Ensuring Feasible Life of Mine Plans for Active...
Transcript of Ensuring Feasible Life of Mine Plans for Active...
Ensuring Feasible Life of Mine Plans for Active Operations
Dr. Martin L. Smith MineSmith, Pty Ltd Brisbane, Australia
Synopsis
• Mine Planning – what is it?
• The mine planning professional – who does it?
• The dominant role of the General Mine Planning (GMP) package
• A comparison of approaches to decision making between the minerals industry and all others
• Why existing GMP-based planning solutions yield operationally infeasible solutions
• Examples of how intelligent application of OR technology yields operationally optimal solutions
• LOBOS – a math programming platform for the minerals industry
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 2
In the midst of powerful technologies, we are failing to produce viable business plans through ignorance of the science of decision making and dependence on inadequate tools.
Mine Planning – what is it?
Essentially, mine planning is about what to mine and process, when to do it and how. It is decision making backed by a variety of engineering and earth science disciplines. Common planning decisions include: • Reserves vs. Resources • Cutoffs (material destination) • Mining methods • Mining and processing capacities and rates • Production resources • Access • Sequencing and scheduling of development and production
Greenfield projects from Brownfield (active) operations should be treated separately, as the focus of planning and level of complexity and risk is quite different, with the first placing emphasis on financial evaluation and the latter on production.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 3
Planning Integrates Design
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 4
Mine Planners must see the forest from the trees
Constraints
Targets
Production targets drive the design process
Design constraints limit what can be accomplished in planning
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 5
The mine planner seeks to maximise stakeholder value
Indigenous Groups
Government Financial Institutions
Land owners
Share holders
While honouring the constraints determined by the deposit and engineering limitations
Access Rates
The larger world: Stakeholder Objectives
The mine: Limits on Production
Re
serv
es
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 6
The mine planning professional – who does it?
We know about geotechnical, ventilation and maintenance engineers, hydrogeologists, metallurgists and geologists. At least you have to get a degree in these professions, often a masters or higher. What about the mine planning engineer? What sort of degree and training does he receive…? What is his professional tool-set? What are the foundations of mine planning? In this industry design oriented engineers are thrust into decision making in a complex, multi-faceted and uncertain environment. For this they are unprepared and poorly equipped.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 7
Current State of Mine Planning
• Mine planning has not evolved from an academic foundation as have design-based engineering disciplines
• It has relatively recent origins in industrial practice and software applications
• General Mine Planning software (GMPs) has transformed mine planning but for many defines what is possible and what is not
• Mining engineers are rarely trained in the foundations of planning. Instead the focus is on using GMPs to support standard mining operations
• Some specialised mine planning software is available, but these are often black boxes to engineers with limited if any training in the underlying technology
• This GMP-based software is inadequate to the task and oriented to greenfield project evaluation – not to the complexities of active operations
• In conclusion, while design engineers have a foundation in the basic sciences and are prepared for independent problem solving, mine planners are limited to GMPs!
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 8
GMP Constituent Technologies Database management:
•Drillhole assay, lithology & survey data
•Surveys of topography, face position & engineering structures
•Map data as points and strings
•Triangulated surfaces and volumes
•Geologic (block) models
•Engineering geometries Point and String Handling:
•Standard CAD functionality
•Mine design specific functionality
•Conversion of multiple strings into volumes
Surface and Volume modeling:
•Triangulation of points and strings
•Areas and volumes of intersction
•Block model interrogation Data Analysis & Geostats:
•Standard statistics
•Variography
•Inverse distance and Kriging
•Conditional Simulation
Scheduling:
•Bench sequencing
•Definitions of constraints
•Definition of scheduling units
•Optimisation?
