ENGINEERING BLDG. - Portland State University - 1.2 General Info. ... (Refer ZGF LSS 2.8 - 5 / 1/...

14
AV S <--> A1.1 Cover Sheet w/ notes, symbols, and index. no scale Contacts Site View Sheet Index Symbols EB PSU Capital Projects and Construction. University Svcs. Bldg. 617 SW Montgomery St. #302 Portland, OR 97201 (503) 725-3738 Ron Blaj - Director Steve Rounds - Asst. Director Gail Hamilton - Const Mgr. PSU Crews. Quinn Soifer - Project Manager James Schmidt - Architectural Intern Tom Arnich - Architect PSU Network -Teleco OIT Todd King - Tech. Services Bldg. 2121 SW 4th Ave. #400 Portland, OR 97201 Office: 503-725-4434 Cell: 360-903-8777 Doug McCartney - AV Services Office: 503-725-9110 ARCHITECTURAL (13 - sheets) Dated: 5 / 8 / 2015 A1.1 - 1.2 General Info. / Specifications A2.0 Existing Plan A2.1 Demo Plan A2.2 Floor Plan A2.3 Reflected Ceiling Plan A2.4 - 2.7 Furniture / Equipment Plans A3.1 - 3.2 Sections / Details A4.1 Schedules A5.1 Interior Elevations STRUCTURAL ENG. (1 sheet) Dated 5 / 8 /15 S1 General Notes / Details MECHANICAL / ELECTRICAL / PLUMBING (8 - sheets) Dated: 05 / 8 / 2015 * ± *HQHUDO 1RWHV DQG 6\PEROV 0 ± 0HFKDQLFDO 'HPROLWLRQ 0 ± 0HFKDQLFDO 1HZ :RUN ( ± (OHFWULFDO 'HPROLWLRQ ( ± (OHFWULFDO 1HZ :RUN ± 3RZHU ( ± (OHFWULFDO 1HZ :RUN ± /LJKWLQJ 3 ± 3OXPELQJ 1HZ :RUN 3 ± 3OXPELQJ 1HZ :RUN ± /DE *DVVHV North-East View CODE NOTES 1. Remodel PSU Labs @ Engineering Bldg. 2. 2014 OSSC. (Refer ZGF LSS 2.8 - 5 / 1/ 06) 3. TYPE 1 Construction 4. Group B Lab Occupancy 5. Existing Fire Sprinklers 6. Floor Remodel area = 1277+ 504 = 1800 sf +/- 7. Existing Bldg. = 5 Stories, Basmt, 2- Parking Levels 8. Total Bldg. Floor Area Gross = 26,000 sf +/- 9. Typ. Occupant Floor Area = 1800 sf / 50 sf per occupant = 36 occupants 10. 36 Occ. = < 50 req'd = 1 exit req'd : (2) exits if less than 500 11. 100' max. com. path egress (sect.1014.3) 12. 300' max. access travel (sect.1016.1) 13. Codes - All work to conform to latest applicable codes for City of Portland, including ADA stnds.,Ceiling stnds, Environmental and Waste management regulations. Cover Sheet FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL, TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION SEE ENGINEER'S DRAWINGS and SPECIFICATIONS. ENGINEERING BLDG. Vicinity Map No Scale SW 4TH AVE. SW HARRISON ST. Location / Egress Plan scale: 1 /32 " = 1'- 0" scale: 1 /16 " = 1'- 0" Code / General Notes 5/08/2015 RM. 550 & 560 - ENGINEERING BUILDING - LAB REMODEL / EQUIPMENT MOVE P O R T L A N D S T A T E U N I V E R S I T Y PSU Capital Projects & Construction EB ENGINEERING BLDG. RM. 550 & 560 INTERIOR LAB REMODEL (Block 091) 1930 SW 4TH Ave. Portland, Oregon 97201 Revisions : Drawn : Checked : Date : Main Egress Path to (3) Exit stairs. SW PEDESTRIAN TRAIL ELEV. Bldg. / Property Manager NAI - Norris, Beggs, & Simpson David Miller 617 SW Montgomery St. #202 Portland, OR 97201 Office: 503-725-9751 Mech / Electrical Engineer Insite Group Inc. Consulting Engineers Chris Wierman Office: (503) 222-2044 310 SW 4th Ave. Suite #1120 Portland , OR 97204 Structural Engineer ABHT Structural Engineers. Clinton Ambrose Office: 971-222-4378 224 NW 13th Ave #325 Portland, OR 97209 City of Portland-BDS Facility Permit Program 1900 SW 4th Ave. #5000 Portland, OR 97201 Scott Burris - Inspector Office: 503-823-0668 Jeff Galvin - Fire Marshal Office: 503-823-4032 PSU Planning & Design Ernest Tipton AIA Assist. Director PSU Facilities Planning and Campus Design Office: 503-725-4318 PSU Campus Public Safety 503-725-4407- Non-Emergency 503-725-4404 - Emergency Client Engineering Bldg. Don Mueller Jun Jiao Lester Lampert ( Total = 22 sheets at 34" x 22" size ) EXIT STAIR EXIT STAIR EXIT STAIR SW FOURTH AVENUE LOVEJOY PARK / FOUNTAIN CITY TOWER (2) exist. "B" occupancy Labs to remain. Rm 550 = 1227 sf@50sf/occ. = 25 Rm 560 = 504 sf @50sf / occ.= 11 Total 36 occupants. 135' 80' (1) hr. fire rated corridor with 20 min fire rated door assemblies. I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A1 - EB550-60 - General.dwg, 5/8/2015 7:19:21 AM, DWG To PDF.pc3

Transcript of ENGINEERING BLDG. - Portland State University - 1.2 General Info. ... (Refer ZGF LSS 2.8 - 5 / 1/...

