Engineering 100: Bridge Project

16
Engineering 100: Bridge Project Group 6 (Team Bacardi) Jon Honari, Kevin Lam, Otis Chantharangsy, Ivee Ilao

description

Engineering 100: Bridge Project. Group 6 ( Team Bacardi ) Jon Honari, Kevin Lam, Otis Chantharangsy, Ivee Ilao. Design Ideas Prototype Bridge Process Testing/Results Prototype Analysis Flaws Improvements . Final Bridge Design Testing/results Final Results Graph Analysis Failures - PowerPoint PPT Presentation

Transcript of Engineering 100: Bridge Project

Page 1: Engineering 100: Bridge Project

Engineering 100:Bridge Project

Group 6 (Team Bacardi)Jon Honari, Kevin Lam,

Otis Chantharangsy, Ivee Ilao

Page 2: Engineering 100: Bridge Project

Presentation Outline Design

Ideas Prototype

Bridge Process Testing/

Results Prototype

Analysis Flaws Improvements

Final Bridge Design Testing/

results Final Results

Graph Analysis Failures

Conclusion

Page 3: Engineering 100: Bridge Project

Design Arch Design

Proved to be strongest structure based on our research

Base Flat and straight

Supports Angle supports

Evenly distributed force

Page 4: Engineering 100: Bridge Project

Prototype Design

QuickTime™ and a decompressor

are needed to see this picture.

Page 5: Engineering 100: Bridge Project

Prototype Process Arch Supports Road Connections Structural

Reinforcements

Page 6: Engineering 100: Bridge Project

Prototype Process

Page 7: Engineering 100: Bridge Project

Prototype Testing/Results

Page 8: Engineering 100: Bridge Project

Prototype Analysis Flaws

Uneven weight distribution Not supported where

bridge met jigUltimate reason for failure

Weak road Sloppy design Unnecessary weight

Page 9: Engineering 100: Bridge Project

Prototype Flaws

Red: Excess Weight Green: Lack of Support

Page 10: Engineering 100: Bridge Project

Final Design Excess weight was removed Top section was more

reinforced Used wood glue instead of

hot glue for the majority Made sure weight was

distributed evenly Reinforced the legs where

the bridge met the jig Added more supports

Page 11: Engineering 100: Bridge Project

Prototype vs. Final Design

Final Bridge Prototype

Page 12: Engineering 100: Bridge Project

Final Design (Completed)

Page 13: Engineering 100: Bridge Project

Final Testing/Results

Page 14: Engineering 100: Bridge Project

Final Design Failure

Important joints were overlooked and were not supported correctly

Page 15: Engineering 100: Bridge Project

Final Analysis Overall, very good

improvement Bridge weighed 0.59 lbs Bridge held 531.89 lbs Performance = Successful With more supports in the

correct places we believe the bridge could hold much more weight

Page 16: Engineering 100: Bridge Project

We conclude… Spending more time on the

construction yielded better results About 170% improvement High efficiency ratio Endures a high amount of pressure Lasts under consistent amount of low

pressure First Bridge: .56 pounds, held 296.00 lb Final Bridge: .59 pounds, held 531.89

lb