(ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

124
CECW-EG Engineer Manual 1110-2-2000 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 EM 1110-2-2000 1 February 1994 Engineering and Design STANDARD PRACTICE FOR CONCRETE FOR CIVIL WORKS STRUCTURES Distribution Restriction Statement Approved for public release; distribution is unlimited.

description

Standard code of practice for Civil Engineers

Transcript of (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

Page 1: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

CECW-EG

Engineer Manual

1110-2-2000

Department of the Army

U.S. Army Corps of EngineersWashington, DC 20314-1000

EM 1110-2-2000

1 February 1994

Engineering and Design

STANDARD PRACTICE FOR CONCRETEFOR CIVIL WORKS STRUCTURES

Distribution Restriction StatementApproved for public release; distribution is

unlimited.

Page 2: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20003 February 1994

US Army Corpsof Engineers

ENGINEERING AND DESIGN

Standard Practice for Concretefor Civil Works Structures

ENGINEER MANUAL

Page 3: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

CECW-EI

ManualNo, 111 o-2-2000

DEPARTMENT OF THE ARMYU.S. Army Corps of Engineers

Washington, DC 20314-1000

EM 111 o-2-2000Change 2

31 March 01

Engineering and DesignSTANDARD PRACTICE FOR CONCRETE

FOR CIVIL WORKS STRUCTURES

1. This Change 2 to EM 1110-2-2000, 1 February 1994, provides updated guidance for theselection of aggregates in Chapter 2.

2. Substitute the attached pages as shown below:

Remove Page Insert page

2-10 2-10

2-11 2-11

3. File this change sheet in front of the publication for reference purposes.

FOR THE COMMANDER:

Colonel, Corps of EngineersChief of Staff

Page 4: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

DEPARTMENT OF THE ARMY EM 1110-2-2000U.S. Army Corps of Engineers Change 1

CECW-ED Washington, DC 20314-1000

ManualNo. 1110-2-2000 31 July 94

Engineering and DesignSTANDARD PRACTICE FOR CONCRETE

FOR CIVIL WORKS STRUCTURES

1. This Change 1 to EM 1110-2-2000, 1 February 1994, updates Chapter 2.

2. Substitute the attached pages as shown below:

Remove page Insert page

2-1 2-1

2-6 2-6

3. File this change sheet in front of the publication for reference purposes.

FOR THE COMMANDER:

WILLIAM D. BROWNColonel, Corps of EngineersChief of Staff

Page 5: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

DEPARTMENTDEPARTMENT OFOF THETHE ARMYARMY EM 1110-2-2000US Army Corps of Engineers

CECW-EG Washington, DC 20314-1000

ManualNo. 1110-2-2000 1 February 1994

Engineering and DesignSTANDARD PRACTICE FOR CONCRETE

FOR CIVIL WORKS STRUCTURES

1. Purpose. The purpose of this manual is to provide information and guidance for the investigation andselection of concrete materials for civil works concrete structures. Elements discussed include design studies andreports, preparation of contract plans and specifications, construction preparation, and concrete construction qualityverification. Emphasis is placed on the problems of concrete for hydraulic structures. Roller-compacted concrete,shotcrete, rigid pavement, architectural concrete, and concrete for repairs are not included. These subjects arediscussed in EM 1110-2-2006, Roller-Compacted Concrete; EM 1110-2-2005, Standard Practice for Shotcrete; TM5-822-7, Standard Practice for Concrete Pavements; EM 1110-1-2009, Architectural Concrete; and EM 1110-2-2002, Evaluation and Repair of Concrete Structures, respectively.

2. Applicability. This manual is applicable to all HQUSACE elements, major subordinate commands, districts,laboratories, and field operating activities having civil works responsibilities.

FOR THE COMMANDER:

WILLIAM D. BROWNColonel, Corps of EngineersChief of Staff

This manual supersedes EM 1110-2-2000, 5 September 1985.

Page 6: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

DEPARTMENT OF THE ARMY EM 1110-2-2000US Army Corps of Engineers

CECW-EG Washington, DC 20314-1000

ManualNo. 1110-2-2000 1 February 1994

Engineering and DesignSTANDARD PRACTICE FOR CONCRETE

FOR CIVIL WORKS STRUCTURES

Table of Contents

Subject Paragraph Page Subject Paragraph Page

Chapter 1Introduction and PolicyPurpose . . . . . . . . . . . . . . . . . . . . . . 1-1 1-1Applicability . . . . . . . . . . . . . . . . . . 1-2 1-1References . . . . . . . . . . . . . . . . . . . 1-3 1-1Explanation of Abbreviations. . . . . . . 1-4 1-1Engineering Responsibilities

and Requirements. . . . . . . . . . . . . . 1-5 1-1Reconnaissance phase. . . . . . . . . . 1-5a 1-1Feasibility phase. . . . . . . . . . . . . . 1-5b 1-1Preconstruction engineering and

design phase. . . . . . . . . . . . . . . 1-5c 1-1Construction phase. . . . . . . . . . . . 1-5d 1-1

Delays in Contract Awards. . . . . . . . . 1-6 1-2

Chapter 2Investigation and Selection of MaterialsIntroduction . . . . . . . . . . . . . . . . . . . 2-1 2-1Cementitious Materials . . . . . . . . . . . 2-2 2-1

General . . . . . . . . . . . . . . . . . . . . 2-2a 2-1Types . . . . . . . . . . . . . . . . . . . . . 2-2b 2-1

Portland cement. . . . . . . . . . . . 2-2b(1) 2-1Blended hydraulic cement. . . . . 2-2b(2) 2-1Pozzolan . . . . . . . . . . . . . . . . . 2-2b(3) 2-1GGBF slag . . . . . . . . . . . . . . . 2-2b(4) 2-1Other hydraulic cements. . . . . . 2-2b(5) 2-1Silica fume . . . . . . . . . . . . . . . 2-2b(6) 2-1Air-entraining portland cement . . 2-2b(7) 2-1

Selection of cementitious materials . 2-2c 2-1General . . . . . . . . . . . . . . . . . . 2-2c(1) 2-1Type of structure . . . . . . . . . . . 2-2c(2) 2-1Other requirements. . . . . . . . . . 2-2c(3) 2-2Requirements for use of other

hydraulic cements. . . . . . . . . . 2-2c(4) 2-4Pozzolans . . . . . . . . . . . . . . . . 2-2c(5) 2-4

Availability investigation ofcementitious materials. . . . . . . . 2-2d 2-5General . . . . . . . . . . . . . . . . . . 2-2d(1) 2-5

Portland cement and blendedhydraulic cements. . . . . . . . . . 2-2d(2) 2-5

Pozzolans . . . . . . . . . . . . . . . . 2-2d(3) 2-6GGBF slag . . . . . . . . . . . . . . . 2-2d(4) 2-6Silica fume . . . . . . . . . . . . . . . 2-2d(5) 2-6

Aggregates . . . . . . . . . . . . . . . . . . . 2-3 2-6General . . . . . . . . . . . . . . . . . . . . 2-3a 2-6

Sources of aggregate(Government or commercial) . . 2-3a(1) 2-6

Minor structures. . . . . . . . . . . . 2-3a(2) 2-7Availability investigation. . . . . . . . 2-3b 2-7

General . . . . . . . . . . . . . . . . . . 2-3b(1) 2-7Service records. . . . . . . . . . . . . 2-3b(2) 2-7Field exploration and sampling

of undeveloped sources. . . . . . 2-3b(3) 2-7Field exploration and sampling

of developed sources. . . . . . . 2-3b(4) 2-7Testing potential aggregate

sources . . . . . . . . . . . . . . . . . 2-3b(5) 2-8Evaluating aggregate qualities . . 2-3b(6) 2-8Nominal maximum size

aggregate. . . . . . . . . . . . . . . . 2-3b(7) 2-12Fine aggregate grading

requirements . . . . . . . . . . . . . 2-3b(8) 2-12Required tests and test limits . . . 2-3b(9) 2-13Aggregate processing study. . . . 2-3b(10) 2-13Location of government-furnished

quarry or pit . . . . . . . . . . . . . 2-3b(11) 2-13Water for Mixing and Curing . . . . . . . 2-4 2-14

General . . . . . . . . . . . . . . . . . . . . 2-4a 2-14Mixing water . . . . . . . . . . . . . . . . 2-4b 2-14Curing water . . . . . . . . . . . . . . . . 2-4c 2-14

Chemical Admixtures . . . . . . . . . . . . 2-5 2-14General . . . . . . . . . . . . . . . . . . . . 2-5a 2-14Air-entraining admixtures. . . . . . . 2-5b 2-14

Policy . . . . . . . . . . . . . . . . . . . 2-5b(1) 2-14Strength loss . . . . . . . . . . . . . . 2-5b(2) 2-15

i

Page 7: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table of Contents (Continued)

Subject Paragraph Page Subject Paragraph Page

Bleeding . . . . . . . . . . . . . . . . . 2-5b(3) 2-15Batching AEA . . . . . . . . . . . . . 2-5b(4) 2-15Dosage . . . . . . . . . . . . . . . . . . 2-5b(5) 2-15Effects of water content

on air content . . . . . . . . . . . . 2-5b(6) 2-15Effects of fine aggregate grading

on air content . . . . . . . . . . . . 2-5b(7) 2-15Effects of temperature on

air content . . . . . . . . . . . . . . . 2-5b(8) 2-15Effect of other admixtures

on air content . . . . . . . . . . . . 2-5b(9) 2-15Effect of mixing action on

air content . . . . . . . . . . . . . . . 2-5b(10) 2-15Accelerating admixture. . . . . . . . . 2-5c 2-15

Uses . . . . . . . . . . . . . . . . . . . . 2-5c(1) 2-16Nonchloride admixtures. . . . . . . 2-5c(2) 2-16Effects on fresh concrete

properties . . . . . . . . . . . . . . . 2-5c(3) 2-16Effect on hardened concrete

properties . . . . . . . . . . . . . . . 2-5c(4) 2-16Other methods of accelerating

strength developments. . . . . . . 2-5c(5) 2-16Retarding admixtures. . . . . . . . . . 2-5d 2-16

General uses. . . . . . . . . . . . . . 2-5d(1) 2-16Dosage . . . . . . . . . . . . . . . . . . 2-5d(2) 2-16Batching . . . . . . . . . . . . . . . . . 2-5d(3) 2-17Effect on strength. . . . . . . . . . . 2-5d(4) 2-17

Water-reducing admixtures. . . . . . 2-5e 2-17Use in mass concrete. . . . . . . . 2-5e(1) 2-17Dosage . . . . . . . . . . . . . . . . . . 2-5e(2) 2-17Use in hot or cool weather. . . . . 2-5e(3) 2-17Air entrainment . . . . . . . . . . . . 2-5e(4) 2-17Bleeding . . . . . . . . . . . . . . . . . 2-5e(5) 2-17

High-range water-reducingadmixtures (superplasticizers) . . . 2-5f 2-17Effect on workability . . . . . . . . 2-5f(1) 2-18Effect on segregation and

bleeding . . . . . . . . . . . . . . . . 2-5f(2) 2-18Effect on air entrainment. . . . . . 2-5f(3) 2-18Effect on setting time. . . . . . . . 2-5f(4) 2-18Compatibility with other

admixtures. . . . . . . . . . . . . . . 2-5f(5) 2-18Antiwashout admixtures. . . . . . . . 2-5g 2-18

General . . . . . . . . . . . . . . . . . . 2-5g(1) 2-19Batching . . . . . . . . . . . . . . . . . 2-5g(2) 2-19Air entrainment . . . . . . . . . . . . 2-5g(3) 2-19Bleeding . . . . . . . . . . . . . . . . . 2-5g(4) 2-19Retardation . . . . . . . . . . . . . . . 2-5g(5) 2-19Compatibility . . . . . . . . . . . . . . 2-5g(6) 2-19

Dosage . . . . . . . . . . . . . . . . . . 2-5g(7) 2-19Pumping . . . . . . . . . . . . . . . . . 2-5g(8) 2-19

Extended set-control admixtures . . . 2-5h 2-19General . . . . . . . . . . . . . . . . . . 2-5h(1) 2-19Stabilizer . . . . . . . . . . . . . . . . . 2-5h(2) 2-20Activator . . . . . . . . . . . . . . . . . 2-5h(3) 2-20Effect on hardened properties . . . 2-5h(4) 2-20Dosage . . . . . . . . . . . . . . . . . . 2-5h(5) 2-20

Antifreeze admixtures. . . . . . . . . . 2-5i 2-20Composition. . . . . . . . . . . . . . . 2-5i(1) 2-20Batching . . . . . . . . . . . . . . . . . 2-5i(2) 2-21Effect on strength. . . . . . . . . . . 2-5i(3) 2-21Effect on resistance to freezingand thawing. . . . . . . . . . . . . . . 2-5i(4) 2-21Use with reactive aggregates . . . 2-5i(5) 2-21Corrosion of steel. . . . . . . . . . . 2-5i(6) 2-21Cost benefits . . . . . . . . . . . . . . 2-5i(7) 2-21

Chapter 3Construction Requirements andSpecial StudiesConstruction Requirements . . . . . . . . 3-1 3-1

General . . . . . . . . . . . . . . . . . . . . 3-1a 3-1Batch-plant location. . . . . . . . . . . 3-1b 3-1Batch-plant type. . . . . . . . . . . . . . 3-1c 3-1Mixer type . . . . . . . . . . . . . . . . . . 3-1d 3-1Batching and mixing plant capacity 3-1e 3-2

Monolith size . . . . . . . . . . . . . . 3-1e(1) 3-2Traditional placing method. . . . 3-1e(2) 3-2Equation for minimum placing

capacity . . . . . . . . . . . . . . . . 3-1e(3) 3-2Graphic calculation of minimum

placing capacity. . . . . . . . . . . 3-1e(4) 3-2Other placing methods. . . . . . . 3-1e(5) 3-5

Conveying and placingconsiderations. . . . . . . . . . . . . . 3-1f 3-5

Use of epoxy resins. . . . . . . . . . . 3-1g 3-5Special Studies. . . . . . . . . . . . . . . . . 3-2 3-5

General . . . . . . . . . . . . . . . . . . . . 3-2a 3-5Thermal studies. . . . . . . . . . . . . . 3-2b 3-5

Material properties needed for athermal study. . . . . . . . . . . . . 3-2b(1) 3-5

Time of completion of thermalstudy . . . . . . . . . . . . . . . . . . 3-2b(2) 3-6

Temperature control techniques . 3-2b(3) 3-6Numerical analysis of temperature

control techniques . . . . . . . . . 3-2b(4) 3-6Abrasion-erosion studies. . . . . . . . 3-2c 3-6

General . . . . . . . . . . . . . . . . . . 3-2c(1) 3-6

ii

Page 8: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table of Contents (Continued)

Subject Paragraph Page Subject Paragraph Page

Test method. . . . . . . . . . . . . . . 3-2c(2) 3-6Application of test results. . . . . 3-2c(3) 3-6

Mixer grinding studies . . . . . . . . . 3-2d 3-6Concrete subjected to high velocity

flow of water . . . . . . . . . . . . . . . 3-2e 3-7General . . . . . . . . . . . . . . . . . . 3-2e(1) 3-7Quality of concrete. . . . . . . . . . 3-2e(2) 3-7Construction joints . . . . . . . . . . 3-2e(3) 3-7Unformed surfaces. . . . . . . . . . 3-2e(4) 3-7Formed surfaces. . . . . . . . . . . . 3-2e(5) 3-7

Unusual or complex problems. . . . 3-2f 3-7

Chapter 4Mixture Proportioning ConsiderationsSelection of Concrete Mixture

Proportions. . . . . . . . . . . . . . . . . . . 4-1 4-1Basis for Selection of

Proportions . . . . . . . . . . . . . . . . . . 4-2 4-1General . . . . . . . . . . . . . . . . . . . . 4-2a 4-1Economy. . . . . . . . . . . . . . . . . . . 4-2b 4-1Strength . . . . . . . . . . . . . . . . . . . 4-2c 4-1Durability . . . . . . . . . . . . . . . . . . 4-2d 4-1Placeability . . . . . . . . . . . . . . . . . 4-2e 4-1

Criteria for MixtureProportioning . . . . . . . . . . . . . . . . . 4-3 4-2

General . . . . . . . . . . . . . . . . . . . . 4-3a 4-2Proportioning criteria . . . . . . . . . . 4-3b 4-2

Maximum permissible w/c. . . . . 4-3b(1) 4-2Structural concrete. . . . . . . . . . 4-3b(2) 4-2Mass concrete . . . . . . . . . . . . . 4-3b(3) 4-2Nominal maximum aggregatesize . . . . . . . . . . . . . . . . . . . . . 4-3b(4) 4-5Water content. . . . . . . . . . . . . . 4-3b(5) 4-5Cement content . . . . . . . . . . . . 4-3b(6) 4-6Proportioning with pozzolans

or GGBF slag . . . . . . . . . . . . 4-3b(7) 4-6Government Mixture Proportioning . . . 4-4 4-6

General . . . . . . . . . . . . . . . . . . . . 4-4a 4-6Coordination between project, district

design personnel, and the divisionlaboratory . . . . . . . . . . . . . . . . . 4-4b 4-6

Sampling of materials. . . . . . . . . . 4-4c 4-7Data supplied by division laboratory

to project . . . . . . . . . . . . . . . . . 4-4d 4-7Adjustment of government mixture

proportions . . . . . . . . . . . . . . . . 4-4e 4-7Evaluation of Contractor-Developed

Mixture Proportions. . . . . . . . . . . . . 4-5 4-8General . . . . . . . . . . . . . . . . . . . . 4-5a 4-8

Reviewing contractor submittals . 4-5b 4-8Minor structures. . . . . . . . . . . . 4-5b(1) 4-8Cast-in-place structural concrete . 4-5b(2) 4-8

Chapter 5Preparation of Plans and Specifications

Selection of Guide Specificationfor Concrete . . . . . . . . . . . . . . . . . 5-1 5-1

General . . . . . . . . . . . . . . . . . . . . 5-1a 5-1Guidelines for selection. . . . . . . . . 5-1b 5-1Use of state specifications. . . . . . . 5-1c 5-1Use of abbreviated specifications . . 5-1d 5-1

Guide Specification "Concrete (for MinorStructures)", CW-03307 . . . . . . . . . 5-2 5-1

General . . . . . . . . . . . . . . . . . . . . 5-2a 5-1Cementitious materials options. . . . 5-2b 5-1Selection of compressive strength . . 5-2c 5-1Selection of nominal maximum

aggregate size. . . . . . . . . . . . . . 5-2d 5-1Finish requirements. . . . . . . . . . . 5-2e 5-2

Guide Specification "Cast-in-Place StructuralConcrete," CW-03301. . . . . . . . . . . 5-3 5-2

General . . . . . . . . . . . . . . . . . . . . 5-3a 5-2Testing of cementitious materials . . 5-3b 5-2Admixtures and curing compounds . 5-3c 5-2Testing of aggregate. . . . . . . . . . . 5-3d 5-2Nonshrink grout. . . . . . . . . . . . . . 5-3e 5-2Cementing materials option. . . . . . 5-3f 5-2Specifying aggregate. . . . . . . . . . . 5-3g 5-3Strength . . . . . . . . . . . . . . . . . . . 5-3h 5-3Batch-plant capacity. . . . . . . . . . . 5-3i 5-3Batch-plant controls. . . . . . . . . . . 5-3j 5-3Concrete deposited in water. . . . . . 5-3k 5-3Finishing unformed surfaces. . . . . 5-3l 5-3Sheet curing . . . . . . . . . . . . . . . . 5-3m 5-3Areas to be painted. . . . . . . . . . . . 5-3n 5-3Finishing formed surfaces. . . . . . . 5-3o 5-3Floor tolerance. . . . . . . . . . . . . . . 5-3p 5-3

Guide Specification "Mass Concrete,"CW-03305 . . . . . . . . . . . . . . . . . . . 5-4 5-3

General . . . . . . . . . . . . . . . . . . . . 5-4a 5-3Sampling of aggregates. . . . . . . . . 5-4b 5-4Mixture proportioning studies. . . . 5-4c 5-4Testing cementitious materials. . . . 5-4d 5-4Surface requirements. . . . . . . . . . 5-4e 5-4

Class A finish . . . . . . . . . . . . . 5-4e(1) 5-4Class AHV finish . . . . . . . . . . . 5-4e(2) 5-4Class B finish . . . . . . . . . . . . . 5-4e(3) 5-4

iii

Page 9: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table of Contents (Continued)

Subject Paragraph Page Subject Paragraph Page

Class C finish . . . . . . . . . . . . . 5-4e(4) 5-4Class D finish . . . . . . . . . . . . . 5-4e(5) 5-4Absorptive form lining . . . . . . . 5-4e(6) 5-4

Appearance. . . . . . . . . . . . . . . . . 5-4f 5-4Cementitious materials option. . . . 5-4g 5-4Bid schedule for cementitious materials

option . . . . . . . . . . . . . . . . . . . . 5-4h 5-5Retarder . . . . . . . . . . . . . . . . . . . 5-4i 5-5Water reducers. . . . . . . . . . . . . . . 5-4j 5-5Fine aggregate grading requirements 5-4k 5-5Coarse aggregate grading

requirements. . . . . . . . . . . . . . . 5-4l 5-5Batching and mixing plant. . . . . . . 5-4m 5-5

Type of plant . . . . . . . . . . . . . . 5-4m(1) 5-5Capacity . . . . . . . . . . . . . . . . . 5-4m(2) 5-5Preset mixes . . . . . . . . . . . . . . 5-4m(3) 5-6Mixers . . . . . . . . . . . . . . . . . . 5-4m(4) 5-6

Conveying and placing. . . . . . . . . 5-4n 5-6Conveyance methods. . . . . . . . . 5-4n(1) 5-6Hot-weather mixing and placing . 5-4n(2) 5-6Placing temperature. . . . . . . . . 5-4n(3) 5-6Lift thickness . . . . . . . . . . . . . . 5-4n(4) 5-6Placing concrete in unformed

curved sections . . . . . . . . . . . 5-4n(5) 5-6Concrete deposited in water. . . . 5-4n(6) 5-6

Finishing . . . . . . . . . . . . . . . . . . . 5-4o 5-6Unformed surfaces. . . . . . . . . . 5-4o(1) 5-6Formed surfaces. . . . . . . . . . . . 5-4o(2) 5-6Insulation and special protection . 5-4o(3) 5-6

Areas to be painted. . . . . . . . . . . . 5-4p 5-6Setting of base plates and bearing

plates . . . . . . . . . . . . . . . . . . . . 5-4q 5-6Measurement and payment. . . . . . 5-4r 5-7

Guide Specification "Formwork for Concrete,"CW-03101 . . . . . . . . . . . . . . . . . . . 5-5 5-7

General . . . . . . . . . . . . . . . . . . . . 5-5a 5-7Shop drawings. . . . . . . . . . . . . . . 5-5b 5-7Sample panels. . . . . . . . . . . . . . . 5-5c 5-7Forms . . . . . . . . . . . . . . . . . . . . . 5-5d 5-7Form removal . . . . . . . . . . . . . . . 5-5e 5-7

Guide Specification "Expansion, Contraction,and Construction Joints in Concrete,"CW-03150 . . . . . . . . . . . . . . . . . . . 5-6 5-7

General . . . . . . . . . . . . . . . . . . . . 5-6a 5-7Cost of testing. . . . . . . . . . . . . . . 5-6b 5-7

Guide Specification "Precast PrestressedConcrete," CW-03425. . . . . . . . . . . 5-7 5-7

General . . . . . . . . . . . . . . . . . . . . 5-7a 5-7

Air content . . . . . . . . . . . . . . . . . 5-7b 5-7Tolerances. . . . . . . . . . . . . . . . . . 5-7c 5-7Cement . . . . . . . . . . . . . . . . . . . . 5-7d 5-7Aggregates . . . . . . . . . . . . . . . . . 5-7e 5-7Finishing . . . . . . . . . . . . . . . . . . . 5-7f 5-7

Guide Specification "Preplaced AggregateConcrete," CW-03362. . . . . . . . . . . 5-8 5-7

Chapter 6Coordination Between Design andField ActivitiesBidability, Constructibility, and

Operability Review . . . . . . . . . . . . . 6-1 6-1General . . . . . . . . . . . . . . . . . . . . 6-1a 6-1Review guidance. . . . . . . . . . . . . 6-1b 6-1

Engineering Considerations and Instructionsfor Construction Field Personnel . . . 6-2 6-1

General . . . . . . . . . . . . . . . . . . . . 6-2a 6-1Content . . . . . . . . . . . . . . . . . . . . 6-2b 6-1Discussion by outline heading. . . . 6-2c 6-2

Introduction . . . . . . . . . . . . . . . 6-2c(1) 6-2Cementitious materials requirements

or properties . . . . . . . . . . . . . 6-2c(2) 6-2Aggregate requirements or

properties . . . . . . . . . . . . . . . 6-2c(3) 6-2Other materials. . . . . . . . . . . . . 6-2c(4) 6-2Concrete qualities required at various

locations within the structures . 6-2c(5) 6-2Concrete temperature-control

requirements . . . . . . . . . . . . . 6-2c(6) 6-3Cold-weather concrete

requirements . . . . . . . . . . . . . 6-2c(7) 6-3Hot-weather concrete

requirements . . . . . . . . . . . . . 6-2c(8) 6-3Contractor quality control and quality

government assurance. . . . . . . 6-2c(9) 6-3Critical concrete placement

requirements . . . . . . . . . . . . . 6-2c(10) 6-3Architectural requirements. . . . . 6-2c(11) 6-3Finish requirements. . . . . . . . . . 6-2c(12) 6-3

Chapter 7Preparation for ConstructionMaterials Acceptance Testing. . . . . . . 7-1 7-1

General . . . . . . . . . . . . . . . . . . . . 7-1a 7-1Cement, pozzolan, and GGBF slag . 7-1b 7-1Chemical admixtures . . . . . . . . . . 7-1c 7-1

Test of air-entraining admixtures 7-1c(1) 7-1

iv

Page 10: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table of Contents (Continued)

Subject Paragraph Page Subject Paragraph Page

Test of other chemicaladmixtures. . . . . . . . . . . . . . . . 7-1c(2) 7-2Tests of accelerators. . . . . . . . . 7-1c(3) 7-2

Aggregates - listed source. . . . . . . 7-1d 7-2Aggregates - nonlisted source. . . . 7-1e 7-2Aggregates - minor concrete jobs . . 7-1f 7-2

Mixture Proportioning . . . . . . . . . . . . 7-2 7-2Concrete Plant and Materials. . . . . . . 7-3 7-3

Review of concrete plant drawings . 7-3a 7-3Estimating plant capacity. . . . . . . . 7-3b 7-3Aggregate storage, reclaiming, washing,

and rescreening. . . . . . . . . . . . . 7-3c 7-3Concrete cooling plant capacity . . . 7-3d 7-4

Batching and Mixing Equipment . . . . 7-4 7-4Checking compliance with specification

requirements. . . . . . . . . . . . . . . 7-4a 7-4Scale checks. . . . . . . . . . . . . . . . 7-4b 7-4Mixer blades and paddles. . . . . . . 7-4c 7-4Recorders . . . . . . . . . . . . . . . . . . 7-4d 7-4Batching sequence. . . . . . . . . . . . 7-4e 7-4Mixer performance andmixing time . . . . . . . . . . . . . . . . . 7-4f 7-4

Conveying Concrete . . . . . . . . . . . . . 7-5 7-5General . . . . . . . . . . . . . . . . . . . . 7-5a 7-5Buckets. . . . . . . . . . . . . . . . . . . . 7-5b 7-5Truck mixers and agitators. . . . . . 7-5c 7-5Nonagitating equipment. . . . . . . . 7-5d 7-5Positive-displacement pump. . . . . . 7-5e 7-5Belts . . . . . . . . . . . . . . . . . . . . . . 7-5f 7-5Chutes . . . . . . . . . . . . . . . . . . . . 7-5g 7-5

Preparation for Placing . . . . . . . . . . . 7-6 7-6General . . . . . . . . . . . . . . . . . . . . 7-6a 7-6Earth foundations. . . . . . . . . . . . . 7-6b 7-6Rock foundations. . . . . . . . . . . . . 7-6c 7-6Cleanup of concrete surfaces. . . . . 7-6d 7-6Placing equipment. . . . . . . . . . . . 7-6e 7-6

Vibrators . . . . . . . . . . . . . . . . . 7-6e(1) 7-6Cold-weather and hot-weather

protection equipment . . . . . . . 7-6e(2) 7-6Communication equipment. . . . . 7-6e(3) 7-6Other equipment. . . . . . . . . . . . 7-6e(4) 7-7

Forms . . . . . . . . . . . . . . . . . . . . . 7-6f 7-7Curing and protection. . . . . . . . . . 7-6g 7-7Approval . . . . . . . . . . . . . . . . . . . 7-6h 7-7Interim slabs on grade. . . . . . . . . . 7-6i 7-7

Chapter 8Concrete ConstructionForms . . . . . . . . . . . . . . . . . . . . . . . 8-1 8-1

Types of materials. . . . . . . . . . . . 8-1a 8-1Quality verification . . . . . . . . . . . . 8-1b 8-1Form coating . . . . . . . . . . . . . . . . 8-1c 8-1

Placing . . . . . . . . . . . . . . . . . . . . . . 8-2 8-1General . . . . . . . . . . . . . . . . . . . . 8-2a 8-1Bedding mortar on rock foundations 8-2b 8-1Mass concrete. . . . . . . . . . . . . . . 8-2c 8-1Structural concrete. . . . . . . . . . . . 8-2d 8-2Tunnel linings . . . . . . . . . . . . . . . 8-2e 8-2

Inverts . . . . . . . . . . . . . . . . . . . 8-2e(1) 8-2Sidewalls and crown. . . . . . . . . 8-2e(2) 8-2

Consolidation. . . . . . . . . . . . . . . . 8-2f 8-2Protection of waterstops. . . . . . . . 8-2g 8-2

Finishing . . . . . . . . . . . . . . . . . . . . . 8-3 8-2Formed surfaces. . . . . . . . . . . . . . 8-3a 8-2Unformed surfaces. . . . . . . . . . . . 8-3b 8-3

Ogee crest. . . . . . . . . . . . . . . . 8-3b(1) 8-3Spillway aprons . . . . . . . . . . . . 8-3b(2) 8-3Trapezoidal channel lining. . . . . 8-3b(3) 8-3Surfaces exposed to high-velocity

flow of water . . . . . . . . . . . . . 8-3b(4) 8-3Floors . . . . . . . . . . . . . . . . . . . 8-3b(5) 8-4

Tolerance requirements for surfacefinish . . . . . . . . . . . . . . . . . . . . 8-3c 8-4General . . . . . . . . . . . . . . . . . . 8-3c(1) 8-4Control surface tolerance by

straightedge. . . . . . . . . . . . . . 8-3c(2) 8-4Control floor tolerance by F-number

system . . . . . . . . . . . . . . . . . 8-3c(3) 8-4Curing . . . . . . . . . . . . . . . . . . . . . . . 8-4 8-5

General . . . . . . . . . . . . . . . . . . . . 8-4a 8-5Moist curing . . . . . . . . . . . . . . . . 8-4b 8-5Membrane curing. . . . . . . . . . . . . 8-4c 8-5Sheet curing . . . . . . . . . . . . . . . . 8-4d 8-5

Cold-Weather Concreting. . . . . . . . . . 8-5 8-6General . . . . . . . . . . . . . . . . . . . . 8-5a 8-6Planning . . . . . . . . . . . . . . . . . . . 8-5b 8-6Protection system. . . . . . . . . . . . . 8-5c 8-6Curing . . . . . . . . . . . . . . . . . . . . 8-5d 8-6Accelerating early strength. . . . . . 8-5e 8-7

Hot-Weather Concreting. . . . . . . . . . . 8-6 8-7General . . . . . . . . . . . . . . . . . . . . 8-6a 8-7Planning . . . . . . . . . . . . . . . . . . . 8-6b 8-7Alleviating measures. . . . . . . . . . . 8-6c 8-7Placing temperature. . . . . . . . . . . 8-6d 8-8Plastic-shrinkage cracks. . . . . . . . 8-6e 8-8Effect on strength and durability . . 8-6f 8-8Cooling . . . . . . . . . . . . . . . . . . . . 8-6g 8-9Curing . . . . . . . . . . . . . . . . . . . . 8-6h 8-9

v

Page 11: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table of Contents (Continued)

Subject Paragraph Page Subject Paragraph Page

Chapter 9Concrete Quality Verification and TestingQuality verification . . . . . . . . . . . . . . 9-1 9-1

General . . . . . . . . . . . . . . . . . . . . 9-1a 9-1Government quality assurance. . . . 9-1b 9-1

Quality assurance representative . 9-1b(1) 9-1Testing technicians. . . . . . . . . . 9-1b(2) 9-1Organization . . . . . . . . . . . . . . 9-1b(3) 9-2Records. . . . . . . . . . . . . . . . . . 9-1b(4) 9-2

Required Sampling and Testingfor CQC and GQC . . . . . . . . . . 9-2 9-3

Aggregate grading. . . . . . . . . . . . 9-2a 9-3Frequency . . . . . . . . . . . . . . . . 9-2a(1) 9-3Size of samples. . . . . . . . . . . . 9-2a(2) 9-3

Aggregate quality - large project . . 9-2b 9-4Free moisture on aggregates. . . . . 9-2c 9-4Slump and air content. . . . . . . . . . 9-2d 9-4Concrete temperature. . . . . . . . . . 9-2e 9-4Compressive strength. . . . . . . . . . 9-2f 9-4

Purpose. . . . . . . . . . . . . . . . . . 9-2f(1) 9-4Testing responsibility . . . . . . . . 9-2f(2) 9-5Sampling plan . . . . . . . . . . . . . 9-2f(3) 9-5Frequency and testing age. . . . . 9-2f(4) 9-5Sampling and testing methods . . 9-2f(5) 9-5Analysis of tests. . . . . . . . . . . . 9-2f(6) 9-5Control criteria . . . . . . . . . . . . . 9-2f(7) 9-6Prediction of later age strengths . 9-2f(8) 9-6

Nondestructive Testing. . . . . . . . . . . . 9-3 9-7General . . . . . . . . . . . . . . . . . . . . 9-3a 9-7Policy . . . . . . . . . . . . . . . . . . . . . 9-3b 9-7Applicability . . . . . . . . . . . . . . . . 9-3c 9-7Nondestructive testing methods . . . 9-3d 9-7

Rebound hammer. . . . . . . . . . . 9-3d(1) 9-7Penetration resistance. . . . . . . . 9-3d(2) 9-7Cast-in-place pullout tests. . . . . 9-3d(3) 9-8Maturity method. . . . . . . . . . . . 9-3d(4) 9-8Cores . . . . . . . . . . . . . . . . . . . 9-3d(5) 9-8Pulse velocity method. . . . . . . . 9-3d(6) 9-8Other methods. . . . . . . . . . . . . 9-3d(7) 9-9

Preplacement Quality Verification. . . . 9-4 9-9Project Laboratory . . . . . . . . . . . . . . 9-5 9-9

General . . . . . . . . . . . . . . . . . . . . 9-5a 9-9Space requirements. . . . . . . . . . . . 9-5b 9-9

Large-volume project . . . . . . . . 9-5b(1) 9-9Other . . . . . . . . . . . . . . . . . . . 9-5b(2) 9-9

Equipment. . . . . . . . . . . . . . . . . . 9-5c 9-9Large-volume project . . . . . . . . 9-5c(1) 9-9Other . . . . . . . . . . . . . . . . . . . 9-5c(2) 9-10

Chapter 10Special ConcretesGeneral. . . . . . . . . . . . . . . . . . . . . . . 10-1 10-1Preplaced-Aggregate Concrete. . . . . . . 10-2 10-1

General . . . . . . . . . . . . . . . . . . . . 10-2a 10-1Applications . . . . . . . . . . . . . . . . 10-2b 10-1Materials and proportioning. . . . . . 10-2c 10-1Preplacing aggregate. . . . . . . . . . . 10-2d 10-2Contaminated water. . . . . . . . . . . 10-2e 10-2Preparation of underwater

foundations . . . . . . . . . . . . . . . . 10-2f 10-2Pumping . . . . . . . . . . . . . . . . . . . 10-2g 10-2Joint construction. . . . . . . . . . . . . 10-2h 10-2Grouting procedure. . . . . . . . . . . . 10-2i 10-3

Horizontal layer . . . . . . . . . . . . 10-2i(1) 10-3Advancing slope. . . . . . . . . . . . 10-2i(2) 10-3Grout insert pipes and sounding

devices . . . . . . . . . . . . . . . . . 10-2i(3) 10-3Finishing unformed surfaces. . . . . 10-2j 10-3

Underwater Concrete. . . . . . . . . . . . . 10-3 10-3General . . . . . . . . . . . . . . . . . . . . 10-3a 10-3Tremie concrete. . . . . . . . . . . . . . 10-3b 10-4Pumped concrete for use

underwater . . . . . . . . . . . . . . . . 10-3c 10-4Blockout Concrete. . . . . . . . . . . . . . . 10-4 10-5

General . . . . . . . . . . . . . . . . . . . . 10-4a 10-5Blockout concrete proportions. . . . 10-4b 10-5

High-Strength Concrete. . . . . . . . . . . 10-5 10-5General . . . . . . . . . . . . . . . . . . . . 10-5a 10-5Definition . . . . . . . . . . . . . . . . . . 10-5b 10-5Materials . . . . . . . . . . . . . . . . . . . 10-5c 10-5Cement type . . . . . . . . . . . . . . . . 10-5d 10-5Cement content. . . . . . . . . . . . . . 10-5e 10-6Aggregates . . . . . . . . . . . . . . . . . 10-5f 10-6Pozzolans . . . . . . . . . . . . . . . . . . 10-5g 10-6Use of HRWRA. . . . . . . . . . . . . . 10-5h 10-6Workability . . . . . . . . . . . . . . . . . 10-5i 10-6Proportioning. . . . . . . . . . . . . . . . 10-5j 10-6Material handling. . . . . . . . . . . . . 10-5k 10-6Preparation for placing. . . . . . . . . 10-5l 10-7Curing . . . . . . . . . . . . . . . . . . . . 10-5m 10-7Testing . . . . . . . . . . . . . . . . . . . . 10-5n 10-7

Pumped Concrete. . . . . . . . . . . . . . . . 10-6 10-7General . . . . . . . . . . . . . . . . . . . . 10-6a 10-7Pump lines . . . . . . . . . . . . . . . . . 10-6b 10-7Mixture proportions . . . . . . . . . . . 10-6c 10-7Coarse aggregates. . . . . . . . . . . . . 10-6d 10-7

vi

Page 12: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table of Contents (Continued)

Subject Paragraph Page Subject Paragraph Page

Fine aggregates. . . . . . . . . . . . . . 10-6e 10-8Slump . . . . . . . . . . . . . . . . . . . . . 10-6f 10-8Admixtures . . . . . . . . . . . . . . . . . 10-6g 10-8Pumpability tests . . . . . . . . . . . . . 10-6h 10-8Planning . . . . . . . . . . . . . . . . . . . 10-6i 10-8Other requirements. . . . . . . . . . . . 10-6j 10-8Quality verification . . . . . . . . . . . . 10-6k 10-8

Fiber-Reinforced Concrete. . . . . . . . . 10-7 10-9General . . . . . . . . . . . . . . . . . . . . 10-7a 10-9Advantages and limitations. . . . . . 10-7b 10-9Toughness. . . . . . . . . . . . . . . . . . 10-7c 10-9Performance characteristics. . . . . . 10-7d 10-9Mixture proportioning. . . . . . . . . . 10-7e 10-9Batching and mixing. . . . . . . . . . . 10-7f 10-9Placement . . . . . . . . . . . . . . . . . . 10-7g 10-10Workability . . . . . . . . . . . . . . . . . 10-7h 10-10Pumping . . . . . . . . . . . . . . . . . . . 10-7i 10-10Other fibers . . . . . . . . . . . . . . . . . 10-7j 10-10Effects of polypropylene fibers

on workability . . . . . . . . . . . . . . 10-7k 10-10Use of polypropylene fibers. . . . . . 10-7l 10-10

Porous Concrete. . . . . . . . . . . . . . . . 10-8 10-10General . . . . . . . . . . . . . . . . . . . . 10-8a 10-10Types . . . . . . . . . . . . . . . . . . . . . 10-8b 10-10Composition . . . . . . . . . . . . . . . . 10-8c 10-11W/C considerations. . . . . . . . . . . . 10-8d 10-11Durability . . . . . . . . . . . . . . . . . . 10-8e 10-11Percent voids. . . . . . . . . . . . . . . . 10-8f 10-11Proportioning porous concrete

mixtures . . . . . . . . . . . . . . . . . . 10-8g 10-11Placement . . . . . . . . . . . . . . . . . . 10-8h 10-11

Flowing Concrete. . . . . . . . . . . . . . . . 10-9 10-11General . . . . . . . . . . . . . . . . . . . . 10-9a 10-11HRWRA . . . . . . . . . . . . . . . . . . . 10-9b 10-12Proportioining flowing concrete . . . 10-9c 10-12Flowing concrete fresh properties . . 10-9d 10-12Flowing concrete hardened

properties . . . . . . . . . . . . . . . . . 10-9e 10-12Silica-Fume Concrete. . . . . . . . . . . . . 10-10 10-12

General . . . . . . . . . . . . . . . . . . . . 10-10a 10-12Properties of silica fume. . . . . . . . 10-10b 10-12Effect on water demand and

bleeding . . . . . . . . . . . . . . . . . . 10-10c 10-12Effect on cohesiveness. . . . . . . . . 10-10d 10-13Effect on air entrainment. . . . . . . . 10-10e 10-13Effect on plastic shrinkage. . . . . . 10-10f 10-13Effect on strength and modulus

of elasticity . . . . . . . . . . . . . . . . 10-10g 10-13Effect on permeability and durability 10-10h 10-13

Chapter 11Concrete Report

General. . . . . . . . . . . . . . . . . . . . . . . 11-1 11-1Policy . . . . . . . . . . . . . . . . . . . . . 11-1a 11-1Author . . . . . . . . . . . . . . . . . . . . 11-1b 11-1Timing . . . . . . . . . . . . . . . . . . . . 11-1c 11-1

Content. . . . . . . . . . . . . . . . . . . . . . . 11-2 11-1Outline . . . . . . . . . . . . . . . . . . . . 11-2a 11-1Detailed instruction. . . . . . . . . . . . 11-2b 11-1

Introduction . . . . . . . . . . . . . . . 11-2b(1) 11-1Aggregate sources. . . . . . . . . . . 11-2b(2) 11-1Aggregate production. . . . . . . . 11-2b(3) 11-1Cementitious materials. . . . . . . 11-2b(4) 11-4Chemical admixtures. . . . . . . . . 11-2b(5) 11-4Concrete batching and mixing

plant . . . . . . . . . . . . . . . . . . . 11-2b(6) 11-4Concrete mixtures used. . . . . . . 11-2b(7) 11-4Equipment and techniques. . . . . 11-2b(8) 11-4Concrete transportation and

placement . . . . . . . . . . . . . . . 11-2b(9) 11-4Concrete curing and protection . . 11-2b(10) 11-4Temperature control. . . . . . . . . 11-2b(11) 11-4Special concretes. . . . . . . . . . . 11-2b(12) 11-4Precast concrete. . . . . . . . . . . . 11-2b(13) 11-4Quality verification and testing . . 11-2b(14) 11-4Summary of test data. . . . . . . . 11-2b(15) 11-4Special problems. . . . . . . . . . . 11-2b(16) 11-5

Appendix AReferences

Appendix BAbbreviations

Appendix CConcrete Materials Design Memorandum

Appendix DAlkali-Silica Aggregate Reactions

Appendix EAlkali-Carbonate Rock Reactions

vii

Page 13: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 1Introduction

1-1. Purpose

The purpose of this manual is to provide information andguidance for the investigation and selection of concretematerials for civil works concrete structures. Elementsdiscussed include design studies and reports, preparation ofcontract plans and specifications, construction preparation,and concrete construction quality verification. Emphasis isplaced on the problems of concrete for hydraulic structures.Roller-compacted concrete, shotcrete, rigid pavements,architectural concrete, and concrete for repairs are notincluded. These subjects are discussed in EM 1110-2-2006,Roller-Compacted Concrete; EM 1110-2-2005, StandardPractice for Shotcrete; TM 5-822-7, Standard Practice forConcrete Pavements; EM 1110-1-2009, ArchitecturalConcrete; and EM 1110-2-2002, Evaluation and Repair ofConcrete Structures, respectively.

1-2. Applicability

This manual is applicable to all HQUSACE elements, majorsubordinate commands, districts, laboratories, and fieldoperating activities having civil works responsibilities.

1-3. References

Applicable references are listed in Appendix A. The mostcurrent versions of all references listed in paragraphs A-1and A-2 should be maintained in all districts and divisionshaving civil works responsibilities. The references shouldbe maintained in a location readily accessible to thosepersons assigned the responsibility for concrete materialsinvestigations and concrete construction. Terms used in thisdocument are defined in ACI 116R.

1-4. Explanation of Abbreviations

Abbreviations used in this manual are explained inAppendix B.

1-5. Engineering Responsibilities andRequirements

This paragraph outlines the concrete-related engineeringresponsibilities and requirements during the development ofa civil works project. A summary of these engineeringrequirements is presented in Table 1-1. Deviations from therequirements described in this paragraph are possible, and

such an option as progression from a feasibility reportdirectly to plans and specifications may be permissible.Requests for exceptions or deviations should be made inaccordance with ER 1110-2-1150.

a. Reconnaissance phase.Concrete investigation isgenerally not required during the reconnaissance phase.However, the engineering effort and budget required forconcrete investigation during the feasibility phase should beidentified and included in the Feasibility Cost-SharingAgreement (FCSA).

b. Feasibility phase.During the feasibility phase, apreliminary investigation, in accordance with therequirements given in Chapter 2, should be conducted todetermine the potential sources and suitability of concretematerials. The engineering effort during this phase shouldbe sufficient so that the baseline cost estimate withreasonable contingency factors for concrete materials can bedeveloped. The potential sources and suitability of concretematerials for the project should be documented in theengineering appendix to the feasibility report (or in ageneral design memorandum (GDM)) in accordance withER 1110-2-1150, Engineering and Design for Civil WorksProjects. Any special studies required during thepreconstruction engineering and design (PED) phase shouldbe identified. These special studies may include, but not belimited to, thermal studies, abrasion-erosion studies, mixergrinding studies, and cavitation studies. The budget andschedules for these special studies and for the concretereport should be included in the project management plan(PMP).

c. Preconstruction engineering and designphase. During the PED phase and prior to the preparationof plans and specifications (P&S), a detailed engineeringinvestigation on concrete materials, including cementitiousmaterials, aggregates, water for mixing and curing, andchemical admixtures, should be conducted in accordancewith the requirements given in Chapter 2. Concrete mixtureproportioning and concrete construction procedures shouldbe investigated in accordance with pertinent requirements inChapters 4 and 7, respectively. The results of theseinvestigations should be documented in a concrete/materialsdesign memorandum (DM). The scope and format for theDM will vary depending on the quantities and criticality ofconcrete involved as outlined in Appendix C. Any specialstudies identified in the feasibility phase should be carriedout during the PED. The concrete plans and specificationsshould be prepared in accordance with Chapter 5. For anyproject which includes major concrete construction, a reportoutlining the engineering considerations and providing

1-1

Page 14: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 1-1

Concrete-Related Engineering Responsibilities and Requirements

Phase Engineering Efforts Document

Reconnaissance Identify engineering efforts and budget

required for concrete investigation

during the feasibility phase

Input to FCSA

Feasibility Preliminary investigations to determine

the potential sources and suitability of

concrete materials

Engineering appendix to Feasibility Report or

GDM

Identify the engineering requirements,

budget, and schedules for the special

studies required during PED.

Engineering appendix to Feasibility Report (or

GDM) and PMP

PED Detailed investigations on concrete

materials, preliminary mixture

proportioning, and concrete construction

procedures

Concrete materials DM

Perform special studies DM or special study reports

Prepare concrete P&S ’s P&S

Prepare engineering considerations and

instructions for field personnel

Report

Construction Develop, adjust, or evaluate mixture

proportions

Site visits and QV

Support for concrete claims and

modifications

Prepare concrete report Concrete Report

instruction for field personnel to aid them in the supervisionand quality verification (QV) of concrete constructionshould be prepared in accordance with Chapter 6.

d. Construction phase.Engineering effort during theconstruction phase generally includes development,adjustment or evaluation of mixture proportions, or both,site visits and QV, support for concrete claims andmodifications, and preparation of a concrete report. Theconcrete construction QV requirements are given inChapter 9. The guidelines for preparing a concrete reportcan be found in Chapter 11.

1-6. Delays in Contract Awards

If delays of 5 years or longer occur between the time ofcompletion of the relevant concrete materials DM and thestart of construction, it will be necessary to reconfirm thevalidity of the findings of the DM immediately prior to theissuance of P&S’s to prospective bidders. The availabilityof the types and sources of cementitious materials should berechecked. If changes have occurred, it may be necessaryto conduct tests to determine the suitability of the currentlyavailable cementitious materials in combination with theavailable aggregates and present findings in supplements to

1-2

Page 15: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

the earlier concrete materials DM. Aggregate sources thathave not been used in the period between the aggregateinvestigations and the preparation for the contract awardmay be assumed to remain acceptable. Commercialaggregates sources that have been used should be examinedto verify that adequate materials remain in the pit or quarryand that the lithology has not changed as materials have

been removed. If significant changes have occurred, theyshould be confirmed petrographically. Depending on theresults of the petrographic examination, it may be necessaryto reevaluate the aggregate source for suitability. Theresults of such a reevaluation should be presented as asupplement to the earlier concrete materials DM.

1-3

Page 16: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-2000Change 131 Jul 94

Chapter 2Investigation and Selection of Materials

2-1. Introduction

During the investigations for a civil works structure thatincorporates concrete, it is necessary to assess theavailability and suitability of the materials needed tomanufacture concrete with qualities meeting the structuraland durability requirements. Materials involved includecementitious materials, fine aggregate, coarse aggregate,water for mixing and curing, and chemical admixtures.These investigations will result in a separate DM or aportion of a DM, in accordance with Appendix C.

2-2. Cementitious Materials

a. General. The goal of the investigation ofcementitious materials should be to determine the suitabilityand availability of the various types of cement, pozzolan,and ground granulated blast-furnace (GGBF) slag for thestructures involved and to select necessary options that maybe needed with the available aggregates. In cases wheretypes or quantities of available cementitious materials areunusually limited, it may be necessary to consider alteredstructural shapes, changing the types of structure, alteredconstruction sequence, imported aggregates, or other meansof achieving an economical, serviceable structure.

b. Types. The following types of cementitiousmaterial should be considered when selecting the materials:

(1) Portland cement. Portland cement and air-entraining portland cement are described in AmericanSociety for Testing and Materials (ASTM) C 150(CRD-C 201).

