ENVIRONMENT MANAGEMENT PLAN · #501, 5th Floor, Block-C, Nirvana Courtyard, Nirvana Country, Sec-...
Transcript of ENVIRONMENT MANAGEMENT PLAN · #501, 5th Floor, Block-C, Nirvana Courtyard, Nirvana Country, Sec-...
ENVIRONMENT MANAGEMENT PLAN
Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Village : Bhaunti
Tehsil : Pichhore
District : Shivpuri
State : Madhya Pradesh
Area : 4.50Hectare
Mineral : Soil/Murrum
Khasra No. : 1847
Production Cap : Soil/Murrum :- Total 75,000Cu.mt
Lease Period : 15 Months
APPLICANT
M/s KCC BUILDCON PVT. LTD
#501, 5th Floor, Block-C, Nirvana Courtyard, Nirvana Country,
Sec- 50, Gurgaon (HR)
Camp- Bhonti, Tehsil- Pichhore, District- Shivpuri,(M.P)
Prepared By:-
Charles Pradeep Singh
Near LIC Office, Jabalpur Road, Bargawan, Katni MP
RQP/DGMMP/061/2013-18
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 2 of 12
1. EXECUTIVE SUMMARY:
Bhaunti Soil/ Murrum mine project covering an area of 4.50Hect. for mining of
minor mineral Soil/ Murrum at village-Bhaunti, Tehsil-Pichhore, District-
Shivpuri.
The mining plan has been approved by Directorate of Geology & Mining Regional
office Gwalior M P vide letter no. 881 on dtd. 14/07/2017. The Collector office
(Khanij Shakha) Shivpuri vide letter No.80-82 /Khanij/2017, dated-
30/06/2017.
2. DETAILS OF THE LESSEE:
Name : M/s KCC BUILDCON PVT. LTD
Address : Resi.- #501, 5th Floor, Block-C, Nirvana Courtyard,
Nirvana Country, Sec- 50, Gurgaon (HR)
Camp- Bhonti, Tehsil- Pichhore, District- Shivpuri,(M.P)
Designation : Individual Owner
3. SALIENT FEATURES OF THE PROJECT:
Particulars Details
Name of the
project
Bhaunti Soil/ Murrum(Temporary Permit) Quarry
Mineral Soil/ Murrum Mining Lease
area
4.50Hect.
Khasra No. 1847 Land Use Govt. Land
Lease Validity Months
Production
Capacity
Soil/ Murrum:- Total 75,000Cu.mt For 15 Months
Village Bhaunti
Tehsil Pichhore
District Shivpuri
Latitude&
Longitude
(A) 25°18'46.21"N 78° 6'27.07"E
(B) 25°18'53.07"N 78° 6'27.92"E
(C) 25°18'52.49"N 78° 6'26.57"E
(D) 25°18'56.69"N 78° 6'27.07"E
(E) 25°18'56.79"N 78° 6'29.60"E
(F) 25°18'56.16"N 78° 6'29.76"E
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 3 of 12
(G) 25°18'56.03"N 78° 6'30.27"E
(H) 25°18'45.37"N 78° 6'29.72"E
Estimated
project cost
40Lacs
Man Power 20-25
Water demand
and supply
4-8KLD
Nearest
habitation/town
The nearest village is Bhaunti which is about 0.70 KMS
from mine site. Nearest Airport The nearest Airport is Jhansi which is about 49KMS from
mine site. Nearest
Connectivity
SH-19, Road, about 100mtr from mine site.
Nearest Railway
Station
The nearest Railway Station is Babina which is about 34.40
KMS from mine site.
Power Supply No electricity is required.
4. DETAILS OF THE AREA:
The details of the lease area to be grant, ownership etc. is as below:
• Topo Sheet : Area falls in survey of India 54- K/3
• Khasra No. : 1847
• Area : 4.50Hectare
• Mineral : Soil/Murrum
• Production Cap : Soil/ Murrum :- Total 75,000Cu.mt
• Period : 15 Months
• Whether area is
recorded in
forests
: No
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 4 of 12
• Khasra Map :
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 5 of 12
• Satellite Image of the mining area:
5. DETAILS OF MACHINE TO BE USED IN MINING OPERATION:
Mining/excavation will be done according to the proposed manner of Manual
& Semi Mechanized workings and some machineries i.e. JCB, Pock Lane,
Dumpers, tractors etc.
6. DETAILS OF MEASUREMENT OF QUARRY PIT EARLIER
EXCAVATION IN THE AREA TO BE SANCTIONED AND
DETAILS OF MINERAL CONCESSIONS SITUATED WITHIN 100
METER PERIPHERY OF THIS AREA:
No seasonal perennial drainage exists within the lease area. No pit was
excavated in the past since this is new lease quarry. The area in
surroundings up to 100meters forms a plain topography with miner
undulations of waste land form.
