Environmental and Social Assessment with Management Plan...
Transcript of Environmental and Social Assessment with Management Plan...
Prepared for National Ganga River Basin Authority (NGRBA)
(Ministry of Environment and Forests, Government of India)
Final Report
Environmental and Social Assessment with Management Plan for Sewerage
Works in Sewerage District ‘A’ of
Allahabad City, Uttar Pradesh
SFG1690 V7P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
ii
© The Energy and Resources Institute 2014
Suggested format for citation
T E R I. 2014
Environmental and Social Assessment with Management Plan for Sewerage Works
in Sewerage District ‘A’ of Allahabad City, Uttar Pradesh
New Delhi: The Energy and Resources Institute.
[Project Report No. 2010WM13]
For more information Project Monitoring Cell
T E R I Tel. 2468 2100 or 2468 2111
Darbari Seth Block E-mail [email protected]
IHC Complex, Lodhi Road Fax 2468 2144 or 2468 2145
New Delhi – 110 003 Web www.teriin.org
India India +91 • Delhi (0)11
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
iii
Table of Contents EXECUTIVE SUMMARY ................................................................................................................... 1
CHAPTER 1 INTRODUCTION ......................................................................................................... 9
1.1 Ganga Clean up Initiatives ............................................................................................. 9
1.2 The Ganga River Basin Project ....................................................................................... 9
1.2.1 World Bank Assistance ................................................................................... 10
1.3 Project Components ....................................................................................................... 10
1.3.1 Component One: Institutional Development .............................................. 10
1.3.2 Component Two: Priority Infrastructure Investments .............................. 11
1.4 Structure of the Report ................................................................................................. 12
CHAPTER 2 PROJECT DESCRIPTION ........................................................................................... 13
2.1 About the City ................................................................................................................ 13
2.2 Existing Sewerage Facilities in Allahabad City ......................................................... 13
2.2.1 Works Completed under Ganga Action Plan Phase – I (GAP-I) .............. 14
2.2.2 Works Completed under Ganga Action Plan Phase II .............................. 15
2.2.3 On-going works in Sewerage District ‘D’ Under JNNURM ..................... 15
2.2.4 City Sewerage Plan ......................................................................................... 16
2.2.5 Works Approved Under NGRBA for District A ......................................... 19
2.3 Necessity of this project ................................................................................................ 19
2.4 Location of Proposed Sewerage Project ...................................................................... 21
2.5 Proposed Sewerage System .......................................................................................... 23
2.5.1 Components of Proposed Sewerage Work .................................................. 23
2.5.2 Implementation Schedule .............................................................................. 25
2.5.3 Financing .......................................................................................................... 25
CHAPTER 3 APPROACH AND METHODOLOGY ......................................................................... 27
3.1 Methodology................................................................................................................... 27
3.2 Project Screening ............................................................................................................ 29
3.3 Conclusion of Screening Activity ................................................................................ 41
CHAPTER 4 REGULATIONS AND LEGAL FRAMEWORK ............................................................. 42
4.1 Applicable Laws and Regulations – Environmental................................................. 42
4.1.1 Legal Framework of Government of India .................................................. 42
4.1.2 Key Environmental Laws and Regulations ................................................. 42
4.2 Applicable Laws and Regulations - Social ................................................................. 45
4.3 Other Legislations applicable to Construction Projects under NGRBP ................. 47
CHAPTER 5 BASELINE STATUS ................................................................................................... 50
5.1 Baseline Environmental ................................................................................................ 50
5.1.1 Physiography and Topography .................................................................... 50
5.1.2 Climate .............................................................................................................. 50
5.1.3 Geological and Geophysical features ........................................................... 51
5.1.4 Ambient Air Quality ....................................................................................... 53
5.1.5 Noise Environment ......................................................................................... 55
5.1.6 Water Environment ........................................................................................ 57
5.1.7 Storm Water Drainage .................................................................................... 63
5.1.8 Waste Water Management ............................................................................. 64
5.1.9 Solid Waste Management .............................................................................. 66
5.1.10 Biological Environment ................................................................................. 68
5.2 Baseline Social Status ..................................................................................................... 71
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
iv
5.2.1 Public Consultation ......................................................................................... 76
CHAPTER 6 ENVIRONMENTAL AND SOCIAL IMPACTS ............................................................ 80
6.1 Potential Environmental Impacts ................................................................................ 80
6.1.1 Design and Development Phase ................................................................... 80
6.1.2 Impacts during construction phase .............................................................. 80
6.1.3 Impacts during operation phase ................................................................... 83
6.2 Potential Social Impacts ................................................................................................ 84
6.3 Conclusion ...................................................................................................................... 87
CHAPTER 7 MITIGATION AND MANAGEMENT PLAN .............................................................. 89
7.1 Environmental Management Plan ............................................................................... 89
7.1.1 Implementation of EMP Specific activities by UPJN ................................. 89
7.1.2 Specific activities by Contractor .................................................................... 89
7.2 Environmental Monitoring Plan .................................................................................. 98
7.3 EMP Budget .................................................................................................................... 98
7.4 Social Management Plan ............................................................................................. 109
7.4.1 Social mitigation plans during construction phase .................................. 109
7.4.2 Social mitigation plans during operation phase ....................................... 111
7.4.3 Mitigation measures adopted by locals during similar nature of
project activities ............................................................................................. 111
7.4.4 Consultation Framework for Participatory Planning and
Implementation of Mitigation Plan ............................................................ 114
7.4.5 Assess the Capacity of Institutions and Mechanisms for
Implementing Social Development Aspects and Social Safeguard Plans; Recommend Capacity building measures ..................................... 114
CHAPTER 8 SOCIAL DEVELOPMENT OUTCOMES AND ISSUES .............................................. 118
8.1 Social Development Outcomes of the sub project ................................................... 118
8.2 Social Development Issues in Project Vicinity and Social Services to be
provided by the project ............................................................................................... 119
CHAPTER 9 CONCLUSION ......................................................................................................... 120
ANNEXURE 1 QUESTIONNAIRE ................................................................................................. 121
ANNEXURE 2 MINUTES OF MEETING WITH KEY STAKEHOLDERS ......................................... 124
ANNEXURE 3 CENSUS DATA ..................................................................................................... 129
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
v
List of Tables
Table 2.1 District wise (A to G) arrangements and status of Sewage Treatment in
Allahabad* .................................................................................................................... 17
Table 2.2 Sewage Flow Generation (Capacities in MLD) ....................................................... 20
Table 3.1 Environment and Social information format for screening .................................. 30
Table 4.1 Environmental Regulations and Legislations ......................................................... 42
Table 4.2 The Land Acquisition Process ................................................................................... 46
Table 5.1 Climatological Normal of Temperature, Humidity and Rainfall at
Allahabad ..................................................................................................................... 51
Table 5.2 Generalized Stratigraphic Sequence Time ............................................................... 52
Table 5.3 Quality of soil sample ................................................................................................. 52
Table 5.4 Latest air quality data of two monitoring stations in Allahabad (March 2010
to April 2011) ............................................................................................................... 53
Table 5.5 Summary of Noise Level Monitored Data Code Range of noise levels
[Leq in dB (A)] ............................................................................................................. 56
Table 5.6 Water consumption in sewerage district ‘A’ ........................................................... 57
Table 5.7 Discharge of the Ganga at Allahabad (Sangam) (m3/s) ......................................... 58
Table 5.8 Water Quality of River Ganga and Yamuna at Allahabad (UP) during
Maghmela (Ardh Kumbha) 2007 .............................................................................. 61
Table 5.9 Water Quality data of Ganga and Yamuna river at Allahabad monitored
during March 2010 to April 2011 .............................................................................. 61
Table 5.10 Wastewater characteristics of Chachar nala and Ghaghar Nala in sewerage
district ‘A’ ..................................................................................................................... 65
Table 5.11 Solid waste generation in sewerage district ‘A ....................................................... 66
Table 5.12 Percentage distribution of the household population by age and sex,
Allahabad ..................................................................................................................... 72
Table 5.13 Ward wise census population and projected population and observed
land use ......................................................................................................................... 73
Table 5.14 Ward wise population density of Allahabad .......................................................... 74
Table 5.15 Ward wise details of the survey is enlisted below in the table ............................. 78
Table 7.1 Environment Management Plan ............................................................................... 91
Table7.2 Environmental Monitoring Plan ............................................................................... 99
Table 7.3 EMP Budget ............................................................................................................... 102
Table 7.4 Cost of Environmental Monitoring Plan ................................................................ 108
Table 7.5 Social Management Plan .......................................................................................... 112
Table 7.6 Role of stakeholder in implementation and mitigation ....................................... 115
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
vi
List of Figures
Figure 2.1 City sewerage Plan of Allahabad city ............................................................... 18
Figure 2.2 Location of Sewerage District ‘A’ in Allahabad City, Uttar Pradesh. ........... 22
Figure 3.1 Flowchart describing the steps adopted for Project Impact Assessment ..... 27
Figure 3.2 Satellite image showing the alignment of trees along the sides of the
roads in District A ................................................................................................ 39
Figure 5.1 SO2, NO2, and PM10 concentration (µg/m3) in Allahabad during
2008-2009 ............................................................................................................... 54
Figure 5.2 Monthwise variation of NO2 and RSPM at two monitoring stations in
Allahabad .............................................................................................................. 55
Figure 5.3 Noise levels in Allahabad City monitoring during 2010 and 2011 ............... 56
Figure 5.4 BOD measured at various stretches of Ganga river for different years ....... 59
Figure 5.5 DO measured at various stretches of Ganga river for different years .......... 60
Figure 5.6 Map showing the drainage system in sewerage district ‘A ........................... 64
Figure 5.7 Map of parks in sewerage district ‘A’ ............................................................... 68
Figure 5.8 Mapping of eco-sensitive areas around Allahabad city ................................. 70
Figure 5.9 Allahabad urban population growth rate ......................................................... 71
Figure 5.10 Map indicating major land use and social survey locations for District A .. 75
Figure 5.11 Connection to sewers ........................................................................................... 77
Figure 5.12 Problems encountered during construction phase .......................................... 77
Figure 6.1 Road network map of District A indicating majority of roads have width
less than 5 units. Around 97.39% of the roads have width less than 5 units,
where the chances of traffic congestion could be high ................................... 85
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
1
Executive Summary
Introduction
As a major first step in achieving the Ganga Clean up Initiatives, the Government of India
(GoI) constituted the National Ganga River Basin Authority (NGRBA), on 20th February
2009, for the comprehensive management of the river. In regards to this initiative, the World
Bank has been formally requested by GOI to provide long-term support to NGRBA through
several phases of substantive financing and knowledge support. The first project of several phases of support aims at:
i. Establishing and operationalizing central and state level NGRBA institutions capable
of planning and implementing a multi sectoral river water quality improvement program
ii. Reducing pollution loads into the river through selected investments.
In continuance with the pollution abatement programs by NGRBA, sewerage works for
Allahabad sewerage district ‘A’ has been recently proposed, as this area has only 45%
sewerage coverage. As per the Environmental and Social Management Framework
(NGRBA, 2011), the implementation of such river pollution mitigation projects under the NGRBP is anticipated to encounter a variety of environmental and social issues/problems.
Therefore the study of environment and social sector is required for analyzing the impacts of
proposed project, and suggesting the management plans to handle any negative impacts. The Detailed Project Report for the above components has been prepared by UPJN and TERI
has been working closely with them for preparing the Environmental and Social Assessment
with Management Plan (ESAMP).
Project Description
Allahabad city’s main land is surrounded by river Ganga and Yamuna in three directions (North, South and East). The sewerage system in the city was first introduced in the year
1901. Sewerage district A forms the core of the city. Considering the density of population,
absence of complete sewerage network (not 100% covered), proximity to the Yamuna river and hence its impact at the point of confluence, it becomes more important to provide
sewerage and treatment infrastructure in the district ‘A’. Sewerage district A has 3 zones
and 27 wards. Old sewers are egged shaped brick sewers. Some of the important sewers are:
• 62”X 93” in Atala area
• 42”X 72” & 32” X48” in Darashah Ajmal area
• 39”X 57” on Jahawar Lal Nehru Road
• 39”X45” on GT Road
• 18”X24” on Lowther Road
• 18”X24” & 18”27” in Lukarganj area
Sewage from this area is collected at Gaughat MPS and pumped through existing rising
mains across the Yamuna railway bridge to Naini STP. Defined under the previous master
plan as Zone I, the sewerage network has been reconfigured under this Master Plan to provide a smaller catchment area that will not exceed the maximum capacity of Gaughat
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
2
MPS and Naini STP (ultimate design capacity of 80 MLD with expansion). Population
densities in this area are generally greater than 300 persons per hectare and water distribution sufficiently good to support full coverage with sewerage. Sewage that does not
enter the sewer system finds its way to Chachar nala, Ghaghar nala and many smaller
tributary drains. Chachar nala flow is at present tapped and pumped to Gaughat MPS.
Status of sewage treatment in Sewerage District A
With the growing population, the total waste water generated in this district during the year
2040 would be 79.85 mld against the installed capacity of 60mld, thus an additional unit of
around 20 mld is needed.
District
Existing
STP
Capacity (MLD)
Required
STP in
2025 (MLD)
Required in 2040
(MLD)
Total STP Capacity by
2040 (MLD)
Proposed
Capacity for
Sub-project (MLD)
District A 60.00 74.36 79.85 80 20
The modification of STP capacity is already taken up under a separate package for NGRBA
funding. The UPJN along with NMCG has prepared an Environment and Social Due
Diligence Report along with EMP for the following project components:
• Expansion of existing STP from 60 MLD to 80 MLD at Naini;
• Expansion of SPS at Gaughat;
• Expansion of SPS at Chachar Nala;
• Laying and replacement of Trunk sewer; and,
• Desilting & rehabilitation of Trunk Sewer
The evaluated proposed project system is designed for 30 years period. The major
components of the proposed project include:
• Approximately 240.6227km long sewerage network
• Intermediate Sewage Pumping Stations at Bairahana, Kydganj (Gate No.9),
Bargadghat SPS
• Sewer cleaning equipment
As per DPR, total cost of the proposed projects is estimated to be Rs. 28894.71 Lakhs i. e. Rs
288.95 Crores.
Approach and Methodology
The methodology adopted for the environmental and social assessment included secondary
data analysis, carrying out scoping in the field, survey of the host population and discussion
with key stakeholders including government officials and local residents. Based on these
outcomes, a screening activity was conducted with the help of the screening checklist format
provided in Environmental and Social Management Framework of NGRBA. Thereafter,
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
3
environmental and social impacts were identified and assessed and a mitigation plan was
developed based on the aforementioned.
The screening checklist included criteria that detailed out the impact level of various
activities during the construction and operation phases. These criteria included
environmental factors such as the presence of eco-sensitive region in and around the project
area, clearance of tree cover, improper storage of excavation spoils, flooding of adjacent
areas, elevated noise and dust levels, damage to existing utilities. Social criteria included
factors such as requirement for land acquisition, displacement of tribes, loss of livelihood
and gender issues.
Based on the criteria-wise screening activity and the categorization of potential sub-projects
of the NGRBP, the present project of Sewerage work in Sewerage District ‘A’ in Allahabad
City falls under low impact category, which do not have any fresh land acquisition and has an
overall positive impact by tapping the wastewater which was earlier polluting the river
Ganga.
Environmental and Social Baseline status
As a part of ESAMP, baseline study of the sewerage district ‘A’ was prepared to understand
the region's existing physical and biological characteristics along with cultural and social
status of the residing community. The baseline information forms the basis to analyse the
probable impacts of the proposed project vis-à-vis the present background environmental
quality of the core study area. In environmental scenario it reflects the status of
environmental entities like status of climate, geological features, air quality, water quality,
waste management and existing green cover in the study area. As per the study, wastewater
generated from sewerage district ‘A’ is observed to be mostly from residential with limited
commercial and no industrial wastes. As mentioned earlier, most of sewerage district ‘A’
area has limited sewer system (45%) and wastewater flows to the river through drains.
Summary of wastewater characteristics of Ghaghar and Chachar nala located in sewer
district ‘A’ indicates that some of the wastewater quality parameters are exceeding the
general discharges standards laid out by CPCB. As reported in DPR, BOD (5dat Sat 20°C) is
32 mg/l at Chachar Nala and 67 mg/l at Ghaghar nala as against the CPCB standard of
30mg/l. They may worsen the water quality, leading to direct impact not only on the
drinking water sector but also other sectors such as fisheries, irrigation, and recreation. Even
the recorded temperature as per DPR is higher than the prescribed standard of CPCB of 5
°C. Ghaghar nala recorded 28° C and Chachar nala recorded 29° C.
As far as air quality is concerned, Allahabad city doesn’t fall under the identified list of
polluted cities in India, but the available data from NAMP monitoring shows that the dust
levels, PM10 (RSPM and SPM) have violated the annual average standards of 60 micro
gram/m3. The concentration of both sulphur- dioxide and nitrogen-dioxide are within the
permissible standards of CPCB.
For Allahabad, limited noise level monitoring has been carried out by JICA at three
locations; Numaya Dahi, Sulem Sarai and near DM office. Out of these 3 sites, only Sulem
Sarai comes in District A. At this site the noise level was higher than the desirable level for
residential area but below the permissible level of commercial and industrial area.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
4
With respect to solid waste it was observed that the waste is not properly handled and is
dumped to open sites at different places in the district. As a result of such practices, the
entire area in and around the disposal sites is unhygienic and pose a serious threat to the
environment and to public health.
While in the baseline status of social section, it brings out the status of demographic
composition of the population, general land-use feature of the wards and also details of the
social survey outcomes at various consultations held in different wards of the sewerage
district.
Potential Environmental and Social Impacts
Although there would not be any permanent negative or adverse environmental or social
impacts, but will have temporary impacts on water quality, air quality (impact on health),
traffic blockages, safety hazards for pedestrians, possible damage to private property,
possible interruption in commercial activity, and accidental breakage of other public
infrastructure such as water pipes. The identified environmental impacts were further
classified under the heads of low lying area near Kydganj that are vulnerable to flooding
and crowded/congested areas such as Muthi ganj, Rambagh area that are susceptible in to
impacts of poor air quality, noise levels and contaminated water resources.
Social assessment clearly defines that no issue of land acquisition and livelihood loss is
foreseen in the project. Hence, no compensation provision is required. However, if any loss
of livelihood is noticed during implementation of this project, then the affected parties will
be compensated according to Environment and Social Management Framework (ESMF)
guidelines set by the NGRBA. Moreover, some inconvenience caused to the local public has
been reported along with the local mitigation plan which they are adopting to overcome any
nuisance in the ongoing JNNURM project. A strong suggestion which was identified from
the consultations was execution of construction work within a scheduled time frame with
provision of prior notice to residents, shop-owners. A public grievance mechanism (as
prescribed by ESMF of NGRBA) is to be followed. There is a clear mention and highlighting
if the social development issues and outcomes in this report. A section chalking out
institutional mechanism, capacity building requirements and monitoring and evaluation
mechanism is also present.
Environmental Management Plan
For all the identified issues a mitigation measure is suggested and if the measure is not
included in the DPR, lumpsum cost estimation has been done and given as EMP cost. The
table below briefly describes the Environment Management Plan.
Phase Component Key temporary Impacts Key Mitigation Measures
Environmental
Design Stage Accidental leakages/ bursts
in sewer
network
Due to accidental burst or
leakage of sewers, flooding of
the nearby areas
Backlogging due to unexpected
heavy flow rates
Designing sewers with adequate
capacity and flow velocity
Provision for Regular inspection
and maintenance of the sewers
Preparation of safety
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
5
and Emergency
Preparedness plan
Construction Phase
Environmental sensitive areas
There are no environmental sensitive areas in the proposed
project area. Further the small
residential parks and road side
trees which will not be affected,
since the sewers are planned to
be laid in the middle of the road and will not pass through
these areas.
-
Air quality
Probable increase in the dust
levels (RSPM and SPM), during
the construction due to
excavation, cutting, back filling and compaction operations.
Water sprinkling over excavated
areas, unpaved movement areas
and stockpiles.
Transportation of loose
construction material through
covered trucks.
Use dust curtains (polysheets/
sheets) around the construction
area for containing dust spread
at SPS building construction site.
Construction equipment must
comply with pollution norms
and carry Pollution Under Control certificate.
Noise levels Increased noise levels due to
construction activities like
plying of construction vehicles,
pumping machines, machinery
and disturbance to residents and business.
Providing curtains or sound
barriers (polysheets/ sheets) all
around the construction site.
Proper maintenance of
construction equipment and vehicles
Water resources
Contamination of nearby water
bodies via storm drains (during
rainfall) by un-managed
construction related material
like suspended particles, pollutants like oil, grease,
cement etc, There may also be
temporary blockage of drains due to unmanaged material
and construction debris.
Suggestion to ensure proper
handling and disposing off
construction wastes at identified
refusal sites.
Proper stock piling of excavated soil and not in any storm drains
or any other areas where water
would naturally accumulate causing flooding.
Temporary flooding due to excavation during monsoons or
blockage of surface drain
Stockpiled areas to be bordered
by berms;
Stockpiles to be done in high areas to avoid flow in storm
water run-off channels and
erosion
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
6
Traffic
Inconvenience
Increased traffic inconvenience
(emissions, congestions, longer
travel times, blockage of access)
Alternate traffic routing must be
adopted in consultation with
concerned traffic police
authorities. Proper traffic
planning be made for narrow
lane areas.
Work should to be completed on
priority near business and
market place to minimize
business loss.
Care should be taken to
minimize congestion and
negative impacts at schools and
hospitals. Safe access shall be
maintained to these places
during construction.
General: safety during
construction
Accidents Safety hazards to labours and public
Comply with the Occupational
health and Safety regulations of
India
Ensure that the contact details of
the police or security company
and ambulance services nearby
to the site.
Ensure that the handling of
equipment and materials is
supervised and adequately
instructed.
Operation Phase
Noise air quality
Water quality
No air and noise problem from sewer line as they will be laid
underground.
Inappropriate handling at IPS
Proper handling and regular maintenance of operating
machines at SPS including
pumps, generators, air diffusers, etc.
Leakage and
overflows in
sewer line
Water pollution and possibility
of mixing with water supply
line
Regular monitoring of sewer line
and manholes for visible
leakages/ overflows.
Immediate repair shall be
carried out to plug the leakages.
Restore the sewer and other utility services if damaged due
to leakages.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
7
Waste handling
in Sewage
Pumping Stations
Bad odour, Health hazard and
public nuisance
Provision for regular clearance
of sludge and solid waste to
minimize odor nuisance
Ensure maintenance of Green
belt as planned
Periodic disposal of
accumulated sludge/solid waste
to disposal site as approved by
DBO engineer.
Sewage
Cleaning
Equipment
Extracted Sewage Sludge
handling and cleaning
equipment maintenance waste
handling
Ensure that extracted sewage
sludge collected during sewers
cleaning is disposed to disposal
site as approved by DBO
engineer.
Sewage solids shall not be
disposed on road sides or non-
designated areas.
Equipment cleaning waste shall
be disposed to public sewer or
STP inlet for treatment
General
Safety Workers
exposure to
toxic gases in
sewers and
hazardous
materials
during
sewer
maintenance work
Serious/health/ safety hazards
The toxic gases are likely to
contract communicable
diseases from exposure to
pathogens present in the
sewage.
During cleaning/ maintenance
operation, the sewer line will be
adequately vented to ensure that
no toxic or hazardous gases are
present in the line.
Ensure availability of PPE for
maintenance workers.
Social
Construction Livelihood No impact, as there will be no
impact on livelihood of any
permanent shop-owners, licensed kiosks
But suggested if noticed during
construction, then should be
compensated according to ESMF
Land
acquisition
No impact, as no fresh land is
required for any construction
-
Inconvenience
to public
There will be some minor
inconveniences to the public
due to construction like access to their premises, etc.
Public notice to be circulated,
construction should be
completed in the given time, debris should be cleared in time
Health issues-due to dust,
noise pollution
During construction dust and noise generated, can cause
nuisance to people especially
elderly and children, but
impact is very limited.
Use of acoustics and water sprinkling
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
8
These temporary impacts can be mitigated with appropriate mitigation plans, which have
been suggested as well, along with monitoring and evaluation of future projects. In order to
implement the Environmental Management and Monitoring an approximate budget of Rs.
90 Lakhs has been estimated and this is also integrated in the DPR cost.
Social Management Plan
Implementation of EMP: In general, the Uttar Pradesh Jal Nigam (UPJN) (with assistance
from Contractor and Independent Engineer/Supervision Consultant) is the responsible
entity for ensuring that the mitigation measures as suggested in the ESAMP are carried out.
