Engineering Project Management Civil Engineering Department.

440
Engineering Project Management Civil Engineering Department

Transcript of Engineering Project Management Civil Engineering Department.

Page 1: Engineering Project Management Civil Engineering Department.

Engineering Project Management

Civil Engineering Department

Page 2: Engineering Project Management Civil Engineering Department.

2

An-Najah National University

Civil Engineering Department

Faculty of EngineeringConstruction Engineering

andManagement

Nabil Dmaidi

April 10, 2023

Page 3: Engineering Project Management Civil Engineering Department.

3

Your Expectations of MeBe preparedBe on time

Teach for full 50 minute period

Fair grading systemFront load the class workDo not humiliate students

Practice golden ruleProvide real world examples

Make you think

April 10, 2023

Page 4: Engineering Project Management Civil Engineering Department.

4

Topics1) Management Functions and introduction of construction project planning and scheduling2)Construction scheduling techniques3)Preparation and usage of bar charts4)Preparation and usage of the Critical Path Method (CPM)5)Preparation and usage of Precedence Diagramming Method (PDM)6)Issues relating to determination of activity duration7)Contractual provisions relating to project schedules8)Resource leveling and constraining9)Time cost tradeoff10)Schedule monitoring and updating.11)Communicating schedule12) Project control and earned value Control13) claims, Safety and Quality control

April 10, 2023

Page 5: Engineering Project Management Civil Engineering Department.

5

Course Outline

Introduction and definitions Float Analysis

Importance of Scheduling The CPM Calculations

Networks, Bar Charts, and Brief introduction on:

Imposed Finish Date and Project Control and Earned

Value Analysis Resource Allocation /Leveling other CPM Issues Time/Cost Trade-off

Precedence Networks

Updating Schedules

Time-Scaled Logic Diagrams

April 10, 2023

Page 6: Engineering Project Management Civil Engineering Department.

6

In order to understand project management, one must begin with the definition of a projectproject. A project can be considered to be any series of activities and tasks that :.

● Have a specific objective to be completed within certain specifications

● Have defined start and end dates

● Have funding limits (if applicable)

● Consume human and nonhuman resources (i.e., money, people, equipment)

● Are multifunctional (i.e., cut across several functional lines)

What is the Project

April 10, 2023

Page 7: Engineering Project Management Civil Engineering Department.

7

OR

‘‘a temporary endeavor undertaken to create a unique product, service, or result’’

April 10, 2023

Page 8: Engineering Project Management Civil Engineering Department.

8

Project Life CycleApril 10, 2023

Page 9: Engineering Project Management Civil Engineering Department.

9

Five Process group

April 10, 2023

Page 10: Engineering Project Management Civil Engineering Department.

10

April 10, 2023

Page 11: Engineering Project Management Civil Engineering Department.

11

Successful project management can then be defined as having achieved the project objectivesproject objectives:

● Within Time

● Within Cost

● At the desired performance/Technology level

● While utilizing the assigned resources effectively and efficiently

● Accepted by the customer

April 10, 2023

Page 12: Engineering Project Management Civil Engineering Department.

12

What is Project Management Project management is the planning, organizing,

directing, and controlling of company resources for a relatively short-term objective that has been established to complete specific goals and objectives.

April 10, 2023

Page 13: Engineering Project Management Civil Engineering Department.

13

The potential benefits from project management are:

● Identification of functional responsibilities

● Minimizing the need for continuous reporting

● Identification of time limits for scheduling

● Identification of a methodology for trade-off analysis.

● Measurement of accomplishment against plans

April 10, 2023

Page 14: Engineering Project Management Civil Engineering Department.

14

The above definition requires further comment. Classical management is usually considered to have five functions or principles:

● Planning

● Organizing

● Staffing

● Controlling

● Directing

April 10, 2023

Page 15: Engineering Project Management Civil Engineering Department.

15

Planning

– Where the organization wants to be in the future and how to get there.

Organizing

– Follows planning and reflects how theorganization tries to accomplish the plan.

– Involves the assignment of tasks, grouping oftasks into departments, and allocation of resources.

April 10, 2023

Page 16: Engineering Project Management Civil Engineering Department.

16

Leading

– The use of influence to motivate employees toachieve the organization's goals.

– Creating a shared culture and values,communicating goals to employees throughoutthe organization, and infusing employees toperform at a high level.Controlling

– Monitoring employees' activities, determining if the organization is on target toward its goals, and making corrections as necessary

April 10, 2023

Page 17: Engineering Project Management Civil Engineering Department.

17

Conceptual Skill—the ability to see the organization as a whole and the relationship between its parts.

Human Skill—The ability to work with and through people.

Technical Skill—Mastery of specific functions and specialized knowledge

Management SkillsApril 10, 2023

Page 18: Engineering Project Management Civil Engineering Department.

18

Project management is designed to manage or control company resources on a given activity, within time, within cost, and within performance. Time, cost, and performance are the constraints on the project.

Constraints of the project April 10, 2023

Page 19: Engineering Project Management Civil Engineering Department.

19

Resources We have stated that the project manager must control company resources within time, cost, and performance. Most companies have six resources:

● Money

● Manpower

● Equipment

● Facilities

● Materials

● Information/technology

April 10, 2023

Page 20: Engineering Project Management Civil Engineering Department.

20

Actually, the project manager does not control any of these resources directly, except perhaps money (i.e., the project budget).

Resources are controlled by the line line managersmanagers .

The project manager project manager is responsible for coordinating and integrating activities across multiple, functional lines. The integration activities performed by the project manager include:

April 10, 2023

Page 21: Engineering Project Management Civil Engineering Department.

21

● Integrating the activities necessary to develop a project plan

● Integrating the activities necessary to execute the plan

● Integrating the activities necessary to make changes to the plan

April 10, 2023

Page 22: Engineering Project Management Civil Engineering Department.

22

Project Scheduling Project Scheduling Planning, Scheduling, Planning, Scheduling,

and Controland Control

April 10, 2023

Page 23: Engineering Project Management Civil Engineering Department.

23

Planning and Scheduling

Planning and scheduling are two terms that are often thought of as synonymous

They are not!

Scheduling is just one part of the planning effort.

April 10, 2023

Page 24: Engineering Project Management Civil Engineering Department.

24

Project planning serves as a foundation for several

related functions such as cost estimating, scheduling,

and project control.

Project scheduling is the determination of the timing and sequence of operations in the project and their assembly to give the overall completion time

April 10, 2023

Page 25: Engineering Project Management Civil Engineering Department.

25

Planning is the process of determining how a project will be undertaken. It answers the questions:

1“ .What” is going to be done,2“ .how,”

3“ .where,”4 .By “whom”, and

5“ .when” (in general terms: start and finish).

Scheduling deals with “when” on a detailed level… See Figure 1 .

April 10, 2023

Page 26: Engineering Project Management Civil Engineering Department.

26

The Plan

WhatHow much

By whom

where

Why

How

when

Figure 1 . Planning and Scheduling

April 10, 2023

Page 27: Engineering Project Management Civil Engineering Department.

27

The PlanPMI defines project management plan as a ‘‘formal, approved document that defines how the project is executed, monitored and controlled”.

The plan can include elements that has to do with scope, design and alternate designs, cost, time, finance, land, procurement, operations, etc.

April 10, 2023

Page 28: Engineering Project Management Civil Engineering Department.

28

WHY SCHEDUALE PROJECTS ?

1 -To calculate the project completion.

2 -To calculate the start or end of a specific activity.

3-To expose and adjust conflict between

trades or subcontractor.

4 -To predict and calculate the cash flow.

5-To evaluate the effect of changing orders ‘CH . ’

April 10, 2023

Page 29: Engineering Project Management Civil Engineering Department.

29

6 -To improve work efficiency.

7 -To resolve delay claims , this is important in critical path method ‘CPM’ discussed later..

8 -To serve as an effective project control tool.

April 10, 2023

Page 30: Engineering Project Management Civil Engineering Department.

30

The Tripod of Good Scheduling System1.The Human Factor : A proficient scheduler

or scheduling team.

2. The Technology : A good scheduling computer system (software and hardware)

3. The Management : A dynamic, responsive, and supportive management.

If anyone of the above three ‘‘legs’’ is missing, the system will fail.

April 10, 2023

Page 31: Engineering Project Management Civil Engineering Department.

31

Scheduling and project management Planning, scheduling, and project control are extremely important components of project management.project management includes other components :• cost estimating and management,

• procurement,

• project/contract administration,

• quality management,

• and safety management.

These components are all interrelated in different ways.

April 10, 2023

Page 32: Engineering Project Management Civil Engineering Department.

32

Quiz 1True or False:

1.There are no two projects that are identical

2.Every construction project needs a CPM schedule

3.Planning and scheduling are two names for the same function

4.The maintenance of a large office building is considered a project

5.The renovation of a large office building is considered a project

6.There is one standard way to break down the project into activities for the purpose of creating a schedule

April 10, 2023

Page 33: Engineering Project Management Civil Engineering Department.

33

Bar (Gantt) ChartsBar (Gantt) Charts

April 10, 2023

Page 34: Engineering Project Management Civil Engineering Department.

34

DEFINITION AND INTRODUCTION

• A bar chart is ‘‘a graphic representation of project activities, shown in a time-scaled bar line with no links shown between activities’’

The bar may not indicate continuous work from the start of the activity until its end.

or

Non continuous (dashed) bars are sometimes used to distinguish between real work (solid line) and inactive periods (gaps between solid lines)

April 10, 2023

Page 35: Engineering Project Management Civil Engineering Department.

35

• Before a bar chart can be constructed for a project, the project must be broken into smaller, usually homogeneous components, each of which is called an activity, or a task.

Item ActivityM 10 Mobilization

Bars ( Month or Year )

April 10, 2023

Page 36: Engineering Project Management Civil Engineering Department.

36

ADVANTAGES OF BAR CHARTS

1- Time-scaled

2- Simple to prepare

3- Can be more effective and efficient if CPM based - Still the most popular method

4- Bars can be dashed to indicate work stoppage.

5- Can be loaded with other information (budget, man hours, resources, etc.)

April 10, 2023

Page 37: Engineering Project Management Civil Engineering Department.

37

Bar Charts Loaded with More Info.Such as : budget, man hours and resources .

10 12 7 11 10 9 15

500$

220$

400$

850$

140$ 500$

900$

April 10, 2023

Page 38: Engineering Project Management Civil Engineering Department.

38

DISADVANTAGES OF BAR CHARTS

1- Does not show logic

2- Not practical for projects with too many activities-As a remedy, we can use bar charts to show:

1. A small group of the activities (subset)

2. Summary schedules

April 10, 2023

Page 39: Engineering Project Management Civil Engineering Department.

39

Quiz 2

True or False:1.The bar representing a 4-day activity is twice as long

as a bar representing a 2-day activity in a bar chart

2.Bar chart method lost its applicability with the introduction of the Critical Path Method

3.Bars in a bar chart must be connected with relationship lines

4.A bar representing an activity in a bar chart may not be continuous

5.Bar charts and Gantt charts are two different methods.

6.Bar charts can be loaded with information other than the timeline of the project

April 10, 2023

Page 40: Engineering Project Management Civil Engineering Department.

40

Basic NetworksBasic NetworksApril 10, 2023

Page 41: Engineering Project Management Civil Engineering Department.

41

DEFINITION AND INTRODUCTION

• A network is a logical and chronological graphic representation of the activities (and events) composing a project.

• Network diagrams are the preferred technique for showing activity sequencing.

• Two main formats are the arrow and precedence diagramming methods.

April 10, 2023

Page 42: Engineering Project Management Civil Engineering Department.

42

Two classic formatsAOA: Activity on ArrowAON: Activity on Node

Each task labeled withIdentifier (usually a letter/code)Duration (in std. unit like days)

There are other variations of labeling

There is 1 start & 1 end event

Time goes from left to right

April 10, 2023

Page 43: Engineering Project Management Civil Engineering Department.

43

Arrow Diagramming Method (ADM)

1 .Also called activity-on-arrow (AOA) network diagram or (I-J) method (because activities are defined by the form node, I, and the to node, J)

2 .Activities are represented by arrows.

3 .Nodes or circles are the starting and ending points of activities.

4 .Can only show finish-to-start dependencies.

April 10, 2023

Page 44: Engineering Project Management Civil Engineering Department.

44

i j

(a) Basic Activity

Activity Name

Node (Event) i

j > i

Each activity should have a unique i – j value

Node (Event) j

Basic Logic Patterns for Arrow Diagrams

April 10, 2023

Page 45: Engineering Project Management Civil Engineering Department.

45

2 A

(b) Independent Activities

4 10 B 12

3 A 6 B 9

(c) Dependent Activities

April 10, 2023

Page 46: Engineering Project Management Civil Engineering Department.

46

2

A

(d) A Merge

4

6B 8

(e) A Burst

C

Activity C depends upon the completion of both Activities A & B

8

A6

2B

4C

Activities B and C both depend upon the completion of Activity A

April 10, 2023

Page 47: Engineering Project Management Civil Engineering Department.

47

(f) A Cross

20

18C

16 D14

A12

B

Activities C and D both depend upon the completion of Activities A and B

April 10, 2023

Page 48: Engineering Project Management Civil Engineering Department.

48

ExampleDraw the arrow network for the project given next.

Activity IPA

A -B A

C A

D B

E C,D

April 10, 2023

Page 49: Engineering Project Management Civil Engineering Department.

49

Solution :

10

30

4020 50

C

D

A

B

E

April 10, 2023

Page 50: Engineering Project Management Civil Engineering Department.

50

Dummy activity (fictitious)

* Used to maintain unique numbering of activities.

* Used to complete logic, duration of “0” *The use of dummy to maintain unique

numbering of activities .

April 10, 2023

Page 51: Engineering Project Management Civil Engineering Department.

51

4 10

4 10

11

A

B

A

B

Divide node to correct

Dummy

(a) Incorrect Representation

(b) Correct Representation

April 10, 2023

Page 52: Engineering Project Management Civil Engineering Department.

52

ExampleDraw the arrow network for the project given next.

Activity IPA

A -B A

C A

D B,C

April 10, 2023

Page 53: Engineering Project Management Civil Engineering Department.

53

10 3020 40

C

DA

B

Solution :

10

30

4020 50

C

DA

BDummy

Improper solution

proper solution

April 10, 2023

Page 54: Engineering Project Management Civil Engineering Department.

545454

ExampleDraw the arrow network for the project given next.

Activity IPA

A -B A

C A

D B

E B,C

F C

April 10, 2023

Page 55: Engineering Project Management Civil Engineering Department.

55

Solution :

10

30

40

20 60

C

EA

B

Dummy 1

50Dummy 2

D

F

April 10, 2023

Page 56: Engineering Project Management Civil Engineering Department.

56

Removal of Redundant Dummies

A

A

A

A

B

B

B

B

C C

Original Diagram Diagram after removal of redundant dummies

(a)

(b)

April 10, 2023

Page 57: Engineering Project Management Civil Engineering Department.

57

A

A

A

A

C

C

B

C

B B

Original Diagram Diagram after removal of redundant dummies(c)

(d)

B E

C

E

E E

April 10, 2023

Page 58: Engineering Project Management Civil Engineering Department.

58

Activity Depends Upon Immediately Preceding Activity (IPA)

ABC

-----A

A, B

-----AB

B CA

Redundant

Relationship

April 10, 2023

Page 59: Engineering Project Management Civil Engineering Department.

59

Activity List with Dependencies:

Activity Description Depends Upon

ABCDEFGHJKLM

Site ClearingRemoval of TreesExcavation for FoundationsSite GradingExcavation for Utility TrenchesPlacing formwork & ReinforcementInstalling sewer linesPouring concreteObtain formwork & reinforcing steelObtain sewer linesObtain concreteSteelworker availability

----------A

A, B, CA, B, C

B, C, J, MB, C, D, E, KD, E, F, G, L

--------------------

April 10, 2023

Page 60: Engineering Project Management Civil Engineering Department.

60

Activity Description Depends Upon

ABCDEFGHJKLM

Site ClearingRemoval of TreesExcavation for FoundationsSite GradingExcavation for Utility TrenchesPlacing formwork & ReinforcementInstalling sewer linesPouring concreteObtain formwork & reinforcing steelObtain sewer linesObtain concreteSteelworker availability

----------A

A, B, CA, B, C

B, C, J, MB, C, D, E, KD, E, F, G, L

--------------------

Removing Redundant Relationships:April 10, 2023

Page 61: Engineering Project Management Civil Engineering Department.