AV

S

<-->

A1.1

Cover Sheet w/ notes, symbols, and index.

no scale

Contacts

Site View

Sheet Index

Symbols

EB

PSU Capital Projects and Construction.

University Svcs. Bldg.

617 SW Montgomery St. #302

Portland, OR 97201

(503) 725-3738

Ron Blaj - Director

Steve Rounds - Asst. Director

Gail Hamilton - Const Mgr. PSU Crews.

Quinn Soifer - Project Manager

James Schmidt - Architectural Intern

Tom Arnich - Architect

PSU Network -Teleco OIT

Todd King - Tech. Services Bldg.

2121 SW 4th Ave. #400

Portland, OR 97201

Office: 503-725-4434

Cell: 360-903-8777

Doug McCartney - AV Services

Office: 503-725-9110

ARCHITECTURAL

(13 - sheets)

Dated: 5 / 8 / 2015

A1.1 - 1.2 General Info. / Specifications

A2.0 Existing Plan

A2.1 Demo Plan

A2.2 Floor Plan

A2.3 Reflected Ceiling Plan

A2.4 - 2.7 Furniture / Equipment Plans

A3.1 - 3.2 Sections / Details

A4.1 Schedules

A5.1 Interior Elevations

STRUCTURAL ENG.

(1 sheet)

Dated 5 / 8 /15

S1 General Notes / Details

MECHANICAL / ELECTRICAL / PLUMBING

(8 - sheets)

Dated: 05 / 8 / 2015

G1 – General Notes and Symbols

M2.0 – Mechanical Demolition

M2.1 – Mechanical New Work

E2.0 – Electrical Demolition

E2.1 – Electrical New Work – Power

E2.2 – Electrical New Work – Lighting

P2.1 – Plumbing New Work

P2.2 – Plumbing New Work – Lab Gasses

North-East View

CODE NOTES

1. Remodel PSU Labs @ Engineering Bldg.

2. 2014 OSSC. (Refer ZGF LSS 2.8 - 5 / 1/ 06)

3. TYPE 1 Construction

4. Group B Lab Occupancy

5. Existing Fire Sprinklers

6. Floor Remodel area = 1277+ 504 = 1800 sf +/-

7. Existing Bldg. = 5 Stories, Basmt, 2- Parking Levels

8. Total Bldg. Floor Area Gross = 26,000 sf +/-

9. Typ. Occupant Floor Area = 1800 sf / 50 sf per

occupant = 36 occupants

10. 36 Occ. = < 50 req'd = 1 exit req'd : (2) exits if less

than 500

11. 100' max. com. path egress (sect.1014.3)

12. 300' max. access travel (sect.1016.1)

13. Codes - All work to conform to latest applicable codes

for City of Portland, including ADA stnds.,Ceiling

stnds, Environmental and Waste management

regulations.

Cover Sheet

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

ENGINEERING BLDG.

Vicinity MapNo Scale

SW

4

TH

A

VE

.

SW HARRISON ST.

Location / Egress Planscale: 1 /32 " = 1'- 0"scale: 1 /16 " = 1'- 0"

Code / General Notes

5/08/2015

RM. 550 & 560 - ENGINEERING BUILDING - LAB REMODEL / EQUIPMENT MOVE

P O R T L A N D S T A T E U N I V E R S I T Y

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Main Egress Path

to (3) Exit stairs.

SW PEDESTRIAN TRAIL

ELEV.

Bldg. / Property Manager

NAI - Norris, Beggs, & Simpson

David Miller

617 SW Montgomery St. #202

Portland, OR 97201

Office: 503-725-9751

Mech / Electrical Engineer

Insite Group Inc.

Consulting Engineers

Chris Wierman

Office: (503) 222-2044

310 SW 4th Ave. Suite #1120

Portland , OR 97204

Structural Engineer

ABHT Structural Engineers.

Clinton Ambrose

Office: 971-222-4378

224 NW 13th Ave #325

Portland, OR 97209

City of Portland-BDS

Facility Permit Program

1900 SW 4th Ave. #5000

Portland, OR 97201

Scott Burris - Inspector

Office: 503-823-0668

Jeff Galvin - Fire Marshal

Office: 503-823-4032

PSU Planning & Design

Ernest Tipton AIA

Assist. Director

PSU Facilities Planning and

Campus Design

Office: 503-725-4318

PSU Campus Public Safety

503-725-4407- Non-Emergency

503-725-4404 - Emergency

Client

Engineering Bldg.