•Schedule reporting
Pit Optimisation:
•Lerchs-Grossman algorithm
•Definition of slopes
•Economic modelling
•Selection of pushbacks
•Reserve reporting
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 9
Decision sciences, modelling and Operations Research
A mine planner without fundaments
Simulation: Evaluation of productivity, capacity and
feasibility
Geostatistics: Estimation,
categorisation and ore/waste
discrimination
Math Programming: Optimisation of mine plans. Options, risk and sensitivity analysis.
Financial modelling: Conversion schedules of cost and revenue into measures of value.
GMPs
Schedule Optimisation Conditional Simulation
Fin
anci
al R
isk
Ge
olo
gic
Ris
k
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 10
Alternative Approaches to Business Improvement
Currently in the Mining Industry
Buy expensive “optimization” software wo fully understanding the problem.
Train (and retain?) a mining engineer to run the application to a presupposed problem.
If the software can´t solve the problem stop (and hire a specialist consultant?) or live with an incomplete (infeasible?) solution.
But in the general industry
Hire a specialist in OR possibly with no prior experience the application.
Integrate the specialist into the planning team (train him up).
Within the team, the specialist defines problem and: • Selects most appropriate
solution technology • Or creates in-house solution • To optimize operations
Specialist becomes a driver of business improvement. … and repeat.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 11
Why existing GMP-based planning solutions yield operationally infeasible solutions
• Mine specific solutions do not account for interaction of business units
• Predetermined levels of production and time granularity do not allow for operational planning
• Inability to add constraints for site specific problems
• No integration of production with haulage and dump construction
• No consideration of processing and environmental constraints
• Do not account for uncertainty
• Simplistic representation of the cutoff problem
• Black Box approach to problem solving – no flexibility
• Lack of OR awareness in Minerals industry – “Tail wagging the dog”
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 12
Mine specific solutions do not account for interaction of business units
Include multiple business streams, mines, plants, processes and products all competing for resources. Determine how much of each product to produce to optimize the overall business along with the activity levels of all mines and plants.
Multiple products: sell concentrate now or cathode later? Multiple processes: ore, concentrate, anode, cathode with by-products.
Is it more profitable to run ore from a different business unit through the concentrator?
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 13
Predetermined levels of production and time granularity do not allow for operational planning
Sto
pin
g U
nit
Sto
pe
Min
ing
Blo
ck
Pa
nel o
r A
rea
Granularity relates to the level of detail used in the planning process. Inappropriate granularity in the size of the scheduling unit and duration of the planning period are a major deficiency in commercial mine planning tools. Mismatched levels of granularity result in strategic planning targets that are operationally infeasible.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 14
Inability to add constraints for site specific problems The general application, black box nature of GMP optimisation solutions does not allow for project specific decisions, constraints and objectives. Active operations are not necessarily NPV driven. Issues such as concentrate grades and penalties, plant and fleet utilisation and environmental constraints are more common drivers of production.
Total mining costs published from the mine context
Multiple products – metal and acid
System variables are deducted from the net benefit for equipment purchases and rehandle as is total waste cost, published from the mine context. The final net benefit is selected as the goal.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 15
No integration of production with haulage and dump construction
Dump construction broken into lifts and cells with associated haulage productivity.
Bench attributes include shovel productivities and haulage rates for each material’s destination.
Pit specific variable and constraints used to track consumption of fleet hours for pit specific and global constraints on shovel and haulage fleet activity.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 16
Optimised Production Fleets
Loader fleet size tracked as a function of activity levels in benches.
Loader fleet hour capacity utilisation tracked over time.
Haulage requirements based on production requirements by stage-bench, cycle time, tray capacity and equipment availability/utilization estimates.
Shovel productivity based on bench geometry. Capacity/availability and minimum shovel working space.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 17
No consideration of processing and environmental constraints
Mill Throughput
Fill 2900
Pnyang SS 2900
Darai LS 2700
Monz PRY 3200
Monzodiorite 2600
Endoskarn 3000
Skarn 2700
PY Skarn 3100
Oxide Skarn 3700
Mill feed capacity is a function of throughput rates – not simply a tonnage limit. Geometallurgy must be accounted for.
