Entry Capacity Substitution Workshop 7 – 10 th February 2009
description
Transcript of Entry Capacity Substitution Workshop 7 – 10 th February 2009
Entry Capacity Substitution Workshop 7 – 10th February 2009
2
Agenda
Timeline
Further review of options
Mechanical approach
Two stage auction
Option model
Next Steps
3
TCMF – Develop Charging Methodology / Pricing Options
Further development of Charging Methodology
Develop Charging Methodology Changes at TCMF
07/11/09Submit Pricing Changes for
Approval
27/07/09Commence informal
Consultation on Pricing Changes
Approval of
Pricing Changes
Draft Timeline – Development of Methodology
Jan 09 Feb 09 Mar 09 Apr 09 May 09 June 09 July 09 Aug 09 Sept 09 Oct 09 Nov 09 Dec 09
Workshops
5 – Review status – explain risks/rewards process5 – High level options – work through of potential options6 – Industry options – review alternatives6 – Review all options – narrow down for development7/8 – Detailed options/examples9 – Finalised options/examples10 - Update industry following Informal Consultation
07/01/09Workshop 6
07/04/09Workshop 8
07/07/09Workshop 10
12/05/09Workshop 9
10/02/09Workshop 7
Develop stage 1 Licence Direction/Changes 01/04/09
Licence Changes Effective
S23 Notice
Develop stage 2 Licence Changes
07/09/09Submit ECS for Approval
07/12/09Approval of
ECS
27/07/09
Impact Assessment as necessary
28D 14DConsult Report
21D 28DConsult Finalise
Start consultationsInformal Formal
08/06/09 24/08/09Close formal consultation
Consult and Report (non-urgent)
Develop UNC Mod Proposals
07/12/09Approval of UNC
Mods
19/11/09Mod Panel Decision
17/09/09Mods to Panel
02/07/09Tx Workstream: present mods
IT Systemsdevelopment
31/03/09Progress
report
4
Summary of workshop 6
Option
1) Draft Methodology
2) Limits on Quantity
3) National Grid Discretion
4) Ofgem Discretion
5) Simple Economic Test
6) Exchange Rate Cap /
Economic Test Combination
7) Option Model
8) Sub-Reserve Prices
9) Early Warning System
10) Two Stage Auction
11) BGT Proposal
After consideration of the 11 options it was agreed that we focus on:
A Mechanical Approach (options 2 and 6);
Two Stage Auction;
Option Model.
All options build upon the draft methodology as the starting point.
5
Base Methodology
Publish QSEC auction invitation -
including entry zones and ASEP distance
order
Hold QSEC auction
Determine whether any requests pass
the NPV test?
No
Finish
Yes
Identify recipient ASEP with lowest
revenue driver auction
Do any ASEPs within zone have capacity above
sold levels?
Yes
Consider all within zone donor ASEP
with capacity above sold level
together
Undertake Network Analysis
Can all reinforcement be
avoided?
Accept substitutions and
update ASEP obligated levels
Are there any other recipient ASEPs?
Yes
Finish
No
Consider non-zonal substitutions
Yes
Undertake Network Analysis
Can all reinforcement be
avoided?
Do any remaining ASEPs have
capacity above sold levels?
No
Consider next nearest out of
zone ASEP with capacity above
sold levels substitutions
Yes
No
Yes
Reject all partial substitutions
No, but retain partial valid substitutions
Entry Capacity Substitution Mechanical Approach
7
Mechanical Approach
Each substitution opportunity progresses subject to satisfying: Limits set on availability of capacity at potential donor ASEP
Use TBE as criteria to exclude capacity from substitution. Alternatives considered, historic, % baseline, % unsold.
An exchange rate cap:
Suggest 5:1 As TBE peak forecast should protect all foreseen developments a high
exchange rate cap should be appropriate and its inclusion ensures that capacity is efficiently re-allocated.
An economic assessment:
Suggest no economic assessment in the mechanical approach. The mechanical approach uses simple physical rules. “Economic” criteria lie
with the economic “options model”.