Don Mueller

Jun Jiao

Lester Lampert

( Total = 22 sheets at 34" x 22" size )

EXITSTAIR

EXITSTAIR

EXITSTAIR

SW FOURTH AVENUE

LOVEJOY PARK / FOUNTAIN

CITY TOWER

(2) exist. "B" occupancy Labs to remain.

Rm 550 = 1227 sf@50sf/occ. = 25

Rm 560 = 504 sf @50sf / occ.= 11

Total 36 occupants.

135'80'

(1) hr. fire rated corridor

with 20 min fire rated

door assemblies.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A1 - EB550-60 - General.dwg, 5/8/2015 7:19:21 AM, DWG To PDF.pc3

arnicht
Stamp
arnicht
Text Box
SEPERATE COVER - MEP SPEC. BOOK = (216) 8- 1/2 X 11 PAGES. Dated : 5-8-15

A1.2

Specification

Spec. Notes

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

A.General Items

A.1. General and Code Notes -- See Cover Sheet.

A.2. Contract Documents and Work - Conform to PSU

General Conditions of Contract and Bid Documents.

A.3. Area / Location of Work -- See drawings.

A.4. All Products shall be installed per manufacturer's

specifications and recommendations. Products listed

shall be as noted. Approved equals shall be allowed

by contractor submitted substitution request form

prior to Bid Invitation deadline. Provide product

submittals samples for PSU to review prior to

ordering product. Product Review approval does not

imply or change the contract documents without an

approved change request and change order.

A.5. See Schedules --- for color / finish / material / room

/roof / door schedules for more specification

information.

A.6. Dimensions & Existing Conditions -- All drawing

dimensions shall have preference over scale. Verify

all dimensions and Existing Conditions prior to

commencement of work. Notify PSU of any

discrepancy.

A.7. Structural Engineer Approvals - Penetrations of

Structure by Contractor, including anchoring, coring,

scraping, cutting or removal is not permitted unless

approved by PSU Structural Engineer.

B.Demolition

B.1. General Demo --- Remove existing walls, doors,

frames, finishes, electrical, mechanical, and other

building items as required to accommodate new

construction. Remove all abandoned mech., elect.,

and plumbing lines in area of work. Verify all existing

structure and protect. Protect all egress paths and

exits.

C.Walls

C.1. Wall Finish -- Smooth texture or to match existing

surrounding surfaces.

C.2. Existing + New Wall Blocking, Patching / Painting --

Block, Patch and Prep and Paint as required to

include at new and existing gypsum brd / plaster and

framing, demo work, cabinetry, woodwork, all new

mechanical and electrical work. Contractor to install

hidden fire retardant or metal framing blocking at all

wall mount accessories.

D.Doors / Windows

D.1. None Required.

E. Door Hardware

E.1. None Required.

F. Signage

F.1. Signage -- BY PSU -- New floor and building interior

signage per code, ADA, and PSU standard

requirements .

G.Access Control

G.1. None Required

H.Metal Cabinetry / Woodwork

H.1. New Metal Cabinetry Island --- Provided by PSU,

assembled and installed by contractor to be

coordinated and adjacent to new hoods.

Manufacturer VWR or approved equal, 8' length

metal cabinetry island and shelves above back to

back units with 5'+/- wide p. resin counter top with

under-counter sitting space each side. See interior

elevations.

H.2. Rework Existing Metal Cabinetry - To accommodate

new undercounter refrigerator and new sinks. All new

finishes to match existing. See details.

H.3. WB -- Wood Base --- None Required.

I. Flooring / Base / Surfaces

I.1. See Schedules.

I.2. Floor Hole Patching --- Verify with Structural

Engineer. For max. 4" dia holes use 6" dia. x 16 ga.

galv metal plate and epoxy. Fill with 1 hr. rated fire

safing and caulk.

I.3. Floor / Wall Preparation -- Prepare, fill and level all

surfaces as required for new finishes for equal

smooth level transitions with existing surfaces. Use

finish manufacturer's approved products and

specifications.

I.4. Tile Floors ,Walls, and Grout -None Required

I.5. Wall Base - Rubber base by Roppe or approved

equal, 4" ht., match existing base color.

I.6. Floor Transitions - Vinyl between different floor

surfaces , Johnsonite or approved equal, conform to

ADA requirements.

I.7. Resin Floor Coating System - Silikal Flake, 62-SLF-M

or approved equal. 1 /4" min. MMA intregal flooring

sytem with 4" ht. wall base application, acid resistant

system , including patch repair, moisture treatment,

primer, membrane, flake coating, and top coat.

Standard Color - #3 , white with black and grey flake

blend.

J. Paint / Coatings / Colors/ Sealants

J.1. Colors --- See Schedules. Provide (3) 8-1 /2 x 11"

draw-down samples of each color on material for

review.

J.2. Products

J.2.1. TYPE - A -- Acro Pure, Miller or approved

equal, water based, Satin sheen unless noted

otherwise. Primer and (2) finish coats. Satin

sheen.

J.2.2. TYPE - B -- 100% Acrylic for use on metal,

PPG Pitt. Tech. Breakthrough or approved

equal, water base, Satin sheen. Primer and

(2) finish coats

J.2.3. TYPE - C -- Clear Flat Finish, Waterborne

Varnish, Emtech EM 8000cv, EM8428, Pre

Cat Waterborne Conversion Varnish, by

Target Coatings or approved equal, clear

natural coating for wood. (4) coats.

