4.2.2 Management Measures ................................................................................................................ 17

4.3 Biodiversity and Natural Resources................................................................................................... 18

4.3.1 Activities That May Result in Biodiversity and Natural Resources Impacts or Risks .................. 18

4.3.2 Management Measures ................................................................................................................ 19

Page 3: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

ii

4.4 Climate Change .................................................................................................................................. 20

4.4.1 Activities That May Result in Climate Change Impacts and Risks ............................................... 20

4.4.2 Management Measures ................................................................................................................ 20

4.5 Community Health, Safety and Working Conditions (including OHS) ............................................. 20

4.5.1 Activities That May Result in Community Health, Safety, Working Condition Impacts and Risks

21

4.5.2 Management Measures ................................................................................................................ 21

4.6 Cultural Heritage ................................................................................................................................ 23

4.6.1 Activities That May Result in Cultural Heritage Impacts and Risks ............................................. 23

4.6.2 Management Measures ................................................................................................................ 23

4.7 Pollution Prevention and Resource Efficiency .................................................................................. 24

4.7.1 Activities That May Result in Pollution and Resource Efficiency Impacts and Risks .................. 24

4.7.2 Management Measures ................................................................................................................ 24

5 Procedures to Address Social and Environmental Impacts ....................................................................... 25

5.1 Sub-Project Screening and Classification Requirements.................................................................. 25

5.1.1 PWP Sub-projects .......................................................................................................................... 26

5.1.2 SFD Sub-projects ............................................................................................................................ 26

5.2 Site-Specific Assessment and Management Requirements ............................................................. 27

6 Institutional Arrangements and Capacity Building ..................................................................................... 27

6.1 General Management Structure and Responsibilities ..................................................................... 27

6.1.1 World Bank ..................................................................................................................................... 27

6.1.2 Project Board (Biannual Review Meetings) .................................................................................. 27

6.1.3 UNDP .............................................................................................................................................. 28

6.1.4 Responsible Parties ........................................................................................................................ 28

6.1.5 Third Party Monitors ..................................................................................................................... 29

6.2 Capacity Building and Training .......................................................................................................... 29

7 Stakeholder Engagement and Information Disclosure .............................................................................. 30

7.1 Principles for Meaningful, Effective and Informed Stakeholder Engagement ................................ 30

7.2 Information Disclosure ....................................................................................................................... 31

7.3 ECRP Systems in Place for Stakeholder Engagement and Information Disclosure ......................... 31

8 Grievance Redress Mechanism ................................................................................................................... 32

8.1 Project-Level Grievance Mechanism ................................................................................................. 32

8.2 UNDP Accountability Mechanism...................................................................................................... 33

8.3 World Bank Inspection Panel ............................................................................................................. 34

Page 4: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

iii

9 Monitoring, Reporting and Evaluation of ESMF Implementation ............................................................. 34

9.1 Management Information System (MIS) .......................................................................................... 34

9.2 Sub-Project Self-Monitoring and Reporting...................................................................................... 35

9.2.1 Social, environmental and OHS incident reporting...................................................................... 35

9.2.2 Daily and weekly inspection checklists ......................................................................................... 35

9.2.3 Corrective Actions.......................................................................................................................... 35

9.2.4 Auditing and Review ...................................................................................................................... 35

9.3 Sub-Project Third-Party Monitoring and Reporting ......................................................................... 35

9.4 Monitoring Plan .................................................................................................................................. 35

Annex 1. Yemen ECRP Revised SES Screening..................................................................................................... 38

Annex 2. Specific Risks and Management Measures by Project Activity .......................................................... 54

Annex 3. Environmental and Social Management Plan - Indicative Outline ..................................................... 70

Annex 4. Guidance for Submitting a Grievance .................................................................................................. 72

Annex 5. OHS Framework .................................................................................................................................... 77

Annex 6. OHS Toolkit ............................................................................................................................................ 77

Annex 7. PWP Operational Manual ..................................................................................................................... 77

Annex 8. PWP Environmental and Social Management Framework (2014) ..................................................... 77

Annex 9. SFD Operational Manual ....................................................................................................................... 77

Annex 10. SFD Phase IV Environmental and Social Management Framework (2014) ..................................... 77

Annex 11. Summary of ECRP ESMF Stakeholder Consultation in Sana’a and Aden ........................................ 77

Annex 12. Third-Party Monitoring Report – ESMF Stakeholder Consultation .................................................. 77

Page 5: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

1

Acronyms

EHS Environmental, Health and Safety

EIA Environmental Impact Assessment

EPA Yemen Public Environmental Protection Agency

EPL Yemen Environmental Protection Law

ESIA Environmental and Social Impact Assessment

ESMF Environmental and Social Management Framework

ESMP Environmental and Social Management Plan

GDP Gross Domestic Product

GIIP Good International Industry Practice

GRM Grievance Redress Mechanism

IDP Internally Displaced Person

ILO International Labour Organization

IPM/IVP Integrated Pest Management / Integrated Vector Management

MFI Multilateral Finance Institution

MIS Management Information System

NBSAP National Biodiversity Strategy and Action Plan

NEAP Yemen National Environmental Action Plan

NGO Non-Governmental Organization

OHS Occupational, Health and Safety

OP World Bank Operational Policy

PAD World Bank’s Project Appraisal Document

PWP Public Works Project

RoY Republic of Yemen

SRM UNDP’s Stakeholder Response Mechanism

SECU UNDP’s Social and Environmental Compliance Unit

SES UNDP’s Social and Environmental Standards

SESP UNDP’s Social and Environmental Screening Procedure

SFD Social Fund for Development

SME Small-to-Medium Enterprise

SMED Small-to-Medium Enterprise Development

SWF Yemen Social Welfare Fund

TPMA Third-Party Monitoring Agent

UN United Nations

UNDP United Nations Development Programme

WHO World Health Organization

YECRP/ECRP Yemen Emergency Response Project

YSMQCO Yemen Standard Metrology Quality Control Organization

Page 6: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

1

Executive Summary

This Environmental and Social Management Framework (ESMF) is prepared by UNDP to ensure the Yemen

Emergency Crisis Response Project (ECRP) is consistent with UNDP’s Social and Environmental Standards

(SES) (www.undp.org/ses) and the World Bank’s Environmental and Social Safeguards Policies. The SES

require that all UNDP projects consider the potential environmental and social opportunities that a project

may generate and ensure that adverse social and environmental risks and impacts are avoided, minimized,

mitigated and managed.

The ESMF is intended to serve as a practical tool to guide identification and mitigation of potential

environmental and social impacts of proposed investments and as a platform for consultations with

stakeholders and potential project beneficiaries. The ESMF identifies the policy triggers for the project, the

screening criteria of sub-projects, the likely environmental and social impacts of the sub-projects and the

mitigation measures to mitigate the identified risks, assessment of the institutional capacity and measures

for capacity-filling gaps.

Although the ECRP is currently in the implementation phase, the ESMF provides a strengthened framework and clarity to ensure consistency with the UNDP SES and World Bank Environmental and Social Safeguards Policies across all sub-projects. The ESMF provides the following:

Description of the project (Section 2): UNDP, in partnership with the World Bank, developed the Yemen

Emergency Crisis Response Project (ECRP) to step up current efforts of the international community to

deliver critically needed livelihood support and service delivery to a population hit hard by the conflict. The

project consists of close to 2,000 sub-projects. Two local institutions are the Responsible Parties: The Social

Fund for Development (SFD) and the Public Works Project (PWP). SFD is responsible for implementation of

labour intensive cash-for-work/social service interventions (approx. 680) in all governorates of Yemen and

small community infrastructure and initiatives (approx. 90); and PWP is responsible for the implementation

of small community infrastructure through local contractors (approx. 1,200). The project aims to mitigate

the impact of the current crisis on local households and communities and assist their recovery from the

bottom-up using local systems, capacities and institutions to progressively resume and scale-up service

delivery. The project will achieve specific results in: 1) Increasing short-term employment and livelihoods

opportunities; 2) Reviving the local private sector; 3) Restoring key service delivery through small-scale

infrastructure.

Overview of the legal and regulatory framework (Section 3): Key national laws and regulations applicable to

social and environmental risk management include the National Environmental Action Plan, National

Biodiversity Strategy and Action Plan, Water Law, Environmental Protection Law, and Labour Law. In the

context of the ECRP, UNDP’s SES and the World Bank’s Environmental and Social Safeguards Policies apply.

In addition, the Responsible Parties (Public Works Project and Social Fund for Development) have elaborated

their own standard operating procedures, that were set up for the World Bank supported projects with the

two institutions prior to the conflict, Environmental and Social Management Frameworks in 2014 and OHS

Framework in 2018. Implementation of these procedures also help to ensure consistency with relevant

international agreements and protocols.

Overview of project activities and key social and environmental risks (Section 4): This section summarizes key social and environmental risks and indicative management measures for the project. The section describes the UNDP social and environmental Principles and Standards that have been triggered based on completion of the project-level Social and Environmental Screening Procedure (SESP, see Annex 1). While the project was initially categorized as Low Risk, the project was recategorized as Moderate Risk following

Page 7: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

2

the 2018 SESP update. As per the World Bank safeguards policy OP 4.01 on ‘Environmental Assessment’ this project is categorized as ‘Category B’. Key risks include those related to human rights and conflict, gender and social inclusion, biodiversity and natural resources, climate change, community health, safety and working conditions (including occupational health and safety), cultural heritage, and pollution. Occupational health and safety risks are identified as a priority. Because a full risk analysis is not possible until site-specific design details are known, the identification of project level risks provides an indicative assessment to be elaborated further through sub-project level screening, assessment and risk management (see Section 5). Therefore, sub-project screening and site-specific assessments and management plans will be essential.

Procedures for screening (Section 5): Each sub-project will be screened for social and environmental risks

and impacts (including OHS risks) applying PWP and SFD screening tools. Screening and classification will be

completed prior to approval of sub-projects and signing of the Financial Agreement. The screening of sub-

projects will also be updated if there are any significant changes in the sub-project’s design or context that

may materially change its social and environmental risk profile. Sub-project screening and categorization

should be conducted at the earliest stage of design when sufficient information is available for this purpose.

Based on the screening, the sub-project is categorized according to the degree of potential social and

environmental risks and impacts (including OHS). The screening process results in a risk-based categorization

of the sub-project (Low Risk, Moderate Risk, or High Risk). Note that High Risk sub-projects will be excluded

from Yemen ECRP funding. If high level risks are identified during implementation, Senior management of

the Responsible Party and UNDP Project Manager will be notified immediately and relevant activities will be

halted until management measures put in place to reduce the levels of risk. An initial gap analysis shows that

PWP and SFD screening processes are generally aligned with SES requirements, as described below.

However, a more detailed gap analysis will be conducted and UNDP together with the World Bank will work

with PWP and SFD to update their screening processes as needed to address gaps and also respond to lessons

learned.

Procedures for assessment and management (Section 5): The targeted and site-specific assessments and

management plans will be undertaken for all Moderate Risk (Category B) sub-projects once project

activities/sub-projects and sites are identified. The assessment(s) will lead to the development of

appropriately scaled management measures and plans to address the identified risks and impacts. Relevant

social and environmental assessments and adoption of appropriate mitigation and management measures

will be completed, disclosed, and discussed with stakeholders prior to implementation of any activities that

may cause adverse social and environmental impacts. Where possible, template simplified ESMPs will be

developed for types of projects and risks for adaptation at the sub-project level. All site-specific assessments

and management plans will be submitted to UNDP and the World Bank for clearance and recorded in the MIS.

In cases where similar activities are being conducted in a particular region, these activities may be grouped

and covered under one site-specific ESMP. All ESMPs will be available upon request.

Institutional arrangements and capacity building (Section 6): The World Bank provides financing for the

project and as such has an oversight role. The World Bank has established a senior management task team

to oversee and make decisions about remedies in connection with the UNDP-implemented activities. The

Project Board (UNDP, World Bank, PWP, SFD) has oversight and advisory authority, representing the highest

body for coordination, strategic guidance, oversight and quality assurance. UNDP will be responsible for

overseeing the implementation and compliance with the ESMF, working closely with PWP and SFD. UNDP

will be responsible for the revision or updates of this document during the course of project, in consultation

with PWP, SFD and the World Bank. During operations the Responsible Parties (SFD and PWP) will be

accountable for implementation of the ESMF. The Responsible Parties are directly accountable to UNDP in

accordance with their Letter of Agreement. Responsible Parties include headquarters offices, branch offices,

Page 8: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

3

site engineers, site supervisors, and workers that also play a role in implementation of the ESMF. A capacity

development plan to ensure ongoing capacity development related to ESMF implementation will be

developed and led by UNDP, working closely with PWP, SFD and the World Bank.

Stakeholder engagement and information disclosure (Section 7): The ECRP and its Responsible Parties will

ensure meaningful, effective and informed stakeholder engagement in the design and implementation of all

sub-projects. Stakeholder engagement supports the development of strong, constructive, and responsive

relationships that are critical for sound project design and implementation. Effective stakeholder

engagement enhances project acceptance and ownership and strengthens the social and environmental

sustainability and benefits of supported interventions. Information disclosure refers to the provision of

timely, accessible information regarding the project and its potential social and environmental impacts to

stakeholders in order to facilitate their meaningful, effective and informed participation in project design

and implementation. Stakeholders require access to relevant project and sub-project information to

understand potential project-related opportunities and risks and to engage in design and implementation. In

addition to have access to general project information, stakeholders need access to screening reports, draft

and final assessments and management plans. This information is to be disclosed in a timely manner, in an

accessible place, and in a form and language understandable to affected persons and other stakeholders.

Meaningful stakeholder engagement is required by PWP and SFD for participation in project intervention by

communities and individuals. The Standard Operating Procedures of both Responsible Parties include

procedures for community and stakeholder engagement within their project cycles as a key component of

project identification, design and implementation, and described a key component of the longer-term

sustainability strategy for operations and maintenance. Stakeholder consultations on the draft ESMF noted

that further stakeholder engagement and information about projects is needed; therefore, the Responsible

Parties Operating Procedures will be reviewed and updated to further strengthen these aspects.

Grievance Mechanism (Section 8): The Project Level Grievance Mechanism is managed by SFD and PWP, who

have their own GRM mechanisms in place. The GRM will be gender- and age-inclusive and responsive and

address potential access barriers to women, the elderly, the disabled, youth and other potentially

marginalized groups as appropriate to the Project. The GRM will not impede access to judicial or

administrative remedies as may be relevant or applicable and will be readily accessible to all stakeholders at

no cost and without retribution. Information about the Grievance Redress Mechanism and how to make a

complaint and/or grievance must be communicated during the stakeholder engagement process and placed

at prominent places for the information of the key stakeholders. All complaints and/or grievances regarding

social and environmental issues can be received either orally (to the field staff), by phone, in complaints box

or in writing to the UNDP, PWP or SFD. A key part of the grievance redress mechanism is the requirement

for the Project Management Team and construction contractor to maintain a register of complaints and/or

grievances received at the respective project site offices, this includes grievances from workers. In addition

to the project-level and national grievance redress mechanisms, complainants have the option to access

UNDP’s Accountability Mechanism, with both compliance and grievance functions. The Social and

Environmental Compliance Unit investigates allegations that UNDP's Standards, screening procedure or

other UNDP social and environmental commitments are not being implemented adequately, and that harm

may result to people or the environment. The Stakeholder Response Mechanism offers locally affected

people an opportunity to work with other stakeholders to resolve concerns, complaints and/or grievances

about the social and environmental impacts of a UNDP project. Stakeholder Response Mechanism is

intended to supplement the proactive stakeholder engagement that is required of UNDP and its

Implementing Partners throughout the project cycle (www.undp.org/secu-srm). Complainants also have

access to the World Bank’s Inspection Panel (www.inspectionpanel.org). TPM Reports and the ESMF

stakeholder consultations noted that there was little awareness by project-affected people of the GRM and

their options. This will be an area to be strengthened moving forward.

Page 9: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

4

Monitoring, reporting and evaluation (Section 9): The ESMF and its procedures are to be reviewed and

updated on a regular basis by UNDP staff, PWP and SFD to reflect knowledge gained during the course of

project delivery/construction. Both PWP and SFD have a Management Information System in place to record

project information and monitoring results. The MIS provides an important mechanism to track information

on environmental and social safeguard implementation. A review will be conducted to identify opportunities

to strengthen environmental and social safeguard elements in the MIS. The Responsible Parties will maintain

and keep all administrative and social and environmental records which would include a log of complaints

and incidents together with records of any measures taken to mitigate the cause of the complaints or

incidents. Any incidents, major injury or fatality, including non-conformance with the procedures of the

ESMF, are to be recorded using an Incident Record and the details entered into a register. For any incident

that causes or has the potential to cause material or significant social and/or environmental harm, the site

supervisor/designated officer shall notify the Responsible Party Senior Management and the ECRP Project

Manager as soon as possible and no later than 48 hours. UNDP will also ensure significant incidents are

reported to the World Bank within 48 hours. The Responsible Party must cease work until remediation has

been completed as per the approval of Project Manager. A daily social and environmental checklist (including

OHS issues) is to be completed for active work sites with moderate risks by the relevant site

supervisor/designated officer and maintained within a register. A weekly social and environmental checklist

is to be completed and will include reference to any issues identified in the daily checklists completed by the

site supervisor or designated person. The progress of all corrective actions will be tracked using the register.

In the case of potential occupational health and safety hazards, safe working systems and procedures will be

developed and applied as well daily permit-to-work forms used to control and minimize risks to acceptable

limits. .A consultant will be recruited to conduct an annual environmental and social compliance and

performance audit by both PWP and SFD. Implementation of the ESMF to be included in overall project

monitoring and reporting, including monitoring conducted by the TPMA.

Page 10: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

5

1 Introduction

This Environmental and Social Management Framework (ESMF) is prepared by UNDP to ensure the Yemen Emergency

Crisis Response Project (ECRP) is consistent with UNDP’s Social and Environmental Standards (SES) (www.undp.org/ses)

and the World Bank’s Environmental and Social Safeguards Policies. The SES require that all UNDP projects consider

the potential environmental and social opportunities that a project may generate and ensure that adverse social and

environmental risks and impacts are avoided, minimized, mitigated and managed. In the context of the Yemen

Emergency Crisis Response Project (ECRP), UNDP’s SES and the World Bank’s Environmental and Social Safeguards

Policies apply. In addition, the Responsible Parties (Public Works Project and Social Fund for Development) have

elaborated their own standard operating procedures, that were set up for the World Bank supported projects with the

two institutions prior to the conflict, ESMFs in 2014, and Occupational Health and Safety Framework in 2018.

The project was originally categorized as Low Risk through UNDP’s Social and Environmental Screening Procedure

(SESP) so a project level Environmental and Social Management Framework (ESMF) was not initially put in place.

However, during implementation, several risks were identified and the SESP was updated accordingly. The update SESP

(see Annex 1) resulted in a Moderate Risk categorization for the project. Because the details of proposed activities are

designed at the sub-project level, an Environmental and Social Management Framework (ESMF) is necessary to ensure

policies and procedures are in place for consistent safeguards implementation across all sub-projects, and as required

by the World Bank safeguards policy OP 4.01 on ‘Environmental Assessment’.

The ESMF is intended to serve as a practical tool to guide identification and mitigation of potential environmental and

social impacts of proposed investments and as a platform for consultations with stakeholders and potential project

beneficiaries. The ESMF has been prepared in compliance with World Bank safeguards policy OP 4.01 on

‘Environmental Assessment’, the UNDP SES and relevant Yemeni policies on environmental assessment. The ESMF

identifies the policy triggers for the project, the screening criteria of sub-projects, the environmental and social impacts

for the likely sub-projects and the mitigation measures to mitigate the identified risks, and assessment of the

institutional capacity and measures for capacity-filling gaps.

Although the ECRP is currently in the implementation phase, the ESMF provides a strengthened framework and clarity to ensure consistency with the UNDP SES and World Bank Environmental and Social Safeguards Policies across all sub-projects. The ESMF was developed through a consultative process led by UNDP in close coordination with the World Bank, PWP and SFD. Stakeholders were consulted through workshops held in Sanaa and Aden and feedback from local communities also obtained through the Third-Party Monitors (see Annexes 11-13 for summaries of these consultations).

The ESMF provides the following:

• Description of the project (Section 2)

• Overview of the legal and regulatory framework (Section 3)

• Overview of project activities and key social and environmental risks (Section 4)

• Procedures for screening, assessment and management (Section 5)

• Institutional arrangements and capacity building (Section 6)

• Stakeholder engagement and information disclosure (Section 7)

• Grievance Mechanism (Section 8)

• Monitoring, reporting and evaluation (Section 9)

2 Project Description

The ongoing conflict in Yemen has resulted in a catastrophic humanitarian emergency with an increasing toll of civilian

deaths and casualties across the country with over 80 percent of Yemen’s population is estimated to need

humanitarian assistance and more than 2.5 million Yemenis have become IDPs. The ongoing conflict has destroyed

much of the institutional ability of key ministries, governorates and local authorities to deliver essential social services

to citizens. Public service restoration is also essential for a smooth transition to recovery, as a political agreement is

being negotiated.

In this context, UNDP, in partnership with the World Bank, developed the Yemen Emergency Crisis Response Project

(ECRP) to step up current efforts of the international community to deliver critically needed livelihood support and

service delivery to a population hit hard by the conflict. The project consists of close to 2,000 sub-projects. Two local

Page 11: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

6

institutions are the Responsible Parties: The Social Fund for Development (SFD) and the Public Works Project (PWP).

SFD is responsible for implementation of labour intensive cash-for-work/social service interventions (approx. 680) in all

governorates of Yemen and small community infrastructure and initiatives (approx. 90); and PWP is responsible for the

implementation of small community infrastructure through local contractors (approx. 1,200).

The project aims to mitigate the impact of the current crisis on local households and communities and assist their

recovery from the bottom-up using local systems, capacities and institutions to progressively resume and scale-up

service delivery. The project will achieve specific results in: 1) Increasing short-term employment and livelihoods

opportunities; 2) Reviving the local private sector; 3) Restoring key service delivery through small-scale infrastructure.

As such, the project contributes to the livelihoods restoration and service delivery restoration components of UNDP’s

Yemen Resilience Programme. The Project’s Theory of Change assumes that if income-generation and livelihoods

opportunities are increased for vulnerable households (including IDPs), with essential service delivery restored and key

local businesses revived, Yemeni households and communities will be able to better cope with the impact of the

current crisis and be strong drivers of the resilience-building and recovery efforts.

The project consists of small, fast-disbursing interventions (sub-projects) that serve as a rapid response, providing

households and communities affected by the conflict with income support (as wages) to purchase basic necessities.

These short-term interventions are also delivering benefits to the wider community by creating community assets,

small infrastructure, and improved access to basic service delivery, as well as restoring livelihoods. The project adopts a

community-based approach, which brings communities together around common humanitarian and development

initiatives and hence promotes social cohesion and the protection of human capital. The project gives special attention

to youth and, as an important peace dividend, provides them with income and participation opportunities, and

includes design features that ensure women’s access to project opportunities.

The project is fully described in the World Bank’s Project Appraisal Document (PAD1797, July 5, 2016) and UNDP

Project document (14 August 2016), and subsequent amendments for additional funding.