Though the project envisages to have some environmental and social impacts, however they
are temporary in nature can be mitigated with the implementation of the EMP and Social
management plan designed for the project along with effective monitoring of the
implementation. The larger environmental value of the project greatly outweighs these
impacts. The project is expected to benefit the Allahabad City, as the wastewater that
currently flows untreated into the Ganga river will be captured, treated and the remainder
of the treated effluent will be allowed to flow into the river.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
9
Chapter 1 Introduction The river Ganga has significant economic, environmental and cultural value in India. Rising
in the Himalayas and flowing in to the Bay of Bengal, the river traverses a course of more
than 2,500 km through the plains of north and eastern India. The Ganga main stem accounts
for 26 per cent of India’s landmass, 30 per cent of its water resources and more than 40 per
cent of its population. The Ganga also serves as one of India’s holiest rivers whose cultural
and spiritual significance transcends the boundaries of the basin.
Despite its importance, extreme pollution pressures from increasing population and
industrialization pose a great threat to the biodiversity and environmental sustainability of
the Ganga, with detrimental effects on both the quantity and quality of its flows. Discharge
of untreated sewage and industrial wastewater, non-point pollution sources from religious
activities along the river, agricultural run off as well as poor municipal solid waste
management is the main causes of pollution in river Ganga.
1.1 Ganga Clean up Initiatives
The Government of India (GoI) has undertaken clean-up initiatives in the past. The most
prominent of such efforts was the Ganga Action Plan, launched in 1985 later complemented
by a similar plan for the river Yamuna, the biggest tributary of the Ganga. These
programmes have faced significant public scrutiny and, despite some gains made in slowing
the rate of water quality degradation, they have been widely perceived as failure. The main
shortcomings of these initiatives were: (1) inadequate attention to institutional dimensions,
including the absence of a long-tem-basin planning and implementation framework; (2) little
effort made in addressing weakness in water , urban wastewater and , municipal solid
waste management, environmental quality monitoring and reporting, regulatory
interventions (3) inadequate planning, scale, coordination and prioritization of investments,
with little emphasis on ensuring their sustainability. These programs also did not pay
sufficient attention to the social dimensions of river clean-up, failing to recognize the
importance of public consultation, participation and awareness-raising.
The lessons drawn from these prior experiences indicate that improving water quality in the
Ganga cannot be achieved by plugging the infrastructure gap alone. Rather, any effective
initiative will have to adopt a three-pronged approach:
• Establishing a basin-level, multi-sectoral framework for addressing pollution in the
river (including national/state policies and river basin management institutions);
• Making relevant institutions operational and effective (e.g. with the capacity to plan,
implement and manage investments and enforce regulations); and,
• Implementing a phased program of prioritized infrastructure investments (with
emphasis on sustainable operations and community support)
1.2 The Ganga River Basin Project
As a major first step in achieving objective of cleaning river Ganga, the Government of India
(GoI) constituted the National Ganga River Basin Authority (NGRBA), on 20th February
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
10
2009, for the comprehensive management of the river. The NGRBA is entrusted to adopt a
river-basin approach and has been given wider mandate to meet above objective. The
NGRBA has resolved that by year 2020, no untreated municipal sewage or industrial
effluents will be allowed to be discharged into River Ganga within Indian Territory.
Considering the requirement of large investment to meet above objective, The World Bank
has been formally requested to provide long-term support to NGRBA, through several
phases of substantive financing and knowledge support. While, the overall technical
assistance and program development under the proposed initiatives will focus on the entire
Ganga, the initial emphasis of the specific investments will be on the main stem of river
Ganga flowing through five basin states of Bihar, Jharkhand, Uttar Pradesh, Uttarakhand
and West Bengal. The priority is given to pollution abatement programs in cities located on
the banks of these States which would include investment for planning and construction of
city sewerage network and sewage treatment plants, industrial pollution control measures,
municipal solid waste and river front management.. This is expected to be achieved through
several phases of substantive financing and knowledge support. The first project of such
several phases of support aims at;
• Establishing and operationalizing central and state level NGRBA institutions capable
of planning and implementing a multi sectoral river water quality improvement
program and;
• Reducing pollution loads into the river through selected investments.
1.2.1 World Bank Assistance
The Government of India is implementing program with the assistance from the World Bank
to support the NGRBA in the long term. This assistance aims to support the NGRBA in
establishing its operational-level institutions and implementing priority infrastructure
investments.
1.3 Project Components
The project will have two components relating to institutional development and priority
infrastructure investments. The first component would seek to build the institutional
capacity to effectively implement the overall NGRBA program, including infrastructure
investments funded by the second component.
1.3.1 Component One: Institutional Development
1.3.1.1 Objective
The objectives of this component are to: (i) build functional capacity of the NGRBA’s
operational institutions at both the central and state levels; and (ii) provide support to
associated institutions for implementing the NGRBA program. The activities financed under
this component are grouped under the following sub-components:
• Sub-component A: NGRBA Operationalization and Program Management
• Sub-component B: Technical Assistance for ULB Service Providers
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
11
• Sub-component C: Technical Assistance for Environmental Regulators
1.3.2 Component Two: Priority Infrastructure Investments
1.3.2.1 Objective
The objective of this component is to finance demonstrative infrastructure investments to
reduce pollution loads in priority locations on the river.
1.3.2.2 Investment Sectors
The majority of investments are expected to be in following four sectors:
I. the wastewater sector, particularly in wastewater treatment plants and sewerage
networks.
II. industrial pollution control and prevention (e.g. construction of common effluent
treatment plants),
III. solid waste management (collection, transport and disposal systems for municipal
waste ),
IV. river front management (e.g. improvement of the built environment along river
stretches, improvement of small ghats and electric crematoria, conservation and
preservation of ecologically sensitive sites).
Many investments are likely to combine elements of more than one of above sectors.
1.3.2.3 The Framework Approach
In lieu of defining and appraising specific investments, the project preparation has focused
on developing investments framework covering all four key sectors of intervention under
the NGRBA program. This single framework will apply to all investments under the
NGRBA program.
The objectives of the investments framework are to:
a) provide a filter for all the NGRBA investments, for ensuring that the selected
investments are well-prepared and amongst the most effective in reducing the
pollution loads;
b) make transparent the decision-making process on investments selection; and
c) ensure that the investments are implemented in a sustainable manner
The investments framework prescribes the criteria and quality assurance standards covering
various aspects including eligibility, prioritization, planning, technical preparation, financial
and economic analyses, environmental and social management, long term O&M
sustainability, community participation, and local institutional capacity1.
1 For more details refer “Environmental and Social Management Framework for World Bank Assisted National
Ganga River Basin Project, 2011”. PMG, National Ganga River Basin Authority, MoEF.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
12
1.3.2.4 Investment Execution
The investments program will be planned and managed by the NGRBA level PMG and
state level PMGs, while the execution of specific infrastructure investments will be done by
the selected existing and qualified state-level technical agencies. To foster competition and
tap private sector efficiencies, the state governments with significant infrastructure
investments are also setting up a public-private joint venture infrastructure company, to
execute NGRBA and other similar investments in the respective states in the medium to long
term.
1.3.2.5 Rehabilitation of existing infrastructure
Investments involving rehabilitation of existing infrastructure will be given priority due to
their intrinsically higher returns in terms of reductions in pollution loads entering the
Ganga.
1.4 Structure of the Report
The Detailed project Report is prepared by UPJN. TERI has worked closely with them while
carrying out environmental and social assessment. This report deals with the Environment
and Social Assessment with Management Plan for the Sewerage works in Sewerage District
‘A’ of Allahabad, Uttar Pradesh. It provides baseline status of the existing sewage
management and expected situation post implementation of the proposed project with
associated environmental and social impacts. The Environmental and Social management
plan prepared for mitigating these associated impacts, as per the Environment and Social
Management Framework is also included in this report. The ESAMP report is presented in
in following 9 chapters:
Chapter 1: Provides an introduction about the programme to clean up River Ganga and
various mechanisms to implement the project. This chapter details out the functionalities of
the institutions involved in the project.
Chapter 2: Provides project description pertaining to the proposed sewerage project in
District A of Allahabad.
Chapter 3: Details out the methodology adopted for the environmental and social
assessment.
Chapter 4: Presents the applicable laws and guidelines related to such kind of projects.
Chapter 5: Presents detailed baseline scenario based on information available for city and for
sewerage district A from environmental and social aspects.
Chapter 6: Provides assessment of environmental and social impacts.
Chapter 7: Presents proposed mitigative measures for identified impacts.
Chapter 8: Present social development outcomes of the proposed project and related issues.
Chapter 9: Presents conclusions of the study, which also concludes that it is low impact
project.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
13
Chapter 2 Project Description
2.1 About the City
Allahabad city lies on the 25°28’ North latitude and 81° 52’ East longitude. Main land of the
city is surrounded by river Ganga and Yamuna in three directions i.e. North, South and east
direction. The river Ganga flows on the north and east boundary of the old city while river
Yamuna flows on south boundary of old city as shown in the Figure 2.1. Allahabad is among
the largest cities in Uttar Pradesh. The city is situated at the auspicious confluence (Sangam)
of three holy rivers 'Ganga', 'Yamuna' and the river of enlightenment, the mythical
'Saraswati'. There are very few places parallel to Allahabad not only in India but also around
the world, which is described in ancient scriptures as Prayag -Prayagraj or Teerthraaj (the
holiest pilgrimage centre). With the additional magnetism of Maha Kumbh Mela, hailed as
the world's largest congregation of devotees, attended by millions of pilgrims, its
importance can hardly be over emphasized.
Plate 2.1 Anand Bhawan- house of Jawaharlal Nehru’s Family (left) and night view of
New Yamuna bridge (right)2
2.2 Existing Sewerage Facilities in Allahabad City
The Sewerage system in the Allahabad city was first introduced in the year 1910. The facility
was subsequently extended in a number of developing areas according to the need and
financial position of the local body. The collection system covers about 45% of the city area
and most of this is within the central core of the city. The total amount of wastewater
measured in drains and at the STPs in the year 2000 was about 210 mld of which 89 mld was
diverted into the sewer collection system. The wastewater flowing into the SPS (Sewage
Pumping Station) is greater than the existing treatment capacity of STP, leading to overflow
of untreated wastewater into the river as shown in Plate 2.2. Further the existing sewers
have outlived their design life and suffer from insufficient hydraulic capabilities, heavy silt
deposition, severe choking due to ingress of solid waste and poor structural conditions in
most of the stretches.
2 Allahabad district government website, <http://allahabad.nic.in/PictureGallery.htm>
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
14
Presently there are 57 drains/ nalas which discharge into the rivers Ganga & Yamuna at
Allahabad. Out of 57 drains, 2 drains fall in the cantonment area under the control of the
defense ministry. Out of remaining 55 polluting drains, 7 major drains have been intercepted
under Ganga Action Plan Phase I (GAP - I), 2 drains have been tapped under Ganga Action
Plan Phase II (GAP - II), further 16 drains will be tapped under the ongoing scheme under
JNNURM, 10 drains are proposed to be tapped under a scheme pending for approval and
new DPR’s are under preparation for tapping of the remaining 20 drains. UPJN (Uttar
Pradesh Jal Nigam) is responsible for pollution prevention and planning capital projects for
sewerage. UPJN also operates and maintains large pumping stations and the treatment
plant. Jal Sansthan is responsible for maintenance of trunk sewers, lateral sewers and
collection of revenue from house connections. The brief details about the completed/ on-
going/ approved sewerage projects in Allahabad city are described below.
Plate 2.2 Chanchar Nala (left) and Wastewater discharged behind the house (right)
2.2.1 Works Completed under Ganga Action Plan Phase – I (GAP-I)
With the objective of abatement of pollution to improve the river water quality and to
reduce the environmental degradation, Ganga Action Plan was launched in 1985 by the
Ministry of Environment & Forests, Government of India. The main focus of the Plan was on
Interception & Diversion and treatment of sewage through 261 schemes spread over 25
Class I towns of U.P., Bihar and West Bengal. Nearly 34 Sewage Treatment Plants (STPs)
with a treatment capacity of 869 mld have been set up under the Plan, which was completed
in March 2000 at a cost of Rs. 452 crores. The Schemes completed under GAP-I in the district
of Allahabad city are summarized below:
• Renovation of Gaughat Main Sewage Pumping Station
• Renovation of Intermediate Sewage Pumping Stations
• Relieving sewer in Kydganj area
• Daraganj sewer and Sewage Pumping Station
• Relieving sewer in Daraganj area
• Tapping of Mumfordganj nala
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
15
• Tapping of Chachar nala
• Partial tapping of Ghaghar nala
• 60 mld sewage treatment works at Naini based on Activated Sludge Process
2.2.2 Works Completed under Ganga Action Plan Phase II
In continuation with the pollution abatement programme, Ganga Action Plan-II was started
in 1993, which planned to cover 59 towns located along the river in the five states of
Uttarakhand, U.P, Jharkhand, Bihar and West-Bengal. Nearly 319 schemes have been taken
up under the plan, out of which 200 have been completed. An expenditure of Rs. 370.40
crore has been incurred so far creating sewage treatment capacity of 130 mld. Later in 1996,
this plan was expanded into the National River Conservation Plan (NRCP), which presently
covers polluted stretches of 36 rivers in 20 States in the country. The Schemes completed
under GAP-I in the district of Allahabad are summarized below:
• Renovation/ Rehabilitation of Chachar nala SPS
• Tapping Salori nala and Construction of Sewage pumping station
• 29 mld Salori STP with land acquisition
• Construction of Morigate Sewage Pumping Station
2.2.3 On-going works in Sewerage District ‘D’ Under JNNURM
In order to encourage the cities in taking up the initiative steps to bring about improvement
in the existing service levels in a financially sustainable manner, Jawaharlal Nehru National
Urban Renewal Mission (JnNURM) was launched in December 2005 by the Government of
India. The primary objective of the JnNURM is to create economically productive, efficient,
equitable and responsive cities. With reference to Allahabad city, the under mentioned
works have been approved by the Central Sanctioning & Monitoring Committee (CSMC) of
the Ministry of Urban Development Govt. of India in 2009. Completion period of the
approved works is 3 years.
• Construction of new Trunk Sewer 7.20 Km
• Replacement of old Trunk Sewer 3.800 Km
• Lateral & Branch sewers 225.000 Km
• Desilting and Rehabilitation of existing old Trunk Sewer 5.474 Km
• Renovation & Upgradation of Alopibagh SPS and its rising main
• Renovation & Upgradation of Morigate SPS and its rising main
• Renovation & Upgradation of Allahpur SPS
• Renovation & Upgradation of Daraganj SPS
• 55 mld Capacity MPS and its rising main at Mumfordganj
• 25 mld Capacity MPS and its rising main at Rajapur
• 60 mld Sewage Treatment Plant at Rajapur
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
16
2.2.4 City Sewerage Plan
As per the recent master plan of city development, Allahabad city has been divided into
seven sewerage districts A-G as shown in Figure 2.1. The District wise (A to G)
arrangements and status of sewage treatment in Allahabad is given in Table 2.1.
• District A: District ‘A’ covers central core conveying sewage to existing Gaughat MPS
and Naini STP. This area includes the old city core with an old sewerage network
dating back to as early as 1910. Wastewater from this area is collected at Gaughat
MPS and pumped through existing rising mains across the Yamuna railway bridge
to Naini STP. Defined under the previous master plan as Zone I, the sewerage
network has been reconfigured under this Master Plan to provide a smaller
catchment area that will not exceed the maximum capacity of Gaughat MPS and
Naini STP (ultimate design capacity of 80 mld with expansion). Population densities
in this area are generally greater than 300 persons per hectare and water distribution
sufficiently good to support full coverage with sewerage. Wastewater that does not
enter the sewer system finds its way to Chachar nala, Ghaghar nala and many
smaller tributary drains. Chachar nala flow is at present tapped and pumped to
Gaughat MPS.
• District B: From Lukerganj SPS to Ghaghar nala SPS, conveying sewage upstream of
Yamuna River to Numaya Dahi STP. This district is located to the west of district A
from Ghaghar nala to Sasur Khaderi river.
• District C: Area north of cantonment conveying sewage to sanctioned Salori STP.
Wastewater from Allapur area has been reassigned to the Salori STP catchment since
crossing the bridge to Phaphamau as previously proposed was not possible. At
present the area has no sewers and waste water flow through the Salori, Allenganj
and Buxibund nala which are intercepted and diverted to 29 mld capacity Salori STP
constructed under GAP II.
• District D: Alopibagh SPS area will convey sewage to proposed Rajapur STP. This
zone is experiencing rapid growth and projected populations indicate that densities
will be much greater than 300 persons per hectare before 2025.
• District E: West Allahabad conveying sewage to Kodara STP and Ponghat STP in
Sulem Sarai area. This district is divided into three nala catchments, namely Ponghat
nala to the west, Kodara nala (central), and Nehru Park nala to the east.
• District F: Phaphamau area conveying sewage to Phaphamau STP. At present the
area has no sewers but in future sewers will be laid as per requirement.
• District G: South of Yamuna river conveying sewage to proposed Mawaiya STP.
Proposed sewerage District G is largely un-sewered at present.
In addition to the seven sewerage districts, the Master Plan has identified two future service
areas (FSA) which are outside the municipal limits but have or will have, within the design
horizon, a population density of more than 120 person / ha. Hence, the sewerage system
needs to be extended to FSAs in the future.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
17
Table 2.1 District wise (A to G) arrangements and status of Sewage Treatment in Allahabad*
Sewer
Service
Areas
Population
in 2001
Projected Population Projected Sewage Flow
in MLD
2010 2025 2040 2010 2025 2040
District
A*
304643 405176 479731 515155 62.80 74.36 79.35
District B 160416 179826 279169 343674 27.87 43.27 53.27
District C 147126 198473 267180 323679 30.76 41.41 50.17
District D 225846 314514 361352 496859 48.75 56.01 77.01
District E 164672 177845 223789 322577 27.57 34.69 50.00
District F 29628 36000 65196 129500 5.58 10.11 20.07
District G 160000 185121 232280 418000 28.69 36.00 64.79
Total 1192331 1496955 1908697 2549444 232.03 295.85 395.16
Source: Detailed Project Report (revised as per ECC Recommendations) of Sewerage Works
in Sewerage District ‘A’ by U P Jal Nigam, 2010-11
*Population figures include daily floating population but do not include population of Kumb Mela.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
18
Figure 2.1 City sewerage Plan of Allahabad city Source: City Development Plan, Allahabad Nagar Niga
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
19
2.2.5 Works Approved Under NGRBA for District A
To ensure effective abatement of pollution and conservation of the river Ganga, keeping
with sustainable development needs, the Government of India (GoI) constituted the
National Ganga River Basin Authority (NGRBA), on 20th February 2009. The prime
objectives of the NGRBA program are to finance infrastructure investments to reduce
pollution loads at priority locations on the river Ganga. The investments are intended to
exemplify, among other attributes, the high standards of technical preparation and
implementation, sustainability of operations, and public participation. With reference to
Allahabad city, DPRs amounting to Rs. 305.34 Crore, has been approved under the National
Ganga River Basin Authority (NGRBA), Ministry of Environment & Forest Govt. of India.
Following sewerage works are going on in sewerage District A under the “Sewerage & Non
sewerage Scheme for Pollution abatement of river Ganga at Allahabad”. This scheme,
amounting to Rs. 305.34 Cr was approved by the NRCD, MoEF, Govt. of India in May 2010.
1. Sewer Laying works
i On MG Marg from High Court to Rambag Railway crossing – 3.80 km
ii. On Attersuiya road, Meerapur, Hatia etc. 5.40 km
2. De-silting & Re-habitation of old trunk sewer
3. Renovation & Up-gradation of Chachar Nala Sewage Pumping Station.
4. Renovation & Up-gradation of Gaughat Sewage Pumping Station.
5. Up-gradation of Naini STP by 20 mld.
The proposed work in District A has following major components:
• Approximately 240.627 km long sewerage network
• Intermediate Sewage Pumping Stations at Bairahana, Kydganj (Gate No.9),
Bargadghat SPS
• Sewer cleaning equipment
2.3 Necessity of this project
NGRBA is the authority working under the nodal Ministry of Environment and Forest
(MoEF). NGRBA has formulated a mission named “Mission Clean Ganga” for preventing,
controlling and effective abatement of pollution happening for river Ganga and is taking
measures for controlling pollution. Under the ‘Mission Clean Ganga’, no untreated
municipal sewage or industrial effluent would be allowed to be discharged into the river
Ganga by the year 2020.
Allahabad city is part of Ganga River Basins and sewerage system does not exist in many
part of the city. At present there is no sewage collection system in many parts of sewerage
District A and existing sewerage system is not capable to tackle the present sewage
generation. Most of the houses have individual soak pits for collecting sewage and sullage is
discharged in open drains which ultimately meets Yamuna River which finally meets the
river Ganga in the downstream side called holy Sangam. Soak pits are required to be
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
20
cleaned periodically. People living in this area are facing problem of odour and nuisance
and leading to unhygienic condition and health concerns.
With a view to Mission Clean Ganga objective of NGRBA, it is proposed to provide
sewerage system of laterals, branches and trunk sewers in Sewerage District –A. . By this
system entire sewage of this sewerage district A will be collected in integrated manner and
brought it up to Gaughat SPS from where it will be diverted to Naini STP for treatment
before discharging into Yamuna River. It will improve sanitation level and prevention of
untreated discharge of sewage into river Yamuna and finally in Ganga River. The expected
sewage generation by 2025 based on project population given at Table 2.1 is given at Table
2.2.
Table 2.2 Sewage Flow Generation (Capacities in MLD)
District
Existing
STP
Capacity
(MLD)
Required
STP in
2025
(MLD)
Required
in 2040
(MLD)
Total STP
Capacity by
2040 (MLD)
Proposed Capacity
for Sub-project
(MLD)
District A 60.00 74.36 79.85 80 20
**DPRs approved
Source: Detailed Project Report of Sewerage Works in Sewerage District ‘A’ by U P Jal Nigam, 2013
• The state of existing sewers is summarized below:
• Most of the existing sewers are old brick sewers which have outlived their design life
• The structural condition of sewers in most stretches is poor
• Hydraulic capacities are insufficient even for the present flows
• All existing lines have heavy silt deposition
• Sewers are severely choked due to ingress of solid waste
• All lines have large variations in constructed slopes
• Wastewater from this area is collected at Gaughat MPS and pumped through
existing rising mains across the Yamuna railway bridge to Naini STP. The existing
capacity of Gaughat MPS does not get fully utilized because of extensive daily power
cuts. MPS has a single supply source and often the diesel is inadequate to operate the
pumps during long power cuts. MPS is also facing problems due to the large load of
solid waste being carried in with the wastewater. The wastewater flowing into the
MPS is greater than the treatment capacity at Naini STP and hence, large amounts
simply overflow untreated into Yamuna River.
• Defined under the previous master plan as Zone I, the sewerage network has been
reconfigured under this Master Plan to provide a smaller catchment area that will not
exceed the maximum capacity of Gaughat MPS and Naini STP (ultimate design
capacity of 80 mld with expansion). The sewer connection ratio in the district is
around 45%. Wastewater that does not enter the sewer system finds its way to
Chachar nala, Ghaghar nala and many smaller tributary drains. Chachar nala flow is
at present tapped and pumped to Gaughat MPS.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
21
Considering the existing situation, completed and ongoing works the proposed works is
essential to meet the objective of cleaning Ganga.
2.4 Location of Proposed Sewerage Project
Sewerage District A of the City of Allahabad covers central core and conveys sewage to
existing Gaughat Main Pumping Station (MPS) and Naini Sewage Treatment Plant (STP)
(refer figure 2.1). This area includes the old city core with an old sewerage network dating
back to as early as 1910. There are totally 27 wards falling under this project area, having a
total population of 405176 as of 20103. The area is mostly residential with some main
markets, institutes and hospitals.
3 Detailed Project Report (revised as per ECC Recommendations) of Sewerage Works in Sewerage District ‘A’ by
U P Jal Nigam, 2010-11
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
22
Figure 2.2 Location of Sewerage District ‘A’ in Allahabad City, Uttar Pradesh.
Source: City Development Plan, Allahabad Nagar Nigam
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
23
2.5 Proposed Sewerage System
The proposed sub-project aims to provide complete sewerage facilities in the
sewerage district ‘A’ of the Allahabad city. The sub-projects covered under this
present sewage projects of district A includes:
• Approximately 240.6227km long sewerage network
• Intermediate Sewage Pumping Stations at Bairahana, Kydganj (Gate No.9),
Bargadghat SPS
• Sewer cleaning equipment
2.5.1 Components of Proposed Sewerage Work
Comprehensive sewerage network is proposed for sewerage district ‘A’ to cover the
remaining area with sewerage system, so that sewage flows can be collected in an
integrated manner and conveyed to STP for treatment before discharge into Ganga
river via Nallah. The proposed sewerage system is designed for 30 years period with
design year 2050. The 240 km stretch will be divided into 3 zones of approximately
80 Kms each.
A. Sewer System
i. Sewer Pipes: It is proposed to lay 240 km long sewer network in sewerage
district A of the city. In proposed system, laterals are proposed along the
roads to connect sewage from individual houses and it is connected to branch
sewers. Branch sewers are joined to trunk sewers and finally to trunk main.
