Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General...
Transcript of Environmental and Social Management Framework: Yemen … self... · 2020-04-04 · 6.1 General...
Environmental and Social Management Framework: Yemen Emergency Crisis Response Project (ECRP)
29 March 2019
Table of Contents
Acronyms ................................................................................................................................................................ 1
Executive Summary ................................................................................................................................................ 1
1 Introduction .................................................................................................................................................... 5
2 Project Description ......................................................................................................................................... 5
2.1 Description of Baseline Environmental and Socioeconomic Conditions ........................................... 6
2.2 Summary of Key Results and Activities ............................................................................................... 7
2.2.1 PWP Project Component (1.2) ........................................................................................................ 7
2.2.2 SFD Project Components (1.1 and 1.3)........................................................................................... 8
3 Legal and Regulatory Framework .................................................................................................................. 9
3.1 National Legislation, Policies and Regulations .................................................................................... 9
3.1.1 National Environmental Action Plan ............................................................................................... 9
3.1.2 National Biodiversity Strategy and Action Plan .............................................................................. 9
3.1.3 National Water Sector Strategy and Investment Program ............................................................ 9
3.1.4 Water Law ........................................................................................................................................ 9
3.1.5 Environmental Protection Law ...................................................................................................... 10
3.1.6 Labour Law ..................................................................................................................................... 10
3.1.7 PWP and SFD Operating Procedures ............................................................................................ 11
3.2 International Agreements and Protocols .......................................................................................... 11
3.3 UNDP’s Social and Environmental Standards ................................................................................... 11
3.4 World Bank Requirements ................................................................................................................. 12
4 Social and Environmental Impacts .............................................................................................................. 13
4.1 Conflict ................................................................................................................................................ 15
4.1.1 Activities That May Result in Conflict Risks .................................................................................. 15
4.1.2 Management Measures ................................................................................................................ 16
4.2 Gender and Social Inclusion............................................................................................................... 17
4.2.1 Activities That May Result in Gender and Social Inclusion Impacts or Risks .............................. 17
4.2.2 Management Measures ................................................................................................................ 17
4.3 Biodiversity and Natural Resources................................................................................................... 18
4.3.1 Activities That May Result in Biodiversity and Natural Resources Impacts or Risks .................. 18
4.3.2 Management Measures ................................................................................................................ 19
ii
4.4 Climate Change .................................................................................................................................. 20
4.4.1 Activities That May Result in Climate Change Impacts and Risks ............................................... 20
4.4.2 Management Measures ................................................................................................................ 20
4.5 Community Health, Safety and Working Conditions (including OHS) ............................................. 20
4.5.1 Activities That May Result in Community Health, Safety, Working Condition Impacts and Risks
21
4.5.2 Management Measures ................................................................................................................ 21
4.6 Cultural Heritage ................................................................................................................................ 23
4.6.1 Activities That May Result in Cultural Heritage Impacts and Risks ............................................. 23
4.6.2 Management Measures ................................................................................................................ 23
4.7 Pollution Prevention and Resource Efficiency .................................................................................. 24
4.7.1 Activities That May Result in Pollution and Resource Efficiency Impacts and Risks .................. 24
4.7.2 Management Measures ................................................................................................................ 24
5 Procedures to Address Social and Environmental Impacts ....................................................................... 25
5.1 Sub-Project Screening and Classification Requirements.................................................................. 25
5.1.1 PWP Sub-projects .......................................................................................................................... 26
5.1.2 SFD Sub-projects ............................................................................................................................ 26
5.2 Site-Specific Assessment and Management Requirements ............................................................. 27
6 Institutional Arrangements and Capacity Building ..................................................................................... 27
6.1 General Management Structure and Responsibilities ..................................................................... 27
6.1.1 World Bank ..................................................................................................................................... 27
6.1.2 Project Board (Biannual Review Meetings) .................................................................................. 27
6.1.3 UNDP .............................................................................................................................................. 28
6.1.4 Responsible Parties ........................................................................................................................ 28
6.1.5 Third Party Monitors ..................................................................................................................... 29
6.2 Capacity Building and Training .......................................................................................................... 29
7 Stakeholder Engagement and Information Disclosure .............................................................................. 30
7.1 Principles for Meaningful, Effective and Informed Stakeholder Engagement ................................ 30
7.2 Information Disclosure ....................................................................................................................... 31
7.3 ECRP Systems in Place for Stakeholder Engagement and Information Disclosure ......................... 31
8 Grievance Redress Mechanism ................................................................................................................... 32
8.1 Project-Level Grievance Mechanism ................................................................................................. 32
8.2 UNDP Accountability Mechanism...................................................................................................... 33
8.3 World Bank Inspection Panel ............................................................................................................. 34
iii
9 Monitoring, Reporting and Evaluation of ESMF Implementation ............................................................. 34
9.1 Management Information System (MIS) .......................................................................................... 34
9.2 Sub-Project Self-Monitoring and Reporting...................................................................................... 35
9.2.1 Social, environmental and OHS incident reporting...................................................................... 35
9.2.2 Daily and weekly inspection checklists ......................................................................................... 35
9.2.3 Corrective Actions.......................................................................................................................... 35
9.2.4 Auditing and Review ...................................................................................................................... 35
9.3 Sub-Project Third-Party Monitoring and Reporting ......................................................................... 35
9.4 Monitoring Plan .................................................................................................................................. 35
Annex 1. Yemen ECRP Revised SES Screening..................................................................................................... 38
Annex 2. Specific Risks and Management Measures by Project Activity .......................................................... 54
Annex 3. Environmental and Social Management Plan - Indicative Outline ..................................................... 70
Annex 4. Guidance for Submitting a Grievance .................................................................................................. 72
Annex 5. OHS Framework .................................................................................................................................... 77
Annex 6. OHS Toolkit ............................................................................................................................................ 77
Annex 7. PWP Operational Manual ..................................................................................................................... 77
Annex 8. PWP Environmental and Social Management Framework (2014) ..................................................... 77
Annex 9. SFD Operational Manual ....................................................................................................................... 77
Annex 10. SFD Phase IV Environmental and Social Management Framework (2014) ..................................... 77
Annex 11. Summary of ECRP ESMF Stakeholder Consultation in Sana’a and Aden ........................................ 77
Annex 12. Third-Party Monitoring Report – ESMF Stakeholder Consultation .................................................. 77
1
Acronyms
EHS Environmental, Health and Safety
EIA Environmental Impact Assessment
EPA Yemen Public Environmental Protection Agency
EPL Yemen Environmental Protection Law
ESIA Environmental and Social Impact Assessment
ESMF Environmental and Social Management Framework
ESMP Environmental and Social Management Plan
GDP Gross Domestic Product
GIIP Good International Industry Practice
GRM Grievance Redress Mechanism
IDP Internally Displaced Person
ILO International Labour Organization
IPM/IVP Integrated Pest Management / Integrated Vector Management
MFI Multilateral Finance Institution
MIS Management Information System
NBSAP National Biodiversity Strategy and Action Plan
NEAP Yemen National Environmental Action Plan
NGO Non-Governmental Organization
OHS Occupational, Health and Safety
OP World Bank Operational Policy
PAD World Bank’s Project Appraisal Document
PWP Public Works Project
RoY Republic of Yemen
SRM UNDP’s Stakeholder Response Mechanism
SECU UNDP’s Social and Environmental Compliance Unit
SES UNDP’s Social and Environmental Standards
SESP UNDP’s Social and Environmental Screening Procedure
SFD Social Fund for Development
SME Small-to-Medium Enterprise
SMED Small-to-Medium Enterprise Development
SWF Yemen Social Welfare Fund
TPMA Third-Party Monitoring Agent
UN United Nations
UNDP United Nations Development Programme
WHO World Health Organization
YECRP/ECRP Yemen Emergency Response Project
YSMQCO Yemen Standard Metrology Quality Control Organization
1
Executive Summary
This Environmental and Social Management Framework (ESMF) is prepared by UNDP to ensure the Yemen
Emergency Crisis Response Project (ECRP) is consistent with UNDP’s Social and Environmental Standards
(SES) (www.undp.org/ses) and the World Bank’s Environmental and Social Safeguards Policies. The SES
require that all UNDP projects consider the potential environmental and social opportunities that a project
may generate and ensure that adverse social and environmental risks and impacts are avoided, minimized,
mitigated and managed.
The ESMF is intended to serve as a practical tool to guide identification and mitigation of potential
environmental and social impacts of proposed investments and as a platform for consultations with
stakeholders and potential project beneficiaries. The ESMF identifies the policy triggers for the project, the
screening criteria of sub-projects, the likely environmental and social impacts of the sub-projects and the
mitigation measures to mitigate the identified risks, assessment of the institutional capacity and measures
for capacity-filling gaps.
Although the ECRP is currently in the implementation phase, the ESMF provides a strengthened framework and clarity to ensure consistency with the UNDP SES and World Bank Environmental and Social Safeguards Policies across all sub-projects. The ESMF provides the following:
Description of the project (Section 2): UNDP, in partnership with the World Bank, developed the Yemen
Emergency Crisis Response Project (ECRP) to step up current efforts of the international community to
deliver critically needed livelihood support and service delivery to a population hit hard by the conflict. The
project consists of close to 2,000 sub-projects. Two local institutions are the Responsible Parties: The Social
Fund for Development (SFD) and the Public Works Project (PWP). SFD is responsible for implementation of
labour intensive cash-for-work/social service interventions (approx. 680) in all governorates of Yemen and
small community infrastructure and initiatives (approx. 90); and PWP is responsible for the implementation
of small community infrastructure through local contractors (approx. 1,200). The project aims to mitigate
the impact of the current crisis on local households and communities and assist their recovery from the
bottom-up using local systems, capacities and institutions to progressively resume and scale-up service
delivery. The project will achieve specific results in: 1) Increasing short-term employment and livelihoods
opportunities; 2) Reviving the local private sector; 3) Restoring key service delivery through small-scale
infrastructure.
Overview of the legal and regulatory framework (Section 3): Key national laws and regulations applicable to
social and environmental risk management include the National Environmental Action Plan, National
Biodiversity Strategy and Action Plan, Water Law, Environmental Protection Law, and Labour Law. In the
context of the ECRP, UNDP’s SES and the World Bank’s Environmental and Social Safeguards Policies apply.
In addition, the Responsible Parties (Public Works Project and Social Fund for Development) have elaborated
their own standard operating procedures, that were set up for the World Bank supported projects with the
two institutions prior to the conflict, Environmental and Social Management Frameworks in 2014 and OHS
Framework in 2018. Implementation of these procedures also help to ensure consistency with relevant
international agreements and protocols.
Overview of project activities and key social and environmental risks (Section 4): This section summarizes key social and environmental risks and indicative management measures for the project. The section describes the UNDP social and environmental Principles and Standards that have been triggered based on completion of the project-level Social and Environmental Screening Procedure (SESP, see Annex 1). While the project was initially categorized as Low Risk, the project was recategorized as Moderate Risk following
2
the 2018 SESP update. As per the World Bank safeguards policy OP 4.01 on ‘Environmental Assessment’ this project is categorized as ‘Category B’. Key risks include those related to human rights and conflict, gender and social inclusion, biodiversity and natural resources, climate change, community health, safety and working conditions (including occupational health and safety), cultural heritage, and pollution. Occupational health and safety risks are identified as a priority. Because a full risk analysis is not possible until site-specific design details are known, the identification of project level risks provides an indicative assessment to be elaborated further through sub-project level screening, assessment and risk management (see Section 5). Therefore, sub-project screening and site-specific assessments and management plans will be essential.
Procedures for screening (Section 5): Each sub-project will be screened for social and environmental risks
and impacts (including OHS risks) applying PWP and SFD screening tools. Screening and classification will be
completed prior to approval of sub-projects and signing of the Financial Agreement. The screening of sub-
projects will also be updated if there are any significant changes in the sub-project’s design or context that
may materially change its social and environmental risk profile. Sub-project screening and categorization
should be conducted at the earliest stage of design when sufficient information is available for this purpose.
Based on the screening, the sub-project is categorized according to the degree of potential social and
environmental risks and impacts (including OHS). The screening process results in a risk-based categorization
of the sub-project (Low Risk, Moderate Risk, or High Risk). Note that High Risk sub-projects will be excluded
from Yemen ECRP funding. If high level risks are identified during implementation, Senior management of
the Responsible Party and UNDP Project Manager will be notified immediately and relevant activities will be
halted until management measures put in place to reduce the levels of risk. An initial gap analysis shows that
PWP and SFD screening processes are generally aligned with SES requirements, as described below.
However, a more detailed gap analysis will be conducted and UNDP together with the World Bank will work
with PWP and SFD to update their screening processes as needed to address gaps and also respond to lessons
learned.
Procedures for assessment and management (Section 5): The targeted and site-specific assessments and
management plans will be undertaken for all Moderate Risk (Category B) sub-projects once project
activities/sub-projects and sites are identified. The assessment(s) will lead to the development of
appropriately scaled management measures and plans to address the identified risks and impacts. Relevant
social and environmental assessments and adoption of appropriate mitigation and management measures
will be completed, disclosed, and discussed with stakeholders prior to implementation of any activities that
may cause adverse social and environmental impacts. Where possible, template simplified ESMPs will be
developed for types of projects and risks for adaptation at the sub-project level. All site-specific assessments
and management plans will be submitted to UNDP and the World Bank for clearance and recorded in the MIS.
In cases where similar activities are being conducted in a particular region, these activities may be grouped
and covered under one site-specific ESMP. All ESMPs will be available upon request.
Institutional arrangements and capacity building (Section 6): The World Bank provides financing for the
project and as such has an oversight role. The World Bank has established a senior management task team
to oversee and make decisions about remedies in connection with the UNDP-implemented activities. The
Project Board (UNDP, World Bank, PWP, SFD) has oversight and advisory authority, representing the highest
body for coordination, strategic guidance, oversight and quality assurance. UNDP will be responsible for
overseeing the implementation and compliance with the ESMF, working closely with PWP and SFD. UNDP
will be responsible for the revision or updates of this document during the course of project, in consultation
with PWP, SFD and the World Bank. During operations the Responsible Parties (SFD and PWP) will be
accountable for implementation of the ESMF. The Responsible Parties are directly accountable to UNDP in
accordance with their Letter of Agreement. Responsible Parties include headquarters offices, branch offices,
3
site engineers, site supervisors, and workers that also play a role in implementation of the ESMF. A capacity
development plan to ensure ongoing capacity development related to ESMF implementation will be
developed and led by UNDP, working closely with PWP, SFD and the World Bank.
Stakeholder engagement and information disclosure (Section 7): The ECRP and its Responsible Parties will
ensure meaningful, effective and informed stakeholder engagement in the design and implementation of all
sub-projects. Stakeholder engagement supports the development of strong, constructive, and responsive
relationships that are critical for sound project design and implementation. Effective stakeholder
engagement enhances project acceptance and ownership and strengthens the social and environmental
sustainability and benefits of supported interventions. Information disclosure refers to the provision of
timely, accessible information regarding the project and its potential social and environmental impacts to
stakeholders in order to facilitate their meaningful, effective and informed participation in project design
and implementation. Stakeholders require access to relevant project and sub-project information to
understand potential project-related opportunities and risks and to engage in design and implementation. In
addition to have access to general project information, stakeholders need access to screening reports, draft
and final assessments and management plans. This information is to be disclosed in a timely manner, in an
accessible place, and in a form and language understandable to affected persons and other stakeholders.
Meaningful stakeholder engagement is required by PWP and SFD for participation in project intervention by
communities and individuals. The Standard Operating Procedures of both Responsible Parties include
procedures for community and stakeholder engagement within their project cycles as a key component of
project identification, design and implementation, and described a key component of the longer-term
sustainability strategy for operations and maintenance. Stakeholder consultations on the draft ESMF noted
that further stakeholder engagement and information about projects is needed; therefore, the Responsible
Parties Operating Procedures will be reviewed and updated to further strengthen these aspects.
Grievance Mechanism (Section 8): The Project Level Grievance Mechanism is managed by SFD and PWP, who
have their own GRM mechanisms in place. The GRM will be gender- and age-inclusive and responsive and
address potential access barriers to women, the elderly, the disabled, youth and other potentially
marginalized groups as appropriate to the Project. The GRM will not impede access to judicial or
administrative remedies as may be relevant or applicable and will be readily accessible to all stakeholders at
no cost and without retribution. Information about the Grievance Redress Mechanism and how to make a
complaint and/or grievance must be communicated during the stakeholder engagement process and placed
at prominent places for the information of the key stakeholders. All complaints and/or grievances regarding
social and environmental issues can be received either orally (to the field staff), by phone, in complaints box
or in writing to the UNDP, PWP or SFD. A key part of the grievance redress mechanism is the requirement
for the Project Management Team and construction contractor to maintain a register of complaints and/or
grievances received at the respective project site offices, this includes grievances from workers. In addition
to the project-level and national grievance redress mechanisms, complainants have the option to access
UNDP’s Accountability Mechanism, with both compliance and grievance functions. The Social and
Environmental Compliance Unit investigates allegations that UNDP's Standards, screening procedure or
other UNDP social and environmental commitments are not being implemented adequately, and that harm
may result to people or the environment. The Stakeholder Response Mechanism offers locally affected
people an opportunity to work with other stakeholders to resolve concerns, complaints and/or grievances
about the social and environmental impacts of a UNDP project. Stakeholder Response Mechanism is
intended to supplement the proactive stakeholder engagement that is required of UNDP and its
Implementing Partners throughout the project cycle (www.undp.org/secu-srm). Complainants also have
access to the World Bank’s Inspection Panel (www.inspectionpanel.org). TPM Reports and the ESMF
stakeholder consultations noted that there was little awareness by project-affected people of the GRM and
their options. This will be an area to be strengthened moving forward.
4
Monitoring, reporting and evaluation (Section 9): The ESMF and its procedures are to be reviewed and
updated on a regular basis by UNDP staff, PWP and SFD to reflect knowledge gained during the course of
project delivery/construction. Both PWP and SFD have a Management Information System in place to record
project information and monitoring results. The MIS provides an important mechanism to track information
on environmental and social safeguard implementation. A review will be conducted to identify opportunities
to strengthen environmental and social safeguard elements in the MIS. The Responsible Parties will maintain
and keep all administrative and social and environmental records which would include a log of complaints
and incidents together with records of any measures taken to mitigate the cause of the complaints or
incidents. Any incidents, major injury or fatality, including non-conformance with the procedures of the
ESMF, are to be recorded using an Incident Record and the details entered into a register. For any incident
that causes or has the potential to cause material or significant social and/or environmental harm, the site
supervisor/designated officer shall notify the Responsible Party Senior Management and the ECRP Project
Manager as soon as possible and no later than 48 hours. UNDP will also ensure significant incidents are
reported to the World Bank within 48 hours. The Responsible Party must cease work until remediation has
been completed as per the approval of Project Manager. A daily social and environmental checklist (including
OHS issues) is to be completed for active work sites with moderate risks by the relevant site
supervisor/designated officer and maintained within a register. A weekly social and environmental checklist
is to be completed and will include reference to any issues identified in the daily checklists completed by the
site supervisor or designated person. The progress of all corrective actions will be tracked using the register.
In the case of potential occupational health and safety hazards, safe working systems and procedures will be
developed and applied as well daily permit-to-work forms used to control and minimize risks to acceptable
limits. .A consultant will be recruited to conduct an annual environmental and social compliance and
performance audit by both PWP and SFD. Implementation of the ESMF to be included in overall project
monitoring and reporting, including monitoring conducted by the TPMA.
5
1 Introduction
This Environmental and Social Management Framework (ESMF) is prepared by UNDP to ensure the Yemen Emergency
Crisis Response Project (ECRP) is consistent with UNDP’s Social and Environmental Standards (SES) (www.undp.org/ses)
and the World Bank’s Environmental and Social Safeguards Policies. The SES require that all UNDP projects consider
the potential environmental and social opportunities that a project may generate and ensure that adverse social and
environmental risks and impacts are avoided, minimized, mitigated and managed. In the context of the Yemen
Emergency Crisis Response Project (ECRP), UNDP’s SES and the World Bank’s Environmental and Social Safeguards
Policies apply. In addition, the Responsible Parties (Public Works Project and Social Fund for Development) have
elaborated their own standard operating procedures, that were set up for the World Bank supported projects with the
two institutions prior to the conflict, ESMFs in 2014, and Occupational Health and Safety Framework in 2018.
The project was originally categorized as Low Risk through UNDP’s Social and Environmental Screening Procedure
(SESP) so a project level Environmental and Social Management Framework (ESMF) was not initially put in place.
However, during implementation, several risks were identified and the SESP was updated accordingly. The update SESP
(see Annex 1) resulted in a Moderate Risk categorization for the project. Because the details of proposed activities are
designed at the sub-project level, an Environmental and Social Management Framework (ESMF) is necessary to ensure
policies and procedures are in place for consistent safeguards implementation across all sub-projects, and as required
by the World Bank safeguards policy OP 4.01 on ‘Environmental Assessment’.
The ESMF is intended to serve as a practical tool to guide identification and mitigation of potential environmental and
social impacts of proposed investments and as a platform for consultations with stakeholders and potential project
beneficiaries. The ESMF has been prepared in compliance with World Bank safeguards policy OP 4.01 on
‘Environmental Assessment’, the UNDP SES and relevant Yemeni policies on environmental assessment. The ESMF
identifies the policy triggers for the project, the screening criteria of sub-projects, the environmental and social impacts
for the likely sub-projects and the mitigation measures to mitigate the identified risks, and assessment of the
institutional capacity and measures for capacity-filling gaps.
Although the ECRP is currently in the implementation phase, the ESMF provides a strengthened framework and clarity to ensure consistency with the UNDP SES and World Bank Environmental and Social Safeguards Policies across all sub-projects. The ESMF was developed through a consultative process led by UNDP in close coordination with the World Bank, PWP and SFD. Stakeholders were consulted through workshops held in Sanaa and Aden and feedback from local communities also obtained through the Third-Party Monitors (see Annexes 11-13 for summaries of these consultations).
The ESMF provides the following:
• Description of the project (Section 2)
• Overview of the legal and regulatory framework (Section 3)
• Overview of project activities and key social and environmental risks (Section 4)
• Procedures for screening, assessment and management (Section 5)
• Institutional arrangements and capacity building (Section 6)
• Stakeholder engagement and information disclosure (Section 7)
• Grievance Mechanism (Section 8)
• Monitoring, reporting and evaluation (Section 9)
2 Project Description
The ongoing conflict in Yemen has resulted in a catastrophic humanitarian emergency with an increasing toll of civilian
deaths and casualties across the country with over 80 percent of Yemen’s population is estimated to need
humanitarian assistance and more than 2.5 million Yemenis have become IDPs. The ongoing conflict has destroyed
much of the institutional ability of key ministries, governorates and local authorities to deliver essential social services
to citizens. Public service restoration is also essential for a smooth transition to recovery, as a political agreement is
being negotiated.
In this context, UNDP, in partnership with the World Bank, developed the Yemen Emergency Crisis Response Project
(ECRP) to step up current efforts of the international community to deliver critically needed livelihood support and
service delivery to a population hit hard by the conflict. The project consists of close to 2,000 sub-projects. Two local
6
institutions are the Responsible Parties: The Social Fund for Development (SFD) and the Public Works Project (PWP).
SFD is responsible for implementation of labour intensive cash-for-work/social service interventions (approx. 680) in all
governorates of Yemen and small community infrastructure and initiatives (approx. 90); and PWP is responsible for the
implementation of small community infrastructure through local contractors (approx. 1,200).
The project aims to mitigate the impact of the current crisis on local households and communities and assist their
recovery from the bottom-up using local systems, capacities and institutions to progressively resume and scale-up
service delivery. The project will achieve specific results in: 1) Increasing short-term employment and livelihoods
opportunities; 2) Reviving the local private sector; 3) Restoring key service delivery through small-scale infrastructure.