Need to consider environmental limits on waste acidity, sulphur and metal in tails or contaminants in concentrates. 3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 18
Do not account for uncertainty
• Planning is being conducted deterministically without consideration of the stochastic behaviour of many inputs (price, exchange rate, cost, capacity, grade, recovery, etc.).
• Robust mine planning requires greater flexibility in the toolbox used by planning engineers: – Conditional Simulation for geologic uncertainty
– Discrete Simulation for production systems
– Options analysis within an exact optimisation framework
– Sensitivity analysis using Linear Programming
– Probabilistic financial modelling with Monte Carlo simulation
• Robust mine planning cannot be limited to flexing a few external sources of risk and requires a systematic and intensive analysis of interacting sources of uncertainty. No single commercial platform is available with this capability, but math programming provides a framework for integrated risk assessment.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 19
Weighted average grade estimates result in poor reconciliation
Simulation 1 Simulation 2 Simulation 3 Simulation 4 Kriged
Running multiple optimised schedules across a range of simulations provides a check on mill feed distributions, avoiding the errors resulting from planning using a smoothed estimator.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 20
Discrete Production Simulation
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte
Focus is production system analysis over a relatively short time frame. How do production fleets of various configurations interact in a static mine plan? Can use simulation to optimise elements of the production system, but not optimisation in the mathematical sense.
Extremely useful complement to deterministic schedule optimisation. Simulation provides realistic scheduling inputs such as equipment utilisation and productivity and production system capacities. Also valuable as a means of testing the feasibility of a production schedule at the level of operational planning.
21
Simplistic representation of the cutoff problem
• Cutoff varies both spatially and temporally as a function of many factors which are often site specific: – The geometallurgy of the deposit which is spatially variable
– Variations in costs (operating and capital) over time (also by mining area or method)
– Mining capacity which varies as a function of the working conditions and equipment used and which can also vary over time according to projected needs
– Milling capacity which can experience episodic changes
– As well as many additional constraints on production (environmental, materials handling, development rates, etc.) which limit the capacity to process specific ores at a given point in the schedule.
• Consequentially, the optimal cutoff is not a single value. Rather it is an outcome of an optimal production policy in which the ore delivered to the mill satisfies all constraints on production while delivering maximum value (as defined by the objective function).
• A complete cutoff policy is derived from an optimised production schedule.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 22
Analyze the distribution of cutoff bins by destination for each mining area based on the objective function (here NSR/t). When material at the same value goes to multiple destinations, evaluate the constraints to determine what is the full cutoff function.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 23
LOBOS – a math programming platform for the minerals industry
The previous examples presented common limitations of commercial black box mine planning systems and how these were overcome in actual projects using the Life of Business Optimisation System (LOBOS) in combination with other OR technologies. LOBOS facilitates the rapid implementation of complex mine plans at a level of detail that supports operational mine planning by producing both feasible and optimal production strategies at the required level of granularity. LOBOS facilitates the generation of LP/MIP models and their optimisation using high-end commercial Solver engines (Cplex and Gurobi). Inputs, outputs and user defined model components allowing the problem to be both site specific and solved to a level of detail and complexity that meets operational requirements. Superior model formulation, solution strategies and state of the art solvers results in solutions that look far into future operations so that today´s decisions are optimal with respect to tomorrow´s production needs.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 24
Alternative Methodologies: a Difference in Emphasis Math Programming (LOBOS)
Model formulation: • Variables • Constraints • Objective
Evaluate model structure: • Linear/Nonlinear • Integer/Convex/Separable • Network/Sparse
Select appropriate algorithm: • Primal/Dual Simplex • Network/Barrier • Steepest gradient
Optimise: • Improve algorithm settings • Improve formulation • Add hueristics
Specialty Algorithms & Black Boxes (GMPs)
Write Solver Engine: • “Model” not accessible • End product is a compiled
executable
Choose technology appropriate for problem: • Ideally LP • Otherwise custom built engine (DP,
GA, SA, other)
Tightly restrict inputs to specific problem to be solved
Provide UAI for specific inputs and outputs
New model components?