The proposed sewers are of RCC pipes (Class NP3) for all the diameters. The
provision is also made for HDPE pipes for 200 & 250 mm dia. in the
congested and narrow lanes to speed up the construction work at site. The
table below presents the size and length of the proposed sewers in the 3 zones
of District A.
Size/ Dia in mm Zone wise Length (m) Total
Length
(m) Zone I Zone II Zone III
200 77132.5 75151.9 63495 215779.4
250 2015.8 2640.2 1149.1 5805.1
300 921.6 2465.5 1011.1 4398.2
350 894.2 1106.2 1090.1 3090.5
400 1271.1 736 411.5 2418.6
500 2631.3 2315.1 1115.5 6061.9
600 158.2 703 406.8 1268
700 0 0 712 712
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
24
ii. Manholes: The ordinary circular manholes of brick masonry are proposed at
all the junctions, change of diameters, and change in pipe gradients and on
straight run of sewer at 30m interval for dia. upto 900mm. Drop manholes are
proposed where the difference between invert level of lateral / branch sewer
and maximum water level (at design peak flows) of main sewer is more than
600mm. RCC precast manholes (for depth upto 2m) are considered in
congested areas with narrow roads for speedy construction.
iii. House connection: The sewer house connections are progressive work and
expected to be achieved more than 95% by year 2020 House connections are
proposed along with sewerage system. Single and multiple connections are
proposed. 100% house connections are proposed for District A since these
areas are mostly un-sewered. Sewer connection ratio of more than 95% is
proposed to be achieved by year 2020.
B. Intermediate Sewage Pumping Stations
i) Proposed New Bairahana SPS of 22.00 MLD capacity
The proposed SPS in New Bairahana area in the sewerage network of Allahabad,
District A Zone I is designed to pump the sewage of Zone I to manhole no. M2-6942.
From where it will be conveyed by gravity to downstream network which will be
ultimately collected at Gaughat SPS from where it will be pumped to Naini STP for
treatment.
ii) Proposed Kydganj SPS of 12 MLD capacity
The proposed SPS in Kydganj area along bank or Yamuna river in the sewerage
network of Allahabad, District A Zone II is designed to pump the sewage to manhole
no. M2-66500. From where it will be conveyed by gravity to downstream network
which will be ultimately collected at Gaughat SPS from where it will be pumped to
Naini STP for treatment.
iii) Proposed Bargadghat SPS of 60 MLD capacity
The proposed SPS at Bargad Ghat on the bank of river Yamuna in the sewerage
network of Allahabad, District A Zone II is designed to pump the sewage to manhole
no. M2-5194. From where it will be conveyed by gravity to downstream network
which will be ultimately collected at Gaughat SPS from where it will be pumped to
Naini STP for treatment.
800 0 142.4 797.8 940.2
900 0 0 153.2 153.2
Total Length 85024.7 85260.3 70342.1 240627.1
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
25
C. Sewer Cleaning Equipment
For proper maintenance of the sewerage system, provision has been made for one no.
Jetting cum suction machine, one no. tractor trolley, mounted tanker and one no.
submersible dredger pump.
2.5.2 Implementation Schedule
It is anticipated that entire work will be completed within 36 months from the date of
approval and allotment of funds.
2.5.3 Financing
Detailed Project Report of Sewerage Works in Sewerage District ‘A’ by U P Jal
Nigam, 2013 under National Ganga River Basin Authority (NGRBA) programme
amounting to Rs. 288.94 Crores.
Under the National River Conservation Plan (NRCP), the Central Government will
provide financial assistance of 70% of the total project cost. The remaining 30% of the
project cost will be borne by the State Government of UP and the ULB/ Allahabad
Municipal Corporation. The share of the Central Government shall accordingly be
Rs. 202.26crore. Balance amount of Rs. 86.68crore will be shared by the Govt. of UP.
The State Government has given its commitment to bear their share of the cost and
accordingly tripartite MoA has been executed in between NMCG, State Government
and Allahabad Municipal Corporation.
ABSTRACT COST ESTIMATION (Rs. In Lakhs)
Sl.No Description Estimated Cost (Rs. In Lakhs)
Civil
Work
E/ M
Works
Total
A Sewerage work in Zone I
1 Sewer Laying by Open Excavation method 7357.92 0 7357.92
2 New Bairahana SPS 332.41 450.11 782.52
3 Rising Main 36 36
4 Kydganj (Gate No.9) SPS 397.51 401.17 798.68 5 Rising Main 120 120
Sub Total (Zone I) of A 8243.84 851.28 9095.12
B Sewerage work in Zone II 1 Sewer Laying by Open Excavation method 7053.58 0 7053.58
2 Bargadghat SPS 394.3 518 912.3
3 Rising Main 379 0 379 Sub Total (Zone II) of B 7826.88 518 8344.88
C Sewerage work in Zone III
1 Sewer Laying by Open Excavation method 5297.61 0 5297.61 2 Sewer Laying by Trenchless method 908.67 0 908.67
3 Desilting& CIPP lining 816.81 0 816.81
Sub Total (Zone III) of C 7023.09 7023.09
D Communication & Public Outreach 105 0 105
E GAAP 30 0 30
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
26
F ESAMP 90 0 90
G Total of (A+B+C+D+E+F) 23318.81 1369.28 24688.09
H Centage charges of (G)
1 Cost of Project preparation @ 4% (maximum) 987.52
2 Cost of supervision of project @ 4% as per
NGRBA PROGRAMME guidelines (maximum)
987.52
I Sub Total of H 1975.05
J Provision for sewer cleaning equipment’s 112.22 112.22 K Five Years O & M Cost 2119.35
L Sub Total of (J+K) 2231.57
Total cost (G+I+L) 28894.71 Total cost in crore 288.94 Cr
.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
27
Chapter 3 Approach and Methodology
3.1 Methodology
As per Environmental and Social Management Frame work (NGRBA, 2011)4, and
considering associated environmental and social impacts, an environmental and
social assessment with corresponding management plans for the proposed project of
sewerage works in sewerage district ‘A’ of Allahabad City has been conducted using
the following methodology:
Figure 3.1 Flowchart describing the steps adopted for Project Impact Assessment
a) Secondary Data analysis (Identify Information/Data Requirements and their
Sources): All the available information and data (quantitative, qualitative)
regarding the proposed project was collected mainly from the Detailed
Project Report (DPR), consultation with stake-holders and other secondary
sources including the water/air/noise monitoring reports of UP Pollution
Board, Water Quality Management Plan of Ganga River Report of JICA and
NRCD, City Development Plan of Allahabad and many others. Through this
secondary information a brief description and analysis of the sub-project
activities along with baseline environmental profile of the project influence
was established. Based on initial understanding, the list of required
information was drafted before conducting the field survey.
4 For more details refer “Environmental and Social Management Framework for World Bank Assisted
National Ganga River Basin Project, 2011”. PMG, National Ganga River Basin Authority, MoEF.
Developing mitigation plan
Identification and assessment of
environmental/ social impacts
Screening activity
Secondary data analysis Field survey and stake-
holder consultation
Brief description & analysis of
the sub project activities
Detailed environmental profile of the
project influence area
Discussion with host population
and key stake-holders
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
28
b) Defining the project area and carrying out scoping in the field: Team undertook the
field survey and transect walk of the sewerage district ‘A’ area to develop the
understanding of the proposed project (refer Plate 3.1, 3.2). GPS surveying of
the study area was also conducted for mapping the social and environmental
issue. Field visits helped to understand the local knowledge and were
valuable in finding alternatives that help avoid or at least reduce the
magnitude and severity of adverse impacts.
Plate 3.1 Consultation with ambulatory vendors
c) Survey of the host population: With the help of questionnaires, local people were
interviewed in groups. A wide range of potentially affected people were
interviewed in District A including street vendors, residents of households,
residents of temporary settlements, shop keepers, hospital patients, hospital
staff, etc. Both men and women were interviewed from different sections of
the society. Team undertook three field visits to carry out the survey and
understand the ground situation. The interviewees were asked about their
awareness of the project, their response to it and if the project is affecting
them (during construction phase) and how it will affect them (after
completion phase). Also they were asked about the mitigation plans they
have adopted or are planning to adopt, suggestions for improvement and any
public grievances. Surveys were conducted along the path of construction
site. Questionnaire used for the survey is attached as Annexure (1).
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
29
Plate 3.2 Consultation with local community
d) Discussion with the key stakeholders: Most of the interactions with important
key stakeholders were through both informal and formal discussions with
them. All the associated government departments were visited to collect the
relevant data and their feedback on the project activities. Minutes of meeting
for all these discussions are attached as Annexure (2).
e) Conduct Screening: Screening is undertaken in the very beginning stages of
project development. The purpose of screening is to screen out “no significant
impacts” from those with significant impacts and get a broad picture of the
nature, scale and magnitude of the issues. Team conducted screening process
using the screening checklist format provided in ESMF report of NGRBA,
which is described in subsequent section.
f) Identify and assess the impacts: Based on the analysis of the data gathered from
field survey, stakeholder interaction/ consultation and secondary sources,
issues related to the environmental and social sectors were been identified.
The impacts so identified were compared with the existing baseline
environmental and social condition of the study region. The impacts of the
activities are mostly positive with few adverse impacts.
g) Develop a mitigation plan: Based on the environmental and social issues
identified, measures needed to prevent, minimize, mitigate, or compensate
for adverse impacts and improve environmental performance were
recommended. The mitigation plans is suggested in all three stages:
designing phase, construction phase and, operation and maintenance phase.
3.2 Project Screening
The project screening was carried out to understand the nature, scale and magnitude
of environmental and social issues associated with the project. The screening activity
was conducted as per the guidelines provided in Environmental and Social
Management Framework of NGRBA (NGRBA, 2011)5 and on the secondary data
5 For more details refer “Environmental and Social Management Framework for World Bank Assisted
National Ganga River Basin Project, 2011”. PMG, National Ganga River Basin Authority, MoEF.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
30
analysis, field assessments and stakeholder interaction/ consultation. The detail of
screening is summarized in the Table 3.1 below.
Table 3.1 Environment and Social information format for screening
Environment and Social information format for screening
Project Title: Sewerage Works in Sewerage District ‘A’ in Allahabad City of Uttar
Pradesh Implementing agency: Ganga Pollution Control Unit, Allahabad
Project cost: Rs 25108.87 Lakhs
Project components: a). Sewer System (~240 km long)
b). 3 Intermediate Sewage Pumping Station
c). Sewer Cleaning Equipment
Project location (Area/ district): Sewerage District A in Allahabad
District A covers central core conveying sewage to existing Gaughat MPS AND Naini
STP. This area includes the old city core with an old sewerage network dating back to
as early as 1910. Wastewater from this area is collected at Gaughat MPS and pumped through existing rising mains across the Yamuna railway bridge to Naini STP.
Screening Criteria Assessment
of category
Explanatory note for
categorization
Evidence and
references
1 Is the project in an
eco-sensitive area or adjoining an eco-
sensitive area?
(Yes/No) If Yes, which is the area?
Elaborate impact
accordingly.
No There are no eco-
sensitive areas such as water bodies, or
protected forested
areas surrounding the project.
The only ASI
monument located in
sewerage district A
namely Kydganj
Cemetery will not be impacted as
proposed sewage line
passes more than 200
m away from the
cemetery.
Figure 5.8: Map
showing the Eco-sensitive areas closest
to Allahabad District
A.
Field visits, secondary
information and
interaction with U.P.
Jal Nigam, ASI official and other
Government officials.
2
Will the project create significant/limited/no social impacts?
2.1 Land acquisition resulting in loss of
income from
agricultural land, plantation or other
existing land-use.
No social impacts
No Land acquisition involved
As per the first hand
observation in the field and through
interviews of key
Figure 5.10: indicating that the sewer line
will pass through the
residential colonies, commercial areas of
the district and would
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
31
stakeholders,
residents, local people,
and other sources like DPR, CRR, it is clear
that no private land
would be acquired for
either laying of sewer
network or for SPS.
Sewer line would be
laid on the public
roads.
So there is no loss of
income from
agricultural land. Moreover there are no
agricultural fields in
the district. Also there exist no
squatters or
encroachers in and around the proposed
project areas.
not enter or pass
through agricultural
fields.
Field visits,
consultation with
stakeholders, like
local people (for
JNNURM projects), local residents,
government officials.
2.2 Loss of livelihood No Loss of livelihood would not take place
and since mobile
vendors can shift their
position only minor
disruption in terms of
access to shops would occur.
Consultation with stakeholders, like (for
JNNURM projects),
DPR & CRR
2.3 Land acquisition
resulting in relocation of households.
No social
impacts
The land acquisition
does not result into acquisition of any
structure nor
replacement of any squatters or
encroachers in and
around the premises. Hence no relocation of
households is
involved. which will
get affected due to it
Field survey,
Consultations with stakeholders, like
local people (for
JNNURM projects), local residents,
government officials.
DPR & CRR
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
32
2. Any reduction of
access to traditional
and river dependent communities (to river
and areas where they
earn for their primary
or substantial
livelihood).
No social
impacts
No access problem to
river
Field visits and
consultations with the
shop keepers, mobile vendors, expert
opinions
2.4 Any displacement or
adverse impact on tribal settlement(s).
No social
impacts
There are no tribal
settlements in the project area.
Consultations with
stakeholders, like local people (for
JNNURM projects),
local residents, government officials.
2.5 Any specific gender
issues.
No social
impacts
No gender issues were
reported during survey
Consultations,
interviews, which were taken up with
females specifically.
3 Will the project create significant / limited / no environmental impacts during the
construction stage? (Significant / limited / no impacts)
3.1 Clearance of
vegetation/ tree-cover
No
environmen
tal impacts
The major land use
pattern of sewerage
district A is mostly residential and
commercial, with no
agricultural and no forested areas.
Also no tree cutting is
involved in the
pumping station sites
Vegetation and tree cover were
insignificant in the
proposed project area.
Also, sewer lines will
be laid in the center of
the roads hence no impact on trees (which
are aligned along the
sides of roads)
Field visits and
Interaction with UP
Jal Nigam, Nagar Nigam department.
Figure 5.10 GIS map of ward localities in
District A.
Figure 3.2: Satellite
image showing the
alignment of trees along the sides of the
roads in District A.
Figure 5.7: GIS map of
identified parks in
District A.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
33
3.2 Direct discharge of
construction run-off,
improper storage and disposal of excavation
spoils, wastes and
other construction
materials adversely
affecting water quality
and flow regimes.
Limited Possibility of
temporary flushing
away of un-managed spoils and
construction wastes
during rainfall to river
Ganga via storm water
drains.
If not appropriately
managed, there may
be potential for
temporarily affecting
storm water flows by
obstruction to flows and blockage of
drains, especially
during rainfall. This may cause floods.
Interaction with UP
Jal Nigam and other
Government officials and consultation with
local residents of
sewerage district ‘A’.
Figure 5.7: GIS map showing the drainage
network of District A.
3.3 Flooding of adjacent areas
Limited
For sewerage works in the entire sewerage
district A, flooding
could be an issue during the monsoons,
since the drainage
system in sewerage
district ‘A’ covers
approximately 60-65
%, which is further ineffective due to
blocked drains and
poor solid waste management.
The areas which are expected to face
temporary flooding
issues include slum area in Kydganj
Additionally, if water
pipes are
inadvertently
breached, flooding will result.
City Development Plan for Allahabad,
Final Report by
Feedback Ventures.
Plate 5.1: Image
showing flooded
streets of Allahabad
District A after
rainfall. .
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
34
3.4 Improper storage and
handling of
substances leading to contamination of soil
and water
Limited
The storage of
construction related
material will not cause any contamination
since these materials
would typically
include: Concrete,
pipes, masonry,
rubber pipes.
There are no water
bodies within the
study area. However,
with other finer
materials such as powders, fluids and
greases, if not
appropriately managed or in the
event of an accident,
there may be potential for temporary
contamination of the
river Yamuna and Ganga via the various
drains and nalas in
sewerage district A,
during rainfall.
Plate 3.4: Image
showing a typical sewage construction
area with material.
Figure 5.6 highlights
the drainage network.
Section 5.1.10.1
provides details about
agricultural land in
sewerage district ‘A’.
Additionally, there is
a provision in the
DPR for Allahabad Sewerage District ‘A’,
Volume I, for
clearance of site after construction period
and unforeseen items
3.5 Elevated noise and
dust emission
Limited
For sewage works,
construction is likely to increase dust and
noise levels
temporarily.
Temporary impacts
may especially be felt at educational facilities
like schools/colleges
Allahabd Degree College, Kesrvidyapith
Inter College, Ewing
Christian College, Shiv
Charan Das,
Kanhaiyalal
Intermediate College Provided that
construction works
near schools and
colleges are carried out
Consultation with
local residents, and interaction with UP
Jal Nigam and other
Government officials.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
35
during vacations and
works near hospitals
are completed on priority basis (in
shorter time period
with alternate
provision of traffic,
accessibility of
exit/entry gates etc.), the impacts may be
limited.
Impacts will be
temporary as 1 km of
sewer line is approximated to be
completed within 3
days. 3.6 Disruption to traffic
movements
Limited Sewer construction
leads to the temporary
tearing-up of roads and increase in large
construction vehicles,
which might impair traffic movement,
especially in the
narrower roads and
lanes as seen mainly in
Muthiganj, Rambagh.
Figure 6.1: GIS map
distinguishing road
network of District A with majority of roads
in the Narrow
category (<=5 units).
Plate 6.1: Image
showing a typical
busy street at
Rambagh Chauraha
in District A
Additionally, there is
a provision in the DPR for Allahabad
Sewerage District ‘A’,
Volume-I for diversion of
traffic/regulation
during construction period
3.7 Damage to existing
infrastructure, public
utilities, amenities etc.
Limited If not appropriately
managed, there may
be potential for
temporarily affecting
the existing public utilities like water
supply, telephone,
electricity cables etc.
Interaction with UP
Jal Nigam and other
Government officials.
Additionally, there is
a provision in the
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
36
Records and layout
plans of existing
underground utilities and cable networks
(like telephone,
electricity water etc.)
were unavailable.
DPR for Allahabad
Sewerage District ‘A’,
Volume- for shifting & reinstatement of
utilities
3.8 Failure to restore temporary
construction sites
Limited From field visits and as per JNNURM
project reinstatement
of dismantled roads
after filling and proper
compaction was
observed.
Although temporary,
concerns regarding failure to restore
construction sites
including failure to close and
appropriately fence-off
open pits were cited as safety concerns
especially for children.
Field visits and interaction with U.P.
Jal Nigam and other
Government officials
and consultation with
local residents.
Plate 3.5: Image
shows the good
practice of fencing-off construction areas;
this was followed in
the JNNURM phase sewerage project in
Allahabad.
Additionally, there is
a provision in the
DPR for Allahabad
Sewerage District ‘A’,
Volume I, for
clearance of site after construction period
and unforeseen items
3.9 Possible conflicts with and/or disruption to
local community
Limited
For the laying of sewer works, there will be
temporary disruption
to the local community in terms of access to
roads (narrow roads),
shops and residences. Conflicts/disruption to
local community was
inferred as limited
based on survey
responses which
indicated the community’s ability to
adapt to temporary
disruptions, and their
overall preference for
Consultation with local people.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
37
the project.
3.1
0
Health risks due to
unhygienic conditions
at workers camps
Limited
Field visits and as per
JNNURM project no
worker camps were seen. However there
might be small camps
within which, if hygienic conditions
are not maintained,
there may be temporary impacts.
3.1
1
Safety hazards during
construction
Limited From field visits and
as per JNNURM
project practices for
safety precautions
such as fencing-off construction areas,
sign posts etc. were
observed.
If not appropriately managed, there may
be potential for
temporary hazards such as injuries and
damage to property
during the construction phase.
Consultation with
local residents of
sewerage district ‘A’
and interaction with
UP Jal Nigam and other Government
officials.
Plate 3.5: Image
shows the good
practice of fencing-off construction areas;
this was followed in
the JNNURM phase sewerage project in
Allahabad.
4 Will the project create significant / limited / no environmental impacts during the
operational stage? (Significant / limited / no impacts)
4.1 Flooding of adjacent areas
Limited Due to the construction of
sewer lines, raw
sewage that currently flows into
the river and/or
overflows into the
streets will now be
routed to the STP.
This will prevent flooding of adjacent
areas.
However,
accidental leakages
during the
operational stage
Interaction with UP Jal Nigam and other
Government officials.
Refer to Plate 5.1 for
area which has been flooded
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
38
will lead to
flooding.
Additionally, overloading and
blockage of sewage
lines will also lead
to backlogging of
sewers and flooding
of branch sewers. 4.2 Impacts to water
quality due to effluent
discharge
No impacts
There will be a
significant
improvement in
water quality due to
effluent discharge
being treated.
Table 5.11: Sewage
flow quality values
before and after
existing STP. section
5.1.8
4.3 Gas emissions No impacts Reduction of bad
smell (Methane and other bad anaerobic
reaction gases)
from open drains since the proposed
sewage networks
will be underground.
4.4 Safety hazards Limited Safety hazard are
associated during
construction and
maintenance stage of the sewage.
However these will
be temporary in nature.
5 Do projects of this nature / type require
prior environmental
clearance either from the MOEF or from a
relevant state
Government
department? (MOEF/
relevant State
Government department/ No
clearance at all)
No clearance required.
As per Environmental
Impact Assessment
Notification, 2006 no clearance would
be required under
Refer to Figure 5.8
Refer to Figure 5.7
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
39
6 Does the project
involve any prior
clearance from the MOEF or State Forest
department for either
the conversion of
forest land or for tree-
cutting? (Yes/ No).If
yes, which?
No As the project does
not cover any
forested area (protected nor
reserved forest
area), no prior
clearance is
required from
relevant authorities (MoEF and State
Forest departments)
under the Forest
(Conservation) Act,
1980.
Refer to Figure 3.2
Refer to Figure 5.8
The figure 3.2 below provides view of project area and environmental setting.
Figure 3.2 Satellite image showing the alignment of trees along the sides of the roads
in District A (Source: Google Earth)
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
40
Plate 3.3 Slum region near Yamuna Bridge, where residents have had complaints
related to flooding due to the low lying location.
Plate 3.4 Typical sewage construction area with material (background) and re-
instated road (foreground)
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
41
Plate 3.5 Image shows the good practice of fencing-off construction areas; this was
followed in the JNNURM phase project in Allahabad
3.3 Conclusion of Screening Activity
In order to facilitate effective management and mitigation of the any impacts arising
from the proposed projects, the Environmental and Social Management Framework
of NRGBA (Section # 4 of ESMF report, NGRBA 2011)6 has grouped the pollution
abatement projects/ investments into the following two categories high and low
• High: Mainly include the sub-projects which are likely to have adverse
impact on the environmental and social aspects of the project influence area
(including land acquisition). This category projects will also include
mandatory environmental clearance as per the EIA notification.
• Low: Projects which are likely to cause minimal or no adverse environmental
impacts on human populations.
Based on the screening activity and the categorization of potential sub-projects of the
NGRBP, the present project of Sewerage work in Sewerage District ‘A’ in Allahabad
City falls under low impact category, which do not have any land acquisition. In
view of the above, these projects would require preparation of an Environmental and
Social Assessment, as part of the DPR, and implementation of Generic Safeguard
Management Plan (SMP), relevant to the project.
Although there would not be any permanent negative or adverse environmental
impacts, but will have temporary impacts like traffic blockages, dust, noise, safety
hazards for pedestrians, possible damage to private property, possible interruption
in commercial activity, and accidental breakage of other public infrastructure such as
water pipes. These temporary impacts can be mitigated with appropriate mitigation
plans. However, the large environmental benefit of the project greatly outweighs the
temporary inconveniences.
6 For more details refer “Environmental and Social Management Framework for World Bank Assisted
National Ganga River Basin Project, 2011”. PMG, National Ganga River Basin Authority, MoEF.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
42
Chapter 4 Regulations and Legal Framework
4.1 Applicable Laws and Regulations – Environmental
The following laws and regulations are applicable to the environmental and social
aspects of the investments implemented under the programme:
• Policy and Regulatory Framework of Government of India (GoI)
• Environmental Policy and Regulations of the respective State Governments
• Legislations applicable to construction activities
4.1.1 Legal Framework of Government of India
The Government of India has laid out various policy guidelines, acts and regulations
pertaining to environment. The Environment (Protection) Act, 1986 is umbrella
legislation for the protection of environment. As per this Act, the responsibility to
administer the legislation has been jointly entrusted to the Ministry of Environment
and Forests (MoEF) and the Central Pollution Control Board (CPCB).
