Enhancing the future
Transcript of Enhancing the future
RAPIDI N F R A S T R U K T U R
MISSION
Our mission is to build and organize infrastructure and industrial plant toenhance the future.
VISIONTo become center of excellence for engineering, construction, and projectmanagement, achieving extraordinary result by incorporating leanphilosophy and state-of-the-art technology
Collaboration for Excellence
HOW WE DELIVER OUR VALUES
P R O J E C TO W N E R
P R O J E C TI N T E G R A T O R
V E N D O R S P E C I A L I S TC O N T R A C T O R
C O N V E N T I O N A L I N T E G R A T E D
P R O J E C T O W N E R
P M C
E P C C O N T R A C T O R
V E N D O R S U B - C O N T R A C T O R
FOR EXAMPLE…
ConventionalProject Scheme
(in million USD)
IntegratedProject Delivery
(in million USD)
MPC 2
EPC
Engineering 5 5
Procurement 55 55
Construction 15 15
Project Management 10 10
Contingency 2 0
Profit 10 0
PPh 3 0
Subtotal 102 85
Contingency 10 27
TOTAL 112 112
Profit sharing
Using Integrated Project Delivery System enable significant improvement which cannot be implemented using the Conventional Project Scheme. We are able to minimize the vertical management chain and ‘flatten’ the organization chart. With the right leadership, this will improve the response time and agility of the project delivery team, also less time and effort for plan-do-check-action iterative cycle.
“Integrated project scheme will be 15% more efficient than conventional project scheme”
SECTOR EXPERTISE
P E T R O C H E M I C A L
W A T E RT R E A T M E N T
S U G A RF A C T O R Y
O I L A N DG A S
O P E R A T I O N A N DM A I N T E N A N C E
P O W E RG E N E R A T I O N
QUALITY ASSURANCE
LEGALITIES
LEGALITIES
CERTIFICATE
CERTIFICATE
OURSERVICES
OPERATIONAL & MAINTENANCE SERVICESEffective Operational & Maintenance practice is the best method to promote reliability,safety, and energy efficiency in our client’s operating plant. Poor management andresource planning on this area would cause time and energy waste. Energy losses fromsteam, water and air leaks, uninsulated lines, and other losses from poor maintenance areoften ignored since operational activities functions just fine.
Our experiences in O&M services includes:• Robotic Borescope Service• Bolt Torque• Preservation Works• Confined Space Works
PRE-COMMISSIONING, COMMISSIONING & START-UPCommissioning & start-up is a phase between construction and operational phase of anindustrial facility. Highly multi-disciplined, systematic, and professional methodology iscritical to escort our client’s facility to their operational phase. It is important for us tomanage this phase with the highest regard of safety, technical efficiency, schedule, andbudget.
Our expertise in various industry and technology implementation helps us to provide ourclients with system-wise commissioning management and execution. Developing a moretime-efficient start-up program with reliable method and supervisory from our engineers.
OURSERVICES
PROJECT MANAGEMENT SERVICESProject Management ConsultancyCost-overrun, progress lagging, and massive re-work usually haunts majority of construction project around
the globe. This was an impact of poor project management coordination, low data input or analytics, and
excessive administration and bureaucracy in project management. Construction industry does not realize this
habit and low efficiency, as the procedure and systems they have had been implemented for decades, even
though it is in dire need of a fresh change.
Rapid emerge as a disruptive idea in the middle of a stagnant industry, granting alternative approach of
project management system to optimize manpower dan administrative functions, cutting through
unnecessary bureaucracy to boost productivity and reduce costs.
Our solution includes, but not limited to:
• Lean construction philosophy and technology• Resource/ contractor management to achieve project on time, on budget & on schedule• Integrate all multidiscipline in the site project• Manage simultaneous operation• Manage system completion and system-wise management
Hazard and Operability Study (HAZOP)Our project management service puts heavy concern on safety and operability of our result of work. We
provide extensive study on the hazard and operability for our clients, before the execution of the projects. Our
team consists of a range of multi-disciplinary team and a number of highly-experienced leaders, with more
than 20 years of domestic and overseas experience.
Our expertise on Geothermal, Oil & Gas, Petrochemical and Food Industry is critical to deliver a time
effective HAZOP study, providing our client with a comprehensive risk assessment result.