8
Mechanical ApproachUses the maximum TBE Forecasts and an XR cap to place limits on substitution
Publish QSEC auction invitation -
including entry zones, ASEP distance order and TBE Maximum Flow Forecast
Figure per ASEP from 42 months
Hold QSEC auction
Determine whether any requests pass
the NPV test?
No
Finish
Yes
Identify recipient ASEP with lowest
revenue driver auction
Do any ASEPs within zone have capacity above
TBE level?
Yes
Consider all within zone donor ASEP
with capacity above TBE level
together
Undertake Network Analysis
Can all reinforcement be
avoided and is the aggregate XR below [5:1]?
Accept substitutions and
update ASEP obligated levels
Are there any other recipient ASEPs?
Yes
Finish
No
Consider non-zonal substitutions
Yes
Do any remaining ASEPs have
capacity above TBE level?
No
Consider next nearest out of
zone ASEP with capacity above
TBE level substitutions
Yes
No
Yes
Do any ASEPs within zone have capacity above
TBE level?
Yes
Consider nearest within zone donor
ASEP with capacity above
TBE level
Undertake Network Analysis
Can all reinforcement be avoided and is the
specific XR below [5:1]?
Yes
No
Undertake Network AnalysisCan all
reinforcement be avoided and is the specific XR below
[5:1]?
Reject all partial substitutions
No, but retain partial valid substitutions
No, but retain partial valid substitutions
Invitation to contain statement that TBE values are not subject to challenge.
Storage sites to be based on Max Deliverability.
References to capacity above TBE mean above sold level if higher.
Exchange rate cap to be proposed at 5:1
9
Mechanical ApproachMaximum TBE Forecasts (storage sites use Max deliverability)
1. Figures obtained from the Licence2. Figures obtained from http://www.nationalgrid.com/uk/Gas/Data/CMR/ as at 01.01.093. Figures obtained from Table A2.3A from 10 Year Statement4.Figures obtained form Platts and are EOD "possible" Maximum delivery figures No published data available
ASEP Baseline 90% Baseline Peak sold TBE Peak Supply Max deliverability
(see note 1) (see note 1) (see note 2) (see note 3) from Platts Gwh GWh Gwh Gwh (see note 4)
Avonmouth 179.3 161.37 22 0 1590
Bacton 1,783.40 1605.06 895 1,488 n/a0 0
Burton Point 73.5 66.15 13 11 n/a0 0
Barrow (TBE excludes Bains) 309.1 278.19 278 90 n/aBaines 0 00Barton Stacey (aka Humbly Grove) 82.6 74.34 90 0 800 0
Cheshire excludes HH (TBE includes British Salt,Holford, Stublach) 285.9 257.31 514 0Holehouse Farm 131.6 118.44 118 0 58Caythorpe 0 0 90 0 910 0
Dynevor Arms 49 44.1 22 0 500 0
Easington (inc Rough) 1,062.00 955.8 1,361 1,310 n/aRough 0 481Fleetwood 0 0 650 00 0
Glenmavis 99 89.1 0 0 1030 0 0Garton (aka Aldbrough) 0 0 420 00 0 0Hatfield Moor (storage) (TBE aggregates storage and onshore) 25 22.5 22 0 26Hatfield Moor onshore 0.3 0.27 00 0
Hornsea 175 157.5 206 0 1930 0
Isle of Grain 218 196.2 666 342 n/a0 0
Milford Haven 0 0 950 538 n/a0 0
Partington 215 193.5 22 0 2240 0 n/aSt Fergus 1,670.70 1503.63 472 1,272 n/a0 0
Teesside 476 428.4 162 337 n/a0 0
Theddlethorpe (TBE excludes Saltfleetby) 610.7 549.63 20 90 n/aSaltfleetby 0 0 860 0
Wytch Farm 3.3 2.97 0 negligble n/a
Entry Capacity Substitution Option Model
11
Option Model (Basic)
Capacity at an ASEP would be prevented from being substituted in response to an incremental signal elsewhere. This would be subject to an “option”. But what exactly is the option?
The option is a means to delay or prevent capacity being substituted from a particularly ASEP.
The option
does not give rights to the Shipper to use the capacity covered by the option;
does not give the Shipper first option to buy the capacity; but
it would reserve capacity at the relevant ASEP for any Shipper to obtain at a later auction.