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 6 of 12
7. SCHEME OF TREE PLANTATION:
During the plan period, benches will reach the ultimate pit limit. The total
exploited Soil/ Murrum shall be transported to nearby market therefore no
waste shall be generated. During the plan period 7.5m barrier zone will be
used for the plantation purposes. 200 no. trees will be planted during
development (15 Months period).
The tree species recommended are Tactonagrandis (Teak),
Azadirachtaindica (Neem),Mangiferaindica (Aam), Acacia Catechu (Khanir),
Emblicaofficinalis (Amla), MahuncaLatitolia (Mahua), Planting should be
done in large sized 90 cm x 90 cm.pits dug in advance and filled with
manure about 50 days before planting. The plantation raised earlier should
be carefully maintained. Mortalities should be replaced by fresh saplings.
� Post Plantation Care
Following precaution to be undertaken for the survival of the plants:
� The samplings will be undertaken for the survival of the plants.
� Healthy tree species will be recommends for plantation.
� Every sapling will be covered by a tree guard to avoid damage through
cattle grazing.
� Necessary arrangement will be provided for watering tree species planted
in different parts.
8. DETAILS AND APPROXIMATE DISTANCE OF NATIONAL
PARK, SANCTUARY, BIODIVERSITY AREA, INTERSTATE
BOUNDARY SITUATED WITHIN PERIPHERY OF 10 KM. FROM
THE AREA TO BE SANCTIONED
Proposed project does not located in whole or in part within 10 km. from
the boundary of:
� Protected areas notified under the Wild Life (Protection)
Act, 1972
:- No
� National Park :- No
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 7 of 12
� Critically polluted areas as notified by the Central Pollution
Control Board from time to time
:- No
� Notified Eco-sensitive areas :- No
� Inter-state boundaries and international boundaries :- No
9. PROPOSED PRODUCTION OF MINERAL:
The yearly production from the quarry is proposed Soil/ Murrum is 75,000
Cu.mt for 15 months with Manual & Semi Mechanized opencast mining
system.
10. EFFECT ON GROUND WATER LEVEL DUE TO MINING
OPERATION AND ITS PREVENTIVE MEASURES:
There is no perennial water body in the area. Mining activities will not cause
adverse impacts as the mineral is non toxic in nature. Lease area is fairly flat
reducing the possibility of soil erosion. Garland drain will be made to
properly channelize the rain water and wash offs in sedimentation ponds.
As the manpower likely to be deployed from nearby village, is not very high
discharge of domestic waste water, will be easily controlled with the
provision of septic tank and soak pit. The stored water will be used for dust
suppression and greenbelt development, etc.
The pit exposed due to mining will become a source for catchment of rain
water and in future it will be helpful to improve the water table of the area.
11. DETAILS OF SCHEME OF CONTINUOUS RECLAMATION AND
REHABILITATION OF THE LAND DEGRADATION DUE TO
MINING OPERATION:
Land degradation is one of the major adverse impacts of open cast mining
activities and any effort to control adverse impacts would be incomplete
without appropriate land reclamation strategy. It is a mining below five
hectares lease area, which is very small in nature therefore no damage of
the land is anticipated.
The area is likely to be degraded due to quarrying, pitting & roads. The
impact on the land form or Physiography will be limited to the modification
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 8 of 12
of the slope. The landscape and land use will undergo a radical change due
to open cast mining. The impact during plan period is limited as benches
will be formed on the already degraded land. Besides these benches, roads
will also modify the Physiography.
During the plan period, benches will reach the ultimate pit limit. The total
exploited Soil/ Murrum shall be transported to nearby market therefore no
waste shall be generated.
Reclamation and rehabilitation will be started at the end of mine life
which required sufficient quantity of waste etc. for back filling. Availability
of waste at the closing time of mine will be very less to meet requirement;
hence the mined out pit will be developed as water reservoir in future.
12. DETAILS OF PREVENTIVE AND CONTROL SCHEME OF AIR
AND WATER POLLUTION:
� Air Pollution Control:
• Regular water Spraying in dry area of quarry
• Wetting of land and dump stock in case it is dry.
• Water sprinkling at dust sources.
• The angle of dip is 45 degrees.
• Dust Mask shall be provided to all working workers in dusty atmosphere.
• Minimizing drop height of stone in trippers.
• No overloading of tractors, dumpers, trucks
• Proper maintenance of vehicles
• Periodic maintenance of kachha/approach road
• Regular sprinkling of water on roads in the morning and also at a moment
if observed that the dust on road is easily getting airborne
• Fortnightly scraping/bulldozing of road to prevent accumulation of lose
dust on road, to shift it to sides and to keep roads almost leveled to ensure
smooth movement of vehicles and also prevent spillage, thereby,
minimizing fugitive dust emissions from the roads towards the villages
• Covering the carrying vehicles with tarpaulin to prevent spillage
• Proper tuning of vehicles to keep the emissions and noise as per norms.