OURSERVICES
COLLABORATIVE CONSTRUCTIONConstruction IntegratorConstructing industrial facilities is an art of combination between simultaneous multi-
discipline works, such as; civil, steel structure, mechanical erection, piping installation,
electrical, and instrument works. Our proficiency in interface management ensures our
clients to gain exemplary benefit on time management, resource management, and project
scheduling.
We manage all our work with lean philosophy, executing simultaneous operations
(SYMOPS) and system-wise completion by committing to our procedures and safety
measurements, ensuring flawless delivery of our work to our clients.
Construction IT ServiceDigitalization is one of the most important aspect in today’s construction industry. A
megaproject would employ thousands of construction workers and hundreds of works
registered only for one working shift. Our RFID (Radio-Frequency Identification) for
manpower, equipment, and material management would provide our clients with the
necessary efficiency evaluation of their resources.
Our CDR (Construction Dashboard Reporting) will optimize progress control work by
digitizing the process of construction progress data gathering. Said data then processed and
analyzed to produce extensive reports on construction progress, delayed or early work, and
recommendation to speed-up work progress based on data analytics.
OURSERVICESPROJECT STUDY, ENGINEERING, and EVALUATION
Before the crucial construction phase of industrial facility, development stages such as project study,
engineering phase, and research evaluation must be conducted to ensure flawless construction and
operational phase. To ensure the quality delivered to our clients, we provide our expertise for in-house
engineering work.
Considering the importance of engineering and study phase in our industry, we always achieve on-time
delivery and outstanding quality on our engineering and research works. Providing study results about
technical, design, and commercial service for our client to support either preliminary study or
construction activity.
BATAM
TANJUNGCARAT
BOJONEGORO
BALIKPAPAN
SUMBA
BINTUNI
PROJECT PORTFOLIOS
ENERCO RPO TDAE PROCESSING PLANT (Pipeline)Project Owner : PT Enerco RPO InternationalProject Value : USD 3,200,000Service Period : May 2018 – Dec 2018
PRE-FEASIBILITY STUDY ON METHANOL PROJECTGRISSIK CORRIDOR FOR RUKUN RAHARJA, TBKClient : Rukun RaharjaService Period : July 2020 – Sept 2020
PERTAMINA JTB EVAPORATOR & CRYSTALISATION UNIT -PMTMain Contractor : Rekind-JGC JOProject Value : USD 2,500,000Schedule : Nov 2019 – Nov 2020
DJARUM GROUPMURIA MANIS SUGAR PLANT – PMTProject Owner : PT Muria Sumba ManisProject Value : USD 4,200,000Schedule : Feb 2020 – Dec 2021
PERTAMINA RDMP RU V WATER TREATMENT PLANT – PMTLOCAL PARTNER FOR FOREIGN SUPPLIER COMPANYMain Contractor : RDMP JOProject Value : USD 18,500,000Service Period : Febr 2020 – Dec 2021
PERTAMINA RDMP CRUDE OIL TANK COMPLEX - PMTMain Contractor : RDMP JOProject Value : USD 8,000,000Schedule : Mar 2019 – Jun 2021
BP TANGGUH LNG PLANTProject Owner : BP p.l.c.Project Value : USD 15,000,000Schedule : Nov 2019 – Dec 2022
PMT for:- Piping
Direct work for:- Structure- Borescope- Bolt Torque- Preservation- Commissioning
PERTAMINA JTB INSTRUMENT, ELECTRICAL, MECHANICAL AND GATHERING PIPELINE WORK PACKAGE Main Contractor : Rekind-JGC JOProject Value : USD 3,000,000Schedule : Jan 2021 – Sept 2021
CILEGON
VESSEL AND TANK FABRICATION PMTClient : PT TIMASProject Value : USD 160,000Schedule : Jun 2021 – Dec 2021
ENERCO RPO TDAE PROCESSING PLANT (O&M)Project Owner : PT Enerco RPO InternationalProject Value : USD 300,000Service Period : Jan 2020 – Jun 2021
ENERCO RPO TDAE PROCESSING PLANT (PMT)Project Owner : PT Enerco RPO InternationalProject Value : USD 1,500,000Service Period : May 2018 – Jun 2021
PERTAMINA RDMP RU V WATER TREATMENT PLANTLOCAL PARTNER FOR FOREIGN SUPPLIER COMPANY (slide 1/2)
Project Value Capacity Schedule Location
USD 18,500,000 3,500 MTPH February 2020 – July 2021 Balikpapan, Indonesia
Scope Stakeholder
Rapid assists the project owner to acquire an improved capacity and quality for their desalination plant with a better price. This is achievable by engineering and designing the suitable technology and process to comply with the standard of our client. We then assist the project owner until the delivery of the technology on-site to ensure perfect delivery and quality to our client.