61

AOA Representation

H4040

G4545

C

F

D3535

1515

1010

55B

A

2020

M

2525J

3030

E

L

K

April 10, 2023

Page 62: Engineering Project Management Civil Engineering Department.

62

NODE NETWORKS MTHOD (AON)

a) Independent Activities

10A

10A

20B

20B

Activity number

Activity name

b) Dependent Activities

20B

20B

10A

10A

Link

LinkB depends on A

April 10, 2023

Page 63: Engineering Project Management Civil Engineering Department.

63

30C

30C

10A

10A

20B

20B

40 D40 D

c) A Merge Relationship

C depends on A & BD depends on C

d) A Burst Relationship

20B

20B

30C

30C

40D

40D

10 A10 A

B depends on AC depends on BD depends on B

April 10, 2023

Page 64: Engineering Project Management Civil Engineering Department.

64

e) Start & Finish Dummy Activities

AA

CC

BB

EE

DDAA

StartDummyStart

DummyFinish

DummyFinish

Dummy

CC

BB

EE

DD

April 10, 2023

Page 65: Engineering Project Management Civil Engineering Department.

6565

ExampleDraw the arrow network for the project given next.

Activity IPA

A -B A

C A

D B

E C,D

April 10, 2023

Page 66: Engineering Project Management Civil Engineering Department.

66

Solution :

A E

C

DB

April 10, 2023

Page 67: Engineering Project Management Civil Engineering Department.

6767

ExampleDraw the arrow network for the project given next.

Activity IPA

A -B A

C A

D B,C

April 10, 2023

Page 68: Engineering Project Management Civil Engineering Department.

68

A

C

D

B

Solution : April 10, 2023

Page 69: Engineering Project Management Civil Engineering Department.

69696969

ExampleDraw the arrow network for the project given next.

Activity IPA

A -B A

C A

D B

E B,C

F C

April 10, 2023

Page 70: Engineering Project Management Civil Engineering Department.

70

Solution :

A PF

C

DB

E

F

April 10, 2023

Page 71: Engineering Project Management Civil Engineering Department.

71

Lags and Leads

In some situations, an activity cannot start until a certain time after the end of its Predecessor.Lag Lag is defined as a minimum waiting period between the finish (or start) of an activity and the start (or finish) of its successor.

Arrow networks cannot accommodate lags. The only solution in such networks is to treat it as a real activity with a real duration, no resources, and a $0 budget.

April 10, 2023

Page 72: Engineering Project Management Civil Engineering Department.

72

Examples

Place Concrete

3

Strips Forms 2

3

A lag in a node network

Place Concrete Strips Forms Cure Concrete

A lag in an arrow network

April 10, 2023

Page 73: Engineering Project Management Civil Engineering Department.

73

The term leadlead simply means a negative lag. It is seldom used in construction. In simple language: A positive time gap (lag) means ‘‘after’’ and a negative time gap (lead) means ‘‘before.’’

April 10, 2023

Page 74: Engineering Project Management Civil Engineering Department.

74

Recommendations for Proper Node Diagram Drawing

Incorrect Correct

April 10, 2023

Page 75: Engineering Project Management Civil Engineering Department.

75

A

B A B

A

B

A

BImproper proper

April 10, 2023

Page 76: Engineering Project Management Civil Engineering Department.

76

Improper Proper

April 10, 2023

Page 77: Engineering Project Management Civil Engineering Department.

77

Improper Proper

April 10, 2023

Page 78: Engineering Project Management Civil Engineering Department.

78

A

B

C

Improper Proper

A

B

C

PS

(a) Do not startstart a network with more than one node

April 10, 2023

Page 79: Engineering Project Management Civil Engineering Department.

79

A

B

C

Improper Proper

A

B

C

PF

(a) Do not endend a network with more than one node

April 10, 2023

Page 80: Engineering Project Management Civil Engineering Department.

80

The Critical Path The Critical Path Method (CPM)Method (CPM)

April 10, 2023

Page 81: Engineering Project Management Civil Engineering Department.

81

Suppose you decide with your friend to go in hunting trip .

You must do specific activity such that the trip well be at the right way. The following activity must be done .

IntroductionApril 10, 2023

Page 82: Engineering Project Management Civil Engineering Department.

82

From chart you can see that the 3rd activity (preparing the jeep) have the longest period of time any delay with this activity leads to delay in the trip this activity is a “critical activitycritical activity”

Critical activity : An activity on the critical path any delay on the start or finish of a critical activity will result in a delay in the entire project Critical path : The longest path in a network from start to finish

April 10, 2023

Page 83: Engineering Project Management Civil Engineering Department.

83

Steps Required To Schedule a Project

The preparation of CPM includes the following four steps:

1 -Determine the work activities:The project must be divided into smaller activities or tasks.

The activity shouldn’t be more than 14-20 days (long durations should be avoided)

Use WBS in scheduling by using an order of letters and numbers

April 10, 2023

Page 84: Engineering Project Management Civil Engineering Department.

84

2 -Determine activity duration: Duration = Total Quantity / Crew Productivity The productivity has many sources:

1 .The company 2 .The market

3 .Special books

Note: Note: The scheduler must be aware about the non-working days , such as holydays or rain days, etc……

April 10, 2023

Page 85: Engineering Project Management Civil Engineering Department.

85

Estimating Activity Duration

Time Interval Time Interval is selected according to the

nature of the activity (seconds - minutes…)

It is common practice in construction industry to use calendar day.

Use one and only one time unit for any schedule.

1. From company’s record

2. From standard estimating guide

3.Interviewing field personnel.

Sources

April 10, 2023

Page 86: Engineering Project Management Civil Engineering Department.

86

Weather and Contingency Allowance

Two approaches for assignment of weather allowance:1. Add the Weather Allowance at the end of the project as a

separate activity.

2. Add Weather Allowance to those affected by the weather.

3.Add weather allowance at the end of each construction segment (site preparation, foundation, … etc.)

Contingency itemsOther activities can be added to allow for contingency such as strikes

Time ZeroThe close of the work period immediately preceding the start

of the project.

April 10, 2023

Page 87: Engineering Project Management Civil Engineering Department.

87

3 -Determine the logical relationships:

This step is a technical matter and obtained from the project manager and technical team, and logical relationships shouldn’t confused with constraints

4- Draw the logic network and perform the CPM calculations

April 10, 2023

Page 88: Engineering Project Management Civil Engineering Department.

88

5-Reiew and analyze the schedule:

1 .review the logic

2 .Make sure the activity has the correct predecessor

3 .make sure there is no redundant activity

April 10, 2023

Page 89: Engineering Project Management Civil Engineering Department.

89

6- Implement the schedule: Definition: take the schedule from paper to the execution.

7-Monitor and control the schedule:

Definition: comparing what we planed with what actually done.

8-Revise the database and record feedback.

9-Resource allocation and leveling.(will discuss in chapter 6)

April 10, 2023

Page 90: Engineering Project Management Civil Engineering Department.

90

The WBS (Work Breakdown Structure) IT is used to break down the project from one

main and relatively big entity into smaller, defined, manageable and controllable units, usually called work groups or tasks, or, at the finest level of detail (which is undesirable) activities

April 10, 2023

Page 91: Engineering Project Management Civil Engineering Department.

91

Take care!!!

The deeper you go into the lower levels of the WBS, the more detailed knowledge you’ll need to know.

A good rule of thumb is the rule of 1-5-5-5, which entails that each level be broken down into a maximum of five lower levels.

April 10, 2023

Page 92: Engineering Project Management Civil Engineering Department.

92

Who develops the WBS?

A WBS is developed by the A/E at the end of the design phase.

and/or by the bidders during the proposal (procurement phase).

April 10, 2023

Page 93: Engineering Project Management Civil Engineering Department.

93

The CWBS (Contract Work breakdown Structure )After contract award, the project manager

expands the WBS into a contract work breakdown structure (CWBS).

as the initial step in the PLANNING process.

The extended CWBS must include the levels at which required reporting information is summarized for submittal to the Owner

April 10, 2023

Page 94: Engineering Project Management Civil Engineering Department.

94

Uses of the WBS The WBS is used to report program status

externally to the Owner.

The CWBS is used internally to plan the program in detail and to collect status information on a periodic basis for the lowest level of the CWBS, namely the schedule activities.

The basis for technical planning and project achievement.

April 10, 2023

Page 95: Engineering Project Management Civil Engineering Department.

95

The CWBS

it is a major task to undo.

Why???

Because cost collections begins at a CWBS element,

The individuals assigned the responsibility for WBS/CWBS development should never lose sight of the fact that the WBS is used for technical planning and status achievement.

April 10, 2023

Page 96: Engineering Project Management Civil Engineering Department.

96

House1.0

Structural Work1.1

fine works

1.2

Sub-Structure

1.1.1

Super-Structure

1.1.2

Finishing 1.21

Doors & Windowsframes

1.2.2

Electrical Works

1.3

Earthwork1.1.1.1

Foundation1.1.1.2

Columns1.1.2.1

Roof slabs1.1.2.2

Conduiting1.3.1

Light Fittings1.3.2

Plaster1.2.1.1

Floor tile1.2.1.2

Excavation1.1.1.1.1

Backfilling1.1.1.1.2

Level 1

Level 2

Level 3

Level 4

Level 5

April 10, 2023

Page 97: Engineering Project Management Civil Engineering Department.

97

Conclusion

The work breakdown structure defines the product elements (work packages).

And their interrelations to each other and to the product.

The WBS mostly ends with project tasks.

Using the tasks you can extract project’s activities.

April 10, 2023

Page 98: Engineering Project Management Civil Engineering Department.

98

TYPES OF ACTIVITIES

1. Production ActivitiesThose that can be taken directly from plans

and specifications

2. Procurement ActivitiesProcurement of material and equipment

3. Management Decision ActivitiesActivities that can be created by

management to avoid certain situationsDelay ConcreteCompany VacationDeer Hunting

April 10, 2023

Page 99: Engineering Project Management Civil Engineering Department.

99

Events and Milestones

An event: a point in time that is usually the start or finish of a certain activity(s)Duration = 0

Important events are called milestonesmilestones such as NTP and finish milestones such as Substantial Completion

An activity has a start date and a finish date

An event / milestone has a start date or a finish date

April 10, 2023

Page 100: Engineering Project Management Civil Engineering Department.

100

ExampleDraw the logic network and perform the CPM calculations for the schedule shown next.

Activity IPA Duration A - 5B A 8C A 6D B 9E B,C 6F C 3G D,E,F 1

April 10, 2023

Page 101: Engineering Project Management Civil Engineering Department.

101

In mathematical terms, the ES for activity j is as follows : ESj =max( EFi )

where (EFi) represents the EF for all preceding activities.

Likewise, the EF time for activity j is as follows :

EF j= ESj + Dur j

where Dur j is the duration of activity j

Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity

Forward pass calculationsApril 10, 2023

Page 102: Engineering Project Management Civil Engineering Department.

102

A5

G1

C6

D9

B8

E6

F3

22,23

5,11

5,13

13,22

13,19

11,14

0,5

Solution : April 10, 2023

Page 103: Engineering Project Management Civil Engineering Department.

103

In mathematical terms, the late finish LF for activity j is as follows:

) LFj =min(LSk

where (LSk) represents the late start date for all succeeding activities.

Likewise, the LS time for activity j (LS j) is as follows:

LS j= LFj - Dur j

where Dur j is the duration of activity

Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has.

Backward pass calculationsApril 10, 2023

Page 104: Engineering Project Management Civil Engineering Department.

104

Solution :

A5

G1

C6

D9

B8

E6

F3

22,23

5,11

5,13

13,22

13,19

11,14

0,5

22,23

13,22

19,22

16,22

5,13

10,16

0,5

CPM ( ES = LS , EF = LF , TF = FF = 0)

April 10, 2023

Page 105: Engineering Project Management Civil Engineering Department.

105

Four Types Of Floats

There are several types of float. The simplest and most important type of float is Total Float (TF) Total float (TF): The maximum amount of

time an activity can be delayed from its early start without delaying the entire project.TF = LS – ES or TF = LF - EF orTF = LF - Dur - ES

April 10, 2023

Page 106: Engineering Project Management Civil Engineering Department.

106

Free Float: may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities

FFi = min(ESi+1) - EFi

where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities

April 10, 2023

Page 107: Engineering Project Management Civil Engineering Department.

107

In the previous example we can find the free float and total float for each activity as the following :

Activity C’s free float, FF = 11 - 11 = 0 daysAnd Activity C’s total float, TF =16 - 11= 5 days …… and so on.

Activity Duration

ES EF LS LF TF FF

A 5 0 5 0 5 0 0B 8 5 13 5 13 0 0C 6 5 11 10 16 5 0D 9 13 22 13 22 0 0E 6 13 19 16 22 3 3F 3 11 14 19 22 8 8G 1 22 23 22 23 0 0

Critical activity Note : We must always realize that FF ≤ TF

April 10, 2023

Page 108: Engineering Project Management Civil Engineering Department.

108

Interfering float: may be defined as the maximum amount of time an activity can be delayed without delaying the entire project but causing delay to the succeeding activities.

TF = FF - Int. or Int. F = TF - FF

Independent float (Ind. F): we may define it as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities and without being affected by the allowable delay of the preceding activities.

Ind. Fi = min(ESi +1 ) – max(LFi-1) – Duri

Note: make sure that Ind. F ≤ FF

April 10, 2023

Page 109: Engineering Project Management Civil Engineering Department.

109

Node Format

Activity Name

Activity ID

Duration

ES EF

LS LF

TF FF

April 10, 2023

Page 110: Engineering Project Management Civil Engineering Department.

110

Example

Activity Duration IPA

A 5 -

B 8 A

C 6 A

D 9 B

E 6 B,C

F 3 C

G 1 D,E,F

April 10, 2023

Page 111: Engineering Project Management Civil Engineering Department.

111

Tabular Solution

Activity Duration ES EF LS LF TF

A 5 0 5 0 5 0

B 8 5 13 5 13 0

C 6 5 11 10 16 5

D 9 13 22 13 22 0

E 6 13 19 16 22 3

F 3 11 14 19 22 8

G 1 22 23 22 23 0

April 10, 2023

Page 112: Engineering Project Management Civil Engineering Department.

112

A5

F3

D9

E6

C6

B8

G1

5, 13

0, 5 13, 19

5, 11

13, 22

11, 14

22, 235, 13

0, 5 16, 22

10, 16

13, 22

19, 22

22, 23

A5

D9

B8

G1

5

3

8

All dates above represent the end of the day

Graphic SolutionApril 10, 2023

Page 113: Engineering Project Management Civil Engineering Department.

113

Example

Activity Duration IPA

A 5 -

B 6 A

C 5 A

D 3 A

E 3 B

F 4 B, C

G 4 D

H 7 B,C,G

I 8 E, F

J 2 F

K 3 H, J

L 2 I, J

April 10, 2023

Page 114: Engineering Project Management Civil Engineering Department.

114

A5

D3

B6

C5

G4

E3

F4

H7

I8

J2

K3

L2

PF

April 10, 2023

Page 115: Engineering Project Management Civil Engineering Department.

115

A5

D3

B6

C5

G4

E3

F4

H7

I8

J2

K3

L2

PF

0, 5

0, 5

5, 11

5, 10

5, 8

11, 15

11, 14

8, 12

15, 17

15, 23

12, 19

23, 25

19, 22

25

25

23, 25

22, 25

15, 23

20, 22

15, 22

12, 15

11, 15

11, 15

5, 11

6, 11

8, 11

1

3

1

3

5

3 3

Graphic SolutionApril 10, 2023

Page 116: Engineering Project Management Civil Engineering Department.

116

Activity ES EF LS LF TF FFA 0 5 0 5 0 0B 5 11 5 11 0 0C 5 10 6 11 1 1D 5 8 8 11 3 0E 11 14 12 15 1 1F 11 15 11 15 0 0G 8 12 11 15 3 0H 12 19 15 22 3 0I 15 23 15 23 0 0J 15 17 20 22 5 2K 19 22 22 25 3 3L 23 25 23 25 0 0

Tabular SolutionApril 10, 2023

Page 117: Engineering Project Management Civil Engineering Department.