(2) Blended hydraulic cement. The types of blendedhydraulic cements are described in ASTM C 595(CRD-C 203). ASTM Type I (PM) shall not be used;reference paragraph 4-3b(7) of this manual.

(3) Pozzolan. Coal fly ash and natural pozzolan areclassified and defined in ASTM C 618 (CRD-C 255).

(4) GGBF slag. GGBF slag is described in ASTM C989 (CRD-C 205).* Test methods cited in this manner are from the American Society forTesting and MaterialsAnnual Book of ASTM Standards(ASTM 1992)and from Handbook of Concrete and Cement(U.S. Army EngineerWaterways Experiment Station (USAEWES) 1949), respectively.

(5) Other hydraulic cements.

(a) Expansive hydraulic cement. Expansive hydrauliccements are described in ASTM C 845 (CRD-C 204).

(b) Calcium-aluminate cement. Calcium-aluminatecements (also called high-alumina cement) are characterizedby a rapid strength gain, high resistance to sulfate attack,resistance to acid attack, and resistance to high temperatures.However, strength is lost at mildly elevated temperatures(e.g. >85 °F) in the presence of moisture. This negativefeature makes calcium-aluminate cement impractical formost construction. It is used predominantly in themanufacture of refractory materials.

(c) Proprietary high early-strength cements. Cementsare available that gain strength very rapidly, sometimesreaching compressive strengths of several thousand poundsper square in. (psi) in a few hours. These cements aremarketed under various brand names. They are often notwidely available, and the cost is much higher than portlandcement. The extremely rapid strength gain makes themparticularly suitable for pavement patching.

(6) Silica fume. Silica fume is a pozzolan. It is abyproduct of silicon and ferro-silicon alloy production.Silica fume usually contains about 90 percent SiO2 inmicroscopic particles in the range of 0.1 to 0.2 µm. Theseproperties make it an efficient filler as well as a veryreactive pozzolan. Silica fume combined with a high-range

* water reducer is used in very high-strength concrete. Silicafume is described in ASTM C1240 (CRD-C270). Detailedinformation can be found in paragraphs 2-2d(5) and 10-10.*

(7) Air-entraining portland cement. Air-entrainingportland cement is only allowed for use on structures co-vered by the specifications for "Concrete for Minor Struc-tures," CW-03307. Air-entraining admixtures are used onall other Corps civil works structures since this allows theair content to be closely controlled and varied if need be.

c. Selection of cementitious materials.

(1) General. The selection of one or several suitablecementitious materials for a concrete structure depends onthe exposure conditions, the type of structure, thecharacteristics of the aggregate, availability of thecementitious material, and the method of construction.

(2) Type of structure. The type of structure, i.e. massor structural, provides an indication of the category of

2-1

Page 17: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

concrete that the structure may contain. Mass concrete isdefined as any volume of concrete with dimensions largeenough to require that measures be taken to cope withgeneration of heat from hydration of the cementitiousmaterials and attendant volume change to minimizecracking. A gravity dam and a navigation lock areexamples of massive structures. Structural concrete isdefined as concrete which will normally be placed inreinforced structural elements such as beams, columns,walls, and slabs that have dimensions such that heatgeneration is not a problem. Many features of a structurewill fall between the two extremes of being either strictlymassive or structural, and the designer will need to decideif measures to limit or mitigate the heat generation will berequired. For example, reinforced walls and slabs of 4- to6-ft thickness in a pumping station that contains 3,000- to5,000-psi concrete would probably generate sufficient heatthat measures should be taken to limit either the peaktemperature of the concrete or the rate at which heat is lostfrom the concrete after the peak temperature is reached.The factors that affect the amount of heat that is generatedand the peak temperature that the concrete will reach are theamount and type of cementitious materials in the concrete,the size of the placement, and the initial placingtemperature.

(a) Table 2-1 lists cementitious materials that shouldbe investigated for availability and suitability, according tothe type of structure. Other more specialized cementitiousmaterials, such as Type V portland cement or proprietaryhigh-early strength cement, should be investigated if needed.

(b) Specification details. Type II cement is describedby ASTM C 150 (CRD-C 201) as a cement for use whenmoderate sulfate resistance or moderate heat of hydration isdesired. The heat-of-hydration part of this descriptionrequires that the 70-calorie/gram optional limit be specified.Many Type II cements evolve heat at rates comparable tothose of Type I cements. The chemical requirement whichis in ASTM C 150 for the purpose of limiting heats ofhydration is not a satisfactory means of assuring reducedheat of hydration and should not be used. Neither Type IVportland cement nor Type P portland-pozzolan cement aregenerally available at the present time. Both also exhibitvery low rates of strength gain. These characteristics shouldbe addressed in the concrete materials DM prior tospecifying either type. ASTM C 989 (CRD-C 205) includesa provision for three grades of GGBF slag, grade 120,which contributes to the fastest strength development, grade100 which is an intermediate grade, and grade 80 whichcontributes least to strength development. However, atpresent, only grade 120 is available. Generally, if othergrades were available, grade 80, 100, or 120 should be

considered for use in mass concrete, and grades 100 and120 should be considered for use in structural concrete.

(3) Other requirements.

(a) General. The investigation of cementitiousmaterials must include an assessment of the impact on costand availability of special requirements or options.Provisions that limit the heat of hydration, provide sulfateresistance, limit the alkali content, or control false set shouldbe invoked based on a demonstrated need for cement havingthese characteristics.

(b) Sulfate exposures. Precautions against thepotentially harmful effects of sulfate will be specified whenconcrete is to be exposed to seawater or the concentrationof water-soluble sulfate (SO4) in soil or in fresh water thatwill be in contact with the concrete (as determined byCRD-C 403 and 408) is greater than 0.10 percent or 150parts per million (ppm,) respectively. Concentrations higherthan these will be classified as representingmoderateorseverepotential exposures according to the criteria shown inTable 2-2. The precautions to be specified will vary withthe availability and anticipated costs of materials and withother factors. Where moderate attack is to be resisted,moderate sulfate-resisting cement (Type II, Type III with theoptional 8 percent limit on C3A invoked, Type IP(MS),Type IS(MS), or Type P(MS)) should be specified. Inseawater where no greater precautions than moderate areneeded, the 8-percent limit on C3A may be increased to 10percent if the water-cement ratio (w/c) of the concrete iskept below 0.45 by mass and the concrete will bepermanently submerged in seawater. If moderate sulfate-resisting cement is not economically available, concrete thatis resistant to moderate attack may be made by using TypeI cement having not more than 10 percent C3A or Types ISor IP which contain an adequate amount of suitable Class Fpozzolan or slag or to which additional Class F pozzolan orslag is added. Performance tests must be conducted todetermine the suitability of any substitutes for sulfate-resistant cement. If straight portland cement is proposed,the test method is described in ASTM C 452 (CRD-C 232).If a blend of portland cement and pozzolan or a blendedhydraulic cement is proposed, the test method is ASTM C1012 (CRD-C 211). Where severe attack is to be resisted,highly sulfate-resistant cement (Type V, Type III with5 percent limit on C3A) should be specified and used unlessproblems of cost or availability are encountered, in whichcase other materials as outlined above should be taken.Additional information may be obtained from AmericanConcrete Institute (ACI) 201.2R.

2-2

Page 18: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 2-1

Guide for Selection of Cementitious Materials According to Type Structure

Cementitious Material Mass Concrete Structural Concrete

Portland cement:

Type I X

Type II X X

Type II with heat of

hydration 70 cal/g or less

X X

Type I with pozzolan X

Type II with pozzolan X X

Type I with GGBF slag X

Type II with GGBF slag X X

Type III X

Type IV X

Blended hydraulic cements:

Type IS(MH) X X

Type IS X

Type IP(MH) X X

Type IP X

Type P X

Type P(LH) X

Type I(SM) X

Type I(SM), (MH) X

Type S, with Type I or Type II

Portland cement

X

Table 2-2

Guide for Determining Sulfate Exposure Condition

Exposure condition

SO4 concentration,

Fresh water

SO4 concentration,

Soil, %

Moderate 150 - 1,500 ppm 0.10 - 0.20

Severe >1,500 ppm >0.20

2-3

Page 19: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(c) False set. False set is one type of the abnormalpremature stiffening of cement within a few minutes ofmixing with water. Remixing of the concrete after a fewminutes of maintaining the mixer at rest or a longer initialmixing time will restore the plasticity of the mixture, and itwill then set and gain strength normally. False set normallydoes not occur when ready-mix trucks are used to transportconcrete because of the length of the mixing cycle. Whensuch lengthy mixing or a remix step, as described above, isimpractical, then the optional requirement limiting false setin ASTM C 150 (CRD-C 201) should be invoked. Whenpremature stiffening cannot be overcome by additionalmixing, it is probably "flash set" due to inadequateretardation of the cement during manufacture.

(d) Cement-admixture interaction. Some cement-admixture combinations show no tendency to cause earlystiffening when tested according to ASTM C 451 (CRD-C259) but will cause early stiffening when used with somewater-reducing admixtures. The phenomenon can bedetected by testing the cement and admixture proposed foruse according to ASTM C 451. Also see paragraph 2-5 onchemical admixtures.

(e) Alkali reactivity. The potential for deleteriousreactivity of the alkalies in the cement with the aggregateshould be evaluated as outlined in Appendixes D and E ofthis manual. If the aggregates are potentially reactive,paragraph D-6 presents options, including disapproval of theaggregate source, use of low-alkali cements, or use ofGGBF slag or pozzolans.

(f) Heat of hydration. The heat of hydration should belimited in those cases where thermal strains induced oncooling of the concrete are likely to exceed the straincapacity of the concrete in the structure. This isaccomplished by specifying the available option for limitingthe heat of hydration for Type II portland cement or usingType IV cement, if available. For blended hydrauliccements, the heat of hydration is limited by specifying thesuffix (MH) for Type IS, I(SM), IP, S, and (LH) for TypeP. The replacement of a portion of the portland cement orin some cases blended hydraulic cement with a pozzolan orGGBF slag should always be considered. The heatgeneration of each proposed cement type and eachcombination of cement and pozzolan or slag should bedetermined. The amount of heat generated should be equalto or less than the amount generated by the Type II withheat-of-hydration option which is also normally specified.

(4) Requirements for use of other hydraulic cements.

(a) Expansive hydraulic cement. Expansive cementshave been used in floor slabs, in the top lifts of some lockwalls, and in the lining slab of spillway channels to reduceshrinkage cracking. The applications have generally beenaccomplished in closely controlled situations and afterextensive investigation. Additional reinforcement is usuallyrequired to control the expansion. Since the use ofexpansive cements in water-control structures is far fromcommon, its proposed use will require a comprehensiveinvestigation to be included in the concrete-materials DM.

(b) High-alumina cement. High-alumina cement is notnormally used in civil works structures and should beconsidered only in those locations which justify its addedcost and after investigating the possible effects of itstendency to lose strength when exposed to heat andmoisture. Its use should be preceded by a comprehensiveinvestigation which is made a part of the concrete materialsDM.

(c) Proprietary high early-strength cements. Cementsthat develop high strength within a few hours are oftenconsidered for use in cold weather applications or for repairapplications, or both, that are required to bear load soonafter finishing. The investigation that precedes its useshould determine availability and the characteristics of theavailable material. The results of the investigation shouldbe included in the concrete materials DM.

(5) Pozzolans. The classes of pozzolans most likelyto be available are classes F and C fly ash and silica fume.Class N may be considered at those sites where a source ofnatural pozzolan is available.

(a) Regulations governing use of fly ash. The SolidWaste Disposal Act, Section 6002, as amended by theResource Conservation and Recovery Act of 1976, requiresall agencies using Federal funds in construction to allow theuse of fly ash in the concrete unless such use can be shownto be technically improper. The basis of this regulation isboth energy savings and waste disposal, since most fly ashin use today is the result of the burning of coal for electricalpower.

(b) General. The use of pozzolan should beconsidered coincident with the consideration of the types ofavailable cements. Portland cement to be used alone shouldalways be considered in the specifications as well asblended hydraulic cements or the combination of portlandcement with slag cement or pozzolan unless one or the latteris determined to be technically improper. Classes F and C

2-4

Page 20: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

fly ash are generally accepted on all Corps of Engineers’(CE) civil works projects, and their use should be allowedin all specifications unless there are technical reasons not todo so.

(c) Class F pozzolan. Class F pozzolan is a fly ashusually obtained from burning anthracite or bituminous coaland is the class of fly ash that has been most commonlyused to date. It must contain at least 70.0 percent ofSi02 + Al203 + Fe203 by chemical analysis.

(d) Class C pozzolan. Class C pozzolan is a fly ashthat is usually obtained from the burning of lignite orsubbituminous coal. It must contain at least 50.0 percentof Si02 + Al203 + Fe203 .

(e) Other considerations. Class C fly ashes oftencontain considerably more alkalies than do Class F flyashes. However, when use of either class in applicationswhere alkali-aggregate reaction is likely, the optionalavailable alkali requirement of ASTM C 618 (CRD-C 255)should be specified. Use of Class F fly ash in replacementof portland cement results in reduction of heat of hydrationof the cementitious materials at early ages. Use of Class Cfly ash in the same proportions usually results insubstantially less reduction in heat of hydration. Ananalysis of the importance of this effect should be made ifClass C fly ash is being considered for use in a massconcrete application. See paragraph 3-2b, "ThermalStudies." Class F fly ash generally increases resistance tosulfate attack. However, if the portland cement is of highC3A content, the amount of improvement may not besufficient so that the combined cementitious materials areequivalent to a Type II or a Type V portland cement. Thiscan be determined by testing according to ASTM C 1012(CRD-C 211). Class C fly ashes are quite variable in theirperformance in sulfate environments, and their performanceshould always be verified by testing with the portlandcement intended for use. Both Class F and Class C flyashes have been found to delay for initial and final set.This retarding action should be taken into consideration ifimportant to the structure. Most Class C and Class F flyashes are capable of reducing the expansion from the alkali-silica reaction. Use of an effective fly ash may eliminatethe need to specify low-alkali cement when a reactiveaggregate is used. The effectiveness of the fly ash must beverified by ASTM C 441 (CRD-C 257). For additionalinformation, see Appendixes D and E.

(f) Class N pozzolan. Class N is raw or calcinednatural pozzolans such as some diatomaceous earths, opalinecherts, tuffs, and volcanic ashes such as pumicite.

(g) Silica fume. Silica fume is a pozzolan. It is abyproduct of the manufacture of silicon or silicon alloys.The material is considerably more expensive than otherpozzolans. Properties of silica fume vary with the type ofsilicon or silicon alloy produced, but in general, a silicafume is a very finely divided product and consequently isused in concrete in different proportions and for differentapplications than are the more conventional pozzolansdiscussed in the previous paragraphs. Applications forwhich silica fume is used are in the production of concretehaving very high strengths, high abrasion resistance, verylow permeability, and increased aggregate bond strength.However, certain precautions should be taken whenspecifying silica-fume concretes. Use of silica fumeproduces a sticky paste and an increased water demand forequal slump. These characteristics are normallycounteracted by using high-range water-reducing admixtures(HRWRA) to achieve the required slump. Thiscombination, together with an air-entraining admixture, maycause a coarse air-void system. The higher water demandfor silica-fume concrete greatly reduces or eliminatesbleeding, which in turn tends to increase the likelihood ofplastic shrinkage cracking. Therefore, steps should be takenas early as possible to minimize moisture loss, and thecuring period should be increased over that required forconventional concrete. For additional information, seeparagraph 10-10i.

d. Availability investigation of cementitious materials.

(1) General. Following the investigation outlinedpreviously in paragraph 2-1c to determine the technicalrequirements of the cementitious materials for a project, itis necessary to assess availability of those materials in theproject area. Technical requirements to use a certain typeor kind of cementitious material to assure long-termdurability and serviceability of the structure shall not becompromised because of the cost of obtaining the material.All cementitious materials should be furnished by theContractor. The contract specifications should allow theContractor maximum flexibility to provide cementitiousmaterials that meet the technical requirements for theproject. The investigation should cover an area sufficient toprovide at least two sources of each cementitious materialto provide price competition. An estimate of the cost perton of each material delivered to the project should besecured from each producer. The key objective of theavailability investigation is to ensure that materials meetingthe technical requirements can be obtained by theContractor.

(2) Portland cement and blended hydraulic cements.The availability of the technically acceptable portland

2-5

Page 21: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-2000Change 131 Jul 94

cement and blended hydraulic cement types must be invest-igated prior to listing materials in the DM or the contractspecifications. Any optional physical or chemical require-ments from ASTM C 150 (CRD-C 201) or ASTM C 595(CRD-C 203) that are to be invoked by the designer must beconsidered during the investigation. For example, Type IIcement or Type IP blended hydraulic cement may be readilyavailable in the project area, but when the heat-of-hydrationoption is invoked from ASTM C 150 for portland cement orfrom ASTM C 595 for blended hydraulic cement, theavailability may be severely reduced. Producers in theproject area should be queried about their current productionand also about their ability and willingness to producematerial that meets any optional physical or chemicalrequirements that the designer deems necessary.

(3) Pozzolans. The availability of technicallyacceptable pozzolans, both natural pozzolans and fly ashes,must be investigated prior to listing materials in the contractspecifications. Normally, only commercial sources ofnatural pozzolan and fly ash that are economically viable foruse on the project will need to be investigated.Undeveloped sources of natural pozzolans should not beinvestigated unless there are no other sources of pozzolanavailable. CECW-EG should be contacted for guidance inevaluating an undeveloped source of natural pozzolan. Theavailability investigation should include any optionalchemical or physical options from ASTM 618 (CRD-C 255)that the designer needs to invoke for technical reasons.Producers in the project area should be queried about theirproduction and material properties and also about theirability and willingness to produce material that meets anyoptional requirements that the designer deems necessary. Itshould be stressed that the uniformity requirement inASTM 618 will be required.

(4) GGBF slag. The availability of technicallyacceptable GGBF slag must be investigated prior to listingit in the contract specifications. Availability is presentlylimited and only Grade 120 material is being produced.GGBF slag must meet the requirements of ASTM C 989(CRD-C 205).

(5) Silica fume. Silica fume is generally availableonly from national distributors as a proprietary material. It

* is a relatively expensive material. Therefore, it is rarelyused in mass concrete structures but more likely in structuralconcrete and shotcrete applications. When specifying silicafume, the optional requirement of specific surface area inASTM C 1240 Table 4 should be invoked in all cases. Theoptional Table 2 in ASTM C 1240 should be used only iflow alkali cement is required. The uniformity requirement

in Table 4 should be invoked when concrete is air-entrained.The sulfate resistance expansion requirement in Table 4need not be included except in areas where sulfate attack isexpected. All other optional requirements in Table 4 neednot be specified unless past experiences or environmentconditions justify these tests. *

2-3. Aggregates

a. General. One of the most important factors inestablishing the quality and economy of concrete is adetermination of the quality and quantity of aggregatesavailable to the project. Preliminary investigation todetermine potential aggregate sources should be performedduring the feasibility phase, and detailed investigationsshould be performed during the PED prior to issuance ofP&S’s. All sources investigated during the PED should bedocumented in the appropriate DM, and those sources foundcapable of producing aggregates of suitable quality shouldbe listed for the Contractor’s information in thespecifications. Ideally, the sources investigated should bewithin a few miles of the project; however, depending onthe quality of aggregates required and the availability oftransportation, aggregates may be transported a considerabledistance. Not all sources within a certain distance of aproject need be investigated, but representative sources fromvarious kinds of sources in the vicinity must be evaluated toestablish the quality of aggregates that can be produced.The investigation should be comprehensive enough to assurethat more than one source of each aggregate type and sizeis available to the Contractor. The decision of whether ornot to investigate a potential source should not be based onthe grading of materials currently stockpiled at the sourcebut should be based on determining the quality of theaggregate from the source or formation. TheContractor/producer should be given the opportunity duringconstruction to adjust his processing to meet the gradingspecified. The investigation will result in a list of aggregatequalities that are required for the project and an acceptancelimit for each quality. The aggregate qualities and theirrespective limits must be documented in a DM and will beused in preparation of specifications for the project.

(1) Sources of aggregate (Government or commercial).The decision to investigate a Government source or onlycommercial sources is based on appraisal of the economicfeasibility of an onsite source when compared to commercialsources that contain aggregate of adequate quality and thatare within economic hauling distance of the project. Theappraisal should also consider the environmentalconsequences of opening and restoring the Government site.

2-6

Page 22: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

If a Government source is investigated, it will be owned orcontrolled by the Government and will be made available tothe Contractor for the production of aggregate. Thepresence of a Government source does not preclude theinvestigation of commercial sources that appear to beeconomically feasible. All sources investigated will bedocumented in the appropriate DM.

(2) Minor structures. For minor structural projects,the source of aggregate need not be listed since a qualityrequirement is specified by reference to ASTM C 33(CRD-C 133). Before specifications are issued, theavailability of aggregate meeting these requirements shouldbe determined. If none are economically available to theproject, then the specifications should be altered to allow theuse of the specification under which most of the satisfactoryaggregate in the area is produced, whether that be a state orlocal specification.

b. Availability investigation.

(1) General. The objectives of the availabilityinvestigation are to determine the required aggregate qualityfor the project, the quality of the aggregate available to theproject, and that sufficient quantity of the required qualityis available. The required aggregate quality is stated in theappropriate DM as a list of aggregate properties and theirrespective acceptance test limits. Preliminary investigationsto determine the potential sources and the required aggregatequality shall be performed during the feasibility phase andthe results documented in the engineering appendix to thefeasibility report. During the PED, field explorations andsampling and testing of aggregates should be initiated basedon the work previously completed in the feasibility report.This activity should be continued with an increasinglyexpanded scope through the completion of the concretematerials DM. If satisfactory Technical Memorandum No.6-370, "Test Data, Concrete Aggregates and Riprap Stone inContinental United States and Alaska" (USAEWES 1953),data are available and less than 5 years old, it will not benecessary to repeat the sampling and testing of those sourcesfor which such data are available. See Appendix C forfurther guidance on the scope of the investigation.

(2) Service records. Service records can be of greatvalue in establishing the quality of an aggregate wherereliable information on the materials used to produce the insitu concrete, construction procedures, and job control areavailable. The service record must be of sufficient time toassure that possible deleterious processes have had time tomanifest themselves and the existing structure must be inthe same environment that the proposed structure will be

subjected to. Photographs should be used to document thecondition of the in situ concrete.

(3) Field exploration and sampling of undevelopedsources. In undeveloped potential quarries, fieldexplorations should consist of a general pattern of coreborings arranged to reveal the characteristic variations andquality of material within the deposit. Representativeportions of the cores should be logged in detail and shouldbe selected for laboratory testing in accordance withCRD-C 100. In addition to the small holes, large calyx drillholes should be used to obtain large samples for processinginto aggregate similar to that required for the project,unless a test quarry or test pit is to be opened. Additionalinformation on the exploration of undeveloped quarrysources is available in EM 1110-1-1804, "GeotechnicalInvestigations," and EM 1110-2-2302, "Construction withLarge Stone," and these references should be consulted priorto undertaking an investigation. During PED, for a sourceof crushed stone for a large project, a test quarry should beopened and samples tested to assure that the required qualityis available. In the case of undeveloped alluvial deposits,explorations should consist of a sufficient number of testpits, trenches, and holes to indicate characteristic variationsin quality and quantity of material in the deposit. Gradingof materials in alluvial deposits should be determined toestablish grading trends within the deposits. Representativesamples of materials should be selected for laboratorytesting in accordance with CRD-C 100. Procedures formaking subsurface explorations are described inEM 1110-1-1804, "Geotechnical Investigations."

(4) Field exploration and sampling of developedsources. In commercial sources, a thorough geologicevaluation should be made of the deposit from which theraw materials are being obtained to determine the extent ofthe deposit and whether or not material remaining in thedeposit may be expected to be essentially the same as thatrecovered from the source at the time of the examinations.In quarries and mines, working faces should be examined,logged, sampled, photographed, and when considerednecessary, mapped. When available, results of and samplesfrom subsurface explorations performed by the owner shouldbe examined and evaluated. Where no subsurfaceinformation is available and proper appraisal cannot bemade without it, arrangements should be made with theowner to conduct the necessary subsurface explorations.The primary source of samples for quality evaluation testingshould be from material produced at the time of theinvestigation. These samples should be supplemented bysamples from working faces and subsurface explorations.All samples should be taken in accordance withCRD-C 100.

2-7

Page 23: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(5) Testing potential aggregate sources. During thePED phase, there should be sufficient testing to define thequality of aggregates available within an economic haulingdistance of the project. The sampling and testing programshould be designed to evaluate geologic formations,deposits, strata, or rock type available to the project. It isnot necessary to sample and test all producers within theeconomic hauling distance of the project.

(6) Evaluating aggregate qualities.

(a) Significance of test results. Aggregate qualitycannot be measured by fixed numbers from laboratory testresults only. These results should be used as indicators ofquality rather than as positive numerical measures ofquality. An aggregate may still be considered acceptable fora given project even though a portion of the test results falloutside the conventional limits found in reference standardssuch as ASTM C 33 (CRD-C 133). Results of individualtests should be considered and the final judgment should bebased on overall performance, including service recordswhere available. The cost of obtaining aggregates of thequality necessary to assure durability during the life of theproject should not be a factor in establishing the requiredquality. The incremental cost of obtaining qualityaggregates during initial construction is always less than thecost of repairs if concrete deteriorates during the service lifeof the project due to aggregate deficiencies. Detaileddiscussions of the interpretation of aggregate test data canbe found in ACI 221R and EM 1110-2-2302, "Constructionwith Large Stone." See also the discussion in paragraph2-3b(9)(b), "Acceptance Criteria."

(b) Petrographic examination (ASTM C 295 (CRD-C127)). Results of a petrographic examination should beused both for assessing the suitability of materials and fordetermining what laboratory tests may be necessary toevaluate the suitability of materials for use as concreteaggregate. Petrographic examination is performed for twopurposes: (1) lithologic and mineralogic identification andclassification and (2) determination of composition, physical,and chemical characteristics. From this examination, adescription of material should be written and a preliminaryestimate of the general quality of the material should bemade. It is possible to identify the presence of constituentsthat are capable of reacting with the alkalies in cement frompetrographic examination. When such constituents areidentified, other investigations, including the QuickChemical Test (ASTM C 289 (CRD-C 128)) or Mortar-BarTest (ASTM C 227 (CRD-C 123)), or both, should beperformed to determine their potential reactive effects.Table 2-3 lists the testing property, testing method, andcomments regarding the testing.

(c) Specific gravity (ASTM C 127; ASTM C 128).Specific gravity of aggregates is necessary for calculatingthe mass for a desired volume of material. It has no clearlydefined significance as a measure of suitability of materialfor use as concrete aggregate. Aggregates with specificgravity below 2.4 are usually suspected of being potentiallyunsound and, thus, not suited for use in the exposed portionsof hydraulic structures in moderate-to-severe exposures.However, these materials may still be used if theirperformance in freezing-and-thawing tests is acceptable.Low specific gravity has been indicative of poor quality inporous chert gravel aggregates having high absorption.Therefore, it may be necessary to set a limit on thepermissible amount of material lighter than a given specificgravity when selecting chert gravel aggregates for use inhydraulic structures in moderate or severe environment.The specific gravity limit and the permissible amount lighterthan the limit should be established on the basis of resultsof laboratory freezing-and-thawing tests.

(d) Absorption (ASTM C 127; ASTM C 128).Absorption is determined primarily as an aid in estimatingamounts of water in aggregates for laboratory and fieldcontrol of amount of mixing water used in the concrete.Absorption data are generally believed to be somewhatindicative of the probable influence of aggregates on thedurability of concrete exposed to freezing and thawing whensubject to critical saturation. However, test results haveindicated that this premise must be used with caution inassessing the quality of material. High absorption inaggregates may be an indication of potential high shrinkagein concrete and may need further investigation. However,absorption alone should not be considered significant as ameasure of suitability of a material for use as concreteaggregate.

(e) Organic impurities (ASTM C 87; ASTM C 40).The test for presence of organic impurities should be usedprimarily as warning that objectionable amounts of organicimpurities may be present in the aggregates. Objectionalamounts of organic matter will usually show "darker thanNo. 3" in the ASTM C 40 test. Primary dependence shouldbe placed on the mortar strength tests as a basis for judgingwhether or not objectionable amounts of organic impuritiesare present in natural fine aggregate. Natural fine aggregateshowing the presence of organic matter and producingmortar strength of less than 95 percent of those produced bythe same aggregate after washing with sodium hydroxide toremove organic matter should not be selected for use unlessit is evident that the material can be adequately processed toremove impurities.

2-8

Page 24: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 2-3

Standard Procedures for Obtaining Information on Aggregate Quality

During the Preconstruction Engineering and Design Phase

Testing Property Testing Method* Comments

Composition and

identification

ASTM C 295 This petrographic examination is recommended for all aggregate evaluation and should

be the basis for the determination of other procedures required.

Specific gravity and

absorption

ASTM C 127

ASTM C 128

Density will affect the density of concrete. In general, higher absorption of coarse

aggregate may indicate less F/T resistance (CRD-C 107 and 108, respectively).

Organic impurities ASTM C 40

ASTM C 87

Too much impurity will affect the concrete strength. ASTM C 87 (CRD-C 116) should be

performed if there are objectionable amounts of organic impurities (CRD-C 121 and 116,

respectively).

Soft constituents CRD-C 141

CRD-C 130

Soft materials in fine aggregate will affect concrete strength and workability. Soft

particles in coarse aggregate will affect the bonding with cement.

Clay lumps and friable

particles

ASTM C 142 Clay lumps and friable particles will affect concrete strength and workability (CRD-C

142).

Lightweight particles ASTM C 123 Lightweight particles will affect the density of concrete (CRD-C 122).

Particle shape ASTM D 4791

CRD-C 120

ASTM D 3398

Particle shape will affect the density and workability of concrete (CRD-C 129).

Soundness of

aggregate in concrete

CRD-C 114

(ASTM C 666)

Results are directly related to the F/T resistance of concrete.

Frost resistance ASTM C 682 This test may be valuable in evaluating frost resistance of coarse aggregate in concrete

(CRD-C 115).

Abrasion loss ASTM C 131

ASTM C 535

These tests may indicate the degree of resistance to degrading of coarse aggregates

during handling and mixing (CRD-C 117 and 145, respectively).

Specific heat CRD-C 124 Needed for thermal analysis.

Linear thermal

expansion

CRD-C 125

CRD-C 126

Needed for thermal analysis. Aggregates with very high or low thermal coefficient may

require further investigation.

Alkali-silica reactivity ASTM C 289

ASTM C 227

Perform these tests if there is an indication of potential alkali-silica reactivity (CRD-C 128

and 123, respectively). (See Appendix D for details.)

Alkali-carbonate

reactivity

ASTM C 586 Perform this test if there is an indication of potential alkali-carbonate reactivity (CRD-C

146). (See Appendix E for details.)

Concrete making

properties

ASTM C 39

and others

Perform these tests as needed to determine the suitability of aggregates for high strength

concrete (CRD-C 14).

*Test methods cited are from the American Society for Testing and MaterialsAnnual Book of ASTM Standards(ASTMAnnual) and from Department of the Army, Corps of Engineers,Handbook of Concrete and Cement(USAEWES 1949).

2-9

Page 25: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 111 o-2-200031 Mar 01Change 2

(f) Soft constituents, clay lumps, and lightweightparticles (ASTM C 123 (CRD-C 122); ASTM C 851(CRD-C 130); CRD-C 141; ASTM C 142 (CRD-C 142)). Resultsof tests for soft particles, clay lumps, and lightweightpieces are largely used as information that may have abearing on or assist in rationalizing results of other testssuch as the accelerated weathering test or the strengthproperties of the concrete. The tests may sometimes beuseful in determining whether or not processing of thematerial to remove the undesirable constituents isfeasible when they occur in proportions which make thematerial unfit for use without removal.

(g) Particle shape (ASTM D 4791; CRD-C 120; ASTMD 3398 (CRD-C 129)). The test for flat and elongatedparticles provides information on particle shape ofaggregates. Excessive amounts of flat or elongatedparticles, or both, in aggregates will severely affect thewater demand and finishability. In mass concretestructures, the amount of flat or elongated particles, orboth, at a 3:l length-to-width (L/W) or width-to-thickness (W/T) ratio is limited to 25 percent in any sizegroup of coarse aggregate. Although there is norequirement in structural concrete, the effect of morethan 25 percent flat or elongated particles should beexamined during the design process. The results of theexamination should be discussed in the appropriatedesign memorandum. The maximum L/W or W/Tratio, when testing in accordance with ASTM D 4791 isnormally 3:l.

(h) Soundness of aggregate by freezing and thawingin concrete (CRD-C 114). This test is similar to ASTM C666 (CRD-C 20), procedure A, except that a standardconcrete mixture is used to evaluate the effect ofaggregates on freezing-and-thawing resistance. This testis more severe than the aggregates will experience inservice. Nevertheless, it provides an importantmeasurement in relative aggregate quality in freezing-and-thawing resistance and is the best means nowavailable for judging the relative effect of aggregates onfrost resistance. In general, however, aggregates arerated in relative quality by this test as shown in Table 2-4. This table also provides the recommended DFE value basedupon the project location, and expected exposure. For thepurpose of simplicity the weathering region (Fig. I) in ASTMC 33 is used as an indicator of the potential freeze and thawexposure for the area. The engineer may adjust thisrequirement if there is data available indicating that thesituation is different from the one shown in ASTM C 33 Fig. 1.Although the test is reasonably repeatable, it is notpossible to prevent small differences in the size anddistribution of air voids caused by different cements andair-entraining admixtures and possible other factors;thus, it is not possible to judge accurately the quality ofprotection of cement paste in each instance even thoughair content for all tests is kept within a small range.Therefore, it is not unusual to find that these differenceswill cause variations in test results of sufficientmagnitude from two separate tests on essentially

identical aggregate samples to shift the quality ratingfrom one level to another. The test also has limitationson the size of aggregates that can be tested. Themaximum size of aggregate used in the tests is l% 19.0mm (3/4 in.), whereas aggregate up to 150 mm (6 in.) isfrequently used in mass concrete. Therefore, the test is oflimited value when the +19.0-mm (+3/4in.) aggregatevaries substantially in characteristics from that finer than19.0 mm (3/4 in.). In spite of its limitations, the testprovides an excellent means of evaluating the relativequality of most materials and results of the test shouldbe given prime consideration in selecting aggregatequality requirements. Where the laboratory freezing-and-thawing test is considered inadequate as a basis forjudging the quality of the aggregates, particularly forsizes larger than 19.0 mm (3/4 in.), concrete made withthe larger sizes may be exposed at Treat Island, Maine,where the Corps of Engineers’ severe-weatheringexposure station is located to determine the durability ofthe specimens. The decision to expose specimens atTreat Island should be made early in the investigation sothat they may be exposed for at least two winters. Todetermine durability, 2-ft cube specimens cast from air-entrained concrete containing the desired maximum sizeof aggregate should be used. In an average period of 2years, specimens are subjected to at least 250 cycles offreezing and thawing. If no marked reduction in pulsevelocity has occurred and no distress is visually evidentin the period, the aggregates may be considered to be ofgood to excellent quality.

(i) Frost-resistance test (ASTM C 682 (CRD-C 115)).This dilation test provides another indication ofaggregate quality in freezing-and-thawing resistancewhen used in concrete. It measures the dilation of aspecimen under slow freezing-and-thawing cycles and issimilar to ASTM C 671 (CRD-C 40) except a standard air-entrained concrete mixture is used. In air-entrainedconcrete in which the paste is adequately protectedagainst frost action, the quality of the aggregate is themain factor that contributes to deterioration. Results ofthis test are very sensitive to the moisture condition ofaggregate and concrete and should be comparedcarefully with the conditions in the field.

(j) Sulfate soundness (ASTM C 88 (CRD-c 137)). Inthe past, ASTM C 88, “Soundness of Aggregates by Useof Sodium Sulfate or Magnesium Sulfate,” has been usedquite often. This test is the only one which is performedon aggregate directly by soaking material in sulfatesolution to simulate the effect of increase in volume ofwater changing to ice or freezing in the aggregate pores.ASTM C 88 is not recommended due to its poorcorrelation with the actual service performance ofconcrete.

(k) Abrasion loss (ASTM C 131 (CRD-C 117); ASTMC 535 (CRD-C 145)). If a material performs well in othertests, particularly resistance to freezing and thawing, high

2-10

Page 26: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-200031 Mar 01Change 2

Table 2-4Concrete Durability Factors for Assessing Aggregate Durability.

DFE Range* Over 75 50-75 25-50 Less than 25

Region perASTM C33Fig. I

Severe Moderate Negligible No F/T cycle

I L

Quality Rating Excellent Good Fair Poor

*DFE = Durability factor (based on relative dynamic modulus of elasticity).

abrasion loss may not be significant. It should be recognized,however, that a material having high abrasion loss will tend todegrade in handling and that excessive grinding may occur withsuch materials during mixing. These aspects should beinvestigated as a basis for evaluating the acceptability of amaterial. It should be noted that there is no relationship betweenabrasion loss from these tests and concrete abrasion or durabilityin service.

(1) Specific heat and thermal expansion (CRD-C 124,CRD-C 125, CRD-C 126). The results of these tests areproperties of the aggregate and are needed when performingthermal analysis.

(m) Alkali-aggregate reactivity (ASTM C 227; ASTM C289; ASTM C 586 (CRD-C 123, 128, and 146, respectively)).Criteria for recognizing potentially deleterious constituents inaggregate and for evaluating potential alkali-silica and alkali-carbonate reactivity are given in Appendixes D and E,respectively. If aggregates containing reactive constituents are tobe used, the problem then becomes one of identifying thereactive constituents and determining the conditions underwhich the available aggregates may be used. Where the reactiveconstituents can be positively determined to occur in such smallproportions as to be innocuous, an aggregate, if otherwise ofsuitable quality, may be used without special precautions. Wherethe reactive constituents occur in such proportions that they arepotentially deleteriously reactive, it will be necessary to use low-alkali cement or an effective pozzolan, or both, with theaggregate. If the requirement of low-alkali cement would imposeserious difficulties of cement procurement or excessive increasein cost, consideration should be given to the use of portlandblast-furnace slag cement (a blend of portland cement and slag),Portland-pozzolan cement, cement with GGBF slag, or cementwith a pozzolan, or both, that will prevent excessive reactioneven when high alkali-cement is used. When consideration isgiven to the use of any of these materials in lieu of low-alkalicement, mortar-bar tests should be conducted to verify that thepotentially deleterious expansion will be reduced to meet thecriteria in Appendix D or E. If petrographic examinationdetermines the presence of potentially reactive materials inexcess of the limits given in Appendix D, mortar-bar tests,ASTM C 227 shall be performed. If the petrographicexamination determines the presence of strained quartz in excess

of the limit given in Appendix D, the high- temperature mortar-bar test shall be performed.

(n) Concrete making properties (ASTM C 39 (CRD-C14)). When it is desired to select aggregate for concrete withstrengths of 6,000 psi or greater, some otherwise acceptableaggregates may not be suitable. Concrete-strength specimens,made from concrete using the aggregate being evaluated and ofthe required slump and air contents, should be tested at variouscement factors, w/c, and including any required chemicaladmixtures. If the required strength cannot be obtained with areasonable slump, air content, cement factor, and chemicaladmixture(s), the aggregate should not be considered asacceptable for the high strength concrete. Materials that aresatisfactory in other respects usually have acceptable strengthand bonding characteristics. A complete discussion of high-strength concrete may be found in AC1 363R.

(0) Service performance. The performance of aggregatesin service in structures is considered the best general evidence ofaggregate quality when dependable records are available and theexposure conditions are similar. Service records are usually ofgreater usefulness when commercial sources of aggregate arebeing investigated. Service performance, however, must beconsidered with caution. Poor condition of a structure is notnecessarily evidence of poor quality aggregate. There are manyfactors which may contribute to the poor performance of theconcrete in service. However, except where a slow actingreactive aggregate is involved, a structure in good condition isalways an indication that the aggregates are of adequate qualityfor concrete exposed to similar conditions.

(7) Nominal maximum size aggregate. In general, it iseconomical to use the largest aggregate compatible with placingconditions. Table 2-5 provides guidance in making theselection. On projects not involving large quantities of

2-11

Page 27: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 2-5

Nominal Maximum Size of Aggregate Recommended for

Various Types of Construction

Features Nominal Maximum Sizes

Section 7-1/2 in. or less in width or slabs 4 in. or less in

thickness. Heavily reinforced floor and roof slabs. Parapets,

corbels, and all sections where space is limited and surface

appearance is important.

High-strength concrete

19.0 mm (3/4 in.)

Section 7-1/2 in. wide and in which the clear distance

between reinforcement bars is at least 2-1/4 in. and slabs at

least 4 in. thick.

37.5 mm (1-1/2 in.)

Unreinforced sections over 12 in. wide and reinforced

sections over 18 in. wide, in which the clear distance

between reinforcement bars is over 4-1/2 in. Piers, walls,

baffles, and stilling basin floor slabs in which satisfactory

placement of 6-in. aggregate concrete cannot be

accomplished even though reinforcement spacing would

permit the use of large aggregate. Slabs 10 in. or greater in

thickness.

75 mm (3 in.)

Massive sections of dams and retaining walls; ogee crests,

piers, walls, and baffles in which clear distance between

reinforcement bars is at least 9 in. and for which suitable

provision is made for placing concrete containing the large

sizes of aggregate without producing rock pockets or other

undesirable results. Slabs 24 in. or greater in thickness.

150 mm (6 in.)

concrete, a careful study should be made of the economy oflarge aggregates. The use of large aggregates reduces thecement content, but it increases plant costs becauseprovision must be made for the handling of more individualsizes. Nominal maximum size aggregate (NMSA), 150 mm(6 in.) or even 75 mm (3 in.), should not be specified if thevolume of concrete is so small that savings in cement willnot pay for increased plant expenses. When an economicstudy indicates the use of 75-mm (3-in.) or 150-mm (6-in.)NMSA concrete results in comparable costs and theadditional cement required in the 75-mm (3-in.) NMSAconcrete does not detrimentally affect the concrete, optionalbidding schedules should be used. The additionalcementitious quantities of 40 lb/cu yd of concrete is typicalwhen 75-mm (3-in.) NMSA concrete is used in lieu of150-mm (6-in.) NMSA concrete.

(8) Fine aggregate grading requirements. During thecourse of the aggregate investigations, the grading of theavailable fine aggregate from all sources should bedetermined and compared to the anticipated project

specifications. The project grading requirements willdepend on the guide specification selected for the project.If the most readily available materials do not meet theapplicable grading requirements and the processing requiredto bring the material into the specified grading limits resultsin increased costs, consideration should be given tosubstituting a state or local specification that is determinedto cover the fine aggregate grading available at commercialsources in the project area. The substitution should bebased on the determination that concrete meeting the projectrequirements can be produced using the locally availablefine aggregate. If a large mass concrete structure isinvolved which will be built to the requirements ofCW-03305, "Guide Specification for Mass Concrete," usingan onsite fine aggregate source, the decision to waive thegrading requirements will also be based on the results of theprocessibility study, which includes estimates of waste andlaboratory data that show that concrete can be producedusing the fine aggregate grading proposed which meets allthe project requirements. The study should include aneconomic evaluation which shows, clearly, that the increased

2-12

Page 28: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

cost of cement and finishing, when a nonstandard grading isused, will be more than offset by the savings in processingand waste reduction. Particular attention should be given tothe increased workability gained by use of an optimumamount of material finer than the 300-µm (No. 50) and150 µm (No. 100) sieves. Many studies have shown that itis cost effective to blend in a fine "admix" sand in this sizerange if the available sand is deficient in these sizes. Thelimits to be permitted on the proposed grading should alsobe stated. Manufactured fine aggregate has a tendency forthe dust that is generated during the crushing and sizingprocess to cling to the larger particles and to clump or ballup when exposed to moisture. The amount of dust can besignificant and can cause problems during construction. Thedust may not come loose or break up during sieving perASTM C 136 (dry grading), and it may be difficult toaccurately monitor the grading. The dust can also cause themoisture content of stockpiled material to be higher andmore variable than expected; this in turn can result indifficulties controlling the batch masses and slump of theconcrete. Excessive dust can cause the water demand ofconcrete to increase with resultant loss of strength.Therefore, when manufactured sand is allowed in projectspecifications, the designer should invoke the optionalrequirements in CW 03305, "Guide Specification for MassConcrete," that will limit the amount of material (dust)passing the 75-µm (No. 200) sieve and that will requirewashing the material during grading testing (ASTM C 117(CRD-C 105)). The option may also be invoked for naturalfine aggregate at the designer’s discretion.

(9) Required tests and test limits.

(a) General. For all civil works concrete constructionprojects except those for which the guide specificationCW-03307, "Concrete for Minor Structures," is used, a listof required quality tests and test limits must be establishedand inserted in the specifications. Required tests and testlimits must be site-specific for the project area, the generalrule being that the best locally available aggregates are to beused. This list of tests and test limits may be specific foronly one project or, according to the amount of diversity ofthe geology and the resulting rock types in an area, could bedistrict- or division-wide lists. On some projects where, forinstance, both river gravels and crushed stone are includedin the list of sources, a set of tests and test limits would berequired for the gravel and a slightly different set of testsand test limits would be required for the crushed stone.

(b) Acceptance criteria. Establishing test limits foraggregate quality for a project is very complex and should

be done with great care and deliberation. Limits establishedfor a specific test for one rock type at one project would notnecessarily assure durable concrete for a different rock typeat the same project or for the same rock type at a differentproject. For example, a minimum density of 2.52 for coarseaggregate at a specific project may be adequate for sometypes of chert or river gravel but would not be adequate forcrushed limestone. The selection of which tests to specifyfor indicating the quality of aggregate and the respectiveacceptance limits for each test should come after completionof all testing for each source or formation and shouldinclude due consideration of service records. Theacceptance limits should be set recognizing that all testresults have some scatter and that most ASTM (CRD) testmethods include precision and bias statements.EM 1110-2-2302, "Construction with Large Stone," containsan excellent discussion on setting acceptance criteria andshould be consulted for further guidance. The districtmaterials engineer should work closely with the divisionoffice when establishing acceptance criteria for a project sothat close coordination between adjacent districts andbetween adjacent divisions can be maintained for a givensource or formation.

(10) Aggregate processing study. A processing studyshould be considered for any government-furnished source.The processing study should be conducted by a divisionlaboratory having the capability of processing large (1- to 2-ton) samples. The sample should be processed to meet thegrading and particle-shape requirements of the project bycrushing and screening as necessary. The processing studywill provide information on which to base estimates ofwaste and also will provide an indication of the potential forthe development of flat and elongated particles to an extentwhich will influence the workability and cementrequirements of the concrete. For large mass concrete jobs,a test quarry may be required. This is usually done as aseparate construction contract to qualified private companiesskilled in blasting (if a quarry operation) and skilled inprocessing rock or gravel deposits to meet concreteaggregate gradings. In this more elaborate type ofinvestigation, the processing of the raw material would beaccomplished onsite, instead of in the division laboratory.Information to be required would include optimum blastingpatterns, quality of each rock stratum, amount of waste,particle shape, and the ability of the deposit to be processedinto the required gradings.

(11) Location of government-furnished quarry or pit.The objective should be to define clearly one or more areaswhich will be described in the specifications and shown inthe contract drawings. The purpose will be to provide the

2-13

Page 29: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

bidders with information that will make it possible for themto estimate accurately the cost of producing the aggregateand subsequently to provide information to the contractorfor use in planning his aggregate production operations.Explorations should be carefully logged and the informationincluded in the contract drawings. Materials recoveredduring these and previous explorations should be preservedand made available for inspection by the bidders and by theContractor for use in planning his work. Where zones orlayers exist that are unsuitable, they should be specificallyidentified and the listing of the source should note theunsuitability of those zones or layers.

2-4. Water for Mixing and Curing

a. General. The most readily available watersources at the project site should be investigated during thePED phase for suitability for mixing and curing water.Also, water that will be in contact with the completedstructure should be tested to determine if it contains aconcentration of chemicals which may attack the hardenedconcrete. For additional information, see the PortlandCement Association’s "Design and Control of ConcreteMixtures" (Kosmatka and Panarese 1988).

b. Mixing water. To determine if water from sourcesother than a municipal water supply is suitable for mixing,it should be investigated during the PED phase inaccordance with CRD-C 400 (USAEWES 1949). Ifcontamination by silt or a deleterious material exists,samples should be taken when contamination is the greatest.

c. Curing water. Water for curing must not containharmful chemical concentrations and it must not containorganic materials such as tannic acid or iron compoundswhich will cause staining. If certain water sources aroundthe project area have a potential for staining and others arenonstaining, the staining sources should be eliminated fromuse by the specifications and the acceptable sources notedso that unsightly staining may be prevented. However, theContractor is responsible for providing surfaces free of stainafter curing. This is a preferable approach to attempting toremove the staining with often unsatisfactory results.Curing water should be tested in accordance withCRD-C 400.

2-5. Chemical Admixtures

a. General. The chemical admixtures that may be usedin concrete on Corps projects are air-entraining admixtures(ASTM C 260), accelerating admixtures, water-reducingadmixtures, retarding admixtures, water-reducing andretarding admixtures, water-reducing and accelerating

admixtures, high-range water-reducing admixtures, and high-range water-reducing and retarding admixtures. All of thelatter are discussed in ASTM C 494 (CRD-C 87). Chemicaladmixtures to produce flowing concrete are discussed inASTM C 1017 (CRD-C 88). Other admixtures may be usedwhen their use on the project results in improved quality oreconomy. When admixtures are considered during the PEDphase to provide special concrete properties, trial batcheswith materials representative of those that will be used forthe project should be proportioned and tested. The effectsof the admixture on the concrete properties and the requireddosage rate should be reported in the concrete materialsDM. Admixtures proposed for use during constructionshould be checked with trial batches, using the actual projectmaterials in the Division laboratory. However, if the sourceof the concrete is a ready-mix plant with a recent history ofuse of the admixture with project materials, trial batchesneed not be required. In some instances, adverse reactionsmay occur between admixtures or between admixtures andcement or water. Admixtures should not be mixed togetherprior to batching, but each should be batched separately. Adetailed discussion of chemical admixtures for concrete isgiven in ACI 212.3R.

b. Air-entraining admixtures.Air-entraining admixtures(AEA’s) are organic materials which entrain small airbubbles into concrete. These bubbles become a part of thecement paste that binds the aggregates together in thehardened concrete. Air entrainment improves theworkability of concrete, reduces bleeding and segregation,and most importantly improves the frost resistance ofconcrete. Air entrainment is essential to ensure thedurability of concrete that will become critically saturatedwith water and then exposed to freezing-and-thawingconditions. However, air entrainment only protects the pastefraction of the concrete. It does not protect concrete fromdeterioration caused by nonfrost-resistant aggregates.

