Engineered Channel Design Criteria - Ian Paton Wright ...
Transcript of Engineered Channel Design Criteria - Ian Paton Wright ...
October 18, 2007, page 1
Agenda
• 1 - Introduction
• 2 -Types of Open Channels
• 3 - Open Channel Design Principles
• 4 - Natural Channel Design Criteria
• 5 - Engineered Channel Design Criteria
• 6 - Hydraulic Structures
• 7- Small Grade Control Structures
October 18, 2007, page 2
Engineered Channel Design CriteriaFlow Rate/Design Flows
• Engineered channel design flows- 25-year flow – conveyed in channel
• In addition- 100-year flow- Must be contained within drainage easement
• Design flows – must be calculated for fully developed watershed condition- Based on current/anticipated land uses
• Upstream detention storage may be considered- If ownership and maintenance responsibilities of facility are clearly defined- To get flow reduction credit, detailed modeling/basin routing must be completed
100-year
25-year
October 18, 2007, page 3
Engineered Channel Design CriteriaFroude Number and Flow Regime
Fr < 1.0 Flow is subcritical
Fr = 1.0 Flow is critical
Fr > 1.0 Flow is supercriticalSupercritical flows should be avoided if possible
- Best to have Fr < 0.8(near 1.0 – flows are unstable)
- Fr should be checked for all unique channel sections for 25-year flow
- Checked using minimum “n” value for channel lining
- If supercritical necessary, then Fr should be > 1.2
- Concrete lining required
October 18, 2007, page 4
Engineered Channel Design CriteriaVelocity
Channel TypeMinimum Velocity
Maximum Velocity
Grass, seed and mulch 2 ft/s 4 ft/s
Grass, sod 2 ft/s 6 ft/sGrass, TRM 2 ft/s 8 ft/sGrass, pre-
vegetated TRM 2 ft/s 10 ft/s
Manufactured hard lining 5 ft/s 12 ft/s
Riprap 5 ft/s 12 ft/s
Concrete 5 ft/s 18 ft/s
Table OC-6 – Design Velocity Limitations for Open Channel With Different Lining Types
Increasing allowable velocity
October 18, 2007, page 5
Engineered Channel Design CriteriaLongitudinal Slope
Acceptable maximum longitudinal slope generally dictated by criteria for:
- Flow regime (i.e., Fr < 0.8)
- Flow velocity (i.e., type of channel lining)
Acceptable minimum slope (to minimize ponding):
- 0.4 percent – for natural linings
- 0.2 percent – for concrete linings
October 18, 2007, page 6
Engineered Channel Design CriteriaLongitudinal Slope
If slope is too steep, options to reduce slope include:
Integrate drop structure into channel
Integrate curvature into channel
- With careful consideration- Centerline of curve should have minimum radius of 2 x top width (25-yr)(radius no less than 100 feet) Every design is
site-specific
October 18, 2007, page 7
Engineered Channel Design CriteriaCurvature and Superelevation
• Solve for Superelevation
cgrTVy
2
2
=∆
Where:Δy = difference in water surface elevation
(inside vs. outside of curve)(ft)V = Mean flow velocity (ft/sec)T = Top width of channel (design flow conditions)(ft)g = gravitational constant (32.2 ft/sec2)rc = radius of curvature (ft)
Superelevation on outside of bend
Channel x-sectionChannel curve –Plan view
For velocity, use minimum range of “n” value (to get max. velocity)
October 18, 2007, page 8
Engineered Channel Design CriteriaFreeboard
The required freeboard for engineered open channels is dependent on the type of channel:
Concrete channels Required freeboard6 inches above 25-year water surface
Other types of channels
Required freeboard12 inches above 25-year water surface
(Except for channels where 25-year flow depth is < 12 inches, then freeboard is only 6 inches above 25-year surface)
October 18, 2007, page 9
Engineered Channel Design CriteriaGrass Channel Example
Design of Trapezoidal Grass-Lined Channel
Open“Open Channel Design” file
Click on“Grass Channel” tab
Project:Channel ID:
*** DRAFT ***
Channel Input ParametersDesign Discharge Qd = 75.00 cfsDesign Discharge Return Period Yeard = 100 yearsExisting Ground Slope Along Channel Centerline So = 0.030 ft/ft25-Year Discharge Q25 = 50.00 cfs2-Year Discharge Q2 = 30.00 cfs
Warning 01 Left Side Slope (H:V) Z1 = 3.00 ft/ftWarning 01 Right Side Slope (H:V) Z2 = 3.00 ft/ft
Min Manning's n (max velocity and Fr # check) nmin = 0.030 See "Design Info" tab forWarning 02 Max Manning's n (min velocity and capacity check) nmax = 0.045 recommended Manning's n values.