As such, the project contributes to the livelihoods restoration and service delivery restoration components of UNDP’s
Yemen Resilience Programme. The Project’s Theory of Change assumes that if income-generation and livelihoods
opportunities are increased for vulnerable households (including IDPs), with essential service delivery restored and key
local businesses revived, Yemeni households and communities will be able to better cope with the impact of the
current crisis and be strong drivers of the resilience-building and recovery efforts.
The project consists of small, fast-disbursing interventions (sub-projects) that serve as a rapid response, providing
households and communities affected by the conflict with income support (as wages) to purchase basic necessities.
These short-term interventions are also delivering benefits to the wider community by creating community assets,
small infrastructure, and improved access to basic service delivery, as well as restoring livelihoods. The project adopts a
community-based approach, which brings communities together around common humanitarian and development
initiatives and hence promotes social cohesion and the protection of human capital. The project gives special attention
to youth and, as an important peace dividend, provides them with income and participation opportunities, and
includes design features that ensure women’s access to project opportunities.
The project is fully described in the World Bank’s Project Appraisal Document (PAD1797, July 5, 2016) and UNDP
Project document (14 August 2016), and subsequent amendments for additional funding.
2.1 Description of Baseline Environmental and Socioeconomic Conditions
The economic impact of the crisis has been devastating for the Republic of Yemen, aggravating an already deteriorating
pre-conflict economic performance. In 2015, according to the World Bank, the economy contracted by about 28
percent of gross domestic product (GDP), while inflation has been estimated to have reached about 40 percent. Public
finances are under severe stress. The fiscal deficit reached around 11 percent of GDP in 2015. The fiscal resources
available in 2015 allowed only for financing basic salaries for public employees and rising interest payments; public
investments in critical sectors such as health and education or other development policy programs were postponed. In
a context of growing liquidity crisis in the country, President Hadi issued a decreed to replace the Central Bank
Governor and move the Central Bank Headquarters from Sana’a to Aden. As a result of the liquidity crisis, the payment
of salaries to civil servants has been disrupted. At a time where major development partners suspended their
engagements since earlier days of the military confrontation in March 2015 and transitioned their support to
emergency and relief operations, the suspension of wage payments causes the crumbling of the health services,
putting additional pressure on the humanitarian response and resilience of the population.
About 14.4 million Yemenis are currently considered food insecure. The poor state of the health services is leading to a
catastrophe in terms of excess mortality due to malnutrition and diseases. At present the Ministry of Health and
international partners are also battling a cholera epidemic. Some 3 million children under five years and pregnant or
lactating women require services to treat or prevent acute malnutrition; 1.3 million under-five children are
malnourished, with 370,000 suffering from severe acute malnutrition, a doubling of pre-crisis levels. Preliminary
estimates of the Nutrition Cluster in October 2016 indicates that 4.5 million children and pregnant and lactating
women require malnutrition treatment or preventive services. The number of people in need of assistance increased
by 148% compared to late 2014. Severe and Acute Malnutrition blunts children intellect and makes them nine times
more likely to die compared to their healthy peers. This poses a serious risk to the future of human development in
Yemen.
Furthermore, it is estimated that approximately 19.4 million Yemenis lack access to clean drinking water and sanitation,
and 14.1 million cannot access adequate health care. Children are facing significant psychological stress; an estimated
1.8 million children are out of school because of fighting and insecurity. 2,007,216 internally displaced persons (IDPs)
across 21 governorates; the majority, 50%, are displaced in Hajjah, Taizz, Amanat Al Asimah and Sana’a. The Task Force
on Population Movement has identified 1,027,674 returnees in 19 governorates; the majority, 68%, have returned to
Aden, Amanat Al Asimah and Taizz.
7
The number of IDPs have risen to over 2 million, with the majority of displaced people hosted by local communities.
According to latest estimates from the Task Force on Population Movement in Janaury 2016, about 1,027,000 IDP
returnees who returned to their place of habitual residence across Yemen, representing about a 32% increase
compared to April 2016. The prospects for women-headed households, which represent more than 50 percent of the
displaced community, are particularly challenging. Households, communities, and public and private institutions need
support to cope and build resilience toward peace and recovery.
Yemeni economic advancement depends on its natural resource base; on agriculture and mining. Agriculture forms an
important sector in the nation’s economy and much of the economic activities depend on exploitation of fresh water
resources, marine resources, and its soil and oil wealth. However, the natural resource base is facing serious
challenges. The rapidly growing population at the rate of 3% annually accelerates pressure on scarce natural resources.
Demand increases on water resources, foodstuff and other products of natural resources. People exploit soil,
vegetation and water without paying adequate attention to the sustainability of these resources. Unplanned expansion
of urban centers exceeds, in some places, the carrying capacities of available resources to meet new demand. It also
causes sanitation and waste management problems and puts pressure on social services, in addition to loss of
biodiversity and agricultural land.
Yemen is a country with rich natural habitats, species and genetic diversity, including many endemic species resulted
from the variant altitudinal topography, climate, and geographical landscapes. The unique geographical position of
Yemen with the variant climatic and topographical features is favorable for existence of diverse ecosystems, natural
habitats, and great marine, coastal, and terrestrial biodiversity. The flora of Yemen is very rich and heterogeneous.
According to the Gap Analysis of Natural Plant Biodiversity of Yemen (2011), about 2,810 plant species were recorded
in Yemen in which endemic and near endemic plants were estimated about 604, among which 455 are endemic (307 in
Soqotra), constituting of about 16% of the flora which does not occur elsewhere (National Biodiversity Strategy and
Action Plan, NBSAP II 2015).
On the other hand, Yemen has very limited natural resources including for instance arable land, water, fishery, and
green cover which evidently experience constant degradation. The arable lands do not exceed 3% of the total natural
area which is dominated by desert and mountains. The arable lands experience continuous deterioration by about
1.8% annually during the period 1999-2006 as a result of the water erosion, desertification, salinization, and
urbanization. The total lands covered by forests are estimated about 1.5% until 2005. Desertification is accounting for
over 50 percent of total land of the country. Desertification of agricultural land ranges from 3-5 percent annually,
whereas the area of deteriorated land due to soil erosion and salinity is estimated to be 12 million hectares and
another 3.8 million hectares, respectively. The situation is further worsened as a result of encroachment of sand dunes
(NSES 2005-2015). The potential for greater desertification is high considering several factors including changes in
socio-economic patterns and farming practices and increasing demand for fuel, abandonment of terraces, overgrazing
and depletion of tree cover and water erosion problems.
2.2 Summary of Key Results and Activities
The project will be implemented through two components:
1. Labor Intensive Works and Community Services
2. Project Management and Monitoring
The overall objectives of Component 1 are to (a) provide income support to target communities through temporary
employment opportunities, (b) increase the productive assets and means of livelihood of beneficiary households and
communities and improve access to community and services and (c) preserve the implementation capacity of the SFD
and PWP, and key national service delivery programs. The component will be implemented through three
subcomponents that engage the SFD in subcomponents 1.1 and 1.3, and PWP in subcomponent 1.2, which build on
existing and well-established program implemented by these entities. Although both subcomponents 1.1. and 1.2 will
deliver labor intensive interventions, their primary objectives and approaches are different: subcomponent 1.1.
delivers cash for work with a safety net approach, whereby beneficiaries of the cash are at the individual household
level, While the primary objective of subcomponent 1.2 is to create community assets and improve community
infrastructure, and in doing so generate short-term employment for participating workers.
2.2.1 PWP Project Component (1.2)
The subcomponent will implement labor intensive, small -scale infrastructure provided through contracting local
private sector contractors. Subprojects will include, but are not limited to, water harvesting schemes, stone paving of
8
village access roads and streets, water supply, sewerage networks and school rehabilitation, among others, based on
the priority needs identified by each targeted community. The choice of these subprojects takes in consideration
communities’ ability to operate and maintain the supported infrastructure and would not require technical expertise to
do so; technical specification of roads and schools’ construction will comply with the standards prepared by relevant
sectoral authorities, as applicable. Wage intensity of subprojects will have to meet the requirement of 35% percent of
above of the subproject cost. This subcomponent will create approximately 256,000 work days of employment, about
20,000 direct beneficiaries are expected to participate in labor, and over 310,000 individuals will have access to basic
services. The subprojects will be implemented through a contractual arrangement and grant provision from the UNDP
to the PWP. The grand under this subcomponent will finance works, goods, consultants’ services, training, non-
consultant services, and operating costs of PWP.
2.2.2 SFD Project Components (1.1 and 1.3)
Subcomponent 1.1: Cash-for Work and Youth-targeted Community Services
The subcomponent will implement labor intensive works subprojects determined by the community, such as in
irrigation, water harvesting, rehabilitation of agricultural terraces, maintenance and improvement of village access
roads, improvement of water resources, access to improved water and sanitation, watershed management,
agricultural inputs, other based on the priority needs identified by each targeted community. Each participating
household would be eligible to receive a maximum of US$ 500 (depending on the household size) in the form of labor
wage. The size and number of interventions assigned to each community will be determined by the total budget
envelope allocated to the community, as calculated based on the number of households who register for participation
in labor. The subcomponent will also finance subprojects that provide income opportunities, training and work
experience to youth in the 16 to 25 year age bracket, engaging them in the delivery of community services, including
hygiene and behavior change, literacy, alternative schooling, nutrition services, planting trees, paving of roads, cleaning
shorelines, and in youth initiatives promoting the protection of human capital through special attention to nutrition-
related interventions; and peace building and social cohesion, interventions, as may be proposed by communities and
youth groups.
The subcomponent is expected to create approximately 900,000 work days of employment over 32,000 direct
beneficiaries are expected to benefit from the wage labor, and about 92,600 individuals will have access to basic
services. The wage intensity of subprojects under this subcomponent is expected to be at least 30-50 percent of the
average total cost of subprojects. The subcomponent will be implemented through a contractual arrangement and
grant provision from the UNDP to the SFD. The SFD will deliver these subprojects with the direct involvement of
community and civil society groups (for example, community-based organizations, user groups, village cooperative
council, and local NGOs) using various implementation methods focused on community-based approaches, such as
community contracting. The grant under this subcomponent will finance community grants, wages, training of youth
and communities, consultants’ services, goods, work, non-consultant services, and operating cost of SFD.
Subcomponent 1.3: SME Revitalization and Employment Generation
The subcomponent will directly support around 2,000 SME clients of microfinance that have been severely affected by
the conflict, by relieving them from their current outstanding loans with the MFIs and by supporting the rehabilitation
of their enterprises. The project will use the existing solidarity funds (Takaful Fund) within each MFI to pay off the
outstanding loans of the targeted SMEs and channel the support needed to rehabilitate and revitalize their damaged
businesses. Moreover, given the important role the microfinance industry plays in contributing to the alleviation of
poverty, the project will support the operating deficit of at least seven rural-based MFIs, which will enable them to
sustain their levels of capacity and outreach, to continue to provide the financial services needed by the poor.
Additionally, the subcomponent will support 800 farms of essential cops, affected by the conflict, with seeds, seedlings,
drip irrigation systems, and other agriculture inputs. The agriculture inputs will substitute for farmers’ damaged inputs
and restore their ability to grow food, generate income, and create wage employment. The focus will be on farms of
the horticulture products, such as tomatoes, potatoes, and cucumbers, and cereals such as wheat, sorghum, and oats.
It is expected that this intervention will generate 6,400 seasonal and permanent employments within the agriculture
sector, increase farmers’ resilience, and increase the supply level and access to basic food commodities within the
targeted communities. The subcomponent will be implemented under the same contractual arrangement and grand
provision from the UNDP to the SFD as in subcomponent 1.1 and will be implemented through the SFD’s well
established SMED program.
9
3 Legal and Regulatory Framework
The ESMF is prepared to:
- comply with national environmental and social laws and regulations, and the operating procedures of PWP
and SFD (including their ESMFs)
- meet the requirements of the World Bank’s Environment Assessment Policy (OP 4.01), including the World
Bank Group Environment, Health and Safety (EHS) Guidelines, most particular the General Guidelines, the
Guidelines for waste management facilities, and the Guidelines for water and sanitation
- meet the UNDP Social and Environmental Standards (SES)
3.1 National Legislation, Policies and Regulations
3.1.1 National Environmental Action Plan
The Republic of Yemen (RoY) enacted a National Environmental Action Plan (NEAP) in 1995 that was prepared with the
support of the World Bank. The NEAP defines priority actions regarding key environmental issues such as water
resources, land resources, natural habitats, and waste management.
3.1.2 National Biodiversity Strategy and Action Plan
The NBSAP calls for “achieving a resilient, productive and sustainable socio- ecosystem by 2050”. The strategy and its
action plan aims to halt the overall biodiversity loss and maintain healthy, productive and functional ecosystems based
on establishing coherent and resilient ecological networks supported by restructured policies and adequately
mandated and empowered local communities and institutions for sustainable and equitable use of natural capital of
importance to human well-being and economic prosperity.
3.1.3 National Water Sector Strategy and Investment Program
This strategy (2004) proposes a set of institutional, financial and other measures, which are aimed at addressing
discrepancies in the five sub-sectors in order to protect the interests of all stakeholders in water resources. Obviously,
if the situation continues as it is without regulation of groundwater extraction and use, without reduction of the
current unsustainable level of water resources use, and without putting an end to the ongoing resource capture, then
this will eventually harm everyone, including farmers, who will be the first victims of water exhaustion.
At the same time, (water) regulation is needed to safeguard or secure the economic and social growth of the cities.
Growth will not happen unless the cities get their water needs. Hence, the strategy notes that an equitable mechanism
for rural-to-urban transfer of water from the rural peripheral areas surrounding cities needs to be developed, as well as
strict measures to protect the water fields, which supply the cities, against illegal drilling.
3.1.4 Water Law
The ECRP project is subject to the following Yemeni laws and regulations: National Water Sector Strategy and
Investment Program; Water Law No. 33 issued in 2002 and modified in 2006 after the creation of Ministry of Water
and Environment, Its by-law was issued in 2011 by the Cabinet decree.
The law defines water resources as any water available in the republic's territory and its share of common waters
jointly owned with neighboring countries. This is comprised of ground water, surface water, wastewater after
purification, and saline water after desalination. The law's main objective is to regulate, develop, sustain and increase
efficiencies in water utilization, protect from pollution, transport, and engage the beneficiaries of water installations in
participatory management, investment, development, operation, maintenance and preservation at the various stages
of development. Water is considered as a common property accessible to all. Management of water resources is
entrusted to the National Water Resources Authority, which assess the resources, classify water basins and zones, and
prepare the national water plan, which is considered as one of the components of national economic and social
planning. Priorities of water use are: drinking and domestic use shall have absolute priority. Then in declining priority,
watering livestock, public utilities, irrigation, industrial purposes, minimal level of environmental needs. For these uses
water distribution and transport should be done according to hygiene means. Existing and acquired water rights prior
to the issuance of the law will be maintained, except in special cases when fair compensation will be ensured.
10
Traditional water rights of rainwater harvesting and natural runoff flow in relation to irrigation shall be maintained. The
same applies for the traditional rights on natural springs, streams, and creeks. The Water Law and its by-law are a
notable achievement in Yemeni legislation and provide important legislation for environmental management of UNDP/
ECRP activities.
3.1.5 Environmental Protection Law
The Environmental Protection Law (Law 26/1995; EPL), enacted in 1995 in the wake of the NEAP, constitutes the
framework environmental legislation for Yemen. It includes provisions for environmental protection in Yemen, the
issuance of permits, and Environmental Impact Assessments (EIAs). The provisions of the law are implemented through
By-Law 148/000.
The law is also designed to: (i) incorporate environmental considerations in economic development plans at all levels
and stages of planning, (ii) protect the national environment from activities practiced beyond national boundaries, and;
(iii) implement international commitments ratified by the RoY in relation to environmental protection, pollution
control, the conservation of natural resources, and global environmental issues such as the depletion of the ozone
layer depletion and climate change.
Environmental Protection Authority
The EPL established an Environmental Protection Council and granted it power to take all measures necessary to
protect and improve the quality of environment and to prevent pollution of the environment. Decree 101/2005
established the Public Environmental Protection Authority (EPA) to replace the Council and lays down its objectives,
tasks and management. The functions assigned to the EPA include:
• preparing and executing appropriate policies/strategies/plans to protect the environment
• conducting environmental surveys
• assessing areas/resources/species to be protected through necessary measures conserving the ecosystem
including flora and fauna, wild and marine life as per existing laws and monitoring their application
• developing legislative proposals for environment protection in coordination with other agencies involved
• developing a National Emergency Plan to combat natural disaster and environmental pollution in consultation
with the agencies concerned implementing environmental protection law and other relevant laws/regulations
• reviewing EIA studies for public /private sector projects for giving clearance and monitoring their execution
• coordinating relevant programs/activities with national, regional and international agencies and organizations
• recommending necessary laws, regulations and systems to protect the environment, in accordance with
regional and international agreements on environmental protection.
• collecting data, assessing and evaluating the status of the environment, and setting up suitable monitoring
systems
• laying down appropriate standards for protecting the environment from pollution and formulating policy
guidelines to combat industrial pollution and protect animal, plant and marine ecology
Environmental Impact Assessments
The EPL requires the preparation of EIAs for projects proposed by the public and private sectors. The proponent is
responsible to undertake the EIA, but the report may be prepared by the proponent or the competent authority or
both. Line ministries and Government bodies commission EIA studies at the request of funding agencies and seek the
advice of the EPA.
The EPA is responsible for implementing screening procedures, assisting in scoping, evaluation and approval of the
Environmental Impact Statement (EIS). However, there is still no regulatory framework to support the implementation
of the EPL and the provision of undertaking EIAs for projects is not strictly enforced, particularly for projects that are
not internationally funded.
Given the current context, modifications to the EIA procedures are not expected during the project. Current
procedures will be taken into account, but there is no expectation at this point that the EPA will review the Project’s
safeguard instruments.
3.1.6 Labour Law
The RoY Labour Law, Act No.5 of 1995, includes OHS requirements for workplaces that needs to be applied in the
project.
11
- The Labor Law (Law 5/1995) states that women are equal to man in all aspects without any discrimination, and that
equality should be maintained between women and men workers in recruitment, promotion, wages, training, social
insurance. It also regulates work time for pregnant women.
- The Labour Law regulates the rights and wages of workers, their protection, occupational health and safety. In
addition, the Social Insurance Law regulates retirement compensation.
- Yemen has ratified ILO Convention Number 138 on Minimum Age for Admission to Employment (Law 7/2001). The
Convention establishes a minimum age for admission to employment.
- Yemen has also ratified the ILO Convention 182 on the Worst Forms of Child Labour. It refers to child labour as
work that is mentally, physically, socially or morally dangerous and harmful to children; and interferes with their
schooling by depriving them of the opportunity to attend school, by obliging them to leave school prematurely; or
by requiring them to attempt to combine school attendance with excessively long and heavy work.
3.1.7 PWP and SFD Operating Procedures
In the context of the Yemen ECRP, both PWP and SFD operating manuals (PWP Operation Manual YECRP, July 2016,
see Annex 7; SFD Manual of Operation, May 2010, see Annex 9) specify operational requirements for the management
and delivery of sub-projects.
In addition, both PWP and SFD have Environmental and Social Management Frameworks in place that cover activities
implemented through the ECRP project (2014: PWP ESMF, Annex 8; SFD ESMF, Annex 10).
3.2 International Agreements and Protocols
The RoY is party to a number of international environmental agreements, the most important of which are:
• World Heritage Convention
• International Convention on Civil Liability for Oil Pollution Damage
• Convention on Biodiversity
• Convention on the Conservation of Migratory Species
• Convention on International Trade in Endangered Species of Wild Fauna and Flora
• United Nations Framework Convention on Climate Change (Yemen acceded to the Kyoto Protocol and is party
to Paris Agreement but not ratified)
• United Nations Convention on Combating Desertification
• Environmental Modification Convention
• Basel Convention on the Control of Transboundary Movements of Hazardous Wastes and Their Disposal
• Convention on Wetlands of International Importance Especially as Waterfowl Habitat
• Law of the Sea
• Montreal Protocol on Substances that Deplete the Ozone Layer
• Stockholm Convention on Persistent Organic Pollutants
In general, national agencies are not currently in a position to handle the technical complexities and reporting
requirements of international agreements.
Project activities are not expected to be in breach of any international agreement to which the RoY is a party.
3.3 UNDP’s Social and Environmental Standards
UNDP’s Social and Environmental Standards (SES) are applied to all UNDP projects, including the ECRP. The application
of the SES, which are broadly consistent with those of the World Bank, will help mitigate potentially high adverse
environmental and social impacts stemming from the selection and implementation of subprojects.
UNDP’s SES came into effect in January 2015. The SES underpin UNDP’s commitment to mainstream social and
environmental sustainability in its Programmes and Projects to support sustainable development. The objectives of the
standards are to:
• Strengthen the social and environmental outcomes of Programmes and Projects
• Avoid adverse impacts to people and the environment
• Minimize, mitigate, and manage adverse impacts where avoidance is not possible
• Strengthen UNDP and partner capacities for managing social and environmental risks
• Ensure full and effective stakeholder engagement, including through a mechanism to respond to complaints
from project-affected people
12
The SES are an integral component of UNDP’s quality assurance and risk management approach to programming. This
includes the Social and Environmental Screening Procedure (see the completed SESP for the project in Annex 1).
Table 1. Key Elements of UNDP’s Social and Environmental Standards (SES)
Overarching Policy Project-Level Standards Policy Delivery Process & Accountability
Principle 1: Human Rights
Principle 2: Gender Equality and
Women's Empowerment
Principle 3: Environmental
Sustainability
Standard 1: Biodiversity Conservation and
Sustainable Natural Resource Management
Standard 2: Climate Change Mitigation and
Adaptation
Standard 3: Community Health, Safety and
Working Conditions
Standard 4: Cultural Heritage
Standard 5: Displacement and Resettlement
Standard 6: Indigenous Peoples
Standard 7: Pollution Prevention and Resource
Efficiency
Quality Assurance
Screening and Categorization
Assessment and Management
Stakeholder Engagement and Response
Mechanism
Access to Information
Monitoring, Reporting, and Compliance
review
The Standards are underpinned by an Accountability Mechanism with two key functions:
• A Stakeholder Response Mechanism (SRM) that ensures individuals, peoples, and communities affected by
UNDP projects have access to appropriate procedures for hearing and addressing project-related grievances;
and
• A Compliance Review process to respond to claims that UNDP is not in compliance with UNDP’s social and
environmental policies.
3.4 World Bank Requirements
World Bank Policy on Environmental Assessment, OP 4.01
The Project triggers the World Bank’s Operational Policy on Environmental Assessment (OP 4.01).
Considering the nature and magnitude of potential environmental impacts that might result from Project funded
activities, the Project was assigned EA Category B according to OP 4.01.
OP 4.01 provides for the use of an Environmental and Social Management Framework (ESMF) when a project consists
of a series of subprojects, and the impacts cannot be determined until the subproject details have been identified. The
ESMFs examine the issues and associated impacts, sets out the principles, rules, guidelines and procedures to assess
the environmental and social impacts during project implementation. It contains measures and plans to reduce,
mitigate and/or offset adverse impacts and enhance positive impacts of subprojects, provisions for estimating and
budgeting the costs of such measures, and information on the agency or agencies responsible for addressing project
impacts.
As there is no cultural inventory in Yemen, OP 4.11 may be triggered in case of archaeological finds, in which case its
implementation falls within the OP 4.01 procedures.
