Engineering for Legionella Control at Cooling Towers€¦ · Cooling Tower Makeup Water with 5.5 C...
Transcript of Engineering for Legionella Control at Cooling Towers€¦ · Cooling Tower Makeup Water with 5.5 C...
Engineering for
Legionella Control at
Cooling Towers
Clive Broadbent AM, FIE Aust.
www.broadbent.com.au
Legionella in the environment
Chain of Causation
Total Microbial Control
Temperature
Biofilm
Protozoa, bacteria
Nutrients
Heat Rejection by Evaporation
Towers on Roof
Towers Indoors
Industrial Applications - small
Larger
Very
Large
Inside
Warning
At Mines
Refining metals
Co-located
Single Flow – for cleaning
Single Flow
Power Stations
Variation of Legionella Counts with
Basin Water Temperature
kW v. Cooling Tower Water Temperature
Total Microbial Control
Temperature
Biofilm
Protozoa, bacteria
Nutrients
Poor Practices
Stagnant water - deadleg
Duty/Standby changeovers
Nutrients - algae on the top deck
Overflow – chemical loss
Uncontrolled Water Losses
Windage
Air intakes
Location
Location
Location
Outbreak Lessons
Outbreak
- chillers
Pumps
Tower 1
Tower 2
Biocide dosing
Two Independent Systems
C1
P1
CT1
C2
P2
CT2
Two Interconnected Systems – Scheme 1
Auto valves
interlocked with
pumps
Allows P1 to
serve C2 or P2 to
serve C1 in event
of failure
Design water flow
maintained
through each
cooling tower
C1
P1
C2
P2
CT1 CT2Auto
Valves
Auto
Valves
C1
P1
C2
P2
CT1 CT2Manual
Valves
Auto
Valves
Auto valves at
towers replaced
with manual
isolating valves
On auto operation,
uncontrolled water
losses occur when
one pump/chiller/
tower is sufficient
for load
Two Interconnected Systems – Scheme 2
Piping (no balance line)
Chemical dosing point (return lines)
Details
Site dust load high
Piping/pumping irregularities
No balance line between towers
Return piping at high level
No anti-syphon trap
Overflow on pump shutdown
Plant, incl. chillers, on manual control
Contd
Details
Chemical injected at return line
Componentry (dosing pump) unreliable
Only one biocide in use
non-oxidising
low concentration
Contractual difficulties
Major L.D. outbreak
Contd
Examples of
Developments
Safety
Example
Example
Snow making
Air Compressors
Towers in the Snow
Dry Basin
Water Saving
Understand and improve plant operation
(best practice)
Uncontrolled water losses (identify, remove)
Fix basin leaks
Increase cycles of concentration if relevant
Clean mud out of fill
Strategies
Splashguards
Eliminators
Sheets rolled back
Cooling Tower Makeup Water
with 5.5 C Range
Water Savings
For a cooling tower rejecting 2,000 kW, return water 35OC, supply water 29.5
OC, recirculation is
s/L87183.4x5.5
2000
Evaporation is s/L82.01000x430,2
996x2000 (where 996 is water density, 2430 is enthalpy of vaporisation).
Drift is 0.002% of flow = 0.002 L/s
Take TDS as 30 ppm (Melbourne)
For 2 cycles, bleed required = s/L82.0)3060(
30x82.0
s/L87
183.4x5.5
2000 s/L87
183.4x5.5
2000 and water
used is 0.82 + 0.82 + 0.002 = 1.64 L/s
For 6 cycles, bleed = s/L16.0)30180(
30x82.0
and water used is 0.16 + 0.82 + 0.002 = 0.98 L/s
Cycles 1.25 1.5 2 2.5 3 4 5 6 7 8 9 10 12 14 16 18 20
Water Use L/s 4.1 2.5 1.6 1.4 1.2 1.1 1 1 1 1 .9 .9 .9 .9 .9 .9 .9
Cooling Tower Makeup Water
with 5.5 C Range
Cooling Tower Makeup Water
with 5.5 C Range
0.00.10.20.30.40.50.60.70.80.91.01.11.21.31.41.51.61.71.81.92.02.12.22.32.42.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Cycles of Concentration
Makeu
p L
/s
Reclaim System at Office
Cost - $140,000
Payback – 2 years
Water saving – 1,135,520 litres reclaimed in 2
months
Reuses tower blowdown
Reclaim tank/flusher tank
Reclaim System at Office
Cooling water system primary disinfection by
bromine generated at site.
Reclaim system secondary disinfection by
electrochlorination – converts high chlorides
in blowdown water into chlorine
Riverside Centre
Reclaim Tank
Standards
AS/NZS 3666 - Microbial Control
Part 1 - Design, installation, commissioning
Part 2 - Operation, maintenance
Part 3 - Performance-based maintenance of
cooling water systems
Design features for towers (prescriptive – Part 1)
Convenient accessible openings
Components that can be removed
Sumps that can be readily drained
Materials compatible with use of disinfectant and hosing
with water jets
Use of components that minimise corrosion
Efficient drift eliminators (0.002% loss)
Minimal internal components such as structural brackets
which can collect sediment
Surfaces which can be readily cleaned
Protection of wetted surfaces from direct sunlight
Operation & maintenance features
(prescriptive – Part 2) Layout of system
Correct and safe operating procedures
Maintenance, cleaning and disinfection procedures and their frequency
Regular water treatment regimes
Bleed rate
Testing requirements pH
total dissolved solids or conductivity
bacterial counts
Disinfectant levels
Safety precautions
Person or contracting agency responsible for: overseeing and recording the work
ensuring that the plant operates normally
Performance-based maintenance (Part 3)
Assessment
the problem
Preventive measures
known controls
Operational procedures
continuing controls
Verification
monitoring the controls
Incident reporting
evidence
Companion Standard
AS 5059 – 2006
Power station cooling tower
water systems – management
of Legionnaires’ disease
health risk
Other Hazards
Artesian Bores
Mine
Are we there yet?
While there is an environmental pathogen and
there are people susceptible to infection, there
may always be cases of disease.
Legionella control is based on a partnership of
disciplines including engineering. Scientific
understanding and wisdom have already come
a long way. But we are still on a journey of
discovery. May all travel well.
Thank you
for
your attention