117

End-of-Day Convention

The dates on the activities represent the “end of day”. That’s why we always start with day 0: end of day 0 = start of day 1

This concept is not applied in computer programs. In computer programs start dates (ES, LS) represent the beginning of the day while finish dates (EF, LF) represent the end of the day

April 10, 2023

Page 118: Engineering Project Management Civil Engineering Department.

118

Exercise Solution Using The Computer

A5

D3

B6

C5

G4

E3

F4

H7

I8

J2

K3

L2

PF

1, 5

1, 5

6, 11

6, 10

6, 8

12, 15

12, 14

9, 12

16, 17

15, 23

13, 19

24, 25

20, 22

25

25

24, 25

23, 25

16, 23

21, 22

16, 22

13, 15

12, 15

12, 15

6, 11

7, 11

9, 11

1

3

1

3

5

3 3

April 10, 2023

Page 119: Engineering Project Management Civil Engineering Department.

119

Comments on the Solution

Near-critical activities may be as important as critical activities

It is a good practice for the project manager not to give subordinates two sets of dates

PM has to choose one set of dates within the range of Early – Late

Management may reserve a number of days as “management float” or “time contingency”

April 10, 2023

Page 120: Engineering Project Management Civil Engineering Department.

120

Float Discussion

Total float –in general- belongs to a path rather than the activity itself

If an activity uses “its” float, successors may lose some or all of “their” float

Total float versus free float

Total float is broken down into free float, independent float, and interfering float.

Researchers have come up with even more types

April 10, 2023

Page 121: Engineering Project Management Civil Engineering Department.

121

The question is: “who owns the float”?

Float distribution attempts

Review the contract – what if it is not mentioned?

Float with resource leveling

Shifting activities within their float may affect:

Start / finish dates of succeeding activities

Resource usage: Labor and equipment (crews)

Materials: delivery, storage

Cash flow

April 10, 2023

Page 122: Engineering Project Management Civil Engineering Department.

122

Lags in Node Networks

A lag is a minimum compulsory waiting period between the start/finish of an activity and the start/finish of the successor

Actual waiting period may be greater, but never less than the lag

Lags are very common with SS and FF relationships

A lead is a negative lag

The lag is added in the CPM’s forward pass calculations and subtracted in the backward pass

April 10, 2023

Page 123: Engineering Project Management Civil Engineering Department.

123

Examples: Concrete curing (before formwork stripping

or reshoring)

Asphalt curing (before striping)

Waiting for a permit to be issued

Waiting for the delivery of a custom material or equipment

April 10, 2023

Page 124: Engineering Project Management Civil Engineering Department.

124

Example

Activity Duration IPA Lag

A 5 -

B 3 -

C 6 -

D 7 A

E 7 A

B 4

F 4 A,B,C

G 5 E

F 3

H 6 D

G 2

I 3 D,G

April 10, 2023

Page 125: Engineering Project Management Civil Engineering Department.

125

C6

B3

A5

G5

F4

E7

D7

H6

I3

4

3

2

PS PF

270

0 27

0, 5 5, 12

0, 3

0, 6

7, 14

6, 10

14, 19

21, 27

19, 22

21, 27

24, 2714, 19

14, 21

7, 14

7, 11

2, 7

0, 3

1, 7

Graphic SolutionApril 10, 2023

Page 126: Engineering Project Management Civil Engineering Department.

126

Activity ES EF LS LF TF FFA 0 5 2 7 2 0B 0 3 0 3 0 0C 0 6 1 7 1 0D 5 12 14 21 9 7E 7 14 7 14 0 0F 6 10 7 11 1 1G 14 19 14 19 0 0H 21 27 21 27 0 0I 19 22 24 27 5 5

Tabular SolutionApril 10, 2023

Page 127: Engineering Project Management Civil Engineering Department.

127

Constraints and the CPM

A Constraint is an externally imposed restriction affecting when an activity can start and/or finished

Constraints may conflict with logical relationships

Constraints are not alternatives for logic

April 10, 2023

Page 128: Engineering Project Management Civil Engineering Department.

128

On a continuous path:

Activities A, B, and C are critical; but D, E, and F notWhy?

A6

B5

C3

D9

E5

F2

Software QuizApril 10, 2023

Page 129: Engineering Project Management Civil Engineering Department.

129

Effect of Imposed Finish Date Imposed Finish Date is the project’s completion

date, as specified in the contract or stipulated by the owner

When compared to the calculated finish date:

Calculated finish date < imposed finish date

• You are in good shape

• What happens if you enter the imposed date?

Calculated finish date > imposed finish date

• Negative float appears when you enter the imposed date

• You need to accelerate / crash the schedule

April 10, 2023

Page 130: Engineering Project Management Civil Engineering Department.

130

Examples with Imposed Finish Dates

Repeat Example 3 with imposed finish date of 28 days

Repeat Example 3 with imposed finish date of 22 days

April 10, 2023

Page 131: Engineering Project Management Civil Engineering Department.

131

Imposed Finish Date > Calculated Finish Date

A5

D3

B6

C5

G4

E3

F4

H7

I8

J2

K3

L2

PF

0, 5

3, 8

5, 11

5, 10

5, 8

11, 15

11, 14

8, 12

15, 17

15, 23

12, 19

23, 25

19, 22

25

28

26, 28

25, 28

18, 26

23, 25

18, 25

15, 18

14, 18

14, 18

8, 14

9, 14

11, 14

3 4

6 6 6 6

8

43 3

3

3

April 10, 2023

Page 132: Engineering Project Management Civil Engineering Department.

132

A5

D3

B6

C5

G4

E3

F4

H7

I8

J2

K3

L2

PF

0, 5

-3, 2

5, 11

5, 10

5, 8

11, 15

11, 14

8, 12

15, 17

15, 23

12, 19

23, 25

19, 22

25

22

20, 22

19, 22

12, 20

17, 19

12, 19

9, 12

8, 12

8, 12

2, 8

3, 8

5, 8

-3

-3

-3

-2 -3

-3

-2 2

0 0 0 0

Imposed Finish Date < Calculated Finish Date

April 10, 2023

Page 133: Engineering Project Management Civil Engineering Department.

133

Negative float is a situation that occurs when performing an activity even on its early dates, fails to meet the project’s imposed finish date or other constraint

It may occur in one of two cases:

Before construction starts

During construction (after normal start)

Negative FloatApril 10, 2023

Page 134: Engineering Project Management Civil Engineering Department.

134

Calendars

Each activity has to be assigned a calendar

Different crews working for different activities work on different calendars.

The crew working for the same activity may work 5 days/week at normal times then switch to 6 or 7 days/week

User has to be aware of the impact of such matter on the duration of activities and consequently the project

April 10, 2023

Page 135: Engineering Project Management Civil Engineering Department.

135

Computer scheduling programs can handle calendars:Global, default, and other calendars

Recurring holidays

Work hours per day

Resource calendars

Scheduling in other countries

April 10, 2023

Page 136: Engineering Project Management Civil Engineering Department.

136

Schedulers must take in account non-work days. This includes:

Scheduled non-work days such as:.

• Holidays,

• Shut-downs.

Unscheduled non-work days such as:

• Rain days (or severe weather),

• Other unforeseen interruptions

Distribution of unscheduled non-work days

Non-Work Days April 10, 2023

Page 137: Engineering Project Management Civil Engineering Department.

137

Event Times in Arrow Networks

The early event time, TE, is the largest (latest) date obtained to reach an event (going from start to finish).

The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from finish to start).Example

Perform the CPM calculations, including the event times, for the arrow network shown below.

April 10, 2023

Page 138: Engineering Project Management Civil Engineering Department.

138

10 30

40

20 60

C

EB 50

D

F

70

A

GH

10

5

7

8

9

4

5

8

d1d2

Arrow network for example

April 10, 2023

Page 139: Engineering Project Management Civil Engineering Department.

139

The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick the largest number. When you are going backward, pick the smallest number.

i jAct. NameDur.

TEi

TLi

TEj

TLj

CPM

April 10, 2023

Page 140: Engineering Project Management Civil Engineering Department.

140

10 30

40

20 60

C

EB 50

D

F

70

A

GH

10

5

7

8

9

4

5

8

d1

d2

10

10

7

0

0

15

10

10

19

19

24

2727

27

(0,10)(0,10)

(5,10)(0,5)

(0,7)(8,15)

(10,18)(11,19)

(10,19)(10,19)

(7,11)(15,19)

(19,24)

(22,27)

(19,27)(19,27)

April 10, 2023

Page 141: Engineering Project Management Civil Engineering Department.

141

Float Calculations From Event Times

Total Float

TFij = TLj - TEi - Tij

Example ( In the previous network )

TF40-50 = TL50 – TE40 – T40-50

= 19 – 7 – 4 = 8

April 10, 2023

Page 142: Engineering Project Management Civil Engineering Department.

142

Free Float

FFij = TEj - TEi – Tij

ExampleFF40-50 = TE50 – TE40 – T40-50

= 19 – 7 – 4 = 8

April 10, 2023

Page 143: Engineering Project Management Civil Engineering Department.

143

Interfering Float

INTFij = TLj – TEj

ExampleINTF40-50 = TL50 – TE50

= 19 – 19 = 0

Independent Float

INDFij= TEj – TLi - Tij

ExampleINDF40-50 = TE50 – TL40 – T40-50

= 19 – 15 – 4 = 0

April 10, 2023

Page 144: Engineering Project Management Civil Engineering Department.

144

Example

Activity Duration IPAs

A 2 --B 2 A

C 4 A

D 1 C

E 4 B,C

F 2 B

G 1 D

H 4 F,E

I 2 F

J 4 G,H

K 4 I,H

L 1 K,J

Draw a network for the following activities

April 10, 2023

Page 145: Engineering Project Management Civil Engineering Department.

145

A

2

C 4

D1

E

4

B

2

F

2

G

1

H

4

I

2

J4

L

1

K4

1 2 3

4

5

6

9 10

7

8

11 12 13

The Arrow Network will be: April 10, 2023

Page 146: Engineering Project Management Civil Engineering Department.

146

A

2

C 4

D1

E

4

B

2

F

2

G

1

H

4

I

2

J4

L

1

K4

1 2 3

4

5

6

9 10

7

8

11 12 13

0 2 4 6 14

6 6 10 14 18 19

147

Forward Pass calculations (ES, EF)April 10, 2023

Page 147: Engineering Project Management Civil Engineering Department.

147

A

2

C 4

D1

E

4

B

2

F

2

G

1

H

4

I

2

J4

L

1

K4

1 2 3

4

5

6

9 10

7

8

11 12 13

0 2 6 10 14

6 6 10 14 18 19

1413

backward Pass calculations (LS, LF)April 10, 2023

Page 148: Engineering Project Management Civil Engineering Department.

148

A

2

C 4

D1

E

4

B

2

F

2

G

1

H

4

I

2

J4

L

1

K4

1 2 3

4

5

6

9 10

7

8

11 12 13

0 2 4 6 14

6 6 10 14 18 19

147

0 2 6 10 14

6 6 10 14 18 19

1413

Specify the Critical PathApril 10, 2023

Page 149: Engineering Project Management Civil Engineering Department.

149

A

2

C 4

D1

E

4

B

2

F

2

G

1

H

4

I

2

J4

L

1

K4

1 2 3

4

5

6

9 10

7

8

11 12 13

0 2 4 6 14

6 6 10 14 18 19

147

0 2 6 10 14

6 6 10 14 18 19

1413

April 10, 2023

Page 150: Engineering Project Management Civil Engineering Department.

150

Activity

Duration

IPAs ES EF LS LF TF

A 2 -- 0 2 0 2 0B 2 A 2 4 4 6 2C 4 A 2 6 2 6 0D 1 C 6 7 12 13 6E 4 B,C 6 10 6 10 0F 2 B 4 6 8 10 4G 1 D 7 8 13 14 6H 4 F,E 10 14 10 14 0I 2 F 6 8 12 14 6J 4 G,H 14 18 14 18 0K 4 I,H 14 18 14 18 0L 1 K,J 18 19 18 19 0

Table of activitiesApril 10, 2023

Page 151: Engineering Project Management Civil Engineering Department.

151

A

B

C

D

E

F

G

H

I

J

K

L

2 4 6 8 10 12 14 16 18 20

Bar / Gantt chart Early Start / FinishEF = ES + D

Activity

Time

April 10, 2023

Page 152: Engineering Project Management Civil Engineering Department.

152

A

B

C

D

E

F

G

H

I

J

K

L

2 4 6 8 10 12 14 16 18 20

Bar / Gantt Chart Late Start / FinishLS = LF - D

Activity

Time

April 10, 2023

Page 153: Engineering Project Management Civil Engineering Department.

153

A

B

C

D

E

F

G

H

I

J

K

L

2 4 6 8 10 12 14 16 18 20

Bar / Gantt of the previous networkApril 10, 2023

Page 154: Engineering Project Management Civil Engineering Department.

154

Summary

i jTTEi

TLi

TEj

TLj

Direction Float TF

FF

Int. F

Ind. F

April 10, 2023

Page 155: Engineering Project Management Civil Engineering Department.

155

True or False:• Determining activities durations is primarily the

scheduler’s job

• You can find out the project’s estimated completion date after

• performing the forward pass only

• You can find out the project’s critical path after performing the forward pass only

• “Event” is another name for an activity

• “Task” is another name for an activity

• There could be more than one critical path in a CPM network

• Total float must be equal to or greater than free float

Quiz 4April 10, 2023

Page 156: Engineering Project Management Civil Engineering Department.

156

Definitions Activity, or taskActivity, or task: A basic unit of work as part of the total project that is easily measured and controlled. It is time- and resource consuming.

Backward passBackward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has.

Critical activityCritical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will result in a delay in the entire project.

Critical pathCritical path: The longest path in a network, from start to finish, including lags and constraints.

.

April 10, 2023

Page 157: Engineering Project Management Civil Engineering Department.

157

Early datesEarly dates: The early start date and early finish date of an activity.

EarlyEarly finish (EF)finish (EF): : The earliest date on which an activity can finish within project constraints.

Early start (ES): Early start (ES): The earliest date on which an activity can start within project constraints.

Event: Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or resources.

Forward passForward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity.

Late dates: Late dates: The late start date and late finish date of an activity.

Late finish (LF): Late finish (LF): The latest date on which an activity can finish without extending the project duration.

Late start (LS): Late start (LS): The latest date on which an activity can start without extending the project duration.

April 10, 2023

Page 158: Engineering Project Management Civil Engineering Department.

158

Precedence DiagramPrecedence Diagram

April 10, 2023

Page 159: Engineering Project Management Civil Engineering Department.

159

The Four Types Relationships

Activities represented by nodes and links that allow the use of four relationships:

1) Finish to Start – FS

2) Start to Finish – SF

3) Finish to Finish – FF

4) Start to Start – SS

April 10, 2023

Page 160: Engineering Project Management Civil Engineering Department.

160

Finish to Start (FS) Relationship. The traditional relationship between

activities .

.Implies that the preceding activity must finish before the succeeding activities can start.

. .Example: the plaster must be finished before the tile can start .

Plaster Tile

April 10, 2023

Page 161: Engineering Project Management Civil Engineering Department.

161

Star to Finish (SF) Relationship

.Appear illogical or irrational.

.Typically used with delay time OR LAG.

.The following examples proofs that its logical .

steelreinforcement

Erect formwork

Order concrete

SF

Pour concrete

5

April 10, 2023

Page 162: Engineering Project Management Civil Engineering Department.

162

Finish to Finish (FF) Relationship

• Both activities must finish at the same time.

• Can be used where activities can overlap to a certain limit. Erect

scaffoldingRemove Old paint

sanding

painting inspectDismantle scaffolding

FF/1

FF/2

April 10, 2023

Page 163: Engineering Project Management Civil Engineering Department.

163

Start to Start (SS) Relationship

• This method is uncommon and non exists in project construction .

Spread groutClean surface

Set tile

SS

Clean floor area

April 10, 2023

Page 164: Engineering Project Management Civil Engineering Department.

164

Advantages of using Precedence Diagram

1. No dummy activities are required.

2. A single number can be assigned to identify each activity.

3. Analytical solution is simpler.

April 10, 2023

Page 165: Engineering Project Management Civil Engineering Department.

165

Calculation

1)1) forward calculationsforward calculations

EF = ES + DEF = ES + D

Calculate the Lag LAGAB = ESB – EFA

Calculate the Free Float

FF = Min. (LAG)

April 10, 2023

Page 166: Engineering Project Management Civil Engineering Department.