Environment, Health and Safety Guidelines
The World Bank Group Environment, Health and Safety (EHS) guidelines are referenced in footnote 1 of OP 4.01. They
are technical reference documents with general and industry-specific examples of Good International Industry Practice
(GIIP). They define acceptable pollution prevention and abatement measures and emission levels in World Bank
financed projects.
13
The EHS Guidelines contain the performance levels and measures that are generally considered to be achievable in
new facilities by existing technology at reasonable costs. Application of the EHS Guidelines to existing facilities may
involve the establishment of site-specific targets, with an appropriate timetable for achieving them.
The application of the Guidelines to existing facilities may involve the establishment of site-specific targets with an
appropriate timetable for achieving them. The environmental assessment process may recommend alternative (higher
or lower) levels or measures, which, if acceptable to the World Bank, become project- or site-specific requirements.
If less stringent levels or measures than those provided in the EHS Guidelines are appropriate, in view of specific
project circumstances, a full and detailed justification for any proposed alternatives is needed as part of the site-
specific environmental assessment. This justification should demonstrate that the choice for any alternate
performance levels is protective of human health and the environment. When host country regulations differ from the
levels and measures presented in the EHS Guidelines, projects are expected to achieve whichever is more stringent.
Due to the nature of ECRP activities, the Project will use as appropriate the General Guidelines, including (i)
Environmental, (ii) Occupational Health and Safety, (iii) Community Health and Safety, and (iv) Construction and
Decommissioning, as well as the Guidelines for Construction and Decommissioning, as well as any other relevant
Guidelines.
4 Social and Environmental Impacts
This section summarizes key social and environmental risks and indicative management measures for the project.
Because a full risk analysis is not possible until site-specific design details are known, the identification of project level
risks provides an indicative assessment to be elaborated further through sub-project level screening, assessment and
risk management (see Section 5). Therefore, sub-project screening and site-specific assessments and management
plans will be essential.
The following section describes the UNDP social and environmental Principles and Standards that have been identified
as relevant based on completion of the project-level Social and Environmental Screening Procedure (SESP, see Annex
1). The project-level screening was updated in 2018 and was informed by project documents, Third-Party Monitoring
reports, sub-project risks, and audits conducted to date. It is based on a precautionary approach, looking at the broad
category of activity/intervention types and assessing potential risks based on the types of activities that are expected
to be implemented at the sub-project level. While the project was initially categorized as Low Risk, the project was
recategorized as Moderate Risk following the 2018 SESP update. Although different levels of risk categories have been
assigned to different activities, varying from Low to Moderate, the overall project categorization should follow the
highest level of risk categorization, which in this case is Moderate.
Table 2 below summarizes key principles and standards that were triggered after pre-screening of the project and the
SES requirements for the project, as identified in the SES and based on the results of the SESP. This table addresses the
principles and standards that have triggered both low and moderate level risks.
Table 2: Summary of Key SES Requirements for the ECRP
SES Principle or Standard Summary of Relevant SES Requirements
Principle 1: Human Rights Recognize centrality of human rights to sustainable development,
upholding principles of accountability and rule of law, participation and
inclusion, and equality and non-discrimination
Adhere to the UN Development Group Statement of Common
Understanding of the Human Rights-Based Approach to Development
Cooperation and Programming
Refrain from providing support for activities that may contribute to
violations of a State’s human rights obligations and the core
international human rights treaties
Principle 2: Gender Equality
and Women’s Empowerment
Promote design and implementation of gender responsive projects
14
Reduce gender inequalities in access to and control over resources and
the benefits of development
Ensure that both women and men are able to participate meaningfully
and equitably
Ensure that projects do not discriminate against women and girls
Principle 3: Environmental
Sustainability
Address poverty and inequality while maintaining and enhancing
natural capital
Apply relevant social and environmental standards to avoid adverse
impacts, or where avoidance is not possible, to minimize, mitigate, and
manage potential residual adverse impacts
Use and promote a precautionary approach to natural resource
conservation
Standard 1: Biodiversity
Conservation and Natural
Resources Management
Natural Habitats: If potential adverse impacts, proceed only if (i) no
viable alternatives, (ii) benefits substantially outweigh environmental
costs, (iii) conservation and mitigation measures in place
Water Resources: Apply integrated water resources management
approach. Seek to avoid significantly altering flow regimes.
Sustainable Management of Living Natural Resources: Ensure
sustainable resource management. Apply appropriate industry-specific
best management practices. Support small-scale producers/harvesters
to adopt sustainable practices.
Standard 2: Climate Change
Adaptation and Mitigation
Climate Change Risks should be identified and assessed. Include
gender risks and potential differentiated impacts
Identify opportunities to facilitate adaptation
Standard 3: Community
Health, Safety and Working
Conditions
Community Health and Safety: Evaluate health and safety risks from
projects: design, construction, operation, decommissioning, and
establish preventive measures consistent with good international
practice (apply World Bank Group EHS Guidelines)
Consider exposure to accidents and natural hazards and avoid
exacerbation (e.g. land use changes that may increase risk of flooding,
landslides)
Consider how women’s and children’s health and safety could be at
risk
Infrastructure safety: Ensure design, construction, approval by
competent professionals and authorities. Where structural failure
poses safety risks, (i) develop/monitor plans for supervision, operation,
maintenance; (ii) independent experts verify design, construction,
operational procedures; (iii) periodic safety inspections are conducted
Emergency Preparedness: Ensure emergency preparations and plans
are in place, resourced, reviewed, and publicized. Ensure emergency
planning is gender sensitive and participatory. Consider potential
differential impacts of emergency situations on men, women, children,
elderly, disabled, potentially marginalized groups
Community exposure to disease: Avoid or minimize the potential for
community exposure to water-borne, water-based, water-related, and
15
vector-borne diseases, and communicable diseases that could result
from Project activities (including labour influx)
Labour Standards: Ensure compliance with national labour and
occupational health and safety laws, with obligations under
international law, and consistency with the principles and standards
embodied in the International Labor Organization (ILO) fundamental
conventions, including forced labour and child labour
Standard 4: Cultural Heritage Avoid adverse impacts, comply with national laws and international
obligations. If avoidance not possible, mitigate impacts. Develop CH
Management Plan to mitigate significant adverse impacts
Use independent experts to assess adverse impacts and stakeholder
consultations
Incorporate chance find procedures
Do not remove cultural heritage unless conditions met
If utilize cultural heritage, (i) inform communities of rights, (ii) conduct
good faith negotiations with documented outcome, (iii) provide for fair
and equitable benefit sharing
Standard 7: Pollution
Prevention and Resource
Efficiency
Pollution prevention: Avoid the release of pollutants, and when
avoidance is not feasible, minimize and/or control the intensity and
mass flow of their release. Apply international good practices and
World Bank Group EHS Guidelines
Wastes: Avoid/minimize generation of waste, ensure recovery, reuse,
proper treatment, disposal. Ensure reputable contractors and chain of
custody
Hazardous Materials: Avoid/minimize release of hazardous materials. If
avoidance not possible, assess health risks, including differentiated
effects on women, men, children. No manufacture or use of materials
subject to international bans or phase-outs (Stockholm POPs, Montreal
Ozone)
Pesticides: Apply IPM/IVM, avoid/reduce synthetics, utilize least
harmful, prohibit use of WHO Class la & lb pesticides and control Class
II, handle per FAO International Code of Conduct
Resource Efficiency: Apply feasible, cost effective resource efficiency
measures (e.g. reduce water usage) to ensure no significant adverse
impacts on others/ecosystems
NOTE: This provides a summary of key relevant requirements, the full SES (www.undp.org/ses) should be referenced for a comprehensive list of requirements.
The main risks identified through the SESP are summarized below along with minimum requirements that need to be
considered and indicative management measures.
4.1 Conflict
4.1.1 Activities That May Result in Conflict Risks
Because of the ongoing conflict in Yemen, all sub-projects need to be developed in a conflict sensitive approach to
ensure activities don’t exacerbate conflict or violence. In addition, local conflicts may occur due to competition over
limited jobs and conflict between contractors and local laborers. This is a key element of UNDP’s commitment to
human rights in the SES.
16
4.1.2 Management Measures
Given that the ECRP is in its third year of implementation, measures have already been undertaken to reduce the
potential impacts. Such measures include mainly developing a clear definition of targeting and selection criteria based
on data provided by the UN Clusters; participatory preparation and implementation of subprojects by communities and
relevant stakeholders (refer to ESMF section on Stakeholder Engagement for further detail); frequent communication
with communities and local stakeholders; grievance redress/ stakeholder response mechanism procedures to ensure
timely handling of grievance redress; and public disclosure of the reasons for the rejection of subprojects, if any, to
increase transparency.
PWP and SFD apply a conflict-sensitive approach to prevent and detect conflict and respond quickly to potential
conflicts. This helps ensure that the implementation process will do no harm and leads to effective development
interventions.
The following steps are taken to ensure achieving such goal (see PWP Operation Manual):
• Through transparent allocation of funds that is based on national statistics indicators in the governorate and
district levels, followed by coordination with local actors and inclusive participatory process, PWP/SFD will be
reducing conflict over resources.
• Selection of the community beneficiaries is based on a transparent eligibility criteria and consultations with
communities and local leaders.
• Before implementation and during the participatory consultations with local communities to define the
interventions, PWP/SFD's teams analyzes the context in which the project will be implemented to make sure
that PWP/SFD's intervention will not cause a conflict or escalate an existing conflict in that particular area. This
analysis enables PWP/SFD to understand the interaction between the intervention and the context in a
particular area. The steps will be as follows:
o Understanding the context in which the project will be implemented
o Carrying out a conflict analysis
o Understanding the interaction between the intervention and the Context
o Linking the conflict analysis with the programming cycle of the Intervention
o Using this understanding to avoid negative impacts and maximize positive impacts
o Implement, monitor and evaluate the intervention under a conflict-sensitive approach (including
redesign when necessary)
• Ensuring transparency of the procurement process including those of community contracting.
• Expected environmental and social impacts (including OHS risks) are identified during the project’s
preparation and mitigation measures are included in the design and implementation plan. Where investments
are required to implement the measures, ensure reflection of these measures quantified as pay-items in the
tender bill of quantities.
• During the implementation process, PWP/ SFD's staff keeps;
o Monitoring the situation to predict and recognize possible conflicts around the project and try to
keep risks at a minimal level.
o Following-up in order to strengthen the partnership with local authorities and community
committees as important players in conflicts resolution.
• PWP/SFD does not interfere to resolve existing conflict or be part of any conflict. However, PWP/SFD’s
intervention might help in reducing existing conflict.
• PWP/SFD might work in an environment where a conflict is prevailing such as the conflicts resulting from the
war in some areas in Yemen or are due to tribal conflicts. The staff in such case are fully aware of the
conflicts that surround their work and activities, but their project does not deal directly with the conflict.
• The evaluation of LIWP and other community-based interventions found that PWP/SFD’s intervention
increases community solidarity and cooperation.
• PWP/SFD's complaint mechanism will be a complementing tool to catch shortcomings that may arise,
through of the above precaution measures, and deal with them transparently and learn lessons from them to
improve performance in future programs. Project-affected people will be informed of the complaint
mechanism.
In addition, stakeholders have noted that there is sometimes conflict between contractors and local labour. This will be
mitigated through greater stakeholder awareness and engagement at the local level and further skill-building of local
labour and ensuring all parties are aware of the grievance mechanism.
17
4.2 Gender and Social Inclusion
With persistent gender gaps existing even prior to the conflict (i.e., in education, legal restrictions on mobility and
decision-making, barriers to female participation in the labor force and in political life, and few opportunities for voice,
paid work and entrepreneurial activity), women are more vulnerable to the economic, social and security challenges
that result from the conflict and should thus be proactively reached for access to cash to improve their purchasing
power for food and basic necessities. The stark gender gaps are influenced by and set within the context of
conservative and strict gender norms. The project includes specific actions and design parameters to ensure the
inclusion and participation of women. Such design parameters will ensure women are provided an equal opportunity
to benefit from the employment opportunities (for example, targeting female-headed households, allowing flexibility in
work hours, and providing on-site child care).
Consideration for IDPs, women and youth as specific vulnerable groups are included in the targeting as well as type of
intervention.
Investing in persons with disability is central to poverty reduction and achieving the sustainable development goals. It
can contribute to greater social equity, inclusion, cohesion, and human capital formation in Yemen, all of which are
critical to breaking the cycle of poverty, deprivation, and social exclusion. The Yemen ECRP has been instrumental in
introducing adaptive and shock responsive safety net responses.
4.2.1 Activities That May Result in Gender and Social Inclusion Impacts or Risks
The ECRP is implemented in the midst of the current crisis in Yemen, where women are adversely affected and at the
same time asked to take on new and additional roles as heads of households or income-earners. In this light, ECRP
implementation is found to have the potential to reproduce discrimination against women based on gender, if
adequate gender mainstreaming considerations are not taken into account within the Project approach.
4.2.2 Management Measures
To the extent possible, the ECRP will promote gender equality and the empowerment of women and seek to reduce
gender inequalities in access to and control over resources and the benefits of development. Sub-projects will ensure
that both women and men are able to participate meaningfully and equitably, have equitable access to project
resources, and receive comparable social and economic benefits.
Sub-projects will not discriminate against women or girls or reinforce gender-based discrimination and/or inequalities.
Sub-projects will ensure precautionary measures are in place to prevent potential exposure of beneficiaries, workers,
and affected people to sexual exploitation and abuse.
Sub-projects will ensure precautionary and control measures are in place to prevent potential exposure of
beneficiaries, workers, and affected people to health and safety hazards.
The project will build upon existing services and pilot new approaches to improve the quality of targeted social care
services and economic opportunities for people with disabilities.
The ECRP has mainstreamed gender issues and is addressing gender equality from project identification, site selection,
management and oversight. Appropriate management measures taken by the project are explained below.
The project has actively targeted women (at least 30%) to support their income-generation opportunities and
contribute to the delivery of community service and livelihood assets through Cash for Work and Cash for Services, and
through earmarked funding (accounting to 15% of the project budget) dedicated to address severe and acute
malnutrition for pregnant and lactating women (and children) by providing cash assistance (mothers are the recipients)
and facilitating the affected families’ access to nutrition services.
To ensure women are targeted by the project, in cash for work interventions, the targeting unit is the household.
Women are encouraged to participate by measures that make their participation easier and acceptable to households
and the community: allowing flexible hours of on-site work, providing on-site child care (this will also hire a caregiver
from the community), having the subproject at the community level and at a location close to the villagers, and by
consulting women on the types of subprojects they can participate in. Subcomponent 1.1 is expected to have 30
percent female participation, and more than 50 percent of the microfinance clients under subcomponent 1.3 are
women. Women are assumed to benefit equally from the community infrastructures created. Women are the primary
beneficiaries of the water harvesting schemes as these reduce time and effort in fetching water, a responsibility for
women and girls. Women also benefit from having latrines at home, they regain dignity and freedom from humiliation
18
of open defecation. Women are also the primary wage participants and beneficiaries of nutrition-based service
delivery.
Additionally, nutrition activities target households with pregnant and lactating women and children under the age of
five. Primary focus is given to eligible households from the list of the Social Welfare Fund (SWF) households – the
poorest of the poor – but will not be limited to them, as many poor HHs are excluded from the SWF program. Women
and children of the SWF households receive cash assistance of YR10,000 per month (about $40) for 12 months
conditions to attending health education sessions and follow up on the treatment (provided by the health sector).
Wider community members with mothers and children under age of 5 who have been screened and identified with
severe or acute malnutrition benefit from a transportation and accommodation allowance and a treatment allowance
of up to YR 10,000 (about $40) per family per month during the treatment period (6-9 months).
4.3 Biodiversity and Natural Resources
Conserving biodiversity, maintaining ecosystem services, and sustainably managing natural resources are fundamental
to sustainable development. The ECRP will seek to maintain and enhance the goods and services provided by
biodiversity and ecosystems in order to secure livelihoods, food, water and health, enhance resilience, conserve
threatened species and their habitats, and increase carbon storage and sequestration. ECRP will also promote
sustainable use of natural resources to support livelihoods of vulnerable communities as well as benefit sharing
between biodiversity conservation and livelihoods restoration.
4.3.1 Activities That May Result in Biodiversity and Natural Resources Impacts or Risks
The project will intervene in fisheries, agriculture and livestock and water resources.
Fisheries (Low Risk)
Project activities to support small scale fishermen through the provision of boat engines in order to increase food
production were found to have a Low Risk Rating. The project will target artisanal fishermen using small boats with one
off-board petrol engine. There is a low risk that the project may impact on biodiversity and natural resources through
overexploitation of fisheries. The small boat engines are not used in deep waters, consequently this reduces the
possibility of overfishing additionally fishermen will use traditional methods of fishing. Some of the fishermen will be
equipped with fish finders, to help expedite the search of the fish and thus economize the use of fuel. The design of
this activity under ECRP project has provisions to ensure sustainability, and the project will carefully monitor the
activities of the fishermen during its implementation.
Small scale farming and livestock (Low to Moderate Risk)
Activities will include: Watershed Management/Water Channels, Rehabilitation of Farm Lands, Rehabilitation of Farm
Irrigation Infrastructure, Agriculture Infrastructure, Agriculture Input Provision, Support to Livestock Producers.
Livestock activities involve the creation of yards in addition to other.
Although the projects are small scale in nature, the cumulative effects of providing support to communities may
involve inadvertent impacts on ecosystems that can result in negative effect to ecosystem services provision and
biodiversity. It may also include adverse impacts in handling of plastic and wastes generated from agricultural inputs.
When further sub-project screening is conducted more information will be available as to the extent of the impacts and
management measures required.
Additionally, under the section below on Pollution standards, a mention of potential impacts of the use of pesticides in
the activity related to provision of agriculture inputs is addressed in more detail.
Water resources (Moderate Risk)
The project activities include rehabilitation of existing water supply infrastructure at a small-scale. This includes rain
water catchments at the household level, community reservoirs and maintenance of clean water supply - piping
systems-, and small-scale agriculture irrigation systems. Sub-projects will not create new extraction points or new
infrastructure for containment or diversion of water. The project aims to rehabilitate or construct a total of 500,000
m3 storage capacity for water supply which are relatively small-scale.
Although the project interventions are small scale in the context of Yemen, in light of its semi-dry and arid climate and
exposure to climate change and variability, all water related interventions may have a potential impact on water
availability in the medium and long term.
19
4.3.2 Management Measures
Considerations for the identification of management measures are summarized below, and additional guidance can be
referred to in the SES Biodiversity Conservation and Natural Resource Management.
Precautionary approach: The ECRP applies a precautionary approach to the use, development, and management of
natural habitats, the ecosystem services of such habitats, and living natural resources.
Assessment: As an integral part of the social and environmental assessment process, direct and indirect impacts on
natural resources, biodiversity and ecosystem services in the Project’s area of influence are identified and addressed.
In sub-projects that present potential significant impacts on natural resources, biodiversity and ecosystem services an
assessment process will consider, inter alia (i) risks of habitat and species loss, degradation and fragmentation, invasive
alien species, overexploitation, hydrological changes, nutrient loading, pollution, and (ii) differing values (e.g. social,
cultural, economic) attached to biodiversity and ecosystem services by potentially affected communities. Potential
cumulative and induced impacts will be assessed. Project-related impacts across potentially affected landscapes should
be considered.
Water resources: For sub-projects that affect water resources, integrated water resources management approaches
will be applied that seek the coordinated development and management of water, land and related resources in order
to maximize the economic and social welfare in an equitable manner and without compromising the sustainability of
ecosystems. Sub-projects will avoid significantly altering flow regimes in ways that prevent water resources from
fulfilling their functions for upstream and downstream ecosystems and their services to local communities. Social and
environmental risk assessments should address, among other issues, potential effects and impacts related to climate
variability, water pollution, sedimentation, water-related disasters, drinking water supply, energy production,
agriculture, and fisheries.
Sustainable management of living natural resources: Living natural resources will be managed in a sustainable manner.
Sustainable resource management is the management of the use, development, and protection of resources in a way,
or at a rate, that enables people and communities, including indigenous peoples, to provide for their social, economic,
and cultural well-being while also sustaining the potential for those resources to meet the needs of future generations.
This includes safeguarding biodiversity and the life-supporting capacity of air, water, and soil ecosystems. Sustainable
management also ensures that people who are dependent on these resources are properly consulted, women and
men have opportunities to equally participate in development, and benefits are shared equitably.
UNDP will ensure sustainable resource management through the application of appropriate, industry-specific best
management practices, and where codified, through application of one or more relevant credible standards as
demonstrated by an independent verification or certification system.
For Projects that involve the production, harvesting, and/or management of living natural resources by small-scale
landholders and/or local communities, UNDP will support adoption of appropriate and culturally sensitive sustainable
resource management practices.
In addition to the general requirements related to management measures as stated in the section above, project
context specific management measures were identified for each sector.
Project specific management measures in addition to standard SES UNDP measures (fisheries)
The project will work with fishing associations responsible for ensuring that fishing protocols that establish procedures
for sustainable fisheries are in place and adhered to, to protect fish stocks and regulate seasonal controls on fishing.
Development and strict implementation of policy, legislative and management tools are working to ensure harvest
level of coastal resources are maintained within the biological limits of Yemen's coastal zones.
The project will be implemented in line with the Biodiversity Conservation and Sustainable NRM of the SES which
includes fishing management. The concept of sustainable and responsible fishing will be promoted through this
partnership. Through its direct support to small scale fishermen, the project will improve community livelihoods and
training on quality and resource sustainability to include the reduction of wastage.
Project specific management measures in addition to standard SES UNDP measures (water resources) (to be developed
based on the local context):
Social and environmental risk assessments should be conducted to address, among other issues, potential effects and
impacts related to climate variability, water pollution, sedimentation, water-related disasters, drinking water supply,
energy production, agriculture, and fisheries.
20
4.4 Climate Change
Climate change is a fundamental threat to sustainable development and the fight against poverty. It has the potential
to stall and even reverse human development through its impacts on key development sectors and activities, including
agriculture and food production, water, ecosystems and other natural resources, disaster risk management and health.
Climate change may exacerbate extreme weather events, increasing the risk of high-impact disasters. Communities
that are already subjected to impacts from climate change may experience an acceleration and/or intensification of
impacts due to Project activities that do not integrate and anticipate climate change risks.
Yemen has a predominantly semi-arid to arid climate and is highly vulnerable to climate change-related impacts such
as drought, extreme flooding, changes of rainfall patterns, increased storm frequency/severity, sea level rise. Literature
show that the main sectors under stress are: water resources, agriculture, and coastal zones. Water scarcity related to
prolonged droughts, evaporation, drying up of wells, excessive rainfall (which produces flash flooding and can
potentially wipe out crops) caused by rainfall variability are the key issues.
ECRP sub-projects will aim to be sensitive to climate change risks and not contribute to increased vulnerability to
climate change.
4.4.1 Activities That May Result in Climate Change Impacts and Risks
The ECRP project activities related to agriculture (including farming, livestock) and fisheries and water (irrigation,
catchment, conservation), will be most sensitive and vulnerable to the impacts of climate change. Infrastructure in
areas of potential flooding may also be at risk.
Some project activities that aim to increase water availability, may inadvertently lead to depletion of groundwater
resources or diversion of sources to some communities in detriment of others, if not properly managed based on
appropriate climate risk information and management measures.
4.4.2 Management Measures
Climate change risk assessment: As an integral part of the social and environmental assessment process, Proposed
subprojects are screened and assessed for climate change-related risks and impacts of and to projects. PWP and SFD
will ensure relevant climatic information is identified and informs project design and management measures. If
significant potential risks are identified, further scoping and assessment of vulnerability, potential impacts, and
avoidance and mitigation measures, including consideration of alternatives to reduce potential risks, will be required.