Grass Channel Lining Type (sets max velocity) Select One
User-Defined Bottom Width B = 5 ft
Maximum Allowable Longitudinal Slope Smax = 0.0225 ft/ft (based on Q25, nmin, & channel lining)User-Defined Longitudinal Slope Suser = 0.0200 ft/ft (min of 0.004 to prevent ponding)Drop Height per 100 ft D = 1.000 ft/ 100 ft
Proposed Channel Conditions (Calculated)25-Year Discharge Flow Depth Required(using Q25 and nmin) (using Q25 and nmax)
25-Year Flow Depth Y= 1.06 ft Y= 1.31 ft25-Year Flow Velocity Vmax= 5.75 fps V= 4.29 fps25-Year Top Width T= 11.37 ft T= 12.84 ft25-Year Flow Area A= 8.69 sq ft A= 11.65 sq ft
Warning 04 25-Year Froude Number Frmax = 1.16 Fr = 0.7925-Year Wetted Perimeter P= 11.72 ft P= 13.26 ft25-Year Hydarulic Radius R= 0.74 ft R= 0.88 ft
2-Year Discharge(using Q2 and nmax)
2-Year Flow Depth Y= 1.01 ft2-Year Flow Velocity Vmin= 3.72 fps2-Year Top Width T= 11.04 ft2-Year Flow Area A= 8.07 sq ft2-Year Froude Number Fr = 0.772-Year Wetted Perimeter P= 11.36 ft2-Year Hydarulic Radius R= 0.71 ft
Design Discharge(using Qd and navg)
Design Discharge Flow Depth YD= 1.46 ftDesign Discharge Flow Velocity VD= 5.47 fpsDesign Discharge Top Width TD= 13.77 ftDesign Discharge Flow Area AD= 13.71 sq ft
Warning 04 Design Discharge Froude Number Fr D= 0.97Design Discharge Wetted Perimeter PD= 14.24 ftDesign Discharge Hydarulic Radius RD= 0.96 ft
Click here for important information
regarding this spreadsheet
sod, Vmax = 6 fps
October 18, 2007, page 11
Engineered Channel Design CriteriaChannel Linings – Soil Bioengineered Lining
Soil bioengineering integrates native vegetation as a structural element of streambank stabilization
Provides:- effective streambank protection- effective energy dissipation- aquatic/terrestrial habitat benefits
Selection of plants and planting method specifications must be prepared by a professional with expertise in stabilization properties of plants
October 18, 2007, page 12
Engineered Channel Design CriteriaChannel Linings – Grass Lining
The design velocity in the channel will dictate the type of grass lining to use
If design velocities exceed the allowable for seed and mulch, the channel will be lined with sod, approved TRM, or approved reinforced sod Up to level
of 25-year water surface
October 18, 2007, page 13
Engineered Channel Design CriteriaChannel Linings – Manufactured Hard Lining
Up to level of 25-year water surface
Similar to reinforced turf, manufactured hard linings must reach
October 18, 2007, page 14
Engineered Channel Design CriteriaChannel Linings – Riprap sizing
• Solve for K-value
66.0
17.0
)1( −=
SGVSK
Where:K = Riprap sizing constantV = Mean channel velocity (ft/sec)S = Longitudinal slope (ft/ft)Gs = Gravitational constant (32.2 ft/sec2)
K Value Rock Type
< 3.3 VL**(d50 = 6 inches)
> 3.3 to < 4.0 L**(d50 = 9 inches)
> 4.0 to 4.6 M**(d50 = 12 inches)
> 4.6 to 5.6 H**(d50 = 18 inches)
> 5.6 to 6.4 VH**(d50 = 24 inches)
October 18, 2007, page 15
Engineered Channel Design CriteriaRiprap Example