2.1 Description of Baseline Environmental and Socioeconomic Conditions

The economic impact of the crisis has been devastating for the Republic of Yemen, aggravating an already deteriorating

pre-conflict economic performance. In 2015, according to the World Bank, the economy contracted by about 28

percent of gross domestic product (GDP), while inflation has been estimated to have reached about 40 percent. Public

finances are under severe stress. The fiscal deficit reached around 11 percent of GDP in 2015. The fiscal resources

available in 2015 allowed only for financing basic salaries for public employees and rising interest payments; public

investments in critical sectors such as health and education or other development policy programs were postponed. In

a context of growing liquidity crisis in the country, President Hadi issued a decreed to replace the Central Bank

Governor and move the Central Bank Headquarters from Sana’a to Aden. As a result of the liquidity crisis, the payment

of salaries to civil servants has been disrupted. At a time where major development partners suspended their

engagements since earlier days of the military confrontation in March 2015 and transitioned their support to

emergency and relief operations, the suspension of wage payments causes the crumbling of the health services,

putting additional pressure on the humanitarian response and resilience of the population.

About 14.4 million Yemenis are currently considered food insecure. The poor state of the health services is leading to a

catastrophe in terms of excess mortality due to malnutrition and diseases. At present the Ministry of Health and

international partners are also battling a cholera epidemic. Some 3 million children under five years and pregnant or

lactating women require services to treat or prevent acute malnutrition; 1.3 million under-five children are

malnourished, with 370,000 suffering from severe acute malnutrition, a doubling of pre-crisis levels. Preliminary

estimates of the Nutrition Cluster in October 2016 indicates that 4.5 million children and pregnant and lactating

women require malnutrition treatment or preventive services. The number of people in need of assistance increased

by 148% compared to late 2014. Severe and Acute Malnutrition blunts children intellect and makes them nine times

more likely to die compared to their healthy peers. This poses a serious risk to the future of human development in

Yemen.

Furthermore, it is estimated that approximately 19.4 million Yemenis lack access to clean drinking water and sanitation,

and 14.1 million cannot access adequate health care. Children are facing significant psychological stress; an estimated

1.8 million children are out of school because of fighting and insecurity. 2,007,216 internally displaced persons (IDPs)

across 21 governorates; the majority, 50%, are displaced in Hajjah, Taizz, Amanat Al Asimah and Sana’a. The Task Force

on Population Movement has identified 1,027,674 returnees in 19 governorates; the majority, 68%, have returned to

Aden, Amanat Al Asimah and Taizz.

Page 12: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

7

The number of IDPs have risen to over 2 million, with the majority of displaced people hosted by local communities.

According to latest estimates from the Task Force on Population Movement in Janaury 2016, about 1,027,000 IDP

returnees who returned to their place of habitual residence across Yemen, representing about a 32% increase

compared to April 2016. The prospects for women-headed households, which represent more than 50 percent of the

displaced community, are particularly challenging. Households, communities, and public and private institutions need

support to cope and build resilience toward peace and recovery.

Yemeni economic advancement depends on its natural resource base; on agriculture and mining. Agriculture forms an

important sector in the nation’s economy and much of the economic activities depend on exploitation of fresh water

resources, marine resources, and its soil and oil wealth. However, the natural resource base is facing serious

challenges. The rapidly growing population at the rate of 3% annually accelerates pressure on scarce natural resources.

Demand increases on water resources, foodstuff and other products of natural resources. People exploit soil,

vegetation and water without paying adequate attention to the sustainability of these resources. Unplanned expansion

of urban centers exceeds, in some places, the carrying capacities of available resources to meet new demand. It also

causes sanitation and waste management problems and puts pressure on social services, in addition to loss of

biodiversity and agricultural land.

Yemen is a country with rich natural habitats, species and genetic diversity, including many endemic species resulted

from the variant altitudinal topography, climate, and geographical landscapes. The unique geographical position of

Yemen with the variant climatic and topographical features is favorable for existence of diverse ecosystems, natural

habitats, and great marine, coastal, and terrestrial biodiversity. The flora of Yemen is very rich and heterogeneous.

According to the Gap Analysis of Natural Plant Biodiversity of Yemen (2011), about 2,810 plant species were recorded

in Yemen in which endemic and near endemic plants were estimated about 604, among which 455 are endemic (307 in

Soqotra), constituting of about 16% of the flora which does not occur elsewhere (National Biodiversity Strategy and

Action Plan, NBSAP II 2015).

On the other hand, Yemen has very limited natural resources including for instance arable land, water, fishery, and

green cover which evidently experience constant degradation. The arable lands do not exceed 3% of the total natural

area which is dominated by desert and mountains. The arable lands experience continuous deterioration by about

1.8% annually during the period 1999-2006 as a result of the water erosion, desertification, salinization, and

urbanization. The total lands covered by forests are estimated about 1.5% until 2005. Desertification is accounting for

over 50 percent of total land of the country. Desertification of agricultural land ranges from 3-5 percent annually,

whereas the area of deteriorated land due to soil erosion and salinity is estimated to be 12 million hectares and

another 3.8 million hectares, respectively. The situation is further worsened as a result of encroachment of sand dunes

(NSES 2005-2015). The potential for greater desertification is high considering several factors including changes in

socio-economic patterns and farming practices and increasing demand for fuel, abandonment of terraces, overgrazing

and depletion of tree cover and water erosion problems.

2.2 Summary of Key Results and Activities

The project will be implemented through two components:

1. Labor Intensive Works and Community Services

2. Project Management and Monitoring

The overall objectives of Component 1 are to (a) provide income support to target communities through temporary

employment opportunities, (b) increase the productive assets and means of livelihood of beneficiary households and

communities and improve access to community and services and (c) preserve the implementation capacity of the SFD

and PWP, and key national service delivery programs. The component will be implemented through three

subcomponents that engage the SFD in subcomponents 1.1 and 1.3, and PWP in subcomponent 1.2, which build on

existing and well-established program implemented by these entities. Although both subcomponents 1.1. and 1.2 will

deliver labor intensive interventions, their primary objectives and approaches are different: subcomponent 1.1.

delivers cash for work with a safety net approach, whereby beneficiaries of the cash are at the individual household

level, While the primary objective of subcomponent 1.2 is to create community assets and improve community

infrastructure, and in doing so generate short-term employment for participating workers.

2.2.1 PWP Project Component (1.2)

The subcomponent will implement labor intensive, small -scale infrastructure provided through contracting local

private sector contractors. Subprojects will include, but are not limited to, water harvesting schemes, stone paving of

Page 13: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

8

village access roads and streets, water supply, sewerage networks and school rehabilitation, among others, based on

the priority needs identified by each targeted community. The choice of these subprojects takes in consideration

communities’ ability to operate and maintain the supported infrastructure and would not require technical expertise to

do so; technical specification of roads and schools’ construction will comply with the standards prepared by relevant

sectoral authorities, as applicable. Wage intensity of subprojects will have to meet the requirement of 35% percent of

above of the subproject cost. This subcomponent will create approximately 256,000 work days of employment, about

20,000 direct beneficiaries are expected to participate in labor, and over 310,000 individuals will have access to basic

services. The subprojects will be implemented through a contractual arrangement and grant provision from the UNDP

to the PWP. The grand under this subcomponent will finance works, goods, consultants’ services, training, non-

consultant services, and operating costs of PWP.

2.2.2 SFD Project Components (1.1 and 1.3)

Subcomponent 1.1: Cash-for Work and Youth-targeted Community Services

The subcomponent will implement labor intensive works subprojects determined by the community, such as in

irrigation, water harvesting, rehabilitation of agricultural terraces, maintenance and improvement of village access

roads, improvement of water resources, access to improved water and sanitation, watershed management,

agricultural inputs, other based on the priority needs identified by each targeted community. Each participating

household would be eligible to receive a maximum of US$ 500 (depending on the household size) in the form of labor

wage. The size and number of interventions assigned to each community will be determined by the total budget

envelope allocated to the community, as calculated based on the number of households who register for participation

in labor. The subcomponent will also finance subprojects that provide income opportunities, training and work

experience to youth in the 16 to 25 year age bracket, engaging them in the delivery of community services, including

hygiene and behavior change, literacy, alternative schooling, nutrition services, planting trees, paving of roads, cleaning

shorelines, and in youth initiatives promoting the protection of human capital through special attention to nutrition-

related interventions; and peace building and social cohesion, interventions, as may be proposed by communities and

youth groups.

The subcomponent is expected to create approximately 900,000 work days of employment over 32,000 direct

beneficiaries are expected to benefit from the wage labor, and about 92,600 individuals will have access to basic

services. The wage intensity of subprojects under this subcomponent is expected to be at least 30-50 percent of the

average total cost of subprojects. The subcomponent will be implemented through a contractual arrangement and

grant provision from the UNDP to the SFD. The SFD will deliver these subprojects with the direct involvement of

community and civil society groups (for example, community-based organizations, user groups, village cooperative

council, and local NGOs) using various implementation methods focused on community-based approaches, such as

community contracting. The grant under this subcomponent will finance community grants, wages, training of youth

and communities, consultants’ services, goods, work, non-consultant services, and operating cost of SFD.

Subcomponent 1.3: SME Revitalization and Employment Generation

The subcomponent will directly support around 2,000 SME clients of microfinance that have been severely affected by

the conflict, by relieving them from their current outstanding loans with the MFIs and by supporting the rehabilitation

of their enterprises. The project will use the existing solidarity funds (Takaful Fund) within each MFI to pay off the

outstanding loans of the targeted SMEs and channel the support needed to rehabilitate and revitalize their damaged

businesses. Moreover, given the important role the microfinance industry plays in contributing to the alleviation of

poverty, the project will support the operating deficit of at least seven rural-based MFIs, which will enable them to

sustain their levels of capacity and outreach, to continue to provide the financial services needed by the poor.

Additionally, the subcomponent will support 800 farms of essential cops, affected by the conflict, with seeds, seedlings,

drip irrigation systems, and other agriculture inputs. The agriculture inputs will substitute for farmers’ damaged inputs

and restore their ability to grow food, generate income, and create wage employment. The focus will be on farms of

the horticulture products, such as tomatoes, potatoes, and cucumbers, and cereals such as wheat, sorghum, and oats.

It is expected that this intervention will generate 6,400 seasonal and permanent employments within the agriculture

sector, increase farmers’ resilience, and increase the supply level and access to basic food commodities within the

targeted communities. The subcomponent will be implemented under the same contractual arrangement and grand

provision from the UNDP to the SFD as in subcomponent 1.1 and will be implemented through the SFD’s well

established SMED program.

Page 14: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

9

3 Legal and Regulatory Framework

The ESMF is prepared to:

- comply with national environmental and social laws and regulations, and the operating procedures of PWP

and SFD (including their ESMFs)

- meet the requirements of the World Bank’s Environment Assessment Policy (OP 4.01), including the World

Bank Group Environment, Health and Safety (EHS) Guidelines, most particular the General Guidelines, the

Guidelines for waste management facilities, and the Guidelines for water and sanitation

- meet the UNDP Social and Environmental Standards (SES)

3.1 National Legislation, Policies and Regulations

3.1.1 National Environmental Action Plan

The Republic of Yemen (RoY) enacted a National Environmental Action Plan (NEAP) in 1995 that was prepared with the

support of the World Bank. The NEAP defines priority actions regarding key environmental issues such as water

resources, land resources, natural habitats, and waste management.

3.1.2 National Biodiversity Strategy and Action Plan

The NBSAP calls for “achieving a resilient, productive and sustainable socio- ecosystem by 2050”. The strategy and its

action plan aims to halt the overall biodiversity loss and maintain healthy, productive and functional ecosystems based

on establishing coherent and resilient ecological networks supported by restructured policies and adequately

mandated and empowered local communities and institutions for sustainable and equitable use of natural capital of

importance to human well-being and economic prosperity.

3.1.3 National Water Sector Strategy and Investment Program

This strategy (2004) proposes a set of institutional, financial and other measures, which are aimed at addressing

discrepancies in the five sub-sectors in order to protect the interests of all stakeholders in water resources. Obviously,

if the situation continues as it is without regulation of groundwater extraction and use, without reduction of the

current unsustainable level of water resources use, and without putting an end to the ongoing resource capture, then

this will eventually harm everyone, including farmers, who will be the first victims of water exhaustion.

At the same time, (water) regulation is needed to safeguard or secure the economic and social growth of the cities.

Growth will not happen unless the cities get their water needs. Hence, the strategy notes that an equitable mechanism

for rural-to-urban transfer of water from the rural peripheral areas surrounding cities needs to be developed, as well as

strict measures to protect the water fields, which supply the cities, against illegal drilling.

3.1.4 Water Law

The ECRP project is subject to the following Yemeni laws and regulations: National Water Sector Strategy and

Investment Program; Water Law No. 33 issued in 2002 and modified in 2006 after the creation of Ministry of Water

and Environment, Its by-law was issued in 2011 by the Cabinet decree.

The law defines water resources as any water available in the republic's territory and its share of common waters

jointly owned with neighboring countries. This is comprised of ground water, surface water, wastewater after

purification, and saline water after desalination. The law's main objective is to regulate, develop, sustain and increase

efficiencies in water utilization, protect from pollution, transport, and engage the beneficiaries of water installations in

participatory management, investment, development, operation, maintenance and preservation at the various stages

of development. Water is considered as a common property accessible to all. Management of water resources is

entrusted to the National Water Resources Authority, which assess the resources, classify water basins and zones, and

prepare the national water plan, which is considered as one of the components of national economic and social

planning. Priorities of water use are: drinking and domestic use shall have absolute priority. Then in declining priority,

watering livestock, public utilities, irrigation, industrial purposes, minimal level of environmental needs. For these uses

water distribution and transport should be done according to hygiene means. Existing and acquired water rights prior

to the issuance of the law will be maintained, except in special cases when fair compensation will be ensured.

Page 15: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

10

Traditional water rights of rainwater harvesting and natural runoff flow in relation to irrigation shall be maintained. The

same applies for the traditional rights on natural springs, streams, and creeks. The Water Law and its by-law are a

notable achievement in Yemeni legislation and provide important legislation for environmental management of UNDP/

ECRP activities.

3.1.5 Environmental Protection Law

The Environmental Protection Law (Law 26/1995; EPL), enacted in 1995 in the wake of the NEAP, constitutes the

framework environmental legislation for Yemen. It includes provisions for environmental protection in Yemen, the

issuance of permits, and Environmental Impact Assessments (EIAs). The provisions of the law are implemented through

By-Law 148/000.

The law is also designed to: (i) incorporate environmental considerations in economic development plans at all levels

and stages of planning, (ii) protect the national environment from activities practiced beyond national boundaries, and;

(iii) implement international commitments ratified by the RoY in relation to environmental protection, pollution

control, the conservation of natural resources, and global environmental issues such as the depletion of the ozone

layer depletion and climate change.

Environmental Protection Authority

The EPL established an Environmental Protection Council and granted it power to take all measures necessary to

protect and improve the quality of environment and to prevent pollution of the environment. Decree 101/2005

established the Public Environmental Protection Authority (EPA) to replace the Council and lays down its objectives,

tasks and management. The functions assigned to the EPA include:

• preparing and executing appropriate policies/strategies/plans to protect the environment

• conducting environmental surveys

• assessing areas/resources/species to be protected through necessary measures conserving the ecosystem

including flora and fauna, wild and marine life as per existing laws and monitoring their application

• developing legislative proposals for environment protection in coordination with other agencies involved

• developing a National Emergency Plan to combat natural disaster and environmental pollution in consultation

with the agencies concerned implementing environmental protection law and other relevant laws/regulations

• reviewing EIA studies for public /private sector projects for giving clearance and monitoring their execution

• coordinating relevant programs/activities with national, regional and international agencies and organizations

• recommending necessary laws, regulations and systems to protect the environment, in accordance with

regional and international agreements on environmental protection.

• collecting data, assessing and evaluating the status of the environment, and setting up suitable monitoring

systems

• laying down appropriate standards for protecting the environment from pollution and formulating policy

guidelines to combat industrial pollution and protect animal, plant and marine ecology

Environmental Impact Assessments

The EPL requires the preparation of EIAs for projects proposed by the public and private sectors. The proponent is

responsible to undertake the EIA, but the report may be prepared by the proponent or the competent authority or

both. Line ministries and Government bodies commission EIA studies at the request of funding agencies and seek the

advice of the EPA.

The EPA is responsible for implementing screening procedures, assisting in scoping, evaluation and approval of the

Environmental Impact Statement (EIS). However, there is still no regulatory framework to support the implementation

of the EPL and the provision of undertaking EIAs for projects is not strictly enforced, particularly for projects that are

not internationally funded.

Given the current context, modifications to the EIA procedures are not expected during the project. Current

procedures will be taken into account, but there is no expectation at this point that the EPA will review the Project’s

safeguard instruments.

3.1.6 Labour Law

The RoY Labour Law, Act No.5 of 1995, includes OHS requirements for workplaces that needs to be applied in the

project.

Page 16: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

11

- The Labor Law (Law 5/1995) states that women are equal to man in all aspects without any discrimination, and that

equality should be maintained between women and men workers in recruitment, promotion, wages, training, social

insurance. It also regulates work time for pregnant women.

- The Labour Law regulates the rights and wages of workers, their protection, occupational health and safety. In

addition, the Social Insurance Law regulates retirement compensation.

- Yemen has ratified ILO Convention Number 138 on Minimum Age for Admission to Employment (Law 7/2001). The

Convention establishes a minimum age for admission to employment.

- Yemen has also ratified the ILO Convention 182 on the Worst Forms of Child Labour. It refers to child labour as

work that is mentally, physically, socially or morally dangerous and harmful to children; and interferes with their

schooling by depriving them of the opportunity to attend school, by obliging them to leave school prematurely; or

by requiring them to attempt to combine school attendance with excessively long and heavy work.

3.1.7 PWP and SFD Operating Procedures

In the context of the Yemen ECRP, both PWP and SFD operating manuals (PWP Operation Manual YECRP, July 2016,

see Annex 7; SFD Manual of Operation, May 2010, see Annex 9) specify operational requirements for the management

and delivery of sub-projects.

In addition, both PWP and SFD have Environmental and Social Management Frameworks in place that cover activities

implemented through the ECRP project (2014: PWP ESMF, Annex 8; SFD ESMF, Annex 10).

3.2 International Agreements and Protocols

The RoY is party to a number of international environmental agreements, the most important of which are:

• World Heritage Convention

• International Convention on Civil Liability for Oil Pollution Damage

• Convention on Biodiversity

• Convention on the Conservation of Migratory Species

• Convention on International Trade in Endangered Species of Wild Fauna and Flora

• United Nations Framework Convention on Climate Change (Yemen acceded to the Kyoto Protocol and is party

to Paris Agreement but not ratified)

• United Nations Convention on Combating Desertification

• Environmental Modification Convention

• Basel Convention on the Control of Transboundary Movements of Hazardous Wastes and Their Disposal

• Convention on Wetlands of International Importance Especially as Waterfowl Habitat

• Law of the Sea

• Montreal Protocol on Substances that Deplete the Ozone Layer

• Stockholm Convention on Persistent Organic Pollutants

In general, national agencies are not currently in a position to handle the technical complexities and reporting

requirements of international agreements.

Project activities are not expected to be in breach of any international agreement to which the RoY is a party.

3.3 UNDP’s Social and Environmental Standards

UNDP’s Social and Environmental Standards (SES) are applied to all UNDP projects, including the ECRP. The application

of the SES, which are broadly consistent with those of the World Bank, will help mitigate potentially high adverse

environmental and social impacts stemming from the selection and implementation of subprojects.

UNDP’s SES came into effect in January 2015. The SES underpin UNDP’s commitment to mainstream social and

environmental sustainability in its Programmes and Projects to support sustainable development. The objectives of the

standards are to:

• Strengthen the social and environmental outcomes of Programmes and Projects

• Avoid adverse impacts to people and the environment

• Minimize, mitigate, and manage adverse impacts where avoidance is not possible

• Strengthen UNDP and partner capacities for managing social and environmental risks

• Ensure full and effective stakeholder engagement, including through a mechanism to respond to complaints

from project-affected people

Page 17: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

12

The SES are an integral component of UNDP’s quality assurance and risk management approach to programming. This

includes the Social and Environmental Screening Procedure (see the completed SESP for the project in Annex 1).

Table 1. Key Elements of UNDP’s Social and Environmental Standards (SES)

Overarching Policy Project-Level Standards Policy Delivery Process & Accountability

Principle 1: Human Rights

Principle 2: Gender Equality and

Women's Empowerment

Principle 3: Environmental

Sustainability

Standard 1: Biodiversity Conservation and

Sustainable Natural Resource Management

Standard 2: Climate Change Mitigation and

Adaptation

Standard 3: Community Health, Safety and

Working Conditions

Standard 4: Cultural Heritage

Standard 5: Displacement and Resettlement

Standard 6: Indigenous Peoples

Standard 7: Pollution Prevention and Resource

Efficiency

Quality Assurance

Screening and Categorization

Assessment and Management

Stakeholder Engagement and Response

Mechanism

Access to Information

Monitoring, Reporting, and Compliance

review

The Standards are underpinned by an Accountability Mechanism with two key functions:

• A Stakeholder Response Mechanism (SRM) that ensures individuals, peoples, and communities affected by

UNDP projects have access to appropriate procedures for hearing and addressing project-related grievances;

and

• A Compliance Review process to respond to claims that UNDP is not in compliance with UNDP’s social and

environmental policies.

3.4 World Bank Requirements

World Bank Policy on Environmental Assessment, OP 4.01

The Project triggers the World Bank’s Operational Policy on Environmental Assessment (OP 4.01).

Considering the nature and magnitude of potential environmental impacts that might result from Project funded

activities, the Project was assigned EA Category B according to OP 4.01.

OP 4.01 provides for the use of an Environmental and Social Management Framework (ESMF) when a project consists

of a series of subprojects, and the impacts cannot be determined until the subproject details have been identified. The

ESMFs examine the issues and associated impacts, sets out the principles, rules, guidelines and procedures to assess

the environmental and social impacts during project implementation. It contains measures and plans to reduce,

mitigate and/or offset adverse impacts and enhance positive impacts of subprojects, provisions for estimating and

budgeting the costs of such measures, and information on the agency or agencies responsible for addressing project

impacts.

As there is no cultural inventory in Yemen, OP 4.11 may be triggered in case of archaeological finds, in which case its

implementation falls within the OP 4.01 procedures.

Environment, Health and Safety Guidelines

The World Bank Group Environment, Health and Safety (EHS) guidelines are referenced in footnote 1 of OP 4.01. They

are technical reference documents with general and industry-specific examples of Good International Industry Practice

(GIIP). They define acceptable pollution prevention and abatement measures and emission levels in World Bank

financed projects.

Page 18: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

13

The EHS Guidelines contain the performance levels and measures that are generally considered to be achievable in

new facilities by existing technology at reasonable costs. Application of the EHS Guidelines to existing facilities may

involve the establishment of site-specific targets, with an appropriate timetable for achieving them.

The application of the Guidelines to existing facilities may involve the establishment of site-specific targets with an

appropriate timetable for achieving them. The environmental assessment process may recommend alternative (higher

or lower) levels or measures, which, if acceptable to the World Bank, become project- or site-specific requirements.

If less stringent levels or measures than those provided in the EHS Guidelines are appropriate, in view of specific

project circumstances, a full and detailed justification for any proposed alternatives is needed as part of the site-

specific environmental assessment. This justification should demonstrate that the choice for any alternate

performance levels is protective of human health and the environment. When host country regulations differ from the

levels and measures presented in the EHS Guidelines, projects are expected to achieve whichever is more stringent.

Due to the nature of ECRP activities, the Project will use as appropriate the General Guidelines, including (i)

Environmental, (ii) Occupational Health and Safety, (iii) Community Health and Safety, and (iv) Construction and

Decommissioning, as well as the Guidelines for Construction and Decommissioning, as well as any other relevant

Guidelines.

4 Social and Environmental Impacts

This section summarizes key social and environmental risks and indicative management measures for the project.