In projects, or a portfolio of projects, that present climate change risk, a climate change risk assessment may include
the following, where relevant:
a) Potential project-related increases in emissions that may exacerbate climate change, such as GHG emissions and
black carbon emissions.
b) The viability or longer-term sustainability of project outcomes due to potential climate change. This will involve the
identification of components that are sensitive or vulnerable to emerging or anticipated manifestations of climate
change.
c) Risks that a project may increase exposure to climate change. Project components must be assessed for potential
unintended or unforeseen increases in vulnerability to climate change.
d) Potential social, gender, and age risks, based on the differentiated impacts of climate change.
e) Opportunities for (i) facilitating adaptation via synergies with existing or planned activities, (ii) combining mitigation
(e.g. reduction in GHG emissions) and adaptation measures, and (iii) exploiting potentially beneficial changes in climatic
or environmental conditions to deliver developmental benefits.
4.5 Community Health, Safety and Working Conditions (including OHS)
The ECRP will avoid or minimize the risks and impacts to community health and safety that may arise from project-
related activities, with particular attention given to marginalized groups. This includes Occupational Health and Safety
(OHS) risks. Labour is one of a country’s most important assets in the pursuit of poverty reduction. Respect of workers’
rights and the provision of safe working conditions are keystones for developing a strong and productive workforce.
The ECRP applies the World Bank Group Environment, Health and Safety (EHS) guidelines.
21
4.5.1 Activities That May Result in Community Health, Safety, Working Condition Impacts and Risks
Sub-project activities, equipment, and infrastructure can increase community exposure to risks and impacts. While this
is identified as a Moderate Risk, some projects have experienced high levels of OHS risks. This has therefore been
identified as a priority risk and management measures put in place to reduce risk and manage risks.
Such project activities such as working from height, excavation works, rock extraction, working in confined areas, lone
workers, traffic, and weak management of work site such as housekeeping and access and egress controls, may pose
hazards and risk threats to the workers and local community members. Exacerbating this, stakeholders have noted that
there is a weak culture of using safety precautions and safety gear in Yemen.
In addition, given the context in Yemen, there is a risk of airstrikes that needs to be minimized to the extent possible.
Another challenge is that some of the safety gear needed is not always available in the local markets.
Basic services, such as water and sewer, may face disruption and present community health and safety risks to those
affected.
Project activities that may trigger such risks to local communities and workers are detailed under the “Hazard
identification, risk assessment and determining controls” section of the latter report and in the SESP and are listed
below:
• Project construction, operation (fall from heights (human and material), slip, trip and falls, transportation
including traffic injuries, material and equipment handling and transfer, excavation work, others e.g. weather
elements, physical exertion, etc.)
• Failure of structural elements of the project may pose risks to communities (e.g. collapse of buildings or
infrastructure, demolishing work, accumulation of soil)
• Potential increased health risks (e.g. from water-borne or other vector-borne diseases or communicable
infections)
• Project implementation activities result in a disruption in basic services, such as water or sewer, temporarily
affecting the local community.
• Risks related to ongoing conflict in Yemen and potential for airstrikes.
4.5.2 Management Measures
Appropriate management measures have been put in place. A detailed OHS risk categorization was developed for the
purpose of identifying sub-project level risks to enable halting any salient high-risk projects from further
implementation until adequate management measures are put in place. Additionally, a specialized consultant was
hired to develop management plans, screening checklists, and ensure high frequency of field monitoring. Additionally,
support to the Responsible Parties has been reinforced by training and monitoring and capacity assessments. The
results of the latter measures taken by UNDP are included in a detailed “OHS Framework” which is available in Annexes
5 and 6.
Community health and safety: Community health and safety refers to protecting local communities from hazards
caused and/or exacerbated by project activities (including flooding, landslides, contamination or other natural or
human-made hazards), disease, and the accidental collapse or failure of Project structural elements such as dams.
Project-related activities may directly, indirectly or cumulatively change community exposure to hazards. A significant
concern with major development projects is the spread of communicable diseases from the workforce to the
surrounding communities.
Risks to, and potential impacts on, the safety of affected communities and workers during the design, construction,
operation, and decommissioning of projects will be assessed to establish preventive measures and plans to address
them in a manner commensurate with the identified risks and impacts. These measures will favour the prevention or
avoidance of risks and impacts over their minimization and reduction. Consideration will be given to potential exposure
to both accidental and natural hazards, especially where the structural elements of the project are accessible to
members of the affected community or where their failure could result in injury to the community. Sub-projects will
avoid or minimize the exacerbation of impacts caused by natural or man-made hazards, such as landslides or floods
that could result from land use changes due to activities.
Infrastructure safety: Structural elements will be designed and constructed by competent professionals and certified or
approved by competent authorities or professionals. Sub-projects with structural elements or components whose
failure or malfunction may threaten the safety of communities, will ensure that: (i) plans for Project supervision,
22
operation, and maintenance are developed and monitored; (ii) independent expertise on the verification of design,
construction, and operational procedures is used; and (iii) periodic safety inspections are carried out.
Emergency preparedness: Responsible Parties will be prepared to respond to accidental and emergency situations in a
manner appropriate to prevent and mitigate any harm to people and/or the environment. This preparation, reflected
in planning documents, will include the identification of areas where accidents and emergency situations may occur,
communities and individuals that may be impacted, response procedures, provision of equipment and resources,
designation of responsibilities, communication, and periodic training to ensure effective response. The emergency
preparedness and response activities will be periodically reviewed and revised, as necessary to reflect changing
conditions. The differential impacts of emergency situations on women and men, the elderly, children, disabled people,
and potentially marginalized groups will be considered, and the participation of women in decision-making processes
on emergency preparedness and response strategies will be strengthened. Appropriate information about emergency
preparedness and response activities, resources, and responsibilities will be disclosed to affected communities.
Community exposure to disease: Sub-projects will avoid or minimize the potential for community exposure to water-
borne, water-based, water-related, and vector-borne diseases, and communicable diseases that could result from
activities, taking into consideration the differentiated exposure to and higher sensitivity of marginalized groups. Sub-
projects will avoid or minimize transmission of communicable diseases that may be associated with the influx of
temporary or permanent project labour. Standing water will be minimized, covered or treated to minimize mosquito
breeding. Local authorities and the Responsible Parties will coordinate closely to ensure any disruption to local basic
services, such as water and sewer, is avoided where possible and otherwise minimized.
Work standards: Sub-projects will comply with national labour and occupational health and safety laws, with
obligations under international law, and consistency with the principles and standards embodied in the International
Labor Organization (ILO) fundamental conventions, including freedom of association, elimination of discrimination in
employment and occupation, elimination of forced or compulsory labour, and elimination of the worst forms of child
labour. The ECRP will not employ people under the age of 18; however, youth that are 16-17 years old may be eligible
for employment training and capacity building.
Occupational health and safety: Occupational health and safety refers to protecting workers from accident, injury or
illness associated with exposure to hazards encountered in the workplace. Hazards can arise from materials (including
chemical, physical and biological substances and agents), environmental or working conditions (e.g. oxygen-deficient
environments, excessive temperatures, improper ventilation, poor lighting, faulty electrical systems), or work
processes (including tools, machinery and equipment).
Responsible Parties’ commitment to the OHS Framework strengthens compliance with OHS requirements and
protection of staff/workers, as well as middle management accountability to implement the policy and roles and
responsibilities and enforcing control measures and procedures. Risk assessment will be conducted for each sub-
project site to identify potential hazards and risks and develop and implement corresponding risk control measures.
Safety measures hierarchy will be applied starting with hazard elimination, substitution, engineering controls,
administrative controls and finally use of PPEs. Furthermore, safe working systems and procedures will be developed
and used as well as permit-to-work forms for high risk activities to control risks, authorize implementation confirming
compliance to OHS requirements and ensuring close monitoring and inspections to control and minimize risks. In
addition the development of positive OHS behavior and strong culture of adherence and compliance to OHS systems
will be promoted including setting up and activating branch OHS committees and conducting of field inspections
regularly by managers to ensure improvement of OHS systems and practices and promote conducive OHS culture.
Workers will be provided with a safe and healthy working environment, taking into account risks inherent to the
particular sector (including gender bias) and specific classes of hazards in the work areas. Steps will be taken to prevent
accidents, injury, and disease arising from, associated with, or occurring during the course of work and will ensure the
application of preventive and protective measures consistent with the World Bank Group’s Environmental, Health, and
Safety Guidelines and other international good practice, as reflected in internationally-recognized standards. The
involved workers will be insured and the insurance payment will be covered directly by the IP in case of direct
implementation modality and as a pay item through bills of quantities in the bidding documents in case of contracting
modality.
Please refer to the ECRP OHS Framework for details (Framework for Actions on Occupational Health and Safety Under
Yemen ECRP (Annex 5)
Security-related issues: Sub-projects under ECRP do not engage security personnel. In case sub-projects do require
involvement and engagement of security personnel to protect facilities and personal property, security arrangements
23
should be provided in a manner that does not violate human rights or jeopardize the community’s safety and security.
Potential risks posed by security arrangements to those within and outside the Project area will be assessed, those
providing security will be appropriately vetted and trained, and security arrangements will be appropriately monitored
and reported. UNDP has currently deconflicted 70 subproject sites in five governorates (Saada, AlHudaydah, Taiz,
AlBaida and Sana’a) in high risk locations to minimize the risk of airstrikes.
4.6 Cultural Heritage
The ECRP seeks to ensure that Cultural Heritage is protected in the course of sub-project activities. UNDP seeks to
ensure equal participation, access and contribution of women and men in protecting and sharing the benefits of
Cultural Heritage.
The Standard applies to sub-projects that may adversely impact Cultural Heritage, including projects that meet any of
the following criteria: (i) located in, or in the vicinity of, a Cultural Heritage site ; (ii) involving significant excavations,
demolitions, movement of earth, flooding, or other environmental changes; (iii) proposes to utilize tangible or
intangible forms of Cultural Heritage for commercial or other purposes. (iv) interventions to preserve the cultural
heritage sites.
4.6.1 Activities That May Result in Cultural Heritage Impacts and Risks
As the project conducts small scale infrastructure activities related to community works such as road paving,
community reservoirs and piping, and repairing of school buildings in addition to others these project activities,
although many do not target the rehabilitation of Cultural Sites directly, they may be located in the vicinity of cultural
heritage sites and consequently produce unintended negative effects on such sites. In addition, those sub-projects that
target the preservation and protection of cultural heritage need to ensure risk management measures are in place.
4.6.2 Management Measures
Avoidance: Avoid significant adverse impacts to Cultural Heritage through alternative project siting and design. The
impacts on Cultural Heritage resulting from project activities, including mitigating measures, may not contravene the
national legislation, or its obligations under relevant international treaties and agreements.
Mitigation: Where potential adverse impacts are unavoidable, appropriate mitigation measures will be identified and
incorporated as an integral part of the social and environmental assessment process. Where potential adverse impacts
may be significant, a Cultural Heritage Management Plan should be developed as part of the Environmental and Social
Management Plan (ESMP).
Use of experts: For projects with potential adverse impacts, qualified and experienced independent experts will assess
the project’s potential impacts on Cultural Heritage using, among other methodologies, field-based surveys and
involving meaningful, effective, and informed stakeholder consultations as part of social and environmental
assessment process. Note that SFD has a Cultural Heritage unit.
Use of Cultural Heritage: Where a project proposes to utilize Cultural Heritage, including the knowledge, innovations,
or practices of local communities, affected communities will be informed of their rights, the scope and nature of the
proposed development, and the potential consequences of such development. The project will not proceed without
meaningful, effective participation of affected communities and unless (i) good faith negotiations with affected
communities result in a documented outcome, and (ii) the Project provides for fair and equitable sharing of benefits
from any commercialization of such knowledge, innovation, or practice, consistent with the affected community’s
customs and traditions. For Projects that propose to utilize Cultural Heritage of indigenous peoples, the requirements
of Standard 6: Indigenous Peoples apply.
Chance find procedures: When the social and environmental assessment process determines that Cultural Heritage is
expected to be found in the project area, chance find procedures will be included in the ESMP. Chance finds will not be
disturbed until an assessment by a competent specialist is made and actions consistent with these requirements are
identified.
Conditions for removal: The project will not remove any Cultural Heritage unless the following conditions are met: (i)
no alternatives are available; (ii) the overall benefits of the Project substantially outweigh the anticipated Cultural
Heritage loss from removal; and (iii) any removal employs best available techniques and is conducted in accordance
with relevant provisions of national and/or local laws, regulations, and protected area management plans and national
obligations under international laws.
24
4.7 Pollution Prevention and Resource Efficiency
4.7.1 Activities That May Result in Pollution and Resource Efficiency Impacts and Risks
The project will support the construction and/or rehabilitation of pit latrines, provide agriculture inputs that may
include pesticides, support small health care centers infrastructure or services, cleaning up public spaces that may
include municipal solid waste, and sewage that may include hazardous/human excreta and waste.
Pit latrines may consist of a pit—circular, rectangular, or square—dug into the ground and covered with a concrete slab
or floor with a hole through which excreta falls. Unimproved pit latrines are those without slabs or platforms. In the
latter there are risks of groundwater contamination. Additionally, the project will intervene by providing small scale
farmers with agriculture inputs, that may involve pesticides. Other activities may include the improvement of health
care services through support to small health care center and cleaning of public spaces including municipal solid waste.
In relation to pit latrines, there are ecological health impacts that may be associated with microbiological and chemical
contamination of groundwater due to use of latrines. In Yemen, the main drinking water sources are extracted from
groundwater (in addition to rainwater harvesting). A concern is that pit latrines, that generally lack a physical barrier,
such as concrete, between stored excreta and soil and/or groundwater. Contaminants from pit-latrine excreta may
potentially leach into groundwater, thereby threatening human health through well-water contamination.
Agriculture related interventions which include the use of pesticides trigger both environmental, health and
occupational health and safety concerns. Runoff waters from agriculture may contaminate local drinking water
sources, such as streams, wells, other leading to potential disease downstream. Project workers and small-scale
farmers handling pesticides are also exposed to health hazards.
Support to small health care centers may include rehabilitation of sewage systems that may consequently involve
hazardous waste water.
Cleaning up of public spaces may involve the handling, disposal and transport of municipal solid waste.
Waste may also be generated during construction and implementation activities.
4.7.2 Management Measures
Pollution prevention: Sub-projects will avoid the release of pollutants, and when avoidance is not feasible, minimize
and/or control the intensity and mass flow of their release. This applies to the release of pollutants to air, water, and
land due to routine, non-routine, and accidental circumstances.
Pollution prevention and control technologies and practices consistent with international good practice are applied
during the project life cycle. The technologies and practices applied will be tailored to the hazards and risks associated
with the nature of the Project.
Ambient considerations: To address adverse impacts on existing ambient conditions (such as air, surface water,
groundwater, and soils), a number of factors will be considered, including the finite assimilative capacity of the
environment, existing and planned land use, existing ambient conditions, the Project’s proximity to ecologically
sensitive or protected areas, the potential for cumulative impacts with uncertain and irreversible consequences, and
strategies for avoiding and minimizing the release of pollutants.
Wastes: Sub-projects will avoid the generation of hazardous and non-hazardous waste materials. Where waste
generation cannot be avoided, Projects will reduce the generation of waste, and recover and reuse waste in a manner
that is safe for human health and the environment. Where waste cannot be recovered or reused, it will be treated,
destroyed, or disposed of in an environmentally sound manner that includes the appropriate control of emissions and
residues resulting from the handling and processing of the waste material. If the generated waste is considered
hazardous, reasonable alternatives for its environmentally sound disposal will be adopted while adhering to the
limitations applicable to its transboundary movement. When hazardous waste disposal is conducted by third parties,
UNDP will ensure the use of contractors that are reputable and legitimate enterprises licensed by the relevant
government regulatory agencies and that chain of custody documentation to the final destination is obtained.
Hazardous materials: Projects will avoid or, when avoidance is not feasible, minimize and control release of hazardous
materials resulting from their production, transportation, handling, storage and use. Where avoidance is not possible,
the health risks, including potential differentiated effects on men, women and children, of the potential use of
hazardous materials will be addressed in the social and environmental assessment. Projects will consider the use of less
hazardous substitutes for such chemicals and materials and will avoid the manufacture, trade, and use of chemicals
25
and hazardous materials subject to international bans or phase-outs due to their high toxicity to living organisms,
environmental persistence, potential for bioaccumulation, or potential for depletion of the ozone layer.
Pesticide use and management: While pesticide use is not anticipated, sub- projects that may involve pest
management activities, integrated pest management approaches will be applied and aim to reduce reliance on
synthetic chemical pesticides. The integrated pest/vector management programme will entail coordinated use of pest
and environmental information along with available pest/ vector control methods, including cultural practices,
biological, genetic and, as a last resort, chemical means to prevent unacceptable levels of pest damage. When pest
management activities include the use of pesticides, pesticides that are low in human toxicity, known to be effective
against the target species, and have minimal effects on non-target species and the environment will be selected. The
health and environmental risks associated with pest management should be minimized with support, as needed, to
institutional capacity development, to help regulate and monitor the distribution and use of pesticides and enhance
the application of integrated pest management.
Projects will not use products that fall in Classes Ia (extremely hazardous) and Ib (highly hazardous) of the World Health
Organization Recommended Classification of Pesticides by Hazard. WHO Class II (moderately hazardous) pesticides will
not be used if the relevant Responsible Party lacks restrictions on distribution and use of these chemicals or facilities to
handle, store, apply and dispose of these products properly, or if they are likely to be accessible to personnel without
proper training and equipment. Pesticides will be handled, stored, applied and disposed of in accordance with
international good practice such as the FAO International Code of Conduct on the Distribution and Use of Pesticides.
5 Procedures to Address Social and Environmental Impacts
5.1 Sub-Project Screening and Classification Requirements
The ECRP will support a series of sub-projects over the course of its implementation. The type of sub-projects are
described in Section 2 of this ESMF. Each sub-project will be screened for social and environmental risks (including OHS
risks) and impacts applying PWP and SFD screening tools. Screening and classification will be completed prior to
approval of sub-projects and signing of the Financial Agreement. The screening of sub-projects will also be updated if
there are any significant changes in the sub-project’s design or context that may materially change its social and
environmental risk profile.
Sub-project screening and categorization should be conducted at the earliest stage of design when sufficient
information is available for this purpose. Based on the screening, the sub-project is categorized according to the
degree of potential social and environmental risks and impacts. In some cases, applicability of specific SES
requirements will need to be determined through additional scoping, assessment, or management review. The
screening process results in one of the following three categories for the proposed sub-project
• Low Risk: Projects that include activities with minimal or no risks of adverse social or environmental impacts.
Further assessment of potential adverse social and environmental risks and impacts is not required.
• Moderate Risk: Projects that include activities with potential adverse social and environmental risks and
impacts, that are limited in scale, can be identified with a reasonable degree of certainty, and can be
addressed through application of standard best practice, mitigation/control measures and stakeholder
engagement during Project implementation. Moderate Risk Projects may require limited social and
environmental assessment and review to determine how the potential impacts identified in the screening will
be avoided or when avoidance is not possible, minimized, mitigated and managed. A site-specific
Environmental and Social Management Plan (scaled to nature of the risks) should be in place to ensure risks
are managed.
• High Risk: Projects that include activities with potential significant and/or irreversible adverse social and
environmental risks and impacts (including OHS), or which raise significant concerns among potentially
affected communities and individuals as expressed during the stakeholder engagement process. High Risk
activities may involve significant impacts on physical, biological, socioeconomic, or cultural resources. Further
impact assessment is required and an Environmental and Social Management Plan will be in place. High Risk
Projects require tight control measures, closer monitoring, enhanced internal and external support.
Note that High Risk sub-projects will be excluded from Yemen ECRP funding. If high level risks are identified during
implementation, Senior management of the Responsible Party and UNDP Project Manager will be notified immediately
and relevant activities will be halted until management measures put in place to reduce the levels of risk.
26
Screening results inform final appraisal and sub-project approval.
An initial gap analysis shows that PWP and SFD screening processes are generally aligned with SES requirements, as
described below. However, a more detailed gap analysis will be conducted and UNDP together with the World Bank
will work with PWP and SFD to update their screening processes as needed to address gaps and also respond to lessons
learned.
5.1.1 PWP Sub-projects
The procedure followed by PWP for undertaking screening and classification of subprojects is articulated in the PWP
ESMF (see Annex 9). An Environmental and Social Impact Assessment Checklist is applied for sub-projects related to
schools, health units/centers, rainwater harvesting reservoirs, sanitation, and rural water projects. The screening
results in one of the following three determinations and is signed by the PWP engineer and PWP environmental
specialist:
• Determination of no adverse impacts
• Determination that there may be adverse impacts and further analysis is required
• Determination of potential adverse impacts and all mitigation measures have been included in the design
and contract conditions.
The first screening is undertaken during application of selection criteria. Those that do not meet criteria for
improvement in environmental conditions will be rejected at the outset.
Sub-projects will then be divided into two groups: those that do not have any significant negative impacts (Low Risk)
and those that may have some impacts (Moderate Risk). PWP does not engage in High Risk projects under the ECRP.
Screening results and classification inform final appraisal and approval of a sub-project. Sub-projects will be grouped
into annual and/or quarterly investment programs to be submitted to the PWP Internal Management Committee for
approval. Social and environmental screening results will be included in the submission. Screening results and ESMPs
will also be recorded in the MIS.
5.1.2 SFD Sub-projects
The procedure followed by SFD for undertaking screening and classification of subprojects is articulated in the SFD
ESMF (see Annex 10). SFD undertakes screening of the subproject proposals and classifies subprojects into Class A, B,
and C, similar to the World Bank categorization and comparable to UNDP’s High, Moderate, Low respectively. The
classification is based on the significance of impacts which depend on the type, location, sensitivity, and scale of the
subproject and the nature and magnitude of its potential environmental impacts. Accordingly, Category C subprojects
(Low Risk) are those which are known to have no adverse environmental and social impacts and accordingly will not
require any further assessment or follow-up. Category B subprojects (Moderate Risk) are those that are likely to have
limited adverse environmental and social impacts that are temporary and/or site specific and can be
reduced/avoided/mitigated with the implementation of appropriate mitigation measures, and these subprojects would
require a scoping to be undertaken and a limited site specific Environmental and Social Management Plan is prepared
as needed. Category A (High Risk) will be excluded from funding.
At the proposal stage, environmental and social responsiveness criteria are applied as well as an occupational hazard
assessment. This is done by using the formats prepared for each type of intervention of class B subprojects (see SFD
ESMF, Annex 9). The format includes decisive questions to examine the responsiveness of the proposal to the
environmental and social issues. The answers to the questions are either "Yes" or "No". If the answer to any of the
questions is "No", then the proposal is dropped or location is changed to ensure full responsiveness to environmental
and social issues.
If the sub-project involves more than one type of activity, all relevant responsive forms should be completed.
At the design stage, a checklist of expected environmental and social impacts to be addressed is completed. This is an
important stage as it will pave the way for the implementation and operation stages. All the expected environmental
and social impacts will be identified at this stage and the mitigation measures will be designed and incorporated in the
subproject design and tender documents, particularly, in the BQ so that it becomes obligatory. The checklist contains
questions about the expected environmental and social mitigation measures to be included in the project documents
for each type of intervention and the answer will be "Yes" or "No". If the answer is "No", then the consultant will need
to justify this in the design report, and also include the completed checklist as an annex to the design report. Annex 3
27
of SFD’s ESMF gives the checklist of the environmental and social issues that will need to be addressed at the Design
Stage for SFD interventions.
If the sub-project involves more than one type of activity, all relevant checklists should be completed.