Scope:• Fabricate and supply Sea Water Desalination, Reverse Osmosis,
De-mineralization and Re-mineralization system• Specialized in carbon steel, super duplex stainless steel, glass
reinforced epoxy (GRE), and fiber-reinforced plastic materials• Project schedule control• Technical assist in project execution design phase
RDMP JOMain Contractor
Aquatech SA – Rapid Infrastruktur Indonesia JOEngineering, Fabrication, and Supply Vendor
PT PertaminaOwner
Subcontractors
PERTAMINA RDMP RU V WATER TREATMENT PLANTLOCAL PARTNER FOR FOREIGN SUPPLIER COMPANY (slide 2/2)
FABRICATED ITEMS
SWRO, BWRO,ERD
Sea Water Desalination, Brackish Water Reverse Osmosis, De-mineralization and Re-mineralization System, and Energy Recovery Device using the most current and reliable technology.
DOSING PACKAGE
• Consists of 48 skid package• 12 hypo dosing and poly
dosing units, including pumps• 7 CS- SS Vessels weighing 12.4
Tonnes, using SA 516 Gr 70 and SA 240 Gr. 316
• Remineralization Vessel weighing 43.3 Tonnes using SA 240 Gr. 316
• Sludge Thickener
PIPE RACK FABRICATION
Fabricating and installing frame, rack, and piping for the skids and the whole system, also its instruments such as valves. Also uses special grade corrosive
resistance Super Duplex Stainless Steel
GLASS REINFORCED
EPOXY
This facility’s piping system also using GRE pipe due to its properties that can withstand high temperature, excellent chemical and corrosion resistance, also able to handle seawater.
Project Value Capacity Schedule Location
USD 8,000,000 15,000 MT (3 tanks) March 2019 – June 2021 Balikpapan, Indonesia
Scope Stakeholder
Rapid provides consulting service to our client starting from proposal ontoproject execution phase. We provide technical and commercial assistance toensure the project runs without any issue on technical execution and projectcashflow.
We help top level management in decision making to avoid delays in projectexecution, since the pandemic hit our project site in the middle of ourworking schedule.
Scope:• Project management for 3882 Tonnes of crude oil tank construction• Plan project execution for additional complementary scope such as;
insulation clip support, walkway and platform, painting, and hydrotest• Cost and project schedule control
RDMP JOMain Contractor
PT Pertamina (Persero) RU VOwner
PT Cahaya Hidup PrimakaryaContractor
PT Rapid Infrastruktur IndonesiaContractor
PERTAMINA RDMP RU V CRUDE OIL TANK COMPLEX - PMT
OUTSIDE VIEW OF CRUDE OIL TANK INSIDE VIEW OF CRUDE OIL TANK
DJARUM GROUP MURIA SUMBA MANIS SUGAR PLANT -PMT
Project Value Capacity Schedule Location
USD 4,000,000 6,000 TCD Feb 2020 – Dec 2021 Sumba, IndonesiaScope Stakeholder
Developing one of the major investments from our client which is 6000-12000 TCD sugarmilling and refining plant. This project is in need for a high-performing managementteam. Therefore, Rapid collaborate with Muria Sumba Manis team to lead, manage,review, rearrange agreements and scope of works between sub-contractors, vendors, andtechnology licensor. We function as project integrator across discipline and stakeholders.
We achieved 200% construction progress after the implementation of our projectmanagement system, bringing the project closer to achieve the targeted schedule.
Project Management Services • Project status and progress evaluation• Commissioning and Start-up assist• Contract settlement process• Crash program design to speed up the project• Refinery sugar is available to be processed from sugar cane and raw sugar• Construct and commissioning boiler STG powered with bagasse and coal• Design, construct and commissioning coal handling system, raw sugar handling
system, and bagging system
PT Muria Sumba ManisOwner
PT Rapid Infrastruktur Indonesia
Project Integrator
Subcontractors• PT Swadaya Graha
• PT Tatamulia Nusanra indah• PT Weltes Energi Nusantara• PT Syamsir Karya Pertama• Statec Binder GmbH.