12
Option Model – What is the Option?
Which “option” for the Option should be considered?
a) Proposal - Simple option with no further rules:
i.e. the option excludes the capacity from substitution processes. It is valid for 1 year covering all auctions (including ad-hocs) and protects capacity for the duration of the auction period;
simple to apply, understandable, provides certainty
b) Variant - Option with an economic test:
i.e. the option excludes the capacity from substitution processes only if the value of the “protected” capacity is greater than the incremental capacity;
more complex, may not provide the protection expected, hence may have no value, nature of the test needs consideration.
c) Rejected - Option and exercise:
i.e. if the “protected” capacity is identified for substitution the User may exercise the option and buy the capacity;
would extend post-auction timelines to exercise option, would require full commitment from User before being ready to commit.
13
Option Model – Possible Timeline for Options(assuming March QSEC)
FEB MARCH
Option window
Timing of Option Window
QSEC invitationletter
QSECauction starts
Shippers need to know how much capacity is available to have an option over:Hence the option window would follows the QSEC invitation.
Option invitation (part of QSEC invite)
Option window open two weeks after invitationOpen for three days
Options placed are not transparent to other Users
NG publishes option information:ASEPs, aggregate option quantity
14
Option Model – How Much?
How much should the Option cost?Needs to be high enough to discourage speculative options, but not too high that it encourages discontinuous single quarter bookings.
As the option protects for the full auction and is valid for a year; what could we link the option price to?
The NPV test is assessed over 32 quarters and can be used with the minimum capacity reserve price.
Propose that Option Price = Q * 0.0001p/unit x 32 quarters.
15
Option Model – How Much?
How much should the Option cost?
Propose that Option Price = 0.0001p/unit x 32 quarters.
32 quarters represents 8 year NPV test period.
Example
For an option over 10 mcmd at any specified ASEP:
Option Cost =
10 * 10.8 * 10^6 (convert to kWh/day) * 0.0001 * 365 * 8 / 100 (convert p to £) = £315,360
This value seems appropriate as it is of the same order as a PWA required to progress works for a year for delivery of incremental capacity.
16
Option Model – Further Rules
Option Rules
Option is placed ahead of QSEC and applies for 12 months, i.e. covers one QSEC and any ad-hoc QSECs before next option window.
Option does not prevent other Shippers (or that Shipper) buying capacity at that ASEP.
Option fees are non-refundable.
Options permitted only up to the quantity available in QSEC (usually 90% baseline – sold).
Fixed option price: options pro-rated if available capacity is exceeded.
Exchange Rate Cap
It is within the Shipper’s ability to define the required level for the option, but as it requires an element of financial commitment a slightly lower exchange rate cap may be appropriate. An exchange rate of 4:1 is proposed.
17
Option Model – Economic Test(assuming March QSEC)
MARCH APRIL
Assume a March QSEC
QSECauction
QSEC analysisNPV test
QSEC analysisFind donor ASEPs
Test applied: requires exchange rate
Capacity release notice to Ofgem
What is the test?The test is intended to measure and compare the value of capacity substituted from a donor ASEP and the value of the incremental capacity released at a recipient ASEP. Where the value at the donor ASEP is higher substitution should not be progressed.
The test needs to be predictable for Users. It should be simple, transparent and have minimal (or no) impact on post QSEC analysis.Needs to be non-discriminatory.
Shipper options placed
NG quantifiesoption value
NG quantifiesincrement value
18
Option Model – Economic Test
Propose to use Licence Revenue Drivers.
NG determines value of capacity at recipient ASEPsUsing incremental bid quantity and relevant revenue drivers.
NG determines value of capacity at donor ASEPsWhere no option in place value is zero, otherwise
Using quantity of capacity covered by option(s) and relevant revenue drivers and the maximum exchange rate. Q * RD * XRmax
If a simple economic test is used there should be no impact on post-auction timelines. A more complex test may require Licence / UNC changes.