Because a full risk analysis is not possible until site-specific design details are known, the identification of project level

risks provides an indicative assessment to be elaborated further through sub-project level screening, assessment and

risk management (see Section 5). Therefore, sub-project screening and site-specific assessments and management

plans will be essential.

The following section describes the UNDP social and environmental Principles and Standards that have been identified

as relevant based on completion of the project-level Social and Environmental Screening Procedure (SESP, see Annex

1). The project-level screening was updated in 2018 and was informed by project documents, Third-Party Monitoring

reports, sub-project risks, and audits conducted to date. It is based on a precautionary approach, looking at the broad

category of activity/intervention types and assessing potential risks based on the types of activities that are expected

to be implemented at the sub-project level. While the project was initially categorized as Low Risk, the project was

recategorized as Moderate Risk following the 2018 SESP update. Although different levels of risk categories have been

assigned to different activities, varying from Low to Moderate, the overall project categorization should follow the

highest level of risk categorization, which in this case is Moderate.

Table 2 below summarizes key principles and standards that were triggered after pre-screening of the project and the

SES requirements for the project, as identified in the SES and based on the results of the SESP. This table addresses the

principles and standards that have triggered both low and moderate level risks.

Table 2: Summary of Key SES Requirements for the ECRP

SES Principle or Standard Summary of Relevant SES Requirements

Principle 1: Human Rights Recognize centrality of human rights to sustainable development,

upholding principles of accountability and rule of law, participation and

inclusion, and equality and non-discrimination

Adhere to the UN Development Group Statement of Common

Understanding of the Human Rights-Based Approach to Development

Cooperation and Programming

Refrain from providing support for activities that may contribute to

violations of a State’s human rights obligations and the core

international human rights treaties

Principle 2: Gender Equality

and Women’s Empowerment

Promote design and implementation of gender responsive projects

Page 19: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

14

Reduce gender inequalities in access to and control over resources and

the benefits of development

Ensure that both women and men are able to participate meaningfully

and equitably

Ensure that projects do not discriminate against women and girls

Principle 3: Environmental

Sustainability

Address poverty and inequality while maintaining and enhancing

natural capital

Apply relevant social and environmental standards to avoid adverse

impacts, or where avoidance is not possible, to minimize, mitigate, and

manage potential residual adverse impacts

Use and promote a precautionary approach to natural resource

conservation

Standard 1: Biodiversity

Conservation and Natural

Resources Management

Natural Habitats: If potential adverse impacts, proceed only if (i) no

viable alternatives, (ii) benefits substantially outweigh environmental

costs, (iii) conservation and mitigation measures in place

Water Resources: Apply integrated water resources management

approach. Seek to avoid significantly altering flow regimes.

Sustainable Management of Living Natural Resources: Ensure

sustainable resource management. Apply appropriate industry-specific

best management practices. Support small-scale producers/harvesters

to adopt sustainable practices.

Standard 2: Climate Change

Adaptation and Mitigation

Climate Change Risks should be identified and assessed. Include

gender risks and potential differentiated impacts

Identify opportunities to facilitate adaptation

Standard 3: Community

Health, Safety and Working

Conditions

Community Health and Safety: Evaluate health and safety risks from

projects: design, construction, operation, decommissioning, and

establish preventive measures consistent with good international

practice (apply World Bank Group EHS Guidelines)

Consider exposure to accidents and natural hazards and avoid

exacerbation (e.g. land use changes that may increase risk of flooding,

landslides)

Consider how women’s and children’s health and safety could be at

risk

Infrastructure safety: Ensure design, construction, approval by

competent professionals and authorities. Where structural failure

poses safety risks, (i) develop/monitor plans for supervision, operation,

maintenance; (ii) independent experts verify design, construction,

operational procedures; (iii) periodic safety inspections are conducted

Emergency Preparedness: Ensure emergency preparations and plans

are in place, resourced, reviewed, and publicized. Ensure emergency

planning is gender sensitive and participatory. Consider potential

differential impacts of emergency situations on men, women, children,

elderly, disabled, potentially marginalized groups

Community exposure to disease: Avoid or minimize the potential for

community exposure to water-borne, water-based, water-related, and

Page 20: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

15

vector-borne diseases, and communicable diseases that could result

from Project activities (including labour influx)

Labour Standards: Ensure compliance with national labour and

occupational health and safety laws, with obligations under

international law, and consistency with the principles and standards

embodied in the International Labor Organization (ILO) fundamental

conventions, including forced labour and child labour

Standard 4: Cultural Heritage Avoid adverse impacts, comply with national laws and international

obligations. If avoidance not possible, mitigate impacts. Develop CH

Management Plan to mitigate significant adverse impacts

Use independent experts to assess adverse impacts and stakeholder

consultations

Incorporate chance find procedures

Do not remove cultural heritage unless conditions met

If utilize cultural heritage, (i) inform communities of rights, (ii) conduct

good faith negotiations with documented outcome, (iii) provide for fair

and equitable benefit sharing

Standard 7: Pollution

Prevention and Resource

Efficiency

Pollution prevention: Avoid the release of pollutants, and when

avoidance is not feasible, minimize and/or control the intensity and

mass flow of their release. Apply international good practices and

World Bank Group EHS Guidelines

Wastes: Avoid/minimize generation of waste, ensure recovery, reuse,

proper treatment, disposal. Ensure reputable contractors and chain of

custody

Hazardous Materials: Avoid/minimize release of hazardous materials. If

avoidance not possible, assess health risks, including differentiated

effects on women, men, children. No manufacture or use of materials

subject to international bans or phase-outs (Stockholm POPs, Montreal

Ozone)

Pesticides: Apply IPM/IVM, avoid/reduce synthetics, utilize least

harmful, prohibit use of WHO Class la & lb pesticides and control Class

II, handle per FAO International Code of Conduct

Resource Efficiency: Apply feasible, cost effective resource efficiency

measures (e.g. reduce water usage) to ensure no significant adverse

impacts on others/ecosystems

NOTE: This provides a summary of key relevant requirements, the full SES (www.undp.org/ses) should be referenced for a comprehensive list of requirements.

The main risks identified through the SESP are summarized below along with minimum requirements that need to be

considered and indicative management measures.

4.1 Conflict

4.1.1 Activities That May Result in Conflict Risks

Because of the ongoing conflict in Yemen, all sub-projects need to be developed in a conflict sensitive approach to

ensure activities don’t exacerbate conflict or violence. In addition, local conflicts may occur due to competition over

limited jobs and conflict between contractors and local laborers. This is a key element of UNDP’s commitment to

human rights in the SES.

Page 21: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

16

4.1.2 Management Measures

Given that the ECRP is in its third year of implementation, measures have already been undertaken to reduce the

potential impacts. Such measures include mainly developing a clear definition of targeting and selection criteria based

on data provided by the UN Clusters; participatory preparation and implementation of subprojects by communities and

relevant stakeholders (refer to ESMF section on Stakeholder Engagement for further detail); frequent communication

with communities and local stakeholders; grievance redress/ stakeholder response mechanism procedures to ensure

timely handling of grievance redress; and public disclosure of the reasons for the rejection of subprojects, if any, to

increase transparency.

PWP and SFD apply a conflict-sensitive approach to prevent and detect conflict and respond quickly to potential

conflicts. This helps ensure that the implementation process will do no harm and leads to effective development

interventions.

The following steps are taken to ensure achieving such goal (see PWP Operation Manual):

• Through transparent allocation of funds that is based on national statistics indicators in the governorate and

district levels, followed by coordination with local actors and inclusive participatory process, PWP/SFD will be

reducing conflict over resources.

• Selection of the community beneficiaries is based on a transparent eligibility criteria and consultations with

communities and local leaders.

• Before implementation and during the participatory consultations with local communities to define the

interventions, PWP/SFD's teams analyzes the context in which the project will be implemented to make sure

that PWP/SFD's intervention will not cause a conflict or escalate an existing conflict in that particular area. This

analysis enables PWP/SFD to understand the interaction between the intervention and the context in a

particular area. The steps will be as follows:

o Understanding the context in which the project will be implemented

o Carrying out a conflict analysis

o Understanding the interaction between the intervention and the Context

o Linking the conflict analysis with the programming cycle of the Intervention

o Using this understanding to avoid negative impacts and maximize positive impacts

o Implement, monitor and evaluate the intervention under a conflict-sensitive approach (including

redesign when necessary)

• Ensuring transparency of the procurement process including those of community contracting.

• Expected environmental and social impacts (including OHS risks) are identified during the project’s

preparation and mitigation measures are included in the design and implementation plan. Where investments

are required to implement the measures, ensure reflection of these measures quantified as pay-items in the

tender bill of quantities.

• During the implementation process, PWP/ SFD's staff keeps;

o Monitoring the situation to predict and recognize possible conflicts around the project and try to

keep risks at a minimal level.

o Following-up in order to strengthen the partnership with local authorities and community

committees as important players in conflicts resolution.

• PWP/SFD does not interfere to resolve existing conflict or be part of any conflict. However, PWP/SFD’s

intervention might help in reducing existing conflict.

• PWP/SFD might work in an environment where a conflict is prevailing such as the conflicts resulting from the

war in some areas in Yemen or are due to tribal conflicts. The staff in such case are fully aware of the

conflicts that surround their work and activities, but their project does not deal directly with the conflict.

• The evaluation of LIWP and other community-based interventions found that PWP/SFD’s intervention

increases community solidarity and cooperation.

• PWP/SFD's complaint mechanism will be a complementing tool to catch shortcomings that may arise,

through of the above precaution measures, and deal with them transparently and learn lessons from them to

improve performance in future programs. Project-affected people will be informed of the complaint

mechanism.

In addition, stakeholders have noted that there is sometimes conflict between contractors and local labour. This will be

mitigated through greater stakeholder awareness and engagement at the local level and further skill-building of local

labour and ensuring all parties are aware of the grievance mechanism.

Page 22: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

17

4.2 Gender and Social Inclusion

With persistent gender gaps existing even prior to the conflict (i.e., in education, legal restrictions on mobility and

decision-making, barriers to female participation in the labor force and in political life, and few opportunities for voice,

paid work and entrepreneurial activity), women are more vulnerable to the economic, social and security challenges

that result from the conflict and should thus be proactively reached for access to cash to improve their purchasing

power for food and basic necessities. The stark gender gaps are influenced by and set within the context of

conservative and strict gender norms. The project includes specific actions and design parameters to ensure the

inclusion and participation of women. Such design parameters will ensure women are provided an equal opportunity

to benefit from the employment opportunities (for example, targeting female-headed households, allowing flexibility in

work hours, and providing on-site child care).

Consideration for IDPs, women and youth as specific vulnerable groups are included in the targeting as well as type of

intervention.

Investing in persons with disability is central to poverty reduction and achieving the sustainable development goals. It

can contribute to greater social equity, inclusion, cohesion, and human capital formation in Yemen, all of which are

critical to breaking the cycle of poverty, deprivation, and social exclusion. The Yemen ECRP has been instrumental in

introducing adaptive and shock responsive safety net responses.

4.2.1 Activities That May Result in Gender and Social Inclusion Impacts or Risks

The ECRP is implemented in the midst of the current crisis in Yemen, where women are adversely affected and at the

same time asked to take on new and additional roles as heads of households or income-earners. In this light, ECRP

implementation is found to have the potential to reproduce discrimination against women based on gender, if

adequate gender mainstreaming considerations are not taken into account within the Project approach.

4.2.2 Management Measures

To the extent possible, the ECRP will promote gender equality and the empowerment of women and seek to reduce

gender inequalities in access to and control over resources and the benefits of development. Sub-projects will ensure

that both women and men are able to participate meaningfully and equitably, have equitable access to project

resources, and receive comparable social and economic benefits.

Sub-projects will not discriminate against women or girls or reinforce gender-based discrimination and/or inequalities.

Sub-projects will ensure precautionary measures are in place to prevent potential exposure of beneficiaries, workers,

and affected people to sexual exploitation and abuse.

Sub-projects will ensure precautionary and control measures are in place to prevent potential exposure of

beneficiaries, workers, and affected people to health and safety hazards.

The project will build upon existing services and pilot new approaches to improve the quality of targeted social care

services and economic opportunities for people with disabilities.

The ECRP has mainstreamed gender issues and is addressing gender equality from project identification, site selection,

management and oversight. Appropriate management measures taken by the project are explained below.

The project has actively targeted women (at least 30%) to support their income-generation opportunities and

contribute to the delivery of community service and livelihood assets through Cash for Work and Cash for Services, and

through earmarked funding (accounting to 15% of the project budget) dedicated to address severe and acute

malnutrition for pregnant and lactating women (and children) by providing cash assistance (mothers are the recipients)

and facilitating the affected families’ access to nutrition services.

To ensure women are targeted by the project, in cash for work interventions, the targeting unit is the household.

Women are encouraged to participate by measures that make their participation easier and acceptable to households

and the community: allowing flexible hours of on-site work, providing on-site child care (this will also hire a caregiver

from the community), having the subproject at the community level and at a location close to the villagers, and by

consulting women on the types of subprojects they can participate in. Subcomponent 1.1 is expected to have 30

percent female participation, and more than 50 percent of the microfinance clients under subcomponent 1.3 are

women. Women are assumed to benefit equally from the community infrastructures created. Women are the primary

beneficiaries of the water harvesting schemes as these reduce time and effort in fetching water, a responsibility for

women and girls. Women also benefit from having latrines at home, they regain dignity and freedom from humiliation

Page 23: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

18

of open defecation. Women are also the primary wage participants and beneficiaries of nutrition-based service

delivery.

Additionally, nutrition activities target households with pregnant and lactating women and children under the age of

five. Primary focus is given to eligible households from the list of the Social Welfare Fund (SWF) households – the

poorest of the poor – but will not be limited to them, as many poor HHs are excluded from the SWF program. Women

and children of the SWF households receive cash assistance of YR10,000 per month (about $40) for 12 months

conditions to attending health education sessions and follow up on the treatment (provided by the health sector).

Wider community members with mothers and children under age of 5 who have been screened and identified with

severe or acute malnutrition benefit from a transportation and accommodation allowance and a treatment allowance

of up to YR 10,000 (about $40) per family per month during the treatment period (6-9 months).

4.3 Biodiversity and Natural Resources

Conserving biodiversity, maintaining ecosystem services, and sustainably managing natural resources are fundamental

to sustainable development. The ECRP will seek to maintain and enhance the goods and services provided by

biodiversity and ecosystems in order to secure livelihoods, food, water and health, enhance resilience, conserve

threatened species and their habitats, and increase carbon storage and sequestration. ECRP will also promote

sustainable use of natural resources to support livelihoods of vulnerable communities as well as benefit sharing

between biodiversity conservation and livelihoods restoration.

4.3.1 Activities That May Result in Biodiversity and Natural Resources Impacts or Risks

The project will intervene in fisheries, agriculture and livestock and water resources.

Fisheries (Low Risk)

Project activities to support small scale fishermen through the provision of boat engines in order to increase food

production were found to have a Low Risk Rating. The project will target artisanal fishermen using small boats with one

off-board petrol engine. There is a low risk that the project may impact on biodiversity and natural resources through

overexploitation of fisheries. The small boat engines are not used in deep waters, consequently this reduces the

possibility of overfishing additionally fishermen will use traditional methods of fishing. Some of the fishermen will be

equipped with fish finders, to help expedite the search of the fish and thus economize the use of fuel. The design of

this activity under ECRP project has provisions to ensure sustainability, and the project will carefully monitor the

activities of the fishermen during its implementation.

Small scale farming and livestock (Low to Moderate Risk)

Activities will include: Watershed Management/Water Channels, Rehabilitation of Farm Lands, Rehabilitation of Farm

Irrigation Infrastructure, Agriculture Infrastructure, Agriculture Input Provision, Support to Livestock Producers.

Livestock activities involve the creation of yards in addition to other.

Although the projects are small scale in nature, the cumulative effects of providing support to communities may

involve inadvertent impacts on ecosystems that can result in negative effect to ecosystem services provision and

biodiversity. It may also include adverse impacts in handling of plastic and wastes generated from agricultural inputs.

When further sub-project screening is conducted more information will be available as to the extent of the impacts and

management measures required.

Additionally, under the section below on Pollution standards, a mention of potential impacts of the use of pesticides in

the activity related to provision of agriculture inputs is addressed in more detail.

Water resources (Moderate Risk)

The project activities include rehabilitation of existing water supply infrastructure at a small-scale. This includes rain

water catchments at the household level, community reservoirs and maintenance of clean water supply - piping

systems-, and small-scale agriculture irrigation systems. Sub-projects will not create new extraction points or new

infrastructure for containment or diversion of water. The project aims to rehabilitate or construct a total of 500,000

m3 storage capacity for water supply which are relatively small-scale.

Although the project interventions are small scale in the context of Yemen, in light of its semi-dry and arid climate and

exposure to climate change and variability, all water related interventions may have a potential impact on water

availability in the medium and long term.

Page 24: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

19

4.3.2 Management Measures

Considerations for the identification of management measures are summarized below, and additional guidance can be

referred to in the SES Biodiversity Conservation and Natural Resource Management.

Precautionary approach: The ECRP applies a precautionary approach to the use, development, and management of

natural habitats, the ecosystem services of such habitats, and living natural resources.

Assessment: As an integral part of the social and environmental assessment process, direct and indirect impacts on

natural resources, biodiversity and ecosystem services in the Project’s area of influence are identified and addressed.

In sub-projects that present potential significant impacts on natural resources, biodiversity and ecosystem services an

assessment process will consider, inter alia (i) risks of habitat and species loss, degradation and fragmentation, invasive

alien species, overexploitation, hydrological changes, nutrient loading, pollution, and (ii) differing values (e.g. social,

cultural, economic) attached to biodiversity and ecosystem services by potentially affected communities. Potential

cumulative and induced impacts will be assessed. Project-related impacts across potentially affected landscapes should

be considered.

Water resources: For sub-projects that affect water resources, integrated water resources management approaches

will be applied that seek the coordinated development and management of water, land and related resources in order

to maximize the economic and social welfare in an equitable manner and without compromising the sustainability of

ecosystems. Sub-projects will avoid significantly altering flow regimes in ways that prevent water resources from

fulfilling their functions for upstream and downstream ecosystems and their services to local communities. Social and

environmental risk assessments should address, among other issues, potential effects and impacts related to climate

variability, water pollution, sedimentation, water-related disasters, drinking water supply, energy production,

agriculture, and fisheries.

Sustainable management of living natural resources: Living natural resources will be managed in a sustainable manner.

Sustainable resource management is the management of the use, development, and protection of resources in a way,

or at a rate, that enables people and communities, including indigenous peoples, to provide for their social, economic,

and cultural well-being while also sustaining the potential for those resources to meet the needs of future generations.

This includes safeguarding biodiversity and the life-supporting capacity of air, water, and soil ecosystems. Sustainable

management also ensures that people who are dependent on these resources are properly consulted, women and

men have opportunities to equally participate in development, and benefits are shared equitably.

UNDP will ensure sustainable resource management through the application of appropriate, industry-specific best

management practices, and where codified, through application of one or more relevant credible standards as

demonstrated by an independent verification or certification system.

For Projects that involve the production, harvesting, and/or management of living natural resources by small-scale

landholders and/or local communities, UNDP will support adoption of appropriate and culturally sensitive sustainable

resource management practices.

In addition to the general requirements related to management measures as stated in the section above, project

context specific management measures were identified for each sector.

Project specific management measures in addition to standard SES UNDP measures (fisheries)

The project will work with fishing associations responsible for ensuring that fishing protocols that establish procedures

for sustainable fisheries are in place and adhered to, to protect fish stocks and regulate seasonal controls on fishing.

Development and strict implementation of policy, legislative and management tools are working to ensure harvest

level of coastal resources are maintained within the biological limits of Yemen's coastal zones.

The project will be implemented in line with the Biodiversity Conservation and Sustainable NRM of the SES which

includes fishing management. The concept of sustainable and responsible fishing will be promoted through this

partnership. Through its direct support to small scale fishermen, the project will improve community livelihoods and

training on quality and resource sustainability to include the reduction of wastage.

Project specific management measures in addition to standard SES UNDP measures (water resources) (to be developed

based on the local context):

Social and environmental risk assessments should be conducted to address, among other issues, potential effects and

impacts related to climate variability, water pollution, sedimentation, water-related disasters, drinking water supply,

energy production, agriculture, and fisheries.

Page 25: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

20

4.4 Climate Change

Climate change is a fundamental threat to sustainable development and the fight against poverty. It has the potential

to stall and even reverse human development through its impacts on key development sectors and activities, including

agriculture and food production, water, ecosystems and other natural resources, disaster risk management and health.

Climate change may exacerbate extreme weather events, increasing the risk of high-impact disasters. Communities

that are already subjected to impacts from climate change may experience an acceleration and/or intensification of

impacts due to Project activities that do not integrate and anticipate climate change risks.

Yemen has a predominantly semi-arid to arid climate and is highly vulnerable to climate change-related impacts such

as drought, extreme flooding, changes of rainfall patterns, increased storm frequency/severity, sea level rise. Literature

show that the main sectors under stress are: water resources, agriculture, and coastal zones. Water scarcity related to

prolonged droughts, evaporation, drying up of wells, excessive rainfall (which produces flash flooding and can

potentially wipe out crops) caused by rainfall variability are the key issues.

ECRP sub-projects will aim to be sensitive to climate change risks and not contribute to increased vulnerability to

climate change.

4.4.1 Activities That May Result in Climate Change Impacts and Risks

The ECRP project activities related to agriculture (including farming, livestock) and fisheries and water (irrigation,

catchment, conservation), will be most sensitive and vulnerable to the impacts of climate change. Infrastructure in

areas of potential flooding may also be at risk.

Some project activities that aim to increase water availability, may inadvertently lead to depletion of groundwater

resources or diversion of sources to some communities in detriment of others, if not properly managed based on

appropriate climate risk information and management measures.

4.4.2 Management Measures

Climate change risk assessment: As an integral part of the social and environmental assessment process, Proposed

subprojects are screened and assessed for climate change-related risks and impacts of and to projects. PWP and SFD

will ensure relevant climatic information is identified and informs project design and management measures. If

significant potential risks are identified, further scoping and assessment of vulnerability, potential impacts, and

avoidance and mitigation measures, including consideration of alternatives to reduce potential risks, will be required.

In projects, or a portfolio of projects, that present climate change risk, a climate change risk assessment may include

the following, where relevant:

a) Potential project-related increases in emissions that may exacerbate climate change, such as GHG emissions and

black carbon emissions.

b) The viability or longer-term sustainability of project outcomes due to potential climate change. This will involve the

identification of components that are sensitive or vulnerable to emerging or anticipated manifestations of climate

change.

c) Risks that a project may increase exposure to climate change. Project components must be assessed for potential

unintended or unforeseen increases in vulnerability to climate change.

d) Potential social, gender, and age risks, based on the differentiated impacts of climate change.

e) Opportunities for (i) facilitating adaptation via synergies with existing or planned activities, (ii) combining mitigation

(e.g. reduction in GHG emissions) and adaptation measures, and (iii) exploiting potentially beneficial changes in climatic

or environmental conditions to deliver developmental benefits.

4.5 Community Health, Safety and Working Conditions (including OHS)

The ECRP will avoid or minimize the risks and impacts to community health and safety that may arise from project-

related activities, with particular attention given to marginalized groups. This includes Occupational Health and Safety

(OHS) risks. Labour is one of a country’s most important assets in the pursuit of poverty reduction. Respect of workers’

rights and the provision of safe working conditions are keystones for developing a strong and productive workforce.

The ECRP applies the World Bank Group Environment, Health and Safety (EHS) guidelines.