166

2) 2) Backward calculationsBackward calculations

For the last task LF=EF , if no information deny that.

LS=LF-D

Calculate Total Float

TF = LS – ES OR LF – EF

TFi = Min (lag ij + TFj )

Determine the Critical Path

April 10, 2023

Page 167: Engineering Project Management Civil Engineering Department.

167

Example

167Dur. E

S E

F FF TF LF

LS

A1 1

2002

1

B

9 2

110011

2

D

5 11

160016

11 4 16

200020

16 1 20

210021

20

F H

C

5 5

10307

2

E

4 10

143011

7 6 14

203317

11

G

54 3

1) Forward pass calculations 4) Backward pass calculations

2) Calculate the Lag ( LAGAB = ESB – EFA)

0

0 0 0 0

0 0

3) Calculate the Free Float (FF) FF = min.( LAG)

5) Calculate total Float (TF = LS – ES OR LF – EF)

April 10, 2023

Page 168: Engineering Project Management Civil Engineering Department.

168

168Dur. E

S E

F FF TF LF

LS

A

1 1

2002

1

B

9 2

110011

2

D

5 11

160016

11 4 16

200020

16 1 20

210021

20

F H

C

5 5

10307

2

E

4 10

143011

7 6 14

203317

11

G

54 3

6) Determine the Critical Path

0

0 0 0 0

0 0

The critical path passes through the critical activities where TF = 0

April 10, 2023

Page 169: Engineering Project Management Civil Engineering Department.

169

Resource Allocation and Resource Leveling

April 10, 2023

Page 170: Engineering Project Management Civil Engineering Department.

170

CATEGORIES OF RESOURCES

Labor

Materials

Equipment’s.

April 10, 2023

Page 171: Engineering Project Management Civil Engineering Department.

171

Labor

1. Salaried staff: like-project engineer, secretary.

2. Hourly workers: like-carpenters.

Equipment and Materials

1. Construction equipment and materials

2. Installed equipment and materials

April 10, 2023

Page 172: Engineering Project Management Civil Engineering Department.

172

What is resource allocation?

Resource allocation(resource loading) :

Is the assignment of the required resources to each activity, in the required amount and timing.What Is Resource Leveling?

Is minimizing the fluctuations in day-to-day resource use throughout the project.

It is usually done by shifting noncritical activities within their available float. It attempts to make the daily use of a certain resource as uniform as possible.

April 10, 2023

Page 173: Engineering Project Management Civil Engineering Department.

173

Why level Resources?

1. When the contractor adds the daily total demand for a specific resource for all activities he must provide the required amount, or work will be delayed.

2. Leveling may also be necessary for an expensive piece of equipment.

3. The main idea of resource leveling is to improve work efficiency and minimize cost during the life of the project.

Note: In general, materials do not need to be leveled

April 10, 2023

Page 174: Engineering Project Management Civil Engineering Department.

174

Leveling Resources in a Project

oResource leveling is a mathematically complex process.

oThe resource-leveling method is called the minimum moment algorithm.

odiscussed by Robert B. Harris (1978) in his classic textbook, Precedence and Arrow Networking Techniques for Construction

April 10, 2023

Page 175: Engineering Project Management Civil Engineering Department.

175

Resource Profiles

Time

Reso

ur

ce n

eed

Actual, not leveled

Ideal

Leveled, realistic

April 10, 2023

Page 176: Engineering Project Management Civil Engineering Department.

176

Sort

Sort : the process of arranging activities in a list to certain specific order.

April 10, 2023

Page 177: Engineering Project Management Civil Engineering Department.

177

Priorities & Sorts

The activities making up the network must be listed in order of their priority of resources allocation.

The network shows the logical sequence of activities. (predecessor and successor).

The listing of activities must therefore reflects the dependency of some activities .

April 10, 2023

Page 178: Engineering Project Management Civil Engineering Department.

178

Activities Sort

Activity Duration ES TF Resource unit

A 1 1 0 8H

B 9 2 0 9H

C 5 2 3 7H

D 5 11 0 5H

E 4 7 3 4H

F 4 16 0 8H

G 6 11 3 2H

H 1 20 0 4H

Activity sort reflects the logic sequence of the network.

April 10, 2023

Page 179: Engineering Project Management Civil Engineering Department.

179

Major Sort

Activity Duration ES TF Resource unit

A 1 1 0 8H

B 9 2 0 9H

C 5 2 3 7H

E 4 7 3 4H

G 6 11 3 2H

D 5 11 0 5H

F 4 16 0 8H

H 1 20 0 4H

Activity sort with ES time as Major sort

April 10, 2023

Page 180: Engineering Project Management Civil Engineering Department.

180

Major & Minor Sorts

Activity Duration ES TF Resource unit

A 1 1 0 8H

B 9 2 0 9H

C 5 2 3 7H

E 4 7 3 4H

D 5 11 0 5H

G 6 11 3 2H

F 4 16 0 8H

H 1 20 0 4H

Activity sort with ES time as Major sort & TF as Minor Sort

April 10, 2023

Page 181: Engineering Project Management Civil Engineering Department.

181

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20Time

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Act

ivit

y

Allocated resources April 10, 2023

Page 182: Engineering Project Management Civil Engineering Department.

182

2 4 6 8 10 12 14 16 18 20

Act

ivit

yTime

Total Labor 8 16 16 16 16 16 1313 13 13 7 7 7 7 7 10 8 8 8 4

Early start resources aggregation

A

B

C

D

E

F

G

H

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

April 10, 2023

Page 183: Engineering Project Management Civil Engineering Department.

183

Resource Aggregation

Resources aggregation: is a summation of the resources that are used to carry out the program on a time period basis. For example, day to day , or week to week.

April 10, 2023

Page 184: Engineering Project Management Civil Engineering Department.

184

184Time

Total Labor 8 16 16 16 16 16 1313 13 13 7 7 7 7 7 10 8 8 8

Lab

or

2

4

6

8

10

12

14

16

Early start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

4April 10, 2023

Page 185: Engineering Project Management Civil Engineering Department.

185

Late start

Another histogram can be obtained if Late start considered. Shows different resources demand.

And many histograms can be obtained considering a different time in the network.

Each histogram shows different resources demand.

April 10, 2023

Page 186: Engineering Project Management Civil Engineering Department.

186

late Start Sorts

Activity Duration LS TF Resource unit

A 1 1 0 8H

B 9 2 0 9H

C 5 5 3 7H

E 4 10 3 4H

D 5 11 0 5H

G 6 14 3 2H

F 4 16 0 8H

H 1 20 0 4H

Activity sort with LS time as Major sort & TF as Minor Sort

April 10, 2023

Page 187: Engineering Project Management Civil Engineering Department.

187

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20

Act

ivit

yTime

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Total Labor 8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4

Late start resources aggregation

April 10, 2023

Page 188: Engineering Project Management Civil Engineering Department.

188

Time

Total Labor

Lab

or

2

4

6

8

10

12

14

16

8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4

Late start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

April 10, 2023

Page 189: Engineering Project Management Civil Engineering Department.

189

189Time

Total Labor

Lab

or

2

4

6

8

10

12

14

16

8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4

Early start vs Late start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

April 10, 2023

Page 190: Engineering Project Management Civil Engineering Department.

190

190Time

Total Labor

Lab

or

2

4

6

8

10

12

14

16

8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4

Early start vs Late start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

April 10, 2023

Page 191: Engineering Project Management Civil Engineering Department.

191

Example

Dur. ES EF FF TF LF

LS

5 5

8

2

2

4

6

32

3

6

A

B

C

D

H

G

F

E

I

J

K1

6 0 0 6

1 6

11 0 0 11

6

6

8 0 6 14

12

8

14 8 8 22

16

11

14 0 0 14

11

11

13 0 6 19

17

10

16 6 6 22

16

6

10 0 6 16

12 13

16 6 6 22

19

14

22 0 0 22

14

22

24 0 0 24

22

April 10, 2023

Page 192: Engineering Project Management Civil Engineering Department.

192

Activity Duration ES TF Resource unit

A 5 1 0 8H

C 5 6 0 2H

D 2 6 6 4H

B 4 6 6 9H

H 6 8 8 5H

E 6 10 6 5H

G 3 11 0 2H

F 2 11 6 8H

I 3 13 6 5H

J 8 14 0 2H

K 2 22 0 6H

Activity sort with ES time as Major sort & TF and duration as Minor Sorts

Activities Sort April 10, 2023

Page 193: Engineering Project Management Civil Engineering Department.

193

2 4 6 8 10 12 14 16 18 20Time

Total Labor

8 8 8 8 8 15 1516 16 12 20 20 17 12 12 2 2 2 2 2

Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

2 6 6

B 9H 9H 9H 9H9H 9H 9H 9H

G 2H 2H 2H

April 10, 2023

Page 194: Engineering Project Management Civil Engineering Department.

194Total Labor

8 8 8 8 8 15 1516 16 12 20 20 17 12 12 2 2 2 2 2 2 6 6L

abo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

Early start resources aggregation diagram

April 10, 2023

Page 195: Engineering Project Management Civil Engineering Department.

195

Activity Duration LS TF Resource unit

A 5 1 0 8H

C 5 6 0 2H

D 2 12 6 4H

B 4 12 6 9H

E 6 16 6 5H

H 6 16 8 5H

G 3 11 0 2H

F 2 17 6 8H

I 3 19 6 5H

J 8 14 0 2H

K 2 22 0 6H

Activity sort with LS time as Major sort & TF and duration as Minor Sorts

Activities Sort April 10, 2023

Page 196: Engineering Project Management Civil Engineering Department.

196

2 4 6 8 10 12 14 16 18 20Time

Total Labor

8 8 8 8 8 2 2 2 2 2 2 15 15 11 11 12 20 2017 17

Late start resources aggregation

A

C

D

F

E

8H

2H 2H 2H 2H

5H 5H

4H 4H

8H

I

J

K

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

17 6 6

5H

B 9H 9H 9H 9H

G 2H 2H 2H

H 5H 5H 5H 5H 5H 5H

April 10, 2023

Page 197: Engineering Project Management Civil Engineering Department.

197Total Labor

Lab

or

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 2 2 2 2 2 2 15 15 11 11 12 20 20 17 17 17 6 6

Late start resources aggregation diagram

April 10, 2023

Page 198: Engineering Project Management Civil Engineering Department.

198

Lab

or

2468

101214161820

Lab

or

2468

101214161820

Late start

Early start

April 10, 2023

Page 199: Engineering Project Management Civil Engineering Department.

199

Smoothing/Leveling

Let us program activity F to start by its late start day which is day 17.

And activity I to start by day 14.

The resulting resources aggregation histogram will be as follows:

April 10, 2023

Page 200: Engineering Project Management Civil Engineering Department.

200

2 4 6 8 10 12 14 16 18 20Time

Total Labor

8 8 8 8 8 15 1516 16 12 12 12 12 12 12 7 10 10 2 2Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

2 6 6

B 9H 9H 9H 9H9H 9H 9H 9H

G 2H 2H 2H

April 10, 2023

Page 201: Engineering Project Management Civil Engineering Department.

201Total Labor

Lab

or

2

4

6

8

10

12

14

16

Time 2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 15 15 16 16 12 12 12 12 12 12 7 10 10 2 2 2 6 6April 10, 2023

Page 202: Engineering Project Management Civil Engineering Department.

202

Smoothing/Leveling

Let us program activity H to start by its late start time.

So its resources demand starts with its Late start date.

The resulting resource aggregation and histogram will be as follows:

April 10, 2023

Page 203: Engineering Project Management Civil Engineering Department.

203

2 4 6 8 10 12 14 16 18 20Time

Total Labor

8 8 8 8 8 15 1516 16 7 15 15 12 7 7 7 7 7 7 7

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

7 6 6

B 9H 9H 9H 9H9H 9H 9H 9H

G 2H 2H 2H

April 10, 2023

Page 204: Engineering Project Management Civil Engineering Department.

204Total Labor

8 8 8 8 8 15 15 16 16 7 15 15 12 7 7 7 7 7 7 7 7 6 6

Lab

or

2

4

6

8

10

12

14

16

Time 2 4 6 8 10 12 14 16 18 20 22 24

18

20

April 10, 2023

Page 205: Engineering Project Management Civil Engineering Department.

205

Smoothing/Leveling

In case activity D is split able activity. It could be interrupted to be carried out in tow parts.

Let us program activity B to start by 7th day .

And activity H to starts by its Late start date.

And activity E to start by day 14.

The resulting resource aggregation and histogram will be as follows:

April 10, 2023

Page 206: Engineering Project Management Civil Engineering Department.

206

2 4 6 8 10 12 14 16 18 20Time

Total Labor

8 8 8 8 8 6 1111 11 11 10 10 11 12 12 12 12 12 12 7

Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H5H

4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

7 6 6

B 9H 9H 9H 9H

G 2H 2H 2H

4H

April 10, 2023

Page 207: Engineering Project Management Civil Engineering Department.

207Total Labor

Lab

or

2

4

6

8

10

12

14

16

Time 2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 6 11 11 11 11 10 10 11 12 12 12 12 12 12 7 7 6April 10, 2023

Page 208: Engineering Project Management Civil Engineering Department.

208

Early Start OR Early Finish

There are many solutions between the limits of Early Start and Early Finish.

The optimal solution is zero fluctuation histogram. Which is hard to be achieved.

It is preferred to solve the problem

toward the Early start resources aggregation diagram.

WHY ?!

April 10, 2023

Page 209: Engineering Project Management Civil Engineering Department.

209

Because if there are labor availability problems to be overcome, they will occur in the early beginning of the project.

By other words, if the program based on the Late Start date, it means that all the activities are Critical, and any labor problem will affect the project completion.

April 10, 2023

Page 210: Engineering Project Management Civil Engineering Department.

210

Allocation within resources restraints

Another situation which you may face in practice is the restricted resources availability.

Where you have to carry out the job with the available resources only.

In this case the project duration may be prolonged to suit the availability of the restricted resources.

April 10, 2023

Page 211: Engineering Project Management Civil Engineering Department.

211

Rules for scheduling activities with limited resources

1) schedule activities to start as soon as their predecessors have been completed.

2) if more than one activity using a specific limited resources can be scheduled, priority is given to the activity with early Late Start. ( LS as Major Sort)

3) if tow or more activities have the same Late start, give priority to the activity with least Total Float. (TF as Minor Sort)

4) if the activities have the same Total Float in the minor sort, give the priority to the activity with the Largest Number of Resources.

5) If the activities are tied in the number of resources, give priority to the activity that has already started.

April 10, 2023

Page 212: Engineering Project Management Civil Engineering Department.

212

A

1 1

2002

1

B

9 2

110011

2

D

5 11

160016

11 4 16

200020

16 1 20

210021

20

F H

C

5 5

10307

2

E

4 10

143011

7 6 14

203317

11

G

Dur. ES EF FF TF LF

LS

Resources

Activity desc.

8H 9H 5H 8H 4H

2H4H7H

ExampleApril 10, 2023

Page 213: Engineering Project Management Civil Engineering Department.

213

Activity Duration ES TF Resource unit

A 1 1 0 8H

B 9 2 0 9H

C 5 2 3 7H

E 4 7 3 4H

D 5 11 0 5H

G 6 11 3 2H

F 4 16 0 8H

H 1 20 0 4H

Activity sort with ES time as Major sort & TF as Minor Sort

April 10, 2023

Page 214: Engineering Project Management Civil Engineering Department.

214

Assume that the available labors in the company restricted to 10 helpers, and the company decided to carry out the job without resorting to hire more labor.

The resulting program will exceed the Early finish date based on the network.

April 10, 2023

Page 215: Engineering Project Management Civil Engineering Department.

215

215Time

Total Labor 8 16 16 16 16 16 1313 13 13 7 7 7 7 7 10 8 8 8

Lab

or

2

4

6

8

10

12

14

16

Early start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

4April 10, 2023

Page 216: Engineering Project Management Civil Engineering Department.

216

Resources aggregation diagram

4 8 12 16 20 24A

ctiv

ity

Time

8 9

ABC

DE

FG

8H

9H

7H

5H

4H

8H

2H

4H

2 6 10 14 22 26Time

18

9 9 9 9 9 9 9 9 7 7 7 7 9 9 9 9 7 10 2 2 4

2

4

6

8

10

Lab

or

12LaborLimit

9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H

4H 4H 4H

5H

2H

5H

2H

5H

2H

5H

2H 2H

8H 8H

10 10Total Labor

H

April 10, 2023

Page 217: Engineering Project Management Civil Engineering Department.