4.1.2 Key Environmental Laws and Regulations
The key environmental laws and regulations as relevant to the projects under the
NGRBP are given in Table 4.1. The key environmental regulations can also be
accessed at www.moef.nic.in/rules-and-regulations
Table 4.1 Environmental Regulations and Legislations
S.
No
Act / Rules Purpose Applicable
Yes/ No
Reason for
Applicability
Authority
1 Environment
Protection Act-
1986
To protect and
improve overall
environment
Yes As all
environmental
notifications, rules and schedules are
issued under this
act.
MoEF, Gol,
DoE, State
Gov. CPCB, SPCB
2 Environmental
Impact
Assessment Notification
14th Sep-2006
To provide
environmental
clearance to new development
activities
following environmental
impact
assessment
No
The present project
is only a sewerage
network project and hence as per
the notification
amended till date does not attract
requirement of
environmental
clearance.
MoEF, EIAA
3 Municipal
Wastes(Management and
To manage the
collection, transportation,
No The present project
does not involved solid waste
MoEF, EIAA,
CPCB, SPCBs
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
43
Handling)
Rules, 2000
segregation,
treatment, and
disposal of municipal solid
wastes
management
measures.
4 Coastal
Regulation
Zone(CRZ)
Notification 1991 (2002)
Protection of
fragile coastal
belt
No The project does
not fall within CRZ
areas.
5 The Land
Acquisition Act
1894 (As
amended in
1985)
Set out rule for
acquisition. of
land by
government
No This act will be
applicable only if
there will be
acquisition of land
for investments but no land acquisition
is involved in the
project.
Revenue
Department
State
Government
6 The Forest
(Conservation)
Act. 1980
To check
deforestation by
restricting conversion of
forested areas
into non- forested areas
No No forest land
diversion is
required in the project.
Forest
Department,
State Government
and Ministry
of Environment
and Forests,
Government
of India
7 Wild Life
Protection Act 1972
To protect
wildlife through certain of
National Parks
and Sanctuaries
No The project does
not pass through any national
park/sanctuary are
nor fall within 10km radius of
such protected
areas.
Chief
Conservator Wildlife,
Wildlife
Wing, State Forest
Department
and Ministry of
Environment
and Forests, Government
of India
8 Air (Prevention
and Control of
Pollution) Act,
1981
To control air
pollution by
controlling
emission of air pollutants as per
the prescribed
standards.
Yes This act will be
applicable during
construction stage
for operation of equipment, DG sets
and hot mix plant.
SPCBs
9 Water To control water Yes This act will be SPCBs
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
44
Prevention and
Control of
Pollution) Act1974
pollution by
controlling
discharge of pollutants as per
the prescribed
standards
applicable during
construction stage
if STP is installed.
10 The Noise
Pollution
(Regulation and Control) Rules,
2000
The standards for
noise for day and
night have been promulgated by
the MoEF for
various land uses.
Yes This act will be
applicable for all
construction equipment
deployed at
worksite.
SPCBs
11 Ancient
Monuments and
Archaeological Sites and
Remains
Act1958
Conservation of
cultural and
historical remains found in India
No Kydganj Cemetery,
the only ASI
recognized structure in
sewerage district A
is more than 200m away from the
proposed sewer
line. Hence the act is not applicable for
the project.
Archaeologica
l Department
Gol, Indian Heritage
Society and
Indian National
Trust for Art
and Culture Heritage
(INTACH).
12 Public Liability and Insurance
Act 1991
Protection form hazardous
materials and
accidents.
NO Contractor unlikely to store material
more than the
threshold limits
defined this Act.
SPCBs
13 Explosive Act
1984
Safe
transportation, storage and use
of explosive
material
Yes For transporting
and storing diesel, Oil and lubricants
etc.
Chief
Controller of Explosives
14 Minor Mineral
and concession
Rules
For opening new
quarry.
No Regulate use of
minor minerals like
stone, soil, river sand etc.
District
Collector
15 Central Motor
Vehicle Act 1988
To check
vehicular air and noise pollution.
Yes This rule will be
applicable to vehicles deployed
for construction
activities and
construction
Machinery.
Motor Vehicle
Department
16 National Forest Policy, 1988
To maintain ecological
stability through
preservation and
restoration of
No This policy will be applicable if any
eco sensitive
feature exists in
and around the
Forest Department,
State
Government
and Ministry
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
45
biological
diversity.
investments of
Environment
and Forests, Government
of India
17 The Mining Act The mining act
has been notified
for safe and
sound mining activity.
No The construction
activities for
investments will
require aggregates. These will be
procured through
mining from
approved quarries
Department
of mining,
State
Government
4.2 Applicable Laws and Regulations - Social
All strategic interventions on human development, spread across all social issues,
need directives of policies and legal support to operationalize the appropriate
actions. These policies and legislations help to overcome the constraints and support
administrator, implementer, community and individual in delivery of justice. This
section includes the National policies and Acts as detailed under:
National Policies and Acts
i. National Tribal Policy, 2006
ii. National Resettlement and Rehabilitation Policy, 2007
iii. Land (Acquisition) Act 1894 (as amended)
iv. Forest Rights Act, 2006
However for the present project, none of the above policies and acts are applicable.
4.2.1 National Policies and Acts
• The National Tribal Policy (2006)
The Policy has the following objectives:
Regulatory Protection
• Providing an environment conducive to the preservation of traditional and customary systems and regime of rights and concessions enjoyed by different
ST communities, and reconciliation of modes of socio-economic development
with these.
• Preventing alienation of land owned by STs and restoring possession of
wrongfully alienated lands.
• Protection and vesting of rights of STs on forestlands and other forest rights
including ownership over minor forest produce (MFP), minerals and water
bodies through appropriate legislations and conversion of all forest villages
into revenue villages.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
46
• Providing a legislative frame for rehabilitation and resettlement in order to
minimize displacement, ensure that affected persons are partners in the growth in the zone of influence, provide for compensation of social and
opportunity cost in addition to market value of the land and rights over
common property (NPV).
• Empowerment of tribal communities to promote self-governance and self-
rule as per the provisions and spirit of the Panchayats (Extension to the
Scheduled Areas) Act, 1996.
• Protection of political rights to ensure greater and active participation of
tribal peoples in political bodies at all levels.
4.2.2 National Resettlement and Rehabilitation Policy for Project
Affected Families – 2007
The national policy on resettlement and rehabilitation represents a significant
milestone in the development of a systematic approach to addressing resettlement.
The policy establishes a Guideline for extending additional assistance to project-
affected families, over and above the compensation for affected assets provided
under the Land Acquisition (LA) Act.
This policy strikes a balance between the need for land for developmental activities
and protecting the interests of land owners and others. The benefits under the new
policy are available to all Affected Persons (AP) and families whose land, property or
livelihood is adversely affected by land acquisition, involuntary displacement due to
natural calamities, etc.
4.2.3 Land Acquisition Act, 1894 (As Modified Until 1st
September, 1985)
The Act is applicable to the whole of India except the state of Jammu and Kashmir.
The policy provides a broad guideline of procedure of land acquisition. The Land
Acquisition (LA) Act of 1984 is commonly used for acquisition of land for any public
purpose. It is used at the State level with State amendments made to suit local
requirements. Expropriation of and compensation for land, houses and other
immovable assets are carried out under the Land Acquisition (Amendment) Act,
1984. The Act deals with compulsory acquisition of private land for public purpose.
The LA Act does not contain any provision specifically dealing with resettlement
including income restoration aspects.
Table 4.2 The Land Acquisition Process
Legal
Provision
Actions
Section 4
Draft prepared by requiring body, verified by the Ministry of Law,
printing and proof reading. Publish in official gazette and two local
newspapers; post notice locality No further land sales, transfers or subdivisions after notice
Appoint Land Acquisition Officer (LAO) to survey land
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
47
4.2.4 Forest Rights Act 2006
The Act basically does two things:
• Grants legal recognition to the rights of traditional forest dwelling
communities, partially correcting the injustice caused by the forest laws.
• Makes a beginning towards giving communities and the public a voice in
forest and wildlife conservation
4.3 Other Legislations applicable to Construction
Projects under NGRBP
Construction stage generally involves equity, safety and public health issues. The construction agencies therefore will be required to comply with laws of the land,
which include inter alia, the following:
1. Workmen's Compensation Act 1923 (the Act provides for compensation in case
of injury by accident arising out of and during the course of employment);
2. Payment of Gratuity Act, 1972 (gratuity is payable to an employee under the Act
on satisfaction of certain conditions on separation if an employee has completed 5 years);
Notices under section 4(1) issued to individual owners and interested
parties (one month)
Declaration of Public
purpose
Government certifies that land is required for a public purpose Declaration is published
Collector / Deputy Commissioner receives order from Revenue
Department, State Government
Land appraisal begins (two weeks to a month)
Section 5(a)
Enquiry
Enquire objections to LA
Land owners and interested parties appear before LAO Revenue commissioner calls for comments of acquiring agency if
objections are raised – (one to three months)
Section 6 State government issues notices
LAO serves individual notice on all interested parties of government’s
intention to take possession of land
Time and place set for claims to LAO Public notice given
Collector or LAO investigate claims (12 months)
Section 9 LAO conducts on-site inquiry regarding area of LA and compensation payable
LAO determines compensation (12 months)
Section 11
and 12
Declaration of final award by Collector/Commissioner/State
Government after inquiry of total valuation
Notice of awards given to interested parties for payment of compensation
Government can take possession of land and hand over to implementing
agency (14 months)
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
48
3. Employees PF and Miscellaneous Provision Act 1952 (the Act provides for
monthly contributions by the employer plus workers);
4. Maternity Benefit Act, 1951 (the Act provides for leave and some other benefits
to women employees in case of confinement or miscarriage, etc.);
5. Contract Labor (Regulation and Abolition) Act, 1970 (the Act provides for certain welfare measures to be provided by the contractor to contract labour);
6. Minimum Wages Act, 1948 (the employer is supposed to pay not less than the
Minimum Wages fixed by the Government as per provisions of the Act);
7. Payment of Wages Act, 1936 (it lays down as to by what date the wages are to
be paid, when it will be paid and what deductions can be made from the wages
of the workers);
8. Equal Remuneration Act, 1979 (the Act provides for payment of equal wages for
work of equal nature to Male and Female workers and not for making
discrimination against Female employees);
9. Payment of Bonus Act, 1965 (the Act provides for payments of annual bonus
subject to a minimum of 83.3% of wages and maximum of 20% of wages);
10. Industrial Disputes Act, 1947 (the Act lays down the machinery and procedure
for resolution of industrial disputes, in what situations a strike or lock-out
becomes illegal and what are the requirements for laying off or retrenching the
employees or closing down the establishment);
11. Industrial Employment (Standing Orders) Act; 1946 (the Act provides for laying
down rules governing the conditions of employment);
12. Trade Unions Act, 1926 (the Act lays down the procedure for registration of trade unions of workers and employers. The trade unions registered under the
Act have been given certain immunities from civil and criminal liabilities);
13. Child Labour (Prohibition and Regulation) Act, 1986 (the Act prohibits
employment of children below 14 years of age in certain occupations and
processes and provides for regulation of employment of children in all other
occupations and processes. Employment of child labour is prohibited in Building and Construction Industry);
14. Inter-State Migrant Workmen’s (Regulation of Employment and Conditions of
Service) Act, 1979 (the inter-state migrant workers, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such
as housing, medical aid, travelling expenses from home to the establishment
and back, etc.);
15. The Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and the Cess Act of 1996 (all the establishments
who carry on any building or other construction work and employs 10 or more workers are covered under this Act; the employer of the establishment is
required to provide safety measures at the building or construction work and
other welfare measures, such as canteens, first-aid facilities, ambulance, housing
accommodation for Workers near the workplace, etc.);
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
49
16. The Factories Act, 1948 (the Act lays down the procedure for approval of plans
before setting up a factory, health and safety provisions, welfare provisions, working hours and rendering information-regarding accidents or dangerous
occurrences to designated authorities);
17. Hazardous Wastes (Management and Handling) Rules, 1989 (the Rules govern
handling, movement and disposal of hazardous waste);
18. Manufacture, Storage and Import of Hazardous Chemicals Rules 1989, amended
1994 and 2000 (the Rules provide indicative criteria for hazardous chemicals and require occupiers to identify major accident hazards and prepare on-site and
off-site emergency plans).
All the laws and regulations set by different authorities (MoEF, NGRBA, CPCB, etc.)
have been reviewed to understand the applicable laws in the context of this proposed
sub-project in Allahabad District A. All the applicable laws enlist the responsible
authority and reasons for its applicability. It is therefore proposed that during the
implementation of this project responsible authorities should be contacted acted by
the implementing agency for monitoring the law and regulation.
Conclusion:
The applicable laws and regulations pertaining to environment and social safeguards
for the present project are listed below:
1. Environment Protection Act 1986;
2. Air (Prevention and Control of Pollution) Act, 1981
3. Water Prevention and Control of Pollution) Act1974
4. The Noise Pollution (Regulation and Control) Rules, 2000
5. Explosive Act 1984
6. Central Motor Vehicle Act 1988
7. Other legislations are mentioned in section 4.3
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
50
Chapter 5 Baseline Status The baseline environmental and social status is important to understand the region's
existing physical and biological characteristics along with cultural and social status
of the residing community. Information and data presented in this section is based
on field surveys, stake-holder interaction/consultation and secondary data collection
which majorly include the draft Detailed Project Report (DPR) of proposed sewerage
work in Allahabad city, City Development Plan (CDP) report by Nagar Nigam,
Water/ Air/ Noise quality monitoring report of UP Pollution Control Board, City
census data and others. The information on the baseline environmental conditions
forms the basis to analyse the probable impacts of the proposed project vis-à-vis the
present background environmental quality of the core study area.
5.1 Baseline Environmental
5.1.1 Physiography and Topography
Allahabad city as a whole occupies the inter-fluvial belt of Ganga River in the north
and the Yamuna in the south. The confluence (Sangam) of the two rivers lies in the
south east of the city. These rivers are perennial rivers, which carry huge volumes of
water during the rainy season. Sewerage district ‘A’ is located in the southern part of
the city, adjoining the river Yamuna in the south side.
Allahabad district is mainly characterized with Ganga, Yamuna alluvial plain and
Vindhyan Plateau. Geological Survey of India (2001) has identified the following
geomorphic features,
• Active Flood Plain: It is quite localized and confined only to the river system.
• Older Alluvial Plain: It is characterized by depositional and erosional terraces
found in patches along the active plain.
• Rocky Surface (Denudational hills): These are prominent in trans-Yamuna
area formed mainly of quartzitic nature.
Allahabad district may be divided into three distinct Physical parts, the trans-Ganga
or the Gangapar Plain, the Doab and the trans-Yamuna or the Yamunapar tract which is
formed by the Ganga and its tributary, the Yamuna, the latter joining the former at
Allahabad, the confluence being known as Sangam. The master slope of trans-Ganga
is towards east or south east, with the altitude ranging from 89.30 - 93.57m above
MSL.
5.1.2 Climate
Climate of Allahabad district is continental. The climate of Allahabad is tropical with
moderate winter and severe extended summer. The nearest large body of water i.e.
the Bay of Bengal is more than 700 km eastward. Due to this, there is a large range of
variation in temperatures of day and night. Allahabad experiences both very dry hot
summers and very cold winters every year. Dust storms in summer and cold north
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
51
winds in winter are common. The average normal maximum temperature has been
observed as 41.8ºC during May and minimum of 8.9ºC during January. The highest
relative humidity in the morning is 85% during August and the lowest being 32% in
April. The district receives rainfall from the south-west monsoon from June to
September. The average rainfall being 962.68 mm takes place normally in 53 days.
The climate information of Temperature, Humidity and Rainfall at Allahabad is
given in Table 5.1 below.
Table 5.1 Climatological Normal of Temperature, Humidity and Rainfall at
Allahabad
Source: India Metrological Department data from 1901-2000 (except Humidity data which is
1951-1980)
5.1.3 Geological and Geophysical features
The sewerage district ‘A’ and whole city of Allahabad occupies the inter-fluvial
sediment of the Ganga River and Yamuna River. These sediments are essentially a
sequence of clays, sands, silts with inter-spread bands of Kankar having limited
extent. Broadly these fluvial sediments are grouped as younger and older alluvium.
The younger alluvium is generally confined to a depth of 60 m below the ground and
it occupies the present day flood plain area. The older alluvial sediments marginally
differ in lithology from that of younger alluvium sediments, with presence of sandy
clay and lenses of gravel/pebbles and Kankar. The older alluvium overlies the
Siwalik group of formations, which in turn overlies the pre-Cambrian formation. The
generalized stratigraphic sequence of the formations is given in Table 5.2. The age of
these formations range from Proterozoic to recent. Granite of Bundelkhand massit
group forms the basement in the area which is unconformably overlain by
Quaternary alluvium.
Month Temperature (oC) Mean rainfall in mm Humidity (%)
Maximum Minimum 0830 Hrs 1730 Hrs
January 23.5 8.9 17.9 78 53
February 26.7 11.4 17.3 66 40 March 33.3 16.6 9.6 46 25
April 39 22.3 5.5 32 18
May 41.8 26.7 8.7 36 36
June
39.8
28.4 88.8 55 41
July 34 26.5 280.8 80 71 August 32.5 25.9 296.1 85 77
September 33 24.9 184.9 80 71
October 32.9 20.2 36.6 69 55
November 29.2 13.5 9.3 65 49
December 24.6 9.3 6.9 75 56
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
52
Table 5.2 Generalized Stratigraphic Sequence Time
Time Unit Formation Rock Unit Thickness (m)
Recent to 0.01 m
year
Newer Alluvium Sand & Clay 60-100
Holocene < 1m year Older Alluvium Sand, clay, pebble,
gravel and Kankar
100-200
------------------------------- Unconformity-------------------------------
Pleistocene & Pleocene
Siwalik Conglomerate, sandstone
shale etc.
Above 350 m
------------------------------- Unconformity------------------------------- Pre Cambrian Vindhyan Sand stone,
Limestone
Not known
------------------------------- Unconformity------------------------------- Archean Bundelkhand
massit
Granite Basement
Source: CGWB, 2009 and Final Report on Water Quality Management Plan for Ganga River,
July 2005. Volume IV-3, Feasibility Study for Allahabad City, Part I, Sewerage Scheme
5.1.3.1 Soil
Soils in sewerage district ‘A’ usually comprises a layer of clay on the top surface,
with a thickness ranging between 10-15 m. Thick sandy horizon occurs beneath the
top clay layer having sufficiently large thickness. The soil in this area, i.e., Doab has
three distinct types. Sandy soil is found on the banks/ flood plain of the rivers
(Yamuna bank of District A) , clay is found in the depressions and loam, a mixture of
sand and clay that is usually a rich and rather dark soil, the less fertile variety.
Chemical analysis study of the soil for Allahabad city carried out by JICA has been
presented in the Table 5.3 below:
Table 5.3 Quality of soil sample
S. No. Parameters Range of test results
1 Type Silty Clay
2 pH 7.9-8.0
3 Bulk density (g/cm) 1.2-1.28
4 Conductivity (µmhos/cm) 390.5-371.6
5 Water holding capacity
(% by mass)
47.7-49.54
6 Organic matter (% by
mass)
1.08-1.16
Source: Final Report on Water Quality Management Plan for Ganga River, July 2005. Volume IV-3, Feasibility Study for Allahabad City, Part I, Sewerage Scheme
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
53
5.1.4 Ambient Air Quality
The ambient air quality presented in this section is monitored under NAMP
(National Air Monitoring Programme) by CPCB and UP Pollution Control Board at
two locations: Bharat Yantra Nigam Limited office and Square crossing near Laxmi talkies
in Allahabad City. Although, Allahabad city does not fall under the identified list of
polluted cities in India, but the available data from NAMP monitoring shows that the
dust levels, PM10 (RSPM and SPM) have exceeded the annual average standards of
60 µg/m3 from 2007 to 2010. The sulphur-di oxide (SO2) concentration have gone
down with reduced sulphur content in the fuels from 2007 to 2009 as shown in
Figure 5.1 and is well within the permissible standards of 20 µg/m3. The nitrogen-di-
oxide (NO2) concentrations, though not exceeding the standards of 30µg/m3, may
exceed in future due to urbanization and rise in vehicular activities.
Table 5.4 Latest air quality data of two monitoring stations in Allahabad (March 2010
to April 2011)
Source: UP Pollution Control Board, 2011
Location Landuse Sulphur-
di-oxide in µg/m3
Nitrogen-
di-oxide in µg/m3
Respirable
Suspended particulate
matter
(RSPM or
PM10)
in µg/m3
Suspended
particulate matter
(SPM)
in µg/m3
Square crossing
circle of Laxmi
talkies
Mixed 5.7 23.6 237.7 469.4
Bharat Yantra
Nigam Ltd.
Residential 5.4 23.7 232.6 459.4
National Ambient
Air Quality
Standards ( 24
hourly)
Residential 80 80 100 --
National Ambient
Air Quality
Standards ( annual
average )
Residential 20 30 60 -
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
54
SO2
0
5
10
15
20
25
2007 2008 2009
Co
ncen
trait
on
(µ
g/m
³)
Figure 5.1 SO2, NO2, and PM10 concentration (µg/m3) in Allahabad during 2008-2009
Source: NAMP, Central Pollution Control Board, Government of India
Seasonal Variation
Month-wise variations of NO2 and RSPM concentrations at the two monitoring stations
are presented in Figure 5.2. Both the stations violate the permissible standards of RSPM
during all the months. Lowest pollutant concentrations are observed in monsoon months
and maximum were observed during winters due to inversion conditions. The effects of
inhaling particulate matter that have been widely studied in humans and animals now
include asthma, lung cancer, cardiovascular issues, birth defects, and premature death.
Annual avg std. 50 µg/m³
NO2
0
5
10
15
20
25
30
35
40
45
2007 2008 2009
Co
nc
en
tra
ito
n (
µg
/m³)
Annual avg. std.
40 µg/m³
PM10
0
50
100
150
200
250
2007 2008 2009
Co
nc
en
tra
ito
n (
µg
/m³)
Annual avg.
(RSPM)
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
55
Figure 5.2 Monthwise variation of NO2 and RSPM at two monitoring stations in
Allahabad
Source: UP Pollution Control Board, 2011
5.1.5 Noise Environment
Noise, in general, is sound that is composed of many frequency components of varying
loudness distributed over the audible frequency range. Increasing ambient noise levels in
public places from various sources, inter-alia, industrial activity, construction activity, fire
crackers, sound producing instruments, generator sets, loud speakers, public address
systems, music systems, vehicular horns and other mechanical devices may have
deleterious effects on human health and the psychological well-being of the people; hence
it is considered necessary to regulate and control any such noise pollution. Limited noise
level monitoring was carried out by JICA at three locations: Numaya Dahi, Sulem Sarai
and near DM office, is as shown in Table 5.5 below. Although, the monitoring stations do
not come under sewerage district ‘A’ except for Sulem Sarai but presents a credible data
of expected noise level in similar settings. The noise levels at Numaya Dahi village are
well within the permissible limits laid down by CPCB (for both day and night time),
whereas the noise levels at Sulem Sarai and near DM office are higher than the desirable
level for residential area but below the permissible level of commercial and industrial
area, respectively.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
56
Table 5.5 Summary of Noise Level Monitored Data Code Range of noise levels [Leq in dB
(A)]
S.No. Location Levels in dB(A) Leq*
Day Night Average
1 Numaya Dahi 45.8 41.1 44.0
2 Sulem Sarai 56.3 48.4 53.4
3 Near Office DM 72.4 54.5 65.7
Note:
• Permissible limit laid down by CPCB: Residential area (55 day time and 45 night time),
Commercial area (65 day time and 55 night time)and Industrial area (75 day time and 70
night time)
• * dB(A) Leq denotes the time weighted average of the level of sound in decibels on scale A
which is relatable to human hearing.
• Leq: It is an energy mean of the noise level over a specified time period
Source: The Noise Pollution (Regulation and Control) Rules 2000, CPCB, and Final Report on
Water Quality Management Plan for Ganga River, July 2005. Volume IV-3, Feasibility Study for
Allahabad City, Part I, Sewerage Scheme
Seasonal Variation
The average day and night ambient noise levels monitored by UP Pollution Control
board for residential, commercial, industrial and sensitive locations during 2010-2011 in
Allahabad city are presented in Figure 5.3. . Noise levels in all areas are largely within the
prescribed limits (Refer Figure 5.3) at most of the locations barring few readings.