Page 26: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

21

4.5.1 Activities That May Result in Community Health, Safety, Working Condition Impacts and Risks

Sub-project activities, equipment, and infrastructure can increase community exposure to risks and impacts. While this

is identified as a Moderate Risk, some projects have experienced high levels of OHS risks. This has therefore been

identified as a priority risk and management measures put in place to reduce risk and manage risks.

Such project activities such as working from height, excavation works, rock extraction, working in confined areas, lone

workers, traffic, and weak management of work site such as housekeeping and access and egress controls, may pose

hazards and risk threats to the workers and local community members. Exacerbating this, stakeholders have noted that

there is a weak culture of using safety precautions and safety gear in Yemen.

In addition, given the context in Yemen, there is a risk of airstrikes that needs to be minimized to the extent possible.

Another challenge is that some of the safety gear needed is not always available in the local markets.

Basic services, such as water and sewer, may face disruption and present community health and safety risks to those

affected.

Project activities that may trigger such risks to local communities and workers are detailed under the “Hazard

identification, risk assessment and determining controls” section of the latter report and in the SESP and are listed

below:

• Project construction, operation (fall from heights (human and material), slip, trip and falls, transportation

including traffic injuries, material and equipment handling and transfer, excavation work, others e.g. weather

elements, physical exertion, etc.)

• Failure of structural elements of the project may pose risks to communities (e.g. collapse of buildings or

infrastructure, demolishing work, accumulation of soil)

• Potential increased health risks (e.g. from water-borne or other vector-borne diseases or communicable

infections)

• Project implementation activities result in a disruption in basic services, such as water or sewer, temporarily

affecting the local community.

• Risks related to ongoing conflict in Yemen and potential for airstrikes.

4.5.2 Management Measures

Appropriate management measures have been put in place. A detailed OHS risk categorization was developed for the

purpose of identifying sub-project level risks to enable halting any salient high-risk projects from further

implementation until adequate management measures are put in place. Additionally, a specialized consultant was

hired to develop management plans, screening checklists, and ensure high frequency of field monitoring. Additionally,

support to the Responsible Parties has been reinforced by training and monitoring and capacity assessments. The

results of the latter measures taken by UNDP are included in a detailed “OHS Framework” which is available in Annexes

5 and 6.

Community health and safety: Community health and safety refers to protecting local communities from hazards

caused and/or exacerbated by project activities (including flooding, landslides, contamination or other natural or

human-made hazards), disease, and the accidental collapse or failure of Project structural elements such as dams.

Project-related activities may directly, indirectly or cumulatively change community exposure to hazards. A significant

concern with major development projects is the spread of communicable diseases from the workforce to the

surrounding communities.

Risks to, and potential impacts on, the safety of affected communities and workers during the design, construction,

operation, and decommissioning of projects will be assessed to establish preventive measures and plans to address

them in a manner commensurate with the identified risks and impacts. These measures will favour the prevention or

avoidance of risks and impacts over their minimization and reduction. Consideration will be given to potential exposure

to both accidental and natural hazards, especially where the structural elements of the project are accessible to

members of the affected community or where their failure could result in injury to the community. Sub-projects will

avoid or minimize the exacerbation of impacts caused by natural or man-made hazards, such as landslides or floods

that could result from land use changes due to activities.

Infrastructure safety: Structural elements will be designed and constructed by competent professionals and certified or

approved by competent authorities or professionals. Sub-projects with structural elements or components whose

failure or malfunction may threaten the safety of communities, will ensure that: (i) plans for Project supervision,

Page 27: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

22

operation, and maintenance are developed and monitored; (ii) independent expertise on the verification of design,

construction, and operational procedures is used; and (iii) periodic safety inspections are carried out.

Emergency preparedness: Responsible Parties will be prepared to respond to accidental and emergency situations in a

manner appropriate to prevent and mitigate any harm to people and/or the environment. This preparation, reflected

in planning documents, will include the identification of areas where accidents and emergency situations may occur,

communities and individuals that may be impacted, response procedures, provision of equipment and resources,

designation of responsibilities, communication, and periodic training to ensure effective response. The emergency

preparedness and response activities will be periodically reviewed and revised, as necessary to reflect changing

conditions. The differential impacts of emergency situations on women and men, the elderly, children, disabled people,

and potentially marginalized groups will be considered, and the participation of women in decision-making processes

on emergency preparedness and response strategies will be strengthened. Appropriate information about emergency

preparedness and response activities, resources, and responsibilities will be disclosed to affected communities.

Community exposure to disease: Sub-projects will avoid or minimize the potential for community exposure to water-

borne, water-based, water-related, and vector-borne diseases, and communicable diseases that could result from

activities, taking into consideration the differentiated exposure to and higher sensitivity of marginalized groups. Sub-

projects will avoid or minimize transmission of communicable diseases that may be associated with the influx of

temporary or permanent project labour. Standing water will be minimized, covered or treated to minimize mosquito

breeding. Local authorities and the Responsible Parties will coordinate closely to ensure any disruption to local basic

services, such as water and sewer, is avoided where possible and otherwise minimized.

Work standards: Sub-projects will comply with national labour and occupational health and safety laws, with

obligations under international law, and consistency with the principles and standards embodied in the International

Labor Organization (ILO) fundamental conventions, including freedom of association, elimination of discrimination in

employment and occupation, elimination of forced or compulsory labour, and elimination of the worst forms of child

labour. The ECRP will not employ people under the age of 18; however, youth that are 16-17 years old may be eligible

for employment training and capacity building.

Occupational health and safety: Occupational health and safety refers to protecting workers from accident, injury or

illness associated with exposure to hazards encountered in the workplace. Hazards can arise from materials (including

chemical, physical and biological substances and agents), environmental or working conditions (e.g. oxygen-deficient

environments, excessive temperatures, improper ventilation, poor lighting, faulty electrical systems), or work

processes (including tools, machinery and equipment).

Responsible Parties’ commitment to the OHS Framework strengthens compliance with OHS requirements and

protection of staff/workers, as well as middle management accountability to implement the policy and roles and

responsibilities and enforcing control measures and procedures. Risk assessment will be conducted for each sub-

project site to identify potential hazards and risks and develop and implement corresponding risk control measures.

Safety measures hierarchy will be applied starting with hazard elimination, substitution, engineering controls,

administrative controls and finally use of PPEs. Furthermore, safe working systems and procedures will be developed

and used as well as permit-to-work forms for high risk activities to control risks, authorize implementation confirming

compliance to OHS requirements and ensuring close monitoring and inspections to control and minimize risks. In

addition the development of positive OHS behavior and strong culture of adherence and compliance to OHS systems

will be promoted including setting up and activating branch OHS committees and conducting of field inspections

regularly by managers to ensure improvement of OHS systems and practices and promote conducive OHS culture.

Workers will be provided with a safe and healthy working environment, taking into account risks inherent to the

particular sector (including gender bias) and specific classes of hazards in the work areas. Steps will be taken to prevent

accidents, injury, and disease arising from, associated with, or occurring during the course of work and will ensure the

application of preventive and protective measures consistent with the World Bank Group’s Environmental, Health, and

Safety Guidelines and other international good practice, as reflected in internationally-recognized standards. The

involved workers will be insured and the insurance payment will be covered directly by the IP in case of direct

implementation modality and as a pay item through bills of quantities in the bidding documents in case of contracting

modality.

Please refer to the ECRP OHS Framework for details (Framework for Actions on Occupational Health and Safety Under

Yemen ECRP (Annex 5)

Security-related issues: Sub-projects under ECRP do not engage security personnel. In case sub-projects do require

involvement and engagement of security personnel to protect facilities and personal property, security arrangements

Page 28: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

23

should be provided in a manner that does not violate human rights or jeopardize the community’s safety and security.

Potential risks posed by security arrangements to those within and outside the Project area will be assessed, those

providing security will be appropriately vetted and trained, and security arrangements will be appropriately monitored

and reported. UNDP has currently deconflicted 70 subproject sites in five governorates (Saada, AlHudaydah, Taiz,

AlBaida and Sana’a) in high risk locations to minimize the risk of airstrikes.

4.6 Cultural Heritage

The ECRP seeks to ensure that Cultural Heritage is protected in the course of sub-project activities. UNDP seeks to

ensure equal participation, access and contribution of women and men in protecting and sharing the benefits of

Cultural Heritage.

The Standard applies to sub-projects that may adversely impact Cultural Heritage, including projects that meet any of

the following criteria: (i) located in, or in the vicinity of, a Cultural Heritage site ; (ii) involving significant excavations,

demolitions, movement of earth, flooding, or other environmental changes; (iii) proposes to utilize tangible or

intangible forms of Cultural Heritage for commercial or other purposes. (iv) interventions to preserve the cultural

heritage sites.

4.6.1 Activities That May Result in Cultural Heritage Impacts and Risks

As the project conducts small scale infrastructure activities related to community works such as road paving,

community reservoirs and piping, and repairing of school buildings in addition to others these project activities,

although many do not target the rehabilitation of Cultural Sites directly, they may be located in the vicinity of cultural

heritage sites and consequently produce unintended negative effects on such sites. In addition, those sub-projects that

target the preservation and protection of cultural heritage need to ensure risk management measures are in place.

4.6.2 Management Measures

Avoidance: Avoid significant adverse impacts to Cultural Heritage through alternative project siting and design. The

impacts on Cultural Heritage resulting from project activities, including mitigating measures, may not contravene the

national legislation, or its obligations under relevant international treaties and agreements.

Mitigation: Where potential adverse impacts are unavoidable, appropriate mitigation measures will be identified and

incorporated as an integral part of the social and environmental assessment process. Where potential adverse impacts

may be significant, a Cultural Heritage Management Plan should be developed as part of the Environmental and Social

Management Plan (ESMP).

Use of experts: For projects with potential adverse impacts, qualified and experienced independent experts will assess

the project’s potential impacts on Cultural Heritage using, among other methodologies, field-based surveys and

involving meaningful, effective, and informed stakeholder consultations as part of social and environmental

assessment process. Note that SFD has a Cultural Heritage unit.

Use of Cultural Heritage: Where a project proposes to utilize Cultural Heritage, including the knowledge, innovations,

or practices of local communities, affected communities will be informed of their rights, the scope and nature of the

proposed development, and the potential consequences of such development. The project will not proceed without

meaningful, effective participation of affected communities and unless (i) good faith negotiations with affected

communities result in a documented outcome, and (ii) the Project provides for fair and equitable sharing of benefits

from any commercialization of such knowledge, innovation, or practice, consistent with the affected community’s

customs and traditions. For Projects that propose to utilize Cultural Heritage of indigenous peoples, the requirements

of Standard 6: Indigenous Peoples apply.

Chance find procedures: When the social and environmental assessment process determines that Cultural Heritage is

expected to be found in the project area, chance find procedures will be included in the ESMP. Chance finds will not be

disturbed until an assessment by a competent specialist is made and actions consistent with these requirements are

identified.

Conditions for removal: The project will not remove any Cultural Heritage unless the following conditions are met: (i)

no alternatives are available; (ii) the overall benefits of the Project substantially outweigh the anticipated Cultural

Heritage loss from removal; and (iii) any removal employs best available techniques and is conducted in accordance

with relevant provisions of national and/or local laws, regulations, and protected area management plans and national

obligations under international laws.

Page 29: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

24

4.7 Pollution Prevention and Resource Efficiency

4.7.1 Activities That May Result in Pollution and Resource Efficiency Impacts and Risks

The project will support the construction and/or rehabilitation of pit latrines, provide agriculture inputs that may

include pesticides, support small health care centers infrastructure or services, cleaning up public spaces that may

include municipal solid waste, and sewage that may include hazardous/human excreta and waste.

Pit latrines may consist of a pit—circular, rectangular, or square—dug into the ground and covered with a concrete slab

or floor with a hole through which excreta falls. Unimproved pit latrines are those without slabs or platforms. In the

latter there are risks of groundwater contamination. Additionally, the project will intervene by providing small scale

farmers with agriculture inputs, that may involve pesticides. Other activities may include the improvement of health

care services through support to small health care center and cleaning of public spaces including municipal solid waste.

In relation to pit latrines, there are ecological health impacts that may be associated with microbiological and chemical

contamination of groundwater due to use of latrines. In Yemen, the main drinking water sources are extracted from

groundwater (in addition to rainwater harvesting). A concern is that pit latrines, that generally lack a physical barrier,

such as concrete, between stored excreta and soil and/or groundwater. Contaminants from pit-latrine excreta may

potentially leach into groundwater, thereby threatening human health through well-water contamination.

Agriculture related interventions which include the use of pesticides trigger both environmental, health and

occupational health and safety concerns. Runoff waters from agriculture may contaminate local drinking water

sources, such as streams, wells, other leading to potential disease downstream. Project workers and small-scale

farmers handling pesticides are also exposed to health hazards.

Support to small health care centers may include rehabilitation of sewage systems that may consequently involve

hazardous waste water.

Cleaning up of public spaces may involve the handling, disposal and transport of municipal solid waste.

Waste may also be generated during construction and implementation activities.

4.7.2 Management Measures

Pollution prevention: Sub-projects will avoid the release of pollutants, and when avoidance is not feasible, minimize

and/or control the intensity and mass flow of their release. This applies to the release of pollutants to air, water, and

land due to routine, non-routine, and accidental circumstances.

Pollution prevention and control technologies and practices consistent with international good practice are applied

during the project life cycle. The technologies and practices applied will be tailored to the hazards and risks associated

with the nature of the Project.

Ambient considerations: To address adverse impacts on existing ambient conditions (such as air, surface water,

groundwater, and soils), a number of factors will be considered, including the finite assimilative capacity of the

environment, existing and planned land use, existing ambient conditions, the Project’s proximity to ecologically

sensitive or protected areas, the potential for cumulative impacts with uncertain and irreversible consequences, and

strategies for avoiding and minimizing the release of pollutants.

Wastes: Sub-projects will avoid the generation of hazardous and non-hazardous waste materials. Where waste

generation cannot be avoided, Projects will reduce the generation of waste, and recover and reuse waste in a manner

that is safe for human health and the environment. Where waste cannot be recovered or reused, it will be treated,

destroyed, or disposed of in an environmentally sound manner that includes the appropriate control of emissions and

residues resulting from the handling and processing of the waste material. If the generated waste is considered

hazardous, reasonable alternatives for its environmentally sound disposal will be adopted while adhering to the

limitations applicable to its transboundary movement. When hazardous waste disposal is conducted by third parties,

UNDP will ensure the use of contractors that are reputable and legitimate enterprises licensed by the relevant

government regulatory agencies and that chain of custody documentation to the final destination is obtained.

Hazardous materials: Projects will avoid or, when avoidance is not feasible, minimize and control release of hazardous

materials resulting from their production, transportation, handling, storage and use. Where avoidance is not possible,

the health risks, including potential differentiated effects on men, women and children, of the potential use of

hazardous materials will be addressed in the social and environmental assessment. Projects will consider the use of less

hazardous substitutes for such chemicals and materials and will avoid the manufacture, trade, and use of chemicals

Page 30: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

25

and hazardous materials subject to international bans or phase-outs due to their high toxicity to living organisms,

environmental persistence, potential for bioaccumulation, or potential for depletion of the ozone layer.

Pesticide use and management: While pesticide use is not anticipated, sub- projects that may involve pest

management activities, integrated pest management approaches will be applied and aim to reduce reliance on

synthetic chemical pesticides. The integrated pest/vector management programme will entail coordinated use of pest

and environmental information along with available pest/ vector control methods, including cultural practices,

biological, genetic and, as a last resort, chemical means to prevent unacceptable levels of pest damage. When pest

management activities include the use of pesticides, pesticides that are low in human toxicity, known to be effective

against the target species, and have minimal effects on non-target species and the environment will be selected. The

health and environmental risks associated with pest management should be minimized with support, as needed, to

institutional capacity development, to help regulate and monitor the distribution and use of pesticides and enhance

the application of integrated pest management.

Projects will not use products that fall in Classes Ia (extremely hazardous) and Ib (highly hazardous) of the World Health

Organization Recommended Classification of Pesticides by Hazard. WHO Class II (moderately hazardous) pesticides will

not be used if the relevant Responsible Party lacks restrictions on distribution and use of these chemicals or facilities to

handle, store, apply and dispose of these products properly, or if they are likely to be accessible to personnel without

proper training and equipment. Pesticides will be handled, stored, applied and disposed of in accordance with

international good practice such as the FAO International Code of Conduct on the Distribution and Use of Pesticides.

5 Procedures to Address Social and Environmental Impacts

5.1 Sub-Project Screening and Classification Requirements

The ECRP will support a series of sub-projects over the course of its implementation. The type of sub-projects are

described in Section 2 of this ESMF. Each sub-project will be screened for social and environmental risks (including OHS

risks) and impacts applying PWP and SFD screening tools. Screening and classification will be completed prior to

approval of sub-projects and signing of the Financial Agreement. The screening of sub-projects will also be updated if

there are any significant changes in the sub-project’s design or context that may materially change its social and

environmental risk profile.

Sub-project screening and categorization should be conducted at the earliest stage of design when sufficient

information is available for this purpose. Based on the screening, the sub-project is categorized according to the

degree of potential social and environmental risks and impacts. In some cases, applicability of specific SES

requirements will need to be determined through additional scoping, assessment, or management review. The

screening process results in one of the following three categories for the proposed sub-project

• Low Risk: Projects that include activities with minimal or no risks of adverse social or environmental impacts.

Further assessment of potential adverse social and environmental risks and impacts is not required.

• Moderate Risk: Projects that include activities with potential adverse social and environmental risks and

impacts, that are limited in scale, can be identified with a reasonable degree of certainty, and can be

addressed through application of standard best practice, mitigation/control measures and stakeholder

engagement during Project implementation. Moderate Risk Projects may require limited social and

environmental assessment and review to determine how the potential impacts identified in the screening will

be avoided or when avoidance is not possible, minimized, mitigated and managed. A site-specific

Environmental and Social Management Plan (scaled to nature of the risks) should be in place to ensure risks

are managed.

• High Risk: Projects that include activities with potential significant and/or irreversible adverse social and

environmental risks and impacts (including OHS), or which raise significant concerns among potentially

affected communities and individuals as expressed during the stakeholder engagement process. High Risk

activities may involve significant impacts on physical, biological, socioeconomic, or cultural resources. Further

impact assessment is required and an Environmental and Social Management Plan will be in place. High Risk

Projects require tight control measures, closer monitoring, enhanced internal and external support.

Note that High Risk sub-projects will be excluded from Yemen ECRP funding. If high level risks are identified during

implementation, Senior management of the Responsible Party and UNDP Project Manager will be notified immediately

and relevant activities will be halted until management measures put in place to reduce the levels of risk.

Page 31: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

26

Screening results inform final appraisal and sub-project approval.

An initial gap analysis shows that PWP and SFD screening processes are generally aligned with SES requirements, as

described below. However, a more detailed gap analysis will be conducted and UNDP together with the World Bank

will work with PWP and SFD to update their screening processes as needed to address gaps and also respond to lessons

learned.

5.1.1 PWP Sub-projects

The procedure followed by PWP for undertaking screening and classification of subprojects is articulated in the PWP

ESMF (see Annex 9). An Environmental and Social Impact Assessment Checklist is applied for sub-projects related to

schools, health units/centers, rainwater harvesting reservoirs, sanitation, and rural water projects. The screening

results in one of the following three determinations and is signed by the PWP engineer and PWP environmental

specialist:

• Determination of no adverse impacts

• Determination that there may be adverse impacts and further analysis is required

• Determination of potential adverse impacts and all mitigation measures have been included in the design

and contract conditions.

The first screening is undertaken during application of selection criteria. Those that do not meet criteria for

improvement in environmental conditions will be rejected at the outset.

Sub-projects will then be divided into two groups: those that do not have any significant negative impacts (Low Risk)

and those that may have some impacts (Moderate Risk). PWP does not engage in High Risk projects under the ECRP.

Screening results and classification inform final appraisal and approval of a sub-project. Sub-projects will be grouped

into annual and/or quarterly investment programs to be submitted to the PWP Internal Management Committee for

approval. Social and environmental screening results will be included in the submission. Screening results and ESMPs

will also be recorded in the MIS.

5.1.2 SFD Sub-projects

The procedure followed by SFD for undertaking screening and classification of subprojects is articulated in the SFD

ESMF (see Annex 10). SFD undertakes screening of the subproject proposals and classifies subprojects into Class A, B,

and C, similar to the World Bank categorization and comparable to UNDP’s High, Moderate, Low respectively. The

classification is based on the significance of impacts which depend on the type, location, sensitivity, and scale of the

subproject and the nature and magnitude of its potential environmental impacts. Accordingly, Category C subprojects

(Low Risk) are those which are known to have no adverse environmental and social impacts and accordingly will not

require any further assessment or follow-up. Category B subprojects (Moderate Risk) are those that are likely to have

limited adverse environmental and social impacts that are temporary and/or site specific and can be

reduced/avoided/mitigated with the implementation of appropriate mitigation measures, and these subprojects would

require a scoping to be undertaken and a limited site specific Environmental and Social Management Plan is prepared

as needed. Category A (High Risk) will be excluded from funding.

At the proposal stage, environmental and social responsiveness criteria are applied as well as an occupational hazard

assessment. This is done by using the formats prepared for each type of intervention of class B subprojects (see SFD

ESMF, Annex 9). The format includes decisive questions to examine the responsiveness of the proposal to the

environmental and social issues. The answers to the questions are either "Yes" or "No". If the answer to any of the

questions is "No", then the proposal is dropped or location is changed to ensure full responsiveness to environmental

and social issues.

If the sub-project involves more than one type of activity, all relevant responsive forms should be completed.

At the design stage, a checklist of expected environmental and social impacts to be addressed is completed. This is an

important stage as it will pave the way for the implementation and operation stages. All the expected environmental

and social impacts will be identified at this stage and the mitigation measures will be designed and incorporated in the

subproject design and tender documents, particularly, in the BQ so that it becomes obligatory. The checklist contains

questions about the expected environmental and social mitigation measures to be included in the project documents

for each type of intervention and the answer will be "Yes" or "No". If the answer is "No", then the consultant will need

to justify this in the design report, and also include the completed checklist as an annex to the design report. Annex 3

Page 32: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

27

of SFD’s ESMF gives the checklist of the environmental and social issues that will need to be addressed at the Design

Stage for SFD interventions.

If the sub-project involves more than one type of activity, all relevant checklists should be completed.

Annex 2 shows summary of project activities, risks and measurement measures for both Responsible Parties (SFD and

PWP)

5.2 Site-Specific Assessment and Management Requirements

The targeted and site-specific assessments and management plans will be undertaken for all Moderate Risk (Cat B) sub-

projects once project activities/sub-projects and sites are identified. The assessment(s) will be conducted in a manner

consistent with national regulations, PWP or SFD operating procedures, the UNDP SES, and the World Bank’s

Environmental and Social Safeguards Policies and lead to the development of appropriately scaled management

measures and plans to address the identified risks and impacts. For projects with easily identified risk management

measures, a simplified ESMP can be developed.

The UNDP SES and SESP as well as the World Bank Safeguards Policy on ‘Environmental Assessment’ require that in all

cases relevant social and environmental assessments and adoption of appropriate mitigation and management measures

be completed, disclosed, and discussed with stakeholders prior to implementation of any activities that may cause

adverse social and environmental impacts. An indicative outline for an Environmental and Social Management Plan is

provided in Annex 4. All site-specific assessments and management plans will be cleared by World Bank and UNDP and

recorded in the MIS. In cases where similar activities are being conducted in a particular region, these activities may be

grouped and covered under one site-specific ESMP. All ESMPs will be available upon request.