217

Money and network schedules

Reminder, cost was one of the elements of project constraints triangle ( COST, TIME & QUALITY).

An effective management tries to minimize and integrate the above mentioned elements.

CPM provides a mean for relating time and money.

The application of resources to a project (materials, manpower and machinery) related to another resource which is MONEY.

The value of the resources for each activity represents a component of project cost.

April 10, 2023

Page 218: Engineering Project Management Civil Engineering Department.

218

Hint

Construction costs includes :

1 )Materials costs.2 )labor costs.

3 )plant and equipment costs4 )overhead costs and profit .

April 10, 2023

Page 219: Engineering Project Management Civil Engineering Department.

219

Example

Dur. ES EF FF TF LF

LS

5 5

8

2

2

4

6

32

3

6

A

B

C

D

H

G

F

E

I

J

K1

6 0 0 6

1 6

11 0 0 11

6

6

8 0 6 14

12

8

14 8 8 22

16

11

14 0 0 14

11

11

13 0 6 19

17

10

16 6 6 22

16

6

10 0 6 16

12 13

16 6 6 22

19

14

22 0 0 22

14

22

24 0 0 24

22

April 10, 2023

Page 220: Engineering Project Management Civil Engineering Department.

220

Activity Duration ES TF )Cost( $

A 5 1 0 650C 5 6 0 1300D 2 6 6 400B 4 6 6 1450H 6 8 8 500E 6 10 6 1100G 3 11 0 600F 2 11 6 350I 3 13 6 1000J 8 14 0 1300K 2 22 0 200

April 10, 2023

Page 221: Engineering Project Management Civil Engineering Department.

221

2 4 6 8 10 12 14 16 18 20Time

Total cost

200 100 200 100 50 550550 400 500 750 450 600 300 350 150 200 100100150

A

C

H

D

F

E

200

150 100 200 200

200 200 100

200 200

150

I

J

K

50 100 150

200

100

22 24

100 200 100 50

150

200 50 50

150 100 150

100

100100

100 150 200 100100 150 100

100 100

100 100 100

B 9H 9H 9H 9H100250 300 100

G 200 200 200

350

April 10, 2023

Page 222: Engineering Project Management Civil Engineering Department.

222

100

200

300

400

500

600

700

800

Time 2 4 6 8 10 12 14 16 18 20 22 24

Total cost 200 100 200 100 50 550550 400 500 750 450 600 300 350 150 200 100100150 100 100 100350

April 10, 2023

Page 223: Engineering Project Management Civil Engineering Department.

223

Cash Flow

It is quite significant to the contractor to know the amount of money that would be spent in each stage of the project.( Expenditures)

And compare it to the amount of money that would be received. (income)

Overtrading Overtrading: arises when the current

liabilities of a company exceed the current assets, even though the business is solvent.

April 10, 2023

Page 224: Engineering Project Management Civil Engineering Department.

224

224

400800

120016002000240028003200

Time 2 4 6 8 10 12 14 16 18 20 22 24

36004000

Cash Flow Diagram

Total cost

44004800

5200560060006400

200 100 200 100 50 550550 400 500 750 450 600 300 350 150 200 100100150 100 100 100350

200 300 500 600 650 1550 21002500 30003750 4200 4800 51005450 5600 58005900600061506250635064501000Com. cost

Com. cost = Cumulative Cost

$

April 10, 2023

Page 225: Engineering Project Management Civil Engineering Department.

225

Time (Months) Cash Flow Curve for revenue and expenditures

CumulativeExpenditures & Revenues

Revenues

ExpendituresRetainage Release

Amount of NegativeCash Flow

April 10, 2023

Page 226: Engineering Project Management Civil Engineering Department.

226

Cash Flow Example

$

Time

early

plannedlate$

$$$

$$

April 10, 2023

Page 227: Engineering Project Management Civil Engineering Department.

227

Spending

Cash Flow: In and Out

Time

$

Reimbursement

Profit

April 10, 2023

Page 228: Engineering Project Management Civil Engineering Department.

228

Cash Flow Analysis

Cash flow analysis consists of a detailed examination of funds disbursement (expenditures) and the receipt of revenue.

Cash flow shows if surplus fund available during project, or if negative cash position will occur during construction.

The cash position of contractor during project whether positive or negative is important.

April 10, 2023

Page 229: Engineering Project Management Civil Engineering Department.

229

Negative cash position

Negative cash position means that the revenues obtained from a project insufficient to meet the financial obligations (expenditures) of the project.

In this case other fund from the company or from outside sources must be used.

April 10, 2023

Page 230: Engineering Project Management Civil Engineering Department.

230

Positive cash position

Positive cash position means that the revenues obtained from a project exceed the financial obligations (expenditures) of the project.

In this case surplus (extra) fund available with the contractor.

And the contractor may invest this surplus funds for short duration.

April 10, 2023

Page 231: Engineering Project Management Civil Engineering Department.

231

Materials Management

Is defined as the planning and controlling of all necessary efforts to ensure that the correct quality and quantity of materials and equipment are appropriately specified in a timely manner, are obtained at a reasonable cost, and are available when needed.

April 10, 2023

Page 232: Engineering Project Management Civil Engineering Department.

232

Materials management functions

Identifying.

Acquiring.

Distributing.

Disposing.

April 10, 2023

Page 233: Engineering Project Management Civil Engineering Department.

233

Objectives of materials management

Ensure that materials meet the specifications and are on hand when and where required.

Obtain the best value for purchased materials.

Provide efficient, low-cost transport, security, and storage of materials at construction sites.

Reduce any surplus to the lowest level possible.

April 10, 2023

Page 234: Engineering Project Management Civil Engineering Department.

Schedule Updating Schedule Updating and Project Controland Project Control

234

April 10, 2023

Page 235: Engineering Project Management Civil Engineering Department.

235

Schedule updating

Schedule updating is just one part of the project control process.

Schedule updating must reflect

Actual work , and involves change orders (CO) .

April 10, 2023

Page 236: Engineering Project Management Civil Engineering Department.

236

What is an updated schedule?A revised schedule reflecting project information at a given data date regarding completed activities , in progress activities , and change in the logic , cost , and resources and allocated at any level .What is data date?

The data date is the date as of which all progress on a project is reported. It is also called as- of datas- of date and status date status date .

April 10, 2023

Page 237: Engineering Project Management Civil Engineering Department.

237

Why Update Schedules?

Schedules (like cost estimates) are always prepared before the project begins. However, updates must take place routinely for the following two reasons:

a. Unintentional events

b. Intentional changes

Schedules without updating, monitoring, controlling, and corrective action are useless

April 10, 2023

Page 238: Engineering Project Management Civil Engineering Department.

238

What kind of information is needed for updating schedules ?

1. Past information : what has happened since the last update ?. 2. Future information : the future category comprises any changes to schedule or schedule items.

Future changes are two types :

A. logic – driven changes

B. user’s changes

April 10, 2023

Page 239: Engineering Project Management Civil Engineering Department.

239

Frequency of updating

Construction schedules may be updated monthly , biweekly, weekly, or according to another time interval .

Project managers must achieve a delicate balance between updates is too long and one is too short

April 10, 2023

Page 240: Engineering Project Management Civil Engineering Department.

240

Updating schedules and pay requests

In many cases , project updating is tied to payment requests.

In general , a pay requests is a document submitted by the contractor to the owner , asking for payment for work actually performed (whether .finished or not)during the period since the last pay request.

April 10, 2023

Page 241: Engineering Project Management Civil Engineering Department.

241

Effect of adding or deleting activities on logic

An activity in a schedule is usually like a link in a chain ; removing a link may disturb the whole chain if it is not done properly.

For example :Deleting activity AS520 in the partial network shown in figure will remove any link between activities in each side.

AS210

AS250

AS260

TL160

AS245

April 10, 2023

Page 242: Engineering Project Management Civil Engineering Department.

242

It is strongly recommended that the scheduler review the logic before making any change by first printing a logic report showing all predecessors .and successors for the activity be deleted.

April 10, 2023

Page 243: Engineering Project Management Civil Engineering Department.

243

Steps for Updating a Schedule

1. The Schedule activity list

• Filter out completed activities

• Eliminating activities in the far future?

• Scheduler sends it to the project PM / superintendent

• Possibility that PM/superintendent wants to change past events

April 10, 2023

Page 244: Engineering Project Management Civil Engineering Department.

244

Example 1: No Cost April 10, 2023

Page 245: Engineering Project Management Civil Engineering Department.

245

Example 2: With Cost April 10, 2023

Page 246: Engineering Project Management Civil Engineering Department.

246

2. The PM (or superintendent) fills up the form, signs and dates it; and submits it back to the scheduler

It is a good idea for the PM to keep a copy for his/her records

It is a good idea to assign “ink colors” to different parties

3. The scheduler enters the info in the computer and updates the project, signs and dates the forms

April 10, 2023

Page 247: Engineering Project Management Civil Engineering Department.

247

4. The scheduler prints a preliminary report and discusses it with the PM

It is a good idea to produce a summary report (what happened between last update and this update)

Based on this discussion, the scheduler makes any necessary adjustments to the schedule or reports

Any changes to the schedule requested by the PM have to be documented by the scheduler

April 10, 2023

Page 248: Engineering Project Management Civil Engineering Department.

248

Myths/Misconceptions About Schedule Updating

We always produce a complete schedule before the commencement of construction. We just don’t update it, We trust our field staff and subcontractors to follow it.

We update projects only when there is a “need” for the update

Everything is going well. There is no need for an update

April 10, 2023

Page 249: Engineering Project Management Civil Engineering Department.

249

Quiz 6

True or False:

1. Updating is needed for projects that have duration of at least one year or a minimum budget of QAR 10 million

2. Data date is the date all information was entered in the computer

3. In updating schedules, we must enter not only actual work progress but also any future changes

4. Negative float is an indication that the schedule is not meeting its expected completion date or an interim imposed date

April 10, 2023

Page 250: Engineering Project Management Civil Engineering Department.

250

Project Control

April 10, 2023

Page 251: Engineering Project Management Civil Engineering Department.

251

Project control is the continuous practice of1. monitoring work progress,

2. comparing it to baseline budget and schedule,

3. detecting any deviations and their causes, and

4. taking a corrective action wherever and whenever necessary

The ability to determine a project status as it relates to the time and schedule selectedAlso called project tracking

Project monitoring?

Project Control April 10, 2023

Page 252: Engineering Project Management Civil Engineering Department.

252

Project control is needed because projects never run exactly as planned.

Project control is a cyclical iterative task: do small part of the work and compare to baseline, do corrective measure, adjust plan (if needed), do another part of the work, and so on..

Project control requires measuring work progress and calculating activities percent complete

Why Project Control?April 10, 2023

Page 253: Engineering Project Management Civil Engineering Department.

253

What is a baseline schedule?A baseline schedule is a schedule prepared by the contractor ,usually before the start of the project ,and used for performance comparison.

Baseline Budget: The project’s original approved budget including any approved changes

April 10, 2023

Page 254: Engineering Project Management Civil Engineering Department.

254

Percent Complete

Percent Complete (PC or PCT): is an estimate, expressed as a percent, of the amount of work that has been completed on an activity or a work breakdown structure component. (PMBOK 2008)

Percent complete may be used to estimate:

Activity

Groups of activities / assembly / work package

Project

April 10, 2023

Page 255: Engineering Project Management Civil Engineering Department.

255

Types of Percent Complete

Depending on the type and nature of the activity, percent complete may be calculated using one of several methods that may yield different results

Some methods are more subjective than others

None of these methods is wrong. None of them is uniquely considered the right method.

Most importantly: Know exactly what each percent complete means

Pick one or two parameters to use and then be consistent

April 10, 2023

Page 256: Engineering Project Management Civil Engineering Department.

256

Major objectives for a good control plan:

1. Should accurately represent the work.

2. Permit deviations to be detected, evaluated and forecasted.

3. Should make provision for periodic corrective actions.

April 10, 2023

Page 257: Engineering Project Management Civil Engineering Department.

257

Level of Control

Small projects - low cost - short duration

Detailed network

Reporting mechanism

Middle-sized projects (300 activities)

Detailed network

Summary network

Area and craft network

April 10, 2023

Page 258: Engineering Project Management Civil Engineering Department.

258

Monitoring the Project1.Feedback from direct contact

Efficient but requires close cooperation between the manager and field personnel.

2. Feedback from photography Record progress and provide permanent

documentation of the work. Tell nothing about the time taken to perform

the work.

3. Feedback from check-off list Planner prepares a check-off list that is

started, to be continued, or to be finished in the next time interval.

Effective if the reporting periods are short “Daily, Weekly” and small number of activities involved.

Disadvantage: false reporting

April 10, 2023

Page 259: Engineering Project Management Civil Engineering Department.

259

4.Feedback from bar chart.

5.Feedback from networks

Advantage:Superintendent has complete information

about the status of the project.Disadvantage:

Diagram may appear confusing to field personnel.

April 10, 2023

Page 260: Engineering Project Management Civil Engineering Department.

260

Setting the Target Schedule

Early Start Schedule: As Target for ControlProblem:

Required high effort to keep the plan working.

Late Start Schedule As Target for ControlProblem:

Because every activity is timed to start as its latest, project overruns are sure to follow.

Activities may be positioned early or late start or somewhat in between.

Non-critical activities allow intermediate start.

April 10, 2023

Page 261: Engineering Project Management Civil Engineering Department.

261

Anticipated target S-Curve April 10, 2023

Page 262: Engineering Project Management Civil Engineering Department.

262

The S-Curve fieldApril 10, 2023

Page 263: Engineering Project Management Civil Engineering Department.

263

Sample Project Cost Data

Activity

Duration (Days)

Cost Rate

($/Day)

Total Cost

($)

A 2 500 1,000 B 17 200 3,400 C 3 300 900 D 5 100 500 E 6 2,000 12,000 F 2 500 1,000 G 1 1,000 1,000

April 10, 2023

Page 264: Engineering Project Management Civil Engineering Department.

264

Early Start TreeApril 10, 2023

Page 265: Engineering Project Management Civil Engineering Department.

265

Late Start TreeApril 10, 2023

Page 266: Engineering Project Management Civil Engineering Department.

266

Target NetworkApril 10, 2023

Page 267: Engineering Project Management Civil Engineering Department.

267

Project S-Curve April 10, 2023

Page 268: Engineering Project Management Civil Engineering Department.

268

Actual Versus Target S-CurvesApril 10, 2023

Page 269: Engineering Project Management Civil Engineering Department.

269

Earned Value Analysis

April 10, 2023

Page 270: Engineering Project Management Civil Engineering Department.

270

Earned Value (EV) Analysis: Earned Value analysis is an integrated cost-schedule approach to monitor and analyze the progress in a project.

Earned Value Management (EVM), started in the 1960’s as a method for integrated project cost and schedule control, was designed by the U.S. Air Force and named the Cost/Schedule Planning and Control System.

In 1967, it became U.S. DOD policy and was renamed Cost/ Schedule Control Systems Criteria, or C/SCSC

Earned Value AnalysisApril 10, 2023

Page 271: Engineering Project Management Civil Engineering Department.

271

The Concept of EVM

The concept of Earned Value is simple; at any given point find out:

1. The cost of work you have actually done (ACWP),

2. The cost of work you planned to do by this date (BCWS),

3. The amount earned for work performed (BCWP),

4. Calculate schedule and budget variances (SV, CV)

5. Analyze causes for major variances and suggest remedies,

6. Extrapolate these variances to the end of the project (FSV, FCV).

April 10, 2023

Page 272: Engineering Project Management Civil Engineering Department.

272

Foundations of modern cost control

What’s more important?• Knowing where you are on schedule?

• Knowing where you are on budget?

• Knowing where you are on work accomplished?

Earned Value Analysis (EVA) addresses all three:

• It compares the PLANNED amount of work with what has actually been COMPLETED to determine if COST, SCHEDULE, and WORK ACCOMPLISHED

are progressing as planned.

April 10, 2023

Page 273: Engineering Project Management Civil Engineering Department.

