Engineering Considerations for Phosphorous Removal
-
Upload
alangbusiness -
Category
Documents
-
view
227 -
download
0
Transcript of Engineering Considerations for Phosphorous Removal
-
7/28/2019 Engineering Considerations for Phosphorous Removal
1/36
ENGINEERINGCONSIDERATIONS
FOR
PHOSPHOROUSREMOVAL
-
7/28/2019 Engineering Considerations for Phosphorous Removal
2/36
-
7/28/2019 Engineering Considerations for Phosphorous Removal
3/36
y ChemicalPhosphorusRemoval(ChemP)vs.Biological
PhosphorusRemoval(BioP)
y FactorsAffectingSelection
y
P
limits
in
NPDES
Permity DependentonPermitlimit/degreeofremovalneeded
y Typeofcurrenttreatmentprocesses
y
Extent
of
plant
modifications
needed
cost
and
operationy Capacityofsludgehandlingsystem
y Futurerequirements
y
Influent
wastewater
characteristics
Overview
-
7/28/2019 Engineering Considerations for Phosphorous Removal
4/36
ChemicalPhosphorusRemoval
y FormPrecipitatesUsingMetal
Salts
y CommonMetalSalts
y Alumy FerrousChloride(byproduct)
y FerricChloride
y Notsocommon
y Ferrous/FerricSulfate
y
Lime
-
7/28/2019 Engineering Considerations for Phosphorous Removal
5/36
y ApplicationPoints
y
Provide
multiple
locations
for
flexibilityy Preprecipitation
y Rawsewagepriortoprimarysedimentation
y Coprecipitation
y Primarysedimentationeffluent
y Mixedliquorintheactivatedsludgeprocess
y
Biological
process
unit
effluenty Postprecipitation
y Secondaryclarifiereffluent
y
Only
with
tertiary
treatment/filtration
ChemicalPhosphorus
Removal
-
7/28/2019 Engineering Considerations for Phosphorous Removal
6/36
ChemicalPhosphorus
Removal
y Whatisneededtomodifyanexistingfacility?
y Notalot?y Chemicalstoragetanky Feedpumps
y Pipingy Applicationpointsy Mixing??(dependsonlocation)
y
Evaluate
sludge
handling
capacityy Digestersy Dewateringy Storage
y Pumping
-
7/28/2019 Engineering Considerations for Phosphorous Removal
7/36
ChemicalPhosphorus
Removal
y Considerationsforchemicalstorageandfeedsystems
y Storagetank
y Multipletanks
y Volume
y Lengthofstoragetime
y Deliveryvolume
y Location(indoors/outdoors)
y Secondarycontainment
y Typeof
pumps/controls
y Flowpaced?
y Undergroundcasing
pipe/handholes
-
7/28/2019 Engineering Considerations for Phosphorous Removal
8/36
y UsingChemP:
y Constantlyadjustthechem feedpumpstomatchflow
y Canoverfeed
chemical
y Erroronthesideofcaution
y Allowfordiurnalflowvariations
y Flowpacing
(?)
consider
recycle
stream
slug
load
conc.
y SeasonalAdjustments
y Winter
y Addmorechemicaltomaintaincompliance
y HighereffluentPvalues
y Cantlandapply
ChemicalPhosphorus
Removal
-
7/28/2019 Engineering Considerations for Phosphorous Removal
9/36
ChemPRemoval
Side
Effects
y MetalsaltswithUVsystemsy Ferric/ferrous coatslamps,frequent
cleaningy Alum OK
y Impacts/effectsofreturnstreamsy HigherPininfluent
y Slugloads
y Impactonsludgeproductionandcharacteristicsy Significantincreasey Land
app
impacts/limits
y O&Mcostimpactsy Chemicalcostsy Sludgedisposalcosts
-
7/28/2019 Engineering Considerations for Phosphorous Removal
10/36
ChemPSummary
y Advantages
y Easytoimplement
y Simpleoperation
y Disadvantages
y
Increased
sludge
production
y AddedO&Mexpense
y Chemicalcosts
y Sludgehandlingcosts
y Ferric/ferroussaltscorrosion
-
7/28/2019 Engineering Considerations for Phosphorous Removal
11/36
y Fairlynewtechnology
y
Growmicroorganisms
that
take
up
extra
P(PAOs)
y Produceproperenvironment
y Requiressignificantmodificationstoexistingfacility
y Relativelyhigh
capital
costs
y LoweroperatingcostcomparedtoChemP
y Avoidorminimizechemicaladdition
y Producesminimal
additional
sludge
BiologicalPRemoval
-
7/28/2019 Engineering Considerations for Phosphorous Removal
12/36
y Whatsinvolved?