J.2.4. Match finish for reworked metal cabinetry. See

cabinetry section and details.

J.3. General Locations

J.3.1. General Painting, Gypsum Board / Plaster

Walls and Ceilings -- TYPE A

J.3.2. Exposed Natural Wood Work including Doors,

Trim or Base -- TYPE C

J.3.3. Existing painted Wood Work with Existing Oil

Based Paint including Doors, Frames, Trim ,

or Base. -- TYPE B

J.3.4. Metal Doors, Frames, Metal Work, Metal

Ceiling grids, or Railings -- TYPE B

J.3.5. Interior Hollow Metal Frames for Doors and

Windows. -- TYPE B

J.3.6. Interior Joint Sealers -- Silicone GE, Dow, or

approved equal. Sanitary type at bathrooms.

J.4. General Notes : Paint all Areas of Work including

exposed areas / surfaces remaining after-demolition,

including exposed mechanical ductwork and electrical

conduit + wiremold and exposed low voltage wiring.

Prepare, fill and level all surfaces as required for new

finishes for equal smooth level transitions with

existing surfaces. Use finish manufacturer's approved

products and specifications.

J.5. Mullion Filler Strip - None Required

K. Furnishings

K.1. White Boards -- Claridge or approved equal. Deluxe

white porcelain enamel steel marker brd. with satin

anodized alum. trim and tray. White # 75 low gloss.

K.2. Systems Furniture - None Required

K.3. Move Existing Equipment - By General Contractor or

PSU as noted on drawings.

K.4. Move Existing Furniture - By PSU with locations

shown per drawings. Existing furniture and chairs in

Engineering bldg rm 550 and 560 to remain and be

protected by Contractor.

K.5. Window Blackout Roller Shades - Blackout

Curtains.com or approved equal Fire Retardant, vinyl

embedded in fiberglass , 100% blackout opacity, R8

manual shade with blackout. Include stainless steel

bead chain, aluminum roller tube with black aluminum

front, end and back fascias, side and sill channels,

with synthetic pile inserts to eliminate light leakage.

Heat welded and enclosed pocket for Hem bar. Verify

existing window conditions for dimensions including

spacing of vertical side channels on window mullions.

Secure to wall structure.

K.6. Laser Curtains - PL Systems Inc. or approved equal

Laser Curtain model T2, double track assembly with

over-lapping curtains at required openings, and 11" +

valence above velcro attach to track assembly , black

color, Modacrylic flame retardant ,self-extinguishing,

light proof fabrics and vinyl backing. Grommet

attachment of Fabric to carrier and 2" floor overlap,

with 2' wide horizontal overlap + velcro at required

exits. Track assembly to include a double 16 ga.

extruded anodized aluminum 1-1 /4" wide track open

at bottom to receive carriers, with end stops as

required and velco attachment to end walls. Curtain to

provide complete Laser light protection. Secure to

structure above. Approx. curtain weight of 50# /ft.

shall be verified by contractor prior to purchase.

L. Appliances / Equipment --

L.1. Fire Cabinets. - See Mechanical Drawings.

L.2. Hoods and Base cabinet w/ toe kick space - See

Mechanical Drawings. PSU to provide. General

contractor to install.

L.3. Metal Cabinetry Island - Adjacent to Hoods. See "H"

portion of these specs.

L.4. Gas Cylinders - PSU to provide, General contractor to

install.

L.5. Gas Cylinder Wall Racks - USA or approved equal,

gas cylinder bracket for (3) cylinders. Chain model #

GB105FS, 11ga. hot rolled steel, powder paint finish,

support edges with steel reinf. vinyl edge guarding.

Wall mounted, 36"W x 2.25"D x 4.25"H. Provide

brackets at top and bottom at each exposed cylinder.

L.6. Chemical Refrigerator - Undercounter VWR model

97049-790 - AGA Marvel white with glass door.

34"h.x24"w.x24"d.

M. Insulation, Acoustical, Fire Caulk, and Safing

M.1. Wall Insulation Batts -- None Required.

M.2. Fire Caulking / Fire Safing --Manuf. 3M, STI, or

approved equal -- 1-hr. rated include at penetrations

at floors, roof, fire rated walls, concrete block

walls,stairway or shaft walls, fire corridors, mechanical

/electrical rooms, and vertical pipe and duct chases

thru floors.

M.3. Ceiling Insulation -- None Required.

M.4. Fire Doors / Smoke Gaskets -- None Required

N. Ceilings

N.1. New Suspended Acoustical Ceiling Tiles - Add to

accommodate existing work. Replace damaged or

stained existing Suspended Ceiling Tiles to match

existing. Armstrong or approved equal to match

existing.

N.2. Existing Ceiling Grids - To Remain. To accommodate

new work. Retrofit or repair to existing or new grid

components and support to be Heavy Duty type

material and installation to conform to City of Portland

latest standards. Armstrong or approved equal to

match existing.

O. Audio Visual

O.1. AV Equipment / Anchors and Cabeling -- None

Required.