273

EVA Terminology

BCWS – Budgeted Cost of Work ScheduledPlanned cost of the total amount of work scheduled to be performed by the milestone date. (a.k.a. your original plan)

BCWP – Budgeted Cost of Work PerformedThe planned (not actual) cost to complete the work that has been done.Also known as “Earned Value”

ACWP – Actual Cost of Work PerformedCost incurred to accomplish the work that has been done to date.

April 10, 2023

Page 274: Engineering Project Management Civil Engineering Department.

274

Input data for EVA

Activity schedule, usually in the form of a bar chart.

Budgeted cost for each activity.

Percent complete for each activity.

Cost to date for each activity.

April 10, 2023

Page 275: Engineering Project Management Civil Engineering Department.

275

Information Needed to Compute Budgeted Cost of Work Scheduled (BCWS)

Activity budget at completion (BAC)

Activity schedule

Data date

Budgeted Cost of Work Performed (BCWP)Activity budget at completion (BAC)

Physical activity progress as a percentage of its total work

Actual Cost of Work Performed (ACWP)

Each activity’s cost to date from the job costing system

April 10, 2023

Page 276: Engineering Project Management Civil Engineering Department.

276

Earned Value Reporting - Costs

ACWP

BCWPCPI

ACWPBCWPCV

CPI = 1, on budgetCPI < 1, over budgetCPI > 1, under budget

Budgeted Cost of Work Performed (BCWP) = earned value of project

Actual Cost of Work Performed (ACWP)

Cost Variance (CV)Difference between earned and actual costs for

the completed work

Cost Performance Index (CPI or CI)

April 10, 2023

Page 277: Engineering Project Management Civil Engineering Department.

277

Earned Value Reporting - Schedule Budgeted Cost of Work Performed (BCWP)

Budgeted Cost of Work Scheduled (BCWS)

Schedule Variance (SV)Difference between the value of work that was planned

for completion and the value of the work that was actually completed

Schedule Performance Index (SPI or SI)

BCWS

BCWPSPI

BCWSBCWPSV

SPI = 1, on scheduleSPI < 1, behind scheduleSPI > 1, ahead of schedule

April 10, 2023

Page 278: Engineering Project Management Civil Engineering Department.

278

Earned Value Reporting

Nabil Dmaidi

278

(earned)

(actual)

(budgeted)

April 10, 2023

Page 279: Engineering Project Management Civil Engineering Department.

279

Example

A simple problem will help to illustrate the application of the principles of earned value . A project has been defined that consist of 12 activities for which the estimated cost and duration have been defined see figure .After three and a half month , the activates 1,2,4,5,7 are completed and (6) is one half complete and(8) is three –fourth complete and (3) is half complete. The incurred cost to date are 152000$ . What is the status of this project in terms of the schedule and the budget?

Solution

April 10, 2023

Page 280: Engineering Project Management Civil Engineering Department.

280

Activity cost m1 m2 m3 m4 m5 m6

1 22000$

2 10000$

3 18000$

4 30000$

5 50000$

6 40000$

7 6000$

8 16000$

9 13000$

10 4000$

11 34000$

12 14000$

April 10, 2023

Page 281: Engineering Project Management Civil Engineering Department.

281

Solution

ACWP =152000$

BCWS=22000+30000+50000+10000+18000+0.5(40000+6000+16000)=161000$

BCWP=22000+30000+50000+10000+6000+0,5(40000)+0.75(16000)+0.5(18000)= 159000$

SV= BCWP-BCWS= -2000$ its behind schedule

CV=BCWP-ACWP= 7000$ below the budget

EAC=ACWP+(BAC-BCWP)=152000+(257000-159000) = 250000$

April 10, 2023

Page 282: Engineering Project Management Civil Engineering Department.

282

Earned Value: Cost and Time Status

$ +

Time

III

III IV

-

- +

April 10, 2023

Page 283: Engineering Project Management Civil Engineering Department.

283

EVA: The CurveApril 10, 2023

Page 284: Engineering Project Management Civil Engineering Department.

284

Quiz 7

True or false:1. Project control is to be practiced by both contractor and

owner

2. Project monitoring is part of project control

3. For assistance in calculating progress payments, percent

4. complete for the project is more important than percent complete of individual activities

5. It is possible that different parties compute the “project percent complete” and come up with different estimates, yet none of them is wrong!

6. It is possible to have the scheduler report saying the project is behind schedule while the earned value analysis is showing a positive schedule variance.

April 10, 2023

Page 285: Engineering Project Management Civil Engineering Department.

285

Time-Cost Trade-OffTime-Cost Trade-Off

Some amount of knowledge brings more……

April 10, 2023

Page 286: Engineering Project Management Civil Engineering Department.

286

Time /cost trade –off analysis

Time /cost trade –off analysis is the compression of the project schedule to achieve a more favorable outcome in term of project duration , cost , and projected revenues

Objective of time /cost trade-off

-compress project to an acceptable duration

-minimize total project costs

Done by selectively crashing specific activities to shorten project duration

April 10, 2023

Page 287: Engineering Project Management Civil Engineering Department.

287

Time /cost trade –off analysis

You might think that total project costs will increase when we begin to crash activities

But ,total project cost consist of both indirect (project –based ) costs (PBC) and activity – based cost (ABC )

-ABC goes up when we crash activities in an effort to finish the project early

-but ,PBC (the indirect cost ) goes down if we finish the project early

April 10, 2023

Page 288: Engineering Project Management Civil Engineering Department.

288

What Is ‘‘Accelerating’’ a Project?

Accelerating a project means shortening the normal duration of the project schedule .

(also called schedule compression).

schedule crashing

Schedule acceleration

April 10, 2023

Page 289: Engineering Project Management Civil Engineering Department.

289

Why Accelerate a Project?

1. The contractor’s ‘‘normal’’ finish date in the planned schedule does not meet the imposed finish date of the contract.

2. After starting construction and completing a certain percentage of the project, the contractor realizes that the project is behind schedule.

3 -when the contractor may have a contractual monetary incentive to finish ahead of schedule.

4- Sometimes, especially when the economy is doing well, finishing early

means—to the contractor—starting another job earlier

and, thus, making more profit.

April 10, 2023

Page 290: Engineering Project Management Civil Engineering Department.

290

Schedule Compression: Multiple Paths

Path 1

Path 2

Path 3

Path 4

Path 5

Path 6

Path 7

Path 8

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

April 10, 2023

Page 291: Engineering Project Management Civil Engineering Department.

291

Cost Changing with Schedule Acceleration

Direct Cost Indirect Cost

Total Cost

Cost $

April 10, 2023

Page 292: Engineering Project Management Civil Engineering Department.

292

Cost

For the following discussions it is important to remember:

Direct costs: Related to putting the facility components in place. They represent the resources used by an activity. (material, labor and equipment).

April 10, 2023

Page 293: Engineering Project Management Civil Engineering Department.

293

Indirect job costs (job overhead): costs that could not be attributed to a specific work item. (such as, site offices, superintendents, security fence & etc.)

These costs are generally incurred whether or not productive work achieved.

Longer project duration will result in higher indirect costs.

April 10, 2023

Page 294: Engineering Project Management Civil Engineering Department.

294

Operating Overhead costs (company overhead): If the cost cannot be attributed to any specific job, they are operating overhead costs, costs of running business. (head office costs, communications & etc).

These costs continue as long as the company exists even one project is running.

April 10, 2023

Page 295: Engineering Project Management Civil Engineering Department.

295

Logic of Time-Cost Trade-Off

Assumption: increasing or decreasing an activity’s duration will lead to increased direct costs for that activity.

April 10, 2023

Page 296: Engineering Project Management Civil Engineering Department.

296

Project duration

General relation of direct costs to project duration

Direct Costs

Direct costs

April 10, 2023

Page 297: Engineering Project Management Civil Engineering Department.

297

Assumption: decreasing a project’s duration will lead to lower indirect costs.

Project duration

General relation of indirect costs to project duration

Indirect Costs

indirect costs

April 10, 2023

Page 298: Engineering Project Management Civil Engineering Department.

298

Assumption: A project’s duration can be decreased by decreasing the duration of one or more critical activities on the critical path.

Assumption: Decreasing a project’s duration may increase or decrease the total cost of a project depending upon whether the additional direct costs required to decrease the activity duration are greater or less than indirect costs savings of decreasing the project’s duration.

April 10, 2023

Page 299: Engineering Project Management Civil Engineering Department.

299

Project duration General relation of project costs to project duration

Project Costs

Direct costs

indirect costs

Total project costs

April 10, 2023

Page 300: Engineering Project Management Civil Engineering Department.

300

Graph analysis

A project’s total costs combines direct costs and indirect costs. Therefore, the curve of total costs versus duration involves adding the cost amounts of direct and indirect costs curves.

Remember, the direct costs curve has a negative slope (direct costs increase as duration decrease) and indirect costs curve has a positive slope (indirect costs decrease as duration decreases).

So, the slope of the total costs curves at any point depends whether the slope of direct costs curve less than that of indirect cost curve.

April 10, 2023

Page 301: Engineering Project Management Civil Engineering Department.

301

How does accelerating a project work

The duration of the project is equal to the duration of the critical path .Thus to shorten the duration of the entire project ,shorten the duration of the critical path.

The cost will vary depending upon which activity duration decreased.

Usually, select the activity with least shortening costs. (lowest additional cost per day of shortening) to minimize the additional costs of shortening

April 10, 2023

Page 302: Engineering Project Management Civil Engineering Department.

302

Reducing Project Duration

-As the critical path of the network decreased, some non-critical activities

lose some amount of their total float .

A

B

C

D

F

April 10, 2023

Page 303: Engineering Project Management Civil Engineering Department.

303

-Thus, the extent to which an activity can be shortened and still has the effect of shortening the project is limited by the amount of total

float exists in the parallel activities .

A

B

C

D

F

April 10, 2023

Page 304: Engineering Project Management Civil Engineering Department.

304

-As the projects duration decreases, the number of critical paths through the network increases .

A

B

C

D

F

April 10, 2023

Page 305: Engineering Project Management Civil Engineering Department.

305

-If more than one critical path exist, it is necessary to reduce all critical paths in the network simultaneously, which becomes

expensive .

A

B

C

D

F

April 10, 2023

Page 306: Engineering Project Management Civil Engineering Department.

306

Four Different Solutions for Each Network

The schedule can be viewed in several different ways in order to satisfy the client. A client may with to perform the project in the lease cost, or in the least time. Or in any manner satisfies him.

1) All Normal: the original network and activity duration result in all normal solution, based on each activity being performed in its “NORMAL” least cost manner.

Remember, it is not necessarily the least cost or least time solution to schedule a project.

April 10, 2023

Page 307: Engineering Project Management Civil Engineering Department.

307

2) Least Cost: considering both direct and indirect costs, it may be possible to find a project duration that minimizes these total costs. By paying more to decrease one or more critical activity (direct cost) and save greater indirect costs. (Means that the result will be total cost saving.)

April 10, 2023

Page 308: Engineering Project Management Civil Engineering Department.

308

Project duration General relation of project costs to project duration

Project Costs

Direct costs

indirect costs

Total project costs

April 10, 2023

Page 309: Engineering Project Management Civil Engineering Department.

309

3) Least Time: A project can be shortened beyond its least cost duration. Until a point reached where no activities in the critical path can be physically shortened regardless of how many resources are applied. (results in higher costs)

4) All crash: in this solution, every activity has been shortened as much as physically possible. Its duration the same as the least time solution, but its costs greater. Because the direct cost increases without further reductions in the indirect costs.

A fully crashed schedule occurs when all activities shortened to their shortest possible duration

April 10, 2023

Page 310: Engineering Project Management Civil Engineering Department.

310

All crash It is not an efficient approach since

some non-critical activities will be shortened without having any shortening influence on the project duration.

April 10, 2023

Page 311: Engineering Project Management Civil Engineering Department.

311

Logically reducing Project Duration

The logical approach is to shorten those activities that contribute to reduce the project duration.

To begin the time-cost trade-off in a rational manner, basic calculations needed.

First compute the early start and early finish times for each activity

April 10, 2023

Page 312: Engineering Project Management Civil Engineering Department.

312

ExampleReducing Project Duration to shortest possible duration

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 73

7

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

9

16

9

12

2

9

16

23

16

19

23

28

5

J16

21

0

0

0

0

3

0

0

00

0 4

1

0

2

4

2

1

00

9

2

00

9

3

11

12

9

70

16

13

44

16

9

00

20

12

73

23

16

00

23

18

22

23

20

44

28

23

00

April 10, 2023

Page 313: Engineering Project Management Civil Engineering Department.

313

By computing the link lag values between activities.

(Lag = ESB – EFA). It is logical that there is at least one path between the first activity and last activity where lag values are 0.

These activities forming the critical path. (other solution can be derived by computing TF).

In the previous network. Activity A,B,F,H and L forming the critical path.

April 10, 2023

Page 314: Engineering Project Management Civil Engineering Department.

314

To shorten the project’s duration it is essential to shorten on of the critical activities. A or B or F or H or L.

Without shortening the project will end after 28 days with a cost of 5300 $.

This is the normal duration cost. And any decrease in duration will increase the direct cost.

The following table shows information about activities.

April 10, 2023

Page 315: Engineering Project Management Civil Engineering Department.

315

Activity Cost / day

Normal Duration

Crash Duration

Normal Cost

Crash Cost

Days to shorten

A - 1 1 800 800 0B 200 7 4 1000 1600 3C 100 6 4 300 500 2D 400 3 2 400 800 1E 50 3 1 100 200 2F 150 7 5 500 800 2G 300 8 4 200 1400 4H 250 7 6 350 600 1J 75 5 3 700 850 2K 500 3 2 500 1000 1L 350 5 4 450 800 1

April 10, 2023

Page 316: Engineering Project Management Civil Engineering Department.

316

Identifying activities for 1st compression cycle

Activity A B F H L

Cost/day

- 200$ 150$ 250$ 350$

F : Least cost activity to shorten

April 10, 2023

Page 317: Engineering Project Management Civil Engineering Department.

317

From the previous table, it can be noticed that activity F has the least incremental shortening cost. ( 150 $ per day).

E.g. Shortening F for 2 days costs 150 x 2 = 300 $.

Bear in mind, activities for shortening selected based on cost per day. Not on cycle cost basis.

April 10, 2023

Page 318: Engineering Project Management Civil Engineering Department.

318

How many days activity F could be shortened?

The answer in computing the Network Interaction Limit (NIL).

So, reducing activity F by 2 days will affect the link lag values of the succeeding activities and TF of parallel activities

April 10, 2023

Page 319: Engineering Project Management Civil Engineering Department.

319

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 73

7

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

9

16

9

12

2

9

16

23

16

19

23

28

5

J16

21

0

0

0

0

3

0

0

00

0 4

1

0

2

4

2

1

00

9

2

00

9

3

11

12

9

70

16

13

44

16

9

00

20

12

73

23

16

00

23

18

22

23

20

44

28

23

00

April 10, 2023

Page 320: Engineering Project Management Civil Engineering Department.

320

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 73

5

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

9

14

9

12

2

9

14

21

14

17

21

26

5

J14

19

0

0

0

0

1

0

0

00

0 2

1

0

2

4

2

1

00

9

2

00

9

3

11

10

7

50

16

13

42

16

9

00

18

10

51

21

14

00

21

16

22

21

18

44

26

21

00

April 10, 2023

Page 321: Engineering Project Management Civil Engineering Department.

321

Summary of the first compression cycle

Cycle

#

Activity to

shorten

Can be shortened

NIL Days shortened

Cost per day

Cost per

cycle

Total cost

Project duration

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

April 10, 2023

Page 322: Engineering Project Management Civil Engineering Department.

322

Identifying activities for 2nd compression cycle

Activity A B F H L

Cost/day

- 200$ - 250$ 350$

B : Least cost activity to shorten

April 10, 2023

Page 323: Engineering Project Management Civil Engineering Department.

323

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 73

5

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

9

14

9

12

2

9

14

21

14

17

21

26

5

J14

19

0

0

0

0

1

0

0

00

0 2

1

0

2

4

2

1

00

9

2

00

9

3

11

10

7

50

16

13

42

16

9

00

18

10

51

21

14

00

21

16

22

21

18

44

26

21

00

April 10, 2023

Page 324: Engineering Project Management Civil Engineering Department.