19
Option model with economic test
Substitution criteriaCapacity available above sold levelOf which, some or all, does not have an option on itValue of capacity is lower than recipient (Q * Rev Driver)
Publish QSEC auction invitation -
including entry zones, ASEP distance order
Hold QSEC auction
Are there any requests from the QSEC auction that pass the NPV test?
No
Finish
Yes
Identify recipient ASEP with lowest
revenue driver auction
Do any ASEPs within zone have
capacity that satisfies the
substitution criteria?
Yes
Consider all within zone donor ASEPs with capacity that
satisfies the substitution criteria
together
Undertake Network Analysis
Can all reinforcement be avoided and is the
aggregate XR below [4:1]?
Accept substitutions and
update ASEP obligated levels
Are there any other recipient ASEPs?
Yes
Finish
No
Consider non-zonal substitutions
Yes
Do any remaining ASEPs have capacity that satisfies the substitution
criteria?
No
Consider next nearest out of zone ASEP with capacity that
satisfies the substitution criteria
Yes
No
Yes
Do any ASEPs within zone have
capacity that satisfies the
substitution criteria?
Consider nearest within zone donor
ASEP with capacity that satisfies the
substitution criteria
Undertake Network Analysis
Can all reinforcement be avoided and is the
specific XR below [4:1]?
YesNo, but retain partial valid substitutions
No
Undertake Network AnalysisCan all
reinforcement be avoided and is the specific XR below
[4:1]?
Reject all partial substitutions
No, but retain partial valid substitutions
Open options window
Publish Options resultsASEPs & aggregate quantity
Identify incremental capacity value
(quantity * revenue driver
20
Option Model – Further Issues
Issues
Is the pricing methodology fair / discriminatory / effective?Treats all ASEPs alike, significant cost but not excessive.
When is the option cost paid?Pay post QSEC, in capacity invoice. Needs commitment, “security” issue, want to avoid need for refunds if capacity substituted.
Would this option encourage single quarter bookings?32 * cost of single quarter,
immediate financial commitment. Should rules be introduced to limit
single quarter bookings?
Can existing systems be used for placing options?Consideration of “options” functionality on Gemini needed.
Do options impact on use of Permits?NG may identify opportunity to release capacity early; would options affect NG’s analysis that leads to this decision?
Can options be made available to Developers?
Entry Capacity Substitution Two Stage Auction
22
Two Stage Auction
This option needs to be considered as a means to prevent capacity being substituted from a particularly ASEP by allowing Shippers an opportunity to respond to perceived vulnerability of certain ASEPs when incremental capacity has been requested elsewhere.
Baseline and incremental capacity can be obtained in the first phase.
Only baseline capacity can be obtained in the second stage.
23
Two Stage Auction – Timeline
STAGE 1 Five rounds
Invitation letter – unchanged
But will include substitution information, e.g. entry zones and distances.
Shippers bid for unsold obligated and incremental.
M T W T F S S
Auction closed
Issues
Auction open at start of month to create time for analysis.
May require Licence changes.
Are five rounds enough?
Stability measure retained.
Auction opened
24
Two Stage Auction – Timeline
STAGE 1 Five rounds
NG identifies valid incremental and publishes ASEPs and
quantities.
Shippers bid for unsold baseline and incremental.
M T W T F S S M T W T F S S M T W T F
Auction closed
Allocations madeon Gemini
Issues
Allocations are made without Ofgem approval. No history of Ofgem rejection.
Would require allocations to be backed out if Ofgem reject.
Assessment of “vulnerable” ASEPs lies with Shipper based on information provided.
Auction opened
Invitation letter – unchanged
But will include substitution information, e.g. entry zones and distances.
Incrementalcapacityidentified
NPVtest
Info published for each ASEP:Total sold
NPV pass quantity
Infopublished
25
Two Stage Auction – Timeline
NG identifies valid incremental and publishes ASEPs and
quantities.
M T W T F S S M T W T F S S M T W T F
Stage 2 will only be run where an incremental signal has been received in stage 1.
Stage 2 run using AMSEC functionality
Possible IT issue.
Stage 2 rules
Pay as bid.
Release to Y+15
Available capacity is same as stage 1 minus any sold in stage 1. No pro-rating across stages.
Three discrete rounds. No next-day withdrawal of bids.