6 Institutional Arrangements and Capacity Building

6.1 General Management Structure and Responsibilities

6.1.1 World Bank

The YECRP is funded by the World Bank. A World Bank senior management task team has been established to oversee

and make decisions about remedies in connection with the UNDP-implemented activities. In particular, the task team’s

functions/responsibilities consist of: (a) reviewing periodic financial and progress and results reports measured by

targets and benchmarks agreed at the time of project approval; (b) applying the agreed process for dealing with

serious issues, including significant social and environmental issues; (c) reviewing progress reports on actions taken to

address a serious situation and results obtained, including details of any recovery of funds or write-off of losses; and (d)

exercising remedies of suspension and termination in accordance with the provision of the legal agreement, if

necessary (see World Bank document PAD 1797).

The World Bank is also engaged in the Biannual Review Meetings (see Section 6.1.2) and conducts Technical Review

Missions.

6.1.2 Project Board (Biannual Review Meetings)

The Project Board (UNDP, World Bank, PWP, SFD) has oversight and advisory authority, representing the highest body

for coordination, strategic guidance, oversight and quality assurance. The body facilitates collaboration between UNDP,

the two responsible parties (PWP and SFD), the World Bank, and other stakeholders for the implementation of the

Project. The Project Board reviews and endorses the Annual Work Plans (AWPs), provides strategic direction and

oversight, reviews implementation progress, and reviews narrative and financial progress reports. The Project Board

will be convened by UNDP and meet at least on a 6-montly basis. It will coincide with the timing of World Bank

technical review missions.

A progress report will be presented to the Project Board and key stakeholders, consisting of progress data showing the

results achieved against pre-defined annual targets at the output level, the annual project quality rating summary, an

updated risk long with mitigation measures, and any evaluation or review reports prepared over the period.

Page 33: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

28

6.1.3 UNDP

UNDP will be responsible for overseeing the implementation and compliance with the ESMF, working closely with PWP

and SFD. The ESMF and developed management plans will be part of any tender documentation.

UNDP will be responsible for the revision or updates of this document during the course of project, in consultation with

PWP, SFD and the World Bank.

Project Management Team

The Project Management Team ensures effective implementation of activities on the ground, risk mitigation, and

timely delivery of the results. The team has geographic presence in both Sana’a and Aden to ensure inclusion and to

minimize political sensitivities.

The Project Manager is responsible for day-to-day management and decision-making for the project. The Project

Manager’s prime responsibility is to ensure that the project produces the results specified in the Project Document to

the required standard of quality and within the specified constraints of time and cost. The Project Manager is

responsible for overseeing implementation of the ESMF and required environmental and social risk management

actions.

The Project Manager is supported by a team that includes National Coordinators, an M&E Specialist, Grievance and

Communication Officer. A Management Information System is in final stages of development to support project

management. It is overseen by the UNDP Programme Team on Economic Resilience and Recovery which has the

responsibility of ensuring technical/substantive quality assurance as well as on other aspects such as finance, HR, audit,

and M&E (pls see section below). The Project Management Team is also supported by experts in UNDP Headquarters

and Regional Hubs, including SES expertise.

The project safeguard team including an International Safeguards Specialist, National SES and National OHS experts will

be responsible for enhancing the capacity of UNDP and Responsible Parties to improve social, environmental and

occupational health standards and services, contributing to improved decision making and to capitalize on potential

opportunities while ensuring that adverse social and environmental risks are avoided, minimized, mitigated and

managed.

Project Oversight and Assurance

The ‘project assurance’ function of UNDP is to support the Project Board by carrying out objective and independent

project oversight and monitoring functions. This role ensures appropriate project management milestones are

managed and completed. Project assurance has to be independent of the Project Manager; therefore, the Project

Board cannot delegate any of its assurance responsibilities to the Project Manager. Furthermore, UNDP provides

quality assurance for the project; ensures compliance with UNDP policies and procedures, including its Social and

Environmental Standards and implementation of the requirements of this ESMF.

The oversight and quality assurance for ECRP is done by the UNDP ERR Programme Team, which oversees the UNDP

Yemen programme portfolio focusing on livelihoods and service delivery. UNDP Headquarters will provide corporate

oversight and management support including finance, human resources, audit and investigations.

6.1.4 Responsible Parties

During operations the Responsible Parties will be accountable for implementation of the ESMF. Personnel working on

the project have accountability for preventing or minimizing environmental and social impacts.

The Responsible Parties are directly accountable to UNDP in accordance with their Letter of Agreement. There are two

responsible parties for the project: PWP and SFD. Responsible Parties include HQ offices, branch offices, site

engineers, site supervisors, and workers that also play a role in implementation of the ESMF. Ultimately the

Responsible Parties are responsible for ensuring implementation of the ESMF within their portfolio of sub-projects and

ensuring all relevant documentation is available and reported to UNDP.

SFD will implement subcomponents 1.1 and 1.3 through its 185 staff working in Sana’a headquarter and nine branch

offices across Yemen. PWP will implement subcomponent 1.2 through its 53 staff in Sana’a headquarters and nine

regional offices.

The top management of the Responsible Parties is ultimately responsible for implementation of the ESMF within all

sub-projects that are part of the ECRP.

Page 34: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

29

The top management shall demonstrate its commitment by: ensuring the availability of resources essential to

establish, implement, maintain and improve implementation of the ESMF; defining roles, allocating responsibilities and

accountabilities, and delegating authorities, to facilitate effective ESMF implementation.

Responsible Parties shall be responsible to develop, implement and monitor contractors.

Environmental and social management duties shall be specifically assigned to certain positions such as site engineer

(Responsible Parties) and site manager (contractors). They shall have social and environmental risk management

training and shall have direct access and reporting channels to most senior management level. Some of the duties of

the site engineer/manager include:

• organization and conduct of training programmes, including induction training for all workers on the site;

• organization of information to be passed from management to workers, including those of subcontractors;

• provision and implementation of environmental and social management measures, including occupational

health and safety measures;

• Investigation and review of the circumstances and causes of environmental and social risks so as to advise to

the senior management on preventive measures; and participation in pre-site planning.

Good planning and organization at each work site and the assignment of clear responsibility to the site supervisors is

fundamental to risk management and safety in construction. “Supervisor” here means the first level of supervision,

which on site is variously termed as “foreman”, “charge hand”, and so on. Each supervisor requires the direct support

of site management and shall seek to assure within his or her field of competence that:

• working conditions and equipment are safe;

• workplace safety and risk management measures are regularly inspected;

• potential environmental and social risks are managed effectively and responded to quickly if unexpected

issues arise;

• workers have been adequately trained for the job they are expected to do;

• social and environmental management measures, including workplace safety measures, are implemented;

• the best solutions are adopted using available resources and skills;

• necessary personal protective equipment is available and used.

Making the work site safe will require regular inspections and provision of the means for taking remedial measures.

The training of workers enables them to recognize the risks involved and how they can overcome them. Workers shall

be shown the safe way of getting a job done. The workers shall be involved directly, such as through the following:

• “Tool-Box Briefing”, a five- to ten-minute session with the supervisor just prior to starting a task gives the

workers and the supervisor a chance to talk about social and environmental risks, including safety problems,

likely to be encountered and potential solutions to those problems. This activity is simple to implement and it

may prevent a serious accident or issue;

• “Safety Check”, a check by workers that the work environment is safe before starting an operation may allow

them to take remedial action to correct an unsafe situation that could later endanger them, another worker,

or surrounding community.

6.1.5 Third Party Monitors

The Third-Party Monitoring Agent (TPMA) reports directly to the UNDP Project Manager, working in close collaboration

with the project M&E Specialist and with the Responsible Parties for project implementation. The TPMA supports the

UNDP project management team to provide the Project Board and other stakeholders with better means for learning

from field experience, improving service delivery to community, planning and allocating resources, and demonstrating

results. The TPMA is expected to provide UNDP with quarterly reports.

Reporting templates/checklists will incorporate social and environmental risk monitoring, including monitoring

implementation of agreed management measures.

6.2 Capacity Building and Training

Responsible Parties have the responsibility for ensuring systems are in place so that relevant employees, contractors

and other workers are aware of the environmental and social requirements for project implementation, including the

ESMF. Project stakeholders have noted that capacity building and training needs to be a priority.

Page 35: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

30

All project personnel will attend an initial induction training of relevant ESMF requirements, including health, safety,

environment and cultural heritage requirements.

Training will be conducted on a sustained basis. The following capacity building and training programmes will be in

place:

• Capacity building of headquarters and branch offices senior management (led by UNDP): To impart awareness

on essential regulatory and other requirements and elements of the ESMF, to help understand the

importance of social and environmental management from design stage through implementation. It is

essential that the trained manpower shall further carry out training and capacity building in their respective

organisations by acting as resource persons for such trainings.

• Capacity building of site engineers/site supervisors on ESMF requirements (led by Responsible Parties, with

UNDP support): To create awareness on specific social and environmental risks and management measures

for their control as applicable to the project activities and to build their capacity to carry out monitoring and

supervision activities in the field.

• Training and awareness of workers including contractual workers and local labour (led by Responsible Parties):

All workers engaged in any activity with the potential to cause serious social and/or environmental harm will

receive task specific training to ensure implementation of the site-specific management measures.

Training procedures shall take into account differing levels of responsibility, ability, language skills, literacy and risk

exposure.

The Responsible Parties shall ensure that persons under their control performing tasks related to environmental and social risk management are competent on the basis of appropriate education, training or experience, and shall retain associated records. Each sub-project should include a budget line for training to ensure capacities and skills of workers to implement risk management measures.

7 Stakeholder Engagement and Information Disclosure

7.1 Principles for Meaningful, Effective and Informed Stakeholder Engagement

The ECRP and its Responsible Parties will ensure meaningful, effective and informed stakeholder engagement in the

design and implementation of all sub-projects. Civil society actors and organizations, local communities and other key

stakeholders are crucial partners for project delivery and advancing sustainable development.

Stakeholder engagement supports the development of strong, constructive, and responsive relationships that are

critical for sound project design and implementation. Effective stakeholder engagement enhances project acceptance

and ownership and strengthens the social and environmental sustainability and benefits of supported interventions. It

is both a goal in itself – upholding the rights of citizens and others to participate in decisions that may affect them – as

well as an effective means for achieving project outcomes, including those related to democratic governance,

protecting the environment, promoting respect for human rights, and preventing and resolving conflict.

Meaningful, effective and informed stakeholder engagement will possess the following characteristics:

• Free of external manipulation, interference, coercion, and intimidation.

• Gender and age-inclusive and responsive.

• Culturally appropriate and tailored to the language preferences and decision-making processes of each

identified stakeholder group, including disadvantaged or marginalized groups.

• Based on prior and timely disclosure of accessible, understandable, relevant and adequate information,

including draft documents and plans.

• Initiated early in the project design process, continued iteratively throughout the project cycle, and adjusted

as risks and impacts arise.

• Addresses social and environmental risks and adverse impacts, and the proposed measures and actions to

address these.

• Seeks to empower stakeholders, particularly marginalized groups, and enable the incorporation of all relevant

views of affected people and other stakeholders into decision-making processes, such as project goals and

design, mitigation measures, the sharing of development benefits and opportunities, and implementation

issues.

• Documented and reported in accessible form to participants, in particular the measures taken to avoid or

minimize risks to and adverse impacts on the project stakeholders.

Page 36: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

31

• Consistent with States’ duties and obligations under international law.

7.2 Information Disclosure

Information disclosure refers to the provision of timely, accessible information regarding the project and its potential

social and environmental impacts to stakeholders in order to facilitate their meaningful, effective and informed

participation in project design and implementation. Stakeholders require access to relevant project and sub-project

information in order to understand potential project-related opportunities and risks and to engage in design and

implementation.

In addition to have access to general project information, stakeholders need access to screening reports, draft and final

assessments and management plans. This information is to be disclosed in a timely manner, in an accessible place, and

in a form and language understandable to affected persons and other stakeholders. These elements of effective

disclosure are briefly elaborated below:

• Timely disclosure: information on potential project-related social and environmental impacts and

mitigation/management measures should be provided in advance of decision-making. Draft screenings,

assessments and management plans should be provided in advance as part of the stakeholder consultation

process. In all cases, draft and final screenings, assessments and management plans must be disclosed and

consulted on prior to implementation of activities that may give rise to potential adverse social and

environmental impacts.

• Accessible information: Stakeholders need to be able to readily access information regarding assessments and

management plans. While local regulatory requirements might mandate availability of environmental

assessments in government offices, this may not be sufficient to ensure that local stakeholders can access the

information. Other means of dissemination may need to be considered, such as posting on websites, public

meetings, local councils or organizations, newsprint, television and radio reporting, flyers, local displays, direct

mail.

• Appropriate form and language: Information needs to be in a form and language that is readily

understandable and tailored to the target stakeholder group. Summary information from assessments and

management plans may need to be translated and presented by various means (e.g. written, verbal). Level of

technical detail, local languages and dialects, levels of literacy, roles of women and men, and local methods of

disseminating information are important considerations in devising appropriate forms of disclosure. A general

solicitation of feedback on project documents may not be an appropriate form of information sharing and

solicitation of input. Rather, the material may need to be presented in a contextual manner, such as the

presentation of options with key information and questions designed to solicit feedback. Appropriate forms of

proactive disclosure should be utilized beyond web posting of information. These may include radio

broadcasts, brochures, community postings, SMS, oral presentations, etc. Also, it is vital to ensure that

appropriate communication methods are devised to reach potentially marginalized and disadvantaged groups.

The stakeholder engagement process is an excellent moment to solicit from stakeholders the types of information they

want and need and the most appropriate formats and languages and mechanisms for dissemination.

The SES contain requirements for the disclosure of screening reports; draft and final social and environmental

assessments and management plans; and any required social and environmental monitoring reports. For further detail

on UNDP SES stakeholder engagement and information disclosure requirements please refer to the UNDP

guidance UNDP Guidance on Stakeholder Engagement -Annex 3.

7.3 ECRP Systems in Place for Stakeholder Engagement and Information Disclosure

Meaningful stakeholder engagement is required by PWP and SFD for participation in project intervention by

communities and individuals. The Standard Operating Procedures of both Responsible Parties include procedures for

community and stakeholder engagement within their project cycles as a key component of project identification,

design and implementation, and described a key component of the longer-term sustainability strategy for operations

and maintenance.

Community committees are set up at the onset of project at the identification and design phase and play a key role in

supporting field teams, facilitating implementation and in the sustainability of community assets that are built through

subprojects, after project closure. To sustain such community participation and engagement, subprojects include

provisions to set up such community committees and provide resources for training whenever required.

Page 37: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

32

The principles for sub-project cycle identification, development, and management specify that communities are

involved from the outset in the selection and design phases, through project closure.

To engage communities and reduce potential risks of conflicts between stakeholders over sub-projects a careful

selection criterion was developed by UNDP and Responsible Parties. While laying out an objective set of criteria, and

national data-based distress index, communities are also called upon to participate at the municipal level to engage in

prioritization of community projects and identification of beneficiaries.

Subprojects must meet the basic needs according to poverty and service needs provided in national indicators. Priority

is given to poorer communities. In addition to data provided through national indicators, community groups are

consulted to identify who will benefit from sub-projects, in this way stakeholders themselves are involved in the

selection and decision of who benefits from sub-projects.

In addition, some procedures include financial contribution by beneficiaries, proportionate to their means. This

contribution is seen as a necessary component for stakeholder engagement, providing a guarantee to future

sustainability through operation and maintenance of subprojects and aims to enhance the firm commitment to the

active participation of beneficiaries.

Both institutions include gender mainstreaming provisions as a means to ensuring equal participation of all

stakeholders in subprojects and provide opportunities to improve women’s participation in decision-making as

indicated in the above section on project impacts and risk, gender section.

Furthermore, in accordance with the ECRP approach to strengthening livelihoods and local economics, in sub-projects

that use community contracting, the procurement of civil works, construction materials, and the hiring of equipment,

transport and skilled laborers, is done by the communities themselves.

The TPMA also helps ensure stakeholders have been duly consulted and monitors their level of satisfaction with the ECRP project including with the sub-project selection criteria. TPM surveys have verified implementation of planned interventions, adherence to agreed implementation procedures, quality of implemented interventions, beneficiaries and community satisfaction on various aspects of project interventions and its effects/impacts on targeted beneficiaries and communities. Women and men, youth are interviewed separately to enable meaningful participation by marginalized groups. An example provided by TPMA report (see TPMA Report from April-June 2018) shows that cash for work interventions were highly satisfactory to beneficiaries in various aspects including project existence (98.5 percent) and beneficiary selection (98 percent). However, ESMF stakeholder consultations noted the need for strengthened and ongoing stakeholder engagement, bringing together the various stakeholders more regularly as true partners to help identify solutions to the challenges faced by the project. Stakeholder engagement will continue to be a priority of the project and project partners will continue to explore new and effective means to deliver on this commitment. Each sub-project should include a budget line for stakeholder engagement and training.

8 Grievance Redress Mechanism

8.1 Project-Level Grievance Mechanism

During the design, construction and implementation of any sub-project, a person or group of people may perceive or

experience potential harm, directly or indirectly due to the project activities. The grievances that may arise can be

related to social issues such as eligibility criteria and entitlements, disruption of services, temporary or permanent loss

of livelihoods and other social and cultural issues. Grievances may also be related to environmental issues such as

excessive dust generation, damages to infrastructure due to construction related vibrations or transportation of raw

material, noise, traffic congestions, decrease in quality or quantity of private/ public surface/ ground water resources

during irrigation rehabilitation, damage to home gardens and agricultural lands, etc.

Should such a situation arise, there must be a mechanism through which affected parties can resolve such issues in a

cordial manner with the project personnel in an efficient, unbiased, transparent, timely and cost-effective manner. To

achieve this objective, a Grievance Redress Mechanism has been included in the ESMF for this project.

The Grievance Redress Mechanism:

a. provides a legitimate process that allows for trust to be built between stakeholder groups and assures

stakeholders that their concerns will be assessed in a fair and transparent manner;

Page 38: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

33

b. allows simple and streamlined access to the Grievance Redress Mechanism for all stakeholders and provide

adequate assistance for those that may have faced barriers in the past to be able to raise their concerns;

c. provides clear and known procedures for each stage of the Grievance Redress Mechanism process, and

provides clarity on the types of outcomes available to individuals and groups;

d. ensures equitable treatment to all concerned and aggrieved individuals and groups through a consistent,

formal approach that, is fair, informed and respectful to a concern, complaints and/or grievances;

e. provides a transparent approach, by keeping any aggrieved individual/group informed of the progress of their

complaint, the information that was used when assessing their complaint and information about the

mechanisms that will be used to address it; and

f. enables continuous learning and improvements to the Grievance Redress Mechanism. Through continued

assessment, the learnings may reduce potential complaints and grievances.

The GRM will be gender- and age-inclusive and responsive and address potential access barriers to women, the elderly,

the disabled, youth and other potentially marginalized groups as appropriate to the Project. The GRM will not impede

access to judicial or administrative remedies as may be relevant or applicable and will be readily accessible to all

stakeholders at no cost and without retribution.

Information about the Grievance Redress Mechanism and how to make a complaint and/or grievance must be

communicated during the stakeholder engagement process and placed at prominent places for the information of the

key stakeholders.

All complaints and/or grievances regarding social and environmental issues can be received either orally (to the field

staff), by phone, in complaints box or in writing to the UNDP, PWP or SFD. A key part of the grievance redress

mechanism is the requirement for the Project Management Team and construction contractor to maintain a register of

complaints and/or grievances received at the respective project site offices, this includes grievances from workers. The

following information will be recorded:

a. time, date and nature of enquiry, concern, complaints and/or grievances;

b. type of communication (e.g. telephone, letter, personal contact);

c. name, contact address and contact number;

d. response and review undertaken as a result of the enquiry, concern, complaints and/or grievances; and

e. actions taken and name of the person taking action.

The project GRM is managed by PWP and SFD, who have a grievance mechanism in place. UNDP will work with the

Responsible Parties to assess the effectiveness of existing GRM and work to address capacity, accessibility, transparency,

gaps, etc. TPM reports and the ESMF stakeholder consultations both raise issues of a lack of awareness of affected-

people of the GRM and how to access it. Therefore, particular efforts will be made to strengthen ongoing

communications and outreach on the GRM.

8.2 UNDP Accountability Mechanism

In addition to the project-level and national grievance redress mechanisms, complainants have the option to access

UNDP’s Accountability Mechanism, with both compliance and grievance functions. The Social and Environmental

Compliance Unit investigates allegations that UNDP's Standards, screening procedure or other UNDP social and

environmental commitments are not being implemented adequately, and that harm may result to people or the

environment. The Social and Environmental Compliance Unit is housed in the Office of Audit and Investigations and

managed by a Lead Compliance Officer. A compliance review is available to any community or individual with concerns

about the impacts of a UNDP programme or project. The Social and Environmental Compliance Unit is mandated to

independently and impartially investigate valid requests from locally impacted people, and to report its findings and

recommendations publicly.

The Stakeholder Response Mechanism offers locally affected people an opportunity to work with other stakeholders to

resolve concerns, complaints and/or grievances about the social and environmental impacts of a UNDP project.

Stakeholder Response Mechanism is intended to supplement the proactive stakeholder engagement that is required of

UNDP and its Implementing Partners throughout the project cycle. Communities and individuals may request a

Stakeholder Response Mechanism process when they have used standard channels for project management and

quality assurance and are not satisfied with the response (in this case the project level grievance redress mechanism).

When a valid Stakeholder Response Mechanism request is submitted, UNDP focal points at country, regional and

headquarters levels will work with concerned stakeholders and Responsible Parties to address and resolve the

concerns. Visit www.undp.org/secu-srm for more details.

Page 39: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

34

8.3 World Bank Inspection Panel

The World Bank’s Inspection Panel is also available to affected people. The Inspection Panel is an independent

complaints mechanism for people and communities who believe that they have been, or are likely to be, adversely

affected by a World Bank-funded project. The Board of Executive Directors created the Inspection Panel in 1993 to

ensure that people have access to an independent body to express their concerns and seek recourse.

The Panel is an impartial fact-finding body, independent from the World Bank management and staff, reporting directly

to the Board. The Inspection Panel process aims to promote accountability at the World Bank, give affected people a

greater voice in activities supported by the World Bank that affect their rights and interests, and foster redress when

warranted.(www.inspectionpanel.org)

9 Monitoring, Reporting and Evaluation of ESMF Implementation

The ESMF and its procedures are to be reviewed regularly and on an ongoing basis by UNDP staff, PWP and SFD. The

objective is to update the ESMF to reflect knowledge gained during the course of project delivery/construction and to

reflect new knowledge.

Amendments will be made to the ESMF if:

• There are relevant changes to social and environmental conditions or generally accepted management

practices; or

• New or previously unidentified social and environmental risks are identified; or

• Information from the project monitoring and surveillance methods indicate that current control measures

require amendment to be effective; or

• There are changes to legislation that are relevant to the project; or

• There is a request made by a relevant regulatory authority.

When an update is made, all site personnel are to be made aware of the revision as soon as possible, e.g. through a

tool box meeting or written notification.

The Project Manager will monitor the overall implementation of the ESMF, most particularly the:

i. timely preparation of environmental and social screening forms for all subprojects (list of subprojects by risk

category by date)

ii. timely preparation and clearance of subproject ESIAs and ESMPs, as needed (list of instruments with dates)

iii. monitoring of ESMP implementation, including monitoring of mitigation measures and monitoring of

contractors environmental and social performance (indicators)

iv. training of project staff, implementing partners, and contractors (list of persons, dates and places)

The Project Manager will prepare:

i. biannual reports summarizing monitoring results, to be included in the Project’s Biannual Review Meetings

ii. an annual evaluation of all environmental and social monitoring activities, which will be submitted to the

World Bank as part of overall project implementation reporting

Monitoring and audit reports will be shared with the World Bank.