(1) Policy. All civil works concrete should be airentrained with an appropriate AEA. Any exceptions to thispractice must be submitted to CECW-EG for approval.

(2) Strength loss. Even if freezing-and-thawingconditions are not prevalent, concrete should be air entrainedbecause of the benefits imparted in other ways. Thepresence of entrained air results in an improvement in theworkability of concrete at the same water content. Tomaintain a given slump, a reduction in the water content ofup to 15 percent can be made depending upon the air andcement contents. The reduction in the water content resultsin a lower w/c, which will offset some or all of the loss instrength due to the presence of the entrained air, dependingon the cement content; calculations indicate that at about

2-14

Page 30: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

300 lb of cement per cubic yard, an increase in air contentwill be balanced by a sufficient decrease in w/c at constantslump to maintain constant strength.

(3) Bleeding. Air-entrained concrete is less susceptibleto bleeding. When successive lifts of concrete are to beplaced, more effort will be required for horizontal lift jointcleanup if bleeding is excessive. A considerable reductionin bleeding by proper air entrainment is usually a majorbenefit. Air entrainment also imparts a buoyant action tothe cement and aggregate particles which helps to preventsegregation. Even though it is an aid against segregation, itcannot prevent segregation of concretes having poorlygraded aggregates, ones that are excessively lean or wet, orones that are improperly transported or placed.

(4) Batching AEA. An AEA should be added to themixing water prior to its introduction into other concretematerials. If other admixtures are also used, the AEAshould be added to the concrete mixer separately and notintermixed with the other admixtures.

(5) Dosage. Many variables will determine the exactdosage of an AEA needed to achieve the proper air-voidsystem in a concrete mixture. In general, larger amounts ofAEA will produce higher air contents in a concrete mixture.However, there is no direct relationship between the dosagerate of a given AEA and the air content that is produced.

(6) Effects of water content on air content. Air contentwill usually increase or decrease as the water content of amixture is increased or decreased. An increase in the watercontent in the concrete results in a more fluid mixture intowhich the air bubbles can be more easily incorporated bythe mixing action. For example, a slump increase of about3 in. can cause an increase in air content of about 1 percentwith the same dosage of an AEA.

(7) Effects of fine aggregate grading on air content.Air is more easily entrained in concretes having higherpercentages of fine aggregate. The fine aggregates provideinterstices that can contain the air bubbles, especially thesizes from about 600 µm (No. 30) to the 150 µm (No. 100).Concretes made with fine aggregates deficient in particles ofthese sizes can require larger amounts of AEA’s to achievethe desired air content, especially in lean concretes.Conversely, concretes made with an excess of finely dividedmaterials can also require larger amounts of AEA’s toachieve the desired air content. Very fine sand fractions(150 µm (No. 100) and smaller), fly ash , and high cementcontents have caused a reduction in air contents. Fly asheswhich have high loss on ignition cause an especially largereduction in the air content. Concrete made with a Type III

cement can require up to 50 percent more AEA’s thanconcrete made with a Type I cement.

(8) Effects of temperature on air content. Thetemperature of the concrete has a direct effect upon the aircontent of the concrete at given AEA dosage. A lowertemperature results in a higher air content, and vice versa.Therefore, if the concrete temperature changes significantlyduring production of a particular concrete mixture, it islikely that the amount of AEA must be adjusted accordinglyto maintain the desired air content.

(9) Effect of other admixtures on air content. LessAEA is generally required to entrain air in concrete whenwater-reducing or retarding admixtures are also used. Therequired amount of AEA may be as much as 50 percentless, especially when lignosulfonate-based chemicaladmixtures are used because these materials also have amoderate air-entraining capacity.

(10) Effect of mixing action on air content. Effectivemixing action is necessary to produce air-entrained concrete.The amount of entrained air will vary with the type andphysical condition of the mixer, the mixing speed, and theamount of concrete being mixed. It is more difficult toentrain air in concrete using a severely worn mixer or onethat has an excessive amount of hardened concrete buildupon the blades or in the drum. Air contents can alsodecrease if the mixer is loaded above its rated capacity.Studies have shown that air contents generally increase withmixing up to about 15 min. Thereafter, additional mixingleads to a decrease in air content, especially for low-slumpconcretes. Any transporting technique that will continue toagitate the concrete, such as pumping or conveying, usuallydecreases the air content.

c. Accelerating admixture.Accelerating admixturesare classified by ASTM C 494 as Type C, accelerating, orType E, water-reducing and accelerating. Acceleratingadmixtures accelerate the setting time or early strengthdevelopment of concrete or both. Initial and final settingtimes must be accelerated by a minimum of 1 hr, and 3-daycompressive strengths must be increased by a minimum of25 percent in order for an accelerating admixture to complywith the requirements of ASTM C 494 (CRD-C 87).

(1) Uses. CW-03301 and CW-03305 provide for theuse of nonchloride accelerating admixtures subject to theapproval of the Contracting officer. The use of anonchloride accelerating admixture may be approved whenconcrete is being placed in cold weather to partially offsetthe retarding effect of the lower temperatures. Its usepermits earlier finishing of slabs and reduces form removal

2-15

Page 31: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

delays. The use of an accelerating admixture does notpermit a reduction of specified curing and protectionperiods.

(2) Nonchloride admixtures. Several nonchlorideorganic and inorganic compounds, such as calcium formate,calcium nitrite, and triethanolamine, are available asaccelerators. However, experience and published researchon these admixtures are limited. The available data suggestthat none of the nonchloride accelerating admixtures are aspowerful an accelerator as calcium chloride at equaldosages. However, adequate acceleration can usually beattained with a nonchloride accelerating admixture if theproper dosage is used. Nonchloride accelerators usuallycome in liquid form and should be added at the mixer witha portion of the mixing water at a dosage rate recommendedby the manufacturer. They should be added to the concreteseparately and not mixed with other admixtures. In someinstances, adverse reactions occur between admixtures whichcan decrease their effectiveness.

(3) Effect on fresh concrete properties. Type Caccelerating admixtures have no significant effect on theinitial workability or air content of a concrete mixture;however, the setting time, heat evolution, and strengthdevelopment are affected. Concretes containing anaccelerating admixture can have a more rapid slump loss,especially concretes having a high cement content. Thebleeding of a concrete mixture is generally reduced when anaccelerating admixture is used.

(4) Effect on hardened concrete properties. Propertiesof hardened concretes containing an accelerating admixtureare generally increased at early ages but may be decreasedat later ages. Compressive and flexural strengths will behigher at early ages but can be lower than those of plainconcrete at later ages. Both creep and drying shrinkage mayincrease. Concretes containing accelerators may be lessresistant to aggressive environments, especially at later ages.The passive layer of protection at the concrete-steel interfacedoes not appear to be attacked by nonchloride accelerators.Proper curing procedures are essential when concretecontains an accelerating admixture.

(5) Other methods of accelerating strengthdevelopment. Frequently, the acceleration of setting timeand early strength development can be obtained by othermeans, such as (a) using a Type III portland cement, (b)using additional cement, (c) lowering the pozzolan content,(d) warming water and aggregates, (e) improving curing andprotection, or (f) some combination of these. In some cases,the use of an accelerator is the most convenient andeconomical method of achieving the desired results;

however, convenience and economics should not takeprecedence over durability considerations.

d. Retarding admixtures.Retarding admixtures arematerials which cause a delay in initial and final settingtimes. However, retarding admixtures do not reduce the rateof slump loss. Retarding admixtures are classified byASTM C 494 (CRD-C 87) as Type B, retarding, or Type D,water-reducing and retarding. They must retard the initialsetting time by a minimum of 1 hr and the final setting timeby a minimum of 3-1/2 hr. Setting times of concrete madewith a portland cement-pozzolan blend will typically beretarded more than when portland cement alone is used.The pozzolan often has a retarding action.

(1) General uses. By using the proper dosage of aretarding admixture, the setting time of a mixture can beextended so as to avoid cold joints and allow for properfinishing. A change in temperature could require anadjustment in the dosage of retarder to maintain the desiredsetting time. Retarding admixtures can be beneficial in hotweather, when long hauling distances are unavoidable, oranytime extended working times are desirable. The timebetween screeding and troweling operations of concreteslabs is extended when retarding admixtures are used. Thiscan be particularly beneficial in hot weather; however,unless proper precautions are taken, such as the use ofsunscreens and wind screens, the surface may dryprematurely and create a crust on the surface. Under theseconditions, careful attention to curing and protection isrequired to obtain a uniform hardening in the entire concreteslab. Retarding admixtures based on hydroxylatedcarboxylic acids and their salts are beneficial in concreteused in flatwork construction during hot weather since theyinduce bleeding and, therefore, aid in the prevention of apremature drying of the top surface.

(2) Dosage. The dosage of admixture recommended bythe manufacturer should be used unless experience or resultsof trial batches indicate otherwise. High temperatures mayrequire higher dosages of retarding admixtures; however,overdosage can cause excessive retardation requiring longercuring times and delays in form removal. The degree ofexcessive retardation could be from a few hours to a fewdays. However, an accidental overdosage of a retardingadmixture does not adversely affect the later age propertiesof a concrete if the concrete is cured properly and the formsare not removed until sufficient strength has been attained.Research has shown that a higher dosage of retardingadmixtures is needed when used with portland cements thathave high C3A and C3S contents, as well as a high alkalicontent. Therefore, to achieve the same effects, a largerdosage of retarding admixture will probably be required if

2-16

Page 32: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

a Type I portland cement is used than will be required if aType II, low-alkali portland cement is used.

(3) Batching. Retarding admixtures should be added tothe mixing water prior to its introduction into other concretematerials. If other admixtures are also used, the retardingadmixture should be added to the concrete mixtureseparately and not mixed with the other admixtures. Insome instances, adverse reactions occur between admixtureswhich can decrease their effectiveness.

(4) Effect on strength. When retarding admixtures areused in concrete, early-age compressive and flexuralstrength may be reduced. If a low dosage of admixture isused, the lower strengths may be evident for as few as 1 or2 days. Greater degrees of retardation may cause thestrengths to be lower for 3 to 7 days. However, in mostcases there will be no retardation of strength developmentby 28-days age. Lower strengths may exist for a longerperiod of time if the concrete is made with a portlandcement-pozzolan blend. At later ages, the strength ofconcrete made with a retarding admixture will usually behigher than that of concrete containing no retardingadmixture.

e. Water-reducing admixtures. Water-reducingadmixtures (WRA’s) are organic materials which reduce theamount of mixing water required to impart a givenworkability to concrete. By definition, WRA’s are requiredto provide a water reduction of at least 5 percent and areclassified by ASTM C 494 (CRD-C 87) as Type A, water-reducing; Type D, water-reducing and retarding; or Type E,water-reducing and accelerating. They can be used toincrease strength, increase workability, or reduce the cementcontent of a concrete mixture.

(1) Use in mass concrete. A WRA generally shouldnot be allowed in lean mass concrete mixtures since neitherhigh strength nor high slump are usually required from thesemixtures. A reduction in the cement content permitted bythe use of a WRA could result in the mixture havinginadequate workability. This is especially true for massconcrete mixtures containing 37.5-mm (1-1/2-in.) or largernominal maximum size aggregate.

(2) Dosage. The usual dosage rate for a WRA isbetween about 2 and 8 fl oz/100 lb of cementitious material.The appropriate amount will be determined by the brand ofWRA being used as well as the combination of otherconcrete materials. Some WRA’s meet ASTM C 494(CRD-C 87) requirements for both Type A and Type D,depending upon the dosage rate used. These WRA’s willusually react as a Type A at the lower limit of the

recommended dosage range and as a Type D at the upperlimit of the recommended dosage range.

(3) Use in hot or cool weather. A Type D WRA canbe beneficial when working in hot weather, when longhauling times are involved, or anytime extended workingtimes are desirable. However, the retarding effect increasesthe concrete setting time only. It does not slow the rate ofslump loss. In fact, concretes containing either Type A,Type D, or Type E WRA generally lose slump at a fasterrate than when a WRA is not used. A Type E WRA maybe beneficial when working in cool temperatures or whenhigher earlier strengths are desired.

(4) Air entrainment. Most lignosulfonate WRA’s willentrain air. However, the amount of entrained air willusually not be sufficient to provide adequate frost resistance.An AEA will be required in addition to the WRA, but theamount of AEA necessary may be as much as 50 percentless. WRA’s based on other compounds generally do notentrain air but do enhance the air-entraining capability ofAEA’s.

(5) Bleeding. WRA’s affect the rate and capacity offresh concrete to bleed. Lignosulfonate WRA’s reduce thebleeding rate and capacity while WRA’s based onhydroxylated carboxylic acids and their salts increase thebleeding rate and capacity of a concrete mixture. Alignosulfonate WRA should be used with caution in concreteplaced in slabs during hot weather. With little bleed watermigrating to the surface, rapid surface drying could occur,leading to a crust on the concrete surface while the concreteunderneath remains plastic. The potential for plasticshrinkage cracking is also greater. It is beneficial to inducebleeding under these ambient conditions. WRA’s based onhydroxylated carboxylic acids and their salts will accomplishthis objective.

f . High-range water-reducing admixtures("superplasticizers").High-range water-reducing admixtures(HRWRA’s) are chemically different from normal WRA’sand are capable of reducing water contents by as much as30 percent without detrimentally affecting air content,bleeding, segregation, setting time, and hardened properties.By definition, HRWRA’s are required to provide a waterreduction of at least 12 percent and are classified by ASTMC 494 as Type F, high-range water-reducing, or Type G,high-range water-reducing and retarding. HRWRA’s can beused to produce concrete having high workability for easyplacement, high strength with normal workability, orcombinations of the two. HRWRA’s can also be used toproduce flowing concrete as described by ASTM C 1017

2-17

Page 33: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(CRD-C 88). Additional information on flowing concretemay be found in paragraph 10-9.

(1) Effect on workability. Significantly highercompressive strengths are possible with the use of anHRWRA. Concrete can be produced having a lower w/cwithout the loss of workability that could occur with the useof WRA’s. The increased workability made possible withan HRWRA permits easier placement of concrete incongested reinforcement and in areas where access islimited. HRWRA’s are beneficial in concrete which ispumped or placed by tremie because they improveworkability without a loss in cohesiveness. The dispersingaction of HRWRA is effective on both portland cements andpozzolans. The ability of an HRWRA to increase the slumpof concrete depends upon the chemical nature of theHRWRA, the dosage used, time of addition, initial slump,composition and amount of cement, and concretetemperature. Recommended dosages of HRWRA’s areusually greater than those of WRA’s. There are somelimitations of HRWRA’s that should be recognized. Undersome conditions, concretes containing HRWRA’s mayexhibit a rapid slump loss as soon as 30 min aftercompletion of mixing. Therefore, HRWRA’s are oftenadded to truck mixers at the job site to minimize placingand consolidation problems associated with concrete whichstiffens rapidly.

(2) Effect on segregation and bleeding. WhenHRWRA’s are used as water reducers, bleeding of theconcrete is usually reduced. Segregation of the aggregateswill not be a problem. When HRWRA’s are used toproduce flowing concrete, both bleeding and segregation canoccur if precautions are not taken. Increasing the volume ofsand in the mixture by 3 to 5 percent may be necessary.The dosage of HRWRA should be limited to the minimumamount necessary to produce the desired slump. Anoverdose can cause excessive bleeding and segregation.However, bleeding and segregation of a high-slump concreteis not as pronounced when the high slump is achievedthrough use of an HRWRA as would be the case if the highslump were achieved through the addition of extra water.Retempering once with an HRWRA is generally anacceptable practice.

(3) Effect on air entrainment. Some HRWRA’senhance the air-entraining capability of AEA’s. However,HRWRA’s can also facilitate the escape of air. Repeateddosing with an HRWRA can accentuate this effect. Inaddition to the rapid slump loss, a significant loss of air canoccur.

(4) Effect on setting time. A Type F HRWRA haslittle effect upon setting times of concrete, while a Type GHRWRA retards the setting time. The usual dosage rangefor HRWRA is between about 10 and 30 fl oz/100 lb ofcementitious materials. The appropriate amount will bedetermined by the type of HRWRA being used as well asthe combination of other concrete materials and admixtures.Some HRWRA’s meet ASTM C 494 requirements for bothType F and Type G, depending on the dosage rate used.These HRWRA’s will usually react as a Type F at the lowerend of the recommended dosage range and as a Type G atthe upper end of the recommended dosage range. If one ofthese HRWRA’s is being used at a low dosage, and it isdesired to increase the dosage for additional water reduction,caution should be exercised. The higher dosage could causeundesirable retardation of concrete setting time and strength.

(5) Compatibility with other admixtures. HRWRA’sare generally compatible with most other concreteadmixtures. However, each admixture combination shouldbe evaluated prior to being used. In particular, attentionshould be given to the air content and air-void systemparameters. Appropriate durability tests should beperformed depending on the environment to which theconcrete will be subjected. When concrete containing anHRWRA is properly air entrained, it will be as durable asthat without an HRWRA.

g. Antiwashout admixtures.In recent years a group ofchemical admixtures known as antiwashout admixtures(AWA’s) has been introduced into the concrete productsmarket. ASTM standard specifications have not yet beendeveloped for these admixtures. They are used to increasethe cohesiveness of a concrete to prevent excessive washingout of cementitious materials when the concrete is placedunderwater. A workability transformation occurs afterseveral minutes of mixing, thereby causing the concrete tobecome very sticky. Present guide specifications do notinclude AWA’s. The use of AWA’s should be discussed inthe appropriate DM.

(1) General. AWA’s can be made from variousorganic and inorganic materials. The two materials mostcommonly marketed as AWA’s are cellulose and gum.They act primarily by increasing the viscosity and the waterretention of the cement paste. Both materials are veryeffective in increasing the washout resistance of a concretemixture. The washout resistance depends upon the type anddosage of AWA, w/c, cement content, and other admixturesused. In general, the washout resistance increases with anincrease of AWA, a decrease in w/c, and an increase in

2-18

Page 34: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

cement content. The loss of cementitious materials due towashing is typically reduced by as much as 50 percent whenconcrete contains an AWA.

(2) Batching. AWA’s based on cellulose are normallypackaged in a powder form. They are usually added to theconcrete mixer with the cement. AWA’s based on gummay be packaged either as a powder or liquid. The powdershould be put into solution with a portion of the mixingwater prior to introduction into the concrete mixture. Theliquid can be added with the mixing water.

(3) Air entrainment. AWA’s based on cellulose tendto entrain air. In combination with some WRA’s orHRWRA’s, AWA’s will entrain an excessive amount of air.When this occurs, an air-detraining admixture must beincorporated into the concrete mixture to reduce the aircontents to acceptable levels. AWA’s based on gum usuallydo not entrain air.

(4) Bleeding. Since AWA’s increase the waterretention of cement paste, virtually no bleeding occurs inconcretes containing these admixtures. However, this wouldnormally be of little concern in concrete placed underwater.

(5) Retardation. AWA’s based on cellulose tend toretard the setting time of concrete. Larger dosages of theseAWA’s can retard concrete setting times significantly, insome cases up to 24 hr. If the delayed setting time posesproblems with other construction operations, an acceleratorcan be used to partially offset the retardation. AWA’sbased on gum usually do not retard setting times as much asthose based on cellulose.

(6) Compatibility. AWA’s have little effect oncompressive strengths of concrete. The amount of mixingwater necessary for concrete made with an AWA is greaterthan would be necessary for concrete without an AWA. Inmany cases the amount of mixing water can be reduced witha WRA or an HRWRA. In fact, when concretes have w/cless than 0.50, the use of a WRA will probably benecessary. When the w/c is less than 0.40, the use of anHRWRA will be necessary to achieve the flowabilitynecessary for an underwater placement. Cellulose-basedAWA’s and napthlene sulfonate-based HRWRA’s areincompatible, and combinations of these should be avoided.Cellulose-based AWA’s are generally compatible with othertypes of HRWRA’s and most WRA’s. Gum-based AWA’sare generally compatible with most WRA’s and HRWRA’s.

(7) Dosage. The proper dosage of AWA’s, WRA’s,and HRWRA’s, as well as the compatibility of theseadmixtures, must be determined in trial batches prior to the

beginning of any concrete placement. The amount of anAWA necessary to achieve the desired washout resistancecan vary considerably depending upon the concrete materialsbeing used and their proportions. An excessive amount ofAWA can render the concrete unworkable, while too littleAWA will not provide adequate washout resistance. Followthe manufacturers recommendations for dosages and adjustas necessary in preliminary trial batches. Extreme cautionshould be exercised if it becomes necessary to adjust thedosage of either the AWA, WRA, or HRWRA after theactual placement begins. A small change in the dosage canresult in a dramatic change in the workability andcohesiveness of the concrete. When the use of an AWA isspecified, the services of a qualified manufacturer’stechnical representative should be required. The technicalrepresentative should be available during mixtureproportioning studies and be onsite during concreteplacement. The concrete mixture containing the AWAshould be proportioned in the division laboratory if themixture is government furnished or in an approvedcommercial laboratory if proportioning is a Contractorresponsibility.

(8) Pumping. The cohesiveness imparted by an AWAactually improves the pumpability of concrete for distancesup to approximately 150 ft. If the pumping distanceexceeds 250 ft, pumping pressures will likely increasesignificantly. If the pumping pressures become excessive,the concrete mixture proportions must be adjusted by addingwater or reducing the amount of the AWA, or the pumpmust be relocated to reduce the pumping distance.Adjusting the mixture proportions in this manner mayreduce the concrete cohesiveness and cause it to be moresusceptible to washout; therefore, relocating the pump, ifpossible is the preferable solution.

h. Extended set-control admixtures.

(1) General. These admixtures are relatively new tothe commercial market and were developed to give theready-mixed concrete producer maximum flexibility incontrolling the rate of hydration of fresh concrete. They aretypically marketed as a two-component system consisting ofa very strong retarding admixture, sometimes referred to bythe manufacturer as a stabilizer, and an acceleratingadmixture, sometimes labeled as an activator by themanufacturer. These admixtures allow the concreteproducer to take advantage of severely retarded freshconcrete in several ways, including:

(a) Treating unhardened concrete which is returned tothe plant with the stabilizer so that it can be kept in theunhardened state, or stabilized, in the truck mixer or holding

2-19

Page 35: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

hopper for several hours. When the concrete is needed,cement hydration is normally reactivated by combiningfreshly mixed concrete with it before sending it to the jobsite. Returned unhardened concrete may also be stabilizedovernight or longer. In these cases, hydration of the cementin the stabilized concrete is typically reactivated by addingthe activator and then combining the concrete with freshlymixed concrete before delivering it to the job site.

(b) Treating the freshly mixed concrete at the plantwith the stabilizer so that hydration is retarded to the extentnecessary for very long hauls. Typically, the duration ofretardation is at least 1 or more hours, and use of theactivator may or may not be necessary at the job site,depending on the dosage of stabilizer used.

(c) Stabilizing plastic concrete in a truck mixer whichhas experienced a mechanical breakdown or an unforeseendelay. In the event of a truck breakdown, the mixer drummust still be able to turn.

(d) Treating wash water from mixers with thestabilizing admixture to reduce the need for conventionalwash water disposal methods and thereby mitigating theenvironmental concerns. Water consumption is alsoreduced. The stabilized wash water is then reused asmixing water in the concrete batched the next day or afterthe weekend.

(2) Stabilizer. The stabilizing admixture slows the rateof hydrate formation by tying up, or complexing, calciumions on the surface of cement particles. It not only formsa protective barrier around the cement particles but also actsas a dispersant preventing hydrates from flocculating andsetting. This protective barrier prevents initial set fromoccurring.

(3) Activator. The activating admixtures typicallysupplied with the extended-set admixture systems arenonchloride accelerating admixtures conforming to ASTMC 494, Type C (CRD-C 87).

(4) Effect on hardened properties. Few published dataexist on the effects of extended set admixtures on thehardened properties of concrete. However, researchindicates the use of a stabilizing admixture may cause finerand denser hydrates to form, which, in turn, appears tobenefit physical properties of paste.

(5) Dosage. Extended-set control admixtures areusually delivered in liquid form. Because they are stillrelatively new to the concrete industry and because there arepresently no standard specifications for them, their use

should be permitted only after data are supplied by theconcrete supplier that the fresh and hardened properties ofthe concrete anticipated for use will not be detrimentallyaffected. Manufacturer’s technical representatives shouldwork closely with the concrete producer to assure correctdosage rates are established for the particular concretes andfield applications.

i. Antifreeze admixtures.A new group of chemicaladmixtures recently introduced into the concrete productsmarket is known as antifreeze or freezing-protectionadmixtures. ASTM standard specifications have not yetbeen developed for these admixtures. These materials,which have been in use in the former USSR since the1950’s and more recently in Western Europe, are designedto depress the freezing point of mixing water and therebyallow concrete to gain strength in an environment belowfreezing without suffering the deleterious effects of iceformation. Concrete made with antifreeze admixtures canbe cured at temperatures below freezing without harming itsperformance compared to that of concrete without theantifreeze admixture and cured at normal temperatures.

(1) Composition. Antifreeze admixtures are similar incomposition to accelerating admixtures, but differences doexist. ACI 212.3R states that accelerating admixturesshould not be used as antifreeze admixtures. However,some compounds used as the basis for nonchlorideaccelerating admixtures, such as sodium nitrite, calciumnitrite, and potassium carbonate, have been successfullyused as antifreeze admixtures.

(2) Batching. Antifreeze admixtures are usuallydelivered in liquid form and should be added at the mixerwith a portion of the mixing water at a dosage raterecommended by the manufacturer. They should be addedto the concrete separately and not mixed with otheradmixtures, since adverse reactions may occur betweenadmixtures which can decrease their effectiveness.

(3) Effect on strength. When antifreeze admixtures areused, early-age compressive strengths are usuallysignificantly lower than when the admixture is not used andthe concrete is cured at normal temperatures. The strengthgain of concrete which contains an antifreeze admixture andis cured at temperatures below freezing proceeds at a slowerrate than concrete which does not contain the admixture andis cured at temperatures above freezing. However, thestrengths of two such concretes may be comparable at laterages.

(4) Effect on resistance to freezing and thawing. Thereis little published documentation describing the frost

2-20

Page 36: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

resistance of concrete made with antifreeze admixtures;however, there is evidence that entrained air bubbles are lessstable when antifreeze admixtures are used. Therefore,these admixtures should not be used unless acceptable frostresistance has been verified according to provisions ofASTM C 494 (CRD-C 87).

(5) Use with reactive aggregates. When sodium nitriteand potassium carbonate go into solution, if the nitrite orcarbonate ions precipitate out, the sodium or potassium ionswill associate with hydroxide ions to raise the pH of thepore fluid. Therefore, antifreeze admixtures containingthese materials should not be used with reactive siliceousaggregates. Concrete made with these materials has alsoweakened after repeated exposure to cycles of wetting anddrying. Therefore, antifreeze admixtures containing sodium

nitrite or potassium carbonate should not be used in amarine environment.

(6) Corrosion of steel. Antifreeze admixtures madefrom nonchloride compounds have shown no tendency tocause corrosion of embedded reinforcing steel. Sodiumnitrite and calcium nitrite reduce corrosion when used inproper amounts.

(7) Cost benefits. The use of an antifreeze admixturein concrete can be cost effective. The cost of concreting invery cold weather may be as much as 50 to 100 percenthigher than that under normal conditions due to increasedequipment and labor costs. The cost of antifreezeadmixtures may be competitive with the higher costsassociated with concreting during subfreezing temperatures.

2-21

Page 37: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 3Construction Requirements and SpecialStudies

3-1. Construction Requirements

a. General. As the concrete materials design of aproject nears its conclusion, adequate data should beavailable related to likely sources of aggregate, water, andlocations of haul roads and access roads to determine if anonsite or offsite plant is required, and if an onsite plant isrequired, the site location. In addition, requirements forbatching plants, mixers, conveying, and placing equipmentmust be established and included in the appropriate DM toguide in the preparation of the plans and specifications.

b. Batch-plant location. The batch plant may belocated onsite or offsite. For a very large dam being builtin a remote location, an onsite plant would be a certainty,and for a culvert headwall in a metropolitan area, theconcrete would certainly be supplied by a ready-mix firmacting as a supplier to the Contractor. Between these twoextremes, there are numerous possibilities that will dependon the scope and location of the work, the nominalmaximum size aggregate required, the desired placing rate,the anticipated workload of the local ready-mix producersduring the period of construction of the Corps projects, andthe availability or nonavailability of a government-controlledaggregate source. Specifically, the concrete batching plantis normally required to be located onsite when the closestsource of ready-mixed concrete is remote from the project,the nominal maximum size aggregate required makes ready-mixed concrete impractical and the required placing capacitycannot be maintained by an offsite plant. An offsite plantshould be considered when the maximum size aggregate is37.5 mm (1-1/2 in.) or less, commercial concrete plantsexist in the project area, the plants are close enough that theinterval between concrete batching and final placement willbe 1-1/2 hr or less, and the required placement rate can bemaintained. Obviously, on many projects, the decisionbetween an onsite or offsite plant is not clear cut. The typeof batching and mixing equipment at each commercial plantshould be surveyed and summarized in the concretematerials DM. If more than one source exists as potentialsupplier, all such sources should be investigated and, ifacceptable, be listed in the concrete materials DM. If thepotential exists for either an onsite plant or the use of offsitecommercial source, it should be possible for the bidders tohave the option of setting up and operating an onsite plantor procuring concrete offsite.

c. Batch-plant type. Available options in batchingequipment include automatic, semiautomatic, partially

automatic, manual, and volumetric batching (ACI 304R,CRD-C 514, and ASTM 685 (CRD-C 98)). The choice ofthe batch-plant control system is dependent on the type ofconcrete, the volume of concrete required, the number ofcoarse aggregate sizes, and the importance of the structure.If mass concrete is being placed, an automatic plant will bespecified when four sizes of coarse aggregate are used,where three sizes of coarse aggregate are used and75,000 yd3 or more of concrete is involved, or when twosizes of coarse aggregate are used and more than 100,000yd3 of concrete is involved. A semiautomatic batch plantmay be specified for mass concrete if not more than threesizes of coarse aggregate are used and less than 100,000 yd3

of concrete is involved. If cast-in-place structural concreteis the type of concrete that will be predominant on theproject, the batching equipment specified may be automatic,semiautomatic, or partially automatic. For major projectsinvolving important structures or where critical smallerstructures are involved, the optional interlocks and recordersshould be required. If the concrete to be placed on a projectis only for minor structures, any of the above plants aresuitable, plus batch plants having manual controls orincorporating volumetric batching. The selection ofbatching and mixing plant requirements must take intoaccount both economy and technical requirements foradequate control of quality. Economic considerationsinclude initial plant cost, economy of operation (productionrates), and economy in concrete materials, particularlycement. It may be noted that either an automatic orsemiautomatic plant may be specified where three sizes ofcoarse aggregate are used, depending on volume of concreteinvolved and the nature of the work. The choice in thesecases is largely dependent on economy. Batch plant types,including volumetric batching, are discussed in ACI 304R.

d. Mixer type. Stationary tilting-drum mixers shouldbe used for mixing concrete containing 150-mm (6-in.)NMSA. For mixing concrete containing 75-mm (3-in.)NMSA, stationary tilting-drum, pugmill, spiral blade, orvertical shaft mixers may be used. However, for concretecontaining 75- or 150-mm (3- or 6-in.) NMSA, theContractor may choose any stationary mixer if it meets therequired capacity and complies with the uniformityrequirements when tested in accordance with CRD-C 55.Concrete containing 37.5-mm (1-1/2-in.) and smaller NMSAmay be mixed in stationary mixers or truck mixers. Forminor structures, any of these types of mixers may be usedas well as a continuous mixer with volumetric batcher.When volumetric batching and continuous mixing are usedfor minor structures, the equipment must meet therequirements of ASTM C 685 (CRD-C 98).

3-1

Page 38: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

e. Batching and mixing-plant capacity. Carefulconsideration must be given to the determination of therequired concrete production capabilities. Thisdetermination is important for both large concrete locks anddams using an onsite batching and mixing plant and forsmaller structures that may use an offsite plant and trucksfor mixing or hauling or both.

(1) Monolith size. A likely construction progressschedule should be developed during the PED phase of aconcrete structure. The fixed constraints such as committedpower-on line or lock operation dates and seasonalconstraints should be incorporated into the schedule.Recently completed similar projects in the area should bereviewed to determine the maximum placement ratesachieved. The likely placement methods such as crane andbucket, pump, or conveyor have to be determined and thestructures analyzed so that the largest continuous placementsare identified. The size of the placements are defined bythe placement of construction joints. Construction jointsshould be shown on the drawings and should be placed bythe structural designer to coincide with structural featuresand reinforcing locations. The thermal study will alsoprovide input for maximum size of monolith and maximumlift heights. Construction joints should be located to providefor as many placements as possible to be approximately thesame volume. If one placement is several times the volumeof all other placements on a project, this will require a muchlarger batching and mixing plant capacity than would benecessary if smaller placements were used. For manysmaller structures, a plant size that will prevent cold jointswill be too small to meet the tentative construction progressschedule. Regardless of the daily requirements, the plantcapacity has to be such that fresh concrete does not remainin the form prior to placement of contiguous concrete longenough to develop a cold joint. The time that concrete mayremain in the form before a cold joint develops is highlyvariable. For example, in warm dry climates the time mayhave to be reduced 50 percent or more. The time may beextended by the use of a retarder (ASTM C 494 (CRD-C87)). As a rule of thumb for initial computation, 2 hr maybe considered the maximum time that cooled concrete isuncovered before a cold joint will form between theconcrete in place and the new concrete. For uncooled massand structural concrete, 1 hr is the maximum time that itshould be uncovered. A cold joint is defined as concretethat is beginning to set and in which a running vibrator willnot sink under its own weight and a hole is left in theconcrete when the vibrator is slowly withdrawn. When acold joint is formed, concrete placement should be stoppedand the cold joint should then be treated as anotherconstruction joint. The selection of the plant size shouldprovide adequate safety factors to cover the variables.

(2) Traditional placing method. For massive structuressuch as locks and dams, the traditional placement methodhas been buckets that are moved on trucks and placed withcranes. There should be a limit of 4 yd3 as the maximumamount of concrete placed in one pile prior to theconsolidation. A typical lift height of 5 or 7-1/2 ft with anapproximate horizontal layer thickness of about 1-1/2 ftwould require five successive horizontal layers in steppedprogression in 7-1/2-ft lifts and three successive horizontallayers in stepped progression in 5-ft lifts.

(3) Equation for minimum placing capacity. Theminimum plant capacity may be estimated by using thefollowing equation or by calculating graphically asillustrated in paragraph 3-1e(4):

(3-1)

whereQ = Plant capacity, yd3/hrW = Width of placement (monolith), ftB = Bucket size, yd3

b = Width of block per bucket, ft. A block isassumed to be a square with a heightequal to approximately 1-1/2 ft. For 4-yd3

bucket, b = 8-1/2 fth = Maximum time before cold joint forms,

hr. For estimating purposes, use h = 2 forcooled concrete and h = 1 for uncooledconcrete.

n = Number of layers per lift, normally threelayers for 5-ft lift and five layers for7-1/2-ft lift.

(4) Graphic calculation of minimum placing capacity.Figures 3-1 and 3-2 illustrate graphically the placingsequences for 7-1/2- and 5-ft lifts, respectively, with a 4-yd3

bucket. As shown in Figure 3-1, the required plant outputwill reach the maximum after 60 buckets of concrete havebeen placed. Each bucket placed after 60 buckets will beexposed, while 36 additional buckets are being placed.Therefore, for cooled mass concrete while each placementmay be exposed for 2 hr before cold joint forms, therequired minimum plant capacity will be 36 × 4 = 144 yd3

in a 2-hr period or 72 yd3 per hour. In Figure 3-2, where a5-ft lift is used, the maximum plant output will be reachedat the sixteenth bucket, and 20 buckets will be placed beforeit will be covered. Therefore, for cooled concrete, therequired minimum capacity will be 20 × 4 = 80 yd3 in a

3-2

Page 39: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Figure 3-1. Stepped placement sequence and plant capacity, 7-1/2-ft lift height

3-3

Page 40: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Figure 3-2. Stepped placement sequence and plant capacity, 5-ft lift height

3-4

Page 41: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

2-hr period or 40 yd3 per hour. The same results can beobtained from Equation 3-1.

(5) Other placing methods. If other placing techniquesare likely to be used such as a pump or conveyor, the plantcapacity has to be adequate to supply the unit at a rate nearits rate capacity to avoid plugs or segregation. The capacityof the plant and placing equipment will have to be adequateto prevent cold joints in the placements. The capacitycalculated for bucket placement may be used as a beginningpoint for plant capacity calculations.

f. Conveying and placing considerations.Historically, most concrete for Corps structures has beenplaced by crane and bucket. Recently, however, thepreferred placing equipment has changed, and conveyors andpumps are being used to place an increasing amount of massand structural concrete, respectively. Mixture proportions,conveying methods, and placing restrictions must beconsidered for each portion of the project during PED toassure that appropriate concrete is placed in each feature.For example, it is impossible to pump lean mass concretewith 75-mm (3-in.) maximum size aggregate, and thereforebuckets, or conveyors must be used. The proportions of theconcrete mixtures must meet the designer’s requirements forstrength, slump, maximum size aggregate, etc., and must becapable of being placed by the Contractor. The mixtureproportions should not be altered to accommodate aContractor’s placing equipment if the designer’srequirements would be compromised.

g. Use of epoxy resins.All epoxy resin shall bespecified to meet ASTM C 881 (CRD-C 595). The typeand grade for specific uses should be as follows:

Dowels in drilled holes Type IV, Grade 3Patching and overlays Type IIIBonding new concrete

to old Type V

Crack injection Type IV, Grade 1

Refer to ASTM C 881 for the correct "class" for use at theanticipated temperature of the surface of the hardenedconcrete. During cooler weather, the epoxy resin should bestored at room temperature for several days prior to use.

3-2. Special Studies

a. General. Often it will be necessary to conducttests that extend in scope beyond those listed above. Theneed for such tests may develop as a result of the size or

complexity of a project, an unusual characteristic of theavailable cementitious materials or aggregates or theclimatic conditions at a project site. The most commonlyrequired studies are thermal studies followed by abrasion-erosion studies and mixer grinding studies. Such studies,when required, should be identified during the feasibilityphase and funding and scheduling should be included in theproject management plan. The results of these studies willbe documented in the appropriate DM.

b. Thermal studies. During the PED for projectsinvolving concrete structures, it is necessary to assess thepossibility that temperature changes in the concrete willresult in strains exceeding the strain capacity of theconcrete. Although temperature control is generallyassociated with large mass-concrete structures, it should benoted that small, lightly reinforced structures may also crackwhen subjected to temperature extremes. Therefore, thermalstudies are required for any important concrete structure.This may include, but not be limited to, dams, locks,powerhouses, and large pumping stations.

(1) Material properties needed for a thermal study.The following concrete material properties should bedetermined. Information on cost and time requirements forthe following material properties tests may be obtained fromCEWES-SC.

(a) Heat of hydration. The heat generated will dependon the amount and type of cementitious materials in theconcrete. The heat of hydration is obtained experimentallyand forms part of the basis for predicting the temperaturerise and decline with time for a concrete (ASTM C 186(CRD-C 229)).

(b) Adiabatic temperature rise. The temperature risein concrete under adiabatic conditions is determinedaccording to CRD-C 38. The cementitious material typesand aggregates in the concrete so tested should be similar tothose proposed for use in the structure.

(c) Thermal conductivity. Thermal conductivity is ameasure of the ability of the material to conduct heat andmay be defined as the ratio of the rate of heat flow to thetemperature gradient. Numerically, thermal conductivity isthe product of density, specific heat, and diffusivity.

(d) Thermal diffusivity. Thermal diffusivity is ameasure of the facility with which temperature changes takeplace within a mass of material (CRD-C 37); it is equal tothermal conductivity divided by specific heat times density.

3-5

Page 42: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(e) Specific heat. Specific heat is the amount of heatrequired per unit mass to cause a unit rise of temperature,over a small range of temperature (CRD-C 124).

(f) Coefficient of thermal expansion. The coefficientof thermal expansion can be defined as the change in lineardimension per unit length per degree of temperature change(CRD-C 39, 125, and 126).

(g) Creep. Creep is time-dependent deformation dueto sustained load (ASTM C 512 (CRD-C 54).

(h) Strain capacity. The ultimate tensile straincapacity of concrete is determined by measuring the unitstrain at the outer fibers of unreinforced beams tested tofailure under both rapid and slow loading (CRD-C 71).

(2) Time of completion of thermal study. The thermaland mechanical properties of the concrete are verydependent on the mineralogical composition of theaggregates and the cement type used. Therefore, it isimperative that thermal studies not be undertaken until suchtime as the aggregate investigations have proceeded to thepoint that the most likely aggregate sources are determined,and the availability of cementitious material is known. Ifchanges occur related to the aggregate source or the type ofcementing material as a result of the Contractor exercisingoptions, supply difficulties, or site conditions, it may benecessary to rerun a portion of the study to verify the earlierresults. The initial study must be completed before plansand specifications are finalized.

(3) Temperature control techniques. All thetemperature control methods available for consideration havethe basic objective of reducing temperature rise due to allfactors including heat of hydration, reducing thermaldifferentials within the structure, and reducing exposure tocold air at the concrete surfaces which would create a sharpthermal differential within the structure. The most commontechniques, in addition to selection of slow heat-gaincementitious materials, are the control of lift thickness,placing interval, maximum placing temperature, and surfaceinsulation. On very large structures, post cooling has beenused (ACI 224R).

(4) Numerical analysis of temperature controltechniques. The analysis of the various temperature controltechniques to determine the combination best suited to aparticular project may be done by computer using a finite-element analysis program. Interdisciplinary coordinationbetween materials engineers, structural engineers, andconstruction engineers is essential to ensure that thecomplex numerical analysis is based on reliable concrete

and foundation properties and realistic constructiontechniques. Requests for consultation and assistance inperforming numerical analysis should be made toCECW-EG. For structures of limited complexity, such asbase slabs, satisfactory results may be obtained by the useof equations in ACI 207.4R.

c. Abrasion-erosion studies.

(1) General. Damage to the floor slabs of stillingbasins due to abrasion by waterborne rocks and other debrisis a constant maintenance problem on existing Corpsprojects. Abrasion-erosion on various projects has rangedfrom a few inches to 10 ft, and on occasion, severe damagehas been noted after only a few years of operation.Hydraulic characteristics have a large effect on erosion andabrasion and should be considered in the design ofspillways, conduits, and stilling basins.

(2) Test method. An underwater abrasion test method,ASTM C 1138 (CRD-C 63), is available to allowcomparisons between materials proposed for use in stillingbasins. Results of tests with several types of materialscommonly thought to offer abrasion resistance suggest thatconventional concrete of the lowest practical w/c and withthe hardest available aggregates offer the best protection fornew construction and for repair to existing hydraulicstructures where abrasion-erosion is of concern. Theabrasion tests should be performed to evaluate the behaviorof several aggregate types for use in the stilling basin whenmore than one type is available.

(3) Application of test results. Because the costs ofstilling basin repair is often substantial, it may provefeasible to import aggregate over a long distance for theconcrete in the stilling basin slab if the aggregate in theproject area is soft and the results of the abrasion test showsthe potential for severe erosion. A discussion of stillingbasin erosion should be included in the concrete materialsDM. In some cases where hard aggregate is noteconomically available, silica-fume concrete with very highcompressive strength may be used. Apparently, thehardened cement paste in the high-strength silica-fumeconcrete assumes a greater role in resisting abrasion-erosion,and as such, the aggregate quality becomes correspondinglyless important.

d. Mixer grinding studies.During the investigationof an aggregate, it may be determined that the materialdegrades during handling and mixing. The tendency may befirst noted as a high loss in the Los Angeles abrasion test(ASTM C 535 (CRD-C 145)). The result of this degradingis a significantly finer aggregate, and the result will be a

3-6

Page 43: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

loss of slump during mixing which will result in an increasein water demand. Tests should be run by mixing the actualmaterials for a time similar to that anticipated on the projectand the mixture proportion adjusted to reflect the finergrading of the aggregate.

e. Concrete subjected to high-velocity flow of water.

(1) General. Wherever concrete surfaces are to besubjected to water velocities in excess of 40 ft/s for frequentor extended periods, special precautions should be taken.Examples of such surfaces include conduits, sluices, tunnels,spillway buckets, spillway faces, baffles, and stilling basins.

(2) Quality of concrete. The concrete should haveexcellent workability and a low w/c as indicated in Table4-1. The nominal maximum size of aggregate should belimited to 37.5 mm (1-1/2 in.) except for the formed por-tions of the downstream face of spillways for gravity damswhere the maximum size aggregate may be up to 75 mm(3 in.). In many projects, a special layer of high-qualityconcrete, at least 1-ft thick, is specified to be placed over alower quality concrete. This is done to keep the overall heatof hydration lower and for economy. The thickness of high-quality concrete adjacent to the critical surface should be thepractical minimum that can reasonably be obtained withconventional placing equipment and procedures, but in nocase less than 1 ft. The high-quality concrete should beplaced integrally with the normal concrete.

(3) Construction joints. Wherever possible, construc-tion or lift joints should be avoided in the water passages.Where joints cannot be eliminated, care must be exercisedduring the construction to obtain required alignment andsmoothness within the specified tolerance. For example,grade strips should be used at the tops of lifts to guide theplacement. After the concrete has been placed to grade, thestrip should be promptly removed and the lift surfaceadjacent to the form should be smoothed to provide an evenjoint when the overlying lift is placed.

(4) Unformed surfaces. Unformed surfaces subjectedto a high-velocity flow of water should be finished with asteel trowel finish with no abrupt edges, pits, or roughness.

(5) Formed surfaces. Formed surfaces should begiven a Class AHV finish. See paragraph 5-4e fordefinitions of classes of finish.

f. Unusual or complex problems.Occasionally duringdesign or construction, problems may be encountered whichrequire specialized knowledge not available within thedistrict or division organization. At this point, considerationshould be given to obtaining the services of CEWES-SC.The selection of a consultant knowledgeable in concretematerials will be made with the advice of the Office of theChief of Engineers, ATTN: CECW-EG.

3-7

Page 44: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 4Mixture Proportioning Considerations

4-1. Selection of Concrete Mixture Proportions

The selection of concrete mixture proportions is animportant step in obtaining economical, durable concretemeeting design requirements. Depending on the types ofstructures, the concrete mixture proportions may be selectedby the Government or by the Contractor. When mixtureproportions are to be selected by the Government, the workwill be accomplished by a division laboratory. Proportionsfor mass concrete or structural concrete are to be selected inaccordance with ACI 211.1 (CRD-C 99) and other criteriaas described in the following paragraphs of this chapterwhether the work is done by the Government or theContractor. Any new materials proposed for use after theinitial mixture proportioning studies must be proportionedby the division laboratory or the Contractor’s commerciallaboratory using actual project materials in a new mixtureproportioning study.

4-2. Basis for Selection of Proportions

a. General. The process of selecting concretemixture proportions is a process of optimization of severaldesirable characteristics based on the project requirements.The characteristics to be optimized are economy, strength,durability, and placeability.

b. Economy. The primary reason for systematicallydetermining mixture proportions is economy. Themaximum economy can be achieved by minimizing theamount of cement used and where appropriate, by replacingportland cement with usually less expensive pozzolan orGGBF slag. Economy is also improved by using the largestnominal maximum size aggregate consistent with thedimensional requirements of the structures on the project,and available to the project.

c. Strength.Strength is an important characteristic ofconcrete but other characteristics such as durability,permeability, and wear resistance may be equally or moreimportant. These may be related to strength in a generalway but are also dependent on other factors. For a givenset of materials, strength is inversely proportional to the w/c.Since the materials which make up concrete are complexand variable, an accurate prediction of strength cannot bebased solely on the selected w/c but must be confirmed bytests of cylinders made from trial batches with the materialsto be used on the project. Strength at the age of 28 days isfrequently used as a parameter for structural design,concrete proportioning, and evaluation of concrete. When

mass concrete is used, the design strength is generallyrequired at an age greater than 28 days, generally 90 days,because mixtures are proportioned with relatively largequantities of pozzolan or GGBF slag to reduce internal heatgeneration. The early strength of mass concrete will be lowcompared to that of structural concrete; therefore, massconcrete should be proportioned for an adequate earlystrength as may be necessary for form removal and formanchorage. A compressive strength of 500 psi at 3 days ageis typical of that necessary to meet form-removal and form-anchorage requirements.

d. Durability. Concrete must resist deterioration bythe environment to which it is exposed, including freezingand thawing, wetting and drying, chemical attack, andabrasion. Concrete must meet three requirements before itmay be considered immune to frost action. It must be madewith nonfrost-susceptible aggregates and a proper air-voidsystem, and it must achieve an appropriate degree ofmaturity before repeated freezing and thawing is allowed totake place while the concrete is critically saturated. Aproper air-void system is achieved by using an AEA. Allexposed concrete placed by the Corps should be airentrained unless it is shown to be improper for a specificsituation. The appropriate maturity exists when the concretehas a compressive strength of approximately 3,500 psi.Generally, durability is also improved by the use of a loww/c since this reduces permeability and the penetration ofaggressive liquids.

e. Placeability. Placeability, including satisfactoryfinishing characteristics, encompasses traits described by theterms "workability" and "consistency." Workability is thatproperty of freshly mixed concrete which determines theease and homogeneity with which it can be mixed, placed,consolidated, and finished. Consistency is the relativemobility or ability of freshly mixed concrete to flow.Workability embodies such concepts as moldability,cohesiveness, and compactability and is affected by thegrading, particle shape, and proportions of aggregate; thequantities and qualities of cementitious materials used; thepresence or absence of entrained air and chemicaladmixtures; and the consistency of the mixture. The slumptest, ASTM C 143 (CRD-C 5), is the only test commonlyavailable to measure any aspect of the several characteristicsincluded in the term "placeability." Moldability,cohesiveness, compactability, and finishability are mostlyevaluated by visual observation, and, therefore, theevaluations are somewhat subjective. Typically, theContractor will evaluate these characteristics from adifferent perspective than the government personnelinvolved, and within the Contractor’s organization, theplacing foreman may evaluate the placeability differently

4-1

Page 45: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

than the finishing foreman. In general, the Contractorwould like a high-slump mixture, while the Governmentdesires a closely controlled slump. The key considerationmust be a carefully proportioned concrete mixture which isplaceable by the conveying and placing equipment to beused on the project without the addition of water at theplacement site. Simply adjusting the water content of amixture that was proportioned for placement by crane andbucket will not assure that it is pumpable or that such anadjustment will result in concrete that meets strength anddurability requirements. Mass concrete mixtures areparticularly susceptible to placing problems if not correctlyproportioned. Care must be exercised to assure that themortar content of lean, mass concrete mixtures is sufficientto provide suitable placing and workability. Water-reducing admixtures should not be used to reduce the pastecontent and the resulting mortar content of these mixtures toa level which causes the mixture to be harsh andunworkable.