NPVtest
STAGE 2 Three rounds
Shippers bid for unsold baseline only.
Shippers identify vulnerable ASEPs /
capacity.
Auction reopened
Allocationsmade onGemini
Infopublished
Auction closed
Shipperreview
26
Two Stage Auction – Timeline
M T W T F S S M T W T F Submit incremental release letter to Ofgem
Stage 2 allocations to be made within 2 months of close of QSEC.
Ofgem 28 day veto period
Post-auction processes
STAGE 2 Three rounds
Auction reopened
Auction closed
If Ofgem veto stage 1 incremental release then the incremental allocations need to be backed out.
[No history of Ofgem veto].
27
STAGE 2: 3 roundsObligated only
Two Stage Auction – March 2010 timeline
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
STAGE 1: Five roundsObligated & incremental
Stage 1 closed
Allocations madeon Gemini
Stage 1 QSECopened
Pre-auction activities include invitation letter / notice of prices / IECRInvitation letter – essentially unchanged, but will include substitution information, e.g. entry zones and distances.
IncrementalcapacityidentifiedNPV
test
Info published for each ASEP:Total sold & quantity passing NPV test
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Stage 2 AMSEC opened
Stage 2 closed
Shipperreview
28
Two Stage Auction – Issues
Exchange rate cap set at 2:1
The two stage option does not protect donor ASEP capacity to the extent of the Mechanical Approach. Unlike the Option Model it requires full financial commitment from the Shipper if capacity is to be protected. Hence a lower cap would be appropriate.
How will the process be applied to ad-hoc auctions?
Run baseline auction (AMSEC functionality)
Major UNC modification.
Re-design of auction processes
Systems impact.
Use of existing functionality being considered
Possible licence change.
Developers cannot place capacity bids.
29
Two stage auction
Publish QSEC auction invitation -
including entry zones, ASEP distance order
Hold "shortened"
QSEC auction - 5
rounds
Are there any requests from the QSEC auction that pass the NPV test?
No
Finish
Yes
Identify recipient ASEP with lowest
revenue driver auction
Do any ASEPs within zone have capacity above
sold level?
Yes
Consider all within zone donor ASEP
with capacity above sold level
together
Undertake Network Analysis
Can all reinforcement be avoided and is the
aggregate XR below [2:1]?
Accept substitutions and
update ASEP obligated levels
Are there any other recipient ASEPs?
Yes
Finish
No
Consider non-zonal substitutions
Yes
Do any remaining ASEPs have
capacity above sold level?
No
Consider next nearest out of
zone ASEP with capacity above
sold level substitutions
Yes
No
Yes
Do any ASEPs within zone have capacity above
sold level?
Consider nearest within zone donor
ASEP with capacity above
sold level
Undertake Network Analysis
Can all reinforcement be avoided and is the
specific XR below [2:1]?
Yes
No, but retain partial valid substitutions
No
Undertake Network AnalysisCan all
reinforcement be avoided and is the specific XR below
[2:1]?
Reject all partial substitutions
Publish incremental signals received
that would pass the NPV test
Hold 3 round pay as bid quarterly auction for obligated capacity for the QSEC auction
transaction period
No, but retain partial valid substitutions
30
Recap of all options.
Do they offer the benefits of substitution?
Is it unduly restrictive?
Do they mitigate the risks presented by substitution?
New long term supply projects
Short term players – price sensitive
New supply projects – marginal fields
How difficult would they be to implement?
Systems impact?
Shipper processes?
National Grid processes?
Three options considered.
Mechanical Approach
TBE
Exchange rate capped at 5:1
Option Model
With / without economic test
Exchange rate capped at 4:1
Two stage auction:
Exchange rate capped at 2:1
Do the options satisfy the main substitution criteria?
31
Next Steps
1) Provide any initial comments on proposed options, and views on bullets 3 to 5, by 20th February 2009;
2) For the next workshop National Grid will amend the options and add further detail as appropriate.
7th April
10am to 1pm
At Elexon (to be confirmed)
3) What information would you require to assess the options at the next workshop?
4) What examples should we consider?
5) Is the level of detail right?