Open“Open Channel Design” file
Click on“Riprap” tab
Project:Channel ID:
*** DRAFT ***
Design Information (Input)Channel Invert Slope So = 0.0200 ft/ftBottom Width B = 0.0 ft Left Side Slope Z1 = 3.0 ft/ftRight Side Slope Z2 = 3.0 ft/ftSpecific Gravity of Rock (minimum of 2.6) Gs = 2.60Radius of Channel Centerline (enter 0 for straight channel) rc = 100.0 ft
Design Disharge Q = 3.0 cfs
Flow Condition (Calculated)Riprap Type (Straight Channel) Type = MIntermediate Rock Diameter (Straight Channel) D50 = 12 inchesCalculated Manning's n (Straight Channel) min-n = 0.038 Riprap Type (Outside Bend of Curved Channel) Type = MIntermediate Rock Dia. (O.B. of Curved Channel) D50 = 12 inchesCalculated Manning's n (O.B. of Curved Channel) min-n = 0.038 Water Depth Y = 0.64 ftTop Width of Flow T = 3.8 ftFlow Area A = 1.2 sq ftWetted Perimeter P = 4.1 ftHydraulic Radius (A/P) R = 0.3 ftAverage Flow Velocity (Q/A) V = 2.5 fpsHydraulic Depth (A/T) D = 0.3 ftFroude Number (max. = 0.8) Fr = 0.780Channel Radius / Top Width rc /T = 26.04
Riprap Design Velocity Factor For Curved Channel Kv = Riprap Sizing Velocity For Curved Channel VKv = fps
Minimum Riprap Sizing Paramenter for Straight Channel K = 0.94Minimum Riprap Sizing Paramenter for Outside Bend of Curve Kcurve =Superelevation (dh) dh = ftRequired channel depth (based on max n value) Yrequired= 0.66 ftTotal channel depth including superelevation Ytotal= 0.66 ft
Discharge (Check) Q = 3.1 cfs
Design of Riprap Channel Cross Section
October 18, 2007, page 16
Engineered Channel Design CriteriaChannel Cross-Sections
• Most desirable cross-section- Relatively wide- Primarily vegetated
• Benefits- Recreation - Maintenance- Safety- Water quality- Downstream impacts- Habitat
October 18, 2007, page 17
Engineered Channel Design CriteriaLow-Flow Channels
• A low-flow channel is necessary for:
• Vegetated channels where:
- Baseflow exists- High peak runoff from developed
area may cause channel erosion- 2-year flow > 5 cfs
(for unreinforced grass only)
• For all channels where erosion is likely to occur (such as downstream from point discharges)
October 18, 2007, page 18
Engineered Channel Design CriteriaChannel Outfalls
• Vegetated channels generally cannot withstand point discharges
• Some type of energy dissipation is necessary to minimize bank, channel, or wall erosion
• Protrusions into the channel (e.g., pipes) should be trimmed flush with the main channel wall or bank
October 18, 2007, page 19
Agenda
• 1 - Introduction
• 2 -Types of Open Channels
• 3 - Open Channel Design Principles
• 4 - Natural Channel Design Criteria
• 5 - Engineered Channel Design Criteria
• 6 - Hydraulic Structures
• 7- Small Grade Control Structures
October 18, 2007, page 20
Hydraulic StructuresLarge Hydraulic Structures
The Open Channels chapter does not provide detailed information on the design of large hydraulic structures
In cases where a large/complex hydraulic structure is proposed, a preliminary meeting must be held with City staff.