P. Telco

P.1. Telephone and Computer Network Cabling and WIFI

-- See Electrical Engineer's dwgs. and specifications.

General contractor to provide and install.

P.2. PSU Equipment - Verify locations of network printer

and AV requirements with Electrical engineer's

drawings.

Q.Lighting / Electrical

Q.1. Electrical and Lighting --- See Electrical Engineer's

drawings for more information. Protect existing as

required. Provide new lighting as indicated on

drawings.

Q.2. Pathway & Boxes - Contractor to provide all boxes at

ceiling, walls, and floors, conduit, and pathway as

req'd. to include Electrical, Audio Visual, Telco,

Alarms, ADA door actuator, and other devises.

Q.3. Exit and Emergency -- Contractor to complete

Construction so as to provide minimum exit, egress,

audible strobe alarms, and emergency lighting as

required by City of Portland, including (1) footcandle

min at floor during construction. All doors, exits, and

hardware, to meet min.code requirements of the

City of Portland for exits and ADA clearances.

Q.4. Systems Furniture -- None Required .

Q.5. PSU Equipment - Verify locations of network printer

and AV requirements with Electrical engineer's

drawings.

R.Mechanical / Air Grilles

R.1. Mechanical -- See Mechanical Engineer's drawings

for mechanical items.

R.2. Balance HVAC system--- Contractor to Balance per

code requirements and submit an Engineer's

approved report for PSU Mechanical Engineer review

and approval.

S.Plumbing

S.1. Plumbing -- See Mechanical Engineer's drawings for

plumbing items

T. Fire - Systems

T.1. Fire Alarm / Sprinkler Systems. -- Refer to Elect.

Engineer drawings and specifications for additional

requirements. Contractor to Submit to city fire marshal

and provide PSU with City of Portland fire marshal

signed and dated approved fire system drawings.

Provide new work to conform to NFPA and include

demolition, relocation, materials and labor for a

complete code compliant installation.

T.2. Fire Sprinkler Heads - Provide New Quick Response

Fire Sprinkler head assembly to replace existing

throughout area of work. Verify existing. Move fire

sprinkler / heads or add new to accommodate new

work per code and approval of Fire Marshall. Match

existing finished sprinkler heads and plates.

U. ALTERNATE BID ITEMS -

U.1. ABI #1 - Resin Floor Coating System

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

ABI # 1

See Bid Forms and plans

for more ABI information.

ABI # 1

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A1 - EB550-60 - General.dwg, 5/8/2015 7:19:24 AM, DWG To PDF.pc3

arnicht
Stamp

A2.1

Demolition Plan

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /4 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

1. Typical Notes - See Specifications Sheet.

2. Existing Countertops - Cabinetry - Protect and to remain.

Modify counter tops for new sinks.

3. Service Drop Structure Above - Modify as required for new

ht. clearances.-See details.

4. Ceiling Modifications - Verify with ceiling plan to

accommodate new demo work including mechanical,

electrical, plumbing, and curtain assembly.

5. Modify cabinetry at new refrigerator location.

6. Modify cabinetry at new sink locations

7. Prep. concrete floor - as required for new flooring. Grind

bolt sleeves as required. Verify location and quantity.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:27 AM, DWG To PDF.pc3

arnicht
Stamp

A2.2

Plan

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /4 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

1. Typical Notes - See Specifications Sheet.

2. Wall Types - See Diagramatic Bldg Section on Detail Sheet.

3. New Laser Curtain - Suspended from Roof Structure above.

PLS Group or approved equal. Black fire retardant,

manually pulled on Manufacturer track. Meet NFPA fire-

retardant standards with signed certificate.

4. Window Blackout Blinds - Secured to wall - min lap windows

all around - verify existing dimensions. Blackout

Curtains.com or approved equal. R8 Roller Shade w/

Blackout. Black fire-retardant, manually pulled on

Manufacturer roller shades with chain in a perimeter metal

channel framework. Meet NFPA fire-retardant standards

with signed certificate.

5. Equipment Anchors - anchor vertical reactor to floor per

structural engineer requirements. See equipment plan for

approx. location.

6. New Sinks - Sawcut existing counter tops as required for

new sinks. Verify size and locations. See Plumbing

drawings.

7. Existing Built-in - Counter tops and cabinets to remain.

8. Racks - for gas cylinders. Sawcut / remove gyp. brd. and

provide sheet metal backing 16 ga x 18" high x stud widths

secured for rack backing at top and bottom area of gas

cylinders. See Equipment dwgs.

See Spec. Notes

THRU

LASER CURTAIN

Patch / Paint asreq'd for newutilities.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:28 AM, DWG To PDF.pc3

arnicht
Stamp

A2.3

Ceiling Plan

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /4 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

1. Typical Notes - See Specifications Sheet.

2. Overhead Utility Rack - See Diagramatic Bldg Section on

Detail Sheet.

3. New Laser Curtain - Suspended from Roof Structure above.

PLS Group or approved equal. Black fire retardant,

manually pulled on Manufacturer track. Meet NFPA fire-

retardant standards with signed certificate.

4. Lighting - Revise to accommodate for new work. w/ New 1x4

fixtures and new can lights.See Elect. Engineer dwg.