Annex 2 shows summary of project activities, risks and measurement measures for both Responsible Parties (SFD and
PWP)
5.2 Site-Specific Assessment and Management Requirements
The targeted and site-specific assessments and management plans will be undertaken for all Moderate Risk (Cat B) sub-
projects once project activities/sub-projects and sites are identified. The assessment(s) will be conducted in a manner
consistent with national regulations, PWP or SFD operating procedures, the UNDP SES, and the World Bank’s
Environmental and Social Safeguards Policies and lead to the development of appropriately scaled management
measures and plans to address the identified risks and impacts. For projects with easily identified risk management
measures, a simplified ESMP can be developed.
The UNDP SES and SESP as well as the World Bank Safeguards Policy on ‘Environmental Assessment’ require that in all
cases relevant social and environmental assessments and adoption of appropriate mitigation and management measures
be completed, disclosed, and discussed with stakeholders prior to implementation of any activities that may cause
adverse social and environmental impacts. An indicative outline for an Environmental and Social Management Plan is
provided in Annex 4. All site-specific assessments and management plans will be cleared by World Bank and UNDP and
recorded in the MIS. In cases where similar activities are being conducted in a particular region, these activities may be
grouped and covered under one site-specific ESMP. All ESMPs will be available upon request.
6 Institutional Arrangements and Capacity Building
6.1 General Management Structure and Responsibilities
6.1.1 World Bank
The YECRP is funded by the World Bank. A World Bank senior management task team has been established to oversee
and make decisions about remedies in connection with the UNDP-implemented activities. In particular, the task team’s
functions/responsibilities consist of: (a) reviewing periodic financial and progress and results reports measured by
targets and benchmarks agreed at the time of project approval; (b) applying the agreed process for dealing with
serious issues, including significant social and environmental issues; (c) reviewing progress reports on actions taken to
address a serious situation and results obtained, including details of any recovery of funds or write-off of losses; and (d)
exercising remedies of suspension and termination in accordance with the provision of the legal agreement, if
necessary (see World Bank document PAD 1797).
The World Bank is also engaged in the Biannual Review Meetings (see Section 6.1.2) and conducts Technical Review
Missions.
6.1.2 Project Board (Biannual Review Meetings)
The Project Board (UNDP, World Bank, PWP, SFD) has oversight and advisory authority, representing the highest body
for coordination, strategic guidance, oversight and quality assurance. The body facilitates collaboration between UNDP,
the two responsible parties (PWP and SFD), the World Bank, and other stakeholders for the implementation of the
Project. The Project Board reviews and endorses the Annual Work Plans (AWPs), provides strategic direction and
oversight, reviews implementation progress, and reviews narrative and financial progress reports. The Project Board
will be convened by UNDP and meet at least on a 6-montly basis. It will coincide with the timing of World Bank
technical review missions.
A progress report will be presented to the Project Board and key stakeholders, consisting of progress data showing the
results achieved against pre-defined annual targets at the output level, the annual project quality rating summary, an
updated risk long with mitigation measures, and any evaluation or review reports prepared over the period.
28
6.1.3 UNDP
UNDP will be responsible for overseeing the implementation and compliance with the ESMF, working closely with PWP
and SFD. The ESMF and developed management plans will be part of any tender documentation.
UNDP will be responsible for the revision or updates of this document during the course of project, in consultation with
PWP, SFD and the World Bank.
Project Management Team
The Project Management Team ensures effective implementation of activities on the ground, risk mitigation, and
timely delivery of the results. The team has geographic presence in both Sana’a and Aden to ensure inclusion and to
minimize political sensitivities.
The Project Manager is responsible for day-to-day management and decision-making for the project. The Project
Manager’s prime responsibility is to ensure that the project produces the results specified in the Project Document to
the required standard of quality and within the specified constraints of time and cost. The Project Manager is
responsible for overseeing implementation of the ESMF and required environmental and social risk management
actions.
The Project Manager is supported by a team that includes National Coordinators, an M&E Specialist, Grievance and
Communication Officer. A Management Information System is in final stages of development to support project
management. It is overseen by the UNDP Programme Team on Economic Resilience and Recovery which has the
responsibility of ensuring technical/substantive quality assurance as well as on other aspects such as finance, HR, audit,
and M&E (pls see section below). The Project Management Team is also supported by experts in UNDP Headquarters
and Regional Hubs, including SES expertise.
The project safeguard team including an International Safeguards Specialist, National SES and National OHS experts will
be responsible for enhancing the capacity of UNDP and Responsible Parties to improve social, environmental and
occupational health standards and services, contributing to improved decision making and to capitalize on potential
opportunities while ensuring that adverse social and environmental risks are avoided, minimized, mitigated and
managed.
Project Oversight and Assurance
The ‘project assurance’ function of UNDP is to support the Project Board by carrying out objective and independent
project oversight and monitoring functions. This role ensures appropriate project management milestones are
managed and completed. Project assurance has to be independent of the Project Manager; therefore, the Project
Board cannot delegate any of its assurance responsibilities to the Project Manager. Furthermore, UNDP provides
quality assurance for the project; ensures compliance with UNDP policies and procedures, including its Social and
Environmental Standards and implementation of the requirements of this ESMF.
The oversight and quality assurance for ECRP is done by the UNDP ERR Programme Team, which oversees the UNDP
Yemen programme portfolio focusing on livelihoods and service delivery. UNDP Headquarters will provide corporate
oversight and management support including finance, human resources, audit and investigations.
6.1.4 Responsible Parties
During operations the Responsible Parties will be accountable for implementation of the ESMF. Personnel working on
the project have accountability for preventing or minimizing environmental and social impacts.
The Responsible Parties are directly accountable to UNDP in accordance with their Letter of Agreement. There are two
responsible parties for the project: PWP and SFD. Responsible Parties include HQ offices, branch offices, site
engineers, site supervisors, and workers that also play a role in implementation of the ESMF. Ultimately the
Responsible Parties are responsible for ensuring implementation of the ESMF within their portfolio of sub-projects and
ensuring all relevant documentation is available and reported to UNDP.
SFD will implement subcomponents 1.1 and 1.3 through its 185 staff working in Sana’a headquarter and nine branch
offices across Yemen. PWP will implement subcomponent 1.2 through its 53 staff in Sana’a headquarters and nine
regional offices.
The top management of the Responsible Parties is ultimately responsible for implementation of the ESMF within all
sub-projects that are part of the ECRP.
29
The top management shall demonstrate its commitment by: ensuring the availability of resources essential to
establish, implement, maintain and improve implementation of the ESMF; defining roles, allocating responsibilities and
accountabilities, and delegating authorities, to facilitate effective ESMF implementation.
Responsible Parties shall be responsible to develop, implement and monitor contractors.
Environmental and social management duties shall be specifically assigned to certain positions such as site engineer
(Responsible Parties) and site manager (contractors). They shall have social and environmental risk management
training and shall have direct access and reporting channels to most senior management level. Some of the duties of
the site engineer/manager include:
• organization and conduct of training programmes, including induction training for all workers on the site;
• organization of information to be passed from management to workers, including those of subcontractors;
• provision and implementation of environmental and social management measures, including occupational
health and safety measures;
• Investigation and review of the circumstances and causes of environmental and social risks so as to advise to
the senior management on preventive measures; and participation in pre-site planning.
Good planning and organization at each work site and the assignment of clear responsibility to the site supervisors is
fundamental to risk management and safety in construction. “Supervisor” here means the first level of supervision,
which on site is variously termed as “foreman”, “charge hand”, and so on. Each supervisor requires the direct support
of site management and shall seek to assure within his or her field of competence that:
• working conditions and equipment are safe;
• workplace safety and risk management measures are regularly inspected;
• potential environmental and social risks are managed effectively and responded to quickly if unexpected
issues arise;
• workers have been adequately trained for the job they are expected to do;
• social and environmental management measures, including workplace safety measures, are implemented;
• the best solutions are adopted using available resources and skills;
• necessary personal protective equipment is available and used.
Making the work site safe will require regular inspections and provision of the means for taking remedial measures.
The training of workers enables them to recognize the risks involved and how they can overcome them. Workers shall
be shown the safe way of getting a job done. The workers shall be involved directly, such as through the following:
• “Tool-Box Briefing”, a five- to ten-minute session with the supervisor just prior to starting a task gives the
workers and the supervisor a chance to talk about social and environmental risks, including safety problems,
likely to be encountered and potential solutions to those problems. This activity is simple to implement and it
may prevent a serious accident or issue;
• “Safety Check”, a check by workers that the work environment is safe before starting an operation may allow
them to take remedial action to correct an unsafe situation that could later endanger them, another worker,
or surrounding community.
6.1.5 Third Party Monitors
The Third-Party Monitoring Agent (TPMA) reports directly to the UNDP Project Manager, working in close collaboration
with the project M&E Specialist and with the Responsible Parties for project implementation. The TPMA supports the
UNDP project management team to provide the Project Board and other stakeholders with better means for learning
from field experience, improving service delivery to community, planning and allocating resources, and demonstrating
results. The TPMA is expected to provide UNDP with quarterly reports.
Reporting templates/checklists will incorporate social and environmental risk monitoring, including monitoring
implementation of agreed management measures.
6.2 Capacity Building and Training
Responsible Parties have the responsibility for ensuring systems are in place so that relevant employees, contractors
and other workers are aware of the environmental and social requirements for project implementation, including the
ESMF. Project stakeholders have noted that capacity building and training needs to be a priority.
30
All project personnel will attend an initial induction training of relevant ESMF requirements, including health, safety,
environment and cultural heritage requirements.
Training will be conducted on a sustained basis. The following capacity building and training programmes will be in
place:
• Capacity building of headquarters and branch offices senior management (led by UNDP): To impart awareness
on essential regulatory and other requirements and elements of the ESMF, to help understand the
importance of social and environmental management from design stage through implementation. It is
essential that the trained manpower shall further carry out training and capacity building in their respective
organisations by acting as resource persons for such trainings.
• Capacity building of site engineers/site supervisors on ESMF requirements (led by Responsible Parties, with
UNDP support): To create awareness on specific social and environmental risks and management measures
for their control as applicable to the project activities and to build their capacity to carry out monitoring and
supervision activities in the field.
• Training and awareness of workers including contractual workers and local labour (led by Responsible Parties):
All workers engaged in any activity with the potential to cause serious social and/or environmental harm will
receive task specific training to ensure implementation of the site-specific management measures.
Training procedures shall take into account differing levels of responsibility, ability, language skills, literacy and risk
exposure.
The Responsible Parties shall ensure that persons under their control performing tasks related to environmental and social risk management are competent on the basis of appropriate education, training or experience, and shall retain associated records. Each sub-project should include a budget line for training to ensure capacities and skills of workers to implement risk management measures.
7 Stakeholder Engagement and Information Disclosure
7.1 Principles for Meaningful, Effective and Informed Stakeholder Engagement
The ECRP and its Responsible Parties will ensure meaningful, effective and informed stakeholder engagement in the
design and implementation of all sub-projects. Civil society actors and organizations, local communities and other key
stakeholders are crucial partners for project delivery and advancing sustainable development.
Stakeholder engagement supports the development of strong, constructive, and responsive relationships that are
critical for sound project design and implementation. Effective stakeholder engagement enhances project acceptance
and ownership and strengthens the social and environmental sustainability and benefits of supported interventions. It
is both a goal in itself – upholding the rights of citizens and others to participate in decisions that may affect them – as
well as an effective means for achieving project outcomes, including those related to democratic governance,
protecting the environment, promoting respect for human rights, and preventing and resolving conflict.
Meaningful, effective and informed stakeholder engagement will possess the following characteristics:
• Free of external manipulation, interference, coercion, and intimidation.
• Gender and age-inclusive and responsive.
• Culturally appropriate and tailored to the language preferences and decision-making processes of each
identified stakeholder group, including disadvantaged or marginalized groups.
• Based on prior and timely disclosure of accessible, understandable, relevant and adequate information,
including draft documents and plans.
• Initiated early in the project design process, continued iteratively throughout the project cycle, and adjusted
as risks and impacts arise.
• Addresses social and environmental risks and adverse impacts, and the proposed measures and actions to
address these.
• Seeks to empower stakeholders, particularly marginalized groups, and enable the incorporation of all relevant
views of affected people and other stakeholders into decision-making processes, such as project goals and
design, mitigation measures, the sharing of development benefits and opportunities, and implementation
issues.
• Documented and reported in accessible form to participants, in particular the measures taken to avoid or
minimize risks to and adverse impacts on the project stakeholders.
31
• Consistent with States’ duties and obligations under international law.
7.2 Information Disclosure
Information disclosure refers to the provision of timely, accessible information regarding the project and its potential
social and environmental impacts to stakeholders in order to facilitate their meaningful, effective and informed
participation in project design and implementation. Stakeholders require access to relevant project and sub-project
information in order to understand potential project-related opportunities and risks and to engage in design and
implementation.
In addition to have access to general project information, stakeholders need access to screening reports, draft and final
assessments and management plans. This information is to be disclosed in a timely manner, in an accessible place, and
in a form and language understandable to affected persons and other stakeholders. These elements of effective
disclosure are briefly elaborated below:
• Timely disclosure: information on potential project-related social and environmental impacts and
mitigation/management measures should be provided in advance of decision-making. Draft screenings,
assessments and management plans should be provided in advance as part of the stakeholder consultation
process. In all cases, draft and final screenings, assessments and management plans must be disclosed and
consulted on prior to implementation of activities that may give rise to potential adverse social and
environmental impacts.
• Accessible information: Stakeholders need to be able to readily access information regarding assessments and
management plans. While local regulatory requirements might mandate availability of environmental
assessments in government offices, this may not be sufficient to ensure that local stakeholders can access the
information. Other means of dissemination may need to be considered, such as posting on websites, public
meetings, local councils or organizations, newsprint, television and radio reporting, flyers, local displays, direct
mail.
• Appropriate form and language: Information needs to be in a form and language that is readily
understandable and tailored to the target stakeholder group. Summary information from assessments and
management plans may need to be translated and presented by various means (e.g. written, verbal). Level of
technical detail, local languages and dialects, levels of literacy, roles of women and men, and local methods of
disseminating information are important considerations in devising appropriate forms of disclosure. A general
solicitation of feedback on project documents may not be an appropriate form of information sharing and
solicitation of input. Rather, the material may need to be presented in a contextual manner, such as the
presentation of options with key information and questions designed to solicit feedback. Appropriate forms of
proactive disclosure should be utilized beyond web posting of information. These may include radio
broadcasts, brochures, community postings, SMS, oral presentations, etc. Also, it is vital to ensure that
appropriate communication methods are devised to reach potentially marginalized and disadvantaged groups.
The stakeholder engagement process is an excellent moment to solicit from stakeholders the types of information they
want and need and the most appropriate formats and languages and mechanisms for dissemination.
The SES contain requirements for the disclosure of screening reports; draft and final social and environmental
assessments and management plans; and any required social and environmental monitoring reports. For further detail
on UNDP SES stakeholder engagement and information disclosure requirements please refer to the UNDP
guidance UNDP Guidance on Stakeholder Engagement -Annex 3.
7.3 ECRP Systems in Place for Stakeholder Engagement and Information Disclosure
Meaningful stakeholder engagement is required by PWP and SFD for participation in project intervention by
communities and individuals. The Standard Operating Procedures of both Responsible Parties include procedures for
community and stakeholder engagement within their project cycles as a key component of project identification,
design and implementation, and described a key component of the longer-term sustainability strategy for operations
and maintenance.
Community committees are set up at the onset of project at the identification and design phase and play a key role in
supporting field teams, facilitating implementation and in the sustainability of community assets that are built through
subprojects, after project closure. To sustain such community participation and engagement, subprojects include
provisions to set up such community committees and provide resources for training whenever required.
32
The principles for sub-project cycle identification, development, and management specify that communities are
involved from the outset in the selection and design phases, through project closure.
To engage communities and reduce potential risks of conflicts between stakeholders over sub-projects a careful
selection criterion was developed by UNDP and Responsible Parties. While laying out an objective set of criteria, and
national data-based distress index, communities are also called upon to participate at the municipal level to engage in
prioritization of community projects and identification of beneficiaries.
Subprojects must meet the basic needs according to poverty and service needs provided in national indicators. Priority
is given to poorer communities. In addition to data provided through national indicators, community groups are
consulted to identify who will benefit from sub-projects, in this way stakeholders themselves are involved in the
selection and decision of who benefits from sub-projects.
In addition, some procedures include financial contribution by beneficiaries, proportionate to their means. This
contribution is seen as a necessary component for stakeholder engagement, providing a guarantee to future
sustainability through operation and maintenance of subprojects and aims to enhance the firm commitment to the
active participation of beneficiaries.
Both institutions include gender mainstreaming provisions as a means to ensuring equal participation of all
stakeholders in subprojects and provide opportunities to improve women’s participation in decision-making as
indicated in the above section on project impacts and risk, gender section.
Furthermore, in accordance with the ECRP approach to strengthening livelihoods and local economics, in sub-projects
that use community contracting, the procurement of civil works, construction materials, and the hiring of equipment,
transport and skilled laborers, is done by the communities themselves.
The TPMA also helps ensure stakeholders have been duly consulted and monitors their level of satisfaction with the ECRP project including with the sub-project selection criteria. TPM surveys have verified implementation of planned interventions, adherence to agreed implementation procedures, quality of implemented interventions, beneficiaries and community satisfaction on various aspects of project interventions and its effects/impacts on targeted beneficiaries and communities. Women and men, youth are interviewed separately to enable meaningful participation by marginalized groups. An example provided by TPMA report (see TPMA Report from April-June 2018) shows that cash for work interventions were highly satisfactory to beneficiaries in various aspects including project existence (98.5 percent) and beneficiary selection (98 percent). However, ESMF stakeholder consultations noted the need for strengthened and ongoing stakeholder engagement, bringing together the various stakeholders more regularly as true partners to help identify solutions to the challenges faced by the project. Stakeholder engagement will continue to be a priority of the project and project partners will continue to explore new and effective means to deliver on this commitment. Each sub-project should include a budget line for stakeholder engagement and training.
8 Grievance Redress Mechanism
8.1 Project-Level Grievance Mechanism
During the design, construction and implementation of any sub-project, a person or group of people may perceive or
experience potential harm, directly or indirectly due to the project activities. The grievances that may arise can be
related to social issues such as eligibility criteria and entitlements, disruption of services, temporary or permanent loss
of livelihoods and other social and cultural issues. Grievances may also be related to environmental issues such as
excessive dust generation, damages to infrastructure due to construction related vibrations or transportation of raw
material, noise, traffic congestions, decrease in quality or quantity of private/ public surface/ ground water resources
during irrigation rehabilitation, damage to home gardens and agricultural lands, etc.
Should such a situation arise, there must be a mechanism through which affected parties can resolve such issues in a
cordial manner with the project personnel in an efficient, unbiased, transparent, timely and cost-effective manner. To
achieve this objective, a Grievance Redress Mechanism has been included in the ESMF for this project.
The Grievance Redress Mechanism:
a. provides a legitimate process that allows for trust to be built between stakeholder groups and assures
stakeholders that their concerns will be assessed in a fair and transparent manner;
33
b. allows simple and streamlined access to the Grievance Redress Mechanism for all stakeholders and provide
adequate assistance for those that may have faced barriers in the past to be able to raise their concerns;
c. provides clear and known procedures for each stage of the Grievance Redress Mechanism process, and
provides clarity on the types of outcomes available to individuals and groups;
d. ensures equitable treatment to all concerned and aggrieved individuals and groups through a consistent,
formal approach that, is fair, informed and respectful to a concern, complaints and/or grievances;
e. provides a transparent approach, by keeping any aggrieved individual/group informed of the progress of their
complaint, the information that was used when assessing their complaint and information about the
mechanisms that will be used to address it; and
f. enables continuous learning and improvements to the Grievance Redress Mechanism. Through continued
assessment, the learnings may reduce potential complaints and grievances.
The GRM will be gender- and age-inclusive and responsive and address potential access barriers to women, the elderly,
the disabled, youth and other potentially marginalized groups as appropriate to the Project. The GRM will not impede
access to judicial or administrative remedies as may be relevant or applicable and will be readily accessible to all
stakeholders at no cost and without retribution.
Information about the Grievance Redress Mechanism and how to make a complaint and/or grievance must be
communicated during the stakeholder engagement process and placed at prominent places for the information of the
key stakeholders.
All complaints and/or grievances regarding social and environmental issues can be received either orally (to the field
staff), by phone, in complaints box or in writing to the UNDP, PWP or SFD. A key part of the grievance redress
mechanism is the requirement for the Project Management Team and construction contractor to maintain a register of
complaints and/or grievances received at the respective project site offices, this includes grievances from workers. The
following information will be recorded:
a. time, date and nature of enquiry, concern, complaints and/or grievances;
b. type of communication (e.g. telephone, letter, personal contact);
c. name, contact address and contact number;
d. response and review undertaken as a result of the enquiry, concern, complaints and/or grievances; and
e. actions taken and name of the person taking action.
The project GRM is managed by PWP and SFD, who have a grievance mechanism in place. UNDP will work with the
Responsible Parties to assess the effectiveness of existing GRM and work to address capacity, accessibility, transparency,
gaps, etc. TPM reports and the ESMF stakeholder consultations both raise issues of a lack of awareness of affected-
people of the GRM and how to access it. Therefore, particular efforts will be made to strengthen ongoing
communications and outreach on the GRM.
8.2 UNDP Accountability Mechanism
In addition to the project-level and national grievance redress mechanisms, complainants have the option to access
UNDP’s Accountability Mechanism, with both compliance and grievance functions. The Social and Environmental
Compliance Unit investigates allegations that UNDP's Standards, screening procedure or other UNDP social and
environmental commitments are not being implemented adequately, and that harm may result to people or the
environment. The Social and Environmental Compliance Unit is housed in the Office of Audit and Investigations and
managed by a Lead Compliance Officer. A compliance review is available to any community or individual with concerns
about the impacts of a UNDP programme or project. The Social and Environmental Compliance Unit is mandated to
independently and impartially investigate valid requests from locally impacted people, and to report its findings and
recommendations publicly.
The Stakeholder Response Mechanism offers locally affected people an opportunity to work with other stakeholders to
resolve concerns, complaints and/or grievances about the social and environmental impacts of a UNDP project.
Stakeholder Response Mechanism is intended to supplement the proactive stakeholder engagement that is required of
UNDP and its Implementing Partners throughout the project cycle. Communities and individuals may request a
Stakeholder Response Mechanism process when they have used standard channels for project management and
quality assurance and are not satisfied with the response (in this case the project level grievance redress mechanism).
When a valid Stakeholder Response Mechanism request is submitted, UNDP focal points at country, regional and
headquarters levels will work with concerned stakeholders and Responsible Parties to address and resolve the
concerns. Visit www.undp.org/secu-srm for more details.
34
8.3 World Bank Inspection Panel
The World Bank’s Inspection Panel is also available to affected people. The Inspection Panel is an independent
complaints mechanism for people and communities who believe that they have been, or are likely to be, adversely
affected by a World Bank-funded project. The Board of Executive Directors created the Inspection Panel in 1993 to
ensure that people have access to an independent body to express their concerns and seek recourse.
The Panel is an impartial fact-finding body, independent from the World Bank management and staff, reporting directly
to the Board. The Inspection Panel process aims to promote accountability at the World Bank, give affected people a
greater voice in activities supported by the World Bank that affect their rights and interests, and foster redress when
warranted.(www.inspectionpanel.org)
9 Monitoring, Reporting and Evaluation of ESMF Implementation
The ESMF and its procedures are to be reviewed regularly and on an ongoing basis by UNDP staff, PWP and SFD. The
objective is to update the ESMF to reflect knowledge gained during the course of project delivery/construction and to
reflect new knowledge.
Amendments will be made to the ESMF if:
• There are relevant changes to social and environmental conditions or generally accepted management
practices; or
• New or previously unidentified social and environmental risks are identified; or
• Information from the project monitoring and surveillance methods indicate that current control measures
require amendment to be effective; or
• There are changes to legislation that are relevant to the project; or
• There is a request made by a relevant regulatory authority.