4-3. Criteria for Mixture Proportioning

a. General. The criteria for proportioning should bedetermined by the designer based upon the design andexposure requirements and conditions for the structureinvolved. Several sets of mixture proportioning criteria maybe required for each structure to meet different designrequirements. These criteria should be transmitted to theresident office as outlined in paragraph 6-2, "EngineeringConsiderations and Instructions for Construction FieldPersonnel."

b. Proportioning criteria.

(1) Maximum permissible w/c. The w/c of bothstructural and mass concrete should satisfy the requirementsof Table 4-1.

(2) Structural concrete. For each portion of thestructure, proportions should be selected so that themaximum permitted w/c is not exceeded and to produce aninitial average compressive strength, fcr , exceeding thespecified compressive strength, f′c , by the amount required.Where a concrete production facility has test records, astandard deviation shall be established. Test records fromwhich a standard deviation is calculated:

• Shall represent materials, quality control procedures,conditions similar to those expected and changes inmaterials, and proportions within the test records shall nothave been more restricted than those for the proposed work.

• Shall represent concrete produced to meet a specifiedstrength or strengths f′c within 1,000 psi of that specifiedfor the proposed work.

• Shall consist of at least 30 consecutive tests or twogroups of consecutive tests totaling at least 30 tests.

A strength test should be the average of the strengths of twocylinders made from the same sample of concrete and testedat 28 days or at some other test age designated . See ACI318 for a more detailed discussion.

(a) Required average compressive strength fcr usedas the basis for selection of concrete proportions shall be thelarger of the following equations using the standarddeviation as determined in paragraph 4-3b(2):

fcr = f ′c + 1.34s

fcr = f ′c + 2.33s - 500

where s = standard deviation

(b) Where a concrete production facility does not haveenough test records meeting the requirements above, astandard deviation may be established as the product of thecalculated standard deviation and a modification factor fromTable 4-2.

(c) When a concrete production facility does not havefield strength test records for calculation of standarddeviation, the required average strength fcr shall bedetermined from Table 4-3.

(d) Evaluation and acceptance of concrete. Thestrength of the concrete will be considered satisfactory solong as the average of all sets of three consecutive testresults equal or exceed the required specified strength f′cand no individual test result falls below the specifiedstrength f′c by more than 500 psi. If the above criteria arenot met, the resident engineer will notify the designerimmediately so that the impact of the low strength may beevaluated. A "test" is the average of two companioncylinders, or if only one test cylinder is made, then a "test"is the strength of the one cylinder.

(3) Mass concrete. For mass concrete, the proportionsselected for each quality of concrete for the project shall notexceed the maximum permitted w/c. Although there istypically a strength requirement for mass concrete, e.g.2,000 psi at 1 year, the maximum-permitted w/c for

4-2

Page 46: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 4-1

Maximum Permissible Water-Cement Ratio (Notes 1 and 2)

Water-Cement Ratios by Mass (for Concrete Containing Cementitious Materials Other

Than 100% Portland Cement, See Note 3)

Severe or Moderate Climate

(Note 4)

Mild Climate, Little Snow/Frost

(Note 4)

Location of Structure

Thin Section

(Note 5) Mass Section

Thin Section

(Note 5) Mass Section

At the water line in hydraulic or waterfront

structures where intermittent saturation is

possible (includes upstream face of dams,

downstream face in overflow sections on dam

where spillage occurs once per year or more

often, and exposed surfaces of lock walls)

0.45 0.50 0.55 0.60

Interior of dams and lock walls and interior of

other large gravity structures where use of two

classes of concrete is practical

-- 0.80 -- 0.80

Ordinary exposed structures, downstream face

of nonoverflow section of dams, downstream

face in overflow section where frequency of

overflow is less than once per year.

0.60 0.60 0.60 0.65

Complete continuous submergence in water

after placement "in the dry" (includes upstream

face of dams below minimum pool elevation)

0.60 0.65 0.60 0.65

Concrete deposited in water 0.45 0.45 0.45 0.45

Pavement slabs on ground:

Wearing slabs

Base slabs

0.50

0.60

--

--

0.55

0.60

--

--

Exposure to sulfate ground water or other

aggressive liquid or salt

0.45 0.45 0.45 0.45

Concrete subjected to high (more than 40 ft/s)

velocity flow of water

0.45 0.45 0.45 0.45

Stilling basins (for flood control and other high-

velocity flow structures)

0.45 0.45 0.45 0.45

Note 1. For all concrete placed in or exposed to seawater, the w/c should be reduced 0.05 below values shown in the table but not lower than

0.45.

Note 2. Mixtures should be proportioned by the division laboratory at the maximum specified slump and air content. They should also be

proportioned at w/c’s 0.02 less than the value shown in the table to allow for batching variability in the field.

Note 3. Where cementitious materials in addition to portland cement are used, the water-cementitious material ratio required is that which would

be expected to give the same level of compressive strength at the time the concrete is exposed to the design environment as would be given

by a mixture using no cementitious material other than portland cement.

Note 4. See Figure 4-1.

Note 5. Largest dimension is 12 in. or less.

4-3

Page 47: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

4-4

Page 48: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 4-2

Modification Factor for Standard Deviation

No. of Tests1

Modification Factor

for Standard Deviation

Less than 15 See Table 4-3

15 1.16

20 1.08

25 1.03

30 or more 1.00

1Interpolate for intermediate numbers of tests.

Table 4-3

(See ACI 318, Table 5.3.2.2)

f ′c fcr

Less than 3,000 psi f ′c + 1,000

3,000 - 5,000 psi f ′c + 1,200

More than 5,000 psi f ′c + 1,400

acceptable durability will often have a correspondingstrength in excess of this value when the mixture meets thecriteria in Table 4-1. Concrete that will be subjected torepeated freezing-and-thawing cycles while criticallysaturated with water must have developed a strength ofabout 3,500 psi before being allowed to freeze and thaw. Ifthe maximum values in Table 4-1 are not low enough toensure this strength under the anticipated environmentalconditions and required duration of curing and protection,then the w/c (or water-cementitious material ratio) must belowered or the required duration of curing and protectionincreased. To ensure that no more than 2 in 10 tests fallbelow the strength corresponding to the required w/c, therequired average strength is determined as follows:

fcr = f ′c + ts

where

t = 0.854 for 30 tests or less; 0.842 if more than 30tests are available

s = standard deviation

Where results of fewer than 30 tests are available, theaverage strength should exceed f′c by 600 psi. Mixtureswill be proportioned to meet the required average strengthexcept where the required w/c provides strength in excess ofthe design strength. The basis for the equation and thecomputation of standard deviation is found in ACI 214.

(4) Nominal maximum aggregate size. The nominalsize of aggregate recommended for various types ofconstruction is listed in Table 2-2.

(5) Water content. The water requirement is afunction of the nominal maximum size aggregate, theaggregate grading, the required air content, and the requiredslump. Given these parameters, the approximate starting

4-5

Page 49: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

water content for mixture proportioning studies can bedetermined from Table 6.3.3 of ACI 211.1. In the range ofnormal concretes, a given combination of aggregatesrequires an approximately constant amount of water percubic yard of concrete for a given slump regardless of thew/c. In mass concrete, the water requirement is maintainedlow by the use of a large nominal maximum aggregate sizeand by the close control of grading.

(6) Cement content. The quantity of cementitiousmaterials will be determined based on the maximum w/cand the estimated water requirement selected for the portionof the structure involved. In mass concrete, the usual lowwater requirement results in a low cement requirementwhich is one of the means of reducing the amount of heatdeveloped by hydration.

(7) Proportioning with pozzolans or GGBF slag.Major economic and temperature rise benefits are derivedfrom the use of pozzolans, blended cement, or GGBF slag.Therefore, concrete should be proportioned with themaximum amount of these materials that will satisfy thestructural, durability, and other technical requirements asappropriate and be economically beneficial. Use ofpozzolans and GGBF slag in mass concrete provides apartial replacement of cement with a material whichgenerally generates less heat at early ages. The effects ofthese materials on the properties of freshly mixed concretevary with the type and fineness; the chemical, mineralogical,and physical characteristics of the material; the fineness andcomposition of the cement; the ratio of cement to pozzolanor GGBF slag; and the total mass of cementitious materialused per unit volume of concrete. Often, it is found that theamount of mixing water required for a given concrete slumpand workability is lower for mixtures containing pozzolansor GGBF slag than for those containing only portlandcement. Air-entraining admixture needs may be reduced byup to approximately 20 percent or increased by over 60percent depending on the characteristics of the pozzolan orslag. Therefore, it is important to evaluate the pozzolan orslag using representative material samples during thelaboratory mixture proportioning study. The dosage rate ofchemical admixtures should generally be based on the totalamount of cementitious material in the mixture. Theproportion of cement to pozzolan or GGBF slag depends onthe strength desired at a given age, heat considerations, thephysical and chemical characteristics of both cement andcement replacement material, and the cost of respectivematerials. As a safety precaution against the possibility ofincreased alkali-silica reaction in concrete containing small(pessimum) amounts of certain pozzolans, the quantities offly ash and natural pozzolan used in concrete should not be

less than 15 percent by mass of total cementitious material.ASTM Type I (PM) should not be specified because of thepossibility that it would contain the pessimum amount ofpozzolan. The selected replacement quantities should bediscussed in the concrete materials DM. This guidance willthen be used by the division laboratory to proportion projectconcrete mixtures using materials submitted by theContractor. Due to differences in their densities, a givenmass of pozzolan or slag will not occupy the same volumeas an equal mass of portland cement. The determination ofw/c, by absolute volume equivalency, when pozzolan or slagis used is described in ACI 211.1.

4-4. Government Mixture Proportions

a. General. When concrete is being placed in astructure requiring the use of the guide specification formass concrete, CW-03305, the mixture proportions aredetermined at a division laboratory using materials providedby the Contractor which are representative of those to beused in the project. Those division laboratories authorizedto test concrete materials are listed in ER 1110-1-8100,"Laboratory Investigations and Materials Testing."Proportions for mass concrete or structural concrete are tobe selected in accordance with ACI 211.1 and other criteriaas described in the following paragraphs of this chapter.

b. Coordination between project, district designpersonnel, and the division laboratory.The criteria forproportioning the concrete mixtures to meet the requirementof each type of concrete required in a project is provided tothe project personnel in detail in paragraph 6-2,"Engineering Considerations and Instructions for FieldPersonnel." The project personnel should notify the divisionlaboratory of the required proportioning criteria at the timethat the samples are transmitted from the Contractor to thelaboratory. Much time is lost when several tons ofaggregate and cement are delivered with no previousnotification by Corps project personnel that the material wascoming and no indication of proportioning criteria required.Since the specification indicates when the Contractor shouldexpect starting mixtures after he submits his materialssamples, close coordination between the Corps personnel onthe project and in the division laboratory is essential, notonly to assure that mixture proportions meet the projectneeds but also to avoid delay claims by the Contractor. The"Guide Specification for Mass Concrete," CW-03305,requires the designer or specification writer to state thenumber of days prior to the start of concrete placing thatmaterials for mixture proportioning studies must besubmitted to the division laboratory. Timely submittal ofthese materials is the responsibility of the project office.

4-6

Page 50: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

c. Sampling of materials. Guide SpecificationCW-03305 outlines the procedure by which samples are tobe taken by the Contractor for mixture-proportioning studies.The Contractor is required to test the aggregates for qualityand grading before shipment to the laboratory. Thesesamples are to be taken under the supervision of theContracting Officer. It is important that this requirement isfollowed. The most common problems arising from lack ofattention to these details are samples arriving at the divisionlaboratory which do not meet project grading requirementsor are not representative of the materials that are actually tobe used or both. Both problems may lead to delays ofconcrete placements or the necessity for considerable fieldmodification of the mixture proportions. The divisionlaboratory should test submitted materials to determine thatthey meet specification requirements prior to using them todevelop mixture proportions. The need for the samples thatare submitted to be representative extends to all thematerials in the concrete, including cement, pozzolans,GGBF slag, and chemical admixtures.

d. Data supplied by division laboratory to project.For each type of concrete required on the project, thedivision laboratory should select initial proportions thatsatisfy the mixture criteria provided by the projectpersonnel. The batch amounts of each constituent in a cubicyard should be reported in the saturated-surface dry (SSD)condition. The amounts of chemical admixtures such as air-entraining and water-reducing admixtures will be reportedas fluid ounces per 100 lb of cementitious materials.Strength data will be provided for each type of concrete tothe extent that it is available by the time the proportions aretransmitted to the project. As a minimum, 24-hour, 7-day,28-day, and design-age strengths should be available priorto the start of placement. A regression analysis ofaccelerated strength at a later age should be computed todetermine the correlation coefficient and 95 percentconfidence limits (see ACI 214.1R). The mixtureproportions provided for each type of concrete shouldinclude a family of curves of strength versus water-cementitious materials ratio at various ages.

e. Adjustment of government mixture proportions.The mixture proportions provided by the division laboratoryprovide starting mixtures meeting the project criteria.However, when these proportions are used in the firstbatches of concrete produced by the Contractor’s plant, it isnot uncommon for the concrete to be deficient in one ormore of the control parameters of the specifications. Themost common deficiency is in the slump. The laboratorywill report mixture proportions based on the aggregates inan SSD condition. A common cause of an increase inslump is the failure to properly adjust for free moisture in

the aggregate, particularly the fine aggregate. Low slumpis normally not a problem if concrete is batched and mixedon site unless rapid slump loss occurs. Variations in thechemical or physical properties of cement or pozzolan arethe most common causes of rapid slump loss althoughtransporting and placing operations may also contribute tothe problem. Assuming all materials and transporting andplacing equipment and operations meet specificationrequirements, the most practical solution for dealing withrapid slump loss is to increase the slump at the mixer to thedegree necessary to have a slump at the forms which iswithin the specification limits. The w/c should bemaintained constant if the slump is increased. Care shouldbe taken to determine if the addition of cementitiousmaterials necessary to maintain a constant w/c willdetrimentally affect the thermal properties of the concrete ornullify results of a thermal stress analysis. Adjustments ofthe dosage of air-entraining admixture by the Contractor arerequired as needed to maintain air contents within thespecified range. As gradings of individual coarse aggregatesize groups change, the proportions of the size groupsshould be adjusted so that the combined coarse aggregategrading approximates the maximum density grading. Themaximum density grading may be computed using EquationA5.3 in ACI 211.1. As the combined coarse aggregategrading approaches the maximum density grading, the voidcontent of the mixture is reduced and more mortar isavailable for placeability, workability, and finishability.Solution of the percentage of each size group can usually bedone such that the combined coarse aggregate grading isgenerally within 2 or 3 percent of the maximum densitygrading. Trial and error may be used in selecting thepercentage of each size group necessary to produce acombined coarse aggregate grading which approximates themaximum density grading; however, proprietary computerprograms are also available. Contact CECW-EG for theavailable computer programs. Adjustments in thepercentage of fine aggregate is less common, but slightchanges may be necessary to compensate for significantchanges in grading over an extended period of production.Adjustments to government mixture proportions are to bemade by government personnel. Changes in aggregate andwater batch weights to compensate for free moisture inaggregates are made by the Contractor and are notconsidered adjustments to mixture proportions. Divisionlaboratory personnel should be present and prepared to makeadjustments in mixture proportions when the Contractorinitiates concrete production on a project and after periodsof batch plant shutdown such as winter shutdowns orprolonged strikes. Procedures for making adjustments aregiven in ACI 211.1 and will be made on an absolute volumebasis. The mortar volume should remain constant andchanges in any one mortar constituent such as water, fine

4-7

Page 51: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

aggregate, air, or cementitious material content should becompensated for by changes in another mortar constituentwithout changing the w/c. It is important that adjustmentsto the government mixture proportions be made during plantshake-down, before any concrete is placed in the structure.

4-5. Evaluation of Contractor-Developed MixtureProportions

a. General. The Contractor should submit hismixture proportions for review prior to initiating concreteplacement. The mixture proportions should be developed inaccordance with ACI 211.1.

b. Reviewing contractor submittals.

(1) Minor structures. When the concrete being placedis in a minor structure, the concrete will almost always besupplied by a ready-mixed concrete producer. The mixtureproportions will normally be submitted as a tear sheet fromthe producer’s catalog or as a data sheet from a localcommercial laboratory which was retained at some time toprepare a series of mixtures for the producer to market.Review of these submittals should include a determinationthat the type of cement used, the air-entraining admixture,and the aggregate source are the same as will be used on theproject and that each constituent meets the specificationrequirements. Test cylinder data submitted by theContractor should not be more than 180 days old. The w/c,f ′c, and fcr must satisfy the contract requirements.

(2) Cast-in-place structural concrete. Because thestructures for which this guide specification is applicable areimportant structures involving water control and powerproduction, the specification requirements provided to theContractor for proportioning the concrete mixtures aresimilar to those followed by the division laboratory whenthe Government is required to proportion the mixture. The

review of the submitted mixture proportions should assurethe following:

(a) Cementitious materials. The submitted mixturemust be proportioned using the same cementitious materialsas will be used in the project. This should include type,manufacturer, mill of origin, and time of manufacture. If apozzolan is to be used, the Contractor’s submittal shouldstate whether the percentage of replacement is based onmass or volume.

(b) Aggregate. The aggregate used in proportioningthe mixture should represent the current production ofwhichever source the Contractor selects. Quality tests andgrading test results should be submitted showing that theaggregates meet specification requirements. Batch amountsfor aggregates should be listed in the SSD condition unlesssome other basis is agreed on.

(c) Admixtures. The admixtures used in proportioningthe mixture should be from the same stock that theContractor has purchased for use on the project or from thecurrent stock of the ready-mix producer for the project. Alladmixtures should meet the project specifications and thedosages should be listed.

(d) Test results. The w/c and required strength testresults should be reviewed to assure that they match projectrequirements. Air contents and slumps should be at theupper limits of the specification requirements.

(e) Placeability. The mixtures must be proportionedto provide the necessary placeability for the conveying andplacing equipment that the Contractor proposes to use. Forinstance, concrete that will be pumped may be proportioneddifferently than concrete that will be delivered by crane andbucket, or directly from the truck mixer, or by tremie pipe,etc.

4-8

Page 52: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 5Preparation of Plans and Specifications

5-1. Selection of Guide Specification for Concrete

a. General. The use of guide specifications isprescribed by ER 1110-2-1200, "Plans and Specifications."Guide specifications for concrete are used to ensure that therequirements for concrete construction for all projects willbe consistent and that the concrete produced will be uniformin properties, of required quality, and economical. Thereare several guide specifications available for concrete placedon Corps of Engineers civil works projects. These guidespecifications should be used in every case, with the onlyexceptions being for situations requiring the use of specialconcrete applications not covered in guide specifications.Changes should be limited to minor technical changes unlessapproved in the DM. No changes should be made in theformat. The completion of project specifications will bebased on the approved concrete materials DM.

b. Guidelines for selection.If the project for whichspecifications are being prepared involves mostly massconcrete as in a lock or dam, Guide SpecificationCW-03305, "Mass Concrete," should be used. For animportant structure, other than a lock or dam, such as apowerhouse superstructure, bridge, fish hatchery complex,visitor center, tunnel lining, major pumping station, intakestructure, or other structures appurtenant to embankmentdams where reinforced concrete is required, the GuideSpecification CW-03301, "Cast-in-Place StructuralConcrete," should be used. If the project is a recreationalsite, road relocation, or other project involving smallamounts of concrete in structures such as culvert headwalls,comfort stations, residences, or low headgate structures, theGuide Specification CW-03307, "Concrete (for MinorStructures)," should be used. There may be instances wheremore than one guide specification will be necessary on thesame project. When this is the case, it will be important toprecisely outline in the specification and on the plans whichspecification applies. The Guide Specification CW-03362,"Preplaced Aggregate Concrete," is chiefly applicable forrepairs to damaged or deteriorated concrete structures.

c. Use of state specifications.The specifications of astate agency, such as a highway department, may besubstituted for all or parts of the Guide SpecificationCW-03307, "Concrete (for Minor Structures)," when thework being accomplished will ultimately be operated ormaintained or both by the state in which it is located orwhen savings will result due to the familiarity of localcontractors with the more usual specifications. One areawhere savings may result would be in the substitution of

state requirements for aggregate quality and grading whenit is known that this is the material produced in greatestquantity by local aggregate producers.

d. Use of abbreviated specifications.For very smallconcrete placements, it may be justifiable to use anabbreviated specification of one or two pages in lengthproduced by editing a state specification or the GuideSpecification CW-03307, "Concrete (for Minor Structures)."Such abbreviated specifications should be considered whenthe only concrete on the project is being placed in picnictable bases, light bases, small culvert headwalls, or othersmall noncritical structures.

5-2. Guide Specification "Concrete (for MinorStructures)," CW-03307

a. General. This guide specification providesrequirements for concrete of adequate quality for minorstructures. All concrete must be air-entrained.

b. Cementitious materials options.The intent of theGuide Specification CW-03307, "Concrete for MinorStructures," is to allow the Contractor maximum flexibilityto use locally available cementitious materials. Accordingly,the optional use of blended hydraulic cement would beallowed if such material is reliably available in the projectarea. Low-alkali portland cement would be a specifiedoption if locally available aggregates are known orsuspected to be potentially deleteriously alkali reactive.Increased resistance to sulfate attack may be obtained withblended hydraulic cement by specifying a suffix of MSfollowing the type of designation. All specifications mustallow the use of pozzolan; reference paragraph 2-2 of thismanual.

c. Selection of compressive strength.The requiredspecified compressive strength will be determined by thestructural designer. Normally, a specified compressivestrength (f′c) of 3,000 psi at 28 days is a reasonable andattainable value in rural areas and remote locations wheremany of the minor structures are located. Higher valuesmay be specified if required. The value specified should beconfirmed as adequate by the designer in every case. Ifdurability is a limiting design factor, the maximum w/c shallnormally be limited to 0.50. Lower values may be specifiedif required. See Table 4-1.

d. Selection of nominal maximum aggregate size.Thelargest nominal maximum size aggregate incorporated intothe minor structures intended to be covered by thisspecification is 37.5 mm (1-1/2 in.). If thin sections areinvolved or there is interference from reinforcement,

5-1

Page 53: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

19.0-mm (3/4-in.) nominal maximum size aggregate will bespecified. Generally, for sections 7-1/2 in. or less in width,heavily reinforced floor and roof slabs, and all sectionswhere space is limited and surface appearance is important,19.0-mm (3/4-in.) maximum size aggregate will bespecified. For sections over 7-1/2 in. wide and in which theclear distance between reinforcement bars is at least2-1/4 in., the maximum size aggregate specified shall be37.5 mm (1-1/2 in.).

e. Finish requirements. This guide specificationrequires a floated finish on unformed surfaces with anoptional paragraph for a steel-trowel finish. A float surfacewill be adequate for most of the concrete covered by thisspecification; however, for shop or office floors, other areaswhere frequent cleaning is necessary, and areas to bepainted or covered by other floor coverings, a steel-trowelfinish should be specified.

5-3. Guide Specification "Cast-in-Place StructuralConcrete," CW-03301

a. General.The Guide Specification CW-03301, "Cast-in-Place Structural Concrete," is for use on importantreinforced structures; therefore, it is not intended to beedited except to select available options. Guidance for theselection of the options is provided in the followingparagraphs. Any substantial departures from the guidespecifications must be included in the appropriate DM forapproval.

b. Testing of cementitious materials.Essentially, thereare two options provided in the guide specification to definethe required preconstruction testing or certification ofcement and pozzolan. The procedures to be followed whencements and pozzolan are to be sampled and tested by theGovernment prior to their use in the construction todetermine compliance or noncompliance with thespecifications are specified. The Contractor may also electto use cement or pozzolan from a source which has beenprequalified by the Government. These guide specificationsdefine those conditions that must be met for the acceptanceof cementitious materials on the basis of a manufacturer’scertification of compliance accompanied by mill test reports.The decision to use the more restrictive paragraphs shouldbe based on the criticality of the structure involved.Generally, government testing will be used for powerhousestructures and any structures appurtenant to locks and damsthat control water, to include tunnel lining, large gatestructures, intake structures, stilling basins, and majorbridges. Certification accompanied by mill test reports, willsuffice for fish hatchery structures, maintenance structures,

and others not specifically designed for the control of waterdownstream. If cementitious materials are to be tested bythe Government, the U.S. Army Engineer WaterwaysExperiment Station (ATTN: CEWES-SC) should becontacted for a current cost. Cement or pozzolan sourcesthat are prequalified must also be periodically tested duringconstruction at CEWES-SC, and the tests must be funded.

c. Admixtures and curing compounds. Optionalparagraphs of CW-03301 provide for air-entrainingadmixtures, water-reducing admixtures, and curingcompounds to be accepted on the basis of eitherpreconstruction testing by the Government or certificationsof compliance submitted by the Contractor. The decision asto which option to use for the admixtures or curingcompounds should be based on the criticality of thestructures involved and on past experience with the productsand suppliers in the project area. If problems have occurredon other projects, then the product should be tested by theGovernment to assure compliance.

d. Testing of aggregate.The division laboratory whichwill receive the samples should be contacted and the samplesizes and the number of days required to evaluate theaggregates established. The number of days listed for thetesting of the aggregate should be chosen to be long enoughto provide for unforeseen delays at the laboratory so that theContractor claims which would result if the evaluation weredelayed can be avoided.

e. Nonshrink grout.The type(s) of nonshrink grout tobe used are to be selected by the Contractor in accordancewith ASTM C 1107 (CRD-C 21). The decision as to thetype of nonshrink grout should be based on the application,exposure conditions, and the manufacturer’srecommendations. If severe exposure conditions areanticipated, testing should be performed on the types ofnonshrink grouts specified to assure their adequacy. If theContractor selects a Grade A prehardening volume adjustinggrout, the space to be grouted must be confined on all sides.

f. Cementing materials option. The inclusion orexclusion of available cementing materials options in thepreparation of project specifications must be based on andsupported by the results of the investigations outlined inChapter 2 of this document. The guide specificationsprovide, as options, those types of portland cement andblended hydraulic cements generally used for cast-in placestructural concrete, and the Contractor should be allowed thewidest choice possible subject to specific suitability andavailability. The Contractor must be allowed the option ofusing fly ash.

5-2

Page 54: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

g. Specifying aggregate.The coarse aggregate gradingsand aggregate quality to be specified in the guidespecifications must be based on and supported by theinvestigations outlined in Chapter 2 of this document. TheASTM C-33 (CRD-C 133) sizes selected as options willdepend on the nominal maximum size aggregate availableand appropriate for use in the various project structures asspecified in the guide specifications. The selection of thenominal maximum size coarse aggregate will also be basedon the aggregate investigation. If technically feasible, thesize number selected will correspond to those available inwhatever commercial aggregate sources are listed. Note thatsize No. 1, 2, 3, and 357 will not be specified since thenominal maximum size represented by these designationsexceeds 37.5 mm (1-1/2 in.), and size No. 7 and 8 are for"pea gravel" sizes not normally used in structural concrete.

h. Strength. The paragraph in part one of CW-03301entitled "Design Requirements" lists the strengths requiredfor the various portions of the structure. It is necessary forthe designer to determine what strength is required and theage at which the strength is needed or the design age.Typically, this is 28 days; however, if construction oroperational loads are not anticipated for some longer periodof time, economies can be realized in the concrete byproportioning concrete mixtures to attain design strengths atlater ages such as 90 or 180 days. It should be noted,however, that durability requirements might result in higherstrengths due to the w/c requirements.

i. Batch-plant capacity.The computation of batch-plantcapacity for cast-in-place structural concrete will be basedon an assessment of the likely placement sequence on theproject. See Chapter 3 of this manual for guidance inselecting the batch-plant capacity.

j. Batch-plant controls.The batch-plant control systemspecified for cast-in-place structural concrete may bepartially automatic, semiautomatic, or automatic. Thesemiautomatic plant should be provided with interlocks andrecorders if the project includes major structures. Iftechnically feasible, the batch-plant requirements shouldcoincide with the equipment which is locally available. SeeChapter 3 of this manual for more guidance on selection ofbatch-plant type.

k. Concrete deposited in water. The optionalparagraph, CW-03301, entitled "Placing Concrete Under-water" will be included in all specifications for projectswhich include underwater placement of concrete. Thedecision to use underwater placement in lieu of dewateringmust be discussed in the Concrete Materials DM.

l. Finishing unformed surfaces. Subparagraphs areprovided in paragraph 8-3 entitled "Finishing" to provide anabrasive aggregate finish, a broom finish, or a bonded two-course floor. The abrasive aggregate finish or broom finishshould be applied in those areas where slippery floorsurfaces would present a problem. A bonded two-coursefloor would be an option for a warehouse area or othersurface exposed to heavy loads, traffic, and abrasion.

m. Sheet curing. Sheet curing may be specified forhorizontally finished surfaces such as roof slabs, floors notsubject to public view, or floors that are to be covered withtile or resilient flooring by listing the areas to be so cured.Polyethylene film shall not be used unless it is coated withburlap or other materials.

n. Areas to be painted.If the project includes largeareas of concrete surfaces to be painted, they should beimpervious sheet cured, moist cured, or cured with achlorinated rubber base curing compound specified byreference to ASTM C 309, (CRD-C 304) Class B.

o. Finishing formed surfaces.Optional subparagraphsare included in the paragraph entitled "Formed Surfaces" toprovide for various finishes to achieve desired architecturaleffects. The selection of the optional paragraphs willdepend on architectural requirements. The architecturaldrawings should be consulted when preparing thisparagraph. When extensive use of architectural finishes areplanned, guidance for expanded specifications may beobtained from CECW-EG. ACI 303R is an excellentreference.

p. Floor tolerance. The optional paragraph in part 3,CW-03301, entitled "Slab Tolerance by F-number System"may be used as this technology becomes available in thelocal project area or immediately as a very flat floor isnecessary. Reference the discussion in Chapter 8 of thismanual before specifying the F-number system.

5-4. Guide Specification "Mass Concrete,"CW-03305

a. General. This specification is intended for largecivil works structures of predominately mass concrete.These structures are almost always important water controlstructures. This guide specification is the most restrictive ofthe guides for concrete construction and is intended to beused unedited except for selecting available options, unlessa deviation has been approved in advance in the materialsDM. Guidance for the selections of some of the options isprovided in the following paragraphs.

5-3

Page 55: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

b. Sampling of aggregates.To complete the paragraphin part 2, CW-03305, entitled "Aggregates," CRD-C 100 andthe concrete materials DM should be consulted. Thedivision laboratory that will receive the samples should becontacted, and the sample sizes and the number of daysrequired to evaluate the aggregate confirmed andestablished. The number of days listed for the testing of theaggregate should be chosen to be long enough to provide forunforeseen delays at the laboratory so that the contractorclaims which could result if evaluation were delayed can beavoided. It may be necessary to have some overlap in thetime required for aggregate quality testing and the timerequired for mixture proportioning studies so as to not delaythe start of construction. Close coordination between theproject office and the division laboratory is important.

c. Mixture proportioning studies. Mixtureproportioning studies will be completed at the assignedCorps of Engineers division laboratory. It is necessary toinsert the address of the assigned division laboratory inGuide Specification CW-03305. The quantities required forthe mixture proportioning studies will be furnished by thelaboratory. Materials shipped to the laboratory should beaccompanied by the required contractor’s quality andgrading test reports. Government quality tests should beperformed in the division laboratory as judged necessary,prior to mixture proportioning studies.

d. Testing cementitious materials.Current costs fortesting hydraulic cement, pozzolan, and GGBF slag shouldbe obtained from the Waterways Experiment Station(ATTN: CEWES-SC). The cost for testing of cementitiousmaterials will be included in Guide SpecificationCW-03305. Samples and funding of testing is required eventhough prequalified sources are selected.

e. Surface requirements.Several classes of finish areavailable in CW-03305 to be employed as described in thefollowing paragraphs.

(1) Class A finish. Class A finish is specified forsurfaces of structures where excellent appearance at closerange is important. Examples of Class A finish includeexterior walls of buildings of all types such assuperstructures of powerhouses and pumping plants, interiorsurfaces of such walls when no other finish treatment is tobe added, floodwalls, and parapets, and other ornamentalstructures on dams. The required form materials forClass A finish are limited to new, well-matched tongue-and-groove lumber or new plywood panels as specified in theparagraph entitled "Materials" in Part 2 of CW-03101. Theforms should be clean, tightly set, and securely anchored toprevent grout leaks.

(2) Class AHV finish. Class AHV is for finishesexposed to a high-velocity (greater than 40 fps) flow ofwater. Examples of this type of surface include lock fillingand emptying ports, lock culverts, outlet works, and spillwaytunnels. The forms should be strong and held rigidly andaccurately to the specified alignment. The materials forforms are the same as Class A finish except that steel formsmay be used.

(3) Class B finish. This finish is specified forpermanently exposed surfaces where excellence ofappearance treatment is not as paramount. Examplesinclude concrete dams and appurtenances (except whereClass A finish is required), retaining walls, floodwalls,exposed surfacing of culverts, and outlet works.

(4) Class C finish. This finish is specified for areas thatare not normally exposed to public view but will not bepermanently covered with backfill. Examples includemachinery rooms and interior passageways in large projects.

(5) Class D finish. This finish is specified for concretesurfaces where roughness and irregularities are notobjectionable. Examples include bulkhead faces ofmonoliths in mass concrete structures and surfaces againstwhich backfill will be placed. The chief requirement of theform is that it be watertight.

(6) Absorptive form lining. Absorptive form liningshould not be specified.Numerous problems have resulteddue to the use of absorptive form linings: small air bubblesremaining immediately below a thin surface skin of mortar,form lining sticking to concrete surfaces, and in general, theresults have not justified the extra cost.

f. Appearance. The paragraph in part 3 entitled"Curing and Protection" of CW-03305, "Guide Specificationfor Mass Concrete," provides for those surfaces on whichdiscoloration would be aesthetically undesirable andtherefore need to be removed. The surfaces are thosepermanently exposed to view by the general public. Inareas where the only available curing water is likely to stainor where aggregate impurities contribute to staining, it maybe economically infeasible to prevent or remove all staining,and staining should be removed only on those surfacesconstantly exposed to public view on which staining wouldbe aesthetically troublesome.

g. Cementitious materials option.The inclusion orexclusion of available cementing materials options in thepreparation of project specifications must be based on andsupported by the results of the investigation outlined inChapter 2 of this manual. The guide specification provides

5-4

Page 56: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

for those types of portland cement and blended hydrauliccements generally used for mass concrete and available inthe project area. Consult the materials DM for thosecementitious material options which should be allowed. Theuse of fly ash will be permitted.

h. Bid schedule for cementitious materials options.Provisions should be made in the bid form for optionalbidding on all the available and acceptable cementitiousmaterials. The estimated quantities of portland cement,blended hydraulic cement, and GGBF slag should beexpressed in units of mass. The quantities may varybetween the various cements due to differences in requiredmixture proportions and density. The estimated quantitiesof pozzolans should be expressed in units of solid volume(cubic feet). This allows for variations in density dependenton the source selected by the Contractor. The estimatedquantities of both cement and pozzolan should be derivedfrom information gained in the preparation of preliminarymixture proportions during the preparation of the concretematerials DM.

i. Retarder. The Contractor may use a retarder at hisoption except in areas where retardation is considered to bedetrimental. A retarder is appropriate when uncooledconcrete is to be placed in very hot weather and the placingschedule is such that a danger of cold joints exists orproblems in finishing may be anticipated. Retarders are alsoapplicable to special structures in which revibration will beused to ensure low permeability.

j. Water reducers. The mandatory use of WRA’sshould be restricted to locations where there is an economicadvantage to the Government. A Contractor’s request to usea WRA in structural concrete should be approved unless itsuse is harmful in a given situation. The material shouldmeet the requirements of ASTM C 494, (CRD-C 87) TypeA or D, unless retardation would be detrimental to the work,in which case only Type A should be specified. Since theeconomic benefits resulting from the use of an admixtureusually cannot be evaluated until the Contractor has madehis choice of materials, the bidding schedule should includea split bid for a WRA. The first item includes formobilization and demobilization costs of storing, dispensing,and recording the admixture. When the laboratoryevaluation indicates no economic benefit from use of theadmixture, it is not necessary to approve its use.

k. Fine aggregate grading requirements. Fineaggregate grading is a major factor affecting the unit waterrequirement, fine aggregate-coarse aggregate ratio, andcement content of a concrete mixture. That portion of thefine aggregate finer than the 150-µm (No. 100) sieve has the

most pronounced effect on these factors. While it ispossible to proportion a workable normal strength concretemixture using most naturally occurring sand deposits, thosegradings that fall within the limits listed in the guidespecifications are more practical, generally requiring lesscement and water for adequate workability. Beneficiationof the natural deposits can be accomplished by use ofequipment which will reject a specific size portion or whichwill blend in a finer sand will usually be cost effective.Most natural river sands are deficient in the sizes finer thanthe 150-µm (No. 100) sieve. This fine sand is oftenavailable and used in local asphaltic concrete paving mixes.The finess modulus (FM) is most useful in controlling theconsistency of the fine aggregate during construction. Theproposed fine aggregate grading requirement should bepresented in the concrete materials DM. Whenmanufactured sand is allowed in the project specifications,the optional requirement limiting the amount of materialpassing the 75-µm (No. 200) sieve should be used if theContractor chooses to use manufactured sand. Seeparagraph 2-3b(8) of this manual entitled "Fine AggregateGrading Requirements."

l. Coarse aggregate grading requirements.Wheneverthe maximum aggregate size is less than 150 mm (6 in.), theinapplicable portion of the table on coarse aggregategradings should be deleted in the project specifications.When coarse aggregate is to be supplied from commercialsources in an area where local practice provides size groupseparations other than those in the table, the table may beappropriately modified providing the local grading practicepermits adequate control of grading. The revised gradingshould be presented for approval in the concrete materialsDM. Rescreening and washing will be required for allmass-concrete structures.

m. Batching and mixing plant.

(1) Type of plant. The specifications provide for twoalternates, an automatic batching plant or a semiautomaticbatching plant. The selection of batch-plant type will bebased on and supported by the concrete materials DM. Theparagraph entitled "Equipment" provides the option of anonsite or offsite plant. The selected option will also bebased on the concrete materials design memorandum.(Reference Chapter 3 herein.)

(2) Capacity. The paragraph in part 2 entitled"Capacity" of CW-03305, "Guide Specification for MassConcrete," requires that a minimum capacity for batching,mixing, and placing system be inserted. The determinationof the plant capacity is a part of the preparation of theconcrete materials DM, and the capacity inserted in the

5-5

Page 57: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

specification should be supported by the DM. Chapter 3 ofthis manual gives additional guidance.

(3) Preset mixtures. If an automatic batching system isrequired, it is necessary to indicate the number of presentmixtures that may be produced by the plant. This numbershould be based on the anticipated construction sequenceand the number of different mixtures to be used in thevarious features of the projects at approximately the sametime. For example, on a large dam it is likely that exteriorand interior mass concrete will be placed at the same timebut in different locations. It is also possible that structuralconcrete may be required during the same shift as massconcrete is being placed elsewhere. The number selectedshould be realistic, not excessive simply to avoid the neededplanning and analysis.

(4) Mixers. Any type of stationary mixer may be usedfor mixing concrete containing 75- or 150-mm (3- or 6-in.)nominal maximum size aggregate if it meets the capacityand the uniformity requirements. Concrete containing50-mm (2-in.) and smaller maximum size aggregate may bemixed in stationary or truck mixers.

n. Conveying and placing.

(1) Conveyance methods. Optional paragraphs areprovided to cover belt conveyors and pump placement, andthese should be included in the project specifications, or not,depending on the project. The concrete materials DMshould be referred to when preparing the specificationsparagraphs related to methods of conveyance.

(2) Hot-weather mixing and placing. To reduce theproblems of slump loss and plastic shrinkage cracking,limits are placed on the temperature of the concrete whenplaced. For guidance in selecting the correct placingtemperatures, see Table 8-1 of this manual.

(3) Placing temperature. An optional paragraph ofCW-03305 requires a special placing temperature in certainportions of the structure. The selection of an alternate andthe completion of the blanks within the paragraph chosenshall be based on and supported by the concrete materialsDM or a separate DM on Thermal Studies as outlined inChapter 3 of this manual.

(4) Lift thickness. Lift thicknesses are to be shown onthe drawing which shall show the required and optionalconstruction joints. The maximum lift height for eachportion of the structure will be determined by the thermalstudy and documented in the appropriate DM.

(5) Placing concrete in unformed curved sections. Thisoptional paragraph will be included in all specifications forprojects that include an ogee spillway crest and spillwaybucket.

(6) Concrete deposited in water. This optionalparagraph will be included in all specifications for projectsthat include underwater placement concrete. The decisionto use underwater placement in lieu of conventionaldewatering must be discussed in the concrete materialsdesign memorandum as outlined in Chapter 2 of thisdocument.

o. Finishing.

(1) Unformed surfaces. A steel-trowel finish may bespecified for those areas requiring it by listing the areas inthe paragraph entitled "Trowel Finish" of the guidespecifications. Steel-trowel finishes are generally requiredin areas where cleaning is required such as generator decks,visitor facilities, and shop and office areas. If the floors areto be overlaid with tile, coatings, or coverings, themanufacturer’s recommendations should be consulted whenpreparing the specifications to determine the finishrequirements.

(2) Formed surfaces. The guide specification providesfor four classes of finish for formed surfaces. The requiredclass of finish must be denoted on the project plans. AnAHV (Class A, high velocity) finish will be required on allsurfaces exposed to water velocities of 40 ft/s or higher.

(3) Insulation and special protection. These paragraphsof CW-03305 contain blanks for cold-weather protection.The information inserted in these paragraphs will be basedon and supported by the thermal study. It is also necessaryto determine the age beyond which insulation will no longerbe required. In areas where concrete placement is subjectto a winter shutdown, it should be assumed that all massconcrete placed since the spring startup will be insulatedthroughout the following winter shutdown period unlessresults of the thermal study indicate otherwise.

p. Areas to be painted.If the project includes largeareas of concrete surfaces that will be painted, they shouldbe impervious-sheet cured, moist cured, or cured with achlorinated-rubber base curing compound.

q. Setting of base plates and bearing plates.Theparagraph with this title in CW-03305 with subparagraphsshould be included in the project specifications if the projectincludes base plates or bearing plates. A gas-liberating

5-6

Page 58: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

admixture should be used only when the area is essentiallyconfined.

r. Measurement and payment.The paragraph entitled"Measurement and Payment," CW-03305, will be edited toreflect the outcome of the cementitious materialsinvestigation outlined in Chapter 2 of this EM anddocumented in the concrete materials DM.

5-5. Guide Specification "Formwork for Concrete,"CW-03101

a. General. The Guide Specification CW-03101,"Formwork for Concrete," will normally be included in anyspecification for a project which includes concrete in anyamount. It is included as "related work specified elsewhere"in each of the three guide specifications for conventionallyplaced concrete, CW-03307, CW-03301, and CW-03305.Guidance for preparation of the project specifications isincluded in the following paragraphs.

b. Shop drawings.The number of days that drawingsshall be submitted prior to fabrication should be based onconsultation with construction division personnel in thedistrict to determine a reasonable time.

c. Sample panels.Sample panels are required any timea Class A or a special architectural finish is required.

d. Forms. The areas on the project to receive eachclass of finish will be listed in the specification paragraphentitled "Materials" of CW-03101. This information mustbe taken from structural and architectural drawings.

e. Form removal. Forms will not be removed until aspecified length of time has elapsed and a percentage of theconcrete strength has been reached. The percentage figureto be inserted must be obtained from the structural designer.

5-6. Guide Specification "Expansion,Contraction, and Construction Joints inConcrete," CW-03150

a. General.This guide specification should be includedin any project specification that includes joints in theconcrete.

b. Cost of testing.Preparation of a project specificationbased on this guide specification requires that a divisionlaboratory be contacted and costs obtained for testing field-molded sealants and nonmetallic waterstop. These costs areinserted in specification CW-03150.

5-7. Guide Specification "Precast-PrestressedConcrete," CW-03425

a. General. This Guide Specification CW-03425,"Precast-Prestressed Concrete," is for use on importantstructures which use precast-prestressed members; therefore,it is not intended to be edited except to select availableoptions. Guidance for the section of the options is providedin the following paragraphs.

b. Air content. The decision of whether or not torequire entrained air in precast members must be madebased on a determination of the exposure conditions towhich the members will be subjected both in service and intransit and storage. Generally, air entrainment should berequired in any precast concrete placed in exposed locationswhere freezing of concrete saturated with water is likely tooccur. When this decision is made, the optional paragraphsin the guide specification will be edited accordingly.

c. Tolerances.The optional tolerance paragraphs willbe edited depending on the type of members being procuredby including or excluding those paragraphs which apply tothat type of member.

d. Cement.Guidance for selecting the various optionalrequirements is provided in paragraph 2-2 of this manual.

e. Aggregates. The option is provided if usingaggregates meeting the requirements of ASTM C 33(CRD-C 133) or if economically beneficial and technicallyacceptable, the specifications of a state or local agency maybe used. This would be the case if, for example, the mostlikely source of precast members was heavily involved inproducing units for a large highway department project andhad produced large quantities of aggregate for that purpose.If the material was shown by case history or by testing to beadequate for the need, advantage should be taken of theavailability and the resultant savings rather than forcingproduction of an aggregate meeting a different specificationbut offering no real advantage in concrete quality.

f. Finishing. Optional requirements are provided forthe type of finish depending on architectural or serviceneeds.

5-8. Guide Specification "Preplaced-AggregateConcrete," CW-03362

Preplaced-aggregate concrete is produced by placing a gap-graded coarse aggregate in a form and later injecting a sand-cement-fly ash grout to fill the voids. Its main advantage is

5-7

Page 59: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

its low volume change because of the high coarse aggregatecontent and the point-to-point contact of the coarse

aggregate particles. See paragraph 11-2 of this manual formore information.

5-8

Page 60: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 6Coordination Between Design and FieldActivities

6-1. Bidability, Constructibility, and OperabilityReview

a. General. The requirements for bidability,constructibility, and operability (BCO) reviews are outlinedin ER 415-1-11, "Bidability, Constructibility, andOperability." BCO reviews are to be performed first duringthe review period for the concrete materials DM and againat least 30 days before formal advertisement for bids of aconstruction contract. When concrete construction isinvolved, it is important to assure that qualified personnelfrom the area office or resident office are included in thisreview process.

b. Review guidance. Some of the areas that thepersonnel in the area or resident office provide importantinput for concrete construction to the designers are:

(1) Recommend location of aggregate production orhandling facilities on or near the project site to avoidconflict with future project construction activities.

(2) Recommend location of batch plant on, or near,the project site for maximum efficiency and ease of concretedelivery and placement.

(3) Recommend types of placing equipment to be andnot to be used.

(4) Present special forming and staging requirements.

(5) Recommend potential water sources.

(6) Recommend location of construction joints.

(7) Clarify bidding documents.

(8) Identify potential placement problem areas relatedto the structural shapes, size, and location of reinforcement,location of embedded items, conduits, blockouts, etc.

(9) Submit effects of proposed architecturalrequirements upon constructibility.

(10) Submit effects on the construction schedule ofinsulation requirements, concrete mixtures which developstrength slowly, or other unusual design requirements.

6-2. Engineering Considerations and Instructionsfor Construction Field Personnel

a. General. Subsequent to the award of anyconstruction which involves concrete features, a reportshould be prepared by the designer outlining all specialengineering considerations and design assumptions andproviding instructions to aid the field personnel in thesupervision and quality verification of the constructioncontract. The information provided will, for the most part,summarize the data contained in the DM’s and include allrequired formal discussions on why specific aggregatesources, plant locations, structural designs, etc. were selectedso that the construction personnel in the field will beprovided the necessary insight and background needed toperform reviews of the Contractor’s various submittalproposals and to resolve construction conflicts withoutcompromising the intent of the design. This informationmust not conflict with the project specifications and mustnot contain any request to change these requirements. In allcases, the contract specification will govern.

b. Content. A typical outline for the concreteconstruction part of the report is provided as an aid inpreparing the engineering considerations and instruction forconstruction field personnel:

I. Introduction

A. Purpose

B. Scope

II. Cementitious Materials Requirements orProperties

A. General

B. Availability

III. Aggregate Requirements or Properties

A. General

B. Basis for selection of listed requirements

C. Possible processing requirements

D. Quality assurance testing

IV. Other Materials

6-1

Page 61: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

A. Chemical admixtures

B. Water

(1) Mixing

(2) Curing

V. Concrete Qualities Required at VariousLocations Within the Structures

VI. Concrete Temperature-Control Requirements

VII. Cold-Weather Concrete Requirements

A. Insulation

B. Time length of protection

VIII. Hot-Weather Concrete Requirements

IX. Contractor Quality Control and GovernmentQuality Assurance

X. Critical Concrete Placement Requirements

XI. Architectural Requirements

XII. Finish Requirements

c. Discussion by outline heading.

(1) Introduction. The purpose of the report will bestated here and will also contain a statement on the scope ofthe engineering considerations and instructions forconstruction field personnel. Types of concrete and theareas each type is to be placed are to be discussed.

(2) Cementitious materials requirements or properties.All those cementitious materials that have been included asoptions in the project should be discussed. If any type ortypes of cementitious material may not be used, the basisfor the exclusion must be discussed to provide theconstruction personnel on the site the information requiredto correctly comment on the Contractor’s submittals andproposed substitution of an unacceptable cementitiousmaterial. All quality assurance testing requirements shouldbe discussed, including the required or desired frequency ofonsite sampling.

(3) Aggregate requirements or properties. All theimportant characteristics of the selected aggregate sources

are to be summarized along with the basis for rejection ofany nearby aggregate sources that were investigated andfound to be unsuitable. Other helpful information to beincluded would be an assessment of potential processingrequirements. Potential processing requirements that are tobe discussed are requirements for spray bars and sandclassifiers, requirements to make up a naturally deficientfine or coarse aggregate size, removal of organic material,and processing because of an excess of elongated particlesby a roll crusher should be noted if the processibility studieshave revealed such. The range of aggregate quantityparameters derived from testing of the listed sources mustbe provided to the field so that the results of the qualityassurance and quality control tests during construction canbe compared to the assumed design values. It is especiallyimportant to note the qualities that are critical and thosequalities that are marginal for acceptability of any source.A list of the quality assurance tests to be performed by theGovernment and the desired frequency of testing is to beincluded.

(4) Other materials.

(a) Chemical admixtures. The reasons for allowing ordisallowing the use of retarding, accelerating, water-reducing, high-range water-reducing, or any other commonlyused chemical admixture must be stated.

(b) Water. It must be noted if the concrete materialsinvestigations have shown any problems with the availablesources of mixing and curing water, such as a tendency tostain the concrete or seasonable variations that would beobjectionable.