5. Fire Sprinkers - Revise and Add to accommodate new work

per code and specifications. Match existing type. N = New,

E= Existing, R = Relocated , D = Demo

6. Mechanical - Relocate existing mech. difusers - see Mech

Eng.dwgs.

7. Suspended Ceiling - Existing - replace damaged or stained

tiles with new.

See Spec. Notes

THRU

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:29 AM, DWG To PDF.pc3

arnicht
Stamp

A2.4

Equipment / Furniture

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /4 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

See systems furniture

designer plans and

spec book items for

more information.

1. Roughing Pump

2. Black Magic Vertical Reactor

3. ICP CVD Water Chiller

4. ICP CVD Controls / Power Rack

5. ICP CVD Vertical Reactor

6. Muffle Furnace

7. Carbonite Split Tube Furnace

8. Roughing Pump

9. Carbonite Split Tube Furnace

10. High Power Laser (ablation)

11. Roughing Pump

12. Tek-Vac Tube Furnace

13. Tek -Vac Pumping Station

14. Roughing Pump

15. MEPS Probe Station

16. MEPS Control / Power Rack

17. Probe Station Water Chiller

18. Lakeshore Magnetic Probe Station

19. Lakeshore Control / Power Rack

20. Raman Spectometer / Microprobe

21. Raman Control / Power Desk

22. Shimadzu UV-Vis Spectro-Photometer

23. Shimadzu Control Computer

24. Newport UV Lamp Controller

25. Newport UV Arc Discharge Lamp

26. Newport Computer Control

27. Vacuum Oven

28. Wafer Hot Plates

29. Centrifuge

30. Spin Coater

31. Laboratory Digital Scale

32. Sonic Probe and Controller

33. UHV System

Equipment List

1. Typical Notes - See Specifications Sheet.

2. Tables - Existing Relocated -- 2' x 6' verify +/-

3. Chairs - Existing Relocated

4. White Board - 4' x 4' Secure to Structure or Wall.

5. Gas Cabinets - Fire Rated - See Plumbing Eng. dwgs for

specification and requirements.

6. Gas Cylinders / Racks - Cylinders by PSU - Contractor to

provide and install racks secured to wall. Gas piping - see

Plumbing Eng. drawings.

7. Short Gas Cylinders - Cylinders by PSU - Contractor to

secure to floor and wall.

8. Laboratory Equipment - See Specs and List.

9. Laser Curtain

10. Equipment Moves - See specifications note sheet for more

information:

10.1. Equipment to go through the hatch: #4, 14, 20, and one

33-UHV system. Equipment item 20 may be

dissassembled unless taking it through the hatch at the

same time of the others is easier to coordinate.

10.2. Equipment moved by PSU staff: #24, 25, 22/23, 27, 31,

32, 00 (both).

32

31

30

29

27

28

26

25

24

23

22

20

21

15

14

16

17

18

19

05

04

03

02

01

06 07 08 09 10 11 12 13

33

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:30 AM, DWG To PDF.pc3

arnicht
Stamp

A2.5

New Items

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /4 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

A. Laser Blackout Curtain at interior - Encloses pillar and surrounds probe stations and Raman

Spectrometer ( requires darkness and adjustable light.) Foot-switch along with wall switch to

control lights within curtained area required. Four openings with and ability to fully retract all

sides.

A.1. Blackout Blinds at Exterior Windows. -

B. Service Drop #1 - Existing Structure Above - This drop serves Vertical Reactor and requires

compressed air, Ar,N

2

, He,CO

2

,H

2

, CH

4

,C

2

H

2

,O

2

,NH

3

. Electrical requirements per equipment

list. (2) data required.

C. Service Drop #2 - Existing Structure Above - This drop is used for general workspace and for

directing gas service to all tube furnaces and requires: compresssed air, Ar,N

2

, He,CO

2

,H

2

,

CH

4

,C

2

H

2

,O

2

,NH

3

. General electrical req'd. (2) Data required.

D. Service Drop #3 - Existing Structure Above - This drop serves the probe stations and Raman

spectrometer. It requires: compressed air, Ar,N

2

,O

2

,NH

3

. Electrical requirements listed in cut

sheets. (3) data required.

D.1. Service Drop #5 - Existing Structure Above - Verify requirements with MEP Engineer Dwgs.

E. Sink #1 - Deep basin sink with eye wash adjacent (left side preferred). Spigot for Type 3 water

required. Soap and paper towel dispenser required.

F. Sink #2 - Shallow basin sink for general use and hand washing with adjacent eyewash station.

Spigot for Type 3 water required. Soap and paper towel dispenser required.

G. Sink #3- double deep basin sink with sediment trap with adjacent eye wash sstation. Spigot for

Type 3 water required. Soap and paper towel dispenser required.

H. Tank Farm (9 tanks) - Ar,N

2

, He,CO

2

,H

2

, CH

4

,C

2

H

2

,O

2

,NH

3

. Stainless steel lines required for all

gases, with check valves at service points.

I. Cryogen Storage (2 tanks) - LN

2

and LHe wall anchoring points for secure storage.