9.1 Management Information System (MIS)

Both PWP and SFD have a Management Information System in place to record project information and monitoring

results. The MIS provides an important mechanism to track information on environmental and social safeguard

implementation. A review will be conducted to identify opportunities to strengthen environmental and social

safeguard elements in the MIS.

Page 40: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

35

9.2 Sub-Project Self-Monitoring and Reporting

For construction activities, the Responsible Party/site supervisor will be responsible for daily inspections (e.g.

environmental inspections, Occupational Health & Safety) of the construction site.

The Responsible Parties will be responsible for the day-to-day compliance of the ESMF at the specific project site. The

Responsible Parties will maintain and keep all administrative and social and environmental records which would

include a log of complaints and incidents together with records of any measures taken to mitigate the cause of the

complaints or incidents (see below sections on incident reporting and on complaints).

9.2.1 Social, environmental and OHS incident reporting

Any incidents, including non-conformances to the procedures of the ESMF, are to be recorded using an Incident Record

and the details entered into a register. For any incident that causes or has the potential to cause material or significant

social and/or environmental harm, the site supervisor/designated officer shall notify the Responsible Party senior

management and ECRP Project Manager as soon as possible and no later than 48 hours. UNDP will also ensure

significant incidents are reported to the World Bank within 48 hours. The Responsible Party must cease work until

remediation has been completed as per the approval of Project Manager.

9.2.2 Daily and weekly inspection checklists

A daily social and environmental checklist (including OHS issues) is to be completed for active work sites with moderate

risks by the relevant site supervisor/designated officer and maintained within a register. A weekly social and

environmental checklist is to be completed and will include reference to any issues identified in the daily checklists

completed by the site supervisor or designated person. The completed checklist is to be forwarded to the site engineer

for review and follow-up if any issues are identified.

9.2.3 Corrective Actions

Any non-conformances to the ESMF are to be noted in weekly social and environmental inspections and logged into

the register. Depending on the severity of the non- conformance, the site supervisor/designated officer may specify a

corrective action on the weekly site inspection report. The progress of all corrective actions will be tracked using the

register. Any non-conformances and the issue of corrective actions are to be advised to Responsible Parties senior

management and ECRP Project Manager.

9.2.4 Auditing and Review

A consultant will be recruited to conduct an annual environmental, social and occupational health compliance and

performance audit by both PWP and SFD. The consultant is given a list of all subprojects, and he/she will select

randomly the subprojects to be audited, which should include all sectors and programs, in different stages of

subproject cycle including design, under implementation, and completed stages, and with different types/levels of risk.

The audit will include both a desk audit/review and a field audit. Consequently, an audit report will be prepared by the

consultant and presented to management. The executive summary of the audit report will be forwarded to the donors

while the detailed report will be distributed to all Responsible Party branches and UNDP Project Manager for correcting

deviations and lessons learning.

9.3 Sub-Project Third-Party Monitoring and Reporting

The TPMA is expected to provide an independent perspective and extend the reach of UNDP in the field. The TPMA will

monitor activities of two identified responsible parties (SFD and PWP) financed by the project. The TPMA is expected to

visit project sites quarterly based on a sampling methodology.

Monitoring of environmental and social risks and implementation of management measures will be included in Third

Party Monitoring templates and reports.

9.4 Monitoring Plan

Table 3. Summary of ESMF Monitoring, Reporting and Evaluation Activities

Page 41: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

36

Monitoring Activity Purpose/Action Frequency Expected Action Roles and Responsibilities

Annual evaluation To ensure Project Board is

updated on ESMF

implementation, issues,

and lessons learned.

Annually Include reporting on ESMF

implementation in

documentation prepared

for Biannual Review

Meetings

ECRP Project Manager

(informed by TPM reports,

self-reporting of sub-projects,

field visits)

Annual review and

audit

Identify issues and lessons

learned related to ESMF

implementation to support

overall project

implementation

Annually Hire consultant to conduct

review and audit of ECRP

portfolio, for both PWP

and SFD

PWP, SFD, and UNDP

Biannaul reports

(for biannual

review meetings)

To ensure Project Board is

updated on ESMF

implementation, issues,

and lessons learned.

Biannually Include reporting on ESMF

implementation in

documentation prepared

for Biannual Review

Meetings

ECRP Project Manager

(informed by TPM reports,

self-reporting of sub-projects,

field visits)

Quarterly

Monitoring

Qualitative and

quantitative review of

selection of projects,

engaging with local

stakeholders. Identification

of any new social and

environmental risks and

monitoring of

implementation of site-

specific management

plans.

Quarterly Apply TPM methodology,

to include consideration of

social, environmental and

occupational health risks

and management

TPMA and UNDP project

team

Field Visits Conduct field visits to spot-

check sub-projects and

ensure effective

implementation, including

ESMF implementation

Periodic Ensure risks are

appropriately identified

and managed. If new risks

identified, screening and

management plan to be

updated.

UNDP Project Management

Team

Learning Knowledge, good practices

and lessons learned

regarding social and

environmental risk

management will be

captured regularly, as well

as actively sourced from

other projects and partners

and integrated back into

the project.

At least annually Relevant lessons are

captured by the project

team and used to inform

management decisions.

UNDP Project Management

Team and UNDP Programme

Review and adapt

activities and

approach as

necessary

Internal review of data and

evidence from all

monitoring actions to

inform decision making.

At least annually Performance data, risks,

lessons and quality will be

discussed by the project

UNDP Project Management

Team and UNDP Programme

Page 42: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

37

board and used to make

course corrections.

Project Progress

Reports

As part of progress report

to be presented to the

Project Board and key

stakeholders, analysis,

updating and

recommendations for risk

management will be

included.

Annually, and at

the end of the

project (final

report)

Incorporation of progress

on risk management

elements, including ESMF

UNDP Project Management

Team

Site Inspections To ensure early

identification and

resolution of potential risks

Daily and weekly Completion of site

inspections checklists (to

include social,

environmental and

occupational hazards and

risks)

Responsible Parties (Site

Supervisors)

Page 43: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

38

Annex 1. Yemen ECRP Revised SES Screening

Project Information

1. Project Title Yemen Emergency Crisis Response Project (ECRP)

2. Project Number 00097850

3. Location (Global/Region/Country) Sana’a, Republic of Yemen

Part A. Integrating Overarching Principles to Strengthen Social and Environmental Sustainability

QUESTION 1: How Does the Project Integrate the Overarching Principles in order to Strengthen Social and

Environmental Sustainability?

Briefly describe in the space below how the Project mainstreams the human-rights based approach

The project upholds the principles of accountability and the rule of law, participation and inclusion, and equality and

non-discrimination based on gender, age, religion, political views or affiliation to parties to the current conflict, social

or geographical origin, birth or other status. UNDP will also ensure the meaningful, effective and informed

participation of stakeholders in the formulation, implementation, monitoring and evaluation of the ECRP. The project

also establishes a dedicated grievance mechanism and capacity to ensure that the duty-bearers are accountable to the

rights-holders for the actions undertaken in the course of the project.

Briefly describe in the space below how the Project is likely to improve gender equality and women’s empowerment

The project recognizes that in the midst of the current crisis in Yemen, women are adversely affected and at the same

time asked to take on new and additional roles as heads of households or income-earners. The project will actively

target women (at least 30%) to support their income-generation opportunities and contribute to the delivery of

community service and livelihood assets through Cash for Work and Cash for Services, and through earmarked funding

(accounting to 15% of the project budget) dedicated to address severe and acute malnutrition for pregnant and

lactating women (and children) by providing cash assistance (mothers are the recipients) and facilitating the affected

families’ access to nutrition services.

Briefly describe in the space below how the Project mainstreams environmental sustainability

An Environmental and Social Management Framework will be developed for the project. This will ensure that social

and environmental sustainability standards are applied to help mitigate potentially high adverse environmental and

social impacts in the selection, prioritization and implementation of subprojects at community level, which UNDP will

also closely monitor any negative environmental and social impact and ensure compliance with the safeguards

through Third Party Monitoring. See ESMF.

Page 44: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

39

Part B. Identifying and Managing Social and Environmental Risks

QUESTION 2: What are the

Potential Social and

Environmental Risks?

QUESTION 3: What is the level of

significance of the potential social and

environmental risks?

QUESTION 6: What social and

environmental assessment

and management measures

have been conducted and/or

are required to address

potential risks (for Risks with

Moderate and High

Significance)?

Risk Description Impact

and

Probabili

ty (1-5)

Significance

(Low,

Moderate,

High)

Comments Description of assessment and

management measures as

reflected in the Project design.

If ESIA or SESA is required note

that the assessment should

consider all potential impacts

and risks.

There is a risk that the Project

would exacerbate conflicts

among and/or the risk of

violence to project-affected

communities and individuals

I = 3

P = 4

Moderate The conflict context may

produce social tensions during

project implementation,

concerning prioritization of

subprojects, locations, and

selection of participants.

Measures to be undertaken

include a clear definition of

targeting and selection criteria

based on data provided by the

UN Clusters; participatory

preparation and

implementation of subprojects

by communities and relevant

stakeholders; frequent

communication with

communities and local

stakeholders; grievance redress/

stakeholder response

mechanism procedures to

ensure timely handling of

grievance redress; and public

disclosure of the reasons for the

rejection of subprojects, if any,

to increase transparency. In

addition, the project will have a

communication strategy which

will include consultations with

government counterparts,

citizen engagement and public

outreach. The project is

implemented by SFD and PWP

which are operating relatively

independently from the

government.

Page 45: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

40

CO will monitor the situation

closely and on a systematic

manner in order to make sure

the project achieves its goals

within the agreed timeline

The Project may potentially

reproduce discriminations

against women based on

gender, especially regarding

participation in design and

implementation or access to

opportunities and benefits.

I= 3

P=2

Moderate The ECRP has mainstreamed

gender considerations through

its project approach, addressing

gender equality from project

identification, site selection,

management and oversight.

The project has actively

targeted women (at least 30%)

to support their income-

generation opportunities and

contribute to the delivery of

community service and

livelihood assets through Cash

for Work and Cash for Services,

and through earmarked funding

(accounting to 15% of the

project budget) dedicated to

address severe and acute

malnutrition for pregnant and

lactating women (and children)

by providing cash assistance

(mothers are the recipients) and

facilitating the affected families’

access to nutrition services.

Small scale farming and

livestock may cause adverse

impacts to habitats (e.g.

modified, natural, and critical

habitats) and/or ecosystems

and ecosystem services ( For

example, through habitat loss,

conversion or degradation,

fragmentation, hydrological

changes)

Activities will include:

Watershed Management/Water

Channels, Rehabilitation of

Farm Lands, Rehabilitation of

Farm Irrigation Infrastructure,

Agriculture Infrastructure,

Agriculture Input Provision,

Support to Livestock Producers.

Livestock activities involve the

creation of yards in addition to

other.

I=3

P=2

Moderate Although the

projects are small

scale in nature, the

cumulative effects

of providing

support to

communities may

involve inadvertent

impacts on

ecosystems that

can result in

negative effect to

ecosystem services

provision and

biodiversity.

When further sub-

project screening is

conducted more

information will be

available as to the

extent of the

impacts and

management

measures required.

The ECRP applies a

precautionary approach to the

use, development, and

management of natural

habitats, the ecosystem

services of such habitats, and

living natural resources.

As an integral part of the social

and environmental assessment

process, direct and indirect

impacts on natural resources,

biodiversity and ecosystem

services in the Project’s area of

influence are identified and

addressed. The assessment

process will consider, inter alia

(i) risks of habitat and species

loss, degradation and

fragmentation, invasive alien

species, overexploitation,

hydrological changes, nutrient

loading, pollution, and (ii)

differing values (e.g. social,

cultural, economic) attached to

Page 46: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

41

biodiversity and ecosystem

services by potentially affected

communities. Potential

cumulative and induced impacts

will be assessed. Project-related

impacts across potentially

affected landscapes should be

considered.

Natural resources will be

managed in a sustainable

manner. This includes

safeguarding biodiversity and

the life-supporting capacity of

air, water, and soil ecosystems.

Sustainable management also

ensures that people who are

dependent on these resources

are properly consulted, women

and men have opportunities to

equally participate in

development, and benefits are

shared equitably.

The Project involves the

production and/or harvesting of

fish populations or other

aquatic species

I = 1

P = 3

Low The project will target artisanal

fishermen using small حرفيون

boats with one off-board petrol

engine, i.e. not used in deep

waters and will not risk

overfishing. The project will

carefully monitor the activities

of the fishermen during its

implementation.

Some of the fishermen will be

equipped with fish finders, to

help expedite the search of the

fish and thus economize the use

of fuel. As the targeted

fishermen will be operating on

small boats using traditional

methods of fishing, there is low

risk that the use of the fish

finders will lead to over catching

the fish. The project will also

work with fishing associations

responsible for ensuring that

fishing protocols are in place

and adhered to, to protect fish

stocks and regulate seasonal

controls on fishing. The project

will be implemented in line with

the Biodiversity Conservation

and Sustainable NRM of the

SES which includes fishing

Page 47: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

42

management. The concept of

sustainable and responsible

fishing will be promoted

through this partnership.

Through its direct support to

small scale fishermen, the

project will improve community

livelihoods and training on

quality and resource

sustainability to include the

reduction of wastage.

The Project involves extraction,

diversion or containment of

surface or ground water

I = 3

P = 3

Moderate The project

rehabilitates

existing water

supply

infrastructure at a

small-scale and will

not create new

extraction points or

new infrastructure

for containment or

diversion of water.

The project aims to rehabilitate

or construct a total of 500,000

m3 of water supply (including

water catchments, reservoirs

and maintenance of clean water

supply etc.), which are relatively

small-scale.

In case of pumping wells, a

monitoring of water level is

needed to control the pumping

and avoid draw down beyond

the recharge (water balance).

Overall the associated risks are

expected to be small scale and

readily managed. Site-specific

management plans will need to

be in place.

The potential outcomes of the Project may be sensitive or vulnerable to potential impacts of climate change.

Yemen has a predominantly

semi-arid to arid climate and is

highly vulnerable to climate

change-related impacts such as

drought, extreme flooding,

changes of rainfall patterns,

increased storm

frequency/severity, sea level

rise. Literature show that the

main sectors under stress are:

water resources, agriculture,

and coastal zones. Water

scarcity related to prolonged

droughts, evaporation, drying

up of wells, excessive rainfall

(which produces flash flooding

and can potentially wipe out

crops) caused by rainfall

variability are the key issues.

The ECRP project activities

related to agriculture (including

I = 3

P = 2

Moderate Proposed subprojects will be

screened and assessed for

climate change-related risks

and impacts. The ECRP will

ensure that the status and

adequacy of relevant climatic

information is identified. If

significant potential risks are

identified, further scoping and

assessment of vulnerability,

potential impacts, and

avoidance and mitigation

measures, including

consideration of alternatives to

reduce potential risks, will be

required. The climate change

risk assessment may focus on :

-The viability or longer-term

sustainability of project

outcomes due to potential

climate change. This will involve

the identification of

components that are sensitive

or vulnerable to emerging or

Page 48: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

43

farming, livestock) and fisheries

and water (irrigation,

catchment, conservation), will

be most sensitive and

vulnerable to the impacts of

climate change.

Some project activities that aim

to increase water availability,

may inadvertently lead to

depletion of groundwater

resources or diversion of

sources to some communities in

detriment of others, if not

properly managed based on

appropriate climate risk

information and management

measures.

anticipated manifestations of

climate change.

-Risks that a project may

increase exposure to climate

change. Project components

must be assessed for potential

unintended or unforeseen

increases in vulnerability to

climate change.

-Potential social, gender, and

age risks, based on the

differentiated impacts of

climate change.

Elements of Project

construction, operation, or

decommissioning pose

potential safety risks to local

communities and workers.

I = 3

P = 3

Moderate The project works

through SFD and

PWP who will be

implementing the

infrastructure

rehabilitation

projects (small-

scale) according to

their Operational

Manuals vetted by

UNDP, which

includes safety

standards. UNDP

will carefully

monitor the

implementation

through TPM and

regular

consultations with

the partners.

Occupational Health and Safety

risks are a priority for the ECRP

project. An OHS Framework

and Toolkit has been developed

and should be applied at the

sub-project level. This

complements measures already

applied by PWP and SFD

through implementation of

their operating manuals. See

OHS Framework for further

details.

Potential impacts may include

insufficient safety

standards used in construction/

rehabilitation of small-scale

infrastructure; dust and noise

during construction/

rehabilitation; and/or

insufficient removal of

construction waste after project

completion. There may also be

safety issues related to the

ongoing conflict and security

measures in place.

OHS risks will be monitored

carefully and all incidents

reported.

Failure of structural elements of

the Project poses risks to

communities and workers (e.g.

collapse of buildings or

infrastructure)

I = 4

P = 2

Moderate . The project works through SFD

and PWP who will be

implementing the infrastructure

rehabilitation projects (small-

scale) according to their

operating manuals and the

Page 49: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

44

ESMF, which includes safety

standards. UNDP will carefully

monitor the implementation

through TPM and regular

consultations with the partners.

The project aims to support the

rehabilitation/reconstruction of

community infrastructure (i.e.

damaged classrooms, small-

scale infrastructure for flood

prevention etc.). These will be

mitigated by the 20-years of

experience of PWP in managing

project impacts successfully

according to their Operational

Manual (endorsed/approved by

UNDP BMS) that lay out clear

criteria for small-scale

infrastructure rehabilitation to

identify, eliminate and address

potential safety risks and UNDP

field monitoring including TPM.

Potential risks to community

health and safety due to the

transport, storage, and use

and/or disposal of hazardous or

dangerous materials (e.g.

explosives, fuel and other

chemicals during construction

and operation)

I = 4

P = 2

Moderate Appropriate management

measures have been put in

place. A detailed risk

categorization was developed

for the purpose of identifying

sub-project level risks to enable

halting any salient high-risk

projects from further

implementation until adequate

management measures are put

in place. Additionally, a

specialized consultant was hired

to develop management plans,

screening checklists, and ensure

high frequency of field

monitoring. Additionally,

support to the Responsible

Parties has been reinforced by

training and monitoring and

capacity assessments. The

results the latter measures

taken by UNDP are included in a

detailed report “OHS

Framework”. The report

highlights both the stated

results and management

measures underway.

Potential for increased health

risks (e.g. from water-borne or

other vector-borne diseases or

communicable infections.

I = 2

P = 1

Low In cases where there may be

pollution, a site-specific

pollution prevention plan

Page 50: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

45

The project will support the

construction and/or

rehabilitation of pit latrines,

sewage systems, provide

agriculture inputs that may

include pesticides, support

small health care centers

infrastructure or services,

cleaning up public spaces that

may include municipal solid

waste, and sewage that may

include hazardous/human

excreta and waste.

should be put in place and

monitored.

Sub-projects will avoid the

release of pollutants, and when

avoidance is not feasible,

minimize and/or control the

intensity and mass flow of their

release. This applies to the

release of pollutants to air,

water, and land due to routine,

non-routine, and accidental

circumstances.

Pollution prevention and

control technologies and

practices consistent with

international good practice are

applied during the project life

cycle. The technologies and

practices applied will be tailored

to the hazards and risks

associated with the nature of

the Project.

Potential for activities that

result in localized pollution.

The project will support the

construction and/or

rehabilitation of pit latrines,

sewage systems, provide

agriculture inputs, support small

health care centers

infrastructure or services,

cleaning up public spaces that

may include municipal solid

waste, and sewage that may

include hazardous/human

excreta and waste. Minimal and

localized air, water, and noise

pollution possible.

I = 2

P = 1

Low In cases where there may be

pollution, a site-specific

pollution prevention plan

should be put in place and

monitored.

Sub-projects will avoid the

release of pollutants, and when

avoidance is not feasible,

minimize and/or control the

intensity and mass flow of their

release. This applies to the

release of pollutants to air,

water, and land due to routine,

non-routine, and accidental

circumstances.

Pollution prevention and

control technologies and

practices consistent with

international good practice are

applied during the project life

cycle. The technologies and

practices applied will be tailored

to the hazards and risks

associated with the nature of

the Project.

Sub-project may involve the

application of pesticides that

may have a negative effect on

I = 2

P = 1

Low Pesticide use and management:

For Projects involving pest

management activities, the

Page 51: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

46

the environment or human

health.

social and environmental

assessment will ascertain that

any pest and/or vector

management activities related

to the ECRP are based on

integrated pest management

approaches and aim to reduce

reliance on synthetic chemical

pesticides. The integrated

pest/vector management

programme will entail

coordinated use of pest and

environmental information

along with available pest/ vector

control methods, including

cultural practices, biological,

genetic and, as a last resort,

chemical means to prevent

unacceptable levels of pest

damage. When pest

management activities include

the use of pesticides, pesticides

that are low in human toxicity,

known to be effective against

the target species, and have

minimal effects on non-target

species and the environment

will be selected. The health and

environmental risks associated

with pest management should

be minimized with support, as

needed, to institutional capacity

development, to help regulate

and monitor the distribution

and use of pesticides and

enhance the application of

integrated pest management.

The ECRP will not use products

that fall in Classes Ia (extremely

hazardous) and Ib (highly

hazardous) of the World Health

Organization Recommended

Classification of Pesticides by

Hazard. WHO Class II

(moderately hazardous)

pesticides will not be used if the

relevant Responsible Party lacks

restrictions on distribution and

use of these chemicals or

facilities to handle, store, apply

and dispose of these products

properly, or if they are likely to

be accessible to personnel

without proper training and

equipment. Pesticides will be

handled, stored, applied and

Page 52: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

47

disposed of in accordance with

international good practice such

as the FAO International Code

of Conduct on the Distribution

and Use of Pesticides.

The ECRP may result in

interventions that would

potentially adversely impact

sites, structures, or objects with

historical, cultural, artistic,

traditional or religious values or

intangible forms of culture (e.g.

knowledge, innovations,

practices).

As the project conducts small

scale infrastructure activities

related to community works

such as road paving, community

reservoirs and piping, and

repairing of school buildings in

addition to others these project

activities, although may not

target the rehabilitation of

Cultural Sites directly, they may

be located in the vicinity of

cultural heritage sites and

consequently produce

unintended negative effects on

such sites.

I = 3

P = 3

Moderate The ECRP will avoid and/or

mitigate any impacts on cultural

heritage through alternative

project siting and design. The

impacts on Cultural Heritage

resulting from project activities,

including mitigating measures,

may not contravene the

national legislation, or its

obligations under relevant

international treaties and

agreements.

Where potential adverse

impacts are unavoidable,

appropriate mitigation

measures will be identified and

incorporated as an integral part

of the social and environmental

assessment process. Where

potential adverse impacts may

be significant, a Cultural

Heritage Management Plan

should be developed as part of

the Environmental and Social

Management Plan (ESMP).

For projects with potential

adverse impacts, qualified and

experienced independent

experts will assess the project’s

potential impacts on Cultural

Heritage using, among other

methodologies, field-based

surveys and involving

meaningful, effective, and

informed stakeholder

consultations as part of social

and environmental assessment

process.

Note SFD has a Quality

assurance system in place for

Cultural Heritage interventions

and a separate Cultural Heritage

Unit.

A number of specialized

experts1 lead and also provide

1 E. Ronald Lewcock - Professor of Architecture at Georgia Tech. Institute and Cambridge University.

Page 53: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

48

technical supervision for SFD’s

main conservation operations

through direct on-site

supervision or regular visits that

take place on monthly, bi-

monthly & semiannual basis.

Additionally, the technical

quality of SFD’s interventions

was positively acknowledged by

a World Bank review mission

undertaken by a Cultural

Heritage expert.

QUESTION 4: What is the overall Project risk categorization?