(5) Concrete qualities required at various locationswithin the structures. The most important objective of thereport is to provide to the construction personnel in the fieldthe quality (type) of concrete required for each structure orspecific portion of a structure. Depending upon the natureof the construction project, this information could bepresented in tabular form or by color coding the appropriateproject drawings. The quality should be designated bymaximum w/c, nominal maximum aggregate size, strengthrequirement, and purpose, such as interior mass, exteriormass, interior structural, exterior structural, backfill,architectural, etc. It should be noted that for isolatedcongested areas the nominal maximum aggregate size mustbe reduced. The basis for the quality requirements, i.e.strength, durability, appearance, etc., is to be stated for eachone listed. The age at which the compressive strength, f′c ,is to be attained should be noted. Other mixtureproportioning requirements which are to be listed are thenominal maximum size aggregate, air content, and the slump

6-2

Page 62: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

range. It should be noted that the concrete should besampled and tested for air, slump, and compressive strengthduring plant shakedown so that any necessary adjustmentsto the laboratory mixture proportions can be made beforeconcrete is placed in the structure. It should also be notedthat sampling for mixture proportioning should be observedby project office personnel to assure that quality and gradingmeet the specifications.

(6) Concrete temperature-control requirements. Iftemperature-control requirements are a part of the projectspecifications, they are to be explained in the report. To themaximum extent possible, this discussion should describethe effects of any changes in the proportioned mixtures uponthe thermal control measures for the project as well as theresults of any changes from the anticipated constructionschedule. If more extensive temperature- control measuresare specified, such as postcooling or postwarming, they areto be described in sufficient detail to allow for timelyreview of the Contractor’s submittals for these systems.The most common methods of temperature control involvespecified maximum or minimum placing temperature,followed by the use of insulation. Some possible methodsthat the Contractor may submit to achieve the specifiedplacing temperatures are to be discussed along with anyknown methods that have been unsuccessful in the past.

(7) Cold-weather concrete requirements. Assumedmethods of achieving the specified results during coldweather are to be discussed in this report. Any specifiedconcretes in the project that require cold-weather protectionin excess of that to ensure freedom from damage of earlyfreezing is to be explained. The use of any specificaccelerators, the keeping of temperature records, heating ofmaterials, foundation preparation, protective insulatingcoverings, heated enclosures, curing, and form removal areto be discussed.

(8) Hot-weather concrete requirements. The assumedmethods of achieving the specified results during periods ofhot weather are to be discussed in this report.

(9) Contractor quality control and government qualityassurance. Contractor quality control (CQC) requirementsare specified in the specification. Government qualityassurance (GQA) sampling and testing requirements shouldbe discussed. These may include, but not be limited to,sampling and testing frequency, sampling size andprocedures, testing methods, and analysis of test results forcementitious materials, aggregate grading, aggregatemoisture, aggregate quality, slump, air content, concretetemperature, and compressive strength.

(10) Critical concrete placement requirements. Allareas of the project that the designer feels require specialmeasures during placement, consolidation, finishing, orcuring are to be discussed in this report. Some examplesare the placement of trunion girders, tunnel linings, bridgedecks, and areas subjected to high-velocity flows of water.

(11) Architectural requirements. All areas where thespecified architectural requirements will affect the concreteplacement are to be discussed in this report. This willinclude all areas where the location of construction joints ismandatory for the desired aesthetic results or where exposedaggregate or form linings are required. The report shouldsupplement the project specifications by providinginformation on possible techniques to achieve the desiredsurface textures and explaining the effects the architectwants in the facility.

(12) Finish requirements. The type of finish, asdetailed on the drawing for each portion of the structure, isto be discussed.

6-3

Page 63: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 7Preparation for Construction

7-1. Materials Acceptance Testing

a. General. Depending on the nature of the projectand the guide specification selected, acceptance of theconcrete materials proposed for use on a project will bebased on testing in a government laboratory, certified testresults, or certificates of compliance submitted by theContractor. An important responsibility of the residentengineer’s staff is to assure that materials submitted fortesting or that certificates of compliance represent the actualmaterials proposed for use.

b. Cement, pozzolan, and GGBF slag. Therequirements for the acceptance testing of cement, pozzolan,and GGBF slag are stated in the various guide specificationsfor concrete. The policy and responsibilities for carryingout the cement, pozzolan, and GGBF slag acceptance testingfunction of the Corps of Engineers is set forth inER 1110-1-2002, "Cement, Pozzolan, and Slag AcceptanceTesting." The procedures for requesting cement, pozzolan,and GGBF slag testing and the procedures for sampling andtesting are outlined in the ER. The USAEWES isresponsible for the sampling, testing, and quality verificationof cement, pozzolan, and GGBF slag at mill or sourcelocations within the Continental United States (CONUS).Personnel at the district, area, or residency level areresponsible for requesting cement, pozzolan, and GGBF slagacceptance testing, determining the amount of the charges,and providing the required funding document to WES.Residency personnel remain responsible for assuring that thecement, pozzolan, and GGBF slag reaching the project siteare from sources that have been tested, have not beencontaminated in transit, and are properly handled and storedat the project site. When cement or pozzolan is suppliedfrom sealed bins, the members of the residency staff areresponsible for sampling, shipping the samples to WES, andsealing the bins and transporting vehicles. For additionalinformation contact CEWES-SC. When cement, pozzolan,and GGBF slag are being supplied from a prequalifiedsource, project samples will be taken and funding to WESprovided as outlined in ER 1110-1-2002. Project personnelshould sample at the frequency required or may choose tosample more frequently if they suspect that the cement,pozzolan, or slag may be deviating from the specificationrequirements. There is no additional charge for testingproject samples when these samples are taken to aid inassessing a problem with the material being delivered to theproject. When cementitious materials are accepted by milltests, this requirement should be strictly enforced, and a fileof the mill test reports should be maintained. Silica fume

will be accepted by certified test reports from themanufacturer.

c. Chemical admixtures. The procedures foracceptance testing of chemical admixtures for concrete areoutlined in ASTM C 260, ASTM C 494, and ASTM D 98(CRD-C 13, 87, and 505, respectively). When acceptancetesting is required by the project specifications, samplingwill be performed by resident office personnel, and testingwill be performed by a division laboratory. To reduceduplication of effort, results of completed tests of chemicaladmixtures should be routinely furnished to WES inaccordance with ER 1110-1-8100, "LaboratoryInvestigations and Materials Testing."

(1) Test of air-entraining admixtures. The proceduresfor testing air-entraining admixtures are covered in ASTM C233 (CRD-C 12), and the specifications for air-entrainingadmixtures are given in ASTM C 260 (CRD-C 13).

(a) Abbreviated tests. When it has been determinedby review of previous data obtained from quality tests thata division laboratory has a sufficient background ofinformation on a given air-entraining admixture to indicatethat it is a product of good quality and acceptability asdetermined by the criteria set forth in ASTM C 260,subsequent samples may be evaluated by abbreviated tests.Abbreviated tests shall consist of performing all tests calledfor under regular tests except those for determination ofcompressive and flexural strength at 28 days, 6 months, and1 year, and resistance to freezing and thawing. Tests todetermine compliance with the time-of-setting requirementsneed not be performed unless specially requested.

(b) Initial uniformity tests. On the first sample of air-entraining admixture tested for a project and found tocomply with the applicable requirements by either thequality tests of ASTM C 260 or by the abbreviated tests,initial uniformity tests will be conducted to provide criteriafor evaluation of results of uniformity tests on samplesrepresenting subsequent lots. The uniformity tests willconsist of pH, density, and air content of mortar as outlinedin ASTM C 233.

(c) Uniformity tests of subsequent samples. Samplesrepresenting a subsequent lot of air-entraining admixturefrom the same source on the same project as a previous lottested by quality or abbreviated tests and found to complywith the applicable requirements may be tested by theuniformity test methods outlined in ASTM C 233. Theresults of uniformity tests will be compared with the resultsof the initial uniformity tests, and if they agree, the air-entraining admixture may be considered to comply with the

7-1

Page 64: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

specifications. Rejection of the air-entraining admixtureshould be based only on full or abbreviated test results.

(2) Test of other chemical admixtures. Thespecifications and procedures for testing and evaluatingchemical admixtures are given in ASTM C 494 and ASTMC 1017 (CRD-C 87 and 88).

(a) Abbreviated tests. When it has been determinedby review of previous data obtained from quality tests thata division laboratory has sufficient background ofinformation on a given admixture to indicate that it is aproduct of good quality and complies with the specificationsset forth in ASTM C 494, subsequent samples may beevaluated by abbreviated tests. Abbreviated tests ofchemical admixtures shall consist of two rounds of tests forwater content, initial time of setting, and compressivestrengths at 3, 7, and 28 days.

(b) Initial uniformity tests. On the first sample ofadmixture tested for a project and complying with theapplicable requirements by either the quality tests ofASTM C 494 or by the abbreviated test, initial uniformitytests will be made to provide criteria for evaluation ofresults of uniformity tests on samples representingsubsequent lots. The uniformity tests will consist of density,residue by oven drying, and infrared spectroscopy.

(c) Uniformity test of subsequent samples. Samplesrepresenting a subsequent lot of admixture from the samesource on the same project as a previous lot tested byquality or abbreviated tests and found to comply with theapplicable requirements may be tested by the uniformity testmethods outlined in ASTM C 494. The results of theseuniformity tests will be compared with the results of theinitial uniformity tests, and if they agree, the admixture maybe considered to comply with the specifications. Rejectionof the admixture should be based on full or abbreviatedtests.

(3) Tests of accelerators. If calcium chloride is usedon a project using the minor concrete guide specifications,it may be accepted based on recent certification that itcomplies with ASTM D 98 (CRD-C 505) or ASTM C 494,Type C or E.

d. Aggregates - listed source.When the Contractorproposes to furnish aggregates from a listed source, theresident engineer remains responsible for assuring that theaggregate being produced is of similar quality to that whichwas tested during the design process. Immediately afterreceipt of information on the Contractor’s source ofaggregates, samples should be taken from material produced

by the Contractor and forwarded to a division laboratory fora confirmation of quality. The amount of testing to beconducted will vary with each individual source. Testingprogram considerations will include length of time sincetesting was last performed, the amount of material removedfrom the source since testing was performed, and thevariability of the deposit. The resident office shouldcorrelate testing requirements with the engineering divisionmaterials engineer. The Contractor on mass concreteprojects using guide specification CW-03305 will haveresponsibility for quality testing before mixtureproportioning samples are taken.

e. Aggregates - nonlisted source. When theContractor proposes to furnish aggregates from a source notlisted in the specifications, samples will be taken by theContractor under the supervision of the resident office. Themethods of sampling are outlined in CRD-C 100. Theapproval or disapproval of the proposed source should behandled as quickly as possible, and appropriate personnelfrom the division and district should make site visits asneeded when a major project is involved. The evaluation oftest results is primarily a responsibility of the engineeringdivision of the district or division office. The source will beaccepted only if the quality meets the required test limits.The aggregate samples will be tested and evaluated inaccordance with the guidance provided in Chapter 2 of thismanual. All testing will be accomplished in the appropriatedivision laboratory.

f. Aggregates - minor concrete jobs.Minor concretejob specifications will require the aggregate to meetASTM C 33 (CRD-C 133) or a state highway specification.If the concrete supplier’s source of aggregate is from a localsource which has been used for some time, then a servicerecord will have been established and only minimum testingis necessary. The resident engineer or project engineer,however, has the responsibility to ascertain that theaggregates meet the required quality, and if there is anyquestion, such as a newly opened source, quality testingshould be performed in the division laboratory.

7-2. Mixture Proportioning

a. For concrete projects using Guide SpecificationCW-03305, mixture proportioning is the responsibility of theGovernment. Before the concrete placing starts, the mixtureproportioning study should be completed using materialsproposed by the Contractor. Chapter 4 of this manualdiscusses in detail the procedures for sampling of concretematerials for mixture proportioning and for proportioning tomeet project requirements. The mixture proportioningcriteria are to be provided to project personnel as outlined

7-2

Page 65: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

in Chapter 6. The importance of submitting samples whichmeet quality and grading requirements and which arerepresentative of materials to be supplied to the project can-not be overstated. Due to the variation of materials suppliedduring construction, mixture proportions may need to beadjusted. Adjustment of laboratory mixture proportionsshould be done during plant shakedown.

b. For projects using Guide Specification CW-03301,the mixture proportioning is the responsibility of the Con-tractor. Before the concrete placing starts, the Contractorshould submit the mixture proportions and all the testreports for review.

c. For structures using Guide SpecificationCW-03307, the concrete will most likely be supplied bylocal ready-mixed plants. The Contractor’s mixtureproportions should be submitted to the resident office andshould be checked for appropriateness and completenessbefore start of concrete production.

7-3. Concrete Plant and Materials

a. Review of concrete plant drawings.The contractspecifications may require the Contractor to submit drawingsshowing the layout and material handling details of the pro-posed concrete plant to the Contracting Officer for review.It is the Contractor’s responsibility to provide and maintaina dependable concrete plant of the required capacity.Review comments should be limited to (1) if the plant meetsthe requirements of the contract specifications or (2) a listof specific deficiencies if the plant does not meet the speci-fied requirements and (3) any other comments on specificplant features or details that are questionable or appeardeficient.

b. Estimating plant capacity. The capacity of aconcrete plant is commonly determined by the number ofmixers, the rated capacity of each mixer, along with thecharging, mixing, and discharging time of each mixer. Thetotal time required should be increased by 15 sec/batchwhen the capacity for sustained operation is computed.Thus, a concrete plant that contains two 4-yd3 tilting drummixers, each of which can be charged in 20 sec anddischarged in 15 sec, would have the following computedcapacity: A "rule of thumb" mixing time for a 4-yd3, one-opening, tilting-type mixer is 1 min, 45 sec. Therefore, thetotal time per 4-yd3 batch for such a mixer is:

20 sec - charging mixer1 min, 45 sec - mixing

15 sec - discharging15 sec - other

______________________2 min, 35 sec - Total

Thus, the concrete plant capacity is 8 yd3 in 2 min, 35 secor approximately 185 yd3/hr. If the number of mixers isinsufficient when judged by the mixing time calculation,which may be the case if the Contractor proposes to useturbine mixers or very large tilting mixers, the plant shouldbe designed so that the extra mixers can be added. Anycomments on the concrete plant should point out that theextra mixer(s) will be required if the mixing time proposedby the Contractor does not satisfy the uniformityrequirements. Normally, batching time is not critical.However, in a plant equipped with a vertical shaft (turbine)mixer, in which cumulative weighing is employed, thebatching cycle should be compared to the mixing cycle todetermine which is critical. It is always necessary to makea careful check of the capacity of the material conveyingsystems into the concrete plant and the concretetransportation system from the concrete plant to theplacement site. When placing concrete in the area of thestructure that is the most remote from the concrete plant, theconcrete transportation system should be capable of handlingthe entire output of the plant with allowances made for anytime required to reposition the discharge equipment andminor delays by the placing crew.

c. Aggregate storage, reclaiming, washing, andrescreening.Most project specifications for any size projectwill require that sufficient aggregate be on the site to permitthe continuous placement and completion of any lift started.The contractor’s proposed plant for the storage and deliveryto and from storage should be checked to determine if theyare of sufficient capacity to be able to easily comply withthe production capacity requirements. The capacity of thestorage bins should be checked against the preliminary mix-ture proportions to assure adequate size for all mixes. If thefine aggregate is wet when it is stockpiled and there are nomechanical dewatering devices provided, there must besufficient storage capacity to allow the fine aggregate todrain freely to obtain a uniform and stable moisture contentbefore being deposited in the batch plant bin. Aggregate re-claiming facilities, washing, and rescreening facilities (whenrequired) should be carefully examined to determine thatthey are of sufficient capacity to maintain all of the binsover the batchers at least half full when the plant is pro-ducing concrete at the rated maximum capacity of the plant.

7-3

Page 66: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

d. Concrete cooling plant capacity.There are twoprincipal requirements of an aggregate cooling system:(1) there must be sufficient refrigeration capacity, and(2) the aggregate must be in contact with cooling systemlong enough to permit the transfer of sufficient heat betweenthe aggregate and the medium. The refrigeration capacitymust be that required for the maximum placing rate duringthe hottest summer months with an assumed loss of at least10 percent between cooling and mixing. The length of timerequired for the heat transfer will depend upon the aggregatesize. For example, if 150-mm (6-in.) aggregate is exposedto ice water for 20 min, less than 85 percent of the potentialcooling will be accomplished regardless of the size of therefrigeration plant. The aggregate handling facilities shouldbe planned so that heat gain is minimized after cooling.Modern ice-making equipment that can handle ice efficientlyis available so that, for saturated aggregates, all the addedwater can be in the form of ice. It is important that all icemelts prior to the conclusion of mixing. Liquid nitrogen isalso extensively used for cooling concrete, especially whenthe nitrogen manufacturing facilities are within thegeographic area. Liquid nitrogen can be sprayed directlyinto the mixer with no ill effect. The nitrogen must beadded while the mixer is turning. ACI 207.4R and the PCA"Design and Control of Concrete Mixtures" (Kosmatka andPanarese 1988) are excellent references for more detailedstudy.

7-4. Batching and Mixing Equipment

a. Checking compliance with specificationrequirements. Prior to the beginning of concretingoperations, the plant should be checked for compliance withthe specification requirements. During the erection of theplant and installation of the equipment on large jobs, theinspection staff should become thoroughly familiar with theplant and its operating features. Plant drawings submittedby the Contractor for review by the Contracting Officershould be used in making the check and in becomingfamiliar with the plant.

b. Scale checks.All scales should be checked bystandard weights before being placed in operation. Duringplant shakedown and the beginning of concrete productionfor onsite plants, the operation of the scales should beobserved closely. If any trouble is apparent, it should becorrected immediately. Subsequently, the accuracy of thescales should be checked once a month. Checking of scalesis a responsibility of the Contractor under the quality controlprovisions, but the government inspection force has theresponsibility for verification. This verification should beaccomplished by observation of the scale checks performed

by the Contractor and actually checking scales when anaccuracy disagreement occurs.

c. Mixer blades and paddles.Mixer blades shouldbe examined before concrete production begins and must bemonitored during construction. If there is a buildup ofhardened concrete in the drum or if the blades become badlyworn, previously obtained uniformity test data are no longerapplicable. Thus, when the blade shows 10-percent wear,the blades should be replaced and additional uniformity testsrun. Several methods have been used to monitor blade wearto determine when the blade has worn 10 percent. Onemethod is making a plywood template of portions of theblades. Another is drilling small holes in the blade where"10-percent wear" would be. Another is simple blademeasurements. Measurements or holes must be located andrecorded so that they can be relocated. Selection of methodand monitoring must begin at the time the uniformity test isperformed. Pug mill paddles should be checked in a similarmanner.

d. Recorders. The agreement between recorderreading and dial indications should be checked regularly.This can be done easily whenever scales are calibrated,although it may be done any time the scales are inoperation. The pens on pen recorders should be examinedfrequently to ensure that they are not clogged, that they havea supply of ink, and that they do not produce too wide aline. It is a source of convenience to write on the chart thelocation at which concrete is being placed at any time.

e. Batching sequence.When aggregates are batchedcumulatively, the last material batched has its mass recordedwith the least accuracy since the tolerances in projectspecifications apply to the total mass in the hopper ratherthan to the mass of the individual fraction. If possible, fineaggregate should not be batched first or last. It should bebatched second, following the coarse aggregate fractionhaving the smallest mass. Batching sequence can have aprofound effect on mixing time for most mixers. If acharging conveyor is used, then ribboning materials togetheron the belt as much as possible can result in more efficientmixing and shorter mixing time. Liquid admixtures shouldbe batched with the water or damp sand. Each chemicaladmixture should be batched separately and should bebatched at the same point in the charging cycle for everybatch.

f. Mixer performance and mixing time.The mixingtime at the start of a job using onsite plant mixers should bedetermined prior to the start of concrete production. Onjobs covered by Guide Specification CW-03305, mixer

7-4

Page 67: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

performance tests will be conducted by the Contractor asrequired by the specifications. The mixer performance testsfor plant mixers are performed in accordance withCRD-C 55 at the specified intervals. The mixerperformance tests for plant mixers using continuous mixersare to be performed in accordance with CRD-C 55 with thespacing of the sampling intervals modified as appropriate forthe continuous operation. Allowable variation will be thesame as for batch mixers. When truck mixers are in use onany size job, their performance will be determined at thespecified intervals in accordance with ASTM C 94 (CRD-C31) and shall meet the variation tolerance specified therein.When mobile volumetric batching and continuous mixingplants are used for minor structures, mixer performance testsshall be performed in accordance with and shall meet thevariation tolerance specified in ASTM C 685 (CRD-C 98).When plant mixers are used, tests at reduced mixing timeswill be made by the Government any time reduced mixingtimes are proposed by the Contractor. Tests may beconducted by the Government at the initial startup of theplant for mass-concrete jobs if desired.

7-5. Conveying Concrete

a. General. Transportation of concrete from themixer to the forms should be done as rapidly as possible sothat the properties of the concrete as discharged from themixer are not changed materially. The devices used forreceiving the concrete from the mixers and conveying it toand depositing it in the forms should be designed tomaintain the concrete in the same condition in which it isdischarged from the mixer. ACI 304R provides an easilyobtainable source of information on transporting concrete.The contractor’s conveying system should be reviewed andappropriate comments provided.

b. Buckets.When concrete is transported from mixerto forms in bottom-dump buckets, controllable dischargebuckets are required. The specifications limit the size of thepile in which concrete may be deposited to 4 yd3. However,buckets with a capacity greater than 4 yd3 may be used ifthey have multiple discharge gates or other controls so thatmore than one pile is deposited on discharge, none of whichexceeds 4 yd3.

c. Truck mixers and agitators.Truck mixers will notadequately mix concrete made with aggregate having amaximum nominal maximum size greater than 37.5 mm(1-1/2 in.) and should not be used for mixing or transportingand agitating such concrete or concrete with 2-in. slump orless. In general, whenever truck mixers are permitted formixing concrete, agitators may be used for hauling concretein the event the contractor elects to use centrally mixed

concrete, except that agitators will not be used when it isnecessary to delay mixing of the batched material until thetruck has arrived at the construction site. This requirementmay occur when the batching, conveying, mixing, andplacing operations would require more time than allowed bythe specifications or when the rate of placement is so slowor intermittent that mixing cannot be properly scheduled atthe central mixing plant. In such situations, a procedure ofbatching all the materials except cement, and not more than80 percent of the water at the batch plant, and transportingto the construction site where the cement and remainingwater is batched and the concrete mixed, should be used.

d. Nonagitating equipment. Truck-mountednonagitating equipment specifically designed for haulingconcrete may be used for a haul requiring less than 15 minover a smooth road. Standard dump trucks should never beused to haul conventional concrete.

e. Positive-displacement pump.The transportation ofconcrete through pipelines by positive-displacement pumpsis an acceptable method for transporting concrete of mediumconsistency. This method is especially useful for tunnellinings and other areas with insufficient room for handlingbuckets. Pumps may be authorized whenever the aggregatesize, slump, and length of line are within the manufacturer’srecommendations for the apparatus proposed and the desiredquality of concrete can be obtained. A positive-displacement pump is a piston pump or a squeeze pressurepump. A pneumatic pump is not a positive-displacementpump. The use of aluminum for concrete pump pipe is notpermitted. The use of aluminum pipe is potentiallydangerous and could result in substantial reduction in thestrength of the concrete. Refer to ACI 304.2R for moreinformation on placing concrete by pumping methods.

f. Belts. Slow conveyor belts are unacceptable asstandard practice for transporting concrete. This methodtends to produce segregation as the concrete travels on aslow belt. Any belt traveling at less than 300 ft/min is con-sidered slow. When making the decision on whether or notto permit the use of conveyor belts to transport concrete,residency or area personnel should refer to ACI 304.4Rwhich includes information on parameters and specificationsfor belt placement. Regardless of the outcome of the analy-sis of the contractor’s proposal, the use of a belt conveyorshould be discontinued if excessive segregation results.

g. Chutes.Chutes which are supplied by the ready-mixed truck manufacturer as a normal part of the ready-mixed trucks are usually satisfactory. Most other chutestend to segregate the concrete as it is discharged and shouldnot be approved.

7-5

Page 68: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

7-6. Preparation for Placing

a. General. Placing of concrete should not bepermitted until preparations have been completed.Preparation for placing includes form construction, cleanupof surfaces, assembling of placing and protection equipment,and other operations essential to proper concretingoperations.

b. Earth foundations.Earth foundations should beproperly compacted and should be clean and damp prior toplacing the concrete.

c. Rock foundations.Rock foundations should bethoroughly cleaned and given any other necessary treatmentrequired to ensure proper bond of the concrete to the rock.Roughening by "bush hammering" or by sandblasting maybe necessary on certain types of rock; however, the removalof all loose coatings, scale, drummy rock, dried grout, andother similar materials usually provides a surface of requiredroughness.

d. Cleanup of concrete surfaces.Construction jointsin concrete to which other concrete is to be bonded must bethoroughly cleaned to remove laitance and other harmfulcoating. When properly prepared, the surface of theconcrete will present only clean coarse aggregate surfacesand sound mortar. Roughness is not necessarily arequirement. Cleanup of construction joints is usuallyaccomplished by either one of three methods or by the useof a combination of these methods. These are the air-watercutting (green-cut), high-pressure water jet, and sandblastingmethods. Some job specifications contain an optionalprovision, which if invoked, makes it possible for theContractor to use a surface-applied retarder to extend theperiod of time during which air-water cutting is effective.When the Contractor elects to use a surface retarder, he isrequired to submit a sample for approval and to demonstratethe method of application. The surface retarder should meetthe requirements of CRD-C 94. The principal requirementto be met by the application procedure is that it supply auniform coat in all kinds of weather. Without retardation,the use of the air-water method requires particular care ifsatisfactory results are to be obtained. The time at whichthe air-water cutting should be accomplished is critical andis materially influenced by prevailing temperatureconditions. When properly timed, the surface can becleaned so that laitance resulting from bleeding is removed.Frequently, the proper timing of the operations on the entiresurface of a lift in a large dam is not achieved and thisprobability should be considered before the method isapproved. Cutting too early by the air-water or high-pressure water jet method results in damage to the surface

by undercutting the large aggregate and in the removal andwasting of otherwise suitable concrete. Cutting too lateresults in failure to clean the surface properly andnecessitates wet sandblasting. A pressure of 3,000 psiappears to be adequate for cleaning concrete by the high-pressure water jet for concrete with strength of 3,000 psi.Higher strength concrete may require a pressure up to asmuch as 6,000 psi. Trials should be conducted on projectconcrete to establish the correct pressure. Cleaning by thesandblast method is accomplished after the surface hashardened and should be delayed as long as practicable,preferably until just prior to placing the next lift. TheContractor will be required to provide means for handlingthe disposal of the joint cleanup waste so that exposedsurfaces will not be stained or otherwise damaged. Lightsandblasting to remove surface stains resulting from faultycleanup operations or the use of unsuitable curing water ispermissible, but it will not be necessary if the cleanupoperations are properly executed. The best bond betweenlifts is obtained when the surface of the old concrete isneither bone dry nor saturated but has been saturated and isin a drying condition.

e. Placing equipment.The requirements for placingequipment vary widely from job to job, depending on theplant used and placing conditions. The necessary facilitiesshould be reviewed in advance and provided ready for use.In reviewing, attention should be given to the followingspecific items.

(1) Vibrators. Vibrators should comply withspecification requirements. A sufficient number of vibratorsshould be at the job site to permit placing. Also thereshould be a reasonable number of spare vibrators available.

(2) Cold-weather and hot-weather protectionequipment. Devices and methods proposed by theContractor must meet the specifications requirements forcold-weather and hot-weather concreting. The equipmentshould be examined for adequacy and applicability well inadvance of winter concreting so that any deficiencies maybe corrected by the Contractor. Refer to ACI 305R andACI 306R for more information on hot-weather and cold-weather concreting.

(3) Communication equipment. The Contractorshould provide equipment for his use between the forms andmixing plant. The need for other equipment such assignaling and identifying devices depends on the complexityof the project and the number of different concrete mixturesemployed. The resident engineer should require theContractor to present for review plans or descriptions of theequipment well in advance of the start of concrete

7-6

Page 69: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

placement. The GQA representative should be providedwith separate communication equipment between the formsand mixing plant on large jobs where the mixtureproportions are provided by the Government.

(4) Other equipment. The need for additionalequipment depends on job requirements. Such equipmentincludes wire brooms for spreading grout, water removalequipment, elephant trunks, etc.

f. Forms. The type of forms to be used by theContractor will be submitted for approval prior toconstruction. The submittal should be checked forcompliance with the specifications.

g. Curing and protection. The methods andequipment proposed by the Contractor for the curing andprotection of concrete should be reviewed to assure that theyare capable of curing the concrete and protecting it incompliance with the specifications. Follow-up inspectionsshould assure that the approved materials and equipment forcuring and protection are available at the project site priorto the beginning of concrete placement.

h. Approval. Concrete placing should never beginuntil approval to do so by the Government has been given.A form checkout record should be used for larger and more

complex projects. The record should include form line andgrade, grout tightness of the form, proper size numbers andposition of reinforcement, waterstops, mechanical orelectrical lines, cleanup of foundation or previous lift, propertransportation, placing and vibrating equipment, and curingand protection equipment. Both the government qualityverifier and the Contractor’s foreman should sign or initialthe record. Figure 7-1 is a sample of a form checkoutrecord.

i. Interim slabs on grade.Unless there is some otheroverriding reason, interior slabs on grade should beunderlain by a capillary water barrier consisting of 4 to 6 in.of open-graded granular material, preferably crushed rock.While some engineers consider a vapor barrier unnecessary,it is usually good practice to install a vapor barrier belowthe concrete slab and above the capillary water barriers.This consists of a continuous plastic sheet, 6 mil or morethick. In some parts of the country, particularly theSouthwest, it is customary to cover the vapor barrier with2 in. of sand because of the concern that, without theseparator, warping of the slab would be intensified. Whilein other parts of the country the vapor barrier is customarilyplaced directly beneath the concrete slab without a sandseparator, it would be conservative practice to use the sandseparator unless previous experience shows no need for it.

7-7

Page 70: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

FORM CHECKOUT

I T E M

INSPECTED BY APPROVED BY

CONTRACTOR CORPS OF ENGINEERS

NAME DATE TIME NAME DATE TIME

GEOLOGY FOUNDATION

DRAINAGE

CROSS SECTION

FORMS

LINE & GRADE CONTROLCONCRETE PLACING

REINFORCING

PIPING

WATER STOP

ANCHOR BOLTS

MISC. MECHANICAL

ELECTRICAL

CLEANUP

SAFETY REQUIREMENTS

WEATHER PROTECTION

VIBRATING EQUIPMENT

CURING MATERIALS

F I N A L C L E A R A N C E

CONTRACTOR REPRS: C.O.E. REPRS:

I N S T R U C T I O N S

CONCRETE PLACING SHALL NOT BEGIN UNTIL EVERY ITEM IS CHECKED AND THE FINAL CLEARANCE IS SIGNED.

IF ANY ITEM IS NOT APPLICABLE, IT SHALL BE NOTED "NA" AND SIGNED.

BEFORE APPROVING THE "SAFETY REQUIREMENTS" ITEM, A FINAL INSPECTION SHALL BE MADE OF ALL WORKING FACILITIES FOR CONCRETE

PLACING SUCH AS SCAFFOLDS, LADDERS, PLATFORMS, ACCESS WAYS, ETC., TO ASSURE THAT THEY ARE ADEQUATE, SAFELY CONSTRUCTED,

AND IN READINESS.

FINAL CLEARANCE SUBJECT TO REVOCATION IF SUBSEQUENT INSPECTION REVEALS ANY DEFICIENCIES.

IF SUMMONED BY THE CONTRACTOR TO CHECK AN ITEM AND IT IS FOUND TO BE UNSATISFACTORY, STATE IN THE "REMARKS" COLUMN THE

TIME SUMMONED AND THE TIME REJECTED.

Figure 7-1. Example of form checkout record

7-8

Page 71: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 8Concrete Construction

8-1. Forms

a. Types of materials.The contract specificationsspecify the types of finish required for the various formedsurfaces and the types of materials permitted for each classof finish. If more than one type of material is permittedwith each class of finish specified, the Contractor shouldalways be permitted to employ his choice of materials.

b. Quality verification. After concrete forms havebeen set to line and grade and prior to permitting anyconcrete to be placed therein, the forms should be carefullyinspected for compliance with all specification requirements,including sheathing materials, alignment of form surfaces,mortar tightness, and apparent strength.

c. Form coating. Most of the form coatingscommercially available are satisfactory for wood forms.Quite frequently, form coatings which are satisfactory forwood forms do not perform satisfactorily on steel forms. Ifthe form coating being used on the work is unsatisfactory,its use should be immediately discontinued and theContractor should be required to obtain a suitable formcoating.

8-2. Placing

a. General. The practices followed in the placementof concrete should have the principal objectives of concretethat is bonded to the foundation or to the previous lift,uniform in quality, free from any objectionable segregation,and thoroughly consolidated. These objectives are bestaccomplished by adequately cleaning and preparing the topsurface of the foundation or the previously completed lift,delivering the freshly mixed concrete to its approximatefinal position in the structure with a minimum ofsegregation, and consolidating the concrete by means ofsufficient vibration to consolidate it completely. In additionto these very general practices, the more detailed practicesoutlined below should be followed.

b. Bedding mortar on rock foundations.All rockfoundations should be covered with a layer of mortar justprior to concrete placement. The mortar should becomposed of the same fine aggregate and cementitiousmaterial used in the exposed concrete mixture. Thesand/cementitious material and w/c of the mortar should alsobe the same as that used in the exterior concrete mixtureproportions. Addition of an air-entraining admixture is notrequired. The thickness of the mortar layer should be

approximately 1/4 in. The delivery and spreading of themortar should be scheduled so that all mortar is covered bythe concrete before the initial set of the mortar.

c. Mass concrete. The general nature of massconcrete, having a stiff and dry consistency and containing75- and 150-mm (3- and 6-in.) maximum size aggregates,is such that the concrete must be deposited in the finalposition in the structure in which it is to remain whencompacted. The quantity of interior mass concrete that canbe properly compacted in one operation is recognized to beabout 4 yd3. The project specifications will usually limit theamount to be deposited in one pile for compaction to 4 yd3

in uncongested areas and to smaller quantities in congestedareas. Depositing 8 yd3 in two contiguous piles from a two-compartment (4-yd3 each) bucket is recognized to be incompliance with this requirement. Whenever the top of alift is not horizontal, the placement must proceed up theslope. The thickness of the exterior concrete in a massconcrete structure is governed by the size of the bucket orthe delivery equipment used in placing the concrete. Sincethe project specifications will limit the amount of concretethat may be deposited in one pile to 4 yd3, the exteriorconcrete will usually average about 5 to 6 ft thick. Theplacing procedure to be followed includes practices designedto keep the thickness of the exterior mixture to a practicalminimum. Usually, a 7-1/2-ft lift of mass concrete is placedin five layers, and a 5-ft lift of mass concrete is placed inthree layers as shown in Figures 3-1 and 3-2 of this manual.For example, in dam construction, if both interior andexterior mass concrete are used, the placement should beginwith the first layer of interior mass concrete at the upstreamend of the placement, leaving a space of the minimumpractical, or specified, width between the interior massconcrete and the form for the placement of the exteriormixture concrete. The exterior mass concrete layer shouldbe placed after the corresponding interior concrete layer hasbeen placed, so as to keep the thickness of the exteriorconcrete to a practical minimum, or that specified. Theintersection of the interior and exterior concretes should becarefully consolidated and "knit" together during vibration.The placement should then proceed toward the downstreamface with the bottom layer preceding the second layer by anapproximate distance equivalent to 4 yd3 of concretecompacted. Each successive layer above should follow thelayer below by approximately the same distance, thusproviding a stepped placing procedure. The placementshould follow a regular sequence for the successive layersby maintaining the stepped relationship of the layers untilthe lift is completed. Dumping of concrete on slopes andchasing it downhill with vibrators is not to be permittedunder any circumstances. The transporting of concrete byvibration is not permitted.

8-1

Page 72: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

d. Structural concrete.Proper care must be taken toavoid segregation when placing concrete into structural unitssuch as walls, columns, slabs, beams, etc. The concrete isto be deposited in approximately its final position in thestructure where it is to remain and should not be movedwithin the forms with vibrators. As a general rule, when theconcrete bucket cannot be lowered to within 5 ft of theposition where the concrete is to be placed, elephant trunkswith a rigid drop chute bottom section are to be used. Allbelt conveyors must have elephant trunks at their dischargeends. The thickness of the layers should not exceed 20 in.The vibrators should be handled carefully so that thoroughconsolidation is achieved without damaging the forms ordisplacing embedded items. The vibrator should not beoperated while being held against the form which results insandy streaks or markings in the finished surface.

e. Tunnel linings.

(1) Inverts. The concrete for tunnel inverts may bedelivered to the placement site by any practical means. Itshould be brought to grade in layers not to exceedapproximately 1-1/2 ft and thoroughly consolidated withvibrators.

(2) Sidewalls and crown. Use of a positivedisplacement pump is the normal method of placing theconcrete in tunnel linings. In the tunnel sidewalls, theconcrete should be placed in successive layers ofapproximately 1-1/2 ft deep and thoroughly consolidated byvibration. In the crown of the tunnel where vibration isimpossible, a length of the special pipeline used in theconcrete pumping operation is kept buried in the freshconcrete. This is necessary to achieve consolidation of theconcrete and to force the concrete into the overbreaks in therock. Placement of the concrete in the crown must begin atthe end of the form that is opposite the concrete pump, andthe embedded pipeline will be backed out as the crown isfilled. Short sections of vertical riser pipes have been usedsatisfactorily, in lieu of the buried pipeline, to place concretein the tunnel crown. Pumping concrete is discussed inparagraph 10-6 of this manual and in ACI 304.2R.

f. Consolidation. Concrete that is placed in the drywith conventional methods should be consolidated by meansof mechanical vibration equipment. The performance of thevibrators used by the Contractor should be periodicallychecked for compliance with the performance characteristicsrequired by the contract specifications. Vibrators shouldnever be used to transport the fresh concrete within theforms. The duration of vibration at a single point in thefresh concrete being consolidated should be approximately10 to 15 sec or until the entrapped air is released, which is

indicated when large air bubbles stop coming to the top ofthe mixture near the insertion point of the vibrator. It isessential that the points of vibration be fairly closely spacedto obtain thorough and complete consolidation of freshconcrete. Proper care must be exercised to thoroughlyvibrate the concrete in all forms, including flowing concrete,to minimize rock pockets, honeycomb, and other defects.It is almost impossible to over vibrate a properlyproportioned concrete mixture. Emphasis should be placedon having closely spaced applications of appropriateduration rather than prolonged vibration at widely spaceddistances. The latter method will result in inadequateconsolidation in some parts of the concrete, which willresult in an overall general reduction in the quality of thehardened concrete. In general, the use of internal vibratorsfor consolidation of freshly mixed concrete has beensatisfactory. A thorough discussion of consolidation isgiven in ACI 309R.

g. Protection of waterstops.There are many cases ofleakage through a joint because of faulty installation of thewaterstop. To eliminate such failures, particular care mustbe exercised to ensure that waterstops are properly protectedand installed. Adequate provisions must be made to supportand protect all waterstops against damage during theprogress of the work. Extraordinary care must be employedin the placement and consolidation of the concrete adjacentto the waterstops to ensure that the waterstops are notdamaged and that they are in the correct position andproperly embedded in the concrete.

8-3. Finishing

a. Formed surfaces. The finishing of concretestructures consists of dressing up the formed surfaces bypatching the form bolt holes and removing any defectiveconcrete and replacing it with sound durable concrete. Thislatter operation can be largely avoided by paying particularand vigilant attention to the details of the concreteplacement operations, especially the consolidation, so thatdefective concrete will not occur. When such conditions dooccur on exposed surfaces, the defective concrete must bechipped back to sound concrete and replaced by dry packingor a conventional concrete placement. In the removal of thedefective concrete, care should be taken to preventdamaging the adjacent concrete while creating a dovetail orkey into the hardened concrete to firmly anchor the newrepair concrete. All defective concrete on the surface of astructure that is permanently exposed to view should berepaired. Additional guidance on repair materials andmethods may be found in EM 1110-2-2002, "Evaluation andRepair of Concrete Structures." Honeycomb and rockpockets on bulkhead faces usually do not need to be

8-2

Page 73: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

repaired unless they are of considerable extent or depth.Extra care must be taken to assure that the color and textureof the repair concrete closely matches that of thesurrounding concrete. The guide specifications are clear anddetailed in their requirements for all formed surfaces. Thekey to quality is the strict enforcement of the specificationrequirements. Class A finish is the best finish with the moststrict requirements, while Class D is the least restrictive.Class AHV is a special finish for spillways, tunnels, or otherwater passages where the velocity of the water is expectedto be 40 ft/s or higher. The materials and workmanship forforming of Class AHV are the same as the Class A finishrequirements in Guide Specification CW-03101, "Formworkfor Concrete," except that steel forms may be used. Theallowance for offsets for Class AHV is more restrictive.

b. Unformed surfaces.The finishing of unformedsurfaces is a very critical operation and requires the use ofjudgment, experience, and skill to produce a finished surfaceof the specified quality and durability. Crazing, scaling, andother defects are usually directly attributable to the use ofconcrete which is too wet (too high a slump), improperfinishing procedures, or a combination of both.Overworking the surface is probably the most commoncause of defective surface finishes. The fresh concreteshould be thoroughly consolidated. The surface of theconsolidated concrete should be slightly above grade.Screeding, or strikeoff, should be done immediately afterconsolidation. The screeding operation, when accomplishedby hand methods, is to be accomplished with a sawingmotion of the screed in the transverse direction to the lineof travel of the screed. This will accomplish the dualpurpose of screeding and compacting the surface at the sametime. Any excess concrete that is left above grade shouldbe carried ahead of the screed. In a properly proportionedair-entrained concrete, a characteristic roll of fresh concretewill form in front of the screed. In air-entrained concretewhich has been properly consolidated, a slight rebound ofthe fresh concrete will occur behind the screed. Screedingshould be limited to two passes of the screed. After thesecond pass of the screed, the rebound will be diminishedto a negligible amount. Floating or darbying should becompleted immediately after screeding and should be limitedto that necessary to fill in low spots. The use of a jitterbugor tamper to embed the coarse aggregate particles should notbe allowed. Floating and troweling should not be permittedon any part of the surface where any bleed water hascollected. This bleed water must either be allowed toevaporate or be removed in a satisfactory manner. Drycement, or a mixture of cement and fine sand, should neverbe applied directly to a surface to be finished for theremoval of bleed water or for any other purpose. Addingwater to the surface by use of a large brush, or other means,

should also be prohibited. The use of power rotarytroweling machines needs to be carefully controlled toprevent overfinishing and the resultant crazing.

(1) Ogee crest. One of the most difficult finishingjobs on unformed surfaces is the ogee crest of a spillway.The following procedure is the most satisfactory onedeveloped to date. The spillway piers and the high-strengtherosion-resistant concrete in the spillway surface are placedmonolithically with the spillway except for the top lift,which includes the ogee crest. Adjustable vertical rigidsupports, conforming to the ogee shape are installed in theplacement, raising the depth of the screed above the finishedgrade and bridging the placement surface. Concrete isplaced and consolidated in the usual manner and thenscreeded and finished using the pipe as an elevation guide.When these operations are properly executed, a durablesurface is produced.

(2) Spillway aprons. No general rules can be givenfor finishing of spillway aprons or stilling basin slabs.Since the shapes required to meet the hydraulic requirementsdiffer for different projects, it is usually necessary todevelop special methods for each situation. The finishing isfrequently done by hand, although properly designed heavy-duty mechanical screeding equipment is acceptable. Themethod described above for ogee crests is suitable, withappropriate modifications, to the finishing of stilling basins,the curved transition surfaces at the toe of a dam, or for flipbucket spillways.

(3) Trapezoidal channel lining. The methods to beused on bottom slabs are the same as for any flat or nearlyflat slab. The concrete should be placed and consolidatedin the usual manner and left slightly above grade. The slabshould then be struck off to grade by screeding and given afloat finish. Finishing the sideslope paving in smallchannels will usually be accomplished by hand methods.Placing of the concrete will proceed upslope. The concreteshould be of medium to dry consistency. The use of amechanical screeding machine is considered advisable.Hand-manipulated screeds which are moved by mechanicalmeans can also be used. Screeding should always proceedupslope. After screeding, the surface should be given afloat finish.

(4) Surfaces exposed to high-velocity flow of water.Surfaces to be exposed to waterflow velocities greater than40 ft/s should be finished carefully (AHV finish) since anydiscontinuity especially a positive offset in downstreamdirection in the surface can be the cause of cavitation.Cavitation has the potential of seriously eroding concrete

8-3

Page 74: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

surfaces so the finishing of areas subject to cavitationdamage should be carefully inspected.

(5) Floors.

(a) Monolithic. Where monolithic floors are specified,the completion of the floors should be delayed, if possible,until all other construction work from which damage to thefloor might occur is completed. If this is impracticable, thefloor should be adequately protected from damage.

(b) Bonded topping. In areas where structural slabsmust be completed for the work to be accomplished, bondedor "two-course" floors are usually selected so that the finalfinish can be delayed until all other work is virtuallycomplete. This eliminates the necessity for specialprotection; however, the rough slab should be protectedagainst spillage of liquids or other materials which mightlater interfere with bonding of the floor topping. Thesurface of the base slab should be prepared for the toppingin the same manner as the surface of any horizontalconstruction joint.

c. Tolerance requirements for surface finish.

(1) General. Control of surface tolerance may becritical in some types of structures such as warehouseguideway surfaces and surfaces subject to high-velocity flow(over 40 ft/s). There are two approaches in controlling thefloor surface tolerance; using straightedge (or curvedtemplates for curved surfaces) or measuring the F numbersin accordance with ASTM E 1155 (CRD-C 641). Bothapproaches are used in Corps of Engineers (CE)specifications depending upon the type of structures.

(2) Control surface tolerance by straightedge. This isthe traditional method for measuring surface tolerance. Thetolerance is defined as the maximum gap between a fixedlength straightedge and the concrete surface at any point.The device is simple, portable, and easy to use. There willbe no calculation or data collection. This procedure can beused on any surface; horizontal, vertical, overhead, evencurved surface (by using a curved template). However,there are some limitations on this approach. Themeasurements are arbitrary, subjective, and generallynonrepeatable. There is no mention of the number ofmeasurements to be made and therefore it totally depends onthe operator. The difficulty in enforcing the requirementusing this method often results in controversies betweenowners and contractors. This procedure is specified formass-concrete structures and minor concrete structures andmay be specified as an option in cast-in-place concretestructures in CE civil works projects. For mass-concrete

structures, the requirement of surface tolerance falls into twoextremes. The surface tolerances for most mass-concretestructures, such as surfaces of a dam or floors of a lockchamber or gallery, are less critical where tight control isnot necessary. Although a 10-ft straightedge has beencommonly used in the industry, a 5-ft straightedge isspecified for mass concrete due to the difficulty in handlingthe 10-ft straightedge on surfaces other than floors. On theother extreme, the surface subject to high-velocity waterflow requires extreme tight control in surface tolerance toreduce the possibility of cavitation and erosion. A specialsurface class (Class AHV) has been created for this purpose.The straightedge or curved template is specified in this casesince most of the surfaces involved are either vertical,overhead, or curved where the F-number system cannot beused. For minor concrete structures where a small quantityof concrete is used, the control of surface tolerance is lesscritical. The use of the F-number system in these structuresis not necessary.

(3) Control floor tolerance by F-number system. In1987 ASTM issued a standard test procedure, ASTM E1155, for measuring floor surface profiles and for estimatingthe characteristic flatness and levelness of a floor. Thisprocedure measures elevations at regular intervals alongstraight lines on the surface. The differences in elevationsbetween adjacent points and between all points 10 ft apartare then calculated. The results of these calculations areanalyzed statistically to obtain floor flatness number (FF)and floor levelness number (FL). Floor flatness is defined asthe degree to which a surface approximates a plane whilelevelness is defined as the degree to which a surfaceparallels horizontal. These two numbers represent theaverage quality of floor finish in a predefined area and arereliable and repeatable. It should be noted that there is nodirect correlation between straightedge tolerances andF-numbers. However, based on the effort required to finisha floor to the corresponding tolerance, Table 8-1 provides arough correlation between the two systems. The F-numbersystem may be specified as an option for all cast-in-placeconcrete floors for consistency with industry standards andpractices. Currently, the construction technology canachieve FF 25 at little or no additional cost. Therefore, fornormal slab or floor construction, FF should be at least 25.FL should be used for slab on grade only, since the levelnessof an elevated floor is beyond the control of the Contractordue to camber and deflection of supporting system. In somecases, it may be necessary to specify localized FF/FL inaddition to the overall FF/FL to assure a uniform floorquality. Details and concept of the F-number system areavailable in ACI 302.1R, ACI 117R commentary, andASTM E 1155.

8-4

Page 75: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 8-1

Floor Quality as Determined by

F-Number System and Straightedge

F-Number

Gap Under an Unleveled

5-ft Straightedge, in.

Gap Under an Unleveled 10-ft Straightedge,

in.

Bull floated FF 12 3/8 1/2

Straightedged FF 20 1/4 5/16

Flat FF 32 1/8 3/16

Very flat FF 50 1/16 1/8

8-4. Curing

a. General. Early hydration proceeds at anacceptable rate only if the concrete is maintained at a highhumidity. Thus, positive curing procedures are essential,especially for thin sections. Even in massive sections, thequality of the surface concrete is dependent upon adequatecuring. The Contractor should present his plans for curingfor approval well before concreting begins. Duringconstruction, these operations must be continually checked.Form curing, where no additional moisture is added, is notan acceptable method of curing. Where forms are left inplace during curing, the forms should be kept wet at alltimes.

b. Moist curing. Proposed methods of keepingconcrete surfaces continually moist by spray-pipe or fogsystems, soaker hoses, ponding, or covering with dampearth, saturated sand, or burlap maintained in a dampcondition in contact with the concrete are satisfactory.Plastic, aluminum, galvanized, or alloy pipe should berequired to avoid rust stains on the concrete surfaces. Handsprinkling is not satisfactory and should not be permittedexcept as an emergency measure. Water that will stain theconcrete should not be approved unless it is not practical tofurnish a nonstaining water. The Contractor should berequired to clean surfaces permanently exposed to view if heuses water that stains.

c. Membrane curing. Areas cured by pigmentedmembrane-forming coring compounds are relatively easy toinspect and should be specified wherever possible. Unevendistribution of the compound is readily revealed by anonuniform appearance. In those areas in which anonpigmented compound is required such as surfaces to beexposed to view, a government quality verifier should be onhand during all spraying operations and should check

closely the uniformity of the application. In a hot, dryenvironment, the energy from the direct sunlight may raisethe surface temperature significantly which will promoteformation of shrinkage cracks on the surface. Therefore,when using nonpigmented curing compound, it is requiredthat shading should be provided for 3 days whenever themaximum ambient temperature during that period isexpected to be higher than 90 °F. Compressed air linesmust have traps to prevent moisture or oil fromcontaminating the compound. Ordinary garden hand-sprayoutfits are not satisfactory and should not be permitted.Application by brushing or rolling should not be permitted.Pigmented compounds should be thoroughly mixed in thereceiving containers by the insertion of a compressed airpipe into and near the bottom of the container prior towithdrawing the material for use. Continuity of themembrane coating must be maintained for the duration ofthe full specified curing period. The membrane should beprotected by suitable means if traffic thereon is unavoidable.Any damage to the membrane during the curing periodshould be immediately repaired at the original specified rateof coverage. Additional information may be found inACI 308.

d. Sheet curing.Sheet curing is an acceptable curingmethod, although it is not often used except for curing slabs.Some of the materials used are easily torn by equipment orby wind, and constant inspection and maintenance isrequired. It is important that very secure tiedowns or heavyobjects be used with this system to maintain a sealedenvironment for curing the concrete. Polyethylene film iseasily torn and tends to leave a pattern on the surface wherethe film wrinkles. Maintenance of the film during thecuring period is a constant problem due to wind andconstruction activity. Inspection requires constant scrutiny.It is not allowed except for smaller jobs.