y Anaerobic/aerobiccyclingofmixedliquor
y Requiresvolatilefattyacids(VFA)
y Growselect
organisms
in
MLSS
to
take
up
and
storeP
y
Remove
organism
(&
P)
in
waste
sludgey Removalofsolidsfromeffluent
BiologicalPRemoval
-
7/28/2019 Engineering Considerations for Phosphorous Removal
13/36
-
7/28/2019 Engineering Considerations for Phosphorous Removal
14/36
-
7/28/2019 Engineering Considerations for Phosphorous Removal
15/36
BioPOxidation
Ditch
&
Anaerobic
Selector
Tank
-
7/28/2019 Engineering Considerations for Phosphorous Removal
16/36
y AerationInfluentcharacteristics/loadings
y MostBio
Pplants
designed
w/o
primary
clarifiers
y Challengesofprimaryeffluent
y Need>~20:1CBOD5:P,~40:1BOD5:COD
y i.e.,too
little
CBOD5 can
hinder
Bio
P
y PrefermentationforVFAs
y Affectssizeofanaerobiczone
y If
-
7/28/2019 Engineering Considerations for Phosphorous Removal
17/36
BiologicalPRemoval
y Whatisneededtomodifyexistingfacility?y
Activatedsludge
systems:
y Anaerobicselectortanky Ifnitrifying,consideranoxic
zonealso
y Removenitrates
(oxygen
source)y Automation/controly Evaluatesludgehandling
capacityy Digestersy Dewateringy Storage
y Tertiarytreatment???
-
7/28/2019 Engineering Considerations for Phosphorous Removal
18/36
y BioPOperationalControl
y KeepMLSS
at
consistent
concentration
(waste
regularly)
y Minimalsludgeblanketinfinalclarifiers(avoidPrelease)
y RASflowpaced
y SRT typically
5to
15
days
y CanloseBioPatlowtemps(
-
7/28/2019 Engineering Considerations for Phosphorous Removal
19/36
y Impacts/effectsofreturnstreamonotherprocesses
y Slugloads of
P
y Considersidestream treatmentorstorage
y Impactonsludgeproductionandcharacteristics
y BythenatureofBNR,phosphorousaccumulatesinthebiosolids
y HighPinWAStoanaerobicdigesters struvite
y Lessdry
tons
produced
than
with
Chem
P
y Landappimpacts/limits
y O&Mcostimpacts
BiologicalPRemoval
-
7/28/2019 Engineering Considerations for Phosphorous Removal
20/36
BioPSummary
y Advantages
y
Reduce/eliminate
chemical
addition
y Reduce/eliminatealkalinityadditionduetoChemP
y Selectsfor
flocculating
bacteriavs.Filamentousbacteria=bettersettling
y Reducesaeration
requirements
y Canimprovenitrification
rates
in
aerobic
zone
y Disadvantages
y
Higher
capital
costs
than
ChemP
y Requiresmorecarefuldesign
y Moresensitiveoperation
y LimitationonnitrateandD.O.recycletoanaerobiczone
y PreventPrelease
in
clarifiers
-
7/28/2019 Engineering Considerations for Phosphorous Removal
21/36
y Customaryprocessesforleveloftreatment(mg/LTP)
BioP ChemP
y Secondary 1.0 0.5
Effluent
y Filtered 0.3.05 0.10.2
Effluent
TreatmentProcess
for
PLimits
-
7/28/2019 Engineering Considerations for Phosphorous Removal
22/36
TertiaryTreatmentOptions
y Filtration
y Gravitysandfilters
y Pressurefilters
y Diskfilters
y PolishingPonds
y TertiaryClarifier
-
7/28/2019 Engineering Considerations for Phosphorous Removal
23/36
TertiaryTreatmentOptions
-
7/28/2019 Engineering Considerations for Phosphorous Removal
24/36
y Clarifiersizingforphosphorusremoval
y Per10StatesStandards
Additional
Topics
Treatment Process
Surface Overflow Rate
at Design Peak Hourly Flow*
Peak Solids Loading Rate***
gpd/ft2 lb/day/ft2
Conventional, Step Aeration,
Complete Mix, Contact Stabilization,
Carb. Stage of Separate Stage Nitr.
1,200** 50
Extended Aeration
Single Stage Nitrification1,000 35
2 Stage Nitrification 800 35
Activated Sludge with Chemical addition toMixed Liquor for Phosphorus Removal
900**** AsAbove
* Basedoninfluentflowonly
** Plantsneedingtomeet20mg/Lsuspendedsolidsshouldreducesurfaceoverflowrateto1,000gallonsperday persquarefoot
*** Clarifierpeaksolidsloadingrateshallbecomputedbasedonthedesignmaximumdayflowthedesignmaximumreturnsludge
rate
requirement
and
the
design
MLSS
under
aeration
**** Whenphosphorusremovaltoaconcentrationoflessthan 1.0mg/L isrequired
-
7/28/2019 Engineering Considerations for Phosphorous Removal
25/36
y Clarifiersizingforphosphorusremoval
y
Modifications/optimizingexisting
clarifiers
y PLimit
-
7/28/2019 Engineering Considerations for Phosphorous Removal
26/36
Stamfordbaffles
-
7/28/2019 Engineering Considerations for Phosphorous Removal
27/36
Aquatic&NaturalSystems
y ExistingPonds&Lagoons
y SupplementalProcesses
y Clarifierswithchem feed
y Sludgehandling
required
y Consideralongwith
ammoniaremoval
(futurelimits?)