Text references are provided for several specific types of hydraulic structures
October 18, 2007, page 21
Agenda
• 1 - Introduction
• 2 -Types of Open Channels
• 3 - Open Channel Design Principles
• 4 - Natural Channel Design Criteria
• 5 - Engineered Channel Design Criteria
• 6 - Hydraulic Structures
• 7- Small Grade Control Structures
October 18, 2007, page 22
Small Grade Control StructuresFive Types of Small Drop Structures Presented
Newberry-style structure
Grouted sloping boulder
Sloping concrete structure
Sculpted concrete structure
Vertical hard basin
October 18, 2007, page 23
Small Grade Control StructuresDesign Conditions
Design Parameter Criteria
Peak flow rate 200 cfs
Typical channel longitudinal slope 0.3 to 0.8 percent
Normal flow depth (maximum) 3 feet
Flow velocity (maximum) 6 ft/s
Froude number (maximum) 0.8
Geotechnical condition (assumed) Moderate strength clay with chert
Table OC-12 – Design parameters for small grade control structures
For drops of 2 feet or less
October 18, 2007, page 24
Small Grade Control StructuresDrop Structure Selection Process – Evaluation Matrix
Primary Considerations- Public Safety- Functional Hydraulic Performance
Grade Control Structure TypeConsiderations for Grade Control
Structure DesignGrouted
Sloping BoulderConcrete Sloping
Vertical Hard Basin Newbury-style Sculpted
Concrete
Primary Considerations
Public Safety More preferred for areas with high public usage
Less preferred for areas with high public usage
Less preferred for areas with high public usage, (though the potential for reverse rollers and backflow eddies is reduced with drop of 2 feet or less)
More preferred for areas with high public usage
More preferred for areas with high public usage
Functional Hydraulic Performance
Good flexibility of layout options. Roughness effective for dissipating kinetic energy
Maximum vertical drop limited by public safety concern
Maximum vertical drop limited by public safety concern (see above)
Good flexibility of layout options. Roughness effective for dissipating kinetic energy
Good flexibility of layout options
October 18, 2007, page 25
Small Grade Control StructuresDrop Structure Selection Process – Evaluation Matrix2ndry - Cost, Ecological Impacts, Aesthetics, Maintenance, Environ. Permitting
Secondary Considerations
Land Use(Contextual Design)
Provides natural channel appearance
Best suited for urban setting
Best suited for urban setting
Provides natural channel appearance
Provides natural channel appearance
Cost Costs comparable for all options
Costs comparable for all options
Costs comparable for all options
Costs comparable for all options
Costs comparable for all options
Ecological Impacts Creates larger footprint than vertical drop
Creates larger footprint than vertical drop. Has no habitat or water quality benefits and may be detrimental.
Creates smallest footprint of any option. Has no habitat or water quality benefits and may be detrimental.
Provides refuge for macroinvertebrates and small fish, fish passage, simulates naturally occurring riffle. Provides refuge during flow event.
Creates larger footprint than vertical drop. Has no habitat or water quality benefits and may be detrimental.
Aesthetics Natural-appearing, aesthetic option
Less aesthetic relative to other options
Less aesthetic relative to other options
Natural-appearing, aesthetic option
Natural-appearing, aesthetic option
Maintenance Potential for scour erosion at downstream end
Potential for scour erosion at downstream end
Sediment deposition in impact basin, scour erosion at downstream end of basin
Little potential for scour erosion at downstream end
Potential for scour erosion at downstream end
Environmental Permitting
More disturbed area than other options
More disturbed area than other options
Less disturbed area than other options
More disturbed area than other options. Simulates naturally occurring riffle. No concrete in stream. When vegetated, supports both terrestrial and aquatic species.