8-5

Page 76: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

8-5. Cold-Weather Concreting

a. General. Cold weather is defined by ACI 306R asa period of three or more consecutive days when theaverage daily ambient temperature is less than 40 °F, andthe ambient temperature is not greater than 50 °F for morethan one-half of any 24-hr period. The average daily airtemperature is the average of the highest and the lowesttemperatures occurring during the period from midnight tomidnight. The objectives of cold-weather concretingpractices are to:

• Prevent damage to concrete due to freezing at earlyages.

• Assure that the concrete develops the requiredstrength for safe removal of forms, shores, and reshores andfor safe loading of the structure during and afterconstruction.

• Maintain curing conditions which foster normalstrength development without using excessive heat andwithout causing critical saturation of the concrete at the endof the protection period.

• Limit rapid temperature changes, particularly beforethe concrete has developed sufficient strength to withstandinduced thermal stresses.

• Provide protection consistent with the intendedserviceability of the structure.

Proper cold-weather concreting practices and procedures arebased on the principles that:

• Concrete that is protected from freezing until it hasattained a compressive strength of at least 500 psi will notbe damaged by a single freezing cycle.

• Where a specified concrete strength must be attainedin a few days or weeks, protection at temperatures above50 °F is required.

• Little or no external supply of moisture is requiredwhen concrete is properly protected and sealed during coldweather except within heated protective enclosures.

b. Planning. Proper planning by the contractor toprotect fresh concrete from freezing and to maintaintemperatures above the required minimum values should bemade well before the freezing temperatures are expected tooccur. Equipment and materials required to protect concretefrom freezing should be at the job site before cold weather

is likely to occur, not after the concrete is placed and itstemperature begins to approach the freezing point. Allsurfaces that will be in contact with newly placed concreteshould be at temperatures that cannot cause early freezingor seriously prolong setting time of the concrete.Ordinarily, the temperatures of these contact surfaces,including subgrade materials, need not be higher than a fewdegrees above freezing.

c. Protection system.ACI 306R provides guidanceon minimum concrete placing temperatures and on themaintenance duration of these temperatures. The actualtemperature at the concrete surface determines theeffectiveness of protection, regardless of the ambienttemperature. Therefore, monitoring concrete temperaturesat several locations along the concrete surface, particularlyat corners and edges, is important. As noted inparagraph 4-2d of this manual, concrete should not beexposed to cycles of freezing and thawing while in acritically saturated condition until it has attained acompressive strength of approximately 3,500 psi. Thespecific protection system required to maintain concretetemperatures above freezing depends on such factors as theambient weather conditions, the geometry of the structure,and the mixture proportions. In some cases, covering theconcrete with insulating materials to conserve the heat ofhydration may be all the protection that is necessary.Insulation must be kept in close contact with the concrete orthe form surface to be effective. Some commonly usedinsulating materials include polystyrene foam sheets,urethane foam, foamed vinyl blankets, mineral wool, orcellulose fibers, straw, and commercial blanket or battinsulation. In more extreme cases, i.e. ambient temperaturesless than -5 °F, it may be necessary to build enclosures anduse heating units to maintain the desired temperatures. Heatcan be supplied to enclosures by live steam, forced hot air,or combination heaters of various types. Although steamprovides an excellent curing environment, it may offer lessthan ideal working conditions and can cause icing problemsaround the perimeter of the enclosure. Heaters and ductsshould be positioned not to cause areas of overheating ordrying of the concrete surface. Combustion heaters shouldbe vented for safety to prevent reaction of carbon dioxide inthe exhaust gases with the exposed surfaces of newly placedconcrete.

d. Curing. Concrete exposed to cold weather is notlikely to dry at an undesirable rate unless the protectionwhich is selected for use increases the likelihood of rapiddrying. Measures should be taken to prevent drying whenconcrete is warmer than 60 °F and exposed to air at 50 °For higher. Either steam or a liquid membrane-formingcuring compound should be used to retard moisture loss

8-6

Page 77: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

from the concrete. Water curing should not be used sinceit increases the likelihood of concrete freezing in a criticallysaturated condition when protection is removed.

e. Accelerating early strength.Acceleratingadmixtures, Type III portland cement, or additional cementcan be used to shorten the times needed to achieve settingand required strength if proper precautions are taken.Reduction in time of setting and acceleration of strengthgain may permit shorter protection periods, faster reuse offorms, earlier removal of shores, or less labor in finishingof flatwork. The acceleration of strength development ofmass concrete should not be allowed since doing so willtend to increase internal temperature rise of the concrete. Amore thorough discussion of all topics related to coldweather concreting is given in ACI 306R.

8-6. Hot-Weather Concreting

a. General. ACI 305R defines hot weather as anycombination of the following conditions that tend to impairthe quality of freshly mixed or hardened concrete byaccelerating the rate of moisture loss and rate of cementhydration, or otherwise resulting in detrimental results:

• High ambient temperature.

• Low relative humidity.

• Wind velocity.

Hot weather may lead to concrete mixing, placing, andcuring problems which adversely affect its properties andserviceability. Most of these problems relate to theincreased rate of cement hydration at higher temperature andthe increased evaporation rate of moisture from the freshlymixed concrete. Detrimental effects of hot weather onfreshly mixed concrete may include increases in: waterdemand, rate of slump loss, rate of setting, tendency forplastic shrinkage, and difficulty in controlling air content.Hardened concrete may potentially experience decreased 28-day and later age strengths, increased tendency for dryingshrinkage, and differential thermal cracking, decreaseddurability resulting from cracking, increased permeability,and greater variability of surface appearance. In addition,proper temperature control of mass concrete may be moredifficult to achieve during hot weather.

b. Planning. Damage to concrete caused by hotweather can never be fully alleviated, and so good judgmentis necessary to select the most appropriate compromise ofquality, economy, and practicability. The type ofconstruction, characteristics of the concrete materials, and

the hot-weather concreting experience of the Contractor allaffect the procedures used to minimize potential problems.Lack of hot-weather concreting experience by theContractor’s personnel usually causes the most difficultiesin achieving concrete of the required quality. Earlypreventative measures should be applied with the emphasison materials evaluation, advanced planning, andcoordination of all phases of the work. Detailed proceduresfor mixing, placing, protecting, curing, temperaturemonitoring, and testing of concrete during hot weathershould be submitted by the Contractor prior to the beginningof hot-weather concreting. The potential for thermalcracking, either from overall volume changes or frominternal restraint, should be anticipated. Items that shouldbe considered to control cracking include limits on concretetemperature, cement content, heat of hydration of cement,form-stripping time, selection and dosage rate or quantity ofchemical admixtures and pozzolans, joint spacing, and useof increased amounts of reinforcing steel.

c. Alleviating measures.Practices and measureswhich will help to reduce or avoid the potential problems ofhot-weather concreting include:

• Using concrete materials and proportions withsatisfactory records in field use under hot weatherconditions.

• Using cooled concrete. For general types ofconstruction in hot weather, it is not practical to recommenda maximum limiting ambient or concrete temperaturebecause circumstances vary widely. Therefore, ACI 305Rrecommends that, if possible, a practical maximum concretetemperature of between approximately 75 and 100 °F bedetermined. This should be done by testing laboratory trialbatches of concrete which are produced at the selectedlimiting temperature or at expected job site hightemperature. For projects using CW 03305, "MassConcrete," the maximum placing temperature for concretein the massive features should be determined by a thermalstudy. For all other concrete, the maximum placingtemperature should be as shown in Table 8-2, which relatesmaximum concrete temperature to relative humidity.

• Using a concrete consistency that permits rapidplacement and effective consolidation.

• Transporting, placing, consolidating, and finishingthe concrete with the least delay.

• Scheduling placing operations during times of theday or night when weather conditions are favorable.

8-7

Page 78: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 8-2Maximum Placing Temperature

Average AnnualRelative Humidity, %

Maximum ConcreteTemperature, °F, at Placement

>60 90

40-60 85

<40 80

NOTE: If the period that the concrete placements may occur can be anticipated, then the Weather Service Office in the project area shouldbe asked to supply an average monthly relative humidity for that period.

• Protecting concrete against moisture loss at all timesduring placing, finishing, and during its curing period.

d. Placing temperature. The problems of placingconcrete in hot weather involve, among other things, slumploss during mixing and transporting and surface crazing afterplacement. To reduce these problems, limits are placed onthe concrete placing temperature in the guide specifications.The temperatures that are selected for inclusion in eachparagraph are dependent on the normal relative humidity inthe project area. The required maximum placingtemperature may be lower if required by thermal studies andincluded in the appropriate DM.

e. Plastic-shrinkage cracks. Plastic-shrinkagecracking is often associated with hot-weather concreting,particularly in arid climates. It occurs primarily in flatwork,but beams and footings are also susceptible if theevaporation rate exceeds the rate of bleeding. Plastic-shrinkage cracking is easily identified since it begins toappear before the concrete completely hardens. The cracksappear in a random pattern on the surface and are wide atthe surface, tapering to nothing at a shallow depth. Thecracks may be up to 1/4 in. (6 mm) wide at the surface andseldom more than 4 to 6 in. (100 to 150 mm) deep. Highconcrete temperatures, high ambient temperatures, high windvelocity, and low relative humidity, alone or in combination,cause rapid evaporation of water from the concrete surfaceand significantly increase the probability of plastic-shrinkagecracking. ACI 305R provides a graphical means for makingevaporation rate estimates based on all the major factors thatcontribute to plastic-shrinkage cracking. A closeapproximation of evaporation rate can also be made in thefield by evaporating water from a shallow pan of knownsurface area. Initial and subsequent weighings made to thenearest 0.1 g every 15 to 20 min allow the evaporation rateto be calculated in a reasonably short period of time prior toconcrete placement. When the evaporation rate approaches0.2 lb/ft2/hr, precautions should be taken by the Contractor

to reduce moisture loss, or plastic-shrinkage cracking mayoccur.

f. Effect on strength and durability. Concretematerial properties and the concrete mixture proportionshave a significant effect on both fresh and hardenedproperties of concrete placed during hot weather. Highmixing water temperatures cause higher concretetemperatures which, in turn, increase the amount of waterneeded to achieve a given slump. If additional water isadded so that the w/c is increased, the strength anddurability of the concrete may be detrimentally affected. A1-in. slump decrease may typically be expected for every20 °F increase in concrete temperature. The increase inwater content necessary to maintain concrete slump in hotweather will range between 2 and 4 percent depending onthe concrete temperature. This increase may be significantlyless if WRA or HRWRA is used. The use of a slowersetting Type II portland cement may help improve thehandling characteristics of concrete in hot weather; however,concrete made with slower setting cements may be morelikely to exhibit plastic-shrinkage cracking. Because thecement makes up only 5 to 15 percent of the mass of aconcrete mixture, its temperature has a relatively minoreffect on concrete temperature. An 8 °F increase in cementtemperature is typically required to increase concretetemperature 1 °F. If the cement has a false set tendency,slump loss may be aggravated in hot weather. RetardingWRA and HRWRA have all been beneficial in offsettingsome of the undesirable effects of hot weather on concrete.Admixtures without a performance history with the concretematerials selected for the work should first be evaluated inlaboratory trial batches at the expected high temperature,using procedures described in ACI 305R. Some HRWRA’smay not demonstrate their potential benefits when used insmall laboratory batches. Further testing may then berequired in full-size batches. Since concrete contains arelatively large mass of coarse aggregate, changes in itstemperature have a considerable effect on concrete

8-8

Page 79: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

temperatures. For example, a 1.5 to 2 °F coarse aggregatetemperature reduction will lower the concrete temperatureabout 1 °F. Therefore, cooling coarse aggregate is a veryeffective means of lowering concrete temperature.

g. Cooling. If limiting temperatures govern thedelivery of the concrete, the availability of cooled concreteshould be ascertained well in advance of the need. Coolingof the concrete will require installation of special equipmentand assurance of an ample supply of cooling materials suchas ice or liquid nitrogen for the anticipated concrete volumeand placement rate. Maintaining a continuous flow ofcooled concrete to the placement is important to avoid thepossible development of cold joints. Arrangements shouldbe made for the ready availability of backup placingequipment and vibrators in the event of mechanicalbreakdowns. Arrangements should be made for ample watersupply at the site for wetting subgrades, fogging forms, andfor moist curing, if applicable. The fog nozzles used shouldproduce a fog blanket and should not be confused withcommon garden-hose nozzles. Materials and means shouldbe on hand for erecting temporary windbreaks and shades asneeded to protect the concrete against drying winds anddirect sunlight. The materials and means for the curing

methods selected should be readily available at the site topermit prompt protection of all exposed concrete surfacesfrom drying upon completion of the placement.

h. Curing. Proper moist curing of concrete placed inhot weather is the best curing method for assuring strengthdevelopment and minimizing drying shrinkage. It can beprovided by ponding, covering with prewetted burlap orcotton mats, covering with clean sand kept continuouslymoist, or continuous sprinkling. The use of a liquidmembrane-forming curing compound may be moreeconomical and practical than moist curing in manyinstances. Properly applied pigmented membrane-formingcuring compounds provide good protection from directsunlight. On flatwork, application should be startedimmediately after disappearance of the surface water sheenafter the final finishing operation. Forms should be coveredand kept continuously moist during the early curing period.They should be loosened, as soon as practical withoutdamaging the concrete, and provisions made for curingwater to run down inside them. A thorough discussion ofcuring and other topics related to hot-weather concreting isgiven in ACI 305R.

8-9

Page 80: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 9Concrete Quality Verification and Testing

9-1. Quality Verification

a. General. The construction quality verificationsystem is necessary to assure the Government that thefinished work complies with the plans and specifications.The inclusion of quality control requirements for theContractor does not relieve the Contracting Officer of theresponsibility for safeguarding the Government’s interest.For civil works concrete construction, the resident engineerhas the added responsibility for obtaining the quality ofconcrete in the various parts of the structure based onexplicit instruction from the engineering division of thedistrict office (see Chapter 6 of this manual). Depending onthe scope of the work and the guide specification selected,the Government may or may not select the mixtureproportions, but in all cases, the Contracting Officer isresponsible for assuring that the strength and otherrequirements as set forth in the specifications or in thedesigner’s instructions to the field personnel are met. TheContractor will mold, cure, and perform strength testing ofconcrete cylinders as part of his quality control program.The Government will perform compressive strength testingas part of the quality assurance program. In case of archdams, all strength testing will be molded, cured, andperformed by the Government. The budget for these GQAresponsibilities should be included in the ProjectManagement Plan. Details of requirements and proceduresfor CQC and GQA are specified in ER 1180-1-6,"Construction Quality Management," which contains detailedrequirements for controlling projects with prescriptivespecifications such as the mass-concrete specification. TheGQA responsibility is not to be imposed on the constructioncontractor. If personnel shortages preclude the use ofgovernment personnel to accomplish GQA, it should bedone by a commercial testing organization under contract tothe Government.

b. Government quality assurance. During theconstruction stage, the Contracting Officer, through hisauthorized representatives, which include the residentengineer and his staff, is responsible for acceptance testingand quality verification to enforce all specificationrequirements and for monitoring the Contractor’s qualitycontrol operations. These functions include but are notlimited to: verification of all operations for compliance withspecifications, reviewing and, when required, approvingcontractor submittals including certificates of complianceand contractor-developed mixture proportions. If acceptancetesting of cement, pozzolan, slag, admixtures, or curingcompounds are required, the resident engineer is responsible

for making the necessary arrangements for such tests withthe appropriate division laboratory, or in the case of cement,pozzolan or GGBF slag, with WES. The resident engineeris responsible for requesting the division laboratory to verifythe quality of the government project laboratory, anycommercial laboratories operating under contract to theGovernment and the contractor’s quality control laboratoryas required by ER 1110-1-261, "Quality Assurance ofLaboratory Testing Procedures."

(1) Quality assurance representative. This individualmay be a government employee or may be an employee ofa private engineering firm under contract to the Governmentand not affiliated with the construction contractor. He is thekey figure in the operations attendant to concrete qualityassurance. The effectiveness of the quality verificationoperation in assuring uniformity of the concrete and inobtaining compliance with specification requirementsdepends to a large degree on the thoroughness with whichthe quality assurance representative is instructed and trainedin the performance of his duties. While it is expected thatthe quality assurance representative will have knowledge ofthe basic requirements for the production of concrete of highquality, it is nevertheless necessary to instruct him in thedetails of quality verification as they apply to each specificproject. This should be accomplished through trainingconferences together with written guides and instructionsprepared by the government concrete engineer and his shiftsupervisors or by the project engineer on smaller projects.Previous experience on similar work is highly desirable.Previous experience cannot entirely compensate, however,for proper instruction and training of quality assurancerepresentatives in the duties unique to a particular project.These representatives should be assigned to a project priorto completion of the contractor’s concrete plant. Preferably,they should be trained for duty on a particular project as theconcrete plant is being erected so that they may becomethoroughly familiar with the plant and particularly thoseaspects of the equipment bearing on the quality verificationprocedures. For example, on a large concrete project themixing plant quality assurance representative should becomefamiliar with the mixing plant and all of its operatingfeatures. All persons assigned as quality assurancerepresentatives should be certified by ACI or haveequivalent training. EP 415-1-261 provides detailedresponsibilities and a check list for the GQA representative.

(2) Testing technicians. Technicians, eithergovernment employees or employees of a privateengineering firm contracted by the Government, areresponsible for the quality assurance testing to verify theContractor’s quality control tests and for acceptance testingof the concrete. They are also responsible for obtaining

9-1

Page 81: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

samples of materials for other laboratories. All work doneby technicians must be done in strict accordance withapplicable standards to ensure the validity and acceptance oftest results. Certification of concrete technicians is providedby ACI. This certification can be obtained by completinga 3- or 4-day course offered by ACI at announced times inmany of the major cities of the country or by completing theConcrete Technicians Course at WES. All persons assignedas concrete technicians and responsible for quality assurancetesting should be certified by ACI or have equivalenttraining.

(3) Organization.

(a) General. The Government’s quality assuranceorganization must be flexible to allow for changes in ratesof placement as construction progresses. In general, thefollowing organizations should be provided by theGovernment to satisfy the area/resident engineer’sresponsibility for acceptance testing and quality verificationto enforce all specification requirements and for monitoringthe contractor’s quality-control operations.

(b) Major concrete project. On large concreteprojects, the organization should have a materials engineer(or technician) reporting directly to the resident engineer andbeing responsible for all phases of quality assurance fromaggregate production through curing and protection of theconcrete. The organization should include a shift supervisor(quality assurance representative) for each shift. Under eachshift supervisor, the organization should include one placingquality assurance representative for each location at whichconcrete is being placed, one mixing plant quality assurancerepresentative, and one quality assurance representativeassigned to verification of cleanup, curing, protection, andfinishing. The organization should include a laboratorytechnician and assistants as required to handle acceptancetesting of aggregates and concrete, to consolidate reports,prepare summary reports, and keep records. The laboratorytechnician should report directly to the materials engineer.On a very large project, several contracts on the sameproject may be supervised by a single area engineer. Undersuch circumstances, the engineer reports to the residentengineer and supervises all concrete activity on the project.The quality assurance force required for aggregate qualityverification depends upon job conditions. Where theContractor’s quality control has been proven satisfactory,sampling should be required only at the point of acceptance(mixing plant) and the quality verification should consistonly of routine observation of plant operations; this workcan be handled jointly by the shift supervisors and theengineers or by special assignment. Usually quality

verification of aggregate processing operations does notrequire continuous assignment of personnel.

(c) Moderate concrete volume. For smaller projects,it is necessary to modify the organization to suit the projectconditions. In most instances, quality assurancerepresentatives are required to serve in dual capacities,shifting from quality verification of concrete mixing andplacing to other phases of the work as required. Qualityassurance representatives may also be required to verifycuring, protection, and cleanup. It is desirable to havecontinuous quality verification of batching and mixingoperations.

(d) Ready-mix operations. When concrete is centrallymixed at the plant, a quality assurance representative shouldbe on duty full time at the plant where he can observe andtest the mixed concrete and can reject concrete which failsto meet job requirements. When concrete is transit-mixed,full-time plant quality verification is desirable, but primaryresponsibility for acceptance of concrete belongs to thequality assurance representative at the site of the work. Iffull-time plant quality verification is not possible, the plantshould be visited frequently to ensure that batching iscarried out properly.

(e) Small job. There is a tendency to overlook smalljobs and the small parts of large jobs. Frequently, smallstructures such as curbs and sidewalks have very severeexposure and require concrete of high durability. Althougha quality assurance representative on a small job may haveduties other than concrete quality verification, no concreteplacing should be started without a quality assurancerepresentative on hand.

(4) Records. The value of clear, concise, andcomplete records is sometimes overlooked during the con-struction of a project. In devising a system of reports, andpreparing forms for these reports, it should be realized thatthese reports will constitute a part of the official record ofthe construction operations and may be the sole source ofreliable information on the procedure, practices, and resultsobtained during construction. Reports in various formsshould be made daily and at other stated intervals forseveral purposes. Standard forms are available for reportingmost test results. Where necessary, special forms may bedevised on the project to suit project requirements. Reportswill supply information on, and preserve as a permanentrecord, facts concerning progress of the work, factorsaffecting progress, instructions given to contractors, samplessecured, tests made, and any other necessary data. Unusualoccurrences in the plant may be noted on the recorder chartby the quality assurance representative or plant operator.

9-2

Page 82: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

The information should ultimately appear in a report. Thereports made by placing quality assurance representativesand quality assurance representatives engaged on cleanup,curing, finishing, and protection should follow a well-devised standard form on which the essential facts arerecorded for the period of quality verification. Governmenttest results should include control charts and variability ofthe material tested. Each such report form should alsoprovide space for recording unusual happenings and for anypertinent remarks concerning shift operations.

9-2. Required Sampling and Testing for CQC andGQA

The following tests are normally required for a major civilworks concrete construction project for CQC and GQApurposes. The procedures and frequencies of all thenecessary CQC tests should be included in the contractspecification. Tests for GQA are at the Government’sdiscretion and should not be specified in the specificationexcept those cases where sampling and facility are theContractor’s responsibility. The required frequencies forGQA and government acceptance tests should be includedin the Engineering Considerations and Instructions to FieldPersonnel for each project. The recommended testingfrequencies for GQA are listed in the following paragraphs.

a. Aggregate grading. In order to determinecompliance with the specification requirement thataggregates must be within certain grading limits as deliveredto the mixers, samples must be obtained as delivered to themixer. On mass concrete projects containing 150-mm(6-in.) NMSA, the specifications require that an automaticsmall screening plant be included in the batch plant. Onconcrete projects containing 75-mm (3-in.) NMSA, a costanalysis should be made before specifying the automaticscreening plant. The automatic screening plant makes useof angled quarry screens, which by their nature are 80-percent efficient at the best and cannot be compared directlyto Gilson screens, which are 95- to 98-percent efficient.The automatic screening plant must contain controls to varythe angle and frequency (vibrations per minute) of eachindividual screen. Optimum loading, screen angle, andfrequency of each screen must be established by theContractor before construction begins. Correlation tests withGilson sieving equipment must be performed beforeconstruction and every 60 days while concrete productioncontinues. The quarry screens on the automatic screeningplant will normally require a larger screen than the Gilsonscreens for comparable results. With such a device, thesampling, screening, determination of mass, and disposal isaccomplished automatically. Normally, it is not necessaryto procure samples at any other location. Samples may be

procured at any point in the production line where it isdeemed necessary. Where 150-mm (6-in.) NMSA is used,it might not be feasible to sample the 75- to 150-mm (3- to6-in.) fraction from the weigh batcher. Then samples maybe obtained from the conveyor belt or other convenientplace as close as possible to the end of the handlingoperations. When sampled from a conveyor belt, the beltshould be stopped, and the sample should consist of acomplete section and not hand-picked from the top. Whereaggregates are supplied by a commercial producer locatedsome distance from the project, sampling for acceptancetests will not be made at the producer’s plant. Such testswould not reflect the possible effects of segregation instockpiling at the project and breakage in handling.

(1) Frequency.

(a) On-site plant. During each 8-hr shift whenconcrete is being produced, at least one sample of each sizeof aggregate should be taken. During the early stage of alarge project, several samples per shift should be tested untilthe production control has achieved uniformity. After 1month, if the Contractor’s control testing has proven to besatisfactory, frequency of government sampling may bereduced to one-third of that stated above.

(b) Off-site commercial plant. The frequency of QAtesting of the aggregate grading at an offsite commercialplant will vary somewhat with the quantity of concrete andthe rate of concrete usage from that plant where concrete issupplied to many customers and the concrete mixture isfurnished by the contractor. For minor concrete jobs, theaggregate should be tested before concrete placing beginsand once per week while concrete is being placed. Onlarger structural concrete jobs, the aggregate grading shouldbe tested by the GQA representative before start of concreteplacement and at least twice per week thereafter whileconcrete is being placed.

(2) Size of samples. Sample sizes for sieve analysisare given in ASTM C 136 (CRD-C 103). For fine aggre-gates and finer sizes of coarse aggregate, samples obtainedin accordance with CRD-C 100 may be reduced in size bya sample splitter or by carefully following instructions forquartering given in ASTM C 702 (CRD-C 118). Foraggregate sizes smaller than 37.5 mm (1-1/2 in.), therequired sample sizes are sufficiently large in relation toindividual particle size so that compliance with the gradingspecification may be fairly determined by a single test. For37.5 mm (1-1/2-in.) and larger sizes, however, this is nottrue. While sample sizes given in ASTM C 136 (CRD-C103) for nominal maximum aggregate sizes larger than37.5 mm (1-1/2 in.) are practical for laboratory sieve

9-3

Page 83: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

analysis testing equipment, the samples are subject to largerandom sampling errors. Therefore, compliance with speci-fication should be determined from the average of fiveconsecutive tests. Whenever a single test result shows amajor deviation from specification requirements, thefrequency of sampling and testing should be accelerated toas great an extent as practical until it is established whetherthe indicated noncompliance was the result of samplingerror or the result of an actual deficiency in the aggregateprocessing equipment. Sometimes a single retest will besufficient to establish the cause of the noncompliance. Ifsampling and testing equipment is installed that is capableof handling specimens five times as large as those requiredby ASTM C 136, averaging of test results is not necessary.

b. Aggregate quality - large project.Paragraph 7-1requires initial testing of the Contractor’s chosen aggregatesources to confirm that the aggregate quality has notchanged since it was tested in the design stage and toconfirm that it meets aggregate quality specificationrequirements. Quality testing by the Government should beperformed during the life of the contract at about 10 percentof the rate listed in the CQC requirements of thespecifications. Tests performed by the Contractor underCQC should be monitored carefully by the GQArepresentative. Experience has shown that quality ofaggregate can change, either gradually, or at timesdramatically as production proceeds laterally and verticallyin the source. Failing quality tests will require additionaltesting by the Contractor and by the Government. Residentoffice personnel should record and monitor the location inthe quarry or pit from which the aggregate is beingproduced. A change in visual appearance or quality testresults could signal a change in production location at thesource.

c. Free moisture on aggregates.Adjustments ofbatch weights to compensate for variation in aggregatemoisture is a basic contractor responsibility. TheContractor’s methods for complying with this requirementshould be reviewed and verified at least once weekly.Whenever the concrete is considered out of control due toslump or air content, the government testing should increasein a cooperative effort with the Contractor in obtainingtesting information needed to perform the necessaryadjustments. When a moisture meter is required by thespecifications, its accuracy should be verified at least onceper week.

d. Slump and air content.The slump test ASTM C143 (CRD-C 5) is made as a check on the uniformity of theconcrete and to determine whether the concrete being sentto the forms is placable. Samples for slump and air content

tests may be taken and tested at the batch plant for onsiteplants; however, the required slump and air content is thatrequired at the placement. If slump or air content loss isexperienced, then occasional tests must be performed at theplacement site to determine amount of slump loss or aircontent loss. In that case, slightly higher values may beadopted for use at the plant, so that the proper slump and airare obtained at the placement. Considerable slump loss andair content loss are usually associated with conveying orpumping concrete considerable distances. Correlation testsamples for compressive strength is also necessary whenconsiderable slump and air content loss is experienced.Variation in slump is caused chiefly by variation inaggregate moisture and air content. Whenever either orboth of these factors vary, slump tests should be made asfrequently as needed to ensure that the concrete is of therequired consistency. When the mixture is of the requiredconsistency, slump tests should be made at least twice pershift for each concrete mixture being placed. Control of aircontent is essential to the placeability and the durability ofconcrete. When no control problems are encountered, theair content should be determined at least twice per shift foreach concrete mixture being placed. When the concretecontains a fly ash with a variable carbon content, the testingrate should be increased. After 3 months, if theContractor’s control has been adequate, slump and aircontent need to be measured by the Government only whencylinders are fabricated.

e. Concrete temperature.The temperature of cooledconcrete should not be measured until 20 minutes aftermixing. If the largest aggregate was cooled for aninsufficient period of time, the particles may be only surfacecooled. If so, this fact will be reflected in the delayedtemperature reading. The sensing element of thethermometer should be at least 3 in. below the surface ofthe fresh concrete when the measurement is made. Thetemperature of each concrete mixture should be checkedtwice per shift when concrete is being placed.

f. Compressive strength.

(1) Purpose. Strength tests are performed for differentpurposes depending on the type of construction and thespecification used. For mass-concrete structures wheremixture proportioning is provided by the Government,strength tests are needed to measure the variability of theconcrete mixture. In this case, strength is not necessarilythe most critical factor concerning the concrete mixture.Other considerations, such as durability or thermal cracking,may dictate the w/c. Nevertheless, compressive strengthsare good indications of variations in other concreteproperties. For concrete structures where mixture

9-4

Page 84: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

proportioning is the Contractor’s responsibility, concretestrength is a part of the acceptance requirements. Thestrength criteria are normally determined by structuralrequirement.

(2) Testing responsibility. The specifications shouldrequire the Contractor to mold, protect, cure, and testcompressive strength cylinders on all concrete constructionwhere the Government furnishes the mixture proportions,except for arch dam construction where the Government willperform all the strength testing. The frequency of testing bythe Contractor should be in accordance with paragraph 9-2f(4). In addition, the GQA representative should mold,cure, protect, and test at least 1 set of test cylinders for each10 sets of cylinders made by the Contractor. The GQA testcylinders should be from the same batch of concrete as oneof the CQC test cylinders. After a minimum of 30 sets ofcylinders are tested, the resident engineer may choose tolower the amount of government-molded, -cured, and -testedcylinders to 5 percent (1 in 20) of the cylinders tested bythe Contractor if the CQC tests are proven satisfactory. A10-percent differential in the test results between CQC testsand GQA tests would be cause for further investigation ofthe Contractor’s casting, curing, and testing procedures andequipment.

(3) Sampling plan. The frequency of sampling,number of cylinders made, and ages at which the cylindersare tested will vary with the type and size of the project. Atthe beginning of each project, a sampling plan will bedeveloped by the Government that is consistent with theproject specifications. The sampling plan should obtaininformation on the quality of each class of concrete at theleast cost. The sampling plan must reflect the variabilitycharacteristics of heterogeneous concrete. The individualsamples must be taken in such a manner that each sampleis selected in an unbiased manner. The number of testspecimens fabricated will depend on the number of ages atwhich they are to be tested. For part of the work, twospecimens should be tested at the same age to derive thewithin-batch coefficient of variation. A test is defined asthe average strength of all specimens of the same age,fabricated from a sample taken from a single batch ofconcrete. Samples should be obtained by means of arandom sampling plan designed to minimize the possibilitythat choice will be exercised by the sampler. Probabilitysampling of materials is discussed in ASTM E 105 (CRD-C579). This procedure should be used for guidance indeveloping a random sampling method. The sampling planshould also include the predetermined sampling locationwhere representative samples will be obtained.

(4) Frequency and testing age. During the early stagesof a project, it is desirable to increase the frequency oftesting until control is established. Structural concreteshould normally be sampled once per shift and massconcrete once per day for each concrete mixture placed.When mixture proportions are provided by a divisionlaboratory, as would be the case of a large mass structuresuch as a lock or dam, accelerated strength testing should beused to control batching and mixing based on relationshipsdeveloped by the laboratory. Two specimens will normallybe molded and cured in accordance with ASTM C 684(CRD-C 97), Method A. Where conditions are not suited tothis method, Method B or C may be used. Laboratorymixture proportioning studies should be developed with thesame method that will be used on the project. The designage should be decided by the designer depending on thetype of structure involved, the types of cementitiousmaterials and the loading conditions anticipated. Asexamples, the design age for a large lock or dam may be180 days or even 1 year if design loadings are not likely tooccur sooner. However, the design age for a bridge orpumping station will likely be 28 days and could possiblybe shorter depending on the construction techniques usedand the construction and in-service loadings anticipated.The information age could be selected to coincide withform-stripping schedules, removal of shoring, or in theabsence of construction considerations at intervals such as7, 14, or 28 days. In addition to control or acceptancecylinders, occasionally there will be a need for extracylinders. With prestressed concrete, for example, whenprestressing is to be applied when the concrete attains itsloading strength, it will be necessary to test cylinders atvarious ages. Sometimes field-cured cylinders are used indetermination of form removal time. A sampling plan guidefor number and test age of cylinders is shown in Table 9-1.

(5) Sampling and testing methods. On all projects,concrete will be sampled in accordance with ASTM C 172(CRD-C 4). The test specimens will be molded and curedin accordance with ASTM C 31 (CRD-C 11). When thenominal maximum size aggregate is larger than 50 mm(2 in.), the concrete sample shall be wet sieved inaccordance with ASTM C 172 over a sieve having 50-mm(2-in.) square openings. Concrete test specimens will betested in accordance with ASTM C 39 (CRD-C 14).

(6) Analysis of tests. Strength variation is the keyconsideration in analysis of data derived from tests ofconcrete cylinders. Because of this variation, statisticalmethods are used to analyze and present the numerical data.The magnitude of variations in the strength of concrete testspecimens depends on how well the materials, concrete

9-5

Page 85: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 9-1Number of Cylinders to Be Cast

Number of Test Specimens at Various Ages

Concrete Type 1 Day Information Age(s) Design Age

Structural & minor 1 2

Mass 2 1 2

manufacture, and testing are controlled. The strength resultswill vary above and below an average and fall into someprobability distribution. The strength test results should beevaluated to determine the within-batch-coefficient ofvariation and overall standard deviation. ACI 214provides details on these methods of analysis. Theprocedures involve mathematical computations which lendthemselves to computer processing. There are manycommercial programs available for this purpose. Theselection of appropriate computer programs for evaluatingtest data may be made with the advice of CECW-EG. Thestandards for control are shown in Table 9-2 for 28-daystrength results. The standards for accelerated strength testresults will be developed by the division laboratory based onan analysis of 28-day strength results and the acceleratedstrength test results. After the first 30 test results areavailable on the project, they should be analyzed for averagestrength and standard deviation and the mixture proportionsadjusted as appropriate.

(a) Within-test coefficient of variation. Within-testcoefficient of variation is caused by fabricating, curing, andtesting the cylinders. When the coefficient of variation isgreater than 5.0 percent, the following procedures should beevaluated:

• Sampling procedures• Fabrication techniques• Handling and curing cylinders• Quality of molds• Variation in curing temperatures• Variation in curing moisture• Delays in transporting to the laboratory• Size of the test specimens• Capping procedures

(b) Overall standard deviation. Overall standarddeviation is a term representing a value related to bothwithin-test variation and batch-to-batch variation. Theoverall standard deviation is defined as the square root of

the sum of squares of within-test and batch-to-batchstandard deviations. The variation may be introduced bypractices in proportioning, batching, mixing, andtransporting concrete. When overall standard deviation ishigher than 600 psi, the following procedures should beevaluated:

• Characteristics and properties of the ingredients• Batching and mixing procedures• Sampling procedures• Causes for variation in w/c, such as aggregate

moisture• Causes for variation in water requirements

(7) Control criteria. On projects where mixtureproportions were developed by the Contractor, theContractor shall submit revised proportions when thecompressive strength tests do not meet the specified criteria.On projects where mixture proportions were developed bya division laboratory, the area/resident engineer in concertwith engineering division personnel should revise theproportions as necessary to meet the required averagestrength criteria. In both cases, adjustments to theprocedures should be made after the first set of 30 tests ifthe overall standard deviation is approaching or beyond thelimit of 600 psi.

(8) Prediction of later age strengths. Where possible,the division laboratory will develop an appropriatecorrelation of the relationship between accelerated tests andstandard cured compression tests. At the start of concreteplacement, testing should be performed at accelerated agesand later age. After the first 30 tests, the linear regressionequation should be verified or reestablished. If there is adiscrepancy between equations, the division laboratoryshould be consulted to analyze the data. As confidence isgained with predicting later age strength with the linearregression equation, the amount of later age testing may bereduced by as much as 50 percent.

9-6

Page 86: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 9-2

Standards of Control for Concrete Compressive Strength

Standards for Concrete Control

Class of

Operation

Excellent Very Good Good Fair Poor

Within test,

coefficient of

variation, percent

0 - 3.0 3.0 - 4.0 4.0 - 5.0 5.0 - 6.0 Above 6.0

Overall standard

deviation, psi

0 - 400 400 - 500 500 - 600 600 - 700 Above 700

9-3. Nondestructive Testing

a. General. Nondestructive testing of concrete asdescribed herein includes methods of tests on concretestructures or structural members which do not reduce thefunctional capability of the structure, although some of themethods listed do require minor repairs if the concrete willbe exposed to view. The tests described are those which areused to gain an indication of the quality of hardenedconcrete in place.

b. Policy. Nondestructive testing will not be used inlieu of compressive strength tests of cylinders, air contenttests by the pressure method, slump tests, or any other testfor the evaluation and acceptance of concrete placed on anycivil works projects.

c. Applicability. Nondestructive tests may be used tolocate areas of unsound concrete or concrete suspected ofbeing significantly below the specified levels of strengthrequired by the design or the required levels of durability.If areas are located where unsound, weak, or deterioratedconcrete is likely, the condition of the concrete may beconfirmed by coring unless the structure is so heavilyreinforced that useful specimens cannot be obtained.Nondestructive testing may also be used to indicate changeswith time in characteristics of concrete such as those causedby the hydration of cement so that it provides usefulinformation in determining when forms and shoring may beremoved.

d. Nondestructive testing methods.The methodsdiscussed do not represent all the available methods but onlythose that have been standardized by ASTM. More detailed

discussion of the advantages and limitations of these testmethods is given in ACI 228.1R.

(1) Rebound hammer (ASTM C 805 (CRD-C 22)).The rebound hammer consists of a spring-loaded steelhammer which, when released, strikes a steel plunger incontact with the concrete surface, and rebounding indicatesa rebound number on a calibrated scale. Only the concretein the immediate vicinity of the plunger influences therebound number; therefore, the test is sensitive to the localconditions where the test is performed. Because therebound hammer tests only the near-surface layer ofconcrete, the rebound number may not be representative ofthe interior concrete. The probable accuracy in predictingconcrete strength in a structure by this method is only± 25 percent, so its use is clearly limited to attempting thedifferentiation between areas of large quality variation in thesame structure. Closer accuracy can be obtained bycalibrating the hammer with project concrete of knownstrength. The main advantage of the rebound hammer is itsextreme portability so that many tests may be made easilyin a short period of time.

(2) Penetration resistance (ASTM C 803 (CRD-C 59)).The penetration-resistance test uses a powder-driven stud tomeasure the penetration resistance of concrete. This test,like the rebound hammer, is a hardness tester; however,attempts continue to be made to correlate the penetration ofthe stud to concrete strength. The apparatus is easilyportable, using a modified powder cartridge stud gun andstuds or probes. The resulting damage to the concretesurface is minor and may be easily repaired. A largenumber of tests may be completed in a relatively shortperiod of time. Attempts to correlate the penetration-resistance test results with core tests and cylinder tests

9-7

Page 87: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

indicate coefficients of variation and range about 10 timesas large as the core and cylinder test results. Therefore, theuse of the this test should be limited to applications wherelarge variations are suspected in the concrete quality or todetermine the locations for borings.

(3) Cast-in-place pullout tests (ASTM C 900 (CRD-C78)). Pullout tests use a hollow stem ram to pull a bolt witha washer on its lower end that has been cast in the concreteat the time of placement. The pullout assemblies areincorporated into the formwork for critical structuralmembers. As an alternative, pullout assemblies may be castinto large blocks which are cast at the same time as thestructural member and consolidated and cured in a similarway. The main advantage of the pullout tests is that it doesproduce a well-defined failure in the concrete and measuresa static strength property of the concrete in a structure. Theequipment is easily portable. The pullout strength doescorrelate with compressive strength; however, the coefficientof variation of pullout test results has been found to beapproximately 7 to 10 percent. This is about two to threetimes greater than that of standard compressive strengthtests. The main limitations are that the test locations arefixed at the time of placement which limits the usefulnessof the pullout test in troubleshooting problems suspectedafter placement is completed and the necessity of repairingthe surface which is marred by a crater about 6 in. across.Commercial inserts have embedment depths on the order of1 to 2 in. Since the vibrator operator may notice where theinserts are, the consolidation of concrete around them maynot be representative of the entire member.

(4) Maturity method (ASTM C 1074 (CRD-C 70)).Assuming sufficient moisture is present, the rate ofhydration of the cementitious materials in a concrete mixtureis influenced by the concrete temperature. Therefore, thestrength of concrete at any age is a function of its thermalhistory. The maturity method accounts for the combinedeffects of temperature and time on strength development.The concrete thermal history and a maturity function areused to calculate a maturity value which quantifies thecombined effects of time and temperature. Concretestrength is expressed as a function of its maturity by meansof a strength-maturity relationship. So, if samples of thesame concrete are subjected to different curing temperatures,the strength-maturity relationship for that concrete and thethermal histories of the samples can be used to estimatetheir strengths. The strength-maturity relationship must beestablished for the concrete to be used in the structure inorder to use the maturity method. ASTM C 1074 describesthe procedure to be followed in developing this relationshipusing the concrete of interest. The temperature of history ofthe in-place concrete is continuously monitored, and from

these data the in-place maturity is calculated. The in-placeconcrete strength can then be estimated at any point in timebased upon the concrete maturity at that same time and thestrength-maturity relationship. Commercial instruments areavailable which automatically compute concrete maturity;however, care should be exercised in their use since thematurity function used by the instrument may not beapplicable to the concrete in the structure. To use thematurity method to estimate in-place concrete strength, theremust be sufficient moisture for continued hydration, and theconcrete in the structure must be the same as that used todevelop the strength-maturity relationship. Proper curingassures the first condition will be met, and conductingslump, air content, unit weight, and accelerated strength testson concrete representative of that going into the structurewill assure the latter condition is met. The maturity methodhas obvious applications in the control of form stripping,shoring removal, and termination of cold-weather protection.

(5) Cores (ASTM C 42) (CRD-C 27). Coring isusually the method ultimately chosen to determine the in-place characteristics of concrete especially if the disputeinvolves payment to the Contractor or other problems suchas the location of the member or the amount ofreinforcement present. Planning for the core sampling andlaying out the drill holes should follow (ASTM C 823(CRD-C 26)). In heavily reinforced structures, it may beimpossible to obtain a core sample from which compressivestrength specimens may be taken since reinforcing steel maybe so prevalent in the concrete that cores free of reinforcingsteel and having height-to-diameter ratios equal to 1 or morecannot be obtained. It may be possible, however, to obtainspecimens from such cores which will allow a determinationof air-void system parameters (ASTM C 457 (CRD-C 42))or analysis for the products of reactivity. Additionally, theeffect of severing reinforcing steel on the integrity of thestructure should be analyzed. If possible, the size of thecore taken should be related to the nominal maximum sizeaggregate in the structure. If 37.5-mm (1-1/2-in.) maximumsize aggregate is used in the structure then 6-in. coresshould be drilled. In structures using larger aggregate, itmay be practical to take cores up to 18 in. in diameter, butcosts increase rapidly and the large core usually cannot betaken to a depth of more than 3 or 4 ft. Coring may proveexpensive and the holes have to be backfilled, but theresulting data are usually accepted as the best evidence ofthe condition of the concrete in place.

(6) Pulse velocity method (ASTM C 597 (CRD-C51)). This method involves the application of a mechanicalimpulse to a solid mass of material. The speed of thewaves which are subsequently generated and which passthrough the material are dependent on the elastic properties

9-8

Page 88: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

of the material. The pulses can be generated either by ahammer blow or by an electroacoustic transducer. Thepulse velocity method may be used to determine theuniformity of concrete. However, a number of factors affectpulse velocity measurements, including concrete moisturecontent and the presence of reinforcing steel. Reinforcingsteel may be especially troublesome if it is oriented parallelto the pulse-propagation direction. The resulting apparentvelocity through such a member will be greater than theactual velocity through the concrete. Failure to account forthe presence and orientation of reinforcing steel may lead toinaccurate conclusions regarding the concrete quality. Whilepulse-velocity equipment is commercially available, its useand the interpretation of the pulse-velocity measurementsrequires special training and techniques.

(7) Other methods. Other methods in addition tothose above are in the development stages. Contact WESfor additional information.

9-4. Preplacement Quality Verification

The quality of all concrete placement areas should beverified prior to the actual placement of any concrete. Forcomplicated placements, these quality verifications should bemade as each element of the preparation for actualplacement is completed. That is, foundation preparation,joint preparation, form installation, the placement ofreinforcing bars, all embedded metal work, waterstops,conduits, mechanical piping, and cleanup should be verifiedfor quality and checked out as each is completed. Otheritems that must be kept in mind at all times during allphases of this work are the provisions for safety and accessto the placements, including all scaffolding, walkways, workplatforms, ladders, and railings along with whatever weatherprotection and drainage provisions are required. If eachelement of this preparation is thoroughly verified as it iscompleted, it will then only require a cursory verificationimmediately prior to the concrete placement to be assuredthat the conditions have not changed. On a small or simpleplacement, the final quality verification may be all that isrequired prior to concrete placement. These preplacementverifications will be more systematic and accurate if achecklist is used. This checklist is to be initiated and datedby the representatives of the Contractor and the Governmentas each element in this preparation is completed. Thesechecklists are known by various names, such as liftcheckout cards and form checkout cards. The format ofthese checklists can vary according to the projectrequirements and the practice of the individual districts. Allessential information is recorded. A separate form orcheckout card is to be prepared for each concrete placementand retained in the Government’s official project files. The

Guide Specifications "Mass Concrete" (CW-03305) and"Cast-In-Place Structural Concrete" (CW-03301) also requirethe Contractor to provide a written report certifying that allelements of the placement are ready to receive concrete.While it has become the practice in some districts anddivisions for the Contractor’s representative and the Corps’quality assurance representative to jointly verify and sign thecheckout card, it should be kept in mind that this is, in fact,the sole responsibility of the contractor and not be inferredas a joint responsibility. The advantage of a jointly signedcard is that it establishes the means by which both theCorps’ quality assurance representative and the contractor’squality control representative will be satisfied that theelements of the placement meet the project specificationrequirements before the concrete placement begins. Figure7-1 is an example of a form checkout record.

9-5. Project Laboratory

a. General.A government field laboratory should beprovided as close as possible to the mixing plant. Thebuilding housing the laboratory normally includes officespace for the concrete personnel and facilities for filing theproject concrete records.

b. Space requirements.

(1) Large-volume mass concrete project. At least1,000 ft2 of work space, exclusive of office space, should beprovided for major mass concrete projects where it isexpected that concrete will be placed on a continuous day-to-day basis throughout the construction season.

(2) Other. At least 500 ft2 of work space, exclusiveof office space, should be provided for moderate sizeprojects.

c. Equipment.

(1) Large-volume mass concrete project. Storagetanks with a capacity of 300 cylinders and a 200,000-lbfcompression testing machine, complying with requirementsof ASTM C 39 (CRD-C 14), should be provided. Newmachines being purchased and older machines, returned tothe manufacturer for repair, should be required to complywith the 1-percent accuracy requirement. Older machines,which are not under manufacturer’s warranty and arepresently in use, should be required to comply with a ± 3-percent accuracy requirement. Aggregate testing equipmentshould include that equipment necessary to perform tests forabsorption, density, surface moisture, and sieve analysis.Heavy-duty laboratory screening equipment, such as theGilson for coarse aggregate and the Ro-Tap for fine

9-9

Page 89: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

aggregate, should be provided. Concrete testing equipmentincludes that equipment necessary for determining aircontent and slump and for molding test specimens. Thelaboratory should not include a concrete mixer.

(2) Other. Moderate size projects should include acuring tank with a capacity of 100 cylinders. If acompression testing machine is not available, cylinders may

be shipped to either a division laboratory or large-volumeproject for testing. Aggregate and concrete testingequipment should be the same as for a large project. Thelaboratory facilities for a small project should be limited toequipment for measuring air content and slump and formolding test specimens. Curing of test cylinders andtransportation to the laboratory for testing must be in strictaccordance with ASTM C 31 (CRD-C 11).

9-10

Page 90: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 10Special Concretes

10-1. General

For purposes of this manual, special concretes areconsidered to be those which contain materials that are notroutinely used in conventional structural or mass concrete,those which are not proportioned using procedures given inCRD-C 99, or those which are placed with equipment or bymethods which require additional attention be given by theContracting Officer to assure the required quality isachieved. Those special concretes for which detailedguidance is given in other Corps publications are notdiscussed in this chapter.