• Restriction of vehicle speed
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 9 of 12
� Water Management and Water Pollution Control:
Mining activities will not cause adverse impacts as the mineral is non toxic
in nature. Lease area is fairly flat reducing the possibility of soil erosion.
Garland drain will be made to properly channelize the rain water and wash
offs in sedimentation ponds. As the manpower likely to be deployed from
nearby village, is not very high discharge of domestic waste water will be
easily controlled with the provision of septic tank and soak pit. The stored
water will be used for dust suppression, and greenbelt development,
etc.Following control measures will be taken to minimize negative due to
mining activity;
• Proposal of garland drain around the excavated pit with the progress
of Mining creation of water bodies will take place and accumulated
water of the same will be used for dust suppression and green belt
development.
• Drain along the periphery, around the quarry pit will be required
together and connected to the proposed water body.
Water Consumption (Avg.) 4-8 KLD
Waste Water
Generation
Only from domestic section, taken care
by Soak pit/ Septic tank arrangement
Source of water Nearby Village
� Noise Environment:
Movement of truck/ dumper will create the transitional noise level.
However noise generated by these will be occurring at low level and will be
within the prescribed upper limit. Following control measures will be taken
to minimize negative impact due to mining activity.
• Proper maintenance of all machines will be carried out which will
reduce noise generation during operations.
• Workers exposed to high noise levels will be provided with ear
defenders.
• Proper maintenance of machinery, equipment’s and improvement on
design of machines.
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 10 of 12
• Use of personal protective devices i.e. earmuffs and earplugs by
workers, working in high noise areas.
• Provision of green belt all along the periphery of the lease area.
• Conducting periodical medical checkup of all workers for any noise
related health problems
• Proper training to personnel to create awareness about adverse noise
level effects.
• Noise barriers, silence and enclosures shall be incorporated in the
equipment, which limit noise levels.
• Unnecessary use of horns by the drivers of the vehicles shall be
avoided.
13. PROVISIONS FOR SEPARATE STACKING OF SURFACE SOIL
EXCAVATED FROM MINING OPERATION AND IT’S UTILITY:
Top soil in the lease area is very scanty. Available soil will be removed and
kept stacked for utilizing for plantation in the backfilled area, when the
mine reaches the ultimate limits. Grasses will be planted on the soil along
the slopes to prevent wash offs during monsoon and prevent landslides.
14. DETAILS OF SOCIAL AND ECONOMIC UP GRADATION OF
MINING EFFECTED AREA DUE TO PROPOSED PROJECT:
4.50 Hectares Bhaunti Soil/ Murrum Quarry of M/s KCC BUILDCON PVT.
LTD. Mine has undertaken community development works in order to
improve the amenities in nearby villages as a part of commitment towards
social and economic upliftment of the area. Mining is expected to have
positive impact on socio-economic life of people living in nearby villages. No
impact on agricultural lands has been reported due to mining, nor has
mining affected the climate of the area. There has been rather an
improvement in the status of the people because of increase in income due
to direct or indirect employment Mining has created awareness amongst
the people for education and general upliftment particularly in the
womenfolk.
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 11 of 12
15. ENVIRONMENTAL MANAGEMENT IMPLEMENTATION
BUDGET:
PROPOSED COST FOR EMP
Sr. No. Particulars Amount (in Rs.)
1. Tree Plantation (including post
plantation care, protection)
1,00,000
2. Pollution control (Water spray, etc.) 45,000
3. Monitoring 40,000
4. Approach Road maintenance 25,000
5. Miscellaneous 30,000
Total 2,40,000/-
PROPOSED COST FOR CSR/ESR
Sr. No. Particulars Amount (in Rs.)
1. Fund for installing Water Tank to the
villagers.
20,000
2. Fund for School for extracurricular
activities and maintenance & other
facilities
25,000
3. Contribution to Swach Bharat Abhiyan 15,000
4. Contribution to Digital India Mission,
Fund for installing a computer setup
in Gram Panchayat Office.
30,000
Total 90,000/-
EMP Bhaunti Soil/ Murrum (Temporary Permit) Quarry
Page 12 of 12
PROPOSED COST FOR LABOUR WELFARE
Sr. No. Particulars Amount (in Rs.)
1. Drinking Water Facility &
Temporary rest shelter
(Construction Cost is fixed)
25,000
2. Mobile toilet 15,000
3. Regular Medical check-up of
laborers
25,000
4. Contribution for laborer's
children education
15,000
Total 80,000/-
16. ANY OTHER DETAILS DESIRED TO BE SUBMITTED BY
MINERAL CONCESSION HOLDER:
All information regarding EMP has been mentioned above point. Other
information is given in Form-1, PFR & Mining plan.