J. Type 3 Water Source - DI (Type 3) water at separate spigots each sink.

K. 6' w. Back to Back Dynamic Barrier Fume Hoods - Requires Ar, N

2

, CH

4

, and O

2

, Type 3 water,

vacuum, flammable and corrosive storage required below hoods.

L. Laboratory Island - Island connected to hoods located under server drop #4. Requires Ar, N

2

,

CH

4

, and O

2

. Shelving in center of island required for sample and chemical storage.

M. Service Drop #4 - Existing Structure Above - Raise as required for hood clearances. Requires

Ar, N

2

, CH

4

, and O

2

, and vacuum line. The vacuum line will be served by a remote roughing

pump (on/off at wall switch)

N. Under Counter Chemical Refrigerator - Storage for temperature sensitive chemicals. Must lock

and be controlled by digital feedback.

New Items - Program list

xx

E

B

C

D

D1

M

K

L

N

G

I

H

J

F

A

A1

A1A1

O

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:32 AM, DWG To PDF.pc3

arnicht
Stamp

A2.6

Equipment Spec.

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /4 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

01

1. Roughing Pump

2. Black Magic Vertical Reactor

3. ICP CVD Water Chiller

4. ICP CVD Controls / Power Rack

5. ICP CVD Vertical Reactor

6. Muffle Furnace

7. Carbonite Split Tube Furnace

8. Roughing Pump

9. Carbonite Split Tube Furnace

10. High Power Laser (ablation)

11. Roughing Pump

12. Tek-Vac Tube Furnace

13. Tek -Vac Pumping Station

14. Roughing Pump

15. MEPS Probe Station

16. MEPS Control / Power Rack

17. Probe Station Water Chiller

18. Lakeshore Magnetic Probe Station

19. Lakeshore Control / Power Rack

20. Raman Spectometer / Microprobe

21. Raman Control / Power Desk

22. Shimadzu UV-Vis Spectro-Photometer

23. Shimadzu Control Computer

24. Newport UV Lamp Controller

25. Newport UV Arc Discharge Lamp

26. Newport Computer Control

27. Vacuum Oven

28. Wafer Hot Plates

29. Centrifuge

30. Spin Coater

31. Laboratory Digital Scale

32. Sonic Probe and Controller

33. UHV System

Equipment

02 03

04,5

04,5

04,506 07 08 09 10

11

20,21

31

12

22,23

32

13

24

14,15,16

25

00

17

22,23

18,19

27

00

33 No Photo -

See existing site

location.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:34 AM, DWG To PDF.pc3

arnicht
Stamp

A2.7

Existing Equipment

SB-1 Basement Plan

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

scale: 1 /8 " = 1'- 0"

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

5/08/2015

1. Roughing Pump

2. Black Magic Vertical Reactor

3. ICP CVD Water Chiller

4. ICP CVD Controls / Power Rack

5. ICP CVD Vertical Reactor

6. Muffle Furnace

7. Carbonite Split Tube Furnace

8. Roughing Pump

9. Carbonite Split Tube Furnace

10. High Power Laser (ablation)

11. Roughing Pump

12. Tek-Vac Tube Furnace

13. Tek -Vac Pumping Station

14. Roughing Pump

15. MEPS Probe Station

16. MEPS Control / Power Rack

17. Probe Station Water Chiller

18. Lakeshore Magnetic Probe Station

19. Lakeshore Control / Power Rack

20. Raman Spectometer / Microprobe

21. Raman Control / Power Desk

22. Shimadzu UV-Vis Spectro-Photometer

23. Shimadzu Control Computer

24. Newport UV Lamp Controller

25. Newport UV Arc Discharge Lamp

26. Newport Computer Control

27. Vacuum Oven

28. Wafer Hot Plates

29. Centrifuge

30. Spin Coater

31. Laboratory Digital Scale

32. Sonic Probe and Controller

33. UHV System

Equipment

Exist. Lab

Exist. Lab

Exist. Lab

Exist. Lab

Exist. Lab

1. Hatch location to ground surface. This will be needed

for equipment item # x,x,x,x which will not fit in the

elevator.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A2 - EB550-60 - Plan.dwg, 5/8/2015 7:19:35 AM, DWG To PDF.pc3

arnicht
Stamp

LASERFIRE CORRIDOR

ROOF AREA ROOF AREA

HOODS STAIR

ROOF DECK

5TH FLOOR

1- HR. 2- HR. SHAFT

ROOF DECK

5TH FLOOR

HOODSSTAIRFIRE CORRIDOR

ROOF AREA

1- HR.

section - south- north

1 /4 " = 1' - 0"

section - west-east

1

-

2

-

Protect existing

structure and

utilities. Obtain core

drill or anchor

location approval.

Line of existing

bldg. wall.

Line of suspended

ceiling

A3.1

Plan Notes

1. See specification sheet for notes.

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

Sections

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

1 /4 " = 1' - 0"

For other notes and info

see plans, detail sheets

and section below.

Line of suspended

ceiling

Verify walls that

extend to structure

above

Existing Concrete

slab on metal

cellular deck. Verify

utility locations in

open cells.

GRIDS - TYP.

Existing Roofing &

Insulation on

concrete slab on

cellular deck.

Typ. Bracing and

support at laser

curtain. See details.

Laser Curtain.