When an update is made, all site personnel are to be made aware of the revision as soon as possible, e.g. through a
tool box meeting or written notification.
The Project Manager will monitor the overall implementation of the ESMF, most particularly the:
i. timely preparation of environmental and social screening forms for all subprojects (list of subprojects by risk
category by date)
ii. timely preparation and clearance of subproject ESIAs and ESMPs, as needed (list of instruments with dates)
iii. monitoring of ESMP implementation, including monitoring of mitigation measures and monitoring of
contractors environmental and social performance (indicators)
iv. training of project staff, implementing partners, and contractors (list of persons, dates and places)
The Project Manager will prepare:
i. biannual reports summarizing monitoring results, to be included in the Project’s Biannual Review Meetings
ii. an annual evaluation of all environmental and social monitoring activities, which will be submitted to the
World Bank as part of overall project implementation reporting
Monitoring and audit reports will be shared with the World Bank.
9.1 Management Information System (MIS)
Both PWP and SFD have a Management Information System in place to record project information and monitoring
results. The MIS provides an important mechanism to track information on environmental and social safeguard
implementation. A review will be conducted to identify opportunities to strengthen environmental and social
safeguard elements in the MIS.
35
9.2 Sub-Project Self-Monitoring and Reporting
For construction activities, the Responsible Party/site supervisor will be responsible for daily inspections (e.g.
environmental inspections, Occupational Health & Safety) of the construction site.
The Responsible Parties will be responsible for the day-to-day compliance of the ESMF at the specific project site. The
Responsible Parties will maintain and keep all administrative and social and environmental records which would
include a log of complaints and incidents together with records of any measures taken to mitigate the cause of the
complaints or incidents (see below sections on incident reporting and on complaints).
9.2.1 Social, environmental and OHS incident reporting
Any incidents, including non-conformances to the procedures of the ESMF, are to be recorded using an Incident Record
and the details entered into a register. For any incident that causes or has the potential to cause material or significant
social and/or environmental harm, the site supervisor/designated officer shall notify the Responsible Party senior
management and ECRP Project Manager as soon as possible and no later than 48 hours. UNDP will also ensure
significant incidents are reported to the World Bank within 48 hours. The Responsible Party must cease work until
remediation has been completed as per the approval of Project Manager.
9.2.2 Daily and weekly inspection checklists
A daily social and environmental checklist (including OHS issues) is to be completed for active work sites with moderate
risks by the relevant site supervisor/designated officer and maintained within a register. A weekly social and
environmental checklist is to be completed and will include reference to any issues identified in the daily checklists
completed by the site supervisor or designated person. The completed checklist is to be forwarded to the site engineer
for review and follow-up if any issues are identified.
9.2.3 Corrective Actions
Any non-conformances to the ESMF are to be noted in weekly social and environmental inspections and logged into
the register. Depending on the severity of the non- conformance, the site supervisor/designated officer may specify a
corrective action on the weekly site inspection report. The progress of all corrective actions will be tracked using the
register. Any non-conformances and the issue of corrective actions are to be advised to Responsible Parties senior
management and ECRP Project Manager.
9.2.4 Auditing and Review
A consultant will be recruited to conduct an annual environmental, social and occupational health compliance and
performance audit by both PWP and SFD. The consultant is given a list of all subprojects, and he/she will select
randomly the subprojects to be audited, which should include all sectors and programs, in different stages of
subproject cycle including design, under implementation, and completed stages, and with different types/levels of risk.
The audit will include both a desk audit/review and a field audit. Consequently, an audit report will be prepared by the
consultant and presented to management. The executive summary of the audit report will be forwarded to the donors
while the detailed report will be distributed to all Responsible Party branches and UNDP Project Manager for correcting
deviations and lessons learning.
9.3 Sub-Project Third-Party Monitoring and Reporting
The TPMA is expected to provide an independent perspective and extend the reach of UNDP in the field. The TPMA will
monitor activities of two identified responsible parties (SFD and PWP) financed by the project. The TPMA is expected to
visit project sites quarterly based on a sampling methodology.
Monitoring of environmental and social risks and implementation of management measures will be included in Third
Party Monitoring templates and reports.
9.4 Monitoring Plan
Table 3. Summary of ESMF Monitoring, Reporting and Evaluation Activities
36
Monitoring Activity Purpose/Action Frequency Expected Action Roles and Responsibilities
Annual evaluation To ensure Project Board is
updated on ESMF
implementation, issues,
and lessons learned.
Annually Include reporting on ESMF
implementation in
documentation prepared
for Biannual Review
Meetings
ECRP Project Manager
(informed by TPM reports,
self-reporting of sub-projects,
field visits)
Annual review and
audit
Identify issues and lessons
learned related to ESMF
implementation to support
overall project
implementation
Annually Hire consultant to conduct
review and audit of ECRP
portfolio, for both PWP
and SFD
PWP, SFD, and UNDP
Biannaul reports
(for biannual
review meetings)
To ensure Project Board is
updated on ESMF
implementation, issues,
and lessons learned.
Biannually Include reporting on ESMF
implementation in
documentation prepared
for Biannual Review
Meetings
ECRP Project Manager
(informed by TPM reports,
self-reporting of sub-projects,
field visits)
Quarterly
Monitoring
Qualitative and
quantitative review of
selection of projects,
engaging with local
stakeholders. Identification
of any new social and
environmental risks and
monitoring of
implementation of site-
specific management
plans.
Quarterly Apply TPM methodology,
to include consideration of
social, environmental and
occupational health risks
and management
TPMA and UNDP project
team
Field Visits Conduct field visits to spot-
check sub-projects and
ensure effective
implementation, including
ESMF implementation
Periodic Ensure risks are
appropriately identified
and managed. If new risks
identified, screening and
management plan to be
updated.
UNDP Project Management
Team
Learning Knowledge, good practices
and lessons learned
regarding social and
environmental risk
management will be
captured regularly, as well
as actively sourced from
other projects and partners
and integrated back into
the project.
At least annually Relevant lessons are
captured by the project
team and used to inform
management decisions.
UNDP Project Management
Team and UNDP Programme
Review and adapt
activities and
approach as
necessary
Internal review of data and
evidence from all
monitoring actions to
inform decision making.
At least annually Performance data, risks,
lessons and quality will be
discussed by the project
UNDP Project Management
Team and UNDP Programme
37
board and used to make
course corrections.
Project Progress
Reports
As part of progress report
to be presented to the
Project Board and key
stakeholders, analysis,
updating and
recommendations for risk
management will be
included.
Annually, and at
the end of the
project (final
report)
Incorporation of progress
on risk management
elements, including ESMF
UNDP Project Management
Team
Site Inspections To ensure early
identification and
resolution of potential risks
Daily and weekly Completion of site
inspections checklists (to
include social,
environmental and
occupational hazards and
risks)
Responsible Parties (Site
Supervisors)
38
Annex 1. Yemen ECRP Revised SES Screening
Project Information
1. Project Title Yemen Emergency Crisis Response Project (ECRP)
2. Project Number 00097850
3. Location (Global/Region/Country) Sana’a, Republic of Yemen
Part A. Integrating Overarching Principles to Strengthen Social and Environmental Sustainability
QUESTION 1: How Does the Project Integrate the Overarching Principles in order to Strengthen Social and
Environmental Sustainability?
Briefly describe in the space below how the Project mainstreams the human-rights based approach
The project upholds the principles of accountability and the rule of law, participation and inclusion, and equality and
non-discrimination based on gender, age, religion, political views or affiliation to parties to the current conflict, social
or geographical origin, birth or other status. UNDP will also ensure the meaningful, effective and informed
participation of stakeholders in the formulation, implementation, monitoring and evaluation of the ECRP. The project
also establishes a dedicated grievance mechanism and capacity to ensure that the duty-bearers are accountable to the
rights-holders for the actions undertaken in the course of the project.
Briefly describe in the space below how the Project is likely to improve gender equality and women’s empowerment
The project recognizes that in the midst of the current crisis in Yemen, women are adversely affected and at the same
time asked to take on new and additional roles as heads of households or income-earners. The project will actively
target women (at least 30%) to support their income-generation opportunities and contribute to the delivery of
community service and livelihood assets through Cash for Work and Cash for Services, and through earmarked funding
(accounting to 15% of the project budget) dedicated to address severe and acute malnutrition for pregnant and
lactating women (and children) by providing cash assistance (mothers are the recipients) and facilitating the affected
families’ access to nutrition services.
Briefly describe in the space below how the Project mainstreams environmental sustainability
An Environmental and Social Management Framework will be developed for the project. This will ensure that social
and environmental sustainability standards are applied to help mitigate potentially high adverse environmental and
social impacts in the selection, prioritization and implementation of subprojects at community level, which UNDP will
also closely monitor any negative environmental and social impact and ensure compliance with the safeguards
through Third Party Monitoring. See ESMF.
39
Part B. Identifying and Managing Social and Environmental Risks
QUESTION 2: What are the
Potential Social and
Environmental Risks?
QUESTION 3: What is the level of
significance of the potential social and
environmental risks?
QUESTION 6: What social and
environmental assessment
and management measures
have been conducted and/or
are required to address
potential risks (for Risks with
Moderate and High
Significance)?
Risk Description Impact
and
Probabili
ty (1-5)
Significance
(Low,
Moderate,
High)
Comments Description of assessment and
management measures as
reflected in the Project design.
If ESIA or SESA is required note
that the assessment should
consider all potential impacts
and risks.
There is a risk that the Project
would exacerbate conflicts
among and/or the risk of
violence to project-affected
communities and individuals
I = 3
P = 4
Moderate The conflict context may
produce social tensions during
project implementation,
concerning prioritization of
subprojects, locations, and
selection of participants.
Measures to be undertaken
include a clear definition of
targeting and selection criteria
based on data provided by the
UN Clusters; participatory
preparation and
implementation of subprojects
by communities and relevant
stakeholders; frequent
communication with
communities and local
stakeholders; grievance redress/
stakeholder response
mechanism procedures to
ensure timely handling of
grievance redress; and public
disclosure of the reasons for the
rejection of subprojects, if any,
to increase transparency. In
addition, the project will have a
communication strategy which
will include consultations with
government counterparts,
citizen engagement and public
outreach. The project is
implemented by SFD and PWP
which are operating relatively
independently from the
government.
40
CO will monitor the situation
closely and on a systematic
manner in order to make sure
the project achieves its goals
within the agreed timeline
The Project may potentially
reproduce discriminations
against women based on
gender, especially regarding
participation in design and
implementation or access to
opportunities and benefits.
I= 3
P=2
Moderate The ECRP has mainstreamed
gender considerations through
its project approach, addressing
gender equality from project
identification, site selection,
management and oversight.
The project has actively
targeted women (at least 30%)
to support their income-
generation opportunities and
contribute to the delivery of
community service and
livelihood assets through Cash
for Work and Cash for Services,
and through earmarked funding
(accounting to 15% of the
project budget) dedicated to
address severe and acute
malnutrition for pregnant and
lactating women (and children)
by providing cash assistance
(mothers are the recipients) and
facilitating the affected families’
access to nutrition services.
Small scale farming and
livestock may cause adverse
impacts to habitats (e.g.
modified, natural, and critical
habitats) and/or ecosystems
and ecosystem services ( For
example, through habitat loss,
conversion or degradation,
fragmentation, hydrological
changes)
Activities will include:
Watershed Management/Water
Channels, Rehabilitation of
Farm Lands, Rehabilitation of
Farm Irrigation Infrastructure,
Agriculture Infrastructure,
Agriculture Input Provision,
Support to Livestock Producers.
Livestock activities involve the
creation of yards in addition to
other.
I=3
P=2
Moderate Although the
projects are small
scale in nature, the
cumulative effects
of providing
support to
communities may
involve inadvertent
impacts on
ecosystems that
can result in
negative effect to
ecosystem services
provision and
biodiversity.
When further sub-
project screening is
conducted more
information will be
available as to the
extent of the
impacts and
management
measures required.
The ECRP applies a
precautionary approach to the
use, development, and
management of natural
habitats, the ecosystem
services of such habitats, and
living natural resources.
As an integral part of the social
and environmental assessment
process, direct and indirect
impacts on natural resources,
biodiversity and ecosystem
services in the Project’s area of
influence are identified and
addressed. The assessment
process will consider, inter alia
(i) risks of habitat and species
loss, degradation and
fragmentation, invasive alien
species, overexploitation,
hydrological changes, nutrient
loading, pollution, and (ii)
differing values (e.g. social,
cultural, economic) attached to
41
biodiversity and ecosystem
services by potentially affected
communities. Potential
cumulative and induced impacts
will be assessed. Project-related
impacts across potentially
affected landscapes should be
considered.
Natural resources will be
managed in a sustainable
manner. This includes
safeguarding biodiversity and
the life-supporting capacity of
air, water, and soil ecosystems.
Sustainable management also
ensures that people who are
dependent on these resources
are properly consulted, women
and men have opportunities to
equally participate in
development, and benefits are
shared equitably.
The Project involves the
production and/or harvesting of
fish populations or other
aquatic species
I = 1
P = 3
Low The project will target artisanal
fishermen using small حرفيون
boats with one off-board petrol
engine, i.e. not used in deep
waters and will not risk
overfishing. The project will
carefully monitor the activities
of the fishermen during its
implementation.
Some of the fishermen will be
equipped with fish finders, to
help expedite the search of the
fish and thus economize the use
of fuel. As the targeted
fishermen will be operating on
small boats using traditional
methods of fishing, there is low
risk that the use of the fish
finders will lead to over catching
the fish. The project will also
work with fishing associations
responsible for ensuring that
fishing protocols are in place
and adhered to, to protect fish
stocks and regulate seasonal
controls on fishing. The project
will be implemented in line with
the Biodiversity Conservation
and Sustainable NRM of the
SES which includes fishing
42
management. The concept of
sustainable and responsible
fishing will be promoted
through this partnership.
Through its direct support to
small scale fishermen, the
project will improve community
livelihoods and training on
quality and resource
sustainability to include the
reduction of wastage.
The Project involves extraction,
diversion or containment of
surface or ground water
I = 3
P = 3
Moderate The project
rehabilitates
existing water
supply
infrastructure at a
small-scale and will
not create new
extraction points or
new infrastructure
for containment or
diversion of water.
The project aims to rehabilitate
or construct a total of 500,000
m3 of water supply (including
water catchments, reservoirs
and maintenance of clean water
supply etc.), which are relatively
small-scale.
In case of pumping wells, a
monitoring of water level is
needed to control the pumping
and avoid draw down beyond
the recharge (water balance).
Overall the associated risks are
expected to be small scale and
readily managed. Site-specific
management plans will need to
be in place.
The potential outcomes of the Project may be sensitive or vulnerable to potential impacts of climate change.
Yemen has a predominantly
semi-arid to arid climate and is
highly vulnerable to climate
change-related impacts such as
drought, extreme flooding,
changes of rainfall patterns,
increased storm
frequency/severity, sea level
rise. Literature show that the
main sectors under stress are:
water resources, agriculture,
and coastal zones. Water
scarcity related to prolonged
droughts, evaporation, drying
up of wells, excessive rainfall
(which produces flash flooding
and can potentially wipe out
crops) caused by rainfall
variability are the key issues.
The ECRP project activities
related to agriculture (including
I = 3
P = 2
Moderate Proposed subprojects will be
screened and assessed for
climate change-related risks
and impacts. The ECRP will
ensure that the status and
adequacy of relevant climatic
information is identified. If
significant potential risks are
identified, further scoping and
assessment of vulnerability,
potential impacts, and
avoidance and mitigation
measures, including
consideration of alternatives to
reduce potential risks, will be
required. The climate change
risk assessment may focus on :
-The viability or longer-term
sustainability of project
outcomes due to potential
climate change. This will involve
the identification of
components that are sensitive
or vulnerable to emerging or
43
farming, livestock) and fisheries
and water (irrigation,
catchment, conservation), will
be most sensitive and
vulnerable to the impacts of
climate change.
Some project activities that aim
to increase water availability,
may inadvertently lead to
depletion of groundwater
resources or diversion of
sources to some communities in
detriment of others, if not
properly managed based on
appropriate climate risk
information and management
measures.
anticipated manifestations of
climate change.
-Risks that a project may
increase exposure to climate
change. Project components
must be assessed for potential
unintended or unforeseen
increases in vulnerability to
climate change.
-Potential social, gender, and
age risks, based on the
differentiated impacts of
climate change.
Elements of Project
construction, operation, or
decommissioning pose
potential safety risks to local
communities and workers.
I = 3
P = 3
Moderate The project works
through SFD and
PWP who will be
implementing the
infrastructure
rehabilitation
projects (small-
scale) according to
their Operational
Manuals vetted by
UNDP, which
includes safety
standards. UNDP
will carefully
monitor the
implementation
through TPM and
regular
consultations with
the partners.
Occupational Health and Safety
risks are a priority for the ECRP
project. An OHS Framework
and Toolkit has been developed
and should be applied at the
sub-project level. This
complements measures already
applied by PWP and SFD
through implementation of
their operating manuals. See
OHS Framework for further
details.
Potential impacts may include
insufficient safety
standards used in construction/
rehabilitation of small-scale
infrastructure; dust and noise
during construction/
rehabilitation; and/or
insufficient removal of
construction waste after project
completion. There may also be
safety issues related to the
ongoing conflict and security
measures in place.
OHS risks will be monitored
carefully and all incidents
reported.
Failure of structural elements of
the Project poses risks to
communities and workers (e.g.
collapse of buildings or
infrastructure)
I = 4
P = 2
Moderate . The project works through SFD
and PWP who will be
implementing the infrastructure
rehabilitation projects (small-
scale) according to their
operating manuals and the
44
ESMF, which includes safety
standards. UNDP will carefully
monitor the implementation
through TPM and regular
consultations with the partners.
The project aims to support the
rehabilitation/reconstruction of
community infrastructure (i.e.
damaged classrooms, small-
scale infrastructure for flood
prevention etc.). These will be
mitigated by the 20-years of
experience of PWP in managing
project impacts successfully
according to their Operational
Manual (endorsed/approved by
UNDP BMS) that lay out clear
criteria for small-scale
infrastructure rehabilitation to
identify, eliminate and address
potential safety risks and UNDP
field monitoring including TPM.
Potential risks to community
health and safety due to the
transport, storage, and use
and/or disposal of hazardous or
dangerous materials (e.g.
explosives, fuel and other
chemicals during construction
and operation)
I = 4
P = 2
Moderate Appropriate management
measures have been put in
place. A detailed risk
categorization was developed
for the purpose of identifying
sub-project level risks to enable
halting any salient high-risk
projects from further
implementation until adequate
management measures are put
in place. Additionally, a
specialized consultant was hired
to develop management plans,
screening checklists, and ensure
high frequency of field
monitoring. Additionally,
support to the Responsible
Parties has been reinforced by
training and monitoring and
capacity assessments. The
results the latter measures
taken by UNDP are included in a
detailed report “OHS
Framework”. The report
highlights both the stated
results and management
measures underway.
Potential for increased health
risks (e.g. from water-borne or
other vector-borne diseases or
communicable infections.
I = 2
P = 1
Low In cases where there may be
pollution, a site-specific
pollution prevention plan
45
The project will support the
construction and/or
rehabilitation of pit latrines,
sewage systems, provide
agriculture inputs that may
include pesticides, support
small health care centers
infrastructure or services,
cleaning up public spaces that
may include municipal solid
waste, and sewage that may
include hazardous/human
excreta and waste.
should be put in place and
monitored.
Sub-projects will avoid the
release of pollutants, and when
avoidance is not feasible,
minimize and/or control the
intensity and mass flow of their
release. This applies to the
release of pollutants to air,
water, and land due to routine,
non-routine, and accidental
circumstances.
Pollution prevention and
control technologies and
practices consistent with
international good practice are
applied during the project life
cycle. The technologies and
practices applied will be tailored
to the hazards and risks
associated with the nature of
the Project.
Potential for activities that
result in localized pollution.
The project will support the
construction and/or
rehabilitation of pit latrines,
sewage systems, provide
agriculture inputs, support small
health care centers
infrastructure or services,
cleaning up public spaces that
may include municipal solid
waste, and sewage that may
include hazardous/human
excreta and waste. Minimal and
localized air, water, and noise
pollution possible.
I = 2
P = 1
Low In cases where there may be
pollution, a site-specific
pollution prevention plan
should be put in place and
monitored.
Sub-projects will avoid the
release of pollutants, and when
avoidance is not feasible,
minimize and/or control the
intensity and mass flow of their
release. This applies to the
release of pollutants to air,
water, and land due to routine,
non-routine, and accidental
circumstances.
Pollution prevention and
control technologies and
practices consistent with
international good practice are
applied during the project life
cycle. The technologies and
practices applied will be tailored
to the hazards and risks
associated with the nature of
the Project.
Sub-project may involve the
application of pesticides that
may have a negative effect on
I = 2
P = 1
Low Pesticide use and management:
For Projects involving pest
management activities, the
46
the environment or human
health.
social and environmental
assessment will ascertain that
any pest and/or vector
management activities related
to the ECRP are based on
integrated pest management
approaches and aim to reduce
reliance on synthetic chemical
pesticides. The integrated
pest/vector management
programme will entail
coordinated use of pest and
environmental information
along with available pest/ vector
control methods, including
cultural practices, biological,
genetic and, as a last resort,
chemical means to prevent
unacceptable levels of pest
damage. When pest
management activities include
the use of pesticides, pesticides
that are low in human toxicity,
known to be effective against
the target species, and have
minimal effects on non-target
species and the environment
will be selected. The health and
environmental risks associated
with pest management should
be minimized with support, as
needed, to institutional capacity
development, to help regulate
and monitor the distribution
and use of pesticides and
enhance the application of
integrated pest management.
The ECRP will not use products
that fall in Classes Ia (extremely
hazardous) and Ib (highly
hazardous) of the World Health
Organization Recommended
Classification of Pesticides by
Hazard. WHO Class II
(moderately hazardous)
pesticides will not be used if the
relevant Responsible Party lacks
restrictions on distribution and
use of these chemicals or
facilities to handle, store, apply
and dispose of these products
properly, or if they are likely to
be accessible to personnel
without proper training and
equipment. Pesticides will be
handled, stored, applied and
47
disposed of in accordance with
international good practice such
as the FAO International Code
of Conduct on the Distribution
and Use of Pesticides.
The ECRP may result in
interventions that would
potentially adversely impact
sites, structures, or objects with
historical, cultural, artistic,
traditional or religious values or
intangible forms of culture (e.g.
knowledge, innovations,
practices).
As the project conducts small
scale infrastructure activities
related to community works
such as road paving, community
reservoirs and piping, and
repairing of school buildings in
addition to others these project
activities, although may not
target the rehabilitation of
Cultural Sites directly, they may
be located in the vicinity of
cultural heritage sites and
consequently produce
unintended negative effects on
such sites.
I = 3
P = 3
Moderate The ECRP will avoid and/or
mitigate any impacts on cultural
heritage through alternative
project siting and design. The
impacts on Cultural Heritage
resulting from project activities,
including mitigating measures,
may not contravene the
national legislation, or its
obligations under relevant
international treaties and
agreements.
Where potential adverse
impacts are unavoidable,
appropriate mitigation
measures will be identified and
incorporated as an integral part
of the social and environmental
assessment process. Where
potential adverse impacts may
be significant, a Cultural
Heritage Management Plan
should be developed as part of
the Environmental and Social
Management Plan (ESMP).
For projects with potential
adverse impacts, qualified and
experienced independent
experts will assess the project’s
potential impacts on Cultural
Heritage using, among other
methodologies, field-based
surveys and involving
meaningful, effective, and
informed stakeholder
consultations as part of social
and environmental assessment
process.