0
10
20
30
40
50
60
70
80
28-M
ar-1
1
26-O
ct-1
0
19-A
ug-1
0
24-A
pr-1
0
23-M
ar-10
26th
Apr
il 20
11
18-N
ov-1
0
26-F
eb-1
1
22-J
an-11
23-D
ec-10
25-S
ep-1
0
24-J
ul-1
0
19-J
un-1
0
28-M
ay-10
26th
Apr
il 20
11
28-M
ar-11
28-M
ay-1
0
18-N
ov-10
24-J
ul-1
0
26-F
eb-1
1
22-Ja
n-11
23-D
ec-1
0
25-S
ep-10
19-J
un-1
0
24-Apr
-10
23-M
ar-1
0
26-O
ct-1
0
19-A
ug-1
0
Res Com Ind Sens
Night
Day
Figure 5.3 Noise levels in Allahabad City monitoring during 2010 and 2011
Source: UP Pollution Control Board, 2011
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
57
5.1.6 Water Environment
Domestic water requirement of district A is met from both surface and ground water
resources. Allahabad Jal Sansthan is the responsible agency for drawing surface water
from river Yamuna and installing tube wells for supply to residential/ commercial and
industrial sector. The raw water from River Yamuna is being tapped for water supply at
Karelibagh raw water pumping station which is pumped to Khusro Bagh water works for
treatment before it is supplied to the consumers. As of 2003, about 217mld of water was
supplied by Jal Sansthan department to entire Allahabad city. In addition to this, there is
sizable amount of unaccounted water supply from private/ institutional bore wells.
Considering the per capita water consumption of 190 litres (including UFW allowance
and institutional demand), as provided in the detailed project report (DPR) for sewer
works in sewerage district ‘A’ by Ganga Pollution Control Unit (GPCU), the total water
consumption in sewerage district ‘A’ is approximately 76.98 million litres as shown in
Table 5.6 below. This consumption is expected to increase with growing population and
urbanization.
Table 5.6 Water consumption in sewerage district ‘A’
Location Population (as
of 2010)
Per capita water
consumption per
day as per DPR
Total water
consumption in
million litres
Sewerage District ‘A’ of
Allahabad city
405176 190 76.98
5.1.6.1 Surface Water
An important surface water system of the city is the easterly flowing Yamuna river which
lies south of the main city. The Ganga is second important source of surface water which
flows easterly. Yamuna River merges with River Ganga close to celebrated temple of
Lord Hanuman in Sangam area of the city. River Yamuna lies to the southern side of the
district A and River Ganga is towards eastern side of sewerage district ‘A’, The maximum
discharge of river Ganga at Sangam is about 16187-12265 m3/s mainly during the months
of August and September and the minimum discharge is 366 to 339 m3/s during April and
May as shown in table 5.7.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
58
Table 5.7 Discharge of the Ganga at Allahabad (Sangam) (m3/s)
Source: Final Report on Water Quality Management Plan for Ganga River, July 2005. Volume IV-3, Feasibility Study for Allahabad City, Part I,
Sewerage Scheme
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1972 401.38 433.61 294.13 288.22 362.67 230.12 2609.37 6664.86 13253.85 2065.6 644.51 489.48
1973 389.03 347.81 283.07 225.23 221.7 478.79 13784 21527.1 28809.04 4651.25 1073.44 598.22
1974 507.35 384.54 325.14 267.79 307.61 260.77 9149.19 19693.1 3915.68 1100.98 691.88 488.52
1975 462.97 303.01 265.96 270.39 189.88 572.22 9742.86 18209.5 15767.68 4366.54 1303.98 724.01
1976 669.83 557.91 420.13 420.78 383.05 1117.08 3359.8 18221.7 161.42.34 1893.42 553.63 482.89
1977 335.1 327.9 270.71 394.99 373.86 332.77 9115.64 17417.4 14236.34 3051.76 1121.82 750.47
1978 707.07 623.33 740.88 707.16 556.8 1077.63 7994.05 29786.2 22399.45 3980.05 1346.27 964.36
1979 924.76 1123.35 217.99 678.51 582.7 474.02 4357.59 5701.17 1476.75 598.01 318.43 518.45
1980 380.91 288.71 224.58 151.84 123.71 406.3 6804.97 21670.9 11438.9 1441.81 684.11 443.14
1981 430.99 439.37 337.12 329.04 314.16 303.28 5841.3 11215 3259.22 2337.97 674.15 507.81
1982 476.17 741.79 645.68 689.06 624.22 626.4 1779.81 28824.3 16981.02 1398.27 763.93 616.34
1983 565.77 552.64 357.87 312.95 499.11 503.91 3738.99 12823 22159.27 7019.81 1522.83 767.78
1984 721.53 551.58 486.94 367.11 279.16 575.6 2261.22 10243.4 11080.78 1237.75 571.11 400.81
1985 433.23 323.99 238.99 262.01 237.49 257.07 1827.61 15588.6 10073.87 12078.5 2174.33 745.18
1986 588.76 736.23 554.26 372.11 309.6 382.35 11078.1 17832 4199.39 1539.24 740.38 519.89
1987 497.74 399.46 334.12 271.71 238.36 247.44 1116.56 3277.58 12471.41 1968.6 589.38 366.13
1988 327.21 279.35 261.2 216.16 173.64 165.69 5489.87 16483.9 4730.56 4060.86 9520.2 476.83
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
59
Surface Water Quality
Water quality status of river Ganga at two places in Allahabad is shown in Figure 5.4 and
Figure 5.5. As per the monitoring results, a Biological Oxygen Demand (BOD) concentration has increased over the period of 2002 to 2008. The Dissolved Oxygen (DO) levels in the river
have been sufficiently high and consistent over the past few years (Figure 5.5). In recent
years, there had been an increasing trend of BOD concentrations in incoming water (Rasoolabad ghat) and more evident trend observed in the outgoing water (Sangam). From
the year 2004 to 2008 an increase in BOD of around 0.4 mg/l to 0.6 mg/l in outgoing water of
river Ganga has been witnessed. This increase can be attributed to the untreated sewage that
has been directly discharged to the river Ganga including some proportion from District A
also.
Figure 5.4 BOD measured at various stretches of Ganga river for different years
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
60
Figure 5.5 DO measured at various stretches of Ganga river for different years
Source: Ganga water quality trend, 2009. Central Pollution Control Board, Government of India
Sangam, the confluence of the Ganga and Yamuna, is the venue of many sacred fairs and
rituals, and attracts thousands of pilgrims throughout the year. This number swells to
millions during the world-famous Kumbh Mela creating high stress on public utilities. Table
5.8 shows the water quality of river Ganga and Yamuna at Allahabad (UP) during
Maghmela (Ardh Kumbha) 2007. It is quite evident that during events like Khumb Mela, the
pollution levels are very high7.
7 Srivastava, R. K., Sinha, A. K., Pande, D. P., Singh, K. P. and Chandra, H., 1996. Water quality of the River
Ganga at Phaphamau (Allahabad)- effect of mass bathing during Mahakumbh. Environmental Toxicology and
Water Quality, 11: 1–5.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
61
Table 5.8 Water Quality of River Ganga and Yamuna at Allahabad (UP) during Maghmela
(Ardh Kumbha) 2007
Location BOD
(mg/l)
DO (mg/l)
Yamuna at Naini Bridge (U/s Sangam) 1.7 8.6
Ganga at Shastri Bridge (U/s sangam) 5.7 10.4
Sangam 4.3 9.3
Yamuna at Karella Bagh 1.8 6.8
Ganga at Phaphamau u/s Sangam 6.4 8.3
Ganga at Diha Ghat d/s Allahabad 4.3 6.3
Recent Data
As per the latest water quality monitoring conducted by UP Pollution Control Board (Table
5.9), the biochemical oxygen demand (BOD) levels at all stations are often found more than
3.0 mg/l , i.e. the water quality is above the permissible limit for bathing as well as for
drinking water quality criteria of CPCB. However, the water quality parameter of dissolved
oxygen (DO) seems within permissible limits. The minimum DO levels for water as per the
Indian standard code ranges from 4.0-6.0 mg/l for drinking and bathing respectively.
Total coliform and fecal coliform were present at all stations, indicating possible
contamination from municipal waste water discharges from the city. The presence of fecal
coliform in the water also indicates a greater potential of the presence of pathogenic
microorganisms, which may cause waterborne diseases, leading to detrimental impacts on
the health of the community. During summer, the river flow reduces and at increased
temperature the bacterial activities increases to oxidize the organic matter discharged into it
from various domestic and industrial sources.
Table 5.9 Water Quality data of Ganga and Yamuna river at Allahabad monitored during
March 2010 to April 2011
Parameters
U/S
Rasoolabad Ghat,
Ganga
Rasoolabad Ghat,
Ganga
Main
Sangam
D/S Ganga on
Mawaiya Ghat
Temp ( C ) 24.9 24.9 25.4 25.5
pH 8.3 8.3 8.3 8.3
DO (mg/l) 7.9 7.7 7.5 7.4
BOD (mg/l) 4.1 4.5 4.2 4.5
COD (mg/l) 28.4 31.4 30.4 34.9
Turbidity (NTU) 94.3 104.5 85.6 90.7
Alkalinity
CaCO3 (mg/l)
168.1 174.6 205.4 213.0
Hardness as CaCO3 (mg/l)
146.9 153.0 166.4 173.6
Calcium as
CaCO3 (mg/l)
87.0 90.6 94.0 99.0
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
62
Magnesium as
MgCO3 (mg/l)
59.9 62.4 72.4 74.6
Conductivity (umho/cm)
427.7 429.4 520.6 531.1
Total Coliform
(PN/100 ml)
4678.6 7857.1 6571.4 9428.6
Fecal Coliform (MPN/100ml)
2742.9 3492.9 3142.9 3785.7
Source: Uttar Pradesh Pollution Control Board, 2011
5.1.6.2 Ground Water
According to the Central Ground Water Board (CGWB), the groundwater problems of
Allahabad are not very serious although, due to rapid urbanization and increasing
population levels, the dependence on groundwater has increased over the years. With
reference to the exploratory drilling data of CGWB and state tubewell department, it is
evident that there are three distinct granular zones at Allahabad city
i. Shallow aquifers ranging from 20 to 50 mbgl8
ii. Middle aquifer ranging from 70 to 120 mbgl and
iii. Deeper aquifer lies below 150 down to depth 300 mbgl.
The extension of individual zones is variable over the district. The ground water generally
occurs in unconfined state within the first shallow aquifer within 50 m from the ground
while in deeper aquifers it occurs in semi confined to confined conditions. The ground water
flow is towards the river Ganga in the north and river Yamuna in the south i.e., both the
rivers are effluent in nature.
Ground Water Quality9
The ground water quality pre and post monsoon has shown small variation in quality as can
be seen tabulation below and can be used for drinking with small treatment.
Parameters Pre monsoon Post Monsoon
pH 7.2-8.1 7.1-7.8 Total Dissolved Solids ( TDS) in mg/l 281 - 1372 <1300
Hardness in mg/l 180-1128 154 to 1092
Conductivity in µmhos/cm 475-1875 Not Available
BOD in mg/l 0.1 - 0.3 Not Available
COD in mg/l 1.0 – 6.0 Not Available
Fluoride in mg/l 0.24 – 1.03 0.23 to 0.93 Phosphate in mg/l 0.38-0.61 0.24 to 0.55
Pesticide in mg/l Absent Absent
Iron in mg/l 6.25 Not Available
8 Meters below ground level
9 Source: Pollution Control Research Institute, BHEL, Hardwar
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
63
5.1.7 Storm Water Drainage
Storm water drainage system is not proper throughout Allahabad city. The city has been
divided into the six storm water planning zones (Morigate, Mumfordganj, Rajapur, Chachar
Nala, Gate No. 9 and Gate No. 13); each zone is identified by the pumping station or the
channel dealing with its discharge. As per the GIS maps provided by Allahabad Nagar
Nigam department, approximately 60-65 percent of area in sewerage district ‘A’ has storm
drainage system as shown in Figure 5.6. Rainwater flows through these drains to nearby
nallas, eventually falling into river Ganga and Yamuna. The human and animal waste
accumulated on the surface is flushed by runoff and carried to rivers by these drains thereby
polluting river waters. As these drains pass from residential areas, they create foul smell and
unhygienic conditions. Further the problem of choking of storm drains due to polythene
bags and solid waste causes water logging during the off-season rains and flooding during
monsoon.
Plate 5.1 Storm water drains visibly clogged with waste in Civil Lines (left) and flooding
upon rainfall in sewerage district ‘A’ (right)
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
64
Figure 5.6 Map showing the drainage system in sewerage district ‘A
5.1.8 Waste Water Management
As already explained in section 2.2 of this report, the sewerage system in the Allahabad city
is old and covers only 45% of the city area and most of this is within the central core of the
city i.e. District A and D. As of 2010, about 232 million liters of waste water is generated
every day in Allahabad city with an average per capita wastewater discharge of 152 liters.
Jal Sansthan is responsible for maintenance and collection of revenue from house
connections for whole of Allahabad city.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
65
Plate 5.2 Open sewage drain behind residence in Krishna Nagar
Wastewater generated from sewerage district ‘A’ is mostly residential with limited
commercial and nil industrial wastes. Table 5.10 below provides the wastewater
characteristics of Chachar and Ghaghar nala located in sewer district ‘A’ which indicates
that waste water exceeds the General standard for discharge on inland surface water in
terms of BOD and TSS.
Table 5.10 Wastewater characteristics of Chachar nala and Ghaghar Nala in sewerage
district ‘A’
Parameter Chachar
Nala
Ghaghar
nala
General standard for
discharge on inland
surface water as per CPCB
BOD(5 day sat
20°C) (mg/l)
32 67 30
COD (mg/l) 69 144 250
TSS (mg/l) 98 648 100
pH 7.0 7.5 5.5 to 9.0
Temperature (°C) 29 28 shall not exceed 5°C above
the receiving water Source: DPR for Sewerage district A10
10 Draft Detailed Project Report of Sewerage Project in Sewerage District ‘A’ of Allahabad City, 2010.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
66
As per 2010 population data, nearly 62.80 mld of wastewater is generated from sewer
district ‘A’ which generally flows in the open drains. 60 mld capacity Naini STP has been
constructed in sewerage district ‘A’ for tapping and treating the wastewater flowing in such
drains. It is further projected that the total sewage generation in this sewerage district will
increase to 74.36 mld by the year 2025, thus creating a treatment capacity gap of 14.36 mld.
5.1.9 Solid Waste Management
As per Nagar Nigam, about 540.0 MT of solid waste is generated every day in Allahabad
city. It has been assumed that the local residents of towns generate solid waste at the rate of
about 400 grams per capita per day on an average. This average generation of solid waste
includes local inhabitants (comprising the wastes generated by the resident population,
shops and commercial establishments, vegetable and fruit markets, construction and
demolition and hospital wastes – non-infectious and non-hazardous) and the floating
population in the town.
The solid waste from sewerage district ‘A’ is mainly from residential areas and very little
comes from commercial areas. As per the data provided by Nagar Nigam, the total solid
waste generated from sewerage district ‘A’ is approximately 162.07 MT as shown in Table
5.12. With growth in population, the per capita waste generation is also expected to increase
thereby increasing the solid waste.
Table 5.11 Solid waste generation in sewerage district ‘A
Location Population (as of
2010)
Average solid
waste generation per capita per day
Total solid waste
generated in MT
Sewerage District ‘A’
of Allahabad city
405176 400 162.07
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
67
The solid waste management in sewerage district ‘A’ is handled by Allahabad Nagar
Nigam, which involves primary collection, storage at source of generation, segregation of recyclable materials, transportation, and treatment & disposal. Recently a new solid waste
management plan for the entire Allahabad city has been prepared and is being implemented
under JNNURM scheme. Practically, the wastes are not being treated properly as the solid waste is not being collected and transported to the current waste processing plant at Baswal.
Further, the waste generated is being transported to different sites for open dumping on
land. Representative pictures of observed open dumping of solid waste in sewerage district
‘A’ are shown in Plate 5.3.
Plate 5.3 Open waste dumping at Kydganj area (top) and Yamuna Bank (bottom).
As a result of such practices the entire area in and around the disposal sites is unhygienic
and poses a serious threat to the environment and to the public health. Open dumping of
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
68
wastes also causes choking of sewers which in turn leads to water logging throughout the
city.
5.1.10 Biological Environment
5.1.10.1 Green cover
1. Gardens/ Parks: There are no important or archeologically identified gardens/ parks in
sewerage district ‘A’. However the region has small residential parks as sited from the
GIS maps provided by Allahabad Nagar Nigam department, which will not be
threatened by the proposed sewer works, since the sewers are planned to be laid in the
middle of the road and will not pass through these areas. The location of these parks in
sewerage district ‘A’ is be represented in Figure 5.7. Some of the residential parks include Habib Park, Guru Teg Bahadur Park, Jaagriti Park
Figure 5.7 Map of parks in sewerage district ‘A’
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
69
Tree Cover: Trees can be seen along the road side in almost all parts of sewerage district ‘A’.
Practically none of the trees will be disturbed nor damaged (tree cutting), since they are
located on the edges and sides of roads, away from the centre, along which the sewers are
planned to be laid as shown in Plate 5.4.
Plate 5.4 Road side trees in Civil line area
Agriculture: There is no agricultural practice in sewerage district ‘A’ of Allahabad city. This
district is the core city area with mix of residents, commercial areas, institutes, hospitals etc.
5.1.10.2 Flora
Allahabad district as a whole has around 19839 hectares of reserved forest area falling under
the jurisdiction of the state forest department. Until the beginning of the present century,
patches of 'dhak' were found in the trans-Ganga tract mostly between Phulpur and Sarai
Mamrez, along the bank of the Sasur Khaderi, but most of them were cleared for agricultural
purposes during the following decades. Patches of Baul could also be seen towards the right
bank of the Ganga. Forests now exist mainly in the trans-Yamuna tracts in Bara tahsil and
the southern tracts of tahsil Meja.
Presently there is no forest cover in and around the sewerage district ‘A’ of Allahabad city.
The project site is mostly residential area and does not have any protected or reserved forest
area. The site also does not fall under India’s notified ecological sensitive areas. This is
evident from Figure 5.8 a, which shows the closest eco-sensitive zones (points A, C and D)
and their average distance from Allahabad.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
70
Figure 5.8 Mapping of eco-sensitive areas around Allahabad city
Source: Google Maps
5.1.10.3 Fauna
The number and species of wild animals are much greater in the trans-Yamuna tract than
elsewhere in the district. The Hyaena (Hyaena hyaena) and the Boar (sus secrofa), which do
much damage to the crops, are also found in the flood plain of the Ganga and the doab. The
Fox (Kulpus bengalensis), the Hare (Lepus rufica udatus), and the Sahi or Indian porcupine
(Hystrix leucura) are found throughout the district. Apart from these, the Gangetic Dolphins
were once found in abundance in the river Ganges. But over the years a steady increase in
pollution in the river has reduced the population of Dolphins. The River Dolphin was
declared as the National Aquatic Animal of India and on January 19, 2010, the Ministry of
Environment & Forests (MoEF) included it in Schedule I for the Wildlife (Protection) Act,
1972.
As mentioned in section 5.10.2 above, there is no eco-sensitive zone in and around the
sewerage district ‘A’ and Allahabad city as a whole as shown in Figure 5.8a. The proposed
project will have a positive impact on aquatic life, as it intends to tap all the waste water
discharge into the river and this will directly improve the river water quality.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
71
5.2 Baseline Social Status
Allahabad city been growing continuously and there has also not been much variation in the
growth rates over the past few decades except for the decade 1961-71. In this particular
decade the growth rate of the city had fallen to 19.11%, the reasons for which are unknown.
Apart from that Allahabad has been growing at a pace faster than the state.
Figure 5.9 Allahabad urban population growth rate
Source: City Development Plan report
Allahabad district is a large, rural district with a very vulnerable population. Its Scheduled
Tribe population (21.58%), consists primarily of the Chamar and Pasi castes. It also has a
relatively low literacy rate of 62.11% in which, predictably, women fall far below the average
at 46.38% while men are better in the average with a rate of 75.81%. Women are also at a
disadvantage in terms of sex ratio, though this appears to be improving as the age 0-6
population shows an increase of 38 females (from 879 to 917) per 1,000 males. Most people
in the city are unemployed (~66%); among those that are employed, 33% are marginal
workers while the rest are main workers. In terms of education, only 6% of the district’s
population has no education at all, while a little less than 35% has a Diploma-equivalnt or
above. This distribution leaves the vast majority of the population somewhere in the middle
with only a basic education; for example, the percentage of the population (43%) with
Primary or less than Primary education exceeds those with Diploma or above, making these
former two groups the largest segment of the population. This lack of education contributes
to populations’ overall vulnerability. In the district, roughly half of all houses are
permanent, while nearly all of the rest are semi-permanent; only a small percentage is
considered temporary.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
72
Table 5.12 Percentage distribution of the household population by age and sex, Allahabad
Drinking water facilities, safe drinking water, and power supply are quite common;
electricity access if more common for domestic uses than agricultural ones. Fitting with the
educational background of the area, primary schools are common while institutes of higher
education are very few. Medical facilities also appear to be in relatively short supply. Paved
and mud roads are nearly equal in prominence, and both appear fairly common. For more
details refer to Annexure (3).
Allahabad has 185 slums spread all over the city. The total population living in slums is
318,000 which is about 30% of the entire city population. It is estimated that one-third of the
slum population can be categorized in the urban poor category. Meera Ganj slum is located
in the middle of Allahabad city. The population in the low-income group is mainly found in
Wards 11, 34, 41, 57, 66, 71, 75 and 77, which includes localities such as Malakraj, Minhajpur,
Nai Basti, Sarai Garhi, Narayan Singh Nagar, Meera Gunj, and Bashi Bazar. Meera Gunj
slum is located at the centre of Allahabad city. Apart from the slums, there are many people
who live in housing that falls under the categories of S.D.P. (Integrated Housing and Slum
Development Programme), S.C.S.P. (Schedule Caste Sub Plan), and I.L.C.S. (Integrated Low
Cost Sanitation).11
Allahabad’s sewage system dates back to 1910 and covers 45% of the city. The city has two
STPs: Naini (60mld) and Salori (29mld; will be expanded by 14mld under proposed project).
Allahabad sewerage district A comprises of 27 wards. Most of the land use in District A has
been identified as residential and commercial, through the field survey.
The existing population and the projected population for the design period year are
described in the table below;
11 Source: www.uhi-india.org - Allahabad City Profile – February 2010
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
73
Table 5.13 Ward wise census population and projected population and observed land use.
Ward Ref.
No.
Ward Land use observation in field Population Projected Population
2001 2010 2025 2040
10 Civil Lines
Mix Residential/Commercial, High income groups, heavy traffic, roads
comparatively wider and better. Posh
colony with a mix of commercial and
residential. Not congested. Sewer line had
been laid down before the rains causing a
few problems to residents, shop keepers and pedestrians. The dug up area has not
been properly laid back
12434 16537 19584 21026
11 Malakraj Mix Residential/Commercial, middle and low income groups. Congested
10612 14114 16714 17945
17 Nyaymar
g
Mostly Institutes and Government offices,
not congested
12062 16042 18998 20397
23 Krishna
Nagar
Mostly residential, some shops and
institutes, banks, etc. Very congested
10654 14170 16780 18016
31 Medical College
Institutional area, not congested, few residents
8395 11165 13222 14196
34 Minhaj
Pur
Mix Residential/Commercial, Middle and
low income groups, very congested
11011 14645 17342 18620
41 New Basti Residential with slums near the Yamuna
Banks, Middle and low income groups,
very congested
10600 14098 16695 17925
51 Katghar Mix Residential/Commercial, middle
income groups, congested
11774 15659 18544 19910
55 Chaukhandi
Residential with markets, congested 10521 13993 16571 17791
57 Sarai
Garhi
Middle and low income groups,
extremely Congested
11333 15073 17849 19164
58 Dariyabad Mostly residential, Congested 10996 14625 17319 18594
60 Muthi
Ganj
Mostly Commercial (with a few residing
in floors above shops), extremely
congested
12080 16066 19026 20427
61 Khalashi
Line
Mostly residential, extremely Congested 11734 15606 18481 19842
63 Shahganj Mix Residential/Commercial, Congested 10817 14387 17037 18292
65 Dariyabad Mostly residential, Congested 13660 18168 21515 23099
66 Moht Mix Residential/Commercial, Middle and
low income groups, Congested
10603 14102 16700 17930
67 Rambagh Mostly Commercial (with a few residing
in floors above shops), congested
10752 14300 16850 18182
68 Muthi Ganj
Mostly Commercial (with a few residing in floors above shops), very congested
10875 14464 17128 18390
71 Narain
Singh Nagar
Mix Residential/Commercial, Middle and
low income groups, Congested
10602 14101 16698 17928
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
74
72 Sultanpur
Bhawa
Commercial with mix of residential, very
congested
12584 16737 19820 21280
73 Malviya Nagar
Mostly residential, Congested 13295 14567 17251 18522
74 Bahadur
Ganj
Extremely Congested 10961 14578 17264 18535
75 Meera
Ganj
Middle and low income groups, Slums,
Congested
11815 15714 15609 19979
77 Bakshi Bazaar
Commercial, Middle and low income groups, congested
13650 18155 21499 23082
78 Atala Residential, Middle to low income
groups, larger Muslim population,
Extremely congested
13316 16198 19182 20595
79 Attar
Suiya
Mostly residential, very congested 11996 14033 16618 17842
80 Dayra
Shah
Azmal
Mix Residential/Commercial, Very
congested
10435 13879 16435 17646
Sub Total
(A)
309567 405176 479731 515155
Population density in Allahabad Sewerage District A: Allahabad sewerage district A
accounts for the central city core and as a result is very dense (300 persons/ha).