GRIDS - TYP.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A3 - EB550-60 - Sections-Details.dwg, 5/8/2015 7:19:36 AM, DWG To PDF.pc3

arnicht
Stamp

+/- verify

A3.2

Details

1 - 1 /2" = 1'-0"

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Plan Notes

1. See specification sheet and room / finish schedules. Information

shown is general and diagramatic.

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

Blinds - Detail

No Scale

Laser Curtain - Info Detail

1 - 1 /2 " = 1' - 0"

Detail

1- 1 /2 " = 1' - 0"

Revised Utility Rack

3" = 1' - 0"

Laser Curtain - Track Detail

1- 1 /2 " = 1' - 0"

Detail

1- 1 /2 " = 1' - 0"

Detail

Detail

No Scale

no scale

See Structural Eng. Details for all Connections.

Vertical all-thread

supports to structural

deck above.

Sway bracing

Cont. Struct Channel

2 x fire retardant

blocking.

Susp. ceiling - break

trim, and secure for

track opening.

Manuf. track - secure with

thru-bolts per structural

engineer.

Double track at curtain

opening with typ. curtain and

fabric valence.

Susp. ceiling - break

trim, and secure for

track opening.

Shorten exist utility rack

metal unistrut supports.

Verify ht. with new

equipment and

cabinetry.

Re-connect U-bracket

metal mounting trim and

utility runs as req'd.

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A3 - EB550-60 - Sections-Details.dwg, 5/8/2015 7:19:36 AM, DWG To PDF.pc3

arnicht
Stamp

A4.1

Plan Notes

schedules

no scale

1. See specification sheet for notes.

2. See plans for recessed entries with low soffits above.

Door / Window / Room

Schedule

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

ABI # 1

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A4 - EB550-60 - Schedules.dwg, 5/8/2015 7:19:37 AM, DWG To PDF.pc3

arnicht
Stamp

Floor

Ceiling

+/- Verify

+/- V

erify

+/- Verify+/- Verify +/- Verify +/- Verify+/- Verify

+/- Verify

+/- V

erify

Floor

Ceiling

+/- Verify

+/- V

erify

ENTRY

+/- Verify+/- Verify

+/- Verify

P. Resin Chemicalresist. solid top,

Adjust. openmetal shelveswith metalsupportstandards,brackets, andedge lip,seismic T-mold

Metal cab.doors, w/drawers above

+ / -

adjustable shelves

+ /

-

+ /

-

2'-0"

Floor

Ceiling

REF

Rework exist metalcabinets to accomodatenew refrigerator provideand install new finishedmetal side panels tomatch as req'd.

Ceiling

30" +/- 3'-0" 3'-0"

Floor

Existing Metalcabinets anddrawers andchemical resistantsolid top

SINK

Rework / demo exist. metalcabinets to accommodatenew sink . Add cabinet doorsto match at locations whereremoval of existing drawersare required.

Ceiling

Varies 2' to 3'

Floor

Existing Metalcabinets anddrawers andchemical resistantsolid top

-

1

Laser Curtains1 /4 " = 1' - 0"

-

2

Window Blinds1 /4 " = 1' - 0"

A5.1

Plan Notes

FOR ALL STRUCTURAL, MECHANICAL, ELECTRICAL,

TELCO AV, AND FIRE SPRINKLER / ALARM INFORMATION

SEE ENGINEER'S DRAWINGS and SPECIFICATIONS.

Int. Elevations

5/08/2015

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR LAB REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

Verify All Dimensions

and Existing Conditions

prior to accommodating

new construction.

North Elevation

North Elevation East Elevation South Elevation

1. Typical Notes - See Specifications Sheet.

2. New Laser Curtain - Suspended from Roof Structure above.

3. Window Blackout Blinds - Secured to wall.

4. New Island Cabinets @ Hood.

5. Under-Counter Refrigerator

6. Typical Sink

-

4

Under-Counter Refrigerator at Existing Cabinets1 /4 " = 1' - 0"

-

5

Typical Sink at Existing Cabinets

South Elevation

-

3

New Cabinets @ Hoods1 /4 " = 1' - 0"1 /4 " = 1' - 0"

Typical Elevation North Elevation (South similar)Section

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\A5 - EB550-60 - Elevations.dwg, 5/8/2015 7:19:37 AM, DWG To PDF.pc3

arnicht
Stamp

S1

Structural Items

PSU Capital Projects & Construction

EBENGINEERING BLDG.

RM. 550 & 560INTERIOR OFFICE REMODEL

(Block 091)1930 SW 4TH Ave.

Portland, Oregon 97201

Revisions :

Drawn :

Checked :

Date :

5 / 08 / 15

Laser Curtain Support Detail

Drawing Notes

1. Coordinate Structural details with Architectural details and

plans.

2. All work and materials per latest City of Portland codes

and manufacturer's industry standards and specifications.

SK-1

-

Calculations

I:\Staff\Facilities\Projects\091_EB\EB_OPEN\2015_091_EB550-560-JunJaio-Lab\3-Arch\0.1-Bid Set - ACAD Dwgs\S1-EB550-560 - Structural.dwg, 5/8/2015 7:19:40 AM, DWG To PDF.pc3