324

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 73

5

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

20

13

16

20

25

5

J13

18

0

0

0

0

0

0

0

00

0 2

0

0

2

4

2

1

00

9

2

00

8

2

00

9

6

40

16

13

42

13

8

00

17

9

40

20

13

00

20

15

22

20

17

44

25

20

00

April 10, 2023

Page 325: Engineering Project Management Civil Engineering Department.

325

Summary of the 2nd compression cycle

Cycle

#

Activity to

shorten

Can be shortene

d

NIL Days shortene

d

Cost per day

Cost per

cycle

Total cost

Project duratio

n

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

April 10, 2023

Page 326: Engineering Project Management Civil Engineering Department.

326

Identifying activities for 3rd compression cycle

Activity A B,C F H L

Cost/day

- 300$ - 250$ 350$

H : Least cost activity to shorten

April 10, 2023

Page 327: Engineering Project Management Civil Engineering Department.

327

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 73

5

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

20

13

16

20

25

5

J13

18

0

0

0

0

0

0

0

00

0 2

0

0

2

4

2

1

00

9

2

00

8

2

00

9

6

40

16

13

42

13

8

00

17

9

40

20

13

00

20

15

22

20

17

44

25

20

00

April 10, 2023

Page 328: Engineering Project Management Civil Engineering Department.

328

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 63

5

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

19

13

16

19

24

5

J13

18

0

0

0

0

0

0

0

00

0 2

0

0

1

3

2

1

00

8

2

00

8

2

00

8

5

30

13

10

22

13

8

00

16

8

30

19

13

00

19

14

11

19

16

33

24

19

00

April 10, 2023

Page 329: Engineering Project Management Civil Engineering Department.

329

Summary of the 3rd compression cycle

Cycle

#

Activity to

shorten

Can be shortene

d

NIL Days shortene

d

Cost per day

Cost per

cycle

Total cost

Project duratio

n

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

3 H 1 2 1 250 250 6050 24

April 10, 2023

Page 330: Engineering Project Management Civil Engineering Department.

330

Identifying activities for 4th compression cycle

Activity A B,C F H L

Cost/day

- 300$ - - 350$

B,C : Least cost activities to shorten

April 10, 2023

Page 331: Engineering Project Management Civil Engineering Department.

331

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 63

5

8

A

B

C

D G

F

E H

K

L1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

19

13

16

19

24

5

J13

18

0

0

0

0

0

0

0

00

0 2

0

0

1

3

2

1

00

8

2

00

8

2

00

8

5

30

13

10

22

13

8

00

16

8

30

19

13

00

19

14

11

19

16

33

24

19

00

April 10, 2023

Page 332: Engineering Project Management Civil Engineering Department.

332

Dur. ES EF FF TF LF

LS

1 4

3

5

3

4 63

5

8

A

B

C

D G

F

E H

K

L1

2

2

6

2

5

5

13

6

11

6

9

2

6

11

17

13

16

17

22

5

J11

16

0

0

0

0

0

2

0

00

0 2

0

0

1

1

2

1

00

6

2

00

6

2

00

6

3

10

11

8

22

11

6

00

14

6

10

17

11

00

17

12

11

17

14

11

22

17

00

April 10, 2023

Page 333: Engineering Project Management Civil Engineering Department.

333

Summary of the 4th compression cycle

Cycle

#

Activity to

shorten

Can be shortene

d

NIL Days shortene

d

Cost per day

Cost per

cycle

Total cost

Project duratio

n

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

3 H 1 2 1 250 250 6050 24

4 B,C 2 3 2 300 600 6650 22

April 10, 2023

Page 334: Engineering Project Management Civil Engineering Department.

334

Identifying activities for 5th compression cycle

Activity A B,C F H L

Cost/day

- - - - 350$

L : Least cost activity to shorten

April 10, 2023

Page 335: Engineering Project Management Civil Engineering Department.

335

Dur. ES EF FF TF LF

LS

1 4

3

5

3

4 63

5

8

A

B

C

D G

F

E H

K

L1

2

2

6

2

5

5

13

6

11

6

9

2

6

11

17

13

16

17

22

5

J11

16

0

0

0

0

0

2

0

00

0 2

0

0

1

1

2

1

00

6

2

00

6

2

00

6

3

10

11

8

22

11

6

00

14

6

10

17

11

00

17

12

11

17

14

11

22

17

00

April 10, 2023

Page 336: Engineering Project Management Civil Engineering Department.

336

Dur. ES EF FF TF LF

LS

1 4

3

4

3

4 63

5

8

A

B

C

D G

F

E H

K

L1

2

2

6

2

5

5

13

6

11

6

9

2

6

11

17

13

16

17

21

5

J11

16

0

0

0

0

0

2

0

00

0 2

0

0

1

1

2

1

00

6

2

00

6

2

00

6

3

10

11

8

22

11

6

00

14

6

10

17

11

00

17

12

11

17

14

11

21

17

00

April 10, 2023

Page 337: Engineering Project Management Civil Engineering Department.

337

Summary of the 5th compression cycle

Cycle

#

Activity to

shorten

Can be shortene

d

NIL Days shortene

d

Cost per day

Cost per

cycle

Total cost

Project duratio

n

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

3 H 1 2 1 250 250 6050 24

4 B,C 2 3 2 300 600 6650 22

5 L 1 ∞ 1 350 350 7000 21

April 10, 2023

Page 338: Engineering Project Management Civil Engineering Department.

338

Identifying activities for 6th compression cycle

Activity A B,C F H L

Cost/day - - - - -

NO Crashing

April 10, 2023

Page 339: Engineering Project Management Civil Engineering Department.

339

Reports and Reports and presentationspresentations

April 10, 2023

Page 340: Engineering Project Management Civil Engineering Department.

340

INTRODUCTION

Without a doubt, good communication is an essential component of the successful management effort. This means conveying the right information to the right party at the right time and in the right form.

April 10, 2023

Page 341: Engineering Project Management Civil Engineering Department.

341

Characteristics of good communication

1- clarity The information must be clear to the receiving party.

2- simplicity Helps improve understanding. Butting information in briefed sentence/s using a simple language .

April 10, 2023

Page 342: Engineering Project Management Civil Engineering Department.

342

3- AccuracyProfessional communications must be accurate, objective, and up to date.

4- preciseness and relevance to the subjectProviding too much or irrelevant information May be confusing and counterproductive. (example: LDS)

5- legibilityPeople whose handwriting illegible or difficult to read, should type their communications using the computer.

April 10, 2023

Page 343: Engineering Project Management Civil Engineering Department.

343

6- proper support tools Pictures, tables, charts, statistics, etc. They are more helpful and unilingual.

7- proper level of detail The communicator must balance the amount of information in an intelligent way.

8- good organization and formality sorting and organizing the info. to make it easy for the viewer to read, follow and retrieve.

FormalityFormality means following the company’s procedures, including the use of standard forms.

April 10, 2023

Page 344: Engineering Project Management Civil Engineering Department.

344

9- Retrievable and transformable Retrieving info. for live (current) projects may be performed easily by Using the computer commands. The ability to convert and open electronic files and to read the info is extremely important ,so using unknown software should be prohibited .

10- Conformance to industry standardsUsing common language when determining specifications and standards such as ISO,IAI.

April 10, 2023

Page 345: Engineering Project Management Civil Engineering Department.

345

Reports and Presentations

-Both are types of communications that aim at conveying information

-Report should be clear and complete because its printed materials are the only vehicle for conveying information between the person preparing the report and the person receiving it.

- Presentations focus on speakers’ persuasive skills, And the speaker focuses on certain points using oral, visual and written (or printed) tools. Audiences have the opportunity to ask for explanation any point unclear to them.

April 10, 2023

Page 346: Engineering Project Management Civil Engineering Department.

346

Types of presentations

1- contract candidate presentations The main focus of this presentation is to convince the owner (or the decision maker) that the presenter not only can do the job but also can do it better than other candidates, Answering the owner’s question “ why should I hire you?” 2- sales and demonstration presentations a presentation to demonstrate a product given by a representative of a manufacturing or vendor.

April 10, 2023

Page 347: Engineering Project Management Civil Engineering Department.

347

3- project status presentationsa presentation to upper management about a particular project and its status given by the PM or a team member.

4- management presentationsa presentation conducted by the management of a company to its staff to inform them about a new work plan, a new system, a new organization, or something else.

April 10, 2023

Page 348: Engineering Project Management Civil Engineering Department.

348

Presenter’s skills for good presentation

1- Focus on the client’s needsPresenting the product or service in the best way that serves the client /audience.

2- honestythe presenter should be honest and objective at all times, especially with regard to facts and numbers.

April 10, 2023

Page 349: Engineering Project Management Civil Engineering Department.

349

5- eye contact The presenter should speak to the audience not to himself or to his notes.

6- body language Body language and hand and arm gestures are important.

8- Manage time wisely Presentations almost always have time limits. Besides, human beings have limited attention span.

9- have a backup plan

April 10, 2023

Page 350: Engineering Project Management Civil Engineering Department.

350

The power of presentation

To create a good report we should ask ourselves the following questions:

1- does the report include all the information the report user needs?

2- does the report include any un needed information ?

3- is the information clear and well organized?

April 10, 2023

Page 351: Engineering Project Management Civil Engineering Department.

351

4- is the information presented in the required format?

5- can the look of the report be enhanced ?

Remember:1)Computer is still a tool . 2)There is no “one size fits all” .

April 10, 2023

Page 352: Engineering Project Management Civil Engineering Department.

352

Any report (text or graphic) should contain the following information:

1- the name, the address and the logo of the company and department or division.

2- the name of the person preparing the report and supervisor’s approval (if needed).

3- the name and the location of the project.

The power of presentation April 10, 2023

Page 353: Engineering Project Management Civil Engineering Department.

353

4- date

5- title of the report

6- attachments if any.

7- page numbering.

8- legends.

9- definitions of terms, acronyms and abbreviations that may not be known.

April 10, 2023

Page 354: Engineering Project Management Civil Engineering Department.

354

printing reports

After reviewing the final form of the report and before printing it consider the following :

make sure that only the needed activities and information are included .

margins may be slightly reduced to allow more information per page.

April 10, 2023

Page 355: Engineering Project Management Civil Engineering Department.

355

use the “fit to one page” function in the Print menu.

in limited cases you may print o both sides of the paper.

using a smaller or a different (narrower) font may help.

many reports may remain in electronic form and need not be printed.

The scheduler must relate the schedule information to the project manager not only as computer-generated colorful charts ,but in clear language as well.

April 10, 2023

Page 356: Engineering Project Management Civil Engineering Department.

356

SUMMARY REPORTS

Summary report should contain :

The overall situation of the project.

The preceding information as compared with that in the last update.

The new critical path, if it changed.

Cost information (if applicable).

April 10, 2023

Page 357: Engineering Project Management Civil Engineering Department.

357

Any other information that may help the project manager identify trouble spots or makeup for any lost time.

No unnecessary details.

The summary report should not exceed one page.

It should be written in the form of a memorandum.

April 10, 2023

Page 358: Engineering Project Management Civil Engineering Department.

358

Scheduling as Part of the Project Management Effort

April 10, 2023

Page 359: Engineering Project Management Civil Engineering Department.

359

Project manager team

The project manager team consist of: (for large project)

assistant PM

project superintendent

project engineer

scheduler

estimator

safety manager

procurement manager

accountant

April 10, 2023

Page 360: Engineering Project Management Civil Engineering Department.

360

Management team field personal

office personal

it may include teams member who are dedicated exclusively to particular project and others who are assigned to project part time or serve on the project for only temporary period .managing project requires several skills as:

technical skills

managerial skills

April 10, 2023

Page 361: Engineering Project Management Civil Engineering Department.

361

Scheduling and Estimating

Scheduling and estimating are related and their relationships is probably one of the most important relationships in project management These two areas intersected in many ways such as the following eight:

1)the estimator need to know how long the project will last in order to estimate certain cost , particularly overhead

2) Scheduling and Estimating department collaborate to provide information to the procurement department 3) The scheduler estimate the duration of activities with help from the estimating department 4)Many schedules are cost loaded . The cost must be imported from the cost estimate

April 10, 2023

Page 362: Engineering Project Management Civil Engineering Department.

362

5) Earned value management

6) progress payment depend on the schedule of value and the percent complete 7) resource allocation and resource leveling may be cost related ,although they are scheduling issues 8)schedule compression always involves a balance between cost and time

April 10, 2023

Page 363: Engineering Project Management Civil Engineering Department.

363

Construction project involved from many parties

1- General contractor.

2- owner.

3- architect (engineer).

4- subcontractors.

5- government.

6- vendors.

April 10, 2023

Page 364: Engineering Project Management Civil Engineering Department.

364

In order to schedule a project there are two approaches

1- build a master schedule that includes several sub schedule .

2- include all activities in one schedule and assign a responsibility code for each contracting party.

April 10, 2023

Page 365: Engineering Project Management Civil Engineering Department.

365

Time contingency and management options

The scheduler or project manager must include a time contingency representing the non work days.

This time contingency includes two types of non work days.

1- known dates such as a holidays and planned shut down days.

2-Unknown dates.

April 10, 2023

Page 366: Engineering Project Management Civil Engineering Department.

366

Scheduling and change orders

The contractor must then implement the CO in the estimating, scheduling, accounting, and other tracking systems.

April 10, 2023

Page 367: Engineering Project Management Civil Engineering Department.

367

Procurement Management

Procurement is the process of acquiring materials , equipment , and services from external sources for use in a project .

Procurement is a process that usually starts long before the start of the construction process and ends with project completion or project closeout .

April 10, 2023

Page 368: Engineering Project Management Civil Engineering Department.

368

The two objectives of procurement, from the general contractor’s viewpoint, are as follow:

1 -To hire the subcontractor who will actually erect and assemble the project.

2-To purchase the materials called for in the contract.

April 10, 2023

Page 369: Engineering Project Management Civil Engineering Department.

369

Linear Scheduling Linear Scheduling MethodMethod

April 10, 2023

Page 370: Engineering Project Management Civil Engineering Department.

370

Definition A simple diagram to show location and time at which a certain crew will be working on a given operation.

April 10, 2023

Page 371: Engineering Project Management Civil Engineering Department.

371

Characteristics

Shows repetitive nature of the construction.

Progression of work can be seen easily.

Sequence of different work activities can be easily understood .

Have fairly high level of detail.

Can be developed and prepared in a shorter time period than other formats.

April 10, 2023

Page 372: Engineering Project Management Civil Engineering Department.

372

Advantages of LSM

Provides more information concerning the planned method of const. than a bar chart.

In certain types of projects, LSM offers some advantages over the network approach.

April 10, 2023

Page 373: Engineering Project Management Civil Engineering Department.

373

Line of Balance Technique

LSM has relationships to the line of balance (LOB) technique, developed by US. Navy in the early 1950s.

First applied to industrial manufacturing and production control.

April 10, 2023

Page 374: Engineering Project Management Civil Engineering Department.

374

Three diagrams are used in LOB

1. Production DiagramShows the relationships of the assembly operations for a single unit. Similar to AOA, except that it shows only one unit of production.

2. Objective DiagramUsed to plot the planned or actual number of units produced vs. time. LSM diagram resembles this diagram.

3. Progress Diagram Shows the number of units for which each of the subassembly operations has been completed.

April 10, 2023

Page 375: Engineering Project Management Civil Engineering Department.

375

Difference between Objective Diagram and LSM

O.D. is used to schedule or record the cumulative events of unit completion.

LSM is used to plan or record progress on multiple activities that are moving continuously in sequence along the length of a single project.

April 10, 2023

Page 376: Engineering Project Management Civil Engineering Department.

376

Implementation of LSM

Can be used for continuous activities rather than discrete activities.

Transportation projects; highway const., highway resurfacing and maintenance, airport runway const. and resurfacing, tunnels, mass transit systems, pipelines, railroads.

High-rise building construction.

Repetitive building units.

April 10, 2023

Page 377: Engineering Project Management Civil Engineering Department.

377

Elements of the LSM

Axis Parameters

Location

Measure of progress.

In high-rises and housing const., measures may be stories, floors, subdivisions, apartments, housing units.

In Transportation projects, distance (ft. or mile can be used, but division by stations (100ft.) is common) is general.

April 10, 2023

Page 378: Engineering Project Management Civil Engineering Department.

378

Time

Hours, days, week, or month - depends on the total project time and level of detail desired in the schedule.

Preferable to prepare the schedule based on working days and convert to calendar days only at the end.

April 10, 2023

Page 379: Engineering Project Management Civil Engineering Department.