10-2. Preplaced-Aggregate Concrete

a. General. Preplaced-aggregate (PA) concrete isproduced by placing coarse aggregate in a form and laterinjecting a portland-cement-sand fly ash grout, usually withchemical admixtures, to fill the voids. The smaller-sizecoarse aggregate is not used in the mixture to facilitate groutinjection. It is primarily applicable to the repair of existingconcrete structures. PA concrete may be particularlysuitable for underwater construction, placement in areas withclosely spaced reinforcing steel and cavities where overheadcontact is necessary, and in areas where low volume changeis required. It differs from conventional concrete in that itcontains a higher percentage of coarse aggregate since thecoarse aggregate is placed directly into the forms with point-to-point contact rather than being contained in a flowableplastic mixture. Therefore, hardened PA concrete propertiesare more dependent on the coarse aggregate properties.Drying shrinkage of PA concrete may be less than one-halfthat of conventional concrete, which partially accounts forthe excellent bond between PA concrete and existingroughened concrete. The compressive strength of PAconcrete is dependent on the quality, proportioning, andhandling of materials but is generally comparable to thatachieved with conventional concrete. The frost resistance ofPA concrete is also comparable to conventional air-entrainedconcrete assuming the grout mixture has an air content, asdetermined by ASTM C 231 (CRD-C 41) of approximately9 percent. PA concrete may be particularly applicable tounderwater repair of old structures and underwater newconstruction where dewatering may be difficult, expensive,or impractical. Bridge piers and abutments are typical ofapplications for underwater PA concrete construction orrepair. A detailed discussion of PA concrete is provided inACI 304.R.

b. Applications. PA concrete has been used ondifferent types of civil works construction including:

(1) Resurfacing of lock chamber walls.

(2) Underwater repair to lock guide walls.

(3) Resurfacing of spillways.

(4) Construction of plugs to close temporary sluicesthrough a dam.

(5) Filling of temporary fish ladders through a dam.

(6) Scroll case embedment.

c. Materials and proportioning. Intrusion groutmixtures should be proportioned in accordance withASTM C 938 (CRD-C 615) to obtain the specifiedconsistency, air content, and compressive strength. Thegrout mixture should also be proportioned such that themaximum w/c complies with those given in Table 4-1.Compressive strength specimens should be made inaccordance with ASTM C 943 (CRD-C 84). Compressivestrength testing of the grout alone should not be done toestimate the PA concrete strength because it does not revealthe weakening effect of bleeding. However, such testingmay provide useful information on the potential suitabilityof grout mixtures. The ratio of cementitious material to fineaggregate will usually range from about 1 for structural PAconcrete to 0.67 for mass PA concrete. A grout fluidifiermeeting the requirements of ASTM C 937 (CRD-C 619) iscommonly used in the intrusion grout mixtures to offsetbleeding, to reduce the w/c and still provide a givenconsistency, and to retard stiffening so that handling timescan be extended. Grout fluidifiers typically contain a water-reducing admixture, a suspending agent, aluminum powder,and a chemical buffer to assure timed reaction of thealuminum powder with the alkalies in the portland cement.Products proposed for use as fluidifiers which have norecord of successful prior use in PA concrete may beaccepted contingent on successful field use. ASTM C 937requires that intrusion grout made as prescribed foracceptance testing of fluidifiers have an expansion withincertain specified limits which may be dependent on thealkali content of the cement used in the test. Experiencehas shown, however, that because of the difference inmixing time and other factors, expansion of the field-mixedgrout ordinarily will range from 3 to 5 percent. If, underfield conditions, expansion of less than 2 percent or morethan 6 percent occurs, adjustments to the fluidifier should bemade to bring the expansion within these limits. Thefluidifier should be tested under field conditions with job

10-1

Page 91: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

materials and equipment as soon as practicable so thatsufficient time is available to make adjustments in thefluidifier if necessary. If the aggregates are potentiallyalkali reactive, the total alkali content of the portland cementplus fluidifier added to increase expansion should notexceed 0.60 percent, calculated as equivalent sodium oxideby mass of cement. The grout submitted for use mayexhibit excess bleeding if its cementitious material to fineaggregate ratio is different than that of the grout mixtureused to evaluate the fluidifier. Expansion of the groutmixture should exceed bleeding at the expected in-placetemperatures. Grout should be placed in an environmentwhere the temperature will rise above 40 °F, sinceexpansion caused by the fluidifier ceases at temperaturesbelow 40 °F. This condition is normally readily obtainablewhen PA concrete is placed in massive sections orplacements are enclosed by timber forms. If an air-entraining admixture is used in the PA concrete, adjustmentsin the grout mixture proportions may be necessary tocompensate for a significant strength reduction caused bythe combined effects of entrained air and the hydrogengenerated by the aluminum powder in the fluidifier.However, these adjustments must not reduce the air contentof the mixture to a level that compromises its frostresistance. The largest practical NMSA should be used toincrease the economy of the PA concrete. A 37.5-mm (1-1/2-in.) NMSA will typically be used in much of the PAconcrete; however, provisions are made for the use of75-mm (3-in.) NMSA when it is considered appropriate. Itis not expected that many situations will arise where the useof aggregate larger than 50 mm (2 in.) will be practical.Pozzolan is usually specified to increase flowability of thegrout.

d. Preplacing aggregate. Care is necessary inpreplacing the coarse aggregate if excessive breakage andobjectionable segregation are to be avoided. The difficultiesare magnified as the nominal maximum size of theaggregate increases, particularly when two or more sizes areblended. Therefore, the Contractor’s proposed methods ofplacing aggregate should be carefully reviewed to ensurethat satisfactory results will be obtained. Coarse aggregatemust be washed, screened, and saturated immediately priorto placement to remove dust and dirt, and to eliminatecoatings and undersize particles. Washing in forms shouldnever be permitted because fines may accumulate at thebottom.

e. Contaminated water. Contaminated water is amatter of concern when PA concrete is placed underwater.Contaminants present in the water may coat the aggregateand adversely affect the setting of the cement or the bondingof the mortar to the coarse aggregate. If contaminants in

the water are suspected, the water should be tested beforeconstruction is permitted. If contaminants are present insuch quantity or of such character that the harmful effectscannot be eliminated or controlled, or if the constructionschedule imposes a long delay between aggregate placementand grout injection, PA concrete should not be used.

f. Preparation of underwater foundations.Difficultyhas been experienced in the past with cleanup offoundations in underwater construction when the foundationmaterial was glacial till or similar material. The difficultydevelops when as a result of prior operations, an appreciablequantity of loose, fine material is left on the foundation orin heavy suspension just above the foundation. The finematerial is displaced upward into the aggregate as it is beingplaced. The dispersed fine material coats the aggregate orsettles and becomes concentrated in the void spaces in theaggregate just above the foundation thus precluding properintrusion and bond. Care must, therefore, be exercised toensure that all loose, fine material is removed insofar aspossible before placement of aggregate is allowed tocommence.

g. Pumping.Pumping of grout should be continuousinsofar as practical; however, minor stoppages arepermissible and ordinarily will not present any difficultieswhen proper precautions are taken to avoid plugging ofgrout lines. The rate of pumping should be regulated by useof sounding wells so that the preplaced aggregate is slowlyintruded to allow complete and uniform filling of all voids.The rate of grout rise within the aggregate should becontrolled to eliminate cascading of grout and to avoid formpressures greater than those for which the forms weredesigned. For a particular application, the grout injectionrate will depend on form configuration, aggregate grading,and grout fluidity.

h. Joint construction.A cold joint is formed in PAconcrete when pumping is stopped for longer than the timeit takes for the grout to harden. When delays in groutingoccur, the insert pipes should be pulled just above the groutsurface before the grout stiffens, and then rodded clear.When pumping is ready to resume, the pipes should beworked back to near contact with the hardened grout surfaceand then pumping resumed slowly for a few minutes.Construction joints are formed in a similar manner bystopping grout rise approximately 12 in. below the aggregatesurface. Care must be taken to prevent dirt and debris fromcollecting on the aggregate surface or filtering down to thegrout surface. If construction joints are made by bringingthe grout to the surface of the coarse aggregate, the jointsurfaces should be cleaned and prepared as discussed inparagraph 7-6 d of this manual.

10-2

Page 92: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

i. Grouting procedure. The two patterns for groutinjection are the horizontal layer and the advancing slope.Regardless of the system used, grouting should start fromthe lowest point in the form.

(1) Horizontal layer. In this method grout is injectedthrough an insert pipe to raise the grout until it flows fromthe next insert hole 3 to 4 ft above the point of injection.Grout is then injected into the next horizontally adjacenthole, 4 or 5 ft away, and the procedure is repeatedsequentially around the member until a layer of coarseaggregate is grouted. Successive layers of aggregate aregrouted until all aggregate in the form has been grouted.

(2) Advancing slope. The horizontal layer method isnot practical for construction of such slabs when thehorizontal dimensions are large. In situations such as this,it becomes necessary to use an advancing slope method ofinjecting grout. In this method, intrusion is started at oneend of the form and pumping continued until the groutemerges on the top of the aggregate for the full width of theform and assumes a slope which is advanced and maintainedby pumping through successive rows of intrusion pipes untilthe entire mass is grouted. In advancing the slope, thepumping pattern is started first in the row of holes nearestthe toe of the slope and continued row by row up the slope(opposite to the direction of advance of slope) to the lastrow of pipes where grouting has not been completed. Thisprocess is repeated, moving ahead one row of pipes at atime as intrusion is completed.

(3) Grout insert pipes and sounding devices. Thenumber required and the location and arrangement of groutinsert pipes will depend on the size and shape of the workbeing constructed. For most work, grout insert pipes willconsist of pipes arranged vertically and at variousinclinations to suit the configurations of the work. Theguide specification provides for the option of the diameterof the grout insert pipes being either 3/4, 1, or 1-1/2 in.Generally, either a diameter of 3/4 or 1 in. would beallowed for structural concrete having a maximum sizeaggregate of 37.5 mm (1-1/2 in.) or less. If the preplacedaggregate has a maximum size larger than 37.5 mm(1-1/2 in.), the grout insert pipes should be 1-1/2 in. indiameter. Intrusion points should be spaced about 6 ftapart; however, spacing wider than 6 ft may be permissibleunder some circumstances, and spacings closer than 6 ft willbe necessary in some situations. Normally, one soundingdevice should be provided for each four intrusion points;however, fewer sounding devices may be permissible undersome circumstances. In any event, there should be enoughsounding devices, and they should be arranged so that thelevel of the grout at all locations can be accurately

determined at all times during construction. Accurateknowledge of the grout level is essential to:

(a) Check the rate of intrusion.

(b) Avoid getting the grout too close to the level ofthe top of the aggregate when placement of the aggregateand intrusion are progressing simultaneously.

(c) Avoid damage to the work which would occur ifa plugged intrusion line were washed out while the end ofthe line was within the grout zone.

Sounding devices usually consist of wells (slotted pipes)through which the level of the grout may be readily andaccurately determined. If sounding devices other than wellsare proposed, approval should be based on conclusivedemonstration that such devices will readily and accuratelyindicate the level of the grout at all times. In repairingvertical surfaces, such as lock chamber walls or slopingsurfaces which are substantial distances and are relativelythin (up to about 2 ft thick), the grout is brought upuniformly from the bottom. Intrusion points for such workshould be arranged in horizontal rows with the rows spacednot more than 4 ft apart horizontally. Holes in adjacenthorizontal rows should be staggered so that a hole in anyrow is at the midpoint of the space between holes in theadjacent rows above and below. Intrusion is controlled bypumping through all holes in each horizontal row until groutflows from all holes in the row above. Grouting thenproceeds through the next row above after the holes below,which have just been grouted are plugged. The process isrepeated until a section is completed. The bottom row ofholes should be placed at the bottom of the form.

j. Finishing unformed surfaces. If a screeded ortroweled finish is required, the grout should be brought upto flood the aggregate surface and any diluted grout shouldbe removed. A thin layer of pea gravel or 3/8- to 1/2-inchcrushed stone should then be worked into the surface byraking and tamping. After the surface has stiffenedsufficiently, it may be finished as required. A finishedsurface may also be obtained on PA concrete by adding abonded layer of conventional concrete of the prescribedthickness to the PA concrete surface. The PA concretesurface should be cleaned and grouted prior to receiving thetopping.

10-3. Underwater Concrete

a. General. For underwater concrete placements tobe successful, careful planning and execution are essential.The location and size of the area to be concreted should be

10-3

Page 93: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

well defined and thoroughly cleaned so that it is free ofmud, silt, and debris. The extent of the cleaning effort willbe determined largely by whether the concrete is beingplaced into a new structure or being used to repair anexisting structure. All marine growth, sediment, debris, anddeteriorated concrete must be removed prior to placing newconcrete. Waterjets and self-propelled vehicles have beeneffective in most cleaning applications. Airlifts should beused to remove sediment and debris from depths of 25 to75 ft. If the concrete is being used to repair an existingstructure, an appropriate number of anchors should begrouted into the existing concrete to tie the new concrete tothe existing concrete. The concrete must be protected fromthe water until it is in place so that the cement fines cannotwash away from the aggregate. This protection can beachieved through the proper use of placing equipment, suchas tremies and pumps. The velocity of the waterimmediately adjacent to the placement should not exceed5 ft/sec. The quality of the in-place concrete can beenhanced by the addition of an AWA which increases thecohesiveness of the concrete. Concrete mixtures to beplaced underwater must be highly workable and cohesive.The degree of workability and cohesiveness can varysomewhat depending upon the type of placing equipmentused and the physical dimensions of the area to be filledwith concrete. A dense, homogeneous mass of concretehaving hardened properties equivalent to those of concreteplaced in the dry should be the result of a good underwaterconcrete operation.

b. Tremie concrete. A massive and confinedplacement, such as a cofferdam or a bridge pier, could becompleted with a conventional tremie concrete mixture. Thedesired workability can normally be produced by using 19.0-or 37.5-mm (3/4- or 1-1/2-in.) NMSA and a w/c notexceeding 0.45. An increase in fine aggregate content ofapproximately 6 percent, as compared to a conventionalconcrete mixture, may be necessary. Rounded aggregatesare preferred over crushed aggregates for both coarse andfine sizes. Listed below is a typical mixture for aconventional tremie mixture:

Portland cement 600 lb/cu ydFly ash 100 lb/cu yd19.0-mm (3/4-in.) NMS natural gravelNatural sandSand-aggregate ratio = 0.45w/c = 0.45WRAAir content = 6 %Slump = 6 to 8 in.

Mixtures of this type must be fully protected from exposureto water until in place. Whether being placed by tremie orpump, it is mandatory that the seal be maintained. Onceconcreting is underway, the bottom of the pipe should bekept buried in the concrete about 5 ft below the surface ofthe concrete. AWA’s can be used in these mixtures but arenot necessary, although their use should enhance the freshproperties of the concrete. Spacing of tremie pipes shouldnot exceed 15 ft. A more complete discussion of tremieconcreting practices is given in ACI 304R.

c. Pumped concrete for use underwater.Many repairsituations require that the concrete flow laterally in thin liftsfor a substantial distance. This exposes the concrete tomuch water while being placed. For this type of placement,an AWA should be used to enhance the cohesiveness of theconcrete. The cohesiveness and flowability required cannotnormally be obtained without use of an AWA. Water-reducing or HRWRA’s are usually necessary as well. Trialbatches must be made to ensure compatibility betweenAWA’s, WRA’s, and HRWR’As. The desired workabilitycan normally be produced with rounded aggregates of19.0-mm (3/4-in.) NMS or smaller and a w/c not exceeding0.45. An increase of approximately 6 percent in fineaggregate content, as compared to a conventional concretemixture, may be necessary. When a repaired area will besubjected to abrasion-erosion, silica fume should beconsidered to enhance the hardened properties of theconcrete. Silica fume will also increase the cohesiveness ofthe fresh concrete mixture. Listed below is a typicalmixture for proportioning an underwater concrete mixturefor use in repairing an existing structure:

Portland cement 600 lb/cu ydFly ash 30 lb/cu ydSilica fume 40 lb/cu yd19.0-mm (3/4-in.) NMS or smaller natural gravelNatural sandSand-aggregate ratio = 0.45w/c = 0.40AWAWRA or HRWRAAir content = 6 %Slump = 8 to 10 in.

Pumping is the preferred method of placement, althoughtremies may be used on some repair jobs. Pumpingdistances should be kept to a minimum. If the pumpingdistance exceeds 250 ft, pumping pressures will likelyincrease significantly due to the increased cohesivenessimparted by the AWA. Excessive pumping pressures will

10-4

Page 94: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

necessitate relocating the pump, using staged pumps toshorten the pumping distance, or modifying the concretemixture or reducing the amount of AWA’s. Someadjustments may reduce the cohesiveness of the concrete,making it more susceptible to washout. If the pumpingdistance is 150 ft or less, the cohesiveness imparted by anAWA actually improves the pumpability of concrete. WhenAWA’s are used, it is not as critical to keep the dischargeend of the tremie or the pump line embedded in the concreteas it is when they are not used. However, the concreteshould not be unnecessarily exposed to water duringplacement. Once in place, concretes of this type can flowup to 30 ft without harmful washout or segregation.Pumped concrete is discussed in detail in paragraph 10-6 ofthis manual. Additional information on pumped concrete foruse under water is given in WES Technical ReportREMR-CS-18 (Neeley 1988) and EM 1110-2-2002,"Evaluation and Repair of Concrete Structures."

10-4. Blockout Concrete

a. General. The use of blockouts in concretemembers is often necessary to embed seats, guides, rails,piping, and electrical and mechanical systems into concreteplacements. Prior to placement of blockout concrete, theblockout or recess should be carefully inspected to assure allsurfaces are thoroughly cleaned of all loose material, oil,grease, and other material which might reduce or destroybond between surfaces of the blockout or recess and thenew concrete. Care should also be exercised in assuringthat blockout concrete is properly consolidated, particularlyin those blockouts or recesses which are heavily congestedwith a combination of embedments and reinforcing steel.

b. Blockout concrete proportions.Blockout concreteis normally proportioned to meet the same strength criteriaas adjacent concrete. The NMSA is usually 19.0 mm(3/4 in.). Bonding of the blockout concrete to the adjacentformed concrete surfaces is most important. These surfacesmust be cleaned of any laitance and any oil, grease, orforeign matter. Cleanup of these surfaces should be thesame as for any other surface to which concrete is to bebonded, although sandblasting or high-pressure water jetblasting is not usually necessary for block outs on verticalsurfaces. The fluidifying-expanding agent should be used insuch proportion that the paste portion of the blockoutconcrete, when tested separately, will have an expansion of2 to 4 percent when tested in accordance with ASTM C940. An expansive admixture conforming to ASTM C 937(CRD-C 619) should be specified for all vertical blockoutsand any other blockouts which are formed or otherwiseconfined on all sides. Where the blockout is on a horizontalsurface and the top of the blockout concrete is to be hand

finished, the expansive admixture should not be used. Anepoxy bonding compound meeting ASTM C 881, Type V(CRD-C 595), has been successfully used for bonding ofblockout concrete to adjacent concrete although timing canbe critical. The new concrete must be placed while theepoxy is still tacky and before it hardens.

10-5. High-Strength Concrete

a. General. High-strength concrete has seenincreasing use in recent years as compressive strengthrequirements have increased and new applications have beendeveloped. Early applications emphasized its use to reducecolumn dimensions. It has now been used to meet specialproject objectives such as in large composite columns,stiffer structures, bridges, stilling basins, and structuressubject to chemical attack. The increased use of high-strength concrete has, in turn, prompted the application ofmore stringent quality control requirements. A thoroughdiscussion of high-strength concrete is given in ACI 363R.

b. Definition. The definition of high-strength concreteis concrete having a 28-day design compressive strengthover 6,000 psi (41 MPa) (ACI 116R). In regions whereconcretes having strengths up to 5,000 psi are readilyavailable, 9,000 psi might be considered to be high-strengthconcrete. However, in regions where concrete having acompressive strength of 9,000 psi is readily available,12,000 psi might be considered to be high-strength concrete.In many instances, the required compressive strength isspecified at 56- or 90-days age rather than 28-days age totake better advantage of pozzolans in the concrete.

c. Materials. When high-strength concrete is to beused, all materials must be carefully selected. Items to beconsidered in selecting materials include cementcharacteristics, aggregate size, strength, shape, and texture,and the effects of chemical admixtures and pozzolans.High-strength concretes are typically proportioned with highcement contents, low w/c, normal weight aggregate,chemical admixtures, and pozzolans. Trial mixtures areessential to ensure that required concrete properties will beobtained.

d. Cement type.The choice of portland cement isvery important. Type I cement is appropriate for use inmost high-strength concrete. If high initial strength isrequired, such as in prestressed concrete, Type III cementmay be more appropriate. However, the high cementcontents associated with high-strength concretes will causea high temperature rise within the concrete. If the heatevolution is expected to be a problem, a Type II moderate-heat-of-hydration cement can be used, provided it meets the

10-5

Page 95: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

strength-producing requirements. However, even within agiven type of cement, such as Type I, II, or III, differentbrands can have different strength developmentcharacteristics because of the variations in their physical andchemical compositions.

e. Cement content.Cement contents typically rangefrom 660 to 940 lb/yd3. However, higher strengths do notalways accompany higher cement contents. The concretestrength for any given cement content will vary with thewater demand of the mixture and the strength-producingcharacteristics of the cement being used. The optimumcement content will depend upon the combinations of allmaterials being used and is best determined by trial batches.

f. Aggregates.The choice of aggregates is veryimportant to the ultimate strength that a high-strengthconcrete will develop since they occupy the largest volumeof any of the constituents in the concrete. Most high-strength concrete has been produced using normal weightaggregates. Some high-strength lightweight aggregates andheavyweight aggregates have also been used successfully inhigh-strength concretes. In general, crushed coarseaggregates, 19.0-mm (3/4-in.) nominal maximum size orsmaller, are preferred for high-strength concretes becausetheir shape and surface texture enable the cement paste tobond to them better than rounded natural aggregates.Smaller size aggregates have better bond strengths and lesssevere stress concentrations around the particles. The idealaggregate should be clean, cubical, angular, 100-percentcrushed aggregate with a minimum of flat and elongatedparticles. The volume of coarse aggregate can usually beincreased up to 4 percent from that recommended inACI 211.1 for conventional concretes. Natural fineaggregates are preferred because they require less mixingwater and provide better workability. Since the concrete hasa high cement content, sands having a high finenessmodulus (about 3.0) usually give better workability andstrength. Sands having fineness moduli of 2.5 and belowusually increase the water demand and give the concrete asticky consistency, making it more difficult to place.

g. Pozzolans.Pozzolans in quantities ranging from 15to 40 percent by mass of cement are frequently used tosupplement the portland cement in high-strength concrete.Silica fume is generally used in amounts ranging from 5 to10 percent by mass of cement. The volume increase incementitious materials resulting from the addition of apozzolan is usually offset largely by a decrease in the fineaggregate content. Depending on the type of pozzolan used,the water demand of the concrete mixture may be increasedor decreased. When silica fume is used, the water demandwill be increased and make the use of an HRWRA

necessary. See paragraph 10-10 of this manual for moreinformation on silica-fume concrete.

h. Use of HRWRA.HRWRA’s are frequently used inhigh-strength concrete to lower the w/c. They can also beused to increase the workability of the concrete. In somecases, an HRWRA may be used in combination with aconventional WRA or a retarding admixture to reduce slumploss. Depending on the specified w/c, the requiredworkability, and the materials being used, a conventionalWRA used at a high dosage may provide the necessarywater reduction. Larger-than-normal dosages of air-entraining admixtures are usually required to entrain air inhigh-strength concretes due to the high cement contents.

i. Workability. Due to their cohesiveness, high-strength concretes can be more difficult to place thanconventional concretes. The mixture should be easy tovibrate and mobile enough to pass through closely spacedreinforcement. A slump of about 4 in. will usually providethe required workability. However, all structural detailsshould be considered prior to specifying the fresh propertiesof the concrete mixtures. Also, the rapid slump lossexhibited by many high-strength concretes should beconsidered. Slumps of less than 3 in. have been difficult toplace without special equipment and procedures.

j. Proportioning. More laboratory trial batches maybe necessary to properly proportion a high-strength concretemixture than would be required to proportion a conventionalconcrete mixture. Once a mixture has been proportioned inthe laboratory, field testing with production-size batches isrecommended. Frequently, the strength level that can bereasonably achieved in the field will be lower than thatattained in the laboratory batches. The water demand mayalso vary from that determined in the laboratory.Production and quality control procedures can be evaluatedmore effectively when production-size batches are producedusing the equipment and personnel that will be doing theactual work.

k. Material handling. The control, handling, andstorage of materials need not be significantly different fromthe procedures used for conventional concrete. However,some emphasis on critical points is prudent. Thetemperature of all ingredients should be kept as low aspossible prior to batching. It may be necessary to makeprovisions to lower the initial temperature of the concrete byusing chilled water, ice, or liquid nitrogen. Delivery timeshould be reduced to a minimum and special attention givento scheduling and placing to avoid having trucks waiting tounload. Where possible, the batching facilities should belocated at or near the job site to reduce haul time. Extended

10-6

Page 96: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

haul times can result in a significant increase in temperatureand loss of slump and should be avoided.

l. Preparation for placing. Preparation for placinghigh-strength concrete should include recognition thatcertain unusual conditions will exist before any placementbegins. Since the effective working time of the concrete isexpected to be reduced, preparation must be made totransport, place, consolidate, and finish the concrete asquickly as possible. Proper planning, skilled workmen,adequate equipment, and stand-by equipment are allessential to a successful high-strength concrete placement.

m. Curing. Proper curing is critical to the productionof high-strength concrete. The potential strength anddurability of any concrete, especially high-strength concrete,will be fully developed only if it is properly cured for anadequate period prior to being placed in service. Watercuring of high-strength concrete, especially at early ages, isrequired because of the low w/c’s. If the w/c is below 0.40,the degree of hydration will be significantly reduced if freewater is not provided during curing. Water curing willallow maximum hydration of the cement.

n. Testing. Since much of the interest in high-strengthconcrete is limited primarily to compressive strength, thesemeasurements are of primary concern in the testing of high-strength concretes. Careful attention should be given to alldetails of the test methods being used while fabricating,curing, and testing compressive strength specimens.Standard specimens are 6-in.-diameter by 12-in.-highcylinders; however, 4-in.-diameter by 8-in.-high cylindricalspecimens have also been used to determine the compressivestrength of high-strength concretes. The 4-in.-diameter by8-in.-high specimens usually exhibit somewhat highercompressive strengths and more variability than the standardsize specimens. Even so, proper testing procedures and asuitably accurate and stiff testing machine are more criticalto attaining good results than is the specimen size. High-strength sulfur mortar may be used to cap specimens havingcompressive strengths up to 10,000 psi. Specimensexpected to have compressive strengths above 10,000 psishould have their ends formed or ground to the requiredtolerance. A caution should be added that these higher-strength concretes require a corresponding larger capacitycompression testing machine.

10-6. Pumped Concrete

a. General. Pumped concrete can be used for moststructural concrete construction but is most useful wherespace for construction equipment is limited or access isdifficult. Concrete pumps can be either truck- or trailer-

mounted and range from small units, exerting pressuresfrom 250 to 300 psi and outputs of 15 to 30 yd3/hr, to largeunits, exerting pressures of 1,000 psi and outputs up to 150yd3. The effective capacity of a pump depends not only onthe pump itself but also on the complete system. Severalfactors including line length, number of bends in the line,type of line, size of line, height to which the concrete isbeing pumped, and the concrete mixture affect the effectiveworking capacity of a concrete pump. An excellentreference is ACI 304.2R.

b. Pump lines.Pump lines are usually a combinationof rigid pipe and heavy-duty flexible hose. Acceptable rigidpipe can be made of steel or plastic and is available in sizesfrom 3 to 8 in. in diameter. Aluminum alloy pipe shouldnot be used as pump line. Flexible hose is made of rubber,spiral wound flexible metal, and plastics. It is useful incurves, difficult placement areas, and as connections tomoving cranes but exhibits greater line resistance to themovement of concrete than rigid pipe and may have atendency to kink. To obtain the least line resistance, thepipeline should be made up primarily of rigid pipe withflexible hose only where necessary. If possible, the pipelineshould be of one size and laid out so as to contain aminimum number of bends.

c. Mixture proportions. Concrete mixture proportionsof pumpable mixtures are essentially the same as those to beplaced by other methods, except that more emphasis shouldbe placed on the grading of the fine aggregates. Concreteswhich are pumped must be cohesive. Harsh mixtures do notpump well. Pressure exerted by the pump can force themortar away from the coarse aggregate causing a blockagein the line if the mixture is not proportioned properly. Thecement content will generally be somewhat higher forpumped mixtures than those of mixtures placed byconventional methods. The higher fine aggregate contentwill have a higher water demand, which in turn will requirea higher cement content. However, extra cement should notbe used to correct pumping deficiencies resulting frompoorly graded aggregates. It is usually more preferable tocorrect deficiencies in the fine aggregates by blending inadditional fine aggregates or pozzolan than by addingcement.

d. Coarse aggregates.The nominal maximum size ofthe coarse aggregate is limited to one-third of the smallestinside diameter of the pump line for crushed aggregates or40 percent of the smallest inside diameter of the pump linefor well-rounded aggregates. Oversize particles should beeliminated. A higher mortar content will be necessary toeffectively pump a concrete containing crushed aggregatesthan for a concrete containing rounded aggregates.

10-7

Page 97: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Depending upon the type and size of the coarse aggregate,it may be necessary to reduce the coarse aggregate contentfrom 5 to 10 percent as compared to mixtures placed byconventional methods.

e. Fine aggregate.The properties of fine aggregatesare more critical in proportioning pumpable mixtures thanare the properties of the coarse aggregates. Together withthe cement and water, the fine aggregates constitute themortar which conveys the coarse aggregates in suspensionthrough the pump line. Fine aggregates should conform tothe requirements given in ASTM C 33 (CRD-C 133) forfine aggregates. In addition, for pump systems having lines6-in. in diameter and smaller, 15 to 30 percent of fineaggregate should pass the 300-µm (No. 50) sieve and 5 to10 percent should pass the 150-µm (No. 100) sieve. Fineaggregates that are deficient in either of these two sizesshould be blended with selected finer aggregates to producethe desired grading. Pumpability of concrete is generallyimproved with a decrease in the fineness modulus. Fineaggregates having a fineness modulus between 2.40 and3.00 are generally satisfactory provided that the percentagespassing the 300- and 150-µm (No. 50 and No. 100) sievesmeet the previously stated guidelines. Fineness modulusvalues alone without stipulations on the finer sizes may notproduce satisfactory results. Both manufactured fineaggregates and natural sands can be used in pumpedmixtures provided their gradings are appropriate; however,natural sands are preferred due to their rounded shape.

f. Slump. The water requirements to establish theoptimum slump and to maintain control of that slumpthroughout the course of a pumping placement are bothextremely important factors. Concretes having slumps lessthan 2 in. when delivered to the pump are difficult to pump.Concretes having slumps over 6 in. can segregate causing ablockage in the pump line and may require a pump aid toincrease the cohesiveness of the concrete to prevent theaggregate from separating from the mortar during pumping.It is much more important to obtain a cohesive concretethrough proper proportioning than to try to overcomedeficiencies by adding extra water. In fact, the use ofexcess water creates more problems than it solves.

g. Admixtures.Materials which improve workability,such as water-reducing, high-range water-reducing, and air-entraining admixtures, as well as pozzolans, usually improvepumpability. It is common to experience a decrease in aircontent during pumping. The specified air contents requiredfor durability should be obtained at the point of placementin the structure. Therefore, it may be necessary to entraina higher air content into the concrete mixture prior topumping. Pumping aids are admixtures which can reduce

friction, reduce bleeding, and increase cohesiveness, all ofwhich make concretes pump easier.

h. Pumpability tests.There is no standard laboratorytest method available to accurately test the pumpability ofa concrete mixture. Testing a concrete mixture forpumpability involves duplicating anticipated job conditionsfrom beginning to end. A full-scale field test forpumpability should be considered to evaluate both themixture proportions and pumping equipment. Prior use ofa mixture and pumping equipment on another job mayfurnish evidence of pumpability if job conditions areduplicated.

i. Planning. Proper planning of the entire pumpingoperation including pump location, line layout, placingsequence, and concrete supply will result in savings of timeand expense. The pump should be as near the placementarea as possible. Concrete delivery systems should haveeasy access to the pump. Lines from the pump to theplacement area should be made up primarily of rigid pipeand contain a minimum number of bends. For largeplacement areas, alternate lines should be laid for rapidconnection when required, and standby power and pumpingequipment should be readily available to replace an initialpiece of equipment should a breakdown occur.

j. Other requirements.When pumping downward 50ft or more, an air release valve at the middle of the top bendwill prevent vacuum or air buildup. When pumpingupward, a shutoff valve near the pump will prevent thereverse flow of concrete during the fitting of cleanupequipment or when working on the pump. Directcommunication should be maintained between the placingcrew and the pump operator. Good communication betweenthe pump operator and the concrete batch plant is alsoimportant. It is desirable to have the concrete delivery suchthat the pumping can proceed continuously. When a delayoccurs, it may be difficult to start the concrete moving inthe line again, especially if the delay has been for aconsiderable length of time. This critical delay time willdepend upon such factors as the concrete mixture,temperature, length of pipeline, and type of pump. It maybe necessary to clean the line and start again if the delaybecomes extended. A grout or mortar should be used tolubricate the pipeline anytime pumping is started with cleanlines, but it should not be pumped into the forms.

k. Quality verification.A high level of quality controlmust be maintained to provide assurance that the concreteis of the desired quality. Concrete should be sampled atboth ends of the pumpline to determine what, if any,changes in the slump, air content, and other concrete

10-8

Page 98: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

properties occur during pumping. However, the quality ofthe concrete being placed in the structure can only bemeasured at the placement end of the pumpline.

10-7. Fiber-Reinforced Concrete

a. General. Fiber-reinforced concrete (FRC) isconcrete which contains dispersed, randomly oriented fibers.Fiber-reinforced concrete and fiber-reinforced shotcrete havebeen used for pavements, overlays, patching, floor slabs,refractory materials, hydraulic structures, thin shells, armorfor jetties, rock slope stabilization, tunnel linings, andprecast units since the mid 1960’s. Fibers have beenproduced from steel, plastic, glass, and natural materials invarious shapes and sizes. ASTM A 820 (CRD-C 539) is thespecification which covers minimum standards for steelfibers intended for use in fiber-reinforced concrete. Thesize of fibers are usually described by their aspect ratio,which is the fiber length divided by an equivalent fiberdiameter. Aspect ratios typically range from about 30 to150. Some steel fibers are collated with water-soluble glueinto bundles of 10 to 30 fibers to facilitate handling andmixing. Uniform dispersion of fibers through the concreteprovides isotropic strength properties not common toconventionally reinforced concrete. Additional informationon steel FRC may be found in ACI 544.1R, ACI 544.2R,ACI 544.3R, and ACI 544.4R.

b. Advantages and limitations.Steel fibers increasethe first crack flexural strength, direct tensile strength, andsplitting tensile strength. Compressive strengths may exhibita minor increase. Fibers can increase the ductility ofconcrete substantially depending on the type and amount offiber present in the concrete. However, balling of fibers inthe mixer hinders uniform distribution and reducesworkability. This can impose an upper limit beyond whichbenefits gained from the fibers are no longer realized. Thisupper limit depends upon the type and size of fibers and themixing procedures being used. Because of mixing andplacing considerations, approximately 2 percent by volumeof the total concrete mixture is considered the practicalupper limit for most types of fibers in field placements.Higher percentages could be used when the fibers are a typethat do not interlock significantly. However, fibers withhooked ends can achieve essentially the same properties asstraight fibers of the same aspect ratio using less fiber.

c. Toughness.Steel fibers increase the toughness,which is a measure of the energy absorption capacity ofconcrete. The increase in toughness depends on the type,amount, and aspect ratio of the fibers. In general, crimpedfibers, surface-deformed fibers, and fibers with hooked ends

produce toughness indexes greater than those for smoothstraight fibers at the same volume concentration.

d. Performance characteristics.Steel fiber concretehas shown good resistance to dynamic forces and asignificant increase in fatigue strength. Fatigue strengthtends to increase with an increase in fiber loading, and thecrack width under fatigue loading tends to decrease. Thebenefits that a conventional concrete mixture gains fromsteel fibers depend primarily on the loading of fibers and thesize, shape, and aspect ratio of the fibers. Steel-fiberconcrete has not shown excessive corrosion of the steelfibers when placed in corrosive environments. Thecorrosion has been confined to the fibers actually exposedto the surface. Fiber-reinforced concrete has shown goodresistance to cavitation forces resulting from high-velocitywater flow and to the damage caused by the impact of largewaterborne debris at high velocity. However, FRC exhibitspoor resistance to abrasion that occurs from the grindingaction of rocks and debris carried in low-velocity water.Therefore, FRC shall not be used in areas subject tounderwater abrasion.

e. Mixture proportioning. Fiber-reinforced concretegenerally has higher cement and fine aggregate contents andsmaller NMSA than conventional concrete. Coarseaggregates are generally 19.0-mm (3/4-in.) nominalmaximum size or smaller. Pozzolans are often used toreduce the relatively high cement contents. Chemicaladmixtures are commonly used for air-entrainment, waterreduction, and workability improvement. To ensure uniformmixing, the maximum aspect ratio of round wire and flatstrip fibers should be no greater than 100.Characteristically, an FRC mixture will experience adecrease in workability as the fiber loading increases.Experience suggests w/c between 0.40 and 0.60 andcementitious contents between 500 and 900 lb/yd3 arerequired when steel fibers are used to produce adequatepaste to coat the large surface area of the fibers. Thepercentage of fine aggregate to total aggregate will rangefrom 45 to 60 percent depending on the NMSA andaggregate gradings. Once mixture proportions have beendeveloped, a full-size trial batch should be produced in theplant and mixer to be used for the project prior to the actualplacement of the fiber-reinforced concrete.

f. Batching and mixing.Mixing of FRC can beaccomplished by different methods, depending on the jobrequirements and the facilities that are available. Theultimate goal is to have a uniform dispersion of the fibersand prevent the segregation or balling of the fibers duringmixing. Segregation or balling of the fibers is related to

10-9

Page 99: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

several factors, the most important of which appears to bethe aspect ratio. Other factors such as the fiber loading,coarse aggregate size, aggregate grading, w/c ratio, andmethod of mixing can also influence the fiber distribution.Increases in aspect ratio, fiber loading, coarse aggregatesize, and quantity of coarse aggregate intensify ballingtendencies. Most fiber balling occurs as the fibers areadded to the concrete mixture and can be eliminated bycontrolling the rate of fiber addition or by the use ofcollated fibers. If collated fibers are used, they may bedumped directly into the concrete mixture as the last step.Subsequent mixing action separates and disperses the fibersthroughout the mixture. If loose fibers are used, they mustbe added slowly and uniformly to the mixture in such a wayas to prevent large clumps of fibers from entering themixture. The fibers can be added to the aggregates prior tointroduction of the cement and water or as the last step.The method of introducing the fiber into the mixture shouldbe tried in the field during a trial mixture. Fiber balling thatoccurs after fiber addition can usually be attributed toovermixing or poor mixture proportions, such as too muchcoarse aggregate or a fiber loading that is too high.

g. Placement.A fiber-reinforced concrete mixture willgenerally require more effort to move and consolidate intoforms. The fibrous nature of the mixture makes the use ofshovels or hoes difficult. Forks and rakes are preferred forhandling low-slump mixtures. Properly controlled internalvibration is acceptable, but external vibration of the formsand exposed surface is preferable to prevent fibersegregation. Standard finishing and curing methods can beused with FRC with one exception. If a textured surface isdesired, a burlap drag is not recommended as the fibers canhang up in the burlap. A textured surface can be obtainedby brooming with a stiff brush, but it should be delayed aslong as possible to prevent pulling fibers to the surface.

h. Workability. The inverted slump cone test,described in ASTM C 995 (CRD-C 67), should be used asan indicator of workability of FRC. The advantage of theinverted slump cone test over the slump test is that it takesinto account the mobility of concrete which comes aboutbecause of vibration. Reliance on the slump test oftenresults in the use of excessive amounts of water in anattempt to increase the slump without improvingworkability.

i. Pumping. Fiber-reinforced concrete with fiberloadings up to 1.5 percent by volume of the total mixturehave been pumped using 5- to 6-in.-diam pipelines. SteelFRC can be produced using conventional shotcreteequipment.

j. Other fibers. Glass fibers are subject to chemicalattack by the alkalinity of the concrete, become brittle, andlose their effectiveness over a period of time. Nylon,polypropylene, and polyethylene fibers are not subject tochemical attack. Polypropylene fibers are available inseveral forms, such as smooth monofilaments, fibrillatedmonofilaments, fibrillated mesh, and collated fibrillatedmesh. Properties of polypropylene FRC can vary somewhatdepending upon the type of fiber used. Incorporation ofpolypropylene fibers into concrete can result in a smallimprovement in flexural and tensile strengths; however,these improvements are not always evident. Compressivestrengths can be either increased or decreased. Fracturetoughness can be increased, and shrinkage can be decreased.

k. Effects of polypropylene f ibers onworkability. Polypropylene fibers also affect the rheologicalproperties of fresh concrete. Slump decreases as the volumeconcentration of fibers increases. The slump of a typicalconcrete can decrease by as much as 50 percent with theaddition of 0.10 percent polypropylene fibers. Bleeding canbe significantly reduced in polypropylene FRC.

l. Use of polypropylene fibers.Polypropylene FRC istypically used in nonload-bearing applications particularlywhere impact resistance is important. The use ofpolypropylene fibers for control of cracking in slabs is stillbeing debated due to the amount of fibers required topositively affect the amount of cracking and the subsequenteffect on workability.

10-8. Porous Concrete

a. General. Porous concrete is commonly used whereeither free drainage is required or where lower mass andlower thermal conductivity are required. The use oflightweight aggregates is not practicable or desired. It isnormally produced by binding a gap-graded or a single-sizeaggregate with a cement paste. The structure of the materialpermits the passage of water but also provides moderatestructural strength. Porous concrete has been used for draintiles, drains beneath hydraulic structures to relieve upliftpressures, pavement edge drains, etc.

b. Types. At least three distinct types of porousconcretes can be produced. These include cellular concretesmade by introducing a preformed foam into the fresh mortaror causing the creation of gas bubbles in the mortar due toa chemical reaction; lightweight aggregate concrete madewith natural or synthetic aggregates which are oftenextremely porous; or concrete which uses gap-graded or

10-10

Page 100: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

single-size aggregate and typically totally eliminates the fineaggregate fraction from the mixture (no-fines concrete).While each of these concretes are porous, they possessdiffering void structures. Cellular and lightweight aggregateconcretes may contain large percentages of voids, but thesevoids are relatively noncommunicating. Porous concretesproduced by intentional gap grading or without fineaggregate can result in concrete with high percentages ofinterconnected voids. The porous concretes withnoncommunicating voids may absorb small amounts ofmoisture, but they do not allow rapid passage of waterthrough the concrete. For this reason cellular andlightweight concretes should not normally be considered forthe porous concrete applications previously noted and arenot discussed in further detail.

c. Composition. Porous concrete is composed ofcoarse aggregate, cementitious material, and water.Occasionally, a small amount of fine aggregate can be usedto increase the compressive strength and to reducepercolation. The coarse aggregate should comply withASTM C 33 (CRD-C 133) size designations No. 8 (9.5-mm(3/8-in.) NMSA), No. 7 (12.5-mm (1/2-in.) NMSA), or No.67 (19.0-mm (3/4-in.) NMSA). Both rounded and crushedaggregates have been used to produce porous concrete.

d. W/C considerations.The w/c of a porous concretemixture is important to achieve the specified strength and tohelp create the proper void structure. A high w/c reducesthe cohesion of the paste to the aggregate and causes thepaste to flow downward and blind the void structure whenthe mixture is even lightly compacted. If the w/c is toolow, balling will occur in the mixture, and the materials willnot be evenly distributed throughout the batch. Experienceindicates that the w/c should fall within a range of 0.35 to0.45 for the paste to be stable and provide the bestaggregate coating. The w/c - compressive strengthrelationship which is normally associated with conventionalconcrete does not apply to porous concrete.

e. Durability. The frost resistance of porous concreteis acceptable if the bonding paste is air entrained. However,because of the interconnected void system and high surfacearea of exposed paste in porous concrete, resistance toaggressive attack by sulfates and acids that may percolatethrough this concrete is questionable.

f. Percent voids.The percent voids, expressed as theair content, should be determined in accordance with ASTMC 138 (CRD-C 7). The air content should be 15 percent orgreater, by volume, to ensure that water will percolatethrough porous concrete. The compressive strength ofporous concrete will range from approximately 3,500 psi at

28-days age when the air content is 15 percent toapproximately 1,500 psi when the air content is 25 percent.The percolation rate is proportional to the air content ofporous concrete while the compressive strength is inverselyproportional. The compressive strength also increases as theNMSA decreases.

g. Proportioning porous concrete mixtures.Althoughno ACI guidance for proportioning porous concrete currentlyis available, research conducted by the National AggregatesAssociation-National Ready Mixed Concrete Association(Meininger 1988) indicates that the dry-rodded unit weightof coarse aggregate as determined by ASTM C 29 (CRD-C106) can be effectively used to proportion porous concrete.This approach to proportioning uses the b/bo conceptdiscussed in CRD-C 99 for proportioning normal weightconcrete. The ratio b/bo compares the amount of coarseaggregate in a unit volume of concrete with the amount ofcoarse aggregate in a like volume of dry-rodded coarseaggregate. This method automatically compensates for theeffects of different coarse aggregate particle shape, grading,and density. Also, the b/bo values for a range of NMSAnormally used in porous concrete (9.5 to 19.0 mm (3/8 to3/4 in.)) are very similar.

h. Placement.Proper construction methods are criticalto the performance of porous concrete. Some compactionis needed during placement and the coarse aggregate on thetop surface needs to be properly seated to reduce ravellingof the surface. Small steel wheel rollers have been usedwith some success for compaction. Curing is veryimportant since porous concrete can dry very rapidly.Curing is vital to the continued hydration of the top surface.The level of compaction should be considered in the mixtureproportioning study. If the porous concrete is compactedtoo much, the void content may be reduced below 15percent, and flow channels will be plugged. Too littlecompaction will cause the concrete to have a very high voidcontent and will result in low strength. Test specimensshould be compacted to the same density as will be obtainedin the field. This may require some experimentation in thelaboratory to obtain comparable compaction in the field andthe laboratory.

10-9. Flowing Concrete

a. General. Flowing concrete is defined by ASTM C1017 (CRD-C 88) as "concrete that is characterized ashaving a slump greater than 7-1/2-in. while maintaining acohesive nature." It can be placed to be self-leveling, yetremaining cohesive without segregation, excessive bleeding,or extended retardation. Flowing concrete can be used in

10-11

Page 101: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

congested areas where members are reinforced or unusuallyshaped or in areas of limited access. Flowing concretepumps easily, and therefore, the concrete pumping distanceand rate are increased. Proper consolidation aroundreinforcement is more easily achieved with flowing concretethan normal-slump concrete, and less vibration is required.Proper vibration is necessary for complete consolidation andbond to reinforcing steel.

b. HRWRA. Flowing concrete is produced by theaddition of a normal (Type I) or a retarding (Type II)HRWRA, as described by ASTM C 1017 (CRD-C 88).These admixtures are generally identical to those describedby ASTM C 494 (CRD-C 87) as HRWRA’s, Types F andG, respectively. Flowing concrete cannot be produced bythe addition of water since it will lose the cohesivenessnecessary to minimize segregation. The amount ofHRWRA required to produce flowing concrete variesdepending upon the cement type, w/c, initial slump,temperature, time of addition, concrete mixture proportions,and the type of admixture. Concretes having lower initialslumps generally require larger amounts of HRWRA toproduce flowing concrete than do concretes having higherinitial slumps. HRWRA are also generally more effectivein concrete having higher cementitious material contents.

c. Proportioning flowing concrete. Mixtureproportions for flowing concrete usually contain more finematerial than a conventional concrete mixture. This isnecessary to achieve a flowable consistency withoutexcessive bleeding or segregation. The fine aggregatecontent is usually increased by 3 to 5 percent, and in somecases, an increase in cement or pozzolan may be necessary.Since HRWRA’s are usually added in large volumes, thewater in the admixture must be accounted for in calculatingw/c and yield. Higher dosages of air-entraining admixtureare usually required to maintain proper air content inflowing concrete. The air content should be monitoredregularly at the point of discharge into the forms so that thedosage of air-entraining admixture can be adjusted asnecessary to maintain the air content within the specifiedrange. The slump should be measured prior to addition ofthe HRWRA to assure that an excessive amount of waterhas not been added to the batch. After the HRWRA isadded and thoroughly mixed into the concrete, the resultingslump should be within the specified range.

d. Flowing concrete fresh properties.Flowingconcretes may exhibit a rapid slump loss depending on avariety of factors. Concrete temperature, cementcomposition, and cement content will influence the rate ofslump loss. Also, flowing concrete made with plasticizingadmixtures can lose much of its slump in as few as

30 minutes. Plasticizing admixtures must be measuredaccurately and discharged onto the concrete properlyregardless of where their addition occurs. Additionaldosages of HRWRA can be used when delays occur andslump is lost. Up to two additional dosages have been usedsuccessfully. In general, the compressive strength isunchanged, but the air content is decreased with additionaldosages of HRWRA. The characteristics of flowingconcrete at the time of finishing should be similar to that ofconventional concrete with the same materials. Properlyproportioned flowing concrete should not exhibitobjectionable bleeding. As with the finishing ofconventional concrete, proper timing of each finishingoperation is imperative.

e. Flowing concrete hardened properties.Thecompressive strength, flexural strength, drying shrinkage,creep, and permeability of flowing concrete is notsignificantly different than that of lower slump concretehaving the same w/c and air content. The air-void systemmay have larger bubble spacing factors and a decrease inthe number of voids per inch compared to the initialconcrete, yet satisfactory frost resistance is still achieved inmost cases.