Select one (see SESP for guidance) Comments

Low Risk ☐

Moderate Risk X Given the need for further

assessment and management

measures at the sub-project

level, an Environmental and

Social Management

Framework will be developed

for the project.

High Risk ☐

QUESTION 5: Based on the identified risks

and risk categorization, what requirements of

the SES are relevant?

Check all that apply Comments

Principle 1: Human

Rights X

Principle 2: Gender

Equality and

Women’s

Empowerment

X

1. Biodiversity

Conservation and

Natural Resource

Management

X

2. Climate Change

Mitigation and

Adaptation

X

Dr. Chris Edens (Archaeologist – former director of the American Institute for Yemeni Studies).

Dr. Ala'a Al Habashi, Professor Eves Eagles, Eng. IssamAwwad, Renzo Ravagnan, Abdullah Al Hadrami

Page 54: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

49

3. Community Health,

Safety and Working

Conditions

X

4. Cultural Heritage X

5. Displacement and

Resettlement ☐

6. Indigenous Peoples ☐

7. Pollution Prevention

and Resource

Efficiency

X

Final Sign Off

Signature Date Description

QA Assessor

Edrees Al-Qadasi , YECRP PM a.i

Signature:

14/03/2019 UNDP staff member responsible for the Project, typically a

UNDP Programme Officer. Final signature confirms they

have “checked” to ensure that the SESP is adequately

conducted.

QA Approver

Auke Lootsma,

Resident Representative

Signature:

14/03/2019 UNDP senior manager, typically the UNDP Deputy Country

Director (DCD), Country Director (CD), Deputy Resident

Representative (DRR), or Resident Representative (RR). The

QA Approver cannot also be the QA Assessor. Final signature

confirms they have “cleared” the SESP prior to submittal to

the PAC.

PAC Chair UNDP chair of the PAC. In some cases PAC Chair may also be

the QA Approver. Final signature confirms that the SESP was

considered as part of the project appraisal and considered in

recommendations of the PAC.

Page 55: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

50

SESP Attachment 1. Social and Environmental Risk Screening Checklist

Checklist Potential Social and Environmental Risks

Principles 1: Human Rights Answer

(Yes/No

)

1. Could the Project lead to adverse impacts on enjoyment of the human rights (civil, political, economic,

social or cultural) of the affected population and particularly of marginalized groups? Yes

2. Is there a likelihood that the Project would have inequitable or discriminatory adverse impacts on affected

populations, particularly people living in poverty or marginalized or excluded individuals or groups? 2 No

3. Could the Project potentially restrict availability, quality of and access to resources or basic services, in

particular to marginalized individuals or groups? Yes

4. Is there a likelihood that the Project would exclude any potentially affected stakeholders, in particular

marginalized groups, from fully participating in decisions that may affect them? No

5. Is there a risk that duty-bearers do not have the capacity to meet their obligations in the Project? No

6. Is there a risk that rights-holders do not have the capacity to claim their rights? No

7. Have local communities or individuals, given the opportunity, raised human rights concerns regarding the

Project during the stakeholder engagement process? No

8. Is there a risk that the Project would exacerbate conflicts among and/or the risk of violence to project-

affected communities and individuals? Yes

Principle 2: Gender Equality and Women’s Empowerment

1. Is there a likelihood that the proposed Project would have adverse impacts on gender equality and/or the

situation of women and girls? No

2. Would the Project potentially reproduce discriminations against women based on gender, especially

regarding participation in design and implementation or access to opportunities and benefits? Yes

3. Have women’s groups/leaders raised gender equality concerns regarding the Project during the

stakeholder engagement process and has this been included in the overall Project proposal and in the risk

assessment?

Yes

4. Would the Project potentially limit women’s ability to use, develop and protect natural resources, taking

into account different roles and positions of women and men in accessing environmental goods and

services?

No

2 Prohibited grounds of discrimination include race, ethnicity, gender, age, language, disability, sexual orientation, religion, political or other opinion, national or social or geographical origin, property, birth or other status including as an indigenous person or as a member of a minority. References to “women and men” or similar is understood to include women and men, boys and girls, and other groups discriminated against based on their gender identities, such as transgender people and transsexuals.

Page 56: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

51

For example, activities that could lead to natural resources degradation or depletion in communities who

depend on these resources for their livelihoods and well being

Principle 3: Environmental Sustainability: Screening questions regarding environmental risks are encompassed

by the specific Standard-related questions below

Standard 1: Biodiversity Conservation and Sustainable Natural Resource Management

1.1 Would the Project potentially cause adverse impacts to habitats (e.g. modified, natural, and critical

habitats) and/or ecosystems and ecosystem services?

For example, through habitat loss, conversion or degradation, fragmentation, hydrological changes

Yes

1.2 Are any Project activities proposed within or adjacent to critical habitats and/or environmentally sensitive

areas, including legally protected areas (e.g. nature reserve, national park), areas proposed for protection,

or recognized as such by authoritative sources and/or indigenous peoples or local communities?

No

1.3 Does the Project involve changes to the use of lands and resources that may have adverse impacts on

habitats, ecosystems, and/or livelihoods? (Note: if restrictions and/or limitations of access to lands would

apply, refer to Standard 5)

No

1.4 Would Project activities pose risks to endangered species? No

1.5 Would the Project pose a risk of introducing invasive alien species? No

1.6 Does the Project involve harvesting of natural forests, plantation development, or reforestation? Yes

(small

scale)

1.7 Does the Project involve the production and/or harvesting of fish populations or other aquatic species? Yes

1.8 Does the Project involve significant extraction, diversion or containment of surface or ground water?

For example, construction of dams, reservoirs, river basin developments, groundwater extraction

No

(small

scale)

1.9 Does the Project involve utilization of genetic resources? (e.g. collection and/or harvesting, commercial

development)

No

1.10 Would the Project generate potential adverse transboundary or global environmental concerns? No

1.11 Would the Project result in secondary or consequential development activities which could lead to adverse

social and environmental effects, or would it generate cumulative impacts with other known existing or

planned activities in the area?

For example, a new road through forested lands will generate direct environmental and social impacts (e.g.

felling of trees, earthworks, potential relocation of inhabitants). The new road may also facilitate

encroachment on lands by illegal settlers or generate unplanned commercial development along the route,

potentially in sensitive areas. These are indirect, secondary, or induced impacts that need to be considered.

No

Page 57: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

52

Also, if similar developments in the same forested area are planned, then cumulative impacts of multiple

activities (even if not part of the same Project) need to be considered.

Standard 2: Climate Change Mitigation and Adaptation

2.1 Will the proposed Project result in significant3 greenhouse gas emissions or may exacerbate climate

change?

No

2.2 Would the potential outcomes of the Project be sensitive or vulnerable to potential impacts of climate

change?

Yes

2.3 Is the proposed Project likely to directly or indirectly increase social and environmental vulnerability to

climate change now or in the future (also known as maladaptive practices)?

For example, changes to land use planning may encourage further development of floodplains, potentially

increasing the population’s vulnerability to climate change, specifically flooding

No

Standard 3: Community Health, Safety and Working Conditions

3.1 Would elements of Project construction, operation, or decommissioning pose potential safety risks to

local communities?

Yes

3.2 Would the Project pose potential risks to community health and safety due to the transport, storage, and

use and/or disposal of hazardous or dangerous materials (e.g. explosives, fuel and other chemicals during

construction and operation)?

Yes

3.3 Does the Project involve large-scale infrastructure development (e.g. dams, roads, buildings)? No

3.4 Would failure of structural elements of the Project pose risks to communities? (e.g. collapse of buildings or

infrastructure)

Yes

3.5 Would the proposed Project be susceptible to or lead to increased vulnerability to earthquakes,

subsidence, landslides, erosion, flooding or extreme climatic conditions?

No

3.6 Would the Project result in potential increased health risks (e.g. from water-borne or other vector-borne

diseases or communicable infections such as HIV/AIDS)?

Yes

3.7 Does the Project pose potential risks and vulnerabilities related to occupational health and safety due to

physical, chemical, biological, and radiological hazards during Project construction, operation, or

decommissioning?

Yes

3.8 Does the Project involve support for employment or livelihoods that may fail to comply with national and

international labor standards (i.e. principles and standards of ILO fundamental conventions)?

Yes

3.9 Does the Project engage security personnel that may pose a potential risk to health and safety of

communities and/or individuals (e.g. due to a lack of adequate training or accountability)?

No

Standard 4: Cultural Heritage

3 In regards to CO2, ‘significant emissions’ corresponds generally to more than 25,000 tons per year (from both direct

and indirect sources). [The Guidance Note on Climate Change Mitigation and Adaptation provides additional

information on GHG emissions.]

Page 58: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

53

4.1 Will the proposed Project result in interventions that would potentially adversely impact sites, structures,

or objects with historical, cultural, artistic, traditional or religious values or intangible forms of culture (e.g.

knowledge, innovations, practices)? (Note: Projects intended to protect and conserve Cultural Heritage

may also have inadvertent adverse impacts)

Yes

4.2 Does the Project propose utilizing tangible and/or intangible forms of cultural heritage for commercial or

other purposes?

No

Standard 5: Displacement and Resettlement

5.1 Would the Project potentially involve temporary or permanent and full or partial physical displacement? No

5.2 Would the Project possibly result in economic displacement (e.g. loss of assets or access to resources due

to land acquisition or access restrictions – even in the absence of physical relocation)?

No

5.3 Is there a risk that the Project would lead to forced evictions?4 No

5.4 Would the proposed Project possibly affect land tenure arrangements and/or community based property

rights/customary rights to land, territories and/or resources?

No

Standard 6: Indigenous Peoples

6.1 Are indigenous peoples present in the Project area (including Project area of influence)? No

6.2 Is it likely that the Project or portions of the Project will be located on lands and territories claimed by

indigenous peoples?

No

6.3 Would the proposed Project potentially affect the human rights, lands, natural resources, territories, and

traditional livelihoods of indigenous peoples (regardless of whether indigenous peoples possess the legal

titles to such areas, whether the Project is located within or outside of the lands and territories inhabited

by the affected peoples, or whether the indigenous peoples are recognized as indigenous peoples by the

country in question)?

If the answer to the screening question 6.3 is “yes” the potential risk impacts are considered potentially

severe and/or critical and the Project would be categorized as either Moderate or High Risk.

No

6.4 Has there been an absence of culturally appropriate consultations carried out with the objective of

achieving FPIC on matters that may affect the rights and interests, lands, resources, territories and

traditional livelihoods of the indigenous peoples concerned?

No

6.5 Does the proposed Project involve the utilization and/or commercial development of natural resources on

lands and territories claimed by indigenous peoples?

No

6.6 Is there a potential for forced eviction or the whole or partial physical or economic displacement of

indigenous peoples, including through access restrictions to lands, territories, and resources?

No

6.7 Would the Project adversely affect the development priorities of indigenous peoples as defined by them? No

4 Forced evictions include acts and/or omissions involving the coerced or involuntary displacement of individuals, groups, or communities from homes and/or lands and common property resources that were occupied or depended upon, thus eliminating the ability of an individual, group, or community to reside or work in a particular dwelling, residence, or location without the provision of, and access to, appropriate forms of legal or other protections.

Page 59: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

54

6.8 Would the Project potentially affect the physical and cultural survival of indigenous peoples? No

6.9 Would the Project potentially affect the Cultural Heritage of indigenous peoples, including through the

commercialization or use of their traditional knowledge and practices?

No

Standard 7: Pollution Prevention and Resource Efficiency

7.1 Would the Project potentially result in the release of pollutants to the environment due to routine or non-

routine circumstances with the potential for adverse local, regional, and/or transboundary impacts? Yes

7.2 Would the proposed Project potentially result in the generation of waste (both hazardous and non-

hazardous)? Yes

7.3 Will the proposed Project potentially involve the manufacture, trade, release, and/or use of hazardous

chemicals and/or materials? Does the Project propose use of chemicals or materials subject to

international bans or phase-outs?

No

7.4 Will the proposed Project involve the application of pesticides that may have a negative effect on the

environment or human health?

Yes

7.5 Does the Project include activities that require significant consumption of raw materials, energy, and/or

water?

No

(small-

scale)

Annex 2. Specific Risks and Management Measures by Project Activity

Sub-Project

Activity

Potential

Impacts

Proposed Mitigation

Measures

Means of

insurance and

compliance

Building

New

Terraces

Air Quality and Noise

Construction

Construction may impact air

quality and generate noise. This

results mainly from excavation,

site grading, vehicle loading

and unloading, and other

construction-related activities.

Operation

Potential impacts on ambient

air quality would result from

odors and gaseous emissions

Air Quality and Noise

Construction

Use dust control measures

onsite, such as water spraying

for dust suppression;

Regulate site access;

Cover lorries transporting

friable construction materials

and spoil;

Prohibit open air burning;

SFD with

beneficiaries

CBOs oversees

construction and

operation

activities and

conducts visual

inspection with

the assistance of

a representative

of the local

community

Contracts and

PCU coordinator

ensures that

Page 60: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

55

generated by stagnant water–

water may increase humidity

- Exposure to or production

cracks, humidity exfoliation

may happen due to high

humidity in the area

- Odor due to increase relative

humidity

- Deterioration of terraces walls

my lead to erosion or flash

flood

- Disturbing the stability of

slopes and soils due to large

quantities of materials extracted

to build the terraces

- Interruption of some runoff

water

Soil Quality and

Surface/Ground water

Pattern/contamination

Construction

Impacts on soil quality may

result from the following

construction activities:

- Change in composition,

filtration.

- Minor oil spills from

construction equipment

Operation

Contamination of soils and

groundwater with chemicals

used in farming and chemicals

and oil spills from equipment.

Spills and leaks at liquid

impoundment areas for fuels,

solvents, waste and from

infrastructure equipment, may

infiltrate through soil pores,

under gravitational forces, and

contaminate ground water

aquifers;

Discharge into surface waters,

or alteration of surface water

quality, including but not

limited to temperature,

dissolved oxygen, turbidity,

solids

Wastewater

Maintain machinery in good

working conditions to

minimize emissions; and

Provide adequate protective

wear for workers, and

equipment must be

maintained regularly to avoid

any emissions;

Pre-treat gases emitted

Operation

Conserve energy use to

reduce fuel combustion;

Mitigation to the first factor

could be addressed by

frequent inspection to the

terraces construction and

apply the required

maintenance. Regular

inspection and examinations

for mentioned impacts and

address them through

maintenance replacement of

materials spoiled.

Minimizing entrance of

heavy machines to reduce

vibration impact. For

handling and occupational

health applying strict

protection regulation for

occupational health

measurements is critical and

a site-specific management

plan is required-including all

operational stages from

handling, washing,

classification, freezing,

backing up to loading and

distribution to consumption

Soil Quality and

Surface/Ground water

pattern/contamination

Construction

Apply, inspect and maintain

temporary/permanent erosion

and sediment control

measures (e.g. silt fences,

contractors

implement

environmental

management

plans/regulations

and that

contractors

perform

continuous

inspection and

monitoring of

areas of potential

pollution and/or

uses with the

potential to result

in soil

contamination;

Complaints from

local community

Review of tender

and bid

documents by

SFD

Page 61: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

56

Potential generation of waste

water resulting from the project

activities and/ or sub-projects

during both construction and

operation.

-contamination of water, soil

and agricultural products with

insecticides and herbicides

Biological Resources- Flora &

Fauna

Removal or disturbance of

natural vegetation, A loss or

disturbance to a unique, rare or

threatened plant community, A

reduction in the numbers or

restriction in the range of any

unique, rare or threatened

species of plants such as

bushes, A deterioration of

existing wildlife habitat,

Introduction of any factors

(light, fencing, noise, human

presence and/or domestic

animals) which could hinder

the normal activities of wildlife

rapid growth vegetation,

erosion control matting) to

exposed areas;

Restrict movement of

vehicles to designated tracks;

Operation

Maintain periodically

vehicles and equipment to

prevent leaks;

Maintain records and

procedures for equipment

maintenance, handling and

storage of liquid fuels and

chemicals; lab regular testing

for ground and surface water

Wastewater

Encourage drying

mechanisms to avoid

stagnant water

Use of bio-treatment to

prevent chemical

contamination

Apply IPMP to avoid

negative impact of pesticides

and herbicides if required,

apply biological control for

pests. 5

Biological Resources- Flora

& Fauna

Applying environmental

operational standards within

the legal, policy and

management framework of

the project to minimize the

negative impact on the

environment using the

comparative advantage of the

different project counterparts.

Compliance with SFD’s

5 Integrated Pest Management Plan as per World Bank operational manual at http://web.worldbank.org/WBSITE/EXTERNAL/TOPICS/EXTARD/EXTPESTMGMT/0

Page 62: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

57

ESMF is critical for the

conservation of biodiversity

Coordination with relevant

stakeholders is very

important, Proper selection of

sites as to avoid damaging

natural habitat. Tender

document will have to

include provisions for site

specific ESMP.

Open

Catchment

Covered

Rainwater

Harvesting

Cisterns for

Domestic

Use

Air Quality and Noise

Construction

Construction may impact air

quality and generate noise. This

results mainly from excavation,

site grading, vehicle loading

and unloading, and other

construction-related activities.

Operation

- Bad odors from donkeys'

droppings together with water

spills from extracting water

- Mosquito breeding may occur

as well as algae growth,

Soil Quality and Ground

Water Contamination

Construction

Impacts on soil quality may

result from the following

construction activities: Site

clearance, site grading,

excavation, infrastructure, and

oil leaks from

vehicles/equipment.

Operation

Donkeys' droppings together

with water spills may percolate

and contaminate groundwater.

-Potential for stagnant

water

Biological Resources- Flora &

Fauna

Construction & Operation

Air Quality and Noise

Construction

Use dust control measures

onsite, such as water spraying

for dust suppression;

Regulate site access;

Cover lorries transporting

friable construction materials

and spoil;

Prohibit open air burning;

Maintain machinery and

vehicles in good working

conditions to minimize

emissions; and

Provide adequate protective

wear for workers

Operation

-Assess the ecology of

disease carriers in the

watershed

- Employ suitable prevention

and mitigation measures,

including education of local

people

and construction workers,

-Monitor disease and public

health indicators,after

construction, and take

corrective measures (e.g.

education, medical) as

needed

- Treatment of stagnant water

to avoid biological

contamination

Biological Resources- Flora

& Fauna

Villages CBOs

with support

from

Governorate

lined Units in

addition to

SFD/PWP

conducting

visual inspection

with the

assistance of a

representative of

the local

community.

Contracts and

ECO ensures that

contractors

implement

environmental

and social

management

plans/regulations

and that

Technical

officials with

CBOs perform

continuous

inspection and

monitoring of

areas of potential

pollution and/or

uses with the

potential to result

in soil

contamination;

Review of tender

and bid

documents by

SFD

Page 63: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

58

Removal or disturbance of

natural vegetation, A loss or

disturbance to a unique, rare or

threatened plant community, A

reduction in the numbers or

restriction in the range of any

unique, rare or threatened

species of plants such as

indigenous herbs, A

deterioration of existing

wildlife habitat, Introduction of

any factors (light, fencing,

noise, human presence and/or

domestic animals) which could

hinder the normal activities of

wildlife

- Applying environmental

operational standards within

the legal, policy and

management framework of

the project to minimize the

negative impact on the

environment using the

comparative advantage of the

different project counterparts.

- Proper selection of sites as

to avoid damaging natural

habitat.

- Tender document will have

to include provisions for site

specific ESMP and

implementation, when

required.

Rooftop

rainwater

harvesting

cisterns

Construction

- Owners tend to have the

cistern very near to the house

sometimes directly adjacent to

the house and this may cause

house damage due possible

water leakage,

- Land acquisition problem may

arise,

Operation

- There is a possibility for

Mosquito breeding and algae

growth,

- Contamination of stored water

as a result of using dirty

bucket and rope for extracting

water.

Clogging of the inlet coarse

filter may cause loss of

precious water to the owner.

Construction

- Proper selection of sites far

from buildings and insure

water tightness of the

cistern,

- Help solving land

acquisition amicably,

Operation

- Educated the owners to

keep the cistern close after

each use and use clean

bucket and rope for

extracting water,

- Clean the course filter

frequently,

- Frequently inspect the

cistern for leakage and the

houses for expected

damages from leakages,

- House owner

and supervising

team to select

good location

for the cistern.

- Supervising

technician and

engineer to

insure the

quality of work

and the water

tightness of the

cistern

Flood

Protection

Alteration or damaging natural

habitat during construction,

contamination may occur from

construction infrastructure and

materials, run-off surface water

obstacles and divert to cause

other flooding hazards

Avoiding damaging natural

habitat during constructions

or minimize it (proper site

selection, use

environmentally friendly

materials, prepare materials

off-site, etc.)

Tender document will have

to include provisions for site

specific ESMP.

Good practice in design

All technical

stakeholders are

involved in

inspection of

quality assurance

with village

CBO and overall

supervision of

SFD/PWP

Page 64: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

59

Water

Saving

Irrigation

Systems

Plastic installation and dioxin

made material could be a

source of contamination for

water and soil and thus public

health

Using materials made from

environmental friendly

materials and good practice

Apply specific site ESMP

All technical

stakeholder are

involved in

inspection of

quality assurance

and WEU with

village CBO

Stone

Pavement

Air Quality and Noise

Construction

Construction may impact air

quality and generate noise. This

results mainly from excavation,

site grading, vehicle loading

and unloading, and other

construction-related activities.

Operation

Potential impacts on ambient

air quality would result from

odors and gaseous emissions

generated by stagnant water –

water may increase humidity

- Exposure to or production

cracks, humidity exfoliation

may happen due to high

humidity in the area

- Odor due to increase relative

humidity

- Deterioration of stone

pavement may lead to erosion

or flash flood

- disturbing the stability of

slopes and soils due to large

quantities used in building

pavements

- interruption of some runoff

water

Soil Quality and

Surface/Ground water

pattern/contamination

Construction

Impacts on soil quality may

result from the following

construction activities:

Change in composition,

filtration.

Operation

Air Quality and Noise

Construction

Use dust control measures

onsite, such as water spraying

for dust suppression;

Regulate site access;

Cover lorries transporting

construction materials;

Prohibit open air burning;

Maintain machinery in good

working conditions to

minimize emissions; and

Provide adequate protective

wear for workers

Pre-treat gases emitted

Operation

Conserve energy use to

reduce fuel combustion;

Regular inspection and

examinations for mentioned

impacts and address them

through maintenance

replacement of materials

spoiled. Minimizing entrance

of heavy machines to reduce

vibration impact. Applying

occupational health

protection regulations and

measurements is critical for

all operational stages from

stone cutting through finish

of pavement. Soil Quality

and Surface/Ground water

pattern/contamination

Design

Include groundwater

recharging means such as

leaching and pits and

trenches to mitigate the

impacts of low infiltration

resulted from pavement

SFD/PWP with

beneficiaries

CBOs oversees

construction and

operation

activities and

conducts visual

inspection with

the assistance of

a representative

of the local

community.

PCU coordinator

ensures that

contractors

implement

environmental

management

plans/regulations

and that

contractors

perform

continuous

inspection and

monitoring of

areas of potential

pollution and/or

uses with the

potential to result

in soil

contamination;

Complaints from

local community

Review of tender

and bid

documents by

SFD/PWP

Page 65: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

60

Contamination of soils and

groundwater with chemicals

used in construction and

chemicals and oil spills from

equipment.

Spills and leaks at liquid

impoundment areas for fuels,

solvents, waste and from

infrastructure equipment, may

infiltrate through soil pores,

under gravitational forces, and

contaminate ground water

aquifers;

Discharge into surface waters,

or alteration of surface water

quality, including but not

limited to temperature,

dissolved oxygen, turbidity,

solids

Wastewater

Potential generation of waste

water resulting from the project

activities and/ or sub-projects

during both construction and

operation.