Engineering and Procurement Vendor• Isgec Heavy Engineering Ltd.
PROCESS EQUIPMENTS VESSELS AND PIPING
POWER PLANT AREA BOILER PIPINGWATER TREATMENT PROCESSPOND
ENERCO RPO TDAE PROCESSING PLANT - PMT
Project Capitalization Capacity Schedule Location
USD 1,500,000 180,000 MTPY May 2018 – June 2021 Batam, Indonesia
Scope Challenges StakeholderEnerco is the pioneer of TDAE plant in Indonesia with its own unique technology. This brings additional challenge as we have no predecessor in constructing the TDAE Plant.
We managed to complete the construction of the plant on-time, on-budget, and proudly exceeds the designed performance.
Project Management and Consultancy Services • Status and progress project evaluation• Bidding process• Commissioning and start-up phase assist• Technical marketing assist• Regular maintenance lead
• Initial schedule from October 2017 - April2019 (18M)
• Status as per April 2018: progress 26% (lag16%)
• Dispute with sub-contractors in term ofscope of work and budget.
• Assisting CESCO for chemical cleaning
Result of hard-work
• LTI Zero• Mechanical Completion achieved on end
March 2019PT Timas
Subcontractor
PT Enerco RPO InternationalOwner
PT Rapid Infrastruktur IndonesiaContractor
PT Energy Management IndonesiaContractor
BIRD EYE VIEW OF ENERCO RPO PLANT TOPSIDE VIEW OF ENERCO RPO PLANT
PIPE PAINTING CLOSER VIEW OF THE PLANT
PERTAMINA JTB EVAPORATOR & CRYSTALISATION UNIT PMT
Project Value Capacity Schedule Location
USD 2,500,000 52,000 MTPY Nov 2019 - Nov 2020 Bojonegoro, Indonesia
Scope Stakeholder
Rapid assists our clients to provide a solution to semi-solid waste treatment in Pertamina JTB Gas Processing Plant.
Using the technology provided & engineered by Rapid, our client could easily dispose their waste in dry-solid form, complying with national regulation.
Project Management and Consultancy Services • Technical and commercial assist for vendor in since
bidding phase• Risk matrix analysis• Cost control• Provide a cutting-edge engineering solution• Project schedule control• Technical assist in project execution design phase
PT Pertamina EP CepuOwner
PT Rapid Infrastruktur IndonesiaContractor
PT Energy Management IndonesiaContractor
Alfa Laval CorporationFabricator
ENERCO RPO TDAE PROCESSING PLANT - PipelineProject Value Pipeline Constructed Schedule Location
USD 3,200,00012 km
17,432 DIMay 2018 – Dec 2018 Batam, Indonesia
Scope Pipeline Details Stakeholder
Pipeline Construction• Constructing 17.432 Dia-inch
carbon steel pipeline from Rubber Processing Plant to Jetty
• Working on Horizontal Directional Drilling (HDD) on the underground pipeline
• Installing pipe sleeper on the surface pipeline
• 12“ Pipeline DAE 3 km
• 12” Pipeline TDAE 3 km
• 12” Pipeline HACE 3 km
• 12” Pipeline Fire Water 3 km
PT Citra Tubindo EngineeringSubcontractor
PT Enerco RPO InternationalOwner
PT Rapid Infrastruktur IndonesiaContractor
FIRE WATER, DAE, TDAE, AND HACE PIPELINES
ENERCO JETTY ANOTHER LOOK OF ENERCO JETTY
PIPELINEPIPELINE TO JETTY PIPELINE
JTB INSTRUMENT, ELECTRICAL, MECHANICAL AND GATHERING PIPELINE WORK PACKAGE (slide 1/3)
Project Value Work Volume Schedule Location
USD 3,000,0006.79 Km9,397 DI
January 2021 – September 2021 Bojonegoro, Indonesia
Scope Stakeholder
Rapid is responsible to manage pipeline works, starting from site preparation onto commissioning. We employ high-performing project management team to tackle any technical and social issue which may arise in executing this project.
We deliver by collaborating with our partners on electrical and instrumentation works, ensuring perfect quality of works to project owner.