Note SFD has a Quality
assurance system in place for
Cultural Heritage interventions
and a separate Cultural Heritage
Unit.
A number of specialized
experts1 lead and also provide
1 E. Ronald Lewcock - Professor of Architecture at Georgia Tech. Institute and Cambridge University.
48
technical supervision for SFD’s
main conservation operations
through direct on-site
supervision or regular visits that
take place on monthly, bi-
monthly & semiannual basis.
Additionally, the technical
quality of SFD’s interventions
was positively acknowledged by
a World Bank review mission
undertaken by a Cultural
Heritage expert.
QUESTION 4: What is the overall Project risk categorization?
Select one (see SESP for guidance) Comments
Low Risk ☐
Moderate Risk X Given the need for further
assessment and management
measures at the sub-project
level, an Environmental and
Social Management
Framework will be developed
for the project.
High Risk ☐
QUESTION 5: Based on the identified risks
and risk categorization, what requirements of
the SES are relevant?
Check all that apply Comments
Principle 1: Human
Rights X
Principle 2: Gender
Equality and
Women’s
Empowerment
X
1. Biodiversity
Conservation and
Natural Resource
Management
X
2. Climate Change
Mitigation and
Adaptation
X
Dr. Chris Edens (Archaeologist – former director of the American Institute for Yemeni Studies).
Dr. Ala'a Al Habashi, Professor Eves Eagles, Eng. IssamAwwad, Renzo Ravagnan, Abdullah Al Hadrami
49
3. Community Health,
Safety and Working
Conditions
X
4. Cultural Heritage X
5. Displacement and
Resettlement ☐
6. Indigenous Peoples ☐
7. Pollution Prevention
and Resource
Efficiency
X
Final Sign Off
Signature Date Description
QA Assessor
Edrees Al-Qadasi , YECRP PM a.i
Signature:
14/03/2019 UNDP staff member responsible for the Project, typically a
UNDP Programme Officer. Final signature confirms they
have “checked” to ensure that the SESP is adequately
conducted.
QA Approver
Auke Lootsma,
Resident Representative
Signature:
14/03/2019 UNDP senior manager, typically the UNDP Deputy Country
Director (DCD), Country Director (CD), Deputy Resident
Representative (DRR), or Resident Representative (RR). The
QA Approver cannot also be the QA Assessor. Final signature
confirms they have “cleared” the SESP prior to submittal to
the PAC.
PAC Chair UNDP chair of the PAC. In some cases PAC Chair may also be
the QA Approver. Final signature confirms that the SESP was
considered as part of the project appraisal and considered in
recommendations of the PAC.
50
SESP Attachment 1. Social and Environmental Risk Screening Checklist
Checklist Potential Social and Environmental Risks
Principles 1: Human Rights Answer
(Yes/No
)
1. Could the Project lead to adverse impacts on enjoyment of the human rights (civil, political, economic,
social or cultural) of the affected population and particularly of marginalized groups? Yes
2. Is there a likelihood that the Project would have inequitable or discriminatory adverse impacts on affected
populations, particularly people living in poverty or marginalized or excluded individuals or groups? 2 No
3. Could the Project potentially restrict availability, quality of and access to resources or basic services, in
particular to marginalized individuals or groups? Yes
4. Is there a likelihood that the Project would exclude any potentially affected stakeholders, in particular
marginalized groups, from fully participating in decisions that may affect them? No
5. Is there a risk that duty-bearers do not have the capacity to meet their obligations in the Project? No
6. Is there a risk that rights-holders do not have the capacity to claim their rights? No
7. Have local communities or individuals, given the opportunity, raised human rights concerns regarding the
Project during the stakeholder engagement process? No
8. Is there a risk that the Project would exacerbate conflicts among and/or the risk of violence to project-
affected communities and individuals? Yes
Principle 2: Gender Equality and Women’s Empowerment
1. Is there a likelihood that the proposed Project would have adverse impacts on gender equality and/or the
situation of women and girls? No
2. Would the Project potentially reproduce discriminations against women based on gender, especially
regarding participation in design and implementation or access to opportunities and benefits? Yes
3. Have women’s groups/leaders raised gender equality concerns regarding the Project during the
stakeholder engagement process and has this been included in the overall Project proposal and in the risk
assessment?
Yes
4. Would the Project potentially limit women’s ability to use, develop and protect natural resources, taking
into account different roles and positions of women and men in accessing environmental goods and
services?
No
2 Prohibited grounds of discrimination include race, ethnicity, gender, age, language, disability, sexual orientation, religion, political or other opinion, national or social or geographical origin, property, birth or other status including as an indigenous person or as a member of a minority. References to “women and men” or similar is understood to include women and men, boys and girls, and other groups discriminated against based on their gender identities, such as transgender people and transsexuals.
51
For example, activities that could lead to natural resources degradation or depletion in communities who
depend on these resources for their livelihoods and well being
Principle 3: Environmental Sustainability: Screening questions regarding environmental risks are encompassed
by the specific Standard-related questions below
Standard 1: Biodiversity Conservation and Sustainable Natural Resource Management
1.1 Would the Project potentially cause adverse impacts to habitats (e.g. modified, natural, and critical
habitats) and/or ecosystems and ecosystem services?
For example, through habitat loss, conversion or degradation, fragmentation, hydrological changes
Yes
1.2 Are any Project activities proposed within or adjacent to critical habitats and/or environmentally sensitive
areas, including legally protected areas (e.g. nature reserve, national park), areas proposed for protection,
or recognized as such by authoritative sources and/or indigenous peoples or local communities?
No
1.3 Does the Project involve changes to the use of lands and resources that may have adverse impacts on
habitats, ecosystems, and/or livelihoods? (Note: if restrictions and/or limitations of access to lands would
apply, refer to Standard 5)
No
1.4 Would Project activities pose risks to endangered species? No
1.5 Would the Project pose a risk of introducing invasive alien species? No
1.6 Does the Project involve harvesting of natural forests, plantation development, or reforestation? Yes
(small
scale)
1.7 Does the Project involve the production and/or harvesting of fish populations or other aquatic species? Yes
1.8 Does the Project involve significant extraction, diversion or containment of surface or ground water?
For example, construction of dams, reservoirs, river basin developments, groundwater extraction
No
(small
scale)
1.9 Does the Project involve utilization of genetic resources? (e.g. collection and/or harvesting, commercial
development)
No
1.10 Would the Project generate potential adverse transboundary or global environmental concerns? No
1.11 Would the Project result in secondary or consequential development activities which could lead to adverse
social and environmental effects, or would it generate cumulative impacts with other known existing or
planned activities in the area?
For example, a new road through forested lands will generate direct environmental and social impacts (e.g.
felling of trees, earthworks, potential relocation of inhabitants). The new road may also facilitate
encroachment on lands by illegal settlers or generate unplanned commercial development along the route,
potentially in sensitive areas. These are indirect, secondary, or induced impacts that need to be considered.
No
52
Also, if similar developments in the same forested area are planned, then cumulative impacts of multiple
activities (even if not part of the same Project) need to be considered.
Standard 2: Climate Change Mitigation and Adaptation
2.1 Will the proposed Project result in significant3 greenhouse gas emissions or may exacerbate climate
change?
No
2.2 Would the potential outcomes of the Project be sensitive or vulnerable to potential impacts of climate
change?
Yes
2.3 Is the proposed Project likely to directly or indirectly increase social and environmental vulnerability to
climate change now or in the future (also known as maladaptive practices)?
For example, changes to land use planning may encourage further development of floodplains, potentially
increasing the population’s vulnerability to climate change, specifically flooding
No
Standard 3: Community Health, Safety and Working Conditions
3.1 Would elements of Project construction, operation, or decommissioning pose potential safety risks to
local communities?
Yes
3.2 Would the Project pose potential risks to community health and safety due to the transport, storage, and
use and/or disposal of hazardous or dangerous materials (e.g. explosives, fuel and other chemicals during
construction and operation)?
Yes
3.3 Does the Project involve large-scale infrastructure development (e.g. dams, roads, buildings)? No
3.4 Would failure of structural elements of the Project pose risks to communities? (e.g. collapse of buildings or
infrastructure)
Yes
3.5 Would the proposed Project be susceptible to or lead to increased vulnerability to earthquakes,
subsidence, landslides, erosion, flooding or extreme climatic conditions?
No
3.6 Would the Project result in potential increased health risks (e.g. from water-borne or other vector-borne
diseases or communicable infections such as HIV/AIDS)?
Yes
3.7 Does the Project pose potential risks and vulnerabilities related to occupational health and safety due to
physical, chemical, biological, and radiological hazards during Project construction, operation, or
decommissioning?
Yes
3.8 Does the Project involve support for employment or livelihoods that may fail to comply with national and
international labor standards (i.e. principles and standards of ILO fundamental conventions)?
Yes
3.9 Does the Project engage security personnel that may pose a potential risk to health and safety of
communities and/or individuals (e.g. due to a lack of adequate training or accountability)?
No
Standard 4: Cultural Heritage
3 In regards to CO2, ‘significant emissions’ corresponds generally to more than 25,000 tons per year (from both direct
and indirect sources). [The Guidance Note on Climate Change Mitigation and Adaptation provides additional
information on GHG emissions.]
53
4.1 Will the proposed Project result in interventions that would potentially adversely impact sites, structures,
or objects with historical, cultural, artistic, traditional or religious values or intangible forms of culture (e.g.
knowledge, innovations, practices)? (Note: Projects intended to protect and conserve Cultural Heritage
may also have inadvertent adverse impacts)
Yes
4.2 Does the Project propose utilizing tangible and/or intangible forms of cultural heritage for commercial or
other purposes?
No
Standard 5: Displacement and Resettlement
5.1 Would the Project potentially involve temporary or permanent and full or partial physical displacement? No
5.2 Would the Project possibly result in economic displacement (e.g. loss of assets or access to resources due
to land acquisition or access restrictions – even in the absence of physical relocation)?
No
5.3 Is there a risk that the Project would lead to forced evictions?4 No
5.4 Would the proposed Project possibly affect land tenure arrangements and/or community based property
rights/customary rights to land, territories and/or resources?
No
Standard 6: Indigenous Peoples
6.1 Are indigenous peoples present in the Project area (including Project area of influence)? No
6.2 Is it likely that the Project or portions of the Project will be located on lands and territories claimed by
indigenous peoples?
No
6.3 Would the proposed Project potentially affect the human rights, lands, natural resources, territories, and
traditional livelihoods of indigenous peoples (regardless of whether indigenous peoples possess the legal
titles to such areas, whether the Project is located within or outside of the lands and territories inhabited
by the affected peoples, or whether the indigenous peoples are recognized as indigenous peoples by the
country in question)?
If the answer to the screening question 6.3 is “yes” the potential risk impacts are considered potentially
severe and/or critical and the Project would be categorized as either Moderate or High Risk.
No
6.4 Has there been an absence of culturally appropriate consultations carried out with the objective of
achieving FPIC on matters that may affect the rights and interests, lands, resources, territories and
traditional livelihoods of the indigenous peoples concerned?
No
6.5 Does the proposed Project involve the utilization and/or commercial development of natural resources on
lands and territories claimed by indigenous peoples?
No
6.6 Is there a potential for forced eviction or the whole or partial physical or economic displacement of
indigenous peoples, including through access restrictions to lands, territories, and resources?
No
6.7 Would the Project adversely affect the development priorities of indigenous peoples as defined by them? No
4 Forced evictions include acts and/or omissions involving the coerced or involuntary displacement of individuals, groups, or communities from homes and/or lands and common property resources that were occupied or depended upon, thus eliminating the ability of an individual, group, or community to reside or work in a particular dwelling, residence, or location without the provision of, and access to, appropriate forms of legal or other protections.
54
6.8 Would the Project potentially affect the physical and cultural survival of indigenous peoples? No
6.9 Would the Project potentially affect the Cultural Heritage of indigenous peoples, including through the
commercialization or use of their traditional knowledge and practices?
No
Standard 7: Pollution Prevention and Resource Efficiency
7.1 Would the Project potentially result in the release of pollutants to the environment due to routine or non-
routine circumstances with the potential for adverse local, regional, and/or transboundary impacts? Yes
7.2 Would the proposed Project potentially result in the generation of waste (both hazardous and non-
hazardous)? Yes
7.3 Will the proposed Project potentially involve the manufacture, trade, release, and/or use of hazardous
chemicals and/or materials? Does the Project propose use of chemicals or materials subject to
international bans or phase-outs?
No
7.4 Will the proposed Project involve the application of pesticides that may have a negative effect on the
environment or human health?
Yes
7.5 Does the Project include activities that require significant consumption of raw materials, energy, and/or
water?
No
(small-
scale)
Annex 2. Specific Risks and Management Measures by Project Activity
Sub-Project
Activity
Potential
Impacts
Proposed Mitigation
Measures
Means of
insurance and
compliance
Building
New
Terraces
Air Quality and Noise
Construction
Construction may impact air
quality and generate noise. This
results mainly from excavation,
site grading, vehicle loading
and unloading, and other
construction-related activities.
Operation
Potential impacts on ambient
air quality would result from
odors and gaseous emissions
Air Quality and Noise
Construction
Use dust control measures
onsite, such as water spraying
for dust suppression;
Regulate site access;
Cover lorries transporting
friable construction materials
and spoil;
Prohibit open air burning;
SFD with
beneficiaries
CBOs oversees
construction and
operation
activities and
conducts visual
inspection with
the assistance of
a representative
of the local
community
Contracts and
PCU coordinator
ensures that
55
generated by stagnant water–
water may increase humidity
- Exposure to or production
cracks, humidity exfoliation
may happen due to high
humidity in the area
- Odor due to increase relative
humidity
- Deterioration of terraces walls
my lead to erosion or flash
flood
- Disturbing the stability of
slopes and soils due to large
quantities of materials extracted
to build the terraces
- Interruption of some runoff
water
Soil Quality and
Surface/Ground water
Pattern/contamination
Construction
Impacts on soil quality may
result from the following
construction activities:
- Change in composition,
filtration.
- Minor oil spills from
construction equipment
Operation
Contamination of soils and
groundwater with chemicals
used in farming and chemicals
and oil spills from equipment.
Spills and leaks at liquid
impoundment areas for fuels,
solvents, waste and from
infrastructure equipment, may
infiltrate through soil pores,
under gravitational forces, and
contaminate ground water
aquifers;
Discharge into surface waters,
or alteration of surface water
quality, including but not
limited to temperature,
dissolved oxygen, turbidity,
solids
Wastewater
Maintain machinery in good
working conditions to
minimize emissions; and
Provide adequate protective
wear for workers, and
equipment must be
maintained regularly to avoid
any emissions;
Pre-treat gases emitted
Operation
Conserve energy use to
reduce fuel combustion;
Mitigation to the first factor
could be addressed by
frequent inspection to the
terraces construction and
apply the required
maintenance. Regular
inspection and examinations
for mentioned impacts and
address them through
maintenance replacement of
materials spoiled.
Minimizing entrance of
heavy machines to reduce
vibration impact. For
handling and occupational
health applying strict
protection regulation for
occupational health
measurements is critical and
a site-specific management
plan is required-including all
operational stages from
handling, washing,
classification, freezing,
backing up to loading and
distribution to consumption
Soil Quality and
Surface/Ground water
pattern/contamination
Construction
Apply, inspect and maintain
temporary/permanent erosion
and sediment control
measures (e.g. silt fences,
contractors
implement
environmental
management
plans/regulations
and that
contractors
perform
continuous
inspection and
monitoring of
areas of potential
pollution and/or
uses with the
potential to result
in soil
contamination;
Complaints from
local community
Review of tender
and bid
documents by
SFD
56
Potential generation of waste
water resulting from the project
activities and/ or sub-projects
during both construction and
operation.
-contamination of water, soil
and agricultural products with
insecticides and herbicides
Biological Resources- Flora &
Fauna
Removal or disturbance of
natural vegetation, A loss or
disturbance to a unique, rare or
threatened plant community, A
reduction in the numbers or
restriction in the range of any
unique, rare or threatened
species of plants such as
bushes, A deterioration of
existing wildlife habitat,
Introduction of any factors
(light, fencing, noise, human
presence and/or domestic
animals) which could hinder
the normal activities of wildlife
rapid growth vegetation,
erosion control matting) to
exposed areas;
Restrict movement of
vehicles to designated tracks;
Operation
Maintain periodically
vehicles and equipment to
prevent leaks;
Maintain records and
procedures for equipment
maintenance, handling and
storage of liquid fuels and
chemicals; lab regular testing
for ground and surface water
Wastewater
Encourage drying
mechanisms to avoid
stagnant water
Use of bio-treatment to
prevent chemical
contamination
Apply IPMP to avoid
negative impact of pesticides
and herbicides if required,
apply biological control for
pests. 5
Biological Resources- Flora
& Fauna
Applying environmental
operational standards within
the legal, policy and
management framework of
the project to minimize the
negative impact on the
environment using the
comparative advantage of the
different project counterparts.
Compliance with SFD’s
5 Integrated Pest Management Plan as per World Bank operational manual at http://web.worldbank.org/WBSITE/EXTERNAL/TOPICS/EXTARD/EXTPESTMGMT/0
57
ESMF is critical for the
conservation of biodiversity
Coordination with relevant
stakeholders is very
important, Proper selection of
sites as to avoid damaging
natural habitat. Tender
document will have to
include provisions for site
specific ESMP.
Open
Catchment
Covered
Rainwater
Harvesting
Cisterns for
Domestic
Use
Air Quality and Noise
Construction
Construction may impact air
quality and generate noise. This
results mainly from excavation,
site grading, vehicle loading
and unloading, and other
construction-related activities.
Operation
- Bad odors from donkeys'
droppings together with water
spills from extracting water
- Mosquito breeding may occur
as well as algae growth,
Soil Quality and Ground
Water Contamination
Construction
Impacts on soil quality may
result from the following
construction activities: Site
clearance, site grading,
excavation, infrastructure, and
oil leaks from
vehicles/equipment.
Operation
Donkeys' droppings together
with water spills may percolate
and contaminate groundwater.
-Potential for stagnant
water
Biological Resources- Flora &
Fauna
Construction & Operation
Air Quality and Noise
Construction
Use dust control measures
onsite, such as water spraying
for dust suppression;
Regulate site access;
Cover lorries transporting
friable construction materials
and spoil;
Prohibit open air burning;
Maintain machinery and
vehicles in good working
conditions to minimize
emissions; and
Provide adequate protective
wear for workers
Operation
-Assess the ecology of
disease carriers in the
watershed
- Employ suitable prevention
and mitigation measures,
including education of local
people
and construction workers,
-Monitor disease and public
health indicators,after
construction, and take
corrective measures (e.g.
education, medical) as
needed
- Treatment of stagnant water
to avoid biological
contamination
Biological Resources- Flora
& Fauna
Villages CBOs
with support
from
Governorate
lined Units in
addition to
SFD/PWP
conducting
visual inspection
with the
assistance of a
representative of
the local
community.
Contracts and
ECO ensures that
contractors
implement
environmental
and social
management
plans/regulations
and that
Technical
officials with
CBOs perform
continuous
inspection and
monitoring of
areas of potential
pollution and/or
uses with the
potential to result
in soil
contamination;
Review of tender
and bid
documents by
SFD
58
Removal or disturbance of
natural vegetation, A loss or
disturbance to a unique, rare or
threatened plant community, A
reduction in the numbers or
restriction in the range of any
unique, rare or threatened
species of plants such as
indigenous herbs, A
deterioration of existing
wildlife habitat, Introduction of
any factors (light, fencing,
noise, human presence and/or
domestic animals) which could
hinder the normal activities of
wildlife
- Applying environmental
operational standards within
the legal, policy and
management framework of
the project to minimize the
negative impact on the
environment using the
comparative advantage of the
different project counterparts.
- Proper selection of sites as
to avoid damaging natural
habitat.
- Tender document will have
to include provisions for site
specific ESMP and
implementation, when
required.
Rooftop
rainwater
harvesting
cisterns
Construction
- Owners tend to have the
cistern very near to the house
sometimes directly adjacent to
the house and this may cause
house damage due possible
water leakage,
- Land acquisition problem may
arise,
Operation
- There is a possibility for
Mosquito breeding and algae
growth,
- Contamination of stored water
as a result of using dirty
bucket and rope for extracting
water.
Clogging of the inlet coarse
filter may cause loss of
precious water to the owner.
Construction
- Proper selection of sites far
from buildings and insure
water tightness of the
cistern,
- Help solving land
acquisition amicably,
Operation
- Educated the owners to
keep the cistern close after
each use and use clean
bucket and rope for
extracting water,
- Clean the course filter
frequently,
- Frequently inspect the
cistern for leakage and the
houses for expected
damages from leakages,
- House owner
and supervising
team to select
good location
for the cistern.
- Supervising
technician and
engineer to
insure the
quality of work
and the water
tightness of the
cistern
Flood
Protection
Alteration or damaging natural
habitat during construction,
contamination may occur from
construction infrastructure and
materials, run-off surface water
obstacles and divert to cause
other flooding hazards
Avoiding damaging natural
habitat during constructions
or minimize it (proper site
selection, use
environmentally friendly
materials, prepare materials
off-site, etc.)
Tender document will have
to include provisions for site
specific ESMP.
Good practice in design
All technical
stakeholders are
involved in
inspection of
quality assurance
with village
CBO and overall
supervision of
SFD/PWP
59
Water
Saving
Irrigation
Systems
Plastic installation and dioxin
made material could be a
source of contamination for
water and soil and thus public
health
Using materials made from
environmental friendly
materials and good practice
Apply specific site ESMP
All technical
stakeholder are
involved in
inspection of
quality assurance
and WEU with
village CBO
Stone
Pavement
Air Quality and Noise
Construction
Construction may impact air
quality and generate noise. This
results mainly from excavation,
site grading, vehicle loading
and unloading, and other
construction-related activities.
Operation
Potential impacts on ambient
air quality would result from
odors and gaseous emissions
generated by stagnant water –
water may increase humidity
- Exposure to or production
cracks, humidity exfoliation
may happen due to high
humidity in the area
- Odor due to increase relative
humidity
- Deterioration of stone
pavement may lead to erosion
or flash flood
- disturbing the stability of
slopes and soils due to large
quantities used in building
pavements
- interruption of some runoff
water
Soil Quality and
Surface/Ground water
pattern/contamination
Construction
Impacts on soil quality may
result from the following
construction activities:
Change in composition,
filtration.
Operation
Air Quality and Noise
Construction
Use dust control measures
onsite, such as water spraying
for dust suppression;
Regulate site access;
Cover lorries transporting
construction materials;
Prohibit open air burning;
Maintain machinery in good
working conditions to
minimize emissions; and
Provide adequate protective
wear for workers
Pre-treat gases emitted
Operation
Conserve energy use to
reduce fuel combustion;
Regular inspection and
examinations for mentioned
impacts and address them
through maintenance
replacement of materials
spoiled. Minimizing entrance
of heavy machines to reduce
vibration impact. Applying
occupational health
protection regulations and
measurements is critical for
all operational stages from
stone cutting through finish
of pavement. Soil Quality
and Surface/Ground water
pattern/contamination
Design
Include groundwater
recharging means such as
leaching and pits and
trenches to mitigate the
impacts of low infiltration
resulted from pavement
SFD/PWP with
beneficiaries
CBOs oversees
construction and
operation
activities and
conducts visual
inspection with
the assistance of
a representative
of the local
community.
PCU coordinator
ensures that
contractors
implement
environmental
management
plans/regulations
and that
contractors
perform
continuous
inspection and
monitoring of
areas of potential
pollution and/or
uses with the
potential to result
in soil
contamination;
Complaints from
local community
Review of tender
and bid
documents by
SFD/PWP
60
Contamination of soils and
groundwater with chemicals
used in construction and
chemicals and oil spills from
equipment.