Biological Resources- Flora &

Fauna

Removal or disturbance of

natural vegetation, A loss or

disturbance to a unique, rare or

threatened plant community, A

reduction in the numbers or

restriction in the range of any

unique, rare or threatened

species of plants such as

bushes, A deterioration of

existing wildlife habitat,

Introduction of any factors

(light, fencing, noise, human

presence and/or domestic

animals) which could hinder

the normal activities of wildlife

Construction

Apply, inspect and maintain

temporary/permanent erosion

and sediment control

measures (e.g. silt fences,

rapid growth vegetation,

erosion control matting) to

exposed areas;

Restrict movement of

vehicles to designated tracks

Operation

Periodically maintain

vehicles and equipment to

prevent leaks;

Maintain records and

procedures for equipment

maintenance, handling and

storage of liquid fuels and

chemicals; lab regular testing

for ground and surface water

Wastewater

Encourage drying

mechanisms to avoid

stagnant water

Use of bio-treatment to

prevent chemical

contamination

Biological Resources- Flora

& Fauna

Applying environmental

operational standards within

the legal, policy and

management framework of

the project to minimize the

negative impact on the

environment using the

comparative advantage of the

different project counterparts.

Compliance with SFD

criteria is critical for the

conservation of biodiversity.

Coordination with relevant

stakeholders is very

important. Proper selection of

sites as to avoid damaging

natural habitat. Tender

document will have to

include provisions for site

specific ESMP.

Page 66: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

61

Basic

services

facilities:

Education,

Health, etc.

Construction

-Dispute among beneficiaries

on the Location

-Water pollution due to

wastewater disposal of

temporary latrines

-Spread out of construction

waste

-Spread out of solid municipal

waste

Operation

Types of health waste can

include:

-Human tissue and blood;

-Soiled surgical dressings and

swabs;

-Discarded syringe needles;

-Other contaminated sharp

instruments;

- Microbiological cultures and

potentially infected wastes from

laboratories;

-Excretions; and

-Drugs and other

pharmaceutical products.

-Radioactive wastes need to be

managed and treated separately

from other healthcare wastes,

and are not covered here (will

require separate EMP)

-Human feces spread

around the site

-Water pollution due to

wastewater disposal of

school bathrooms

Proper selection of sites as to

avoid dispute among

beneficiaries on the location.

Tender document will have

to include provisions for site

specific ESMP.

-Applying occupational

health risk control measures

regulations and procedures

-Locate latrines, septic

systems and soakaways at

least 30m from any water

body (e.g. stream, river, lake,

pond)

-Ensure adequate design,

installation and maintenance

of latrines, holding tanks,

septic systems and

wastewater soakaways. This

is especially important where

the water table is

high or soils have a high clay

or sand content

-Ensure adequate spacing

between latrines and

soakaways

- Tender document for

hazardous wastes will have to

include provisions for site

specificmanagement

measures specified in ESMP.

Determine the approximate

volumes of waste materials

by category (e.g. sharps,

body tissues, dressings,

pharmaceutical products,

non-hazardous healthcare

wastes, etc.), and design the

management system to deal

with each waste category

separately as required

- Assess current practices and

address the priority gaps and

risks, building on any

successful aspects of the

current system. All measures

and facilities should be

planned within an overall

strategy for hazardous

healthcare waste

management. This overall

strategy will ensure

consistent and efficient

methods, and sharing of good

practices.

All technical

stakeholders are

involved in

inspection of

quality assurance

with village

CBO

Page 67: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

62

- Provide specialized, clearly

labeled containers for

hazardous healthcare wastes

to separate them at source,

manage the risks of exposure,

and secure the wastes before

removal for treatment or

storage.

- Plan, design, construct and

operate a shared treatment

facility. Types of facilities

include heat treatment

disinfection, incineration,

chemical & biological

treatment.

- Until a shared treatment

facility is established, employ

interim measures to ensure

the safe and secure storage of

wastes. In some cases, an

appropriate interim measure

will be to bury the waste in

deep (e.g. >2m) trenches in

municipal disposal sites, and

ensure the trenches are

immediately covered with

other municipal solid waste.

-Implementing the Self

Monitoring and Follow up

and sewage treatment

Implementing the items in

the TD related to dealing

with municipal solid wastes

and the components needed

for SWMP

Rural

Feeder Road

Construction

Construction may impact air

quality and generate noise. This

results mainly from excavation,

site grading, vehicle loading

and unloading, and other

construction-related activities.

Solid wastes

Construction wastes

Historical monuments

Green areas

Sanitary drainage

Deformation of grades

Blockage of water canals and

drainage course at their

intersection with road.

-Good practice during

construction. Proper

treatment of solid waste and

other byproduct during

construction

-Applying occupational

health risk control measures

regulations and procedures

-Apply suitable design for

natural water courses and

putting measures for

preserving wildlife

-Avoiding damaging natural

habitat during constructions

or minimize it (proper site

selection, use

environmentally friendly

materials, prepare materials

off-site, etc.)

All technical

stakeholders are

involved in

inspection of

quality assurance

with village

CBO and overall

supervision of

SFD

Page 68: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

63

Alteration or damaging natural

habitat during construction,

contamination may occur from

construction infrastructure and

materials, run-off surface water

obstacles and divert to cause

other flooding hazards. A

deterioration of existing

wildlife habitat, Introduction of

any factors (light, fencing,

noise, human presence and/or

domestic animals) which could

hinder the normal activities of

wildlife

Operation

Abrasion of road

Increase of traffic accidents

-Avoid creating congested

and unsafe road conditions at

intersections, and in villages

and towns

-Good practice in design to

avoid traffic accidents such

as Sloping of road Curves

-Include components that

reduce traffic accidents such

as speed breakers and speed

limits signs

-Tender document will have

to include provisions for site

specific ESMP.

Improving

Rural

Markets

Construction

Construction may impact air

quality and generate noise. This

results mainly from excavation,

site grading, vehicle loading

and unloading, and other

construction-related activities.

Solid wastes

Construction wastes

Historical monuments

Green areas

Sanitary drainage

Deformation of grades

Operation

Solid waste, wastewater from

market latrines may cause soil

and water sources pollution

Construction

-Maintain equipment in good

working condition to reduce

emissions and noise,

-Use dust control measures

onsite, such as water spraying

for dust suppression;

-Good practice associated

with quality assurance and

regular site inspection

-Cover lorries transporting

friable construction materials

-Maintain a system for

collecting and disposing

garbage during construction

-Collect construction wastes

and transport them to the

agreed site

-Tendering should include

specific site ESMP

-Applying occupational

health risk control measures

regulations and procedures

Operation

-Enforce the solid waste

management system that

should have been developed

by the SA at the preparation

stages

District/town/vill

age councils with

support from

CBOs and SFD

Page 69: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

64

-Maintain good operation and

maintenance of market

latrines

Water

Supply

During design

-Health: Vector breeding sites;

-Land use: Disputes about

designed project site

on privately owned land, or

disconcerting areas of public,

touristic interest, disturbing

wildlife etc.

-Disputes about

designed route of

pipes through privately

owned land

-Land

Resources: Ground water

pollution from pit

latrines polluting the underlying

aquifer.

During construction:

- Air: Increased dust during

excavation and burial of pipes.

-Hygienic conditions

around public collection

points by

paving at least 1 m² apron

concrete slab under the water

taps with proper drainage and

fencing.

-Discuss the planned

site with landowners to

get approval. If land cannot

be obtained through

voluntary land donation, it

needs to change the design to

communal owned land or to

land with less expected

conflicts. Consider drop of

sub- project if problems are

not resolved.

-Discuss the planned

route with landowners

to get their approval. If the

land cannot be obtained

through voluntary land

donation, it needs to change

the planned route to avoid

conflicts.

- Ground water quality

testing at source

development and

regular intervals.

Soil/site inspection

before latrine

construction. Latrines to

be more

than 50 m from wells.

-Applying occupational

health risk control measures

regulations and procedures

-Coordinate with local

authorities to avoid or

minimize disruption to basic

services such as water and

sewer.

-Inform nearby households.

SFD/PWP

Environmental

Specialist

And Local NGOs

Page 70: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

65

- Health: Collection, handling

and disposal of solid waste.

- Infrastructure services:

Possible damage to water

supply pipes paved roads,

cables, existing cesspits, leaking

or blowout of water reservoir.etc.

-Noise: Increased levels of

noise and vibration

- Safety: possibility of

Accidents

- Increased Traffic: Disruptions

of water supply and local access

- Water: Pit latrines can

pollute the underlying aquifer.

Protect excavation works

with proper shielding

scaffolds.

Spraying water during

excavation might reduce the

dust. Workers wear protective

masks

- Take health and safety

measures when disposal of

excavated soil to a safe

location.

-Proper maintenance and

inspection of water pipes and

community reservoirs to

ensure leaks or damage are

avoided and repaired quickly

if/when identified to prevent

ruptures.

-Avoid causing damages.

Dispose all waste and soil

to a safe location.

Repair pavement on the

completion of the

Works

- Inform nearby houses.

Avoid work during

night hours.

Provide workers with

Protection

- Protect work zones

with portable scaffold

sheets.

Provide proper support for

trench sides to protect

against their collapse.

Improve the readiness

of health facilities in the

region to deal with

emergency cases. Provide

workers with protective

clothing.

- Inform the affected

houses in advance and

keep disruptions as

short as possible

Contracts to include

provisions for chance find.

Training will take place

Page 71: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

66

Archaeological find:

Damaging important

and/or precious cultural

heritage

Safety: possibility of accidents

During Operation:

- Health: The possible

formation of vector breeding

stagnant effluent ponds.

Water: Ground water

Pollution from Pit latrine

for crew/supervisors,

to spot potential

archaeological finds. In the

event of a potential find,

liaise with the archaeological

department at MoC or a local

university for quick

assessment and action

Protect construction site from

trespassers.

Improve the readiness of

health facilities in the region

to deal with emergency cases.

Provide workers with

protective clothing.

Take necessary actions for

fighting vectors (spraying

with insecticides,

reclamation of stagnant

pools, using nets on

windows and beds, etc.)

- Ground water quality

testing at source at regular

intervals.

Sewerage

Networks

During design:

Water: Land use: Disputes

about designed route of

pipes through privately owned

land

During construction:

- Air: Increased dust during

excavation and burial of pipes

- Health: Removal and disposal

of waste material from

- Discuss the planned

route with landowners

to get their approval. If the

land cannot be obtained

through voluntary land

donation, it needs to change

the planned route to avoid

conflicts

-Applying occupational

health risk control measures

regulations and procedures

Spraying water during

excavation might reduce the

dust. Workers wear protective

masks

-Avoid causing damages.

SFD/PWP

Environmental

Specialist

EPA

Local NGOs

Page 72: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

67

(existing) pits. Collection,

handling and disposal of solid

waste.

- Infrastructure services:

Possible destruction

of water supply pipes,

paved roads, cables, existing

cesspits, .etc.

Noise: Increased levels of noise

and vibration

Occupational Health and Safety

Traffic: Disruptions of water

supply and local access

- Archaeological find:

Damaging important

and/or precious cultural

heritage

Take health and safety

measures when demolishing

existing cesspits and on the

disposal of sludge and

polluted excavated soil.

Dispose all polluted waste

and soil to a safe location.

Repair pavement on the

completion of the

Works

- Inform nearby houses.

Avoid work during

night hours.

- Protect work zones with

portable scaffold

sheets.

Provide proper support for

trench sides to protect

against their collapse.

Improve the readiness of

health facilities in the region

to deal with emergency cases.

Provide workers with proper

safety equipment and

clothing.

Inform the affected

houses in advance and

keep disruptions as

short as possible.

- Contracts to include

provisions for chance find.

Training will take place for

crew/supervisors,

to spot potential

archaeological finds. In the

event of a potential find,

liaise with the archaeological

department at MoC or a local

university for quick

assessment and action.

- Protect construction site

from trespassers.

- Improve the readiness

of health facilities in the

region to deal with

emergency cases.

Page 73: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

68

Safety: possibility of accidents

Schools During design:

Land use: Disputes about

designed project site on

privately owned land, or

disconcerting areas of public,

touristic interest, disturbing

wildlife etc.

Health: Lack or failure of

sanitation facilities

During construction:

Noise: Increased levels of noise

and vibration.

- Archaeological find:

Damaging important and/or precious cultural

heritage.

Safety: Possibility of

accidents/hazards

Discuss the planned site

with landowners to get

approval. If the land cannot be

obtained through voluntary

land donation, it needs to

change the design to

communal owned land or to

land with less expected

conflicts.

Add sanitation facilities to

the design or upgrade

existing facilities.

Inform nearby houses.

Avoid work during night

hours.

- Training will take place for crew/supervisors, to spot potential archaeological finds. In the event of a potential find, liaise with the archaeological department at MoC or a local university for quick assessment and action.

- Protect construction

site from trespassers.

SFD/PWP

Environmental

Specialist

EPA

Local NGOs

Page 74: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

69

Provide proper support for

trench sides to protect

against their collapse.

Improve the readiness

of health facilities in the

region to deal with

emergency cases.

Provide workers with

protective clothing.

-Applying occupational

health and safety risk

control measures

regulations and procedures

Page 75: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

70

Annex 3. Environmental and Social Management Plan - Indicative Outline

Please refer to the UNDP SES Guidance Note on Assessment and Management for additional information.

The content of the ESMP may be presented in different formats (per templates of SFD and PWP) but should

address the following elements:

(1) Project Information: Project title and brief description of project activities, location and surrounding

area. Note key stakeholders. Inclusion of drawing or map

(2) Impacts and Mitigation Measures: Identifies measures and actions in accordance with the mitigation

hierarchy that avoid, or if avoidance not possible, reduce potentially significant adverse social and

environmental impacts to acceptable levels. Specifically, the ESMP: (a) identifies and summarizes all

anticipated significant adverse social and environmental impacts; (b) describes – with technical details –

each mitigation measure, including the type of impact to which it relates and the conditions under which it

is required (e.g., continuously or in the event of contingencies), together with designs, equipment

descriptions, and operating procedures, as appropriate; (c) estimates any potential social and

environmental impacts of these measures and any residual impacts following mitigation; and (d) takes into

account, and is consistent with, other required mitigation plans (e.g. for displacement, indigenous peoples).

(2) Monitoring: Identifies monitoring objectives and specifies the type of monitoring, with linkages to the

impacts assessed in the environmental and social assessment and the mitigation measures described in the

ESMP. Specifically, the monitoring section of the ESMP provides (a) a specific description, and technical

details, of monitoring measures, including the parameters/indicators to be measured, methods to be used,

sampling locations, frequency of measurements, detection limits (where appropriate), and definition of

thresholds that will signal the need for corrective actions; and (b) monitoring and reporting procedures to

(i) ensure early detection of conditions that necessitate particular mitigation measures, and (ii) furnish

information on the progress and results of mitigation.

(3) Capacity development and training: To support timely and effective implementation of social and

environmental project components and mitigation measures, the ESMP draws on the environmental and

social assessment of the existence, role, and capability of responsible parties on site or at the agency and

ministry level. Specifically, the ESMP provides a description of institutional arrangements, identifying which

party is responsible for carrying out the mitigation and monitoring measures (e.g. for operation,

supervision, enforcement, monitoring of implementation, remedial action, financing, reporting, and staff

training). Where support for strengthening social and environmental management capability is identified,

ESMP recommends the establishment or expansion of the parties responsible, the training of staff and any

additional measures that may be necessary to support implementation of mitigation measures and any

other recommendations of the environmental and social assessment.

(4) Stakeholder Engagement: Outlines plan to engage in meaningful, effective and informed consultations

with affected stakeholders. Includes information on (a) means used to inform and involve affected people

in the assessment process; (b) summary of stakeholder engagement plan for meaningful, effective

consultations during project implementation, including identification of milestones for consultations,

information disclosure, and periodic reporting on progress on project implementation; and (c) description

of effective processes for receiving and addressing stakeholder concerns and grievances regarding the

project’s social and environmental performance.

Page 76: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

71

(5) Implementation action plan (schedule and cost estimates): For all four above aspects (mitigation,

monitoring, capacity development, and stakeholder engagement), ESMP provides (a) an implementation

schedule for measures that must be carried out as part of the project, showing phasing and coordination

with overall project implementation plans; and (b) the capital and recurrent cost estimates and sources of

funds for implementing the ESMP. These figures are also integrated into the total project cost tables. Each

of the measures and actions to be implemented will be clearly specified and the costs of so doing will be

integrated into the project's overall planning, design, budget, and implementation.

Page 77: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

72

Annex 4. Guidance for Submitting a Grievance

Guidance for Submitting a Request to UNDP Social and Environmental Compliance Unit (SECU) and/or the Stakeholder Response Mechanism (SRM) [for more information go to www.undp.org/secu-srm]

Purpose of this form

- If you use this form, please put your answers in bold writing to distinguish text - The use of this form is recommended, but not required. It can also serve as a guide

when drafting a request.

This form is intended to assist in:

(1) Submitting a request when you believe UNDP is not complying with its social or environmental policies or commitments and you are believe you are being harmed as a result. This request could initiate a ‘compliance review’, which is an independent investigation conducted by the Social and Environmental Compliance Unit (SECU), within UNDP’s Office of Audit and Investigations, to determine if UNDP policies or commitments have been violated and to identify measures to address these violations. SECU would interact with you during the compliance review to determine the facts of the situation. You would be kept informed about the results of the compliance review.

and/or

(2) Submitting a request for UNDP “Stakeholder Response” when you believe a UNDP project is having or may have an adverse social or environmental impact on you and you would like to initiate a process that brings together affected communities and other stakeholders (e.g., government representatives, UNDP, etc.) to jointly address your concerns. This Stakeholder Response process would be led by the UNDP Country Office or facilitated through UNDP headquarters. UNDP staff would communicate and interact with you as part of the response, both for fact-finding and for developing solutions. Other project stakeholders may also be involved if needed.

Please note that if you have not already made an effort to resolve your concern by communicating directly with the government representatives and UNDP staff responsible for this project, you should do so before making a request to UNDP’s Stakeholder Response Mechanism.

Confidentiality If you choose the Compliance Review process, you may keep your identity confidential (known only to the Compliance Review team). If you choose the Stakeholder Response

Page 78: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

73

Mechanism, you can choose to keep your identity confidential during the initial eligibility screening and assessment of your case. If your request is eligible and the assessment indicates that a response is appropriate, UNDP staff will discuss the proposed response with you, and will also discuss whether and how to maintain confidentiality of your identity.

Guidance

When submitting a request please provide as much information as possible. If you accidentally email an incomplete form, or have additional information you would like to provide, simply send a follow-up email explaining any changes.

Information about You

Are you…

1. A person affected by a UNDP-supported project?

Mark “X” next to the answer that applies to you: Yes: No:

2. An authorized representative of an affected person or group?

Mark “X” next to the answer that applies to you: Yes: No:

If you are an authorized representative, please provide the names of all the people whom you are representing, and documentation of their authorization for you to act on their behalf, by attaching one or more files to this form.

3. First name:

4. Last name:

5. Any other identifying information:

6. Mailing address:

7. Email address:

8. Telephone Number (with country code):

9. Your address/location:

10. Nearest city or town:

11. Any additional instructions on how to contact you:

12. Country:

What you are seeking from UNDP: Compliance Review and/or Stakeholder Response

You have four options:

• Submit a request for a Compliance Review;

• Submit a request for a Stakeholder Response;

• Submit a request for both a Compliance Review and a Stakeholder Response;

• State that you are unsure whether you would like Compliance Review or Stakeholder Response and that you desire both entities to review your case.

13. Are you concerned that UNDP’s failure to meet a UNDP social and/or environmental policy or commitment is harming, or could harm, you or your community? Mark “X” next to the answer that applies to you: Yes: No:

14. Would you like your name(s) to remain confidential throughout the Compliance Review process?

Page 79: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

74

Mark “X” next to the answer that applies to you: Yes: No:

If confidentiality is requested, please state why:

15. Would you like to work with other stakeholders, e.g., the government, UNDP, etc. to jointly resolve a concern about social or environmental impacts or risks you believe you are experiencing because of a UNDP project?

Mark “X” next to the answer that applies to you: Yes: No:

16. Would you like your name(s) to remain confidential during the initial assessment of your request for a response?

Mark “X” next to the answer that applies to you: Yes: No:

If confidentiality is requested, please state why:

17. Requests for Stakeholder Response will be handled through UNDP Country Offices unless you indicate that you would like your request to be handled through UNDP Headquarters. Would you like UNDP Headquarters to handle your request?

Mark “X” next to the answer that applies to you: Yes: No:

If you have indicated yes, please indicate why your request should be handled through UNDP Headquarters:

18. Are you seeking both Compliance Review and Stakeholder Response?

Mark “X” next to the answer that applies to you: Yes: No:

19. Are you unsure whether you would like to request a Compliance Review or a Stakeholder Response? Mark “X” next to the answer that applies to you: Yes: No:

Information about the UNDP Project you are concerned about, and the nature of your concern:

20. Which UNDP-supported project are you concerned about? (if known):

21. Project name (if known):

22. Please provide a short description of your concerns about the project. If you have concerns about UNDP’s failure to comply with its social or environmental policies and commitments, and can identify these policies and commitments, please do (not required). Please describe, as well, the types of environmental and social impacts that may occur, or have occurred, as a result. If more space is required, please attach any documents. You may write in any language you choose

23. Have you discussed your concerns with the government representatives and UNDP staff responsible for this project? Non-governmental organisations?

Mark “X” next to the answer that applies to you: Yes: No:

If you answered yes, please provide the name(s) of those you have discussed your concerns with

Name of Officials You have Already Contacted Regarding this Issue:

Page 80: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

75

First Name Last Name Title/Affiliation Estimated

Date of

Contact

Response from the

Individual

24. Are there other individuals or groups that are adversely affected by the project?

Mark “X” next to the answer that applies to you: Yes: No:

25. Please provide the names and/or description of other individuals or groups that support the request:

First Name Last Name Title/Affiliation Contact Information

Please attach to your email any documents you wish to send to SECU and/or the SRM. If all of your attachments do not fit in one email, please feel free to send multiple emails.

Submission and Support

To submit your request, or if you need assistance please email: [email protected]

Complaints Registration Form at PWP

Complaints registration form at PWP

.................................................التاريخ:project Noرقم المشروع:..Date ..............................

Projectاسم المشروع: .

Name...........................................................................................

Name ofاسم الشاكي:......

complainant..............................................................................

Page 81: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

76

Complaintنص الشكوى:.

content .........................................................................................

.............................................................................Actions takenاإلجراءات المتخذه: ...

The date of resolving theتاريخ انتهاء المشكله: ..

complaints ...................................................

..............................................................................................Commentsالمالحظات:..............

Follow-up department مدير إدارة المتابعة Responsible person المختص: Manager

signature التوقيع signature :التوقيع

Complaint Handling Mechanism (CHM) Online Form for SFD [for more information go to https://chm.sfd-yemen.org/complaint/online-form/]

Page 82: Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General Management Structure and Responsibilities ... GRM Grievance Redress Mechanism ... NGO

77

Annex 5. OHS Framework

(attached separately)

Annex 6. OHS Toolkit

(attached separately)

Annex 7. PWP Operational Manual

(attached separately)

Annex 8. PWP Environmental and Social Management Framework (2014)

(attached separately)

Annex 9. SFD Operational Manual

(attached separately)

Annex 10. SFD Phase IV Environmental and Social Management Framework (2014)

(attached separately)

Annex 11. Summary of ECRP ESMF Stakeholder Consultations in Sana’a and Aden

(attached separately)

Annex 12. Third-Party Monitoring Report – ESMF Stakeholder Consultation

(attached separately)