Table 5.14 Ward wise population density of Allahabad
The table shows that out of twenty seven wards only four wards i.e. Civil Area, Nyaymarg,
Medical College and Rambagh are in the category of under 200 people per hectare. However
it was observed during the field visit that Rambagh had areas that were very congested. As
per the analysis done by District Urban Development Authority (DUDA) all of the six wards
that had a density of more than 600 people per hectare including all the six wards with a
density of 400- 600 people per hectare fall in district A.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
75
Figure 5.10 Map indicating major land use and social survey locations for District A
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
76
Cultural Significance
Allahabad or City of God in Persian is also known famous by the name of Prayag and
Sangam. Haridwar, Allahabad, and Varanasi are the three holy towns which attract
thousands of pilgrims to its waters. Allahabad stands at the confluence of two of India’s
holiest rivers, the Ganga and the Yamuna. Sangam, as the confluence is called, is the venue
of many sacred fairs and rituals, and attracts thousands of pilgrims throughout the year.
This number swells to millions during the world-famous Kumbh Mela. A third mythical
Saraswati river, believed to flow underground towards the Sangam, gives the confluence its
other name 'Triveni'. Thousands of Hindu pilgrims arrive at this town to take a dip in the
Ganges (Plate 5.5), which is believed to cleanse oneself of sins and help attain salvation.
During festival of Chatth, Ganga ghats attracts thousands of devotes and tourists.
Plate 5.5 Auspicious bathing at Allahabad Kumbh mela 2007 (left) and Aarti pooja delivery
during Kumbh
5.2.1 Public Consultation
The approach and methodology followed for social baseline study as well as the social
survey has been discussed in the Section 2.6.
Group discussion and stakeholder consultations were performed during the field surveys to
assess the situation and get the feedback about the project from all the concerned
stakeholders. Household owners in all the 27 wards were consulted, additionally other
important set of locals interviewed or consulted were pedestrians, shop-owners, mobile
vendors, members of sensitive places like hospital staff, school teachers, etc. Some of these
27 wards have academic and government institutions and most of them are residential in
landuse. There were no tribal population in the surveyed areas and it is in agreement with
the fact stated by census of India also.
All these people are already witnessing the construction impacts happening during ongoing
execution of JNNURM project. General perception about the ongoing project of JNNURM
and upcoming project of NGRBA was good. All the local stakeholders accepted the project
with positive gesture and have just given few suggestions based on their experience with the
ongoing project, which could help in better execution of the project.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
77
Households surveyed were from both rich and poor colonies and was a heterogeneous
group of male and females. Most of the household have access to drinking water facilities
and electricity and have toilets as well, but most of the toilets are not connected to sewer
networks. They have pit toilets as disposal system. But most of them responded that they are
not aware that whether their household will be connected to sewer network or not.
Figure 5.11 Connection to sewers
One of the important question that was asked to communities was on the consequence of
construction of this project on certain factors like traffic, health, noise, livelihood etc. showed
the following result;
Figure 5.12 Problems encountered during construction phase
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
78
The figure clearly shows that traffic congestion is the most highly ranked problem. 50% of
the respondents feel that construction will lead to more traffic congestion. This is followed
by noise as a problem during the construction phase. Pollution in terms of dust generation is
the next problematic area according to the respondents and finally 10% of the respondents
mentioned that basic services like water and electricity lines will be damaged.
Table 5.15 Ward wise details of the survey is enlisted below in the table
Consult
ation no.
Place Date No. of
Participants
Nature of
participants
Key issues raised
1 Civil Lines 22/8/11 4 Residents, shop
keepers,
women
Execution to happen in time
Construction should
not happen in monsoon
2 Malakraj 22/8/11 4 Mix
residential
and
commercial.
Traffic congestion
3 Nyaymarg 22/8/11 3 Officials
visiting
institutional
area
Noise and dust during
construction
4 Krishna Nagar
22/8/11 4 Residents Traffic congestion, dust generation
5 Medical
College
22/8/11 4 Members of
institutions, hospital staff
Noise and dust
pollution. Debris is not cleared on time
6 Minhaj Pur 22/8/11 3 Residents :
females
Traffic congestion.
But overall impact will be good
7 New Basti 22/8/11 3 Residents Inconvenience to daily
life routine 8 Katghar 22/8/11 4 Residents:
females
Traffic congestion, no
prior information is
provided to the
residents
9 Chaukhan
di
22/8/11 3 Shop owners Congestion and dust
generation 10 Sarai Garhi 22/8/11 4 Residents,
mobile
vendors
Traffic congestion,
piles of excavated soil
which is not disposed off
11 Dariyabad 22/8/11 5 Residents,
and pedestrians
Traffic congestion and
inconvenience to daily life
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
79
12 Muthi Ganj 22/8/11 5 Show
owners
Already congested
area, so will be more
chaotic
13 Khalashi
Line
23/8/11 3 Residents Traffic congestion
14 Shahganj 23/8/11 5 Mix group
(residential and
commercial)
Traffic congestion
15 Dariyabad 23/8/11 3 Residents: female
Traffic congestion, dust, inconvenience in
daily routine life
16 Moht 23/8/11 3 Shop owners Dust generation
17 Rambagh 23/8/11 4 Shop owners Traffic congestion
18 Muthi Ganj 23/8/11 5 Shop owners Traffic congestion
19 Narain Singh
Nagar
23/8/11 4 Shop owners Traffic congestion
20 Sultanpur
Bhawa
23/8/11 4 Shop owners Traffic congestion,
Dust generation
21 Malviya
Nagar
23/8/11 3 Residents Traffic congestion,
noise pollution
22 Bahadur
Ganj
23/8/11 4 Residents Traffic congestion,
noise pollution
23 Meera Ganj 23/8/11 3 Residents Traffic congestion,
Dust generation
24 Bakshi Bazaar
23/8/11 4 Shop owners Traffic congestion, Dust generation
25 Atala 23/8/11 3 Residents Traffic congestion,
noise pollution
26 Attar Suiya 23/8/11 3 Residents: Female
Traffic congestion, Dust generation
27 Dayra
Shah Azmal
23/8/11 6 Mix group
(residential and
commercial)
Traffic congestion
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
80
Chapter 6 Environmental and Social Impacts Any development projects have associated environmental and social positive and negative
impacts. Planners and decision makers have realized the importance of understanding the
consequences of any such projects on both environmental and social sectors, and have
started integrating measures in project design to avoid any adverse impacts. Based on the
major findings of field visits and secondary data analysis, the possible environmental and
social impacts due to proposed sewerage subproject in district A are identified and
presented in following sections below.
6.1 Potential Environmental Impacts
The proposed project of sewer works in sewerage district ‘A’ would influence the
environment during all three following phases:
• During Design and Development phase
• During construction phase During operation phase
6.1.1 Design and Development Phase
Design with inadequate consideration to likely environmental impacts associated with
construction and operation stages may lead to significant environmental impacts due to the
projects. Anticipated impacts which either can be eliminated or minimize with design
consideration are identified at design stage and required measures are integrated in the
designs. The identified impacts requiring design stage considerations are stated below:
• Accidental leakages/burst in trunk sewerage line due to inadequate design ( non-
consideration of project population or sewage load) or lack of maintenance
provisions.
• Sewage Pumping Station locational specific : noise and odour nuisance, tree cutting,
• Alignment planning considering least shifting of utilities
6.1.2 Impacts during construction phase
The proposed sub-project consists of the following activities which include:
• Approximately 240.6227km long sewerage network
• Intermediate Sewage Pumping Stations at Bairahana, Kydganj (Gate No.9),
Bargadghat SPS
• Sewer cleaning equipment
The construction activities would generally include earthworks (excavation, filling,
shuttering, compacting), temporary diversion of existing sewer lines, civil construction
(sewer lines, STP, SPS, etc) and E & M installation and commissioning. The impacts of these
construction stage activities on the various environmental parameters are examined below:
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
81
i) Environmental sensitive areas
Based on observations and findings from field visits, interaction with government officials
and consultation with local residents, an assessment of the environmentally and ecologically
sensitive areas was made (Refer to screening checklist Table 3.1)..The nearest eco-sensitive
areas such as the Panna National Park, Dudhwa National Park and Jim Corbett National
Park are at a minimum distance of about 150 km away from the proposed project site. Small
residential parks (Figure 5.7) and road side trees (Plate 5.4) are located in this area, which
will not be affected by the proposed sewer works, since the sewers are planned to be laid in
the middle of the road and will not pass through these areas. With regard to sensitive
aquatic areas and water bodies, there are none. It was also observed that the major land use
pattern of District A is residential, with no agricultural and no forest areas.
There are no major tourist areas falling under sewerage district ‘A’, except Sangam area
which is mainly utilized by tourists/ pilgrims for conducting aarthi Pooja or homm-havans
and for having a holy bath especially during festival times. Out of the four ASI
(Archeological Survey of India) monuments in Allahabad city which include Allahabad fort,
Alfred park, Khusrau Bhag, and Cemetery at Kydganj, only 1 is within the boundary of
sewerage district ‘A’ which is the cemetery in Kydganj. This will not be affected by the
proposed sewer works as the sewerage lines will pass through considerable distance (more
than 200m away) away from the cemetery boundary. As the Central Government has
declared upto 100 meters from the protected limits to be prohibited area and further beyond
it up to 200 meters to be regulated area for purposes of both mining operation and
construction. So, as per ASI official, permission would be required if the construction of the
sewer line falls within 200 m distance.
ii) Air quality
Based on the field observation of ongoing JNNRUM projects and interaction/consultation
with stake-holders, it is expected that the levels of dust (RSPM and SPM), carbon mono-
oxide (CO), hydrocarbons and NOx (NO &NO2) is likely to increase during the construction
phase mainly because of:
• Excavation, backfilling, compaction activity and movement of vehicles on un-paved
roads (increases dust level)
• Vehicle exhausts from construction machinery and from light and heavy vehicles for
transportation of pipes and construction material like cement, etc (increases NO2).
• Use of portable diesel generators and other fuel fired machinery, and (increases CO).
A high concentration of SPM could also be a leading cause for eye, ear, nose and throat
infections and related discomfort. Laying of sewerage lines mainly falls in the residential
area, hence temporary impact on air quality in these areas is of greater concern.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
82
iii) Noise levels
The proposed construction activities are expected to increase the noise levels mainly due to
plying of construction vehicles, pumping machines, use of portable generators, mechanical
machinery such as cranes, riveting machines, hammering etc. These activities will occur
round the clock and the noise pollution thus created may affect human habitations,. As per
the baseline environmental status, the noise levels in sewerage district ‘A, are expected to be
within permissible limits as the area is mostly residential and has limited commercial, and
no industrial area. Facilities that are expected to feel the temporary impacts more than others
include schools/colleges (Allahabad Degree College, Kesrvidyapith Inter College, Ewing
Christian College), hospitals (Swarup Rani Nehru Hospital.
Jeevan Jyoti Multispeciality Hospital) and cultural centres like Shree Swami Narayan
Temple, Masjid – e- imam Sajjad, etc. However, these impacts are of temporary nature,
lasting only during the construction period.
iv) Water resources
From field visits, interactions and consultations, it was found that there were no water
bodies in the project area. The natural drainage channels of the project area are likely to be
affected in the following ways:
• Direct discharge from construction activities – If the construction wastes and
construction related material are not properly handled/ managed, then certain
impurities like suspended particles, pollutants like oil, grease, cement etc, may find
their way to the river Yamuna via storm drains during rainfall. (refer to Figure 5.6 for
drainage network of District A). There may also be temporary blockage of drains due
to unmanaged material and construction debris.
• Flooding is likely during monsoon as drainage paths could be obstructed and
redirected by the debris (noted during field visits and as per the Section 5.1.9 of
baseline environmental status); this concern was also voiced by residents. During
construction of sewerage works in District A, there may be flooding due to the
already blocked state of drains and nalas, due to poor solid waste management (refer
to Plate 5.3). Areas that are expected to face temporary flooding issues include Civil
Line area, Kydganj, etc.
• The excavation activities will be carried out up to a depth of 15 m or so, and will not
impact the groundwater levels of the region since a provision for dewatering and
lowering of water table has been made in the detailed project report.12
• Excavation may lead to damage to underground water supply lines or other utilities.
As per the baseline environmental status, the Biochemical Oxygen Demand (BOD) levels,
Total coliform and faecal coliform in the rivers are often above the permissible limits
12 Detailed Project Report (revised as per ECC Recommendations) of Sewerage Works in Sewerage District ‘A’ by
U P Jal Nigam, 2010-11
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
83
indicating possible contamination from municipal waste water discharges from the city.
Therefore this new sewer project will be have a positive effect on the river Ganga and
Yamuna, as the untreated sewage would now be diverted to sewerage district A (Naini STP)
and would not be let into the Yamuna13. Improved water quality provides cleaner water
supply to the city of Allahabad, safer irrigation water for the farmers around and
downstream of the city, and an improved bathing experience for the religious pilgrims that
visit the city.
v) Management and Disposal of Excavated Material during construction
The proposed project will have lot of construction involved and as such if the management
and disposal of excavated material is not properly done, it will impose a problem to local
people and residents. This would be a temporary impact but a mitigation measure for this
has been suggested. Top soil productivity will also be lost, if it is not preserved separately.
vi) Safety and traffic management: accidental damage due to erosion/sliding of vertical
sides of excavated trenches while placing pipes, Temporary flooding due to excavation
during monsoon or blockage of surface drains. Increased traffic inconvenience (emissions,
congestions, longer travel times, blockage of access) .
6.1.3 Impacts during operation phase
i) Water environment
Water resources in the project area would be the most positively benefited by the sanitation
project since additional sewage will now be routed to the STP. Therefore proper operation
and maintenance mechanism must be followed for efficient working of the system. The
probably environmental impacts related to water during operation stage may include
unpredictable events such as:
• Temporary flooding of adjacent areas due to accidental leakages/bursts and also due
to blockages and backlogging of lines.
• Water pollution and possibility of mixing with water supply line due to leakages/
overflows from the sewer lines
• Impairment of receiving water quality in surface/sub-surface source due to
inadequate /inefficient sewage treatment process.
ii) Noise and air quality
Improper handling and irregular maintenance of operating machines including pumps,
generators, air diffusers, etc may lead to increased noise pollution during operation activity.
There will also be minimisation of gas being emitted from the sewage drains, since during
operation, most of the works will be laid underground.
13 Mr. Rohit, Asst. Project Engineer, State Pollution Control Board, Allahabad
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
84
iii) Sludge Disposal from the Pumping Station and STP
It is possible that during the operation of pumping station and STP sludge generated may
not be properly handled. This could be a cause of concern from environmental aspect.
Plate 6.1 Traffic at Rambagh Chauraha
6.2 Potential Social Impacts
The proposed project of sewer works in sewerage district ‘A’ would influence the social
sector in a distinct phase of construction period which would be temporary and short term.
Social Impacts
i. Impact on human health
One of the potential impacts of the proposed sub-projects will be on the air quality due to
the dust generated during excavation and tunneling. The amount of dust generated will
depend upon the level of digging and the prevailing weather conditions and can have an
adverse impact on the health of the persons residing or working near the project sites.
Increased dust was witnessed during the field visit during construction of JNNURM-related
sewage projects. Since the district has more of residential land use, the number of people
who will be affected is more. Residential population includes more vulnerable groups such
as the elderly and children. Some of the residential colonies are Krishna Nagar, New Basti,
Chaukhandi, Khalashi Line, Dariyabad, Atala, Attar Suiya, etc.
ii. Traffic Congestion
Due to the excavation work which will take place on the main roads of the city, there will be
a disturbance in the traffic movement. People may suffer some inconvenience during the
morning and evening peak hours. This issue is discussed in the DPR, and suggests de-
routing of the traffic as the mitigation measure. Few residents at Civil Lines also complained
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
85
that they were unable to move their cars due to the excavation outside their house.
Commercial areas such as Rambagh, Muthi ganj, etc. are very busy congested areas; any excavation in this area will inhibit traffic movement. Diversion of traffic maybe required for
such areas. This issue is discussed in the DPR.
Figure 6.1 Road network map of District A indicating majority of roads have width less than
5 units. Around 97.39% of the roads have width less than 5 units, where the chances of traffic
congestion could be high
iii. Impact on livelihood
The excavation and tunneling work will lead to road blockage and as a result the
commercial establishments and vendors will have some trouble in operating their business
on daily basis. But there will be no loss of livelihood. Ambulatory vendors can very well
shift their place as and when required. So, overall no loss of livelihood has been reported
during the survey.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
86
As per anecdotal evidence gathered in the field visit, most shop-owners and mobile vendors
are welcoming the sewage project implementation as they see a direct benefit of improved
living and working conditions. They are aware of, and prepared to face temporary
inconveniences caused by construction if the project is implemented in a timely manner.
However, the same interviewees felt that they had little confidence in the ability of the
agency to execute a project in an efficient manner. They had grievances with the long
duration of construction work.
Plate 6.2 Interview- Mobile vendors
iv. Impact on existing utility services
The road opening activities may damage the underground water pipelines or electricity
poles in the vicinity of the site for the proposed sub-projects. This will lead to water supply
interruptions, disruption in electricity supply and will involve expensive repair costs.
Flooding of areas could also occur. Officials of UP Jal Nigam stated that they receive some
complaints about water line brakeage during the construction phase. With no other
alternative source readily available, people have to buy water from private tanks or buy
bottled water for drinking purpose till the time service is restored to normal. The DPR also
notes impacts on utility services as a potential issue.
v. Safety hazards
There are potential hazards for the workers as well as for the pedestrians. Additionally,
there have been reports, gathered during the field visit and interviewing that, of children
falling into holes left open by construction crews on JNNURM projects, and children were
seen playing around active construction sites. Resident of locality Allahabad stated that they
have witnessed such causality during construction. Safety equipment for workers is
provided as part of the DPR.
vi. Elevated Noise Levels
Increased noise pollution was noted during JNNRUM construction from construction
equipment. This will disturb residences, and especially schools and institutes in and around
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
87
Civil Lines area, Medical College area, etc. For elderly and students, noise is disturbing and
affects their comfort. This could be a problem especially in sensitive areas like school and
hospitals.
vii. Failure to Restore Temporary Construction Sites
Excessive debris, trash or construction remnants (e.g. dirt piles) would create problems
related to drainage, unhygienic conditions and poor aesthetics; however, clean-up and
debris clearance is budgeted in the DPR so this should not be a concern.
viii. Affect to daily life
Resident of Civil Lines colonies complained that during construction in JNNURM projects,
they were not able to take out their vehicles from their house premises and even there was
no space outside for parking.
ix. Land Acquisition
Consultations with relevant officials including UP Jal Nigam officials, Revenue Department,
community, other sources14 and first-hand observations during the field visit no additional
land is required for the project, as sewage construction will not result in land seizures of any
kind. Moreover, the SPS compound would need around 1000 m2 of land. The land on which
the SPS is proposed to come up belongs to the government and has no habitation. Hence, no
relocation would be needed, as per the dialogue with UP Jal Nigam officials. Moreover there
would be no loss of community assets during the construction as noticed during field survey
and interaction with the local people. Also Figure 5.10 indicate that the project construction
will happen in public land, there will be no agricultural or forest community land
requirement for laying sewer lines.
6.3 Conclusion
Based on the overall secondary data analysis and field investigation, the proposed project is
expected to benefit the Allahabad City, as the wastewater that currently flows untreated into
the Ganga river will be captured, treated and the remainder of the treated effluent will be
allowed to flow into the river. The likely beneficial impacts of the projects include
• Improvement in sewerage collection and treatment within the cities/towns
• Prevention of storm drains carrying sanitary sullage or dry weather flow
• Prevention of ground water and soil pollution due to infiltration of untreated liquid
waste
• Prevention of discharge of untreated sewage into River Ganga
• Improvement in water quality of River Ganga, a national resource
• Improvement in environmental sanitation health and reduction in associated health
hazards within the cities/towns
14 Detailed Project Report (revised as per ECC Recommendations) of Sewerage Works in Sewerage District ‘A’ by
U P Jal Nigam, 2010-11.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
88
• Improvement in quality of life, human dignity and increased productivity
• Reduced nuisance of open defecation due to low cost sanitation and reduced
malarial risks and other health hazards
Although there would not be any permanent negative or adverse environmental impacts,
but will have temporary impacts, that can be mitigated with appropriate mitigation plans.
However, the large environmental benefit of the project greatly outweighs the temporary
inconveniences.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
89
Chapter 7 Mitigation and Management Plan
7.1 Environmental Management Plan
Table 7.1 summarizes the generic environmental management plan for low category
investment that identifies the potential issues of various activities that are anticipated in the
design and development, construction, and operation phases of the proposed sewer work in
sewerage district ‘A’. The environmental management plan ensures to suggest appropriate
mitigation measure against the issues/ concerns identified during the environmental and
social assessment study.
In general, the Uttar Pradesh Jal Nigam (UPJN) (with assistance from Contractor and
Independent Engineer/Supervision Consultant) is the responsible entity for ensuring that the
mitigation measures as suggested in the ESMP. The roles and responsibilities of the involved
institutes are described below.
7.1.1 Implementation of EMP Specific activities by UPJN
The role of UPJN in the implementation of EMP involves the following activities:
• EMP clearance from NMCG and World Bank and disclosure as required;
• Integrating the EMP in the bid document of contractor as an addendum;
7.1.2 Specific activities by Contractor
The activities to be performed by the contractor to implement the EMP shall comprise the
following:
7.1.2.1 Implementation of EMP
The contractor shall be responsible to implement the EMP primarily in assistance with the
Project Management Consultant team. The Environmental Specialist from the Independent
Engineer/ Supervision Consultant shall monitor the compliance of the EMP and all the
design drawings of various civil structures shall be implemented after his approval.
The State, local Government will be responsible for Coordination, Monitoring and
evaluation of the Environment Management Plan. It should ensure all the safeguarding
plans are in line and acted upon. Contractor shall report the implementation of the
Environment Management Plan to the Environmental Expert and the Project management
consultant as well as to UP Jal Nigam through monthly reports. Further a quarterly report is
required to be prepared and required to be given to National Mission for Clean Ganga
(NMCG) for the progress made in implementing the Environment Management Plan.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
90
Feedback from the local residents can also be taken from time to time to cross check the
contractor’s report. Project management consultants should make inspection visits at
construction site to check the implementation of Environment Management Plan as per the
contract. Broad Institutional arrangement for implementation of EMP is shown in figure 7.1
below:
Chief Engineer-Allahabad Zone
Scheme Implementation Team (including EMP and R&R implementation)
UPJN
Project Manager (Contractor)
Environmental Officer
(Contractor)
Team Leader
(Supervision Consultant)
Environmental Expert
(Supervision Consultant)
State Pollution Control Board
PM-1 PM-2 PM-3
GM-Ganga Pollution control unit
Figure 7.1: Organization Structure for Implementation of EMP
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
91
Table 7.1 Environment Management Plan
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
Sewerage and Sanitation Investments
A. Design and Development Phase
Sewerage
Network (
Trunk Sewer
Line)
Accidental
leakages/
bursts
Due to accidental burst or
leakage of sewers, flooding
of the nearby areas
Backlogging due to
unexpected heavy flow
rates
Temporary Designing sewers with adequate capacity
and flow velocity
Provision for Regular inspection and
maintenance of the sewers
Preparation of safety and Emergency
Preparedness plan
DBO Operator
Sewage
Pumping
Station
Location of
Sewage
Pumping
Station and
Pumping of
sewage in
District A
Noise and odour nuisance
hazards to neighboring
areas.