Spills and leaks at liquid
impoundment areas for fuels,
solvents, waste and from
infrastructure equipment, may
infiltrate through soil pores,
under gravitational forces, and
contaminate ground water
aquifers;
Discharge into surface waters,
or alteration of surface water
quality, including but not
limited to temperature,
dissolved oxygen, turbidity,
solids
Wastewater
Potential generation of waste
water resulting from the project
activities and/ or sub-projects
during both construction and
operation.
Biological Resources- Flora &
Fauna
Removal or disturbance of
natural vegetation, A loss or
disturbance to a unique, rare or
threatened plant community, A
reduction in the numbers or
restriction in the range of any
unique, rare or threatened
species of plants such as
bushes, A deterioration of
existing wildlife habitat,
Introduction of any factors
(light, fencing, noise, human
presence and/or domestic
animals) which could hinder
the normal activities of wildlife
Construction
Apply, inspect and maintain
temporary/permanent erosion
and sediment control
measures (e.g. silt fences,
rapid growth vegetation,
erosion control matting) to
exposed areas;
Restrict movement of
vehicles to designated tracks
Operation
Periodically maintain
vehicles and equipment to
prevent leaks;
Maintain records and
procedures for equipment
maintenance, handling and
storage of liquid fuels and
chemicals; lab regular testing
for ground and surface water
Wastewater
Encourage drying
mechanisms to avoid
stagnant water
Use of bio-treatment to
prevent chemical
contamination
Biological Resources- Flora
& Fauna
Applying environmental
operational standards within
the legal, policy and
management framework of
the project to minimize the
negative impact on the
environment using the
comparative advantage of the
different project counterparts.
Compliance with SFD
criteria is critical for the
conservation of biodiversity.
Coordination with relevant
stakeholders is very
important. Proper selection of
sites as to avoid damaging
natural habitat. Tender
document will have to
include provisions for site
specific ESMP.
61
Basic
services
facilities:
Education,
Health, etc.
Construction
-Dispute among beneficiaries
on the Location
-Water pollution due to
wastewater disposal of
temporary latrines
-Spread out of construction
waste
-Spread out of solid municipal
waste
Operation
Types of health waste can
include:
-Human tissue and blood;
-Soiled surgical dressings and
swabs;
-Discarded syringe needles;
-Other contaminated sharp
instruments;
- Microbiological cultures and
potentially infected wastes from
laboratories;
-Excretions; and
-Drugs and other
pharmaceutical products.
-Radioactive wastes need to be
managed and treated separately
from other healthcare wastes,
and are not covered here (will
require separate EMP)
-Human feces spread
around the site
-Water pollution due to
wastewater disposal of
school bathrooms
Proper selection of sites as to
avoid dispute among
beneficiaries on the location.
Tender document will have
to include provisions for site
specific ESMP.
-Applying occupational
health risk control measures
regulations and procedures
-Locate latrines, septic
systems and soakaways at
least 30m from any water
body (e.g. stream, river, lake,
pond)
-Ensure adequate design,
installation and maintenance
of latrines, holding tanks,
septic systems and
wastewater soakaways. This
is especially important where
the water table is
high or soils have a high clay
or sand content
-Ensure adequate spacing
between latrines and
soakaways
- Tender document for
hazardous wastes will have to
include provisions for site
specificmanagement
measures specified in ESMP.
Determine the approximate
volumes of waste materials
by category (e.g. sharps,
body tissues, dressings,
pharmaceutical products,
non-hazardous healthcare
wastes, etc.), and design the
management system to deal
with each waste category
separately as required
- Assess current practices and
address the priority gaps and
risks, building on any
successful aspects of the
current system. All measures
and facilities should be
planned within an overall
strategy for hazardous
healthcare waste
management. This overall
strategy will ensure
consistent and efficient
methods, and sharing of good
practices.
All technical
stakeholders are
involved in
inspection of
quality assurance
with village
CBO
62
- Provide specialized, clearly
labeled containers for
hazardous healthcare wastes
to separate them at source,
manage the risks of exposure,
and secure the wastes before
removal for treatment or
storage.
- Plan, design, construct and
operate a shared treatment
facility. Types of facilities
include heat treatment
disinfection, incineration,
chemical & biological
treatment.
- Until a shared treatment
facility is established, employ
interim measures to ensure
the safe and secure storage of
wastes. In some cases, an
appropriate interim measure
will be to bury the waste in
deep (e.g. >2m) trenches in
municipal disposal sites, and
ensure the trenches are
immediately covered with
other municipal solid waste.
-Implementing the Self
Monitoring and Follow up
and sewage treatment
Implementing the items in
the TD related to dealing
with municipal solid wastes
and the components needed
for SWMP
Rural
Feeder Road
Construction
Construction may impact air
quality and generate noise. This
results mainly from excavation,
site grading, vehicle loading
and unloading, and other
construction-related activities.
Solid wastes
Construction wastes
Historical monuments
Green areas
Sanitary drainage
Deformation of grades
Blockage of water canals and
drainage course at their
intersection with road.
-Good practice during
construction. Proper
treatment of solid waste and
other byproduct during
construction
-Applying occupational
health risk control measures
regulations and procedures
-Apply suitable design for
natural water courses and
putting measures for
preserving wildlife
-Avoiding damaging natural
habitat during constructions
or minimize it (proper site
selection, use
environmentally friendly
materials, prepare materials
off-site, etc.)
All technical
stakeholders are
involved in
inspection of
quality assurance
with village
CBO and overall
supervision of
SFD
63
Alteration or damaging natural
habitat during construction,
contamination may occur from
construction infrastructure and
materials, run-off surface water
obstacles and divert to cause
other flooding hazards. A
deterioration of existing
wildlife habitat, Introduction of
any factors (light, fencing,
noise, human presence and/or
domestic animals) which could
hinder the normal activities of
wildlife
Operation
Abrasion of road
Increase of traffic accidents
-Avoid creating congested
and unsafe road conditions at
intersections, and in villages
and towns
-Good practice in design to
avoid traffic accidents such
as Sloping of road Curves
-Include components that
reduce traffic accidents such
as speed breakers and speed
limits signs
-Tender document will have
to include provisions for site
specific ESMP.
Improving
Rural
Markets
Construction
Construction may impact air
quality and generate noise. This
results mainly from excavation,
site grading, vehicle loading
and unloading, and other
construction-related activities.
Solid wastes
Construction wastes
Historical monuments
Green areas
Sanitary drainage
Deformation of grades
Operation
Solid waste, wastewater from
market latrines may cause soil
and water sources pollution
Construction
-Maintain equipment in good
working condition to reduce
emissions and noise,
-Use dust control measures
onsite, such as water spraying
for dust suppression;
-Good practice associated
with quality assurance and
regular site inspection
-Cover lorries transporting
friable construction materials
-Maintain a system for
collecting and disposing
garbage during construction
-Collect construction wastes
and transport them to the
agreed site
-Tendering should include
specific site ESMP
-Applying occupational
health risk control measures
regulations and procedures
Operation
-Enforce the solid waste
management system that
should have been developed
by the SA at the preparation
stages
District/town/vill
age councils with
support from
CBOs and SFD
64
-Maintain good operation and
maintenance of market
latrines
Water
Supply
During design
-Health: Vector breeding sites;
-Land use: Disputes about
designed project site
on privately owned land, or
disconcerting areas of public,
touristic interest, disturbing
wildlife etc.
-Disputes about
designed route of
pipes through privately
owned land
-Land
Resources: Ground water
pollution from pit
latrines polluting the underlying
aquifer.
During construction:
- Air: Increased dust during
excavation and burial of pipes.
-Hygienic conditions
around public collection
points by
paving at least 1 m² apron
concrete slab under the water
taps with proper drainage and
fencing.
-Discuss the planned
site with landowners to
get approval. If land cannot
be obtained through
voluntary land donation, it
needs to change the design to
communal owned land or to
land with less expected
conflicts. Consider drop of
sub- project if problems are
not resolved.
-Discuss the planned
route with landowners
to get their approval. If the
land cannot be obtained
through voluntary land
donation, it needs to change
the planned route to avoid
conflicts.
- Ground water quality
testing at source
development and
regular intervals.
Soil/site inspection
before latrine
construction. Latrines to
be more
than 50 m from wells.
-Applying occupational
health risk control measures
regulations and procedures
-Coordinate with local
authorities to avoid or
minimize disruption to basic
services such as water and
sewer.
-Inform nearby households.
SFD/PWP
Environmental
Specialist
And Local NGOs
65
- Health: Collection, handling
and disposal of solid waste.
- Infrastructure services:
Possible damage to water
supply pipes paved roads,
cables, existing cesspits, leaking
or blowout of water reservoir.etc.
-Noise: Increased levels of
noise and vibration
- Safety: possibility of
Accidents
- Increased Traffic: Disruptions
of water supply and local access
- Water: Pit latrines can
pollute the underlying aquifer.
Protect excavation works
with proper shielding
scaffolds.
Spraying water during
excavation might reduce the
dust. Workers wear protective
masks
- Take health and safety
measures when disposal of
excavated soil to a safe
location.
-Proper maintenance and
inspection of water pipes and
community reservoirs to
ensure leaks or damage are
avoided and repaired quickly
if/when identified to prevent
ruptures.
-Avoid causing damages.
Dispose all waste and soil
to a safe location.
Repair pavement on the
completion of the
Works
- Inform nearby houses.
Avoid work during
night hours.
Provide workers with
Protection
- Protect work zones
with portable scaffold
sheets.
Provide proper support for
trench sides to protect
against their collapse.
Improve the readiness
of health facilities in the
region to deal with
emergency cases. Provide
workers with protective
clothing.
- Inform the affected
houses in advance and
keep disruptions as
short as possible
Contracts to include
provisions for chance find.
Training will take place
66
Archaeological find:
Damaging important
and/or precious cultural
heritage
Safety: possibility of accidents
During Operation:
- Health: The possible
formation of vector breeding
stagnant effluent ponds.
Water: Ground water
Pollution from Pit latrine
for crew/supervisors,
to spot potential
archaeological finds. In the
event of a potential find,
liaise with the archaeological
department at MoC or a local
university for quick
assessment and action
Protect construction site from
trespassers.
Improve the readiness of
health facilities in the region
to deal with emergency cases.
Provide workers with
protective clothing.
Take necessary actions for
fighting vectors (spraying
with insecticides,
reclamation of stagnant
pools, using nets on
windows and beds, etc.)
- Ground water quality
testing at source at regular
intervals.
Sewerage
Networks
During design:
Water: Land use: Disputes
about designed route of
pipes through privately owned
land
During construction:
- Air: Increased dust during
excavation and burial of pipes
- Health: Removal and disposal
of waste material from
- Discuss the planned
route with landowners
to get their approval. If the
land cannot be obtained
through voluntary land
donation, it needs to change
the planned route to avoid
conflicts
-Applying occupational
health risk control measures
regulations and procedures
Spraying water during
excavation might reduce the
dust. Workers wear protective
masks
-Avoid causing damages.
SFD/PWP
Environmental
Specialist
EPA
Local NGOs
67
(existing) pits. Collection,
handling and disposal of solid
waste.
- Infrastructure services:
Possible destruction
of water supply pipes,
paved roads, cables, existing
cesspits, .etc.
Noise: Increased levels of noise
and vibration
Occupational Health and Safety
Traffic: Disruptions of water
supply and local access
- Archaeological find:
Damaging important
and/or precious cultural
heritage
Take health and safety
measures when demolishing
existing cesspits and on the
disposal of sludge and
polluted excavated soil.
Dispose all polluted waste
and soil to a safe location.
Repair pavement on the
completion of the
Works
- Inform nearby houses.
Avoid work during
night hours.
- Protect work zones with
portable scaffold
sheets.
Provide proper support for
trench sides to protect
against their collapse.
Improve the readiness of
health facilities in the region
to deal with emergency cases.
Provide workers with proper
safety equipment and
clothing.
Inform the affected
houses in advance and
keep disruptions as
short as possible.
- Contracts to include
provisions for chance find.
Training will take place for
crew/supervisors,
to spot potential
archaeological finds. In the
event of a potential find,
liaise with the archaeological
department at MoC or a local
university for quick
assessment and action.
- Protect construction site
from trespassers.
- Improve the readiness
of health facilities in the
region to deal with
emergency cases.
68
Safety: possibility of accidents
Schools During design:
Land use: Disputes about
designed project site on
privately owned land, or
disconcerting areas of public,
touristic interest, disturbing
wildlife etc.
Health: Lack or failure of
sanitation facilities
During construction:
Noise: Increased levels of noise
and vibration.
- Archaeological find:
Damaging important and/or precious cultural
heritage.
Safety: Possibility of
accidents/hazards
Discuss the planned site
with landowners to get
approval. If the land cannot be
obtained through voluntary
land donation, it needs to
change the design to
communal owned land or to
land with less expected
conflicts.
Add sanitation facilities to
the design or upgrade
existing facilities.
Inform nearby houses.
Avoid work during night
hours.
- Training will take place for crew/supervisors, to spot potential archaeological finds. In the event of a potential find, liaise with the archaeological department at MoC or a local university for quick assessment and action.
- Protect construction
site from trespassers.
SFD/PWP
Environmental
Specialist
EPA
Local NGOs
69
Provide proper support for
trench sides to protect
against their collapse.
Improve the readiness
of health facilities in the
region to deal with
emergency cases.
Provide workers with
protective clothing.
-Applying occupational
health and safety risk
control measures
regulations and procedures
70
Annex 3. Environmental and Social Management Plan - Indicative Outline
Please refer to the UNDP SES Guidance Note on Assessment and Management for additional information.
The content of the ESMP may be presented in different formats (per templates of SFD and PWP) but should
address the following elements:
(1) Project Information: Project title and brief description of project activities, location and surrounding
area. Note key stakeholders. Inclusion of drawing or map
(2) Impacts and Mitigation Measures: Identifies measures and actions in accordance with the mitigation
hierarchy that avoid, or if avoidance not possible, reduce potentially significant adverse social and
environmental impacts to acceptable levels. Specifically, the ESMP: (a) identifies and summarizes all
anticipated significant adverse social and environmental impacts; (b) describes – with technical details –
each mitigation measure, including the type of impact to which it relates and the conditions under which it
is required (e.g., continuously or in the event of contingencies), together with designs, equipment
descriptions, and operating procedures, as appropriate; (c) estimates any potential social and
environmental impacts of these measures and any residual impacts following mitigation; and (d) takes into
account, and is consistent with, other required mitigation plans (e.g. for displacement, indigenous peoples).
(2) Monitoring: Identifies monitoring objectives and specifies the type of monitoring, with linkages to the
impacts assessed in the environmental and social assessment and the mitigation measures described in the
ESMP. Specifically, the monitoring section of the ESMP provides (a) a specific description, and technical
details, of monitoring measures, including the parameters/indicators to be measured, methods to be used,
sampling locations, frequency of measurements, detection limits (where appropriate), and definition of
thresholds that will signal the need for corrective actions; and (b) monitoring and reporting procedures to
(i) ensure early detection of conditions that necessitate particular mitigation measures, and (ii) furnish
information on the progress and results of mitigation.
(3) Capacity development and training: To support timely and effective implementation of social and
environmental project components and mitigation measures, the ESMP draws on the environmental and
social assessment of the existence, role, and capability of responsible parties on site or at the agency and
ministry level. Specifically, the ESMP provides a description of institutional arrangements, identifying which
party is responsible for carrying out the mitigation and monitoring measures (e.g. for operation,
supervision, enforcement, monitoring of implementation, remedial action, financing, reporting, and staff
training). Where support for strengthening social and environmental management capability is identified,
ESMP recommends the establishment or expansion of the parties responsible, the training of staff and any
additional measures that may be necessary to support implementation of mitigation measures and any
other recommendations of the environmental and social assessment.
(4) Stakeholder Engagement: Outlines plan to engage in meaningful, effective and informed consultations
with affected stakeholders. Includes information on (a) means used to inform and involve affected people
in the assessment process; (b) summary of stakeholder engagement plan for meaningful, effective
consultations during project implementation, including identification of milestones for consultations,
information disclosure, and periodic reporting on progress on project implementation; and (c) description
of effective processes for receiving and addressing stakeholder concerns and grievances regarding the
project’s social and environmental performance.
71
(5) Implementation action plan (schedule and cost estimates): For all four above aspects (mitigation,
monitoring, capacity development, and stakeholder engagement), ESMP provides (a) an implementation
schedule for measures that must be carried out as part of the project, showing phasing and coordination
with overall project implementation plans; and (b) the capital and recurrent cost estimates and sources of
funds for implementing the ESMP. These figures are also integrated into the total project cost tables. Each
of the measures and actions to be implemented will be clearly specified and the costs of so doing will be
integrated into the project's overall planning, design, budget, and implementation.
72
Annex 4. Guidance for Submitting a Grievance
Guidance for Submitting a Request to UNDP Social and Environmental Compliance Unit (SECU) and/or the Stakeholder Response Mechanism (SRM) [for more information go to www.undp.org/secu-srm]
Purpose of this form
- If you use this form, please put your answers in bold writing to distinguish text - The use of this form is recommended, but not required. It can also serve as a guide
when drafting a request.
This form is intended to assist in:
(1) Submitting a request when you believe UNDP is not complying with its social or environmental policies or commitments and you are believe you are being harmed as a result. This request could initiate a ‘compliance review’, which is an independent investigation conducted by the Social and Environmental Compliance Unit (SECU), within UNDP’s Office of Audit and Investigations, to determine if UNDP policies or commitments have been violated and to identify measures to address these violations. SECU would interact with you during the compliance review to determine the facts of the situation. You would be kept informed about the results of the compliance review.
and/or
(2) Submitting a request for UNDP “Stakeholder Response” when you believe a UNDP project is having or may have an adverse social or environmental impact on you and you would like to initiate a process that brings together affected communities and other stakeholders (e.g., government representatives, UNDP, etc.) to jointly address your concerns. This Stakeholder Response process would be led by the UNDP Country Office or facilitated through UNDP headquarters. UNDP staff would communicate and interact with you as part of the response, both for fact-finding and for developing solutions. Other project stakeholders may also be involved if needed.
Please note that if you have not already made an effort to resolve your concern by communicating directly with the government representatives and UNDP staff responsible for this project, you should do so before making a request to UNDP’s Stakeholder Response Mechanism.
Confidentiality If you choose the Compliance Review process, you may keep your identity confidential (known only to the Compliance Review team). If you choose the Stakeholder Response
73
Mechanism, you can choose to keep your identity confidential during the initial eligibility screening and assessment of your case. If your request is eligible and the assessment indicates that a response is appropriate, UNDP staff will discuss the proposed response with you, and will also discuss whether and how to maintain confidentiality of your identity.
Guidance
When submitting a request please provide as much information as possible. If you accidentally email an incomplete form, or have additional information you would like to provide, simply send a follow-up email explaining any changes.
Information about You
Are you…
1. A person affected by a UNDP-supported project?
Mark “X” next to the answer that applies to you: Yes: No:
2. An authorized representative of an affected person or group?
Mark “X” next to the answer that applies to you: Yes: No:
If you are an authorized representative, please provide the names of all the people whom you are representing, and documentation of their authorization for you to act on their behalf, by attaching one or more files to this form.
3. First name:
4. Last name:
5. Any other identifying information:
6. Mailing address:
7. Email address:
8. Telephone Number (with country code):
9. Your address/location:
10. Nearest city or town:
11. Any additional instructions on how to contact you:
12. Country:
What you are seeking from UNDP: Compliance Review and/or Stakeholder Response
You have four options:
• Submit a request for a Compliance Review;
• Submit a request for a Stakeholder Response;
• Submit a request for both a Compliance Review and a Stakeholder Response;
• State that you are unsure whether you would like Compliance Review or Stakeholder Response and that you desire both entities to review your case.
13. Are you concerned that UNDP’s failure to meet a UNDP social and/or environmental policy or commitment is harming, or could harm, you or your community? Mark “X” next to the answer that applies to you: Yes: No:
14. Would you like your name(s) to remain confidential throughout the Compliance Review process?
74
Mark “X” next to the answer that applies to you: Yes: No:
If confidentiality is requested, please state why:
15. Would you like to work with other stakeholders, e.g., the government, UNDP, etc. to jointly resolve a concern about social or environmental impacts or risks you believe you are experiencing because of a UNDP project?
Mark “X” next to the answer that applies to you: Yes: No:
16. Would you like your name(s) to remain confidential during the initial assessment of your request for a response?
Mark “X” next to the answer that applies to you: Yes: No:
If confidentiality is requested, please state why:
17. Requests for Stakeholder Response will be handled through UNDP Country Offices unless you indicate that you would like your request to be handled through UNDP Headquarters. Would you like UNDP Headquarters to handle your request?
Mark “X” next to the answer that applies to you: Yes: No:
If you have indicated yes, please indicate why your request should be handled through UNDP Headquarters:
18. Are you seeking both Compliance Review and Stakeholder Response?
Mark “X” next to the answer that applies to you: Yes: No:
19. Are you unsure whether you would like to request a Compliance Review or a Stakeholder Response? Mark “X” next to the answer that applies to you: Yes: No:
Information about the UNDP Project you are concerned about, and the nature of your concern:
20. Which UNDP-supported project are you concerned about? (if known):
21. Project name (if known):
22. Please provide a short description of your concerns about the project. If you have concerns about UNDP’s failure to comply with its social or environmental policies and commitments, and can identify these policies and commitments, please do (not required). Please describe, as well, the types of environmental and social impacts that may occur, or have occurred, as a result. If more space is required, please attach any documents. You may write in any language you choose
23. Have you discussed your concerns with the government representatives and UNDP staff responsible for this project? Non-governmental organisations?
Mark “X” next to the answer that applies to you: Yes: No:
If you answered yes, please provide the name(s) of those you have discussed your concerns with
Name of Officials You have Already Contacted Regarding this Issue:
75
First Name Last Name Title/Affiliation Estimated
Date of
Contact
Response from the
Individual
24. Are there other individuals or groups that are adversely affected by the project?
Mark “X” next to the answer that applies to you: Yes: No:
25. Please provide the names and/or description of other individuals or groups that support the request:
First Name Last Name Title/Affiliation Contact Information
Please attach to your email any documents you wish to send to SECU and/or the SRM. If all of your attachments do not fit in one email, please feel free to send multiple emails.
Submission and Support
To submit your request, or if you need assistance please email: [email protected]
Complaints Registration Form at PWP
Complaints registration form at PWP
.................................................التاريخ:project Noرقم المشروع:..Date ..............................
Projectاسم المشروع: .
Name...........................................................................................
Name ofاسم الشاكي:......
complainant..............................................................................
76
Complaintنص الشكوى:.
content .........................................................................................
.............................................................................Actions takenاإلجراءات المتخذه: ...
The date of resolving theتاريخ انتهاء المشكله: ..
complaints ...................................................
..............................................................................................Commentsالمالحظات:..............
Follow-up department مدير إدارة المتابعة Responsible person المختص: Manager
signature التوقيع signature :التوقيع
Complaint Handling Mechanism (CHM) Online Form for SFD [for more information go to https://chm.sfd-yemen.org/complaint/online-form/]
77
Annex 5. OHS Framework
(attached separately)
Annex 6. OHS Toolkit
(attached separately)
Annex 7. PWP Operational Manual
(attached separately)
Annex 8. PWP Environmental and Social Management Framework (2014)
(attached separately)
Annex 9. SFD Operational Manual
(attached separately)
Annex 10. SFD Phase IV Environmental and Social Management Framework (2014)
(attached separately)
Annex 11. Summary of ECRP ESMF Stakeholder Consultations in Sana’a and Aden
(attached separately)
Annex 12. Third-Party Monitoring Report – ESMF Stakeholder Consultation
(attached separately)