379

Activity Production Rates

Obtained by the usual estimating methods as a function of the activity, equip. characteristics, labor, and job conditions.

The initial rate should be associated with the min. direct cost of accomplishing the single activity.

April 10, 2023

Page 380: Engineering Project Management Civil Engineering Department.

380

Activity Interruption and Restraint

Prod. rate may vary with locations or time periods.

Progress may be interrupted intentionally and restraints may occur between activities due to limited equip. or crews.

April 10, 2023

Page 381: Engineering Project Management Civil Engineering Department.

381

Buffers

When const. activities progress continuously in a chain, some spacing between activities is required.

This spacing serves as a buffer and may require distance or time interval between activities.

April 10, 2023

Page 382: Engineering Project Management Civil Engineering Department.

382

Activity Intervals

Used to describe the period of time between the start and finish of an activity at a particular location.

Intervals can be indicated by a broad line, two narrow lines, etc.

Monitoring Progress.

Working calendar can be marked with a moving symbol or a line, tape, etc.

vertically across the diagram.

Progress on individual activities would be marked by location rather than time.

April 10, 2023

Page 383: Engineering Project Management Civil Engineering Department.

383

Project Time Optimization

The total project time may be such that indirect costs and liquidated damages assessed are more costly than the expense of accelerating certain activities.

Cost-duration analysis can be used to minimize the total cost, as follows :

Identify all activities that can be accelerated or

decelerated.

Among the above, consider only those that are

at a buffer limitation at both the start and the

finish of the activity.

April 10, 2023

Page 384: Engineering Project Management Civil Engineering Department.

384

Of these, select the one activity with the

lowest cost slope associated with

acceleration (or deceleration).

Accelerate (or deceleration) the activity

rate of production the maximum feasible

amount.

Repeat the above steps successively until

the optimum project cost and associated

duration are obtained.

April 10, 2023

Page 385: Engineering Project Management Civil Engineering Department.

385

Discrete Activities

Discrete are best scheduled by other methods. Once the duration is determined by network analysis, it can be scheduled on the LSM diagram and coordinated with the linear activities.

Seasonal Adjustments

When developing LSM, appropriate adjustments can be made for seasonal effect on construction

April 10, 2023

Page 386: Engineering Project Management Civil Engineering Department.

386

Project Progress and Resource Management

Project progress is often estimated by the S-curve with bar chart development.

In LSM, the determination of activity progress is facilitated and made more rigorous.

April 10, 2023

Page 387: Engineering Project Management Civil Engineering Department.

387

LSM Schedule

4

3

2

1

2 4 6 8 10 12 14 16 18 20 22 24

Excav

ate Fnd

s

F & P Fnds & Slab

Frame

April 10, 2023

Page 388: Engineering Project Management Civil Engineering Department.

388

LSM Schedule with Brickwork

4

3

2

1

2 4 6 8 10 12 14 16 1820 22 24

Excav

ate Fnd

s

F & P Fnds & Slab

Frame

Brickwork

Buffer

April 10, 2023

Page 389: Engineering Project Management Civil Engineering Department.

389

Four-unit Duplex I-J Fragnet

2EXC FNDSBLDG 1

7F&P FNDS& SLABBLDG 1

8FRAMEBLDG 1

2EXC FNDSBLDG 2

7F&P FNDS& SLABBLDG 2

8FRAMEBLDG 2

2EXC FNDSBLDG 3

7F&P FNDS& SLABBLDG 3

8FRAMEBLDG 3

2EXC FNDSBLDG 4

7F&P FNDS& SLABBLDG 4

April 10, 2023

Page 390: Engineering Project Management Civil Engineering Department.

390

4

3

2

1

2 4 6 8 10 12 14 16 18

Excav

ate Fou

ndati

ons

Days

Dup

lex

Num

ber

LSM ScheduleApril 10, 2023

Page 391: Engineering Project Management Civil Engineering Department.

391

Construction Delay Construction Delay ClaimsClaims

April 10, 2023

Page 392: Engineering Project Management Civil Engineering Department.

392

DEFINITIONS

Delay: An event or a condition that results in finishing the project later than stipulated in the contract .

Claim: a request from one contracting party to another party for additional compensation ,a time extension , or both .

Note: a claim is not always a negative action ,nor does it automatically indicate a confrontation .

April 10, 2023

Page 393: Engineering Project Management Civil Engineering Department.

393

Delay claims and change order

A CO may be initiated at the request of the Owner ,Contractor , Sub-Contractor.

They must submit a request for quotation (RFQ) to initiate their CO , And this request could be an owner decision or a “what if ” inquiry , the quotation may includes a cost estimate and the impact on the schedule .

April 10, 2023

Page 394: Engineering Project Management Civil Engineering Department.

394

To minimize the number of CO’s Owners should define the scope of the project and select a competent designer .

Many projects suffer from scope-creep syndrome , in which CO’s keep adding to the project budget and put it at levels far beyond what the owner originally planned.

April 10, 2023

Page 395: Engineering Project Management Civil Engineering Department.

395

Reasons for delay claims

1- Differing site conditions

2- design errors or omissions

3- changes in Owner’s Requirements

4- Unusually adverse weather

5- Miscellaneous factors

6- Force Majeure

April 10, 2023

Page 396: Engineering Project Management Civil Engineering Department.

396

Changes in owner’s requirements

May constitute a change in the contract and provide a foundation for Cos. Owners are always encouraged to know exactly what the want within their budgetary limits.

April 10, 2023

Page 397: Engineering Project Management Civil Engineering Department.

397

Force Majeure (superior force)

In the context of construction projects, this term usually involves three important elements :

1- Something that is superior, overwhelming, or overpowering (i.e, can not be prevented)

2- Something that is unexpected or cannot be reasonably anticipated or controlled.

3- Something that has a destructive or disruptive effect on the construction process.

April 10, 2023

Page 398: Engineering Project Management Civil Engineering Department.

398

Types of delays resulting in claims

1- Excusable delay.

2- Non excusable delay.

3- Concurrent delays.

April 10, 2023

Page 399: Engineering Project Management Civil Engineering Department.

399

Delay claims prevention

1- Baseline schedules that don’t show logic.

2- baseline schedule with dates rather than logic.

3- Overuse of constrains.

4- Erasing footprints.

5- unrealistic baseline schedule.

6- schedule with logic errors.

7- skipping periodic updates.

8- lack of proper documentation.

9- lack of a reasonable time contingency.

April 10, 2023

Page 400: Engineering Project Management Civil Engineering Department.

400

Communication means conveying information from one

party to other parties across the organization

Documentation means saving the information in an

organized manner for possible future retrieval.

Communication and documentation

April 10, 2023

Page 401: Engineering Project Management Civil Engineering Department.

401

Communications and documentation must both contain:

Clear information.

Provide the proper a mount oh details.

Be stored efficiently, so that the information can be retrieved easily .

April 10, 2023

Page 402: Engineering Project Management Civil Engineering Department.

402

1- The project baseline schedule that the owner accepted

2- Periodic schedule updates

3- Change orders

4- Job diary

5- Correspondence with the home office

6- Submittal records, such as shop drawings and material samples.

We must document these information

April 10, 2023

Page 403: Engineering Project Management Civil Engineering Department.

403

7- Records of any transmittals

8- Meeting minutes

9- Procurement records

10- Government records

11- Records of payment

12- Project manager’s daily log

April 10, 2023

Page 404: Engineering Project Management Civil Engineering Department.

404

Logbook should include daily information such as the following :

•Weather condition: temperature, wind.

•Work performance during that day.

•The number of workers on-site.

•Equipment on-site and its condition.

•Any accidents that occurred on-site

April 10, 2023

Page 405: Engineering Project Management Civil Engineering Department.

405

Methods of resolving claims

Negotiation

The most direct method for resolving any type of construction claim.

Requires certain skills that reduce the gap between the negotiation parties.

The objective: is to reach a solution that might be acceptable to both parties.

April 10, 2023

Page 406: Engineering Project Management Civil Engineering Department.

406

Mediation When negotiation does not work, either because

of lack of trust or a lack of skills, mediation may be an option.

The mediator may be an individual or a team. Dispute review boards

The owner and the contractor select an independent neutral panel with construction experience when the contract is signed .

Rather than waiting until the end of project to settle claims, (DRBs) resolve disputes as they arise.

April 10, 2023

Page 407: Engineering Project Management Civil Engineering Department.

407

Arbitration It is usually a formal process performed by an

independent professional arbitrator.

Arbitration is voluntary.

Arbitration does not require the use of lawyers

Litigation When none of the previous work and parties

can not reach a settlement, the complaining party uses the other party in a court of law.

Construction litigation is usually complicated lengthy, and expensive.

April 10, 2023

Page 408: Engineering Project Management Civil Engineering Department.

408

Method of Schedule Analysis

As- build schedule As – planned schedule Comparison schedule

Accelerated schedule

Recovery schedule

April 10, 2023

Page 409: Engineering Project Management Civil Engineering Department.

409

As-Built Schedule

The as-built schedule should reflect what actually happened in the filed.

Activities are plotted by their real start and real finish , disregarding any logic

Contain real budget and real resources

April 10, 2023

Page 410: Engineering Project Management Civil Engineering Department.

410

As – planned schedule

The as-planned schedule describes the manners in which the contractor in tended to built the project.

April 10, 2023

Page 411: Engineering Project Management Civil Engineering Department.

411

Comparison schedule

revised to incorporate any claimed delays .

for delay claim the contractor submits two schedules.

without the causative factors

with the causative factors

April 10, 2023

Page 412: Engineering Project Management Civil Engineering Department.

412

Accelerated schedule

Submitted by the contractor.

The project can finish by the contractor finish date.

April 10, 2023

Page 413: Engineering Project Management Civil Engineering Department.

Safety Safety & Health Management & Health Management

413

April 10, 2023

Page 414: Engineering Project Management Civil Engineering Department.

Introduction

One of the most important factors that should be taken in consideration in the site, (from engineering point view), is the safety and health management.

Safety and health management; is considered as a progress measure of the engineering and construction companies.

414

April 10, 2023

Page 415: Engineering Project Management Civil Engineering Department.

Safety: The condition or state of being safe;

freedom from danger or hazard; exemption from

hurt, injury, or loss.

415

April 10, 2023

Page 416: Engineering Project Management Civil Engineering Department.

Hazard: A condition with the potential of causing or contributing to an accident or

illness.

416

April 10, 2023

Page 417: Engineering Project Management Civil Engineering Department.

417

April 10, 2023

Page 418: Engineering Project Management Civil Engineering Department.

418

April 10, 2023

Page 419: Engineering Project Management Civil Engineering Department.

419

April 10, 2023

Page 420: Engineering Project Management Civil Engineering Department.

420

April 10, 2023

Page 421: Engineering Project Management Civil Engineering Department.

421

April 10, 2023

Page 422: Engineering Project Management Civil Engineering Department.

422

April 10, 2023

Page 423: Engineering Project Management Civil Engineering Department.

Rules in construction area under safety outline:

1 )knowing hazards and how to avoid them.

this mean know Construction Activity /

Corresponding Hazard Identification and activity

classification with respect to hazard as shown in

the following table.

423

April 10, 2023

Page 424: Engineering Project Management Civil Engineering Department.

424

• Heavy Equipment Operation -Class II• Material Handling -Class II • Temporary & Permanent Electricity -Class III • Cranes & Critical Lifts -Class III • Slings & Lifting Gear -Class III • Welding, Cutting & Brazing -Class III • Hand/Power Tools -Class II • Sanitation & Housekeeping -Class I • Scaffolding/Ladders -Class III • Manholes Excavations, Pits, Trenching & Shoring -Class III • Camp, Site Office & Lay down Yard -Class II • Over head Obstruction -Class III • Road Construction & Re-routing of Existing Roads -Class I • Concrete, Concrete Forms & Shoring -Class I • Sandblasting -Class II • Thrust Boring -Class I • Hot Taps -Class I • Personal Safety -Class I • Paints & Coatings -Class I • Piling Operations -Class II • Demolition -Class III • Mechanical Equipment -Class II • Chemical -Class III • Liquefied Petroleum Gas (LPG) -Class III • Fuel -Class III • Site Operations & Hydrocarbon -Class III

April 10, 2023

Page 425: Engineering Project Management Civil Engineering Department.

Rules in construction area under safety outline: (cont.)

•2 )use Personal Protective Equipments (PPE).

425

April 10, 2023

Page 426: Engineering Project Management Civil Engineering Department.

Rules in construction area under safety outline: (cont.)

3 )how to deal with emergency situations and what are the proper steps.

426

April 10, 2023

Page 427: Engineering Project Management Civil Engineering Department.

Rules in construction area under safety outline: (cont.)

•4 )follow the instructions carefully.

427

April 10, 2023

Page 428: Engineering Project Management Civil Engineering Department.

Occupational Safety & Health Administration

An organization that interests in achieving and applying safety factors in the construction field .

It deals with the identification and control of environmental and personal hazards in the work place.

428

April 10, 2023

Page 429: Engineering Project Management Civil Engineering Department.

OBJECTIVE OF S&HMANAGEMENT

Minimize losses –Avoid injuries

–Avoid OSHA fines –Avoid litigation

Development and implementation of S&H program is key to good management

429

April 10, 2023

Page 430: Engineering Project Management Civil Engineering Department.

ELEMENTS OF S&H PROGRAMS

430

Top management commitment Goal setting and planning Organization & administration Project safety rules Substance abuse program Emergency management Safety orientation & training Accident investigation &

recordkeeping Safety budget Safety in contracts Safety program evaluation TQM integration.

April 10, 2023

Page 431: Engineering Project Management Civil Engineering Department.

UNIQUE FACTORS INCONSTRUCTION AFFECTING S&H

431

Large but diverse and fragmented industry

every job is unique with numerous complex tasks

Labour intensive work involving large forces

Transient workforce which is difficult to train.

Complex contractual arrangements leading to multi-employer projects

April 10, 2023

Page 432: Engineering Project Management Civil Engineering Department.

HOW SAFETY SAVES MONEY

432

Economic impacts

Direct and indirect accident costs

Workers compensation and EMR

Accident cost accounting

April 10, 2023

Page 433: Engineering Project Management Civil Engineering Department.

ECONOMIC IMPACTS OF S&H

433

Myth: There is a trade-off between safety

and cost and productivity

Truth: Safety saves money

April 10, 2023

Page 434: Engineering Project Management Civil Engineering Department.

COSTS ASSOCIATED WITH S&H

434

A. Direct (insured) costs of accidents, injuries and illnesses

B. Indirect (hidden) costs – uninsured

C. Costs associated with company s&h programs

-Resource allocations for: Safety director/coordinator Equipment and supplies Time (meetings, inspections, etc.)

April 10, 2023

Page 435: Engineering Project Management Civil Engineering Department.

DIRECT COSTS

435

Workers compensation insurance premiums

paid by contractor (mainly for medical bills)

Liability insurance costs

Property related insurance costs.

April 10, 2023

Page 436: Engineering Project Management Civil Engineering Department.

INDIRECT (HIDDEN) COSTS436

Transportation for first aid/medical treatment Delays resulting from accident Wages paid to injured worker for time not worked Loss of crew efficiency Training new/substitute worker. Clean-up, equip. repair, stand-by Rescheduling work Post accident extra safety supervision OSHA and civil fines Legal fees Cost of administrative time for investigations and reports.

April 10, 2023

Page 437: Engineering Project Management Civil Engineering Department.

BASIC AIM OF THE OSHA

437

To ensure, so far as possible, every working person safe and healthful conditions in the workplace, which must be free from recognized

hazards likely to cause death or serious physical

harm.

Applicable to all employers – Records of illness/injury must be kept by employers with more than ten employees.

– Not applicable to self-employed and work places covered by other federal agencies

April 10, 2023

Page 438: Engineering Project Management Civil Engineering Department.

SUMMARY

438

Accidents can be tragic and costly.

Safety and health programs prevent injuries and fatalities, and save money

Effective program organization and implementation will help achieve OSHA compliance and lead to success at corporate and project levels.

April 10, 2023

Page 439: Engineering Project Management Civil Engineering Department.

remember

If it is unsafe, just don’t do it... If it is dangerous, always avoid it

for all we know

Safety is everyone‘s responsibility

439

April 10, 2023

Page 440: Engineering Project Management Civil Engineering Department.

Good LuckTHE END