Cutting of Trees
Permanent
Ensure minimum noise generation at
pump station in SPS by use of less noise
generating equipment meeting prescribed
noise standards as applicable and
enclosed generators.
Minimize Tree cutting if involved.
Tree plantation of at least two rows
around the periphery of SPS site and
landscaping to prevent spread of bad
odour with large canopy/ broad leaves
trees like Sesum, Neem, Bargad, Teak, Sal,
etc.
Accumulated sludge and solid waste to be
cleared at short intervals and spraying of
suitable herbicides on accumulated
sludge/solid waste to reduce odour.
Provision for regular maintenance and
switching off equipment when not in use;
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
92
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
B. Construction phase
Sewerage
(laying of
sewers) and
Sewage
Pumping
station
Excavation,
cutting, back
filling,
compaction
and
construction
operations
Damage to underground
utilities like water, gas line,
electricity and telephone
conduits, etc due to
construction activities.
Temporary Identify existing underground other
utility structures, lines through available
records and in consultation with
concerned authorities and plan
construction activities accordingly to
minimize damage to such utilities. these
underground utilities encountered in
excavating trenches carefully shall be
supported, maintained and protected
from damage or interruption of service
until backfill is complete and settlement
has taken place
DBO Operator
Accidents/ damages due to
erosion/ sliding of vertical
sides of excavated trenches
while places the pipes
Temporary Maintaining excavation by shoring trench
sides by placing sheeting, timber shores,
trench jacks, bracing, piles, or other
material
Exposed surface shall be resurfaced and
stabilized. Exposed surface will be
resurfaced and stabilized by making
sloping sides of trench to the angle of
repose at which oil will remain safely
DBO Operator
Generation of substantial
debris, top soil and muck
during construction
Temporary Top soil shall be preserved and may be
used for agricultural purpose or
development of city parks.
Soil and debris may be managed for
planned land filling and landscaping;
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
93
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
Debris may be suitably stored to filling
back the excavated areas after placing the
trunk sewer lines.
Dust Generation ( Air
Pollution) due to
excavation, cutting, back
filling and compaction
operations
Temporary Water sprinkling over excavated areas,
unpaved movement areas and stockpiles.
Transportation of loose construction
material through covered trucks.
Use dust curtains (polysheets/ sheets)
around the construction area for
containing dust spread at SPS building
construction site.
Construction equipment must comply
with pollution norms and carry Pollution
Under Control certificate.
DBO Operator
Noise and vibration
disturbances to residents
and businesses
Temporary Construction activities to be carried out in
day time with prior intimation to local
residents and shop keepers.
Construction work near schools and
colleges to be carried out during vacations
and work near hospitals to be completed
on priority basis (in shorter time period
with alternate provision of traffic,
accessibility of exit/entry gates etc.).
Use of low noise and vibrating equipment
meeting prescribed noise standards.
Provision of protective equipment (PPE)
like ear muffs and plugs for construction
workers.
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
94
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
Provision of noise barriers in inhabited
areas, particularly near sensitive zones
like hospitals, schools etc.
DG set to be fitted acoustic enclosure.
Temporary flooding due to
excavation during
monsoons or blockage of
surface drain
Temporary Stockpiled areas to be bordered by berms;
Stockpiles to be done in high areas to
avoid flow in storm water run-off
channels and erosion
DBO Operator
Increased traffic
inconvenience (emissions,
congestions, longer travel
times, blockage of access)
Temporary Alternate traffic routing must be adopted
in consultation with concerned traffic
police authorities. Proper traffic planning
be made for narrow lane areas.
Work should to be completed on priority
near business and market place to
minimize business loss.
Care should be taken to minimize
congestion and negative impacts at
schools and hospitals. Safe access shall be
maintained to these places during
construction.
Provide temporary crossing/ bridges as
may be required to facilitate normal life
and business
DBO Operator
Settlement of backfilled area
after construction
Temporary The backfilling material shall be free from
petroleum products, slag, cinders, ash or
other material.
Backfilling activity shall be completed
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
95
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
within five days of laying of sewer.
Proper compaction as per the soil
condition and retain the original level of
alignment and grade.
Spillage of fuel and oil Temporary Care to be taken to store fuel and oil (if
required) at a place away from any
drainage channel/nalla preferably to be
stored in drums mounted on a concrete
paved platform with slop draining to
small spills collection pit.
DBO Operator
Nuisance due to solid waste
disposal
Temporary Provide two bins for recyclable and non-
recyclable wastes.
Ensure that recyclable and non-recyclable
wastes are collected in segregated manner
in theses bins before disposal. Recyclable
material should be sold. Non-recyclable
material should be disposed for
designated land fill area of the city.
Provide adequate sanitation facility for
workers at construction sites.
DBO Operator
General:
safety
during
construction
Accidents Safety hazards to labours
and public
Temporary Comply with the Occupational health and
Safety regulations of India
Ensure that the contact details of the
police or security company and
ambulance services nearby to the site.
Ensure that the handling of equipment
and materials is supervised and
adequately instructed.
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
96
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
Erect warning signs/ tapes and temporary
barriers and/or danger tape, marking
flags, lights and flagmen around the
exposed construction works warn the
public and traffic flow of the inherent
dangers.
Provide adequate safety precautions such
as helmets, safety shoes, gloves, dust
masks, gumboots, etc. to workers
Monthly reporting of all accidents and
immediate reporting to DBO engineer and
owner
C. Operation phase
Sewer line Leakage/
overflows
Water pollution and
possibility of mixing with
water supply line
Temporary Regular monitoring of sewer line and
manholes for visible leakages/ overflows.
Immediate repair shall be carried out to
plug the leakages. Restore the sewer and
other utility services if damaged due to
leakages.
DBO Operator
Sewage
Pumping
Station
Waste
Handling
Bad odour, Health hazard
and
public nuisance
Temporary Provision for regular clearance of sludge
and solid waste to minimize odor
nuisance
Ensure maintenance of Green belt as
planned
Periodic disposal of accumulated
sludge/solid waste to disposal site as
approved by DBO engineer.
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
97
Activity Potential Negative
Impact/Concern
Duration of
impact
Mitigation Measures Responsible
agency
Sewage
Cleaning
Equipment
Extracted
Sewage Sludge
handling and
cleaning
equipment
maintenance
waste handling
Bad odour, Health hazard
and
public nuisance and
possible land
contaminations
Temporary Ensure that extracted sewage sludge
collected during sewers cleaning are
disposed to disposal site as approved by
DBO engineer.
Sewage solids shall not be disposed on
road sides or non-designated areas.
Equipment cleaning waste shall be
disposed to public sewer or STP inlet for
treatment
Waste oil if any generated shall be
separately collected. It shall be sold to
authorized waste oil recyclers.
DBO Operator
General
Safety
Workers
exposure to
toxic gases in
sewers and
hazardous
materials
during
sewer
maintenance
work
Serious/health/ safety
hazards
The toxic gases are likely to
contract communicable
diseases from exposure to
pathogens present in the
sewage.
Temporary During cleaning/ maintenance operation,
the sewer line will be adequately vented
to ensure that no toxic or hazardous gases
are present in the line.
Ensure availability of PPE for
maintenance workers.
Follow safety and Emergency
Preparedness plan prepared at design
stage
Monthly reporting of all accidents and
immediate reporting to DBO engineer and
owner.
DBO Operator
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
98
7.2 Environmental Monitoring Plan
The Environmental Monitoring Programme has been detailed out in Table 7-2. Successful
implementation of the Environmental Monitoring Program is contingent on the following:
• The Project Management Consultant (PMC) along with UPJN to request the
Contractor to commence all the initial tests for monitoring (i.e. for Air, Water Quality
and Noise Levels) early in the Contract to establish 'base' readings (i.e. to assess the
existing conditions prior to effects from the Construction activities being felt);
• The PMC along with UPJN to request the Concessionaire / Contractor to submit for
approval a proposed schedule of subsequent periodic tests to be carried out;
• Monitoring by the PMC's Environmental Officer of all the environmental monitoring
tests, and subsequent analysis of results;
• Where indicated by testing results, and any other relevant on-site conditions, PMC
to instruct the Concessionaire / Contractor to:
o Modify the testing schedule (dates, frequency);
o Modify (add to or delete) testing locations;
o Verify testing results with additional testing as/if required;
o Require recalibration of equipment, etc., as necessary; and,
o Request the Concessionaire to stop, modify or defer specific construction
equipment, processes, etc., as necessary, that are deemed to have contributed
significantly to monitoring readings in excess of permissible environmental
"safe" levels.
7.3 EMP Budget
The environmental budget for the various environmental management measures proposed
in the ESMP is detailed in Table 7-3 and the cost of the Environmental Monitoring is given
in Table 7-4. There are several other environmental issues that have been addressed as part
of good engineering practices, the costs for which have been accounted for in the
Engineering Cost. The rates adopted for the budget has been worked out on the basis of
market rates and the Schedule of rates. Various environmental aspects covered/will be
covered under engineering costs are listed below:
• Proper drainage arrangements to prevent water stagnation/ flooding in SPS site area
• Appropriate siting, and enclosing within building to reduce noise and odour
nuisance to surrounding area Drainage along the ghats to collect the discharge from
the residents and connecting to city sewer
• Alternate traffic re-routing,
• Ensuring storage of excavated soil material on the higher lying areas
• Solid Waste Management
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
99
Table7.2 Environmental Monitoring Plan
Env.
Component Stage Institutional Responsibilities
Parameter Standards/
Methods
Locations Frequency Implementation Supervision
Air
Qu
alit
y
Co
nst
ruct
ion
PM10 µg /m3,
PM2.5 µg/m3,
SO2, NOX, CO
CPCB
Sewer
Constructio
n Sites
Once in every
season (except
monsoon
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Op
era
tio
n
PM10 µg /m3,
PM2.5 µg/m3,
SO2, NOX, CO
Sewer
Constructio
n Sites
Once in a year
except monsoon
for first 5 years.
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Met
eoro
log
y
Co
nst
ruct
ion
Rainfall,
humidity, Wind
Speed, Wind
direction,
Temperature
USEPA's
Meteorological
Monitoring
Guidance for
Regulatory
Modeling
Applications
One
location
within
Allahabad
A district
Once in every
season
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Op
erat
ion
Rainfall, humidity,
Wind Speed, Wind
direction,
Temperature
USEPA's
Meteorological
Monitoring
Guidance for
Regulatory
Modeling
One
location
within
Allahabad
A district
Once in a year Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
100
Applications
No
ise
Lev
els C
on
stru
ctio
n Leq dB (A) (Day
and Night)
Average and Peak
values
Ambient Noise
Standard
CPCB
Sewer
Constructio
n Sites
Once in every
season (except
monsoon)
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Op
era
tio
n Leq dB (A) (Day
and Night)
Average and Peak
values
Sewer
Constructio
n Sites
Once in a year
except monsoon
for first 5 years.
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
So
il
Co
nst
ruct
ion
Physical
Parameter:
Texture, Grain
Size, Gravel, Sand,
Silt, Clay;
Chemical
Parameter: pH,
Conductivity,
Calcium,
Magnesium,
Sodium, Nitrogen,
Absorption Ratio
Consider the
following methods:
IS-2720 (Various
part);
Soil Chemical
Analysis by M.L.
JACKSON.
Soil Test Method by
Ministry of
agriculture
Sewer
Constructio
n Sites and
SPS
Once in every
season
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
101
Op
era
tio
n
Physical : Texture,
Grain Size, Gravel,
Sand, Silt, Clay;
Chemical
Parameter: pH,
Conductivity,
Calcium,
Magnesium,
Sodium, Nitrogen,
Absorption Ratio
Consider the
following methods:
IS-2720 (Various
part);
Soil Chemical
Analysis by M.L.
JACKSON.
Soil Test Method by
Ministry of
agriculture
Along
sewer
constructio
n sites, SPS
Twice in a year
(Pre-monsoon and
Post monsoon) for
first 5 years,
Contractor through
approved monitoring
agency/Lab
PMC, UPJN and
SPMG
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
102
Table 7.3 EMP Budget
Phase Component of
EMP Mitigation measure
Cost included
in the DPR
(Yes/no/not
clear)
Cost in Rupees
(or Details if
provided in DPR)
Remarks
Design
and
Develop
ment
Provision for
accidental
leakages / bursts
in SPS
Proper drainage
arrangements to prevent
water stagnation/ flooding in
SPS site area
Yes (not
specific but
included as a
part of
associated
construction
activity)
DPR for Sewerage
system in
Sewerage District
‘A’ Allahabad,
The proposed DPR includes these
activities
Location of SPS Appropriate siting, and
enclosing within building to
reduce noise and odour
nuisance to surrounding
area
Yes DPR for Sewerage
system in
Sewerage District
‘A’ Allahabad,
The proposed SPS will be indoor
which will prevent noise and
enclosed nature and appropriate
cleaning and maintenance will
prevent odour nuisance
Constru
ction
Excavation,
Cutting and filling
operations
Review of existing
infrastructure, shoring
trenches, reinstatement/
resurfacing
Yes DPR for Sewerage
system in
Sewerage District
‘A’ Allahabad,
The proposed DPR includes these
activities
Damage public
utilities
Proper reviewing of existing
drawing s of utilities,
informing concern
authorities and
reinstatement of public
utilities
Yes DPR for Sewerage
system in
Sewerage District
‘A’ Allahabad,
The proposed DPR includes these
activities
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
103
Dust generation Water sprinkling on
excavated material to
suppress dust and provision
of top cover when
transported through vehicles
No Water tanker: Rs.
Approximately
Rs. 28,80,000
/-
Top cover for
dumper truck: Rs.
33750/-
According to DPR 80Km stretch in
each zone will be completed in
3years. This means approximately
75 m will be covered per day.
750 L of water will be consumed
for 75 m using sprinkler average 2
times a day
Labour cost-Rs. 150/day
Rs. 300/tanker+Rs150/labourer =
Rs. 450
Per meter cost = Rs. 450/75m = Rs
6/-
Total cost for 80 Km= Rs.
480000
Keeping a 2 day margin for
construction and reinstatement of
the site
2x480000= Rs. 960000/-
For 240km stretch:
Rs. 28,80,000/-
Top cover:
Approximately 30 Sqm of top
cover may require for each
vehicle. Assuming 5 such vehicle
involved in transporting excess
soil to dumping location
(considering construction
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
104
schedule and max excavated earth
disposal). Hence 5 trucks*
required top cover 30 Sqm* Cost
of Tripol cover at Rs. 75/ Sqm
Noise and
vibrations
Usage of sound barriers or
sheets.
No. Rs. 9,29,850/- As per the schedule, the
construction of 80km in 3zones
each has to be executed in 36
months For providing sound
barriers like GI sheets, 4Km out of
80 Km of stretch of sensitive zones
in sewer work is considered
assuming excavation, construction
and backfilling activity will take
place simultaneously at different
stretches.
Considering 302 GI sheet of 3’x 8’
would cover 75m length (both
sides) of construction activity
daily. (150 sheets are needed of for
one side of 150 m stretch, so for 2
sides 300 sheets and 2 more sheets
to enclose one open side of the
barricading; 150 m is taken as a
safer option as it will not be
possible to shift the barrier to
another site same day)
Hence 302 sheets* Cost of GI sheet
Rs.1000 per sheet (Rs.70-100 per
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
105
Kg)* labour cost ( two labours at
avg. rate of Rs. 150 per day) = Rs.
309950
And for 240 Kms = Rs. 9,29,850/-
Temporary
flooding or , water
logging
Alternate traffic re-routing,
Ensuring storage of
excavated soil material on
the higher lying areas
Yes DPR for Sewerage
system in
Sewerage District
‘A’ Allahabad,
Increased traffic
inconvenience
Traffic re-routing Yes DPR for Sewerage
system in
Sewerage District
‘A’ Allahabad,
Safety hazards to
workers and
residents
Putting fences or other
barricades to demarcate the
area
No Rs. 16875 Assuming a stretch of 75m per
day, 150 rods will be used, @ Rs.
75/- per rod.
Labour
camps
(if
adopted)
Health hazards
and nuisance due
to absence of
facility for
sanitation or solid
waste
management
Sanitation No Cost of
construction of pit
and toilet building
& cleaning
approximately Rs.
15,12,000/-
Total no. of labour is estimated
assuming 35% of total project
working for 36 months .The
labour camps can be divided into
1 camps for each zone, for
appropriate management and
maintenance work. So per day
each camp will have around 950
labourers
A toilet with septic tank is been
suggested for sanitation facility at
labour camps. Septic tank of
capacity 45 m3 will be used. For
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
106
950 labourers 63 m3 of total pit
capacity would be needed. Hence
2 pits will be needed. Cost of one
pit is Rs. 1,20,000. Cost of 2 pits
would ne Rs. 2,40,000/-
For this 3 toilet buildings of 15
closets will be needed. Cost of one
toilet building is Rs. 80,000. So for
3 toilet building total cost is Rs.
2,40,000.
Therefore, total cost of toilet
construction at one camp site
would be Rs 4,80,000/-
For constructing toilet at 3 camps
expenditure would be Rs.
14,40,000/-
Cleaning of pit cost Rs 4000/-. And
after 9 months cleaning is needed
so thrice cleaning is needed. So for
2 pits X 3 camps X 3 times
cleaning the cost will come as
Rs.72000/-
Water Supply No Approximately Rs.
1213821/-
As estimated 950 labourers will be
at one camp, so approximately 190
families will be placed at one
camp. Around 10 standposts will
be needed at one camp. One
standpost construction cost is Rs
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
107
6250/-. So for 3 camps total cost
will be Rs 187500 for construction.
At the rate of 135 LPCD, 128250L
of water is needed for each camp.
At the rate of Rs 2.5KL, the cost of
water provisioning would be Rs
320.65 per day. Total cost for 36
months would be Rs 342106.875
and the total cost for all camps
would be Rs 1026320.625.
Total cost of construction and
provisioning would be Rs
1213820.625
Dust bins No Approximately Rs.
200000/-
Solid waste generation: Generally
about 200 grams of solid waste is
generated per 5 persons every
day. Hence two cluster dustbin
(one for biodegradable waste and
one for non-biodegradable waste
of 1 cum size at the rate of Rs.
2000/-) may handle solid waste
generated.
Total Cost of Environment Management Rs 6786296/-
Total cost for EMP is estimated to be approximately Rs. 6786296/- excluding budget for environmental monitoring plan.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
108
Table 7.4 Cost of Environmental Monitoring Plan
Allahabad-A SEWERAGE SCHEME, UP
Item Location Season Year Total no. of
samples Unit Cost Total Cost
Environment Monitoring during Construction Stage
Air quality Monitoring 8 3 3 72
7,000.00
504,000.00
Metrological data 1 4 3 12 5,000.00 60,000.00
Noise / vibration 8 3 3 72 2,000.00 144,000.00
Soil analysis 8 2 3 48 5,500.00 264,000.00
Travel and Transportation of
monitoring Team
Lumpsum 240,000.00
Sub total 1,212,000.00
Environment Monitoring Cost (Operation Stage)
Air quality Monitoring 8 1 5 40
7,000.00
280,000.00
Metrological data 1 1 5 5 5,000.00 25,000.00
Noise / vibration 8 1 5 40 2,000.00 80,000.00
Soil analysis 4 2 5 40 5,500.00 220,000.00
Sub-Total 605,000.00
Travel and Transportation of
monitoring Team
Lumpsum 400,000.00
TOTAL for Environmental Monitoring 2,217,000.00
Total Cost of EMP and Environmental Monitoring (Total of Table 7.3 and Table 7.4) 90,03,296.00 Say 90 Lakhs
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
109
7.4 Social Management Plan
7.4.1 Social mitigation plans during construction phase
Based on the identified social issues, doable mitigation plans are proposed. Some of these
measures are already listed in the DPRs, and some of them are additionally recommended
for social development of the project and the concerned stakeholders.
i. Impact on human health
Mitigation Measure: Acoustic enclosures or hoardings can be constructed at the proposed
sites
Mitigation plan involves the erection of temporary enclosures around construction
sites. These barriers will help entrap some of the dust that is brought up in digging.
They will also provide safety benefits, to be detailed below. According to the
interaction/consultation with the key stakeholders, it was said that contractors are
doing water sprinkling in the construction area.
ii. Traffic Congestion
Mitigation Measure: Re-route traffic whenever possible and employing traffic police
to manage the traffic movement.
Traffic must be re-routed to facilitate ease of movement. Proper signage should
provide detailed information on the dates and duration of road closures and which
detours will be available, ideally well in advance of actual construction so residents
can plan accordingly. Strategic placement of traffic police at critical intersections will
also facilitate better flow of traffic. Plans and budget for these measures are already
included in the DPR.
iii. Impact on livelihood
Sewer constructions will invariable lead to road closures, which will adversely affect
shops on those streets. The first priority is for the contractor to take the necessary measures to ensure that pedestrians always have access to shops, vendors, etc. For
mobile vendors, this may include adjusting the location of the cart, etc. to a similar
location in the immediate vicinity of the original location for the duration of the project. Projects should also proceed on schedule so as to minimize disruption.
Additionally, clean-up of debris and clearance of blockages should commence
immediately after project completion so as to remove any potential obstacles that
might prevent customers from accessing businesses or other disruptions.
In the event that the contractor, despite best efforts, is unable to avoid blockages of
the roads and/or disruption of local businesses, some compensation is necessary. The ESMF currently mandates compensation only in the case of permanent
livelihood loss or displacement and provides no provisions for livelihood loss of
mobile vendors. Additionally, no regulation, policy, guideline, etc. exists which can provide precedent or guidance in this instance. ESMF clearly states that
mobile/ambulatory hawkers: fruit cart vendors, etc. who can easily relocate fall into
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
110
this category. These vendors are most eligible for a temporary relocation just outside
the construction area, and will thus not be eligible for compensation as is the case for this proposed project.
However if during the construction of the project any party faces livelihood loss due
to the proposed project, then that party should be compensated according to the
entitlement matrix given in the ESMF report.
iv. Impact on existing utility services
Mitigation Measure:
• Circulating the layout plans of the existing underground alignment near the work
site.
• Contacting the relevant department in case there is any damage to any of the utility
services and ensuring prompt fixing/replacing of damaged infrastructure
Temporary shifting of power/water lines for construction purposes is already
budgeted for in the DPR. Nevertheless, all construction personnel must receive
detailed layout plans of existing underground structures to prevent accidental
water/electricity supply disruptions. The relevant departments should also be made
aware of the timing and location of digging near supply lines so they can make the
necessary preparations to respond swiftly to disruptions.
v. Safety hazards
Mitigation Measure: Fencing of the excavation site and providing proper caution sign boards.
As mentioned above, fencing should be erected around construction sites and
appropriately marked with caution signage. These fences/signs should remain in
place even if construction is not active, so long as a hazard (e.g. open pit) remains.
Currently, no provision for fences are explicitly mentioned in the DPR, and, in field
visits to JNNURM sites, some had fences while others did not.
vi. Elevated Noise Levels
According to UP Jal Nigam officials, construction will take place after school hours
or at other times of school closing to avoid interfering with school function. Beyond
that, construction must simply proceed in a deliberate and judicious manner to avoid
unnecessary noise pollution.
vii. Failure to Restore Temporary Construction Sites
As mentioned above, provisions to rehabilitate roads and clear debris are already
included in the DPR.
viii. Public Notice: according to the suggestion given by locals during the interview.
Government and contractor should give a prior notice to each and every locality with the details of project, street wise start date of construction and street wise end date of
construction, contact person during emergency. This information would help them
better adjust to the situation and make necessary adjustments and provisions.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
111
ix. Health Programme for Workers: If un-sanitary conditions prevail at workers camp,
health programmes for their well-being should be implemented.
7.4.2 Social mitigation plans during operation phase
Noise pollution due to improper handling of machines: proper O&M should be carried out
during the operation phase to ensure least disturbance is caused to the neighbouring
residents.
7.4.3 Mitigation measures adopted by locals during similar nature of
project activities
From the field surveys and interviewing the locals including shop-owners, residents, mobile
vendors, following local adaptive measures have been recorded;
• Using transparent plastic sheets to block entry of dust into shops
• Avoiding opening of windows, especially when the construction is going on
• Taking different routes if possible to avoid areas where construction is happening
• Laying wooden plank over the excavated pits for making access route to house or
shops
• Mobile vendors stated that they place their carts at some other place and vacate
construction area for the time when construction is on
• Many public institutes like hospitals, schools and colleges reported that they have
more than one gate which makes the access easier during construction period.
The above measures indicate that the general public has already created adaptation
measures to sewage construction projects.
Public Grievances
Locals also reported few instances where they lodged complaints about un-cleared debris, or
damage of public utility generally to UP Jal Nigam officials. They usually do not lodge complaints due to the prior experience of the lack of response from government officials.