-
7/28/2019 Engineering Considerations for Phosphorous Removal
28/36
NutrientFarmingProcessesforSidestreams
y Nutrientrecoveryprocesses
y Producesstruvite fertilizery ReducesrecyclingofP&Ny Reducesstruvite formation
y Ostara
y Multiform
Harvest
-
7/28/2019 Engineering Considerations for Phosphorous Removal
29/36
1. Whichof
the
following
chemicals
is
NOT used
for
chemicalprecipitationinwastewatertreatment:a) Alum
b) Ferric
Chloridec) FerrousChloride/hydrochloricacidmixture(pickleliquor)
d) FerricSulfate
e) Lime
f) None allcanbeused
Test
Time!!!!MultipleChoice
-
7/28/2019 Engineering Considerations for Phosphorous Removal
30/36
2. InaWWTPwithprimarytreatmentandsecondarytreatment,whichONEofthefollowinggenerallocationswouldaddingametalsalttoremove
phosphorus
NOT
be
beneficial:a) Preprecipitation addedtorawsewagepriortoprimary sedimentation
b) Coprecipitation addedtoprimarysedimentationeffluent
c) Coprecipitation addedtomixedliquorintheactivatedsludgeprocess
d) Coprecipitation
added
to
the
biological
process
unit
effluent
e) Postprecipitation addedtothesecondaryclarifiereffluent
f) None allabovelocationswouldbebeneficial
3. Alumis
an
abbreviated
term
for
what
chemical?
Fullname: Chemicalformula: _________
Aluminumsulfate Al2(SO4)3
TestTime
(cont.)
-
7/28/2019 Engineering Considerations for Phosphorous Removal
31/36
4. Howmanypoundsofachemical,appliedattherateof5mg/L,arerequired
to
dose
7 million
gallons?a. 35.0lb
b. 58.4lb
c. 291.9lb
d.
350.0lb
5. A15,000galtankisfullofaliquidchemicalwithaspecificgravityof1.25.Whatistheweightofthecontentsofthetank?
a. 7819lb
b. 18,750lb
c. 125,100lb
d. 156,375lb
TestTime
(cont.)
5mg/Lx7MGDx8.34=291.9
8.34lb/galx1.25S.G.x15,000gal=156,375lb
-
7/28/2019 Engineering Considerations for Phosphorous Removal
32/36
6. WhichofthefollowingisNOT atypicalconsideration
whenevaluating
which
chemical
to
utilize
for
phosphorusremoval?
a. Costofthechemical
b.Alkalinity
consumption
c. Quantitiesofsludgegeneratedbyitsaddition
d. Ultravioletlighttransmittance
e.
Safetyand
handling
requirements
f. Oxygentransferrate
TestTime
(cont.)
-
7/28/2019 Engineering Considerations for Phosphorous Removal
33/36
7. Circlethetwo (2)generaltypesofcolloidalsolidparticle
dispersionsin
liquids.
a. Heterotropic
b. Hydrophobic
c.
Hemophilic
d. Hydroliphic
e. Hydroponic
f.
Hydrophilic
g. Hydrostatic
h. Hydrofluxcapacitor
TestTime
(cont.)
-
7/28/2019 Engineering Considerations for Phosphorous Removal
34/36
8. Additionofalumwillincreasethealkalinityinthewaterbeingtreatedduringthecoagulationprocess.
9. Theformation
of
limestone
(calcium
carbonate)
is
notaseriousprobleminlimesystemsusedforphosphorusremoval.
10. Addingametalsalttoaprimarysedimentation
basinwill
not
affect
BOD
and
TSS
removal
efficiencies.
11. Addingferrousmetalsaltscanaffectthealkalinityofyourwastewaterstream.
12. Intheluxuryuptakephosphorusremovalprocess,bacteriareleasephosphorusinanaerobicreleasetank.
Test
Time
True/FalseFALSE
FALSE
FALSE
TRUE
FALSE
-
7/28/2019 Engineering Considerations for Phosphorous Removal
35/36
13. Inmostcases,ferroussulfatecannotbeusedaloneasaprecipitantbecauselimemustbeaddedatthesametimetoformaprecipitate.
14. If yourNPDESPermitdoesnotincludephosphorusortotalnitrogenlimits,youcannotusechemicalprecipitationtoimproveplantperformance.
15. Polymerscanbeusedinconjunctionwithmetalsaltstoaidinphosphorusremoval.
16. Priortoanactivatedsludgetypeoftreatmentprocess,
it
is
desirable
to
remove
as
much
phosphorusaspossibleintheprimaryclarifiers.
17. Everyoperatorhasaresponsibilitytoensurethatthe
treatments
plants
are
a
safe
place
to
work
and
visit.
Test
Time
(cont.)TRUE
FALSE
TRUE
FALSE
TRUE
-
7/28/2019 Engineering Considerations for Phosphorous Removal
36/36
Questions?