Revise en
gine
New model components?
Rev
ise
mo
del
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 25
LOBOS: Recent Projects in Active Operations
• PanAust Phu Kam Copper Gold operation – Cutoff optimisation – Waste production and storage integrated
with LoM plan • DeBeers Cullinen Diamond Mine
– Draw control optimisation with a LOBOS prototype (IDCS)
• Rio Tinto Lisheen UG Copper Mine – Primary through tertiary stope scheduling – Alternative cutoffs
• Zinifex, Century Open Pit Lead Zinc Mine – Stage/Bench/Block sequencing – Earth moving fleet minimisation – Haulage and dump construction
• XSTRATA Zinc UG Lead Zinc Mining Complex – LoM production plan for multiple products – Open cut and UG mines – Stockpile usage
• Beaconsfield Gold UG Gold Mine – Alternative reserve scenarios – Cutoff grade by stope – Development, fill and production schedules
• OTML OK Tedi Copper – Gold Mining Complex – Extend OC production scheduling to
production panels – Inclusive of metallurgical model – Fleet size and allocation – Dump and stockpile usage – Cutoff and stockpile optimisation – Strategies for sulphur reduction in mine
wastes • BHPB Olympic Dam Uranium-Copper UG Expansion
– High level LoMP production schedule – Inclusive of metallurgical model – Regional Cut-off grade optimisation
• Roche Mining Kogan Creek Coal Open Cut – Pit and production schedule optimisation – Blend optimisation
• Kaltim Prima Coal, Open Cut Mining Complex – Multi-pit optimisation – Contractor v. owner haulage – Mine Reserve optimisation
• Consolidated Minerals, Open Cut Manganese Complex – Multi-pit business optimisation – Development rate/dewatering strategy
• Hecla Mining, Greens Creek (PRIMO) – Strategy optimisation (cutoff, methods, reserves)
• Oz Minerals, Prominent Hill UG Mine (PRIMO) – Strategic and tactical mine plan optimisation
• Oz Minerals, Prominent Hill Open cut and UG Complex – Stockpiling strategy and cutoffs – Open pit schedule optimisation – Blending, concentrate grade optimisation – Multiple underground mines
• Codelco, San Antonio open cut copper project – Option analysis for a large oxide-sulphide copper
open cut including alternative stage configurations and mineral processing options and capacities.
– Fleet optimisation – Scheduling
• Barrick Lumwana open cut copper complex – Medium term to Life of Mine production
scheduling – Stockpiling and cutoff strategies – Reserve optimisation – Production fleet optimisation
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 26
MineSmith : types of project
• Any project requiring the integration of multiple business units in a mining complex: multi-mine, multi-product, surface to underground transition
• Cutoff optimisation at a level supporting actual implementation (what goes where and when) inclusive of complex stockpiling strategies
• Implementation of complex geometallurgical constraints, ore hardness, complex recovery relationships, concentrate contaminants limits & ore-waste blending
• Control of environmental constraints in tailings, emissions and waste dumps.
• Determination of production fleet requirements and routing
• Integration of waste production with dump construction
• Coordination of development with production schedules in underground mines
• Evaluation of risk (geologic, financial and production) in an optimisation paradigm
Effectively, any problem that cannot be solved by a GMP solution and which must be put into operational practice and when a superior solution is required.
3/21/2013 UFMG - Engenharia Minas, Belo Horizonte 27
MineSmith Pty Ltd Mine Optimisation Services
ABN: 58 137 563 136
www.minesmith.com.au
Australia Martin Smith, Managing Director [email protected]
LOBOS: Life of Business Optimisation System