Scope:• Site Preparation and Civil Work• Pipeline Works• River & Road Crossing Works• Pre-commissioning & Testing• Mechanical Installation• Electrical & Instrument Works
Rekind-JGC JOMain Contractor
PT Pertamina EP CepuOwner
PT Bojonegoro Bangun SaranaContractor
PT Rapid Infrastruktur IndonesiaContractor
We’re working on this project from
site preparationuntil
pre-commissioning
Gathering Pipeline consists of
1.53 km 20” Pipeline5.26 km 18” Pipeline
With total
9,397 DI
SPECIFICATION HIGHLIGHTS
Coated with
3-Layer Polypropylene
Coatingeasier to fabricate, and more
corrosion resistant and heat resistant than carbon steel
Using rare material
INCOLOY 825That’s easier to fabricate, and more corrosion resistant and
heat resistant than carbon steel
Welded with both
GTAW and SMAW
JTB INSTRUMENT, ELECTRICAL, MECHANICAL AND GATHERING PIPELINE WORK PACKAGE (slide 2/3)
Mechanical Works• 47 pcs Spool Bolting• 525 EA of Valves (Gate, Ball,
Globe, Check, DBB, Control Valves) sizes ranging from ½” up to 18”
• 3 Pig signal
JTB INSTRUMENT, ELECTRICAL, MECHANICAL AND GATHERING PIPELINE WORK PACKAGE (slide 3/3)
Electrical Works• 17,60 km FO Cable size 48C• 9,20 km Power Cable 3C-95
mm2• 5,12 km Power Cable 3C-70
mm2• Cathodic Protection installed
on the pipeline to prevent rust and corrotions
PIPE STRINGING PIPE LINEUP PIPE LOWERING
PIPE NEAR THE FACILITY
PIPE WELDING WELD INSPECTION GTAW WELD
WELD RESULTS
WELDING PREP
Project Value Work Volume Schedule Location
USD 900,000 15,000 DI 15 November 2019 - 31 May 2020 Papua, Indonesia
Scope of Work Stakeholder
Rapid was given the responsibility to lead the project management on LNG cold section piping work, to evaluate monthly progress and speed up the construction to achieve targeted schedule.
We review and rearrange project execution plan for direct and indirect manpower to increase productivity and achieve on-time delivery.
Scope:• Progress management • Material controlling• Construction supervision• Manpower supply
BP TANGGUH LNG PLANT- Piping
Chiyoda-Saipem-Tripatra-Suluh Ardhi Engineering JO Main Contractor
PT Rapid Infrastruktur IndonesiaContractor
BP P.L.COwner
ENERCO RPO TDAE PROCESSING PLANT OPERATION & MAINTENANCE
Project Value Capacity Schedule Location
USD 300,000 180,000 MTPY January 2020 – June 2021 Batam, Indonesia
Scope Stakeholder
Rapid supports Enerco TDAE Plant even further after the completion of the plant, Supporting operational and maintenance activity to ensure every aspect of engineered process and mechanical performance runs without any crucial issue.
Scope:• Upgrading and provide improvement for convenience plant
operation and maintenance• Network of manufacturing facilities and service centers, which
provides support for operation and maintenance activities• 24/7 services manpower support to run the plant safely and finish
every job incident free• Confined space maintenance work
PT Rapid Infrastruktur IndonesiaContractor
PT Enerco RPO InternationalOwner
HEAT EXCHANGER CLEANINGPREPARATION FOR CLEANING COLUMN
(CONFINED SPACE)
HEAT EXCHANGER (HE) DISASSAMBLING
HEAT EXCHANGER TUBINGLIFTED
WORKERS USING HAZMAT SUIT TO CLEAN THE HE
HEAT EXCHANGER DISASSAMBLING PULLING OUT HE TUBING
Project Value Schedule Location
USD 15,000,000 Nov 2019 – present Papua, Indonesia
Scope of Work Stakeholder
BP Tangguh LNG Expansion Project was located in a very remote area which makes logistics becomes one of the main determining factors for the project success. Therefore, it is essential to avoid re-work and preserve equipment integrity.
Rapid brings additional value by delivering precise work on our maintenance and support for our client’s facilities, ensuring no issue will rise once the plant is fully operational. borescope inspection & bolt tightening service are some examples of our supporting services, delivering excellence on our client’s assets commissioning phase.