More disturbed area than other options
Sculpted ConcreteNewbury-styleVertical
Hard BasinConcrete Sloping
Grouted Sloping Boulder
Grade Control Structure TypeConsiderations for Grade Control
Structure Design
October 18, 2007, page 26
Small Grade Control StructuresGrouted Sloping Boulder
Pros• Preferred in areas with high public
usage• More aesthetic than vertical hard
basin drop• Low maintenance
Cons• Dependent on availability of rock
October 18, 2007, page 27
Small Grade Control StructuresGrouted Sloping Boulder – Design Criteria (p. 1 of 2)
General Feature Design Parameter Parameter Value
Approach Approach length (La)
8 feet(armored with grouted rock-see below for boulder sizing)
Boulder sizing—nominal size
18 inches(acceptable range: 17 to 20 inches)
Boulder placement—crest
and cutoff
Grouted boulders must cover the crest and cutoff and extend downstream through the energy dissipating basin
Boulder placement—through drop
Boulders must be carefully placed to create a stepped appearance, which helps to increase roughness.
Boulder placement—basin
end
Boulders must be placed at basin end to create a sill transitionto downstream channel invert elevation.
Grout Grout thickness (Dg)
½ mean diameter of boulders (Dr)
Crest Crest width(minimum)
Minimum width same as upstream channel bottom width
Longitudinal slope of drop
Maximum slope 4H:1V(slopes flatter than 4:1 promote increased safety, enhanced
structure stability, and improved appearance)
Boulders
October 18, 2007, page 28
Small Grade Control StructuresGrouted Sloping Boulder – Design Criteria (p. 2 of 2)
General Feature Design Parameter Parameter Value
Basin length (Lb) 20 feet
Basin width (B) Same as crest width
Basin depression
1 foot
Upstream configuration
Trickle or low-flow channel should extend through the drop crest section
Downstream configuration
Trickle or low-flow channel protection should extend downstream from the main channel protection
Trickle zone protection width
below drop
Smaller of:i) 3 times trickle zone channel width, or ii) trickle zone channel width, squared
Energy dissipation
Install large boulders in center basin zone to dissipate energy of high flow stream
Downstream channel Downstream channel armoring
Buried riprap zone shall be installed for a minimum of 10 feet downstream of the drop basin sill
Note: Design guidelines contained in this table are for channels that meet the threshold criteria for maximum allowable flow depth and velocity.
Low-flow Zone(if necessary)
Basin Geometry
October 18, 2007, page 29
Small Grade Control StructuresGrouted Sloping Boulder – Conceptual Drawing (Plan View)
October 18, 2007, page 30
Small Grade Control StructuresGrouted Sloping Boulder – Conceptual Drawing (Profile)
October 18, 2007, page 31
Small Grade Control StructuresSloping Concrete Structure
Pros• Allows for sloped drop if boulders unavailable
• Relatively straightforward to construct
Cons• Lack of energy dissipation results in greater potential for scour at toe of structure – increased maintenance • Less aesthetic • Larger relative disturbance area
October 18, 2007, page 32
Small Grade Control StructuresVertical Hard Basin
Pros• Can construct if boulders unavailable
Cons• Less preferred in areas with high public usage• Less aesthetic
October 18, 2007, page 33
Small Grade Control StructuresNewberry-Style Structure
Pros• Interstitial rock spaces provide refuge for macroinvertebrates and small fish• More aesthetic than other hard basin structures• Simulates natural riffle• Provides energy dissipation• Naturalizes over time
Cons• Shallow slope of rock ramp results in large footprint from structure• Live stake must be planted during dormant period• More difficult to achieve shape in very small streams.
October 18, 2007, page 34
Small Grade Control StructuresSculpted Concrete Structure
Pros• Preferred in areas with high public usage• Allows for sloped drop if boulders unavailable• More aesthetic than vertical hard basin structure
Cons• Requires contractor labor force with specialized skill and/or more field oversight by designer• Less energy dissipation than grouted boulders• Does not provide habitat for macroinvertebrates and small fish