Additionally, the interviewees said that they understood the inconveniences were of a
temporary measure and are providing a social good. Thus, they have created local adaptation measures as quick and efficient ways to mitigate the temporary inconveniences.
However the proposed project has grievance redress mechanism which will be adopted as
mentioned in the Environment and Social Management Framework.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
112
Table 7.5 Social Management Plan
Activity Potential Negative
Impact/Concern Mitigation Measures Cost Issues
I. Sewerage and Sanitation Projects A. Design and Development Phase Land Acquisition
for new pumping
station
NA • SPS is planned on land already owned
by the government and confirmed by
the Revenue department
NA
B. Construction Phase Laying of sewer network *
Safety hazards to workers and residents
• Provide workers with adequate safety equipment such as helmets, safety
shoes, gloves, etc.
• Fences/temporary enclosures should be put around construction sites (even
inactive ones, if hazards, like open pits,
remain); enclosures should be properly marked with caution signs
• Safety gear already provided by contractor
• Putting fences or other barricades
to demarcate the area, is already being done
DPR for Sewerage system in
Sewerage District ‘
Dust generation, with resulting
implications for human health
• Water sprinkling, removal of excess
materials, cleaning of sites upon
completion of activities. • Construction of temporary enclosures to
entrap dust.
• Water sprinkling
Reduced pedestrian and vehicle access to residences and
businesses, with inverse effects
• Work should proceed on schedule so as to minimize road closures
• Upon project completion, quick
• NA Debris clearance budgeted for in
DPR
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
113
on livelihoods clearance of debris, etc. will facilitate
access by customers to local business
and residents to their households
DPR for Sewerage system in
Sewerage District ‘A’ Allahabad,
Volume.-I
Temporary water , electricity,
supply interruptions
• Circulation of layout plan for all
underground infrastructure to ensure
that contractor is aware of
water/electricity lines in construction
zones • Local utilities should be made aware of
timing/location of all construction,
enabling them to respond swiftly to
supply disruption, especially in the
event of flooding, etc.
• Provision for temporary shifting
of water/power lines, etc. already
in DPR
DPR for Sewerage system in
Sewerage District ‘A’ Allahabad, Volume.-I
Increased traffic inconvenience (emissions, congestions, longer
travel times)
• Use of alternate traffic routes; signage should clearly indicate dates of road
closures and new routes so residents
can plan accordingly • Placement of traffic officers at busy
intersections to facilitate easy of
movement
• Provisions for traffic diversion, with signage already in DPR
DPR for Sewerage system in
Sewerage District ‘A’ Allahabad, Volume.-I
Impact to daily life • Prior public notice indicating the date of
start of construction and end date of construction should be provided road-
wise to the locals, allowing them to
make adjustments accordingly
Note: *** denotes – Significant Impact; ** Denotes-Moderate Impacts and *- Minor Impact.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
114
7.4.4 Consultation Framework for Participatory Planning and
Implementation of Mitigation Plan
Relevant stakeholders, especially community members (residents, shop owners, etc.) may be
informed about the details of the proposed mitigation plan. A public consultation may be
conducted where the mitigation plan is presented, and feedback solicited from the
community. Individual meetings with other key stake holders – government officials,
relevant NGOs, etc. – could be scheduled to solicit their feedback as well. Once construction
begins and the mitigation plan is put into effect, third party audits should be taken up so as
to evaluate the efficacy of the mitigation plan, as well as gauge local sentiments related to
the construction and identify/address new issues that may have arisen during construction.
Stakeholders that should be involved in planning and implementation of the mitigation plan
include;
• All affected persons (APs), program beneficiaries, including representatives of
vulnerable households;
• decision makers, policy makers, elected representatives of people, community and
citizens, NGOs etc;
• staff of executing agency, implementing agencies, GPCU, etc
• officials of the revenue departments, social welfare department etc; and
• Representatives of the various state government departments, as required.
7.4.5 Assess the Capacity of Institutions and Mechanisms for
Implementing Social Development Aspects and Social Safeguard
Plans; Recommend Capacity building measures
Roles and functions of the institutions are pre-defined, but they can enhance their capacity
for better implementation and operation of the project. There should be synergies and
continual interaction amongst the departments for better coordination. The officers of the
relevant departments can be trained in social sciences, social management plan, etc.
Institutional reform and capacity building of local body is in process under JNNURM, it will
be required to ensure that operating authorities have the ability and equipment to properly
manage and finance the operation and maintenance of sewerage schemes. Otherwise
continued development will not be sustainable.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
115
Table 7.6 Role of stakeholder in implementation and mitigation
Stakeholder
Category Role in project implementation Role in mitigation
NGRBA Over all coordination Coordinating so that the
mitigation plan is
implemented well Ensuring funds for mitigation
plan execution
Executing agencies (UP Jal Nigam,
Ganga Pollution
Control Unit)
Implementation of the project by awarding the project to the
suitable contractor and regional
coordination Informing the relevant
departments about the progress
of the project
Ensuring that the relevant departments are available for
mitigation plan
Enough safety provisions are available for the project
implementation.
Jal Sansthan While execution of projects
related to sewerage line, Jal
Sansthan is responsible for the damage caused to the public
utility functions like drinking
water pipe lines
Should ensure that the basic
amenities are in order during
the construction and operational phase of the
project
Municipality Ensuring better access to
households
Should ensure all the
households envisaged at
project planning phase gets access to the services. Weaker
section of the society should
get equitable share. State, local
Government
Coordination
Monitoring and evaluation
Coordination
Monitoring and evaluation
Ensure all the safeguarding plans are in line and acted
upon.
NGOs, CSOs, Research Institutes (
Allahabad
University)
Awareness creation about the project activities
Community participation for
better project implementation
Public participation and coordination
7.4.6 Develop Monitoring and Evaluation Mechanisms to Assess Social
Development Outcomes
Regular monitoring and evaluation of the project activities should be carried out to judge its
success or any gaps. Certain key parameters can be taken as the benchmark for monitoring
and evaluation of the project based on the identified development outcomes. Some of the
indicators are listed below;
• Increase in sewer access (number of households linked to the sewer network)
• Decrease in effluent discharge into the Ganga (water quality assessment of the river)
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
116
• Proper sites for industries, building etc.
• Accessibility of the service to backward and weaker sections of the society
• Increase in public toilet
• Increase in the land rate (property appreciation value)
• Decrease in water borne disease incidence in the area
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
118
Chapter 8 Social Development Outcomes and Issues
8.1 Social Development Outcomes of the sub project
• Access to sewer network: This service will cater to the projected population until
the year 2040. According to the DPR, population is expected to increase from 405176
in 2010 to 515155 by 2040. In this time, waste water generation is expected to increase
from 62.80 MLD to 79.85 MLD. Hence the increase sewerage will prevent outflow of
waste water to the Ganga.
• Better hygienic conditions: The sewerage network will provide improved
environmental conditions due to the contained handling of wastes, leading to
improved public health conditions and will likely reduce the average medical
expenses of the residents in the project areas. According to DPR this area has
sewerage system but the sewers are very old, under capacity and deteriorated
condition, which causes significant flow of untreated sewage into river and also this
sewage gets accumulated on road/drain sides. These areas suffer from powerful
odors and greater amounts of flies/mosquitoes, which will be mitigated with the
sewerage connection and overall improvement in environment and health is
anticipated from this project.
• Decrease in water pollution: Because of the sewer line connection, all the waste
water will be collected and directed to treatment plant, which only after treatment
will be disposed off to the river, hence decreasing the pollutant load in the river.
Due to current pollution, water quality in the river Ganga is impaired at the City of
Allahabad. As the water enters Allahabad (at Rasoolabad) from Kanpur, it has a BOD
much higher than the safe bathing limit of 3mg/L at about 4.5 mg/L. Downstream
from Allahabad (post Sangam and before Assighat, Varanasi), the BDO reduces to
below the safe bathing limit15.
• Increase in aesthetic value of the project area: connection to sewer lines enhance the
aesthetic value of the area, as there will be more cleanliness and no wastewater
discharge to open area. This will also lead to appreciation in the property value. This
will eventually lead to increase in standard of living of the people in the project site.
The support for this statement comes from the counter-factual scenario observed in
areas with only nalas (bad odor, insects, etc.).
• Reduction in cost of implementation: According to DPR, wherever possible
development of sewerage will be integrated with existing GAP infrastructure to
reduce the overall investment cost.
• Cultural sentiments: Proper sewage disposal would increase the river water quality.
As the holy river is attached to many rituals and customs, enhanced river water
quality would connect to sentiments of the people. Especially during ‘Kumbh Mela’
15Source: SanjivSwarup 2007, Affidavit of status report as on October 31,2006 filed on behalf of NRCD as per
orders of the SC dated Oct 10, 2006, New Delhi January, mime
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
119
better water quality for bathing would be boon for pilgrims. At present as recorded
by UP State Pollution Control Board river water at Allahabad has high fecal coliform
concentration, and it has been reported that some sadhus and saints protest against
the river pollution and boycott the ritual bathing16. This could be sorted out with
better river water quality.
8.2 Social Development Issues in Project Vicinity and Social
Services to be provided by the project
The social benefits of the proposed project are given above. The social services required to
ensure that these benefits are realized are given below:
• Ensure backward section of the society gets the facility: Some residents complained
that they did not feel they personally would benefit from the project as their houses
did not have sewer connection. Thus, increasing household connections will ensure
that project benefits are equitably distributed. Plans for increasing connections are
detailed in the DPR that is by 2025 coverage would increase to 75% from 45% of 2010
ratio. Special care should be taken to ensure access for backward and vulnerable
sections of the society. Full benefits of the facilities proposed under DPR cannot be
realized unless a programme to improve coverage of branch sewers and household
connection is carried in parallel.
• Increasing public toilet facilities: Similarly increasing public toilet facilities will
ensure that residents of Allahabad without permanent housing and tourists
(especially visiting during ‘Kumbh Mela’ are able to benefit from the increased
sewerage access. Increasing toilet access will decrease practices such as Open
Defecation. This eventually would lead to better water quality and would have better
environment and social ramifications.
• Targeting of economically weaker communities: for construction jobs related to
sub-project: In order to ensure that the economic benefits of the sub-project is felt by
those in need, those from backward communities should be specifically targeted for
relevant jobs.
• Proper clean-up of project debris: In order to maximize aesthetic benefits and
ensure that debris does not clog sewer path, proper clean-up of project areas must be
performed after the project is completed. Collection and disposal of debris is
essential for proper function of other essential processes like traffic routing,
pedestrian pathways, and clearance of dust and particles causing pollution. Clean
area will also enhance the aesthetic value and increase the property rate of the area.
• Sanitation for slum dwellers: Allahabad district has many slums, as mentioned
above around 185 slums spread across the city. District A also has number of slums.
All these slums have no legal rights over land so it is not possible to provide such
services to them. But their unsanitary condition is an impediment for over all
sanitary development. Hence they should be provided with the scheme of low cost
sanitation technologies without sewerage connection.
16http://www.ecofriends.org/main/eganga/images/Critical%20analysis%20of%20GAP.pdf
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
120
Chapter 9 Conclusion The project report of the proposed sub-project for sewerage district ‘A’ of the Allahabad city
after environment and social analysis concludes that the project falls in ‘low impact’
category and have overall positive benefits on the life and environment of the people. There
has been no reported land acquisition or livelihood losses to be caused under this project. As
per environmental and social management framework guidelines of NGRBA,
Environmental and Social Assessment, with a Generic Safeguard Management Plan was
conducted for addressing possible issues/ concerns arising from proposed project.
Impacts of activities identified during the assessment fell under two separate categories of
Construction and Operation. Although no such permanently negative or adverse
environmental or social impacts were identified, there were certain temporary impacts, for
which appropriate mitigation plans have also been suggested. The environmental
management plan ensures to suggest appropriate mitigation measure against the issues/
concerns identified during the environmental and social analysis study. All the social and
environmental issues were appropriately studied and have been substantiated using
appropriate evidences, to ascertain the magnitude of their impacts. Even the issues of public
grievances and public notice have been taken care in the report to confirm transparency
during the project implementation. Report also ensures that well defined institutional
mechanism is in place to monitor and evaluate the progress of the project during
construction, implementation and operation phases.
Stakeholder consultations, and interviews helped to understand the general perception of
public towards the project and it can be determined that the people of the project site are
happy and welcome such an initiative for their betterment. It was also pointed out that the
large overall environmental benefits of the project such as prevention of discharge of
untreated sewage into River Ganga, improvement in sewerage collection and treatment,
prevention of untreated liquid waste infiltrating into ground water and soil, improvement in
quality of life, human dignity and increased productivity greatly outweigh the temporary
inconveniences faced during the implementation stages.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
121
Annexure 1 Questionnaire TERI-Water Resources Division Date:__/__/2011
NGRBA Project Impact Assessment
Interviewer:__________________
Site: __________________________
Interviewee:________________________
Location: Residential____Public Place_______
For PP: Park______Office____Market__School____Store______Religious place____
Classification: Resident______ShopKeeper___StreetVendor_____Officeworker____School_______pedestria
n___
Religious figure_____Other_______
1. Are you aware that this project will be constructed?
2. Do you think it is necessary to have this kind of project? You feel connection to sewerage is important?
3. Will your household be connected to sewer line?
4. What do you think will be the consequences of the construction this project on the
following: (classify as short term and long term impacts)
a. Traffic blockages?
b. Parking?
c. Aesthetic value of neighbourhood/ environment sanitation
d. Health
e. Access to river water source
f. Noise?
g. Pollution? Dust, air quality, leakages
h. Smell/flies, etc.?
i. Basic services? Drinking water pipes, electricity poles, etc.
j. Livelihood? (temporary or permanent)
k. Family?
l. Daily Life?
m. Impact of worker’s camp (unsanitary conditions there, safety concerns, etc.)
n. Other?
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
122
5. What do you think will be the consequences of this project, post completion?
a. Pollution?
b. Smell/flies, etc.?
c. Access to river water source
d. Basic services? Drinking water pipes, electricity poles, etc.
e. Livelihood?
f. Family?
g. Daily Life?
h. Other?
6. Are you aware of similar projects (prompt Jnnurm projects) in your
area/neighbourhood?
7. How are you coping up with these difficulties?
a. Traffic blockages?
b. Parking?
c. Aesthetic value of neighbourhood
d. Health
e. Access to river water source
f. Noise?
g. Pollution? Dust, air quality, leakages
h. Smell/flies, etc.?
i. Basic services? Drinking water pipes, electricity poles, etc.
j. Livelihood? (Temporary/permanent)
k. Family?
l. Daily Life?
m. Impact of worker’s camp (unsanitary conditions there, safety concerns, etc.)
n. Other?
8. Have you/or anyone you know of have complained on any similar projects in the
past?
9. What are your suggestions on improving the project construction/operation phase?
10. Are you aware of what will happen in the absence of the project?
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
123
11. Do you think this is a no regret investment by GoI (explain what is no regret
investment) and more such projects should be implemented?
12. Do you perceive any conflicts during implementation/construction of the project?
(get details)
13. Do you know of any conflicts in the past due to similar projects?
14. Do you know of any land acquisition for this project?
15. Do you know of any rehabilitation/resettlement that might be required during project implementation phase?
16. Do you think these projects; will help in improving Ganga river quality, if replicated and upscaled in different
areas or not?
17. Are you aware of any community/social movement against this upcoming project?
18. Are you aware of any community/social movement/ cultural issues/security threats
(due to labour migration) against similar projects in your area in the past?
19. Are you willing to cope with the temporary disruptions/disturbances during the construction/operational phase? (prompt and get reason for willingness to cope, if
answer is yes/no)
20. Do you believe that the authority will implement the project in a timely and efficient
manner?
21. Have you/or anyone you know of approached the public grievance authority in the
past regarding similar projects? (note down details)
22. Do you feel this project has minimal/no impact in comparison with some other
projects/programmes you know of in the region?
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
124
Annexure 2 Minutes of meeting with key stakeholders
Allahabad 28-29th April 2011
S.
no
Name and
designation Contact No. Minutes of Meeting
1 Mr. Rohit, Asst.
Project Engineer,
State Pollution Control Board,
Allahabad
9473942159 • According to rough estimates
the project in District C
would help in treating 2.61 MLD of sewage, and in
District A around 7 MLD of
sewage. This will help prevent flow of
approximately 10 MLD of
sewage into River Ganga.
• During construction work,
they make sure appropriate
safety equipments are available along with proper
caution signage and contact
number of the concerned project coordinator. Also
proper shuttering to be
placed as excavation commences; water to be
sprinkled through tankers,
twice a day, to avoid dust pollution.
• Work in front of schools and
hospitals to be prioritized
and finished urgently. Work
could be conducted during
day/night shifts. • Upstream/downstream water
quality data can be retrieved
from the MoEF public
domain.
• There are no forested areas
or protected monuments being threatened by the
projects.
• There is no threat to Groundwater Resources
since digging for sewers does
not go below 6-7 meters. 2 Mr. R S Singh, State 9473942675 • Said that he dealt mainly
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
125
Pollution Control
Board, Allahabad
with the Operation and
Maintenance phase of the
projects. • Introduced TERI to Mr. Rohit
for all necessary information.
• TERI submitted a letter of
request to Mr. R.S Singh,
requesting relevant data for
ESIA.
Allahabad 5thAugust 2011
S.
no Name and designation Minutes of Meeting
1 MoEF, PMG ,World Bank
team, U.P. Jal Nigam, Nagar Nigam, Tata
Consulting Engineers
(TCE), TERI
Venue: Jal Nigam,
Training Centre, Sangam Hall
• There was a verbal agreement between the Nagar
Nigam, UP Jal Nigam and other offices that each construction site for laying of sewer lines will be
completed and restored in maximum period of 1
month.
• It was brought to the attention that since no maps,
plans of underground utilities exists, damage to
them will be inevitable. • It was agreed upon that a ‘Social publicity Programme’
would be launched, the budget for which was to be
prepared by Jal Kal department.
• There was a suggestion to use SewerCad and it was
recommended that all sewer maps and details
should be mapped using it. • The issue of providing sewer lines to unauthorized
colonies was brought up. One solution was to
provide sewerage to all habitations and unauthorized colonies except where public land has
been encroached. Another suggestion was to
provide network in all areas where a water connection already exists. This matter is still under
review and consideration.
• Suggestion was made by the World Bank to initiate a plan to involve and motivate local residents to
install sewer connections in their homes. One such
idea for a scheme would provide a free connection
to all those who applied in the 1st six months.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
126
Allahabad 23rd - 26th August 2011
S.
no Name and designation Contact No. Minutes of Meeting
1 Mr. A.K Mittal, General
Manager, Ganga Pollution Control Unit
(GPCU), UP Jal Nigam,
Allahabad, Uttar Pradesh.
9473942672 • He shared basic
information on the existing sewerage system in
Allahabad city and
provided contacts of important officials
required for the
environmental and social assessment study.
• Important issues such as
damage to public utilities,
traffic congestion, dust
pollution etc. were
highlighted. • Data and Maps related to
Water Supply, Solid Waste
management, storm drainage, health and social
issues were not available
with UP Jal Nigam and would be with the Nagar
Nigam.
2 Mr. J.P Mani, Project Manager, Ganga
Pollution Control Unit
(GPCU), UP Jal Nigam,
Allahabad, Uttar
• As secondary data on Allahabad “A report on sub-
soil exploration for design
foundation of sump well at
Gaughat, Allahabad (U.P.)”
3 Dr. Mukesh Sharma,
Envrionment Officer, Project Implementation
Unit, Allahabad Nagar
Nigam.
09935754985
• Stated that most of the data
is with the UP Jal Nigam • Shared statistics about
solid waste management in
city.
• Overall the SWM plans are
have reached only 20%
implementation in all wards.
• 400 gm/head solid waste is
collected adding up to a total of 540 Million Metric
Tonnes per day.
• Door to Door Collection (DTDC) is followed in 18
wards of District A. No
slums are included in the DTDC plans.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
127
• The major dumping sites
are Allahpur, Govindpur
and KarelBagh. The major processing plant is at
Baswar.
• With regard to waste
water, BPCL is a major
industry that dumps waste
water into the Simraha Ghat. Other industries in
NAINI area are
Baidyanath, AREVA and
RECRON.
• Provided information on
water supply for the city which included pumps,
tube wells and overhead
tanks (18 under JNNURM, each storing
2000KiloLitres). There are
also 3 underground reservoirs in District A (2
are complete, 1 is 30%
constructed) 4 Mr. Tiwary, Social
officer, Allahabad
Nagar Nigam.
07376336219 • Informed that there is not
much data that exists on
social issues at the
moment.
• Provided TERI with a
photocopy of wards in Allahabad district and a
list of slums.
5 Mr. P.K Mishra, Land Officer, Nagar Nigam.
• Informed that there is no landuse data or maps
available for Allahabad
due to lack of recording and poor response from
locals.
6 Mr, K.K Srivastav, JE, Gaughat Pumping
Station, Allahabad.
09473942168 • Provided important information with regard to
the Gaughat pumping
station and overall sewage
system in Allahabad.
• The current pumping
capacity of the Gaughat MPS is 72MLD and it has
the capacity to handle extra
increased levels of 7 to 8 m.
• The MPS was built in 1988
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
128
and is very old, it should
have been changed in 2003
(after 15 years). • There is no provision to
handle high flows/excess
flows during the monsoon.
During these times,
backlogging leads to
flooding of the sewage network. It was suggested
that storm water be
bypassed to the river to
avoid this kind of flooding.
• There have been no
complaints from the residents neighboring the
MPS about noise or air
quality. • Polythene is a major issue
at the pumping station.
Approximately 2 trucks per week are transported
to dumping sites from
Gaughat MPS. 7 World Bank, TCE and
UPJN
[email protected] • All 3 parties discussed the
day’s field visits and the
World Bank gave their
impression and
expectations of the project
work. The following points are to be mentioned:
• As per JNNURM, by
March 2012, water supply is targeted to be 100% in
Allahabad.
• The main concern for finishing the project in
time is the upcoming
Kumbh Mela in 2013 at Prayag.
• GIS maps are to be
acquired from TCE in the
form of a CD.
• The UPJN agreed to
provide field assistance to all field going teams, as
suggested by the World
Bank.
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
129
Annexure 3 Census Data District Allahabad (45), Uttar Pradesh (09)
Population
Persons 4,936,105 Males 2,626,448
Females 2,309,657
Growth (1991-2001) 26.72
Rural 3,729,320
Urban 1,206,785
Scheduled Caste Population 1,065,097 Percentage to total Population 21.58
Literacy and Educational level
Literates
Persons 2,506,942
Males 1,635,387
Females 871,555 Literacy rate
Persons 62.11
Males 75.81 Females 46.38
Workers
Total workers 1,671,349 Main workers 1,106,596
Marginal workers 564,751
Non-workers 3,264,756 Scheduled Castes (Largest three)
1. Pasi 304,424
2. Chamar etc. 402,347
3. Kol 106,164
Religions (Largest three)
1. Hindus 4,284,834 2. Muslims 627,735
3. Christians 9,114
Important Towns (Largest three) Population
1. Allahabad (M Corp.) 975,393
2. Allahabad (CB) 24,137 3. Lal Gopalganj Nindaura (NP) 22,992
House Type
Type of House (% of households occupying) Permanent 50.7
Semi-permanent 45.5
Temporary 3.8
Number of households 740,941
Household size (per household) 7
Sex ratio (females per 1000 males) 879 Sex ration (0-6 years) 917
Environmental and Social Assessment with Management Plans (Sewerage District ‘A’-Allahabad)
130
Scheduled Tribe population 4,273
Percentage to total population 0.09
Educational Level attained Total 2,506,942
Without level 152,585
Below primary 536,398
Primary 542,568
Middle 404,832
Matric/Higher Secondary/Diploma 616,060 Graduate and above 254,138
Age groups
0-4 years 586,483
5-14 years 1,374,513
15-59 years 2,598,662
60 years and above (incl. A.N.S.) 376,447 Scheduled Tribes (Largest three)
1. Generic Tribes etc. 3,322
2. Tharu 870 3. Jaunsari 57
Amenities and infrastructural facilities
Total inhabited villages Amenities available in villages
No. of Villages
Drinking water facilities 2,783 Safe Drinking water 2,783
Electricity (Power Supply) 2,289
Electricity (domestic) 1,066
Electricity (Agriculture) 703
Primary school 1,733
Middle schools 613 Secondary/Sr Secondary schools 214
College 61
Medical facility 651 Primary Health Centre 53
Primary Health Sub-Centre 66
Post, telegraph and telephone facility 910 Bus services 201
Paved approach road 1,956
Mud approach road 1,986