BP TANGGUH LNG PLANT (slide 1/2)
Chiyoda-Saipem-Tripatra-Suluh Ardhi Engineering JO Main Contractor
PT Rapid Infrastruktur IndonesiaContractor
BP P.L.COwner
PRESERVATION1 January 2020 – 31 January 2021
COMMISSIONING1 July 2020 – 30 June 2021
BORESCOPE7 December 2019 – 31 August 2021
BOLT TORQUEING15 November 2019 – 30 November 2020
Scope of Work• Condition monitoring for
valve, pipe, and instrument devices
• Steel structure erection for Train 3 and brownfield area
Scope of Work• Pipe visual inspection• Repair recommendation• Assistance for
commissioning activity• Flange Management based
in torque standard
Scope of Work• Pipe inner layer camera-
assisted inspection • Making report of the pipe
inspection• Recommending action plan
based on the inspection
Scope of Work• Flange Management based
in torque standard• Pre-checking flange, bolt,
and gasket condition• Tightening bolt in a
sequence using a minimum of three torquing passes and the maximum bolt stress as defined in the reference documents
BP TANGGUH LNG PLANT (slide 2/2)
BORESCOPE MONITORING SETTING UP BORESCOPE MONITOR
BP PLC TANGGUH SITE BORESCOPE PREPARATION
SAFETY AWARD FOR RAPID INFRASTRUKTUR WORKERS FROM
CSTS JO
INSPECTING PIPE THROUGH MONITOR USING FLEXIBLE
BORESCOPE
ENGINEERING SERVICES FOR SUGAR FACTORY 6000 TCD
Project Value Capacity Schedule Location
USD 200,000 6,000 TCD June 2020 – December 2020 Jakarta, Indonesia
Scope Stakeholder
• Detailed engineering design in regards ofprocurement and construction phase for process,piping, mechanical, civil, structure, electrical,instrument and valve criticality construction
• Design engineering in regards of balance of plant tosupport sugar processing plant, such as coalhandling, raw sugar handling, automatic baggingsystem, and automatic fuel distribution
PT Rapid Infrastruktur IndonesiaEngineering Consultant
PT Muria Sumba ManisOwner
3D OVERVIEW OF SUGAR MILL PLANT
DETAILS OF THE PROCESSING PLANT
STRUCTURAL 3D MODEL
EVALUATION OF ENERCO TDAE PLANT FEASIBILITY AT 170,000 MTPY CAPACITY
Project Capitalization Capacity Schedule Location
USD 80,000 180,000 MTPY March 2020 – present Batam, Indonesia
Scope Stakeholder
Rapid collaborates with Institut Teknologi Bandung to conductan evaluation of design capacity of the TDAE Plant in severaloperational scenarios.
Our study proves through calculated simulation that anadditional capacity is available for utilization and added valueto our client
Scope:Evaluating plant current condition to perform at 170,000 MTPYCapacity. The evaluation had been done by simulation withprocess software such as HYSYS and HTRI. The result of thesimulation was compiled into a comprehensive report
PT Rapid Infrastruktur IndonesiaConsultant
PT LAPI ITBConsultant
PT Enerco RPO InternationalOwner
PRE-FEASIBILITY STUDY ON METHANOL PROJECT IN GRISSIK CORRIDOR FOR RUKUN RAHARJA Tbk.
Schedule Location
July 2020 - September 2020 Tanjung Carat, Indonesia
Scope Stakeholder
Rapid collaborates with Institut Teknologi Bandung to evaluate the feasibility of a high-capacity methanol plant business plan prepared by Rukun Raharja Tbk.
We provided detailed technical opinion on preferred plant capacity, compatible technology, suitable project location, and appropriate methods to improve project economics.
Scope:• Condition and Petrochemical Industry Mapping Study in Indonesia• Study of raw material• Market and factory capacity study• Technology review• Data study, analysis, and calculation• Methanol transportation and storage study• Risk analysis and study business models• Regulatory and policy review
PT Rapid Infrastruktur IndonesiaConsultant
Rukun Raharja Tbk.Owner
E-mail: [email protected]@rapidinfrastruktur.com
Phone: +62 21-27819899
Talavera Office Park, Lt. 8 (Marketing)Lt. 12 (Operation)
Address:Jl T.B. Simatupang No. 23, RT.3/RW.1, Cilandak Barat, DKI Jakarta 12430
Website: www.rapidinfrastruktur.com
CONTACT US