10-10. Silica-Fume Concrete

a. General. The use of silica fume as a pozzolan inconcrete produced in the United States has increased inrecent years. When properly used, it can enhance certainproperties of both fresh and hardened concrete includingcohesiveness, strength, and durability. Silica-fume concretemay be appropriate for concrete applications which requirevery high strength, high abrasion resistance, very lowpermeability, or where very cohesive mixtures are needed toavoid segregation.

b. Properties of silica fume. Silica fume is a by-product of fabrication of silicon or ferrosilicon alloys. It isa very fine powder having a medium to dark gray color. Itis available as loose powder, densified powder, slurry, andin some areas as a blended portland-silica-fume cement.Silica-fume particles are spherical and are typically 100times smaller than portland-cement grains. It typically hasan SiO2 content of 85 to 98 percent. It appears thatconcretes benefit from both the pozzolanic properties ofsilica fume as well as from the extremely small particle size.Silica fume is generally proportioned as an addition, bymass, to the cementitious materials and not as a substitutionfor any of those materials.

c. Effect on water demand and bleeding.Silica fumehas a great affinity for water because of its high surface

10-12

Page 102: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

area, and this is reflected in the concrete which contains it.The increased water demand of concrete containing silicafume can be overcome with the use of a WRA or HRWRAand to a lesser extent by reducing the fine aggregate contentof the mixture. Silica-fume concrete exhibits less bleedingthan conventional concrete because the high affinity of silicafume for water results in very little water left in the mixturefor bleeding. Silica-fume particles attach themselves toadjacent cement particles and reduce the available channelsfor bleeding.

d. Effect on cohesiveness.Concrete containing silicafume is more cohesive and less prone to segregation than acomparable mixture without fume; however, it also tends tolose slump more rapidly. Silica-fume additions greater than10 percent should generally be avoided because the resultingconcrete mixture will become "sticky" and require morevibration for proper consolidation. A slump increase ofapproximately 2 in. may be necessary to overcome thisproblem and to maintain the same consistency for somelength of time. On the other hand, some increase incohesiveness is an advantage in both flowing and pumpedconcretes.

e. Effect on air entrainment.The dosage of AEArequired to produce a particular air content in concreteincreases significantly with increasing amounts of silicafume. The amount of AEA needed in silica-fume concreteto entrain a specified amount of air may be as much as fivetimes greater than that required for similar concrete withoutfume. It may also be difficult to entrain more than 5percent air in concrete containing high silica-fume contents.

f. Effect on plastic shrinkage. When the curingconditions allow a faster rate of evaporation of water fromthe surface of fresh concrete than the water replaced bybleeding from the concrete underneath, plastic shrinkagecracking will occur. Therefore, all admixtures andpozzolans which reduce bleeding of fresh concrete make itmore prone to plastic shrinkage cracking. This isparticularly true for silica-fume concrete in which bleedingis significantly reduced. The problem can become very

serious under curing conditions of high temperature andhigh wind velocity which favor faster evaporation of waterfrom fresh concrete surfaces. A light fog spray of water canbe used to keep surfaces from drying between finishingoperations, or a sheet material can be used to cover thesurface. Moist curing should begin immediately afterfinishing and should continue for a minimum of 14 days.

g. Effect on strength and modulus of elasticity.Strength development characteristics of silica-fume concreteare similar to those of fly ash except that the results of thepozzolanic reactions of silica fume are evident at early ages.This is because silica fume is a very fine material with avery high glass and silica content. However, since silicafume increases the water demand of a mixture, use of aWRA or HRWRA to offset water demand is necessary totake full advantage of silica fume’s full potential forincreasing strength. The ratio of flexural to compressivestrength of silica-fume concrete follows the same pattern asconventional concrete. There are no significant differencesbetween the Young’s modulus of elasticity of concrete withand without silica fume. However, very high-strengthconcretes tend to be more brittle, and this is also true ofhigh-strength silica-fume concrete.

h. Effect on permeability and durability.Pozzolansand GGBF slag often significantly reduce the permeabilityof concrete due to their influence on the fine pore structureand interfacial effects. Silica fume is a much more efficientpozzolanic material than natural pozzolans or fly ash, andtherefore, it decreases concrete permeability dramatically.However, silica-fume concrete must still be properly air-entrained if it is subject to critical saturation and repeatedcycles of freezing and thawing. Silica-fume concretes haveexhibited reduced chloride-ion permeability, enhancedresistance to attack from sulfates and other aggressivechemicals, and enhanced abrasion resistance. Whileabrasion resistance is more dependent upon the hardness ofthe aggregate than upon that of the paste, the addition ofsilica fume can increase the abrasion resistance of concretewhen hard aggregates are unavailable or cannot beeconomically justified, and inferior aggregates must be used.

10-13

Page 103: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Chapter 11Concrete Report

11-1. General

a. Policy. A concrete report will be completed at theconclusion of construction on any major concrete structuresuch as a concrete dam, lock, or any project that is uniqueor unusual. The specific requirements for concrete reportare outlined in ER 1110-2-402, "Concrete Reports." Theconcrete report will serve the dual purpose of meeting therequirements of ER 1110-2-100, "Periodic Inspection andContinuing Evaluation of Completed Civil WorksStructures," for engineering data retained at the project siteand advancing the state of the art of constructing largeconcrete structures by providing personnel working onsubsequent projects with a discussion of problemsencountered and solutions devised.

b. Author. The concrete report should be completedby personnel who are familiar with the project preferablythe concrete engineer assigned to the project. Personnelfrom the engineering division should contribute to the reportin any areas where they have special knowledge.

c. Timing. The report should be written as the projectprogresses so that important information is not lost aspersonnel changes occur. The report should be completedwithin 120 days of substantial completion of concreteplacing.

11-2. Content

a. Outline. The concrete report should be written tofulfill the objectives of providing information to those whomay investigate problems with concrete on the project in thefuture, those embarking on the design of a similar project,or those periodically inspecting the project. The concretereport should include discussions of problems encounteredin each phase of concrete production and placement,including the production of aggregates. The solutions tothese problems should be summarized. The typical outlineprovided in Table 11-1 should serve as a guide in thepreparation of the concrete report.

b. Detailed instruction. The information to beincluded in the concrete report are discussed in accordancewith the outline listed in Table 11-1.

(1) Introduction. The introduction of the report shouldstate the purpose of the report, its scope, and the authorityfor the document in accordance with ER 1110-2-402,

"Concrete Reports" In addition, the report should include aproject description and a location and vicinity map to serveas a guide independent of other project documents. Theintroduction should also include a summary table of thequantities of each major type of concrete on the project, i.e.interior mass, exterior mass, structural, tremie, backfill, etc.

(2) Aggregate sources. Each aggregate source usedfor concrete on the project should be provided by name,coordinates, and/or street or township of the pit or quarry.If test data are available in TM 6-370 (USAEWES 1953),the volume, area, and index numbers should be provided.Drawings or photographs should be provided to indicate theexact location within the pit or quarry from which theaggregate was produced.

(3) Aggregate production.

(a) Pit or quarry operation. This section discusses theremoval of material from the pit or quarry including themake, model, and capacity of the primary equipment. Incase of a quarry, the most commonly used blasting patternshould be detailed to include blast hole spacing and depth,powder types and requirements, and powder factor.Photographs should be used to the maximum extent to showthe equipment and operation.

(b) Fine aggregate production. Photographs and aflow chart should be included showing the sequentialprocessing of the fine aggregate. The major equipment usedin the fine aggregate production should be listed by make,model, and capacity.

(c) Coarse aggregate production. Photographs and aflow chart should be included showing the sequentialprocessing of the coarse aggregate. The major equipmentused should be listed by make, model, and capacity. Theparticle shape should be discussed. In this regard, closeupphotographs of the various stockpiles are most helpful.Readily visible and identifiable objects such as pens,hardhats, or rules should be placed nearby to provide scale.If spray bars or wood pickers are required, this should benoted.

(d) Stockpiling and handling. The number ofstockpiles and the sizes of aggregate in each stockpileshould be noted. The approximate size of the stockpileduring normal aggregate production and concrete placingshould be noted. Photographs or drawings are preferred forthis purpose. If a stockpile was reduced to a very low levelduring the placing of concrete, the time of this occurrenceshould be noted. The equipment used to move aggregate toand from the stockpile should be noted.

11-1

Page 104: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 11-1

Concrete Report - Typical Outline

1. Introduction.

a. Purpose, scope, and authority

b. Project description

c. Concrete quantities by type

d. List of responsible personnel

2. Aggregate sources

a. General

b. Properties of sources used

3. Aggregate production

a. Pit or quarry operation

b. Fine aggregate production

c. Coarse aggregate production

d. Stockpiling and handling

4. Cementitious materials

a. Portland cement sources

b. Blended hydraulic cement sources

c. Pozzolan sources

d. GGBF slag

e. Silica fume

5. Chemical admixtures

a. Air-entraining admixtures

b. Water-reducing admixtures

c. Retarding admixtures

d. Accelerating admixtures

e. Others

6. Concrete batching and mixing plant(s)

7. Concrete mixtures used

a. Mass concrete

b. Structural concrete

c. Special concrete (RCC, fiber reinforced)

d. Shotcrete

8. Construction joint preparation

11-2

Page 105: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Table 11-1 (Continued)

9. Concrete transportation, placement, and consolidation

a. Concrete transportation

b. Concrete placement

c. Shotcrete placement

d. Concrete placing schedule

e. Concrete consolidation

10. Concrete curing and protection

11. Temperature control

a. Insulation

b. Precooling

c. Postcooling

d. Heating

12. Special concretes

a. Fiber-reinforced concrete

b. Roller-compacted concrete

c. Tremie concrete placed in cutoff walls

d. Tremie concrete in underwater applications

e. Other unusual applications of material or means of placement

13. Precast concrete

14. Quality verification and testing

a. Government quality verification

b. Laboratory facilities

15. Summary of test data

a. Aggregate quality tests

b. Aggregate grading tests

c. Tests of cementitious materials

d. Tests of admixtures

e. Concrete strength tests

f. Concrete F/T tests

g. Air content tests

h. Slump tests

i. Placing temperature

j. Resistance thermometer data

16. Special problems

a. Problem

b. Actions

c. Comments

11-3

Page 106: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(4) Cementitious materials.

(a) Portland cement sources. The sources of portlandcement used on the project should be noted as well as thedates they were used and the approximate locations of theiruse. The means of transporting the cement to the projectsite should be noted and the transfer and storage facilitiesdescribed.

(b) Blended hydraulic cement sources. If blendedhydraulic cement is used on the project, it should bediscussed as described for portland cement in the previousparagraph.

(c) Pozzolan source. The sources of pozzolan used onthe project should be listed. If commercial sources are used,the location of the firms supplying the pozzolan should belisted. If a source of natural pozzolan is developed andused by the Contractor or if a natural source is openednearby by a commercial operator to supply pozzolan to theproject, the location of the source should be provided andthe processing requirements outlined.

(d) GGBF slag or silica fume. The sources of GGBFslag or silica fume, or both, if used, should be listed.Storage, handling, and batching facilities should bedescribed. If they were used only in certain locations in thestructures, the locations, dates placed, and mixtureproportions should be included.

(5) Chemical admixtures. The brand name, sources,and available test data of all chemical admixtures used onthe project should be listed as well as the structure featurein which they were used.

(6) Concrete batching and mixing plant. The concretebatching and mixing plant should be described to includemake, model, and capacity of major bins, conveyor belts,hoppers, mixers, and controls. Photographs of the overallplant layout should be included.

(7) Concrete mixtures used. The proportions of theconcrete mixtures used during the bulk of the placement ofeach major class of concrete should be tabulated. Theaggregate batch weights should be reported at saturatedsurface dry. If significant field adjustments were made tothe concrete mixtures that were supplied by the divisionlaboratory being placed in a dam, power plant, lock, orother major water control structures, the extent of theadjustment should be noted and reasons for the adjustmentdiscussed. If shotcrete is used on the project, the type ofplacement (wet or dry) should be noted and the type andcapacity of equipment listed.

(8) Equipment and techniques. The equipment andtechniques used for joint preparation should be described.

(9) Concrete transportation and placement. The typeand capacity of equipment used to transport the concretefrom the mixer to the placement site should be described.The means of placement should be described and thenumber and type of vibrators noted. The normal andmaximum rates of placement of each major class ofconcrete on the project should be listed.

(10) Concrete curing and protection. A briefdescription should be provided outlining the Contractor’sselected means of curing and protecting the concrete. Anymishaps which occurred during curing and protection whichmay have reduced the level of protection or truncated thecuring process on parts of major structures should be noted.

(11) Temperature control. The description of thetemperature control measures used on the project willinclude the types of insulation used, the major componentsof any required pre- or postcooling systems, the dates thatvarious control measures were used during the constructionperiod, and any mishaps which resulted in deviations fromthe specified temperature control requirements.

(12) Special concretes. On any project that includesconcrete different than the usual cast-in-place mass orstructural concrete, a section should be provided detailingthe materials used, the method of placement, problemsencountered, and how they were solved. Concreteapplications which should be discussed include tremieconcrete when placed in a major project element such as acutoff wall, underwater foundation, or fiber-reinforcedconcrete.

(13) Precast concrete. The type, description, name,and location of the manufacturer of precast units used on theproject should be provided.

(14) Quality verification and testing. The procedureand extent of the GQA program and the CQC programshould be described. The types and frequencies of the testsand quality verifications performed by the Governmentshould be listed. The facility used by the Government forGQA purposes and by the Contractor for CQC should bedescribed.

(15) Summary of test data. The format for thepresentation of data from the various quality assurance testsand quality control tests should be such that long tables ofraw data are avoided. Charts should be used wherepossible. Charts and tables when used should show the

11-4

Page 107: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

average of the values presented as well as the extremes andthe specification limits. Use of computer programs forcompiling and analyzing concrete data during constructionis encouraged. The reports generated by these computerprograms may be incorporated into the concrete report withminimum efforts. It is recommended that complete testingdata stored in disks be included as enclosure for future use.

(16) Special problems. Any unusual problemsencountered during the concrete construction and correctiveactions taken should be described. Any comment orevaluation of the results should be provided or documented.

11-5

Page 108: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Appendix AReferences

A-1. Required Publications

TM 5-822-7Standard Practice for Concrete Pavements

ER 415-1-11Biddability, Constructibility, and Operability

ER 1110-1-261Quality Assurance of Laboratory Testing Procedures

ER 1110-1-2002Cement, Pozzolan, and Slag Acceptance Testing

ER 1110-1-8100Laboratory Investigations and Materials Testing

ER 1110-2-100Periodic Inspection and Continuing Evaluation of CompletedCivil Works Structures

ER 1110-2-402Concrete Reports

ER 1110-2-1150Engineering and Design for Civil Works Projects

ER 1110-2-1200Plans and Specifications

ER 1180-1-6Construction Quality Management

EM 1110-1-1804Geotechnical Investigations

EM 1110-2-2002Evaluation and Repair of Concrete Structures

EM 1110-2-2302Construction with Large Stone

EP 415-1-261Quality Assurance Representative’s Guide

CW 03101Formwork for Concrete

CW 03150Expansion, Contraction, and Construction Joints in Concrete

CW 03301Cast-in-Place Structural Concrete

CW 03305Guide Specification for Mass Concrete

CW 03307Concrete (for Minor Structures)

CW 03362Preplaced Aggregate Concrete

CW 03425Precast-Prestressed Concrete

US Army Engineer Waterways Experiment Station 1949US Army Engineer Waterways Experiment Station. 1949.Handbook for Concrete and Cement,with quarterlysupplements (all CRD-C designations), Vicksburg, MS.Note: Use latest edition of all designations.

US Army Engineer Waterways Experiment Station 1953US Army Engineer Waterways Experiment Station. 1953.Test Data, Concrete Aggregates in Continental United Statesand Alaska,with annual supplements, Technical Memoran-dum No. 6-370, Vicksburg, MS.

American Concrete Institute (Annual)American Concrete Institute. Annual.Manual of ConcretePractice,Five Parts, Detroit, MI, including:

"Cement and Concrete Terminology," ACI 116R

"Standard Specifications for Tolerances for ConcreteConstruction and Materials," ACI 117

"Guide to Durable Concrete," ACI 201.2R

"Cooling and Insulating Systems for Mass Concrete," ACI207.4R

"Standard Practice for Selecting Proportions for Normal,Heavyweight, and Mass Concrete," ACI 211.1

"Chemical Admixtures for Concrete," ACI 212.3R

"Recommended Practice for Evaluation of Strength TestResults of Concrete," ACI 214

"Use of Accelerated Strength Testing," ACI 214.1R

"Guide for Use of Normal Weight Aggregates in Concrete,"ACI 221R

A-1

Page 109: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

"Control of Cracking in Concrete Structures," ACI 224R

"In-Place Methods for Determination of Strength ofConcrete," ACI 228.1R

"Guide for Concrete Floor and Slab Construction," ACI302.1R

"Guide to Cast-in-Place Architectural Concrete Practice,"ACI 303R

"Guide for Measuring, Mixing, Transporting, and PlacingConcrete," ACI 304R

"Placing Concrete by Pumping Methods," ACI 304.2R

"Placing Concrete with Belt Conveyors," ACI 304.4R

"Hot Weather Concreting," ACI 305R

"Cold Weather Concreting," ACI 306R

"Standard Practice for Curing Concrete," ACI 308

"Guide for Consolidation of Concrete," ACI 309R

"Building Code Requirements for Reinforced Concrete (ACI318) and Commentary," ACI 318/318R

"State-of-the-Art Report on High Strength Concrete," ACI363R

"State-of-the-Art Report on Fiber-Reinforced Concrete,"ACI 544.1R

"Measurement of Properties of Fiber-Reinforced Concrete,"ACI 544.2R

"Guide for Specifying, Mixing, Placing, and Finishing SteelFiber-Reinforced Concrete," ACI 544.3R

"Design Considerations for Steel Fiber ReinforcedConcrete," ACI 544.4R

American Society for Testing and Materials (Annual)American Society for Testing and Materials. (Annual).Annual Book of ASTM Standards, Philadelphia, PA.

Note: Use the latest available issue of each ASTMStandard.

A-2. Related Publications

ER 415-2-100Construction Management Policies, Procedures, and Staffingfor Civil Works Projects

ER 1110-1-1804Geotechnical Investigation

ER 1110-1-8101Reports of Pertinent Activities at Division Laboratories

EM 1110-1-2009Architectural Concrete

EM 1110-1-2101Working Stresses for Structural Design

EM 1110-2-2005Standard Practice for Shotcrete

EM 1110-2-2006Roller-Compacted Concrete

American Concrete Institute 1988American Concrete Institute. 1988. "No-fines PerviousConcrete for Paving," Concrete International: Design andConstruction, Vol. 10, No. 8, Detroit, MI.

American Society for Testing and Materials 1978American Society for Testing and Materials. 1978. "TheSignificance of Tests and Properties of Concrete andConcrete-Making Materials," ASTM Special TechnicalPublication No. 169B, Philadelphia, PA. (Use 169C whenit appears ~ probably early in 1994.)

Bisque and Lemish 1958Bisque, R. E., and Lemish, John. 1958. "Chemical Charac-teristics of Some Carbonate Aggregate as Related to Dura-bility of Concrete," Highway Research Board Bulletin 196,Washington, DC, pp 29-45.

Buck 1965Buck, A. D. 1965 (Jun). "Investigation of a ReactionInvolving Nondolomitic Limestone Aggregate in Concrete,"Miscellaneous Paper No. 6-724, 38 pp, U.S. Army EngineerWaterways Experiment Station, Vicksburg, MS.

Buck 1983Buck, A. D. 1983. "Alkali Reactivity of Strained Quartz asa Constituent of Concrete Aggregate," Miscellaneous Paper

A-2

Page 110: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

SL-83-13, U.S. Army Engineer Waterways ExperimentStation, Vicksburg, MS.

Buck 1988Buck, A. D. 1988. "Use of Pozzolan or Slag in Concreteto Control Alkali-Silica Reaction and Sulfate Attack,"Technical Report SL-88-29, U.S. Army Engineer WaterwaysExperiment Station, Vicksburg, MS.

Bureau of Reclamation 1975Bureau of Reclamation. 1975.Concrete Manual8thedition. For sale by Superintendent of Documents, USGovernment Printing Office, Washington, DC 20402.

Canadian Standards Association 1986Canadian Standards Association. 1986 (Oct). "PotentialExpansivity of Cement Aggregate Combinations (ConcretePrism Expansion Method)," CAN3-A23.2-M77, A23.2-14A,Supplement No. 2.

Diamond 1976Diamond, S. 1976. "A Review of Alkali Silica Reactionand Expansion Mechanisms: 2. Reactive Aggregates,"Cement and Concrete Research,Vol 6, pp 549-560.

Diamond 1978Diamond, S. 1978. "Chemical Reactions Other ThanCarbonate Reactions," Chapter 23,ASTM Special TechnicalPublication 169B, pp 700-721.

Dolar-Mantuani 1983Dolar-Mantuani, L. 1983. Handbook of ConcreteAggregates,Chapter 7, "Alkali-Aggregate Reactivity," NoyesPublications, Park Ridge, NJ, pp 79-125.

Grattan-Bellew 1987Grattan-Bellew, P. E., ed. 1987. "Concrete Alkali-Aggregate Reactions,Proceedings 7th InternationalConference,Noyes Publications, Park Ridge, NH, 509 pp.

Grattan-Bellew 1992Grattan-Bellew, P. E. 1992. "Microcystalline Quartz,Undulatory Extinction & the Alkali-Silica Reaction,"Proceedings 9th International Conference,The ConcreteSociety, Slough, Vol 1, pp 383-394.

Hadley 1961Hadley, David W. 1961. "Alkali Reactivity of CarbonateRocks--Expansion and Dedolomitization,"Proceedings,Highway Research Board,Vol 40, pp 462-474, 664 pp.

Hadley 1968Hadley, David W. 1968. "Field and Laboratory Studies on

the Reactivity of Sand-Gravel Aggregate,"Journal of PCAR&D Labs,PCA Research Bulletin No. 221, Vol 10, No. 1pp 17-33.

Highway Research Board 1964Highway Research Board. 1964. "Symposium on Alkali-Carbonate Rock Reactions," Highway Research RecordNo. 45 , HRB Publication 1167, 244 pp.

Kosmatka and Panarese 1988Kosmatka, Steven H., and Panarese, William C. 1988.Design and Control of Concrete Mixtures,13th ed., PortlandCement Association, Skokie, IL.

MacInnis 1992MacInnis, Cameron. 1992. "Guide to Durable Concrete,"ACI Committee Report 201.2R-92,ACI Manual of ConcretePractice,Part I, American Concrete Institute, Detroit, MI.

Mather 1948Mather, Bryant. 1948. "Petrographic Identification ofReactive Constitutents in Concrete Aggregate,"Proceedings,American Society for Testing Materials,Vol 48, pp 1120-1125.

Mather, K. et al 1963Mather, Katharine; Luke, Wilbur I.; and Mather, Bryant.1963 (Jun). "Aggregate Investigations, Milford Dam,Kansas; Examination of Cores from Concrete Structures,"Technical Report No. 6-629, 81 pp, U.S. Army EngineerWaterways Experiment Station, Vicksburg, MS.

Meininger 1988Meininger, Richard C. 1988 (Aug). "No-Fines PerviousConcrete for Paving,"Concrete International,AmericanConcrete Institute, Vol 10, No. 8.

Mielenz 1958Mielenz, R. C. 1958. "Evaluation of the Quick-ChemicalTest for Alkali Reactivity of Concrete Aggregate,"HighwayReserch Bulletin No. 171,pp 1-15.

Mindess and Young 1981Mindess, Sidney, and Young, J. Francis. 1981.Concrete,Prentice-Hall, Englewood Cliffs, NJ.

Natesaiyer and Hover 1985Natesaiyer, K., and Hover, K. 1985. "Insitu Identificationof ASR Products in Concrete,"Cement and ConcreteResearch,Vol 18, pp 455-463.

National Ready-Mixed Concrete Association 1982National Ready-Mixed Concrete Association. 1982 (Sep).

A-3

Page 111: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Concrete Plant Standards of the Concrete Plant Manu-facturers Bureau, 8th revision, Spring Street, Silver Spring,MD (also available as CRD-C 514).

Neeley 1988Neeley, Billy D. 1988 (Apr). "Evaluation of ConcreteMixtures for Use in Underwater Reapirs," Technical ReportREMR-CS-18, U.S. Army Engineer Waterways ExperimentStation, Vicksburg, MS.

Neville 1981Neville, Alan M. 1981.Properties of Concrete, 3rd Edition,Pitman Publishing, Marshfield, MA.

Oberholster and Davies 1986Oberholster, R. E., and Davis, G. 1986. "An AcceleratedMethod for Testing the Potential Alkali Reactivity ofSiliceous Aggregates,"Cement and Concrete Research,Vol 16, pp 181-189.

Pepper 1953Pepper, Leonard. 1953. "Tests for Chemical ReactivityBetween Alkalies and Aggregate; QuickChemical Test,"Technical Memorandum No. 6-368, Report 1, U.S. ArmyEngineer Waterways Experiment Station, Vicksburg, MS.

Poole, McLachlan, and Ellis 1988Poole, A. B., McLachlan, A., and Ellis, D. J. 1988. "ASimple Staining Technique for the Identification of Alkali-Silica Gel in Concrete and Aggregate,"Cement andConcrete Research, Vol 18, pp 116-120.

Porter 1978Porter, L. C. 1978. "A 25-Year Evaluation of ConcreteContaining Reactive Kansas-Nebraska Aggregates, ReportREC-ERC-78-5, Engineering Research Center, Bureau ofReclamation, Denver, CO.

Saucier 1980Saucier, Kenneth L. 1980. "High-Strength Concrete, Past,Present, Future,"Concrete International,American ConcreteInstitute, Vol 2, No. 6, pp 46-50.

Stark 1983Stark, David. 1983. "Osmotic Cell Tests to IdentifyPotential for Alkali-Aggregate Reactivity,"Proceedings, 6thInternational Conference on Alkalies in Concrete,Copenhagen.

Stark 1991Stark, David. 1991. "Handbook for the Identification ofAlkali-Silica Reactivity in Highway Structures,"SHRP-C/FR-91-101, Strategic Highway Research Program,Washington, DC, 49 pp.

Tye and Mather 1956Tye, R. V., and Mather, Bryant. 1956. "Tests for ChemicalReactivity Between Alkalies and Aggregate: Mortar-BarTest," Technical Memorandum No. 6-368, Report 2, U.S.Army Engineer Waterways Experiment Station, Vicksburg,MS.

Tynes et al. 1966Tynes, W. O., Luke, W. I., and Houston, B. J. 1966."Results of Laboratory Tests and Examinations of ConcreteCores, Carlyle Reservoir Spillway, Carlyle, Illinois,"Miscellaneous Paper No. 6-802, 29 pp, U.S. Army EngineerWaterways Experiment Station, Vicksburg, MS.

Waddell 1974Waddell, Joseph J. 1974. Concrete ConstructionHandbook,2nd edition, McGraw-Hill, New York.

A-4

Page 112: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

AppendixAppendix BBAbbreviationsAbbreviations

ACI . . . . . . . . . . . . . . American Concrete InstituteAEA . . . . . . . . . . . . . air-entraining admixtureAHV . . . . . . . . . . . . . Class A, High VelocityASTM . . . . . . . . . . . . American Society for Testing

and MaterialsAWA . . . . . . . . . . . . . antiwashout admixtureBCO . . . . . . . . . . . . . bidability, constructability,

and operabilityCE . . . . . . . . . . . . . . . Corps of EngineersCECW-EG . . . . . . . . . Geotechnical and Materials

Engineering Branch, CivilWorks Directorate, Headquar-ters U.S. Army Corps ofEngineers

CEWES-SC . . . . . . . . U.S. Army Engineer Waterways Experiment Station,Structures Laboratory, Con-crete Technology Division

CONUS . . . . . . . . . . . Continental United StatesCQC . . . . . . . . . . . . . contractor quality controlCSA . . . . . . . . . . . . . . Canadian Standards AssociationCW . . . . . . . . . . . . . . civil worksDM . . . . . . . . . . . . . . design memorandumDFE . . . . . . . . . . . . . . durability factor (based on

relative dynamic modulus ofelasticity)

EPA . . . . . . . . . . . . . . Environmental ProtectionAgency

FCSA . . . . . . . . . . . . . Feasibility Cost-SharingAgreement

FM . . . . . . . . . . . . . . fineness modulusFRC . . . . . . . . . . . . . . fiber-reinforced concreteGDM . . . . . . . . . . . . . generic design memorandumGGBF . . . . . . . . . . . . ground granulated blast-furnaceGQA . . . . . . . . . . . . . government quality assuranceHRWRA . . . . . . . . . . . high-range water-reducing

admixtureHQUSACE . . . . . . . . . Headquarters, US Army Corps

of EngineersMSA . . . . . . . . . . . . . maximum size aggregateNMSA . . . . . . . . . . . . nominal maximum size

aggregateNISA . . . . . . . . . . . . . nonlinear, incremental structural

analysisPA . . . . . . . . . . . . . . . preplaced-aggregate concretePED . . . . . . . . . . . . . . preconstruction engineering

and designPMP . . . . . . . . . . . . . . project management planP&S . . . . . . . . . . . . . . plans and specificationsSSD . . . . . . . . . . . . . . saturated-surface dry conditionw/c . . . . . . . . . . . . . . water-cement ratioWES . . . . . . . . . . . . . Waterways Experiment StationWRA . . . . . . . . . . . . . water-reducing admixture

B-1

Page 113: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Appendix CConcrete Materials Design Memorandum

C-1. Concrete Materials Investigation

The scope of the investigation will vary depending on thequantity, criticality of the exposure condition, and the typeof structure. Critical exposure condition is defined as anexposure condition which is deleterious to concrete such asfreezing and thawing, sulfate exposure, or acid attack. Fora small (less than 5,000 yd3 of concrete), nonhydraulicstructure exposed to a noncritical environment, investigationwill generally be limited to determining that a commercialready-mix plant is within acceptable haul distance. Exam-ples of such structures include sidewalks, fireplaces, boatramps, and picnic table bases in a recreation area or culvertheadwalls on an access road. For a small nonhydraulicstructure which will be subjected to critical exposureconditions, additional investigations addressing the measuresto be specified to mitigate the potential concrete deteriora-tion should be included in the DM. Regardless of thecriticality of the exposure condition, if the structure contains5,000 yd3 or more of concrete, a more detailed investigationwill normally be required. A more rigorous and detailedinvestigation will also be required for hydraulic structuressuch as locks, dams, intake structures, powerhouses, majorpumping stations, urban floodwalls, concrete-lined channels,tunnel linings, and appurtenant structures of earth-fill dams.A separate DM is required for lock or dam.

C-2. Concrete Materials Design Memorandum

The following typical information should be covered inconcrete materials design memoranda for various types ofstructures and exposure conditions.

a. Small nonhydraulic structure (less than5,000 yd3 of concrete) subjected to noncritical exposurecondition.

(1) Concrete quantity.

(2) Environmental and functional conditions towhich concrete will be subjected.

(3) Source of concrete (available commercialready-mix plants).

(4) Availability of aggregate of the quality andgrading which is to be specified.

(5) Determination of strength or w/c requirements.

b. Small nonhydraulic structure (less than5,000 yd3 of concrete) subjected to critical exposurecondition.

(1) Concrete quantity.

(2) Description of critical environmental and/orfunctional conditions to which concrete will be subjected.

(3) Specifications requirements to be used toobtain satisfactory durability, including thermal consider-ations of placing temperature and insulation.

(4) Availability of concrete meeting the specifica-tions from commercial ready-mix plants in the project area.

(5) Availability of aggregate of the quality andgrading which is to be specified.

(6) Determination of strength or w/c requirements.

c. Hydraulic structures other than lock or dam orlarge nonhydraulic structure (5,000 yd3 or more of concrete)regardless of the criticality of the exposure condition.

(1) Structures in this category include:

(a) Powerhouse superstructures.

(b) Bridges.

(c) Fish hatchery complexes.

(d) Visitor centers.

(e) Water or vehicular tunnel linings.

(f) Major pumping stations.

(g) Intake structures.

(h) Urban floodwalls.

(2) Brief description and location of project.

(3) Concrete investigation.

(a) Concrete quantity.

(b) Climatic and functional conditions to whichconcrete will be subject (frost action, sulfate attack, acidwater, etc.).

C-1

Page 114: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(c) Concrete qualities to be required.

(d) Typical sectional views of various portions ofthe structures showing classes of concrete.

(4) Portland cement investigation.

(a) Special requirements to be specified forcementitious materials (low alkali, heat of hydration, falseset, C3A limitations, etc.).

(b) Availability of these cementitious materials.

(c) Types of cementitious material to be specifiedwith justification.

(d) Testing requirements.

(e) Cost data.

(5) Pozzolan and other cementitious materialsinvestigation.

(a) Types investigated for use.

(b) Availability.

(c) Cost data.

(6) Aggregate investigation.

(a) Description of aggregate sources investigatedincluding photographs of working faces of operatingquarries.

(b) Cost estimates.

• Cost at source.

• Distance to project.

• Available mode of transportation.

• Transportation cost.

• How a source’s use affects the cost of cementitio-us material due to aggregate reactivity, water requirement,strength characteristics, etc.

(c) Documentation of aggregate quality.

• Reference

• Reference to TM 6-370 (USAEWES 1953)*,including volume numbers, area, latitude, longitude, andindex number.

• If satisfactory TM 6-370 data are not available,local aggregate sources should be evaluated as outlined inparagraph 2-3.

(d) Service records.

(e) Map showing location of project and deposits.

(f) Volume of concrete of each maximum sizeaggregate (MSA).

(g) Recommendations as to which sources shouldbe listed in the specifications.

(h) Recommendations for required aggregate qualitytests and test limits and discussion of how test limits wereset.

(7) Construction plant investigation.

(a) Onsite batch plant requirements, type andcapacity.

(b) Mixer requirements, type.

(c) Commercial ready-mix plant availability,capacity and plant type.

(d) Special requirements (time of delivery, tempera-ture control, maximum lift thickness, insulation, curingmethods, including requirements for shielding concrete fromthe direct rays of the sun on areas cured with clear curingcompound).

(e) Conveying requirements.

d. Lock or dam or both (separate DM).

(1) Description and location of project.

(2) Concrete investigations.

(a) Approximate quantities of concrete in variousstructures or parts of structures by types or classes.

* References cited in this appendix are given in AppendixA of this EM.

C-2

Page 115: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(b) Anticipated number of separate contracts withconcrete quantities included in each contract.

(c) Climatic and functional conditions to whichconcrete will be subjected.

(d) Concrete qualities to be required, includeanticipated instructions to be furnished the governmentresident engineer (see paragraph 6-2).

(e) Sectional views of various portions of thestructures showing classes of concrete.

(3) Portland cement investigations.

(a) Types of portland cement to be specified,including special requirements with justification.

(b) Availability of these cementitious materials.

(c) Testing requirements.

(d) Results of laboratory studies to determinenecessary cementitious contents to obtain desired concretequalities.

(e) Map showing location of project and sources.

(4) Pozzolan and other cementitious materialsinvestigation.

(a) Types of pozzolan and other cementitiousmaterials investigated.

(b) Availability of pozzolans and other cementitiousmaterials.

(c) Map showing location of sources and locationof project.

(d) Cost data.

(e) Anticipated quantity of pozzolan and othercementitious materials to be used per cubic yard of concretefor various classes of concrete (include test data).

(f) Type(s) of pozzolan and other cementitiousmaterials to be specified or allowed.

(5) Aggregate investigation.

(a) Summary of aggregate investigation conducted.

(b) Description of each source investigated includ-ing unsatisfactory sources.

(c) Aggregate processing requirements.

(d) Map showing location of project and sources.

(e) Drawing showing locations and logs of cores ortest pits.

(f) Photographs of cores or typical material fromsand and gravel deposits.

(g) Photographs of working faces in existingquarries.

(h) Cost estimates.

• Cost at source.

• Distance to project.

• Available transportation.

• Transportation cost.

• Cost of special processing.

(i) Documentation of aggregate quality.

• Reference to TM 6-370, including volumenumbers, area, latitude, longitude, and index number.

• If satisfactory TM 6-370 data are not available,local aggregate sources should be evaluated as outlined inparagraph 2-3 of the text.

(j) Discussion of test results.

(k) Service records including photographs whereavailable.

(l) Test quarry-test pit investigations. This mayrequire a separate DM.

(m) Recommendations as to which sources shouldbe listed in the specifications.

(n) Recommendations for required aggregategradings, aggregate quality tests and test limits, and discus-sion of how test limits were set.

(6) Construction plant investigation.

C-3

Page 116: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(a) Plant requirement, type, and capacity.

(b) Mixer requirements, type, and expected capacityand quantity.

(c) Anticipated area at project site to be reservedfor concrete production.

(7) Conveying equipment.

(a) Bucket size.

(b) Time of delivery.

(c) Conveyor belts, pumps, etc.

(8) Thermal studies. The discussion of the consid-erations related to the steps necessary to minimize theeffects of the heat of hydration in a massive structure maybe of such length as to justify a separate DM or a

separate chapter or appendix in the concrete materials DM.The following items should be discussed:

(a) Concrete properties used as input to thenonlinear, incremental structural analysis (NISA).

(b) Results of the NISA.

(c) Insulation requirements including R-value andduration.

(d) Special curing requirements.

(e) Lift thickness.

(f) Minimum time between lifts.

(g) Form stripping time.

(h) Maximum placing temperature.

C-4

Page 117: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Appendix DAlkali-Silica AggregateReactions

D-1. Alkali-Silica Aggregate Reactions

a. General. The use of certain aggregates inconcrete may result in a chemical process in which particu-lar constituents of the aggregates react with alkali hydrox-ides dissolved in concrete pore solutions. These alkalihydroxides are derived mostly from the sodium and potassi-um in portland cement and other cementitious materials, butoccasionally alkalies may be introduced into concrete fromexternal sources or may be released slowly from certainalkali-bearing rock components within the aggregate. Whilemany aggregates may react in concrete, distress in structuresis observed only when significant amounts of expansivereaction products are formed, and they take up water andexpand. The reaction products concerned are hydrous gelswhose chemical composition always includes silica, alkalies,and at least a little calcium. The silica component is alwaysderived from the reactive aggregate, which is usually anamorphous or metastable crystalline form of silica; some-times it is a more complex assemblage of fine-grainedsilicate components. Some authorities distinguish between"alkali-silica" and "alkali-silicate" reactions, but the distinc-tion is not clear cut. By itself, the formation of alkali-silicareaction product creates little distress; the damage inconcrete is associated with subsequent expansion andcracking that occurs when the reaction product gel absorbswater and swells. Keeping affected concrete dry oftenprevents or at least mitigates the deleterious response.Alkali-aggregate reactions were first observed in Californiain the 1940’s but have subsequently been recognized inmany countries. In the United States, alkali-silica reactiveaggregates are more common in western and southwesternstates; in certain parts of the Southeast, including especiallyAlabama, South Carolina, and Georgia; and in some of theGreat Plains states.

b. Nature of the reaction.Field evidence for theoccurrence of alkali-silica reaction in a given concrete in-cludes expansion and development of polygonal or mapcracking as a characteristic feature, especially whenaccompanied by gel deposits exuding from the cracks.However, a number of other causes of distress may showsuperficially similar features, and a petrographicexamination of the affected concrete is generally necessaryto confirm that alkali-silica reaction is actually taking place.Generally speaking, the higher the alkali content of thecement used, the higher the resulting alkali-hydroxideconcentration and pH and the greater the potential for alkali-silica attack. The specific reacting agent is the hydroxide

ion itself. The hydroxide ions break Si-O-Si bonds in thereactive silica or siliceous aggregate components, thusbreaking up their cross-linked structure and isolating anddissolving individual silica tetrahedral units. In the absenceof calcium, such reaction merely produces dissolved silica.However, in the presence of the solid calcium hydroxidealways found in hydrated cement, an alkali-silica gelcontaining some calcium is formed. In the past, it has beensuggested that only gels of minimum calcium content wereexpansive and gels of higher calcium content were limitedswelling gels not capable of causing distress, but someworkers now suggest that this seems not to be the case.One of the common petrographic features of alkali-silicareaction is the occurrence of a zone immediatelysurrounding the reacting aggregate particle in which thecement paste is partially or wholly depleted of calciumhydroxide, the latter having been incorporated into the gel.The actual distress in concrete is associated not withformation of the gel product but with subsequent expansiontaking place when gel absorbs water (or solution) andswells. The swelling pressure generated may be of theorder of 7 MPa (1,000 psi), sufficient to crack thesurrounding paste. If many aggregate grains have reactedto form gel and if sufficient water is available, the combinedeffect results in macroscopic swelling and eventually avisible crack pattern develops. In some concrete structuresthat are geometrically sensitive, the irregular expansion itselfmay be highly damaging to proper functioning, even ifvisible cracks or other evidences of concrete deteriorationare hardly developed. Reactions with strained quartz andwith reactive silicate aggregates generally are slower thanother alkali-silica reactions, but slow expansion maycontinue for many years. Such reactions may producecomparatively little reaction gel and are particularly difficultto identify without petrographic examination. Among theunusual features of the alkali-silica reaction is the existenceof a so-called "pessimum effect." If mortars or concretesare made using varying proportions of reactive and inertaggregate, the expansion may be greatest for a mixture witha comparatively small proportion of the reactive component.The proportion giving rise to the greatest expansion is thepessimum proportion. This proportion is particularly lowwith opal. With most other common types of reactiveaggregate, the pessimum proportion is usually higher, and insome cases, it is 100 percent, i.e., the pessimum effect doesnot occur.

D-2. Criteria for Recognition of PotentiallyDeleterious Constituents in Aggregate

A number of siliceous components of aggregates may bepotentially reactive. Reactive aggregate components may befound in igneous, sedimentary, or metamorphic rocks of

D-1

Page 118: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

various textures and ages. Among the more commonlyencountered reactive aggregate components are:

a. Reactive substances.

(1) Opal. Opal is a variety of amorphous silica witha porous internal structure which contains water. Opal mayoccur in cherts, volcanic rocks, shales, sandstones, andcarbonate rocks; frequently, it may occur in segregatedforms in cavity fillings, crack linings, or as cementingmaterial in concretions. Opal is the most reactive of thevarious reactive aggregate components ordinarily encoun-tered and may cause damage in concrete when as little as afraction of a percent is present in the aggregate.

(2) Chalcedony. Chalcedony is a siliceous componentof some cherts; microscopically it is distinguished byradiating sheaf-like or fibrous structures embedded in agroundmass from which they cannot be separated. Chalce-donic material is largely very fine quartz, but amorphoussilica may be present as well.

(3) Volcanic glass. Particles of volcanic glass orsometimes devitrified volcanic glass in aggregates may bereactive, depending on composition. Acid glasses (those ofsilica content above 65 percent) and intermediate glasses (ofsilica contents between 55 and 65 percent) are commonlyreactive; more basic glasses (silica content below 55 perce-nt) are less so. Reactive glasses may be identified byrefractive indices below 1.57. The presence of water involcanic glasses seems to be associated with reactivity.

(4) Tridymite and cristobalite. These are crystallineforms of silica that are metastable at ordinary temperaturesbut that may be found in various igneous rocks, especiallyandesites and rhyolites.

b. Other potentially reactive substances.In additionto these substances just listed, the following may also bereactive:

(1) Quartz. Well crystallized quartz may be reactiveand may give rise to problems in concrete if the crystals arestrained and finely crushed material produced as in faultzones (mylonite) by virtue of previous geological activity.Strained quartz can be detected petrographically by measure-ment of the undulatory extinction angle. Rocks such asgranites and sandstones may thus be suspect if the forma-tions from which they are derived have a history of exten-sive metamorphic activity.

(2) Silicates. Various sedimentary or metamorphicrock types containing clays or micas have been observed to

be reactive. Such rock types include graywackes, argillites,phyllites, siltstones, etc. There is considerable dispute as towhether the reactive component is finely divided quartz oramorphous silica within the rock or whether the reactioninvolves the clay mineral or mica components. Alkalireactions with such rock types tend to be unusually slowand may escape detection by the normal screening tests forreactive aggregate. If aggregate to be used containssignificant contents of such rock types, low-alkali cementshould be used where available. If not available or if it isavailable only at greatly increased cost, additional studiesmay be required and HQUSACE should be notified (Atten-tion: CECW-EG).

(3) Sandgravel. "Sandgravel" aggregates in parts ofKansas, Nebraska, and Wyoming, especially those from thePlatte, Republican, and Laramie Rivers, have been involvedin the deterioration of concrete. Aggregates from theseareas should be viewed with suspicion unless an acceptableservice record has been compiled or no reactive constituentsare found on petrographic examination.

(4) Disseminated silica in limestones. A number ofinstances of alkali silica reactivity leading to serious distresshave been observed with limestone aggregate that containssmall amounts of dispersed silica, often skeletal remains ofsmall organisms. The fact that limestone aggregates maynot be of the characteristic dolomite composition andimpurity content that results in alkali-carbonate reactiondoes not preclude the possibility of alkali-silica reaction ifdisseminated reactive silica exists in the material.

D-3. Methods of Determining thePotential for Reactivity

a. Standard methods.

(1) American Society for Testing and Materials(ASTM) C 227 (CRD-C 123) - "Potential Alkali Reactivityof Cement-Aggregate Combinations (Mortar-Bar Method)."*In this method the length change of mortar bars preparedwith the aggregate in question (prepared to a specifiedparticle size distribution) and either high-alkali or thespecified job cement is measured over a 1-year period.

* Test methods cited in this manner are from theAnnualBook of ASTM Standards(ASTM 1992) and from theHandbook of Concrete and Cement(U.S. Army EngineerWaterways Experiment Station (USAEWES) 1949), respec-tively. References cited in this appendix are given inAppendix A of this EM.

D-2

Page 119: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

(2) ASTM C 289 (CRD-C 128) - "Potential Reactivi-ty of Aggregates (Chemical Method)." In this so-called"quick chemical test," finely crushed aggregate is immersedin concentrated sodium hydroxide and heated under pressurefor 24 hours. The reaction is monitored by subsequentdetermination of the amount of dissolved silica and thedegree of reduction in the alkalinity of the solution. Thistest gives an indication of possible reactivity but is notsufficiently definitive to be used alone without additionaltesting.

(3) ASTM C 295 (CRD-C 127) - "PetrographicExamination of Aggregates for Concrete." This is theprocedure for petrographic examination of aggregates,including the determination of whether potentially deleteri-ous components are present. The services of a qualifiedpetrographer are required.

(4) A test method involving measurement of lengthchange of concrete prisms rather than mortar bars hasrecently been adopted by the Canadian Standards Associa-tion (CSA) (CSA A23.2-14A 1986). It is intended toovercome criticism of other tests that they do not involveconcrete specimens.

b. Nonstandard methods of determining the potentialfor alkali reactivity.

(1) General. A number of nonstandard methods havebeen developed to determine potential reactivity of aggre-gates. Noteworthy among these is the osmotic methoddescribed by Stark, high-temperature accelerated testdescribed by Oberholster and Davies (1986), and two veryrecent rapid tests: a staining procedure developed by Poole,McLachlan, and Ellis (1988) and a fluorescent methodreported by Natesaiyer and Hover. While none of theseprocedures has yet replaced any of the standard methods oftest for reactive aggregates, they may constitute usefulsupplementary tests that can be carried out relativelyquickly. Most of them require some special apparatus.

(2) Osmotic method. In the osmotic method,powdered aggregate is immersed in sodium hydroxide andseparated by a cement paste membrane from a reservoir ofsodium hydroxide of the same concentration. Theosmotically induced flow of the fluid from the reservoir tothe solution containing the aggregate is monitored, and if itexceeds a specified amount in several weeks, the aggregateis considered reactive.

(3) Accelerated test. In the high-temperatureaccelerated test, mortar prisms made according to theprocedure of ASTM C 227 (CRD-C 123) are immersed in

a one-normal sodium hydroxide solution at 80 °C (176 °F)for 12 days with measurements of expansion made daily.An expansion of 0.11 percent or greater over this period istaken as indicating that the aggregate is deleteriouslyreactive.

(4) Staining test. In the staining procedure, thepotentially reactive rock is reacted with a special alkalisolution so that the gel formed gives rise to a blue-coloredcomplex; the intensity of the color is measured and relatedto the reactivity of the rock.

(5) Fluorescence test. In the fluorescence method,uranyl acetate solution is applied to the concrete; if gel hasformed, uranyl ions are quickly exchanged for alkali ions.The presence of such uranyl-bearing gel is easily observedby examination under ultraviolet light.

D-4. Reliability of Available Test Methods

a. General. Despite continuing research andimprovements, none of the standard methods can be reliedon independently or collectively to provide an unquestion-ably definitive answer, especially to the question of whetherseriously deleterious reaction should be expected if smallamounts of moderately reactive components are discovered.

b. Petrographic examination.The results of petro-graphic examination by an experienced petrographer shouldprovide an indication of the presence of any potentiallyreactive components in the aggregate. The mortar-bar testshould provide an indication of whether any reactions takingplace will be extensive enough to induce unacceptable levelsof expansion. Thus, combining the results of petrographicexamination with mortar-bar expansion test results isconsidered to be the most reliable way to predict possibleexcessive expansion using the standard test procedures.However, contradictory indications will sometimes beprovided by the results of the two methods, and bothmethods entail certain uncertainties. Petrographic examina-tion requires interpretation, and small amounts of certainimportant components, especially opal, can readily bemissed. Mortar-bar tests require at least 6 months and maynot even then detect certain slow forms of reactivity.Furthermore, the reproducibility of the mortar-bar test is nothigh.

c. Quick chemical test.The quick chemical test isgenerally considered to be of limited reliability; its majoradvantage is that it can be accomplished in little more thana day. Spurious results may be obtained in the presence ofcarbonate rock components.

D-3

Page 120: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

d. Test samples.All of these methods require thatthe small volume of aggregate sample examined be trulyrepresentative of the very large and often inhomogeneousdeposit being sampled. This often poses an impossiblecondition, even when standard methods of aggregatesampling (e.g. those specified in ASTM D 75 (CRD-C 155)amd ASTM D 3665) are employed.

e. CSA concrete test.The CSA concrete test wasdesigned to provide a rapid indication of reactivity particu-larly with a fine-grained silicate rock. Unfortunately, sinceno minimum expansion limit is prescribed, interpretation ofthe results are difficult.

f. Osmotic test.The osmotic test has been used fora number of years by the Portland Cement Association andits Construction Technology Laboratories Division andappears to give promising results. Similarly, the acceleratedhigh temperature test has been used for a few years by theNational Building Research Institute in South Africa, and ittoo appears promising for future adoption. The staining andfluorescent analysis procedures are so new that theirreliability has not been assessed.

D-5. Criteria for EvaluatingPotential Reactivity

a. General. The fine and coarse aggregates suggest-ed for use in a given concrete mixture should be evaluatedseparately for potential reactivity, regardless of whether ornot they come from the same source.

b. Petrographic analysis results.A fine or coarseaggregate will be classified as "potentially deleteriouslyreactive," i.e. capable of causing damage to concrete madewith high-alkali cement, if the petrographic examinationreveals any of the following:

(1) Presence of any opal.

(2) More than 5 percent of particles of chert in whichany chalcedony is detected.

(3) More than 3 percent of particles of glassy igneousrocks in which any acid or intermediate glass is detected.

(4) More than 1 percent of particles in which anytridymite or cristobalite is detected.

(5) More than 20 percent of particles containingstrained quartz in an aggregate in which the measuredaverage extinction angle is at least 15 degrees.

(6) More than 15 percent of particles consisting ofgraywacke, argillite, phyllite, or siltstone containing anyvery finely divided quartz or chalcedony.

c. Mortar-bar results. A fine or coarse aggregatewill be classified as "potentially deleteriously reactive" if theexpansion measured in tests with cement containing not lessthan 1.0 percent alkalies calculated as Na2O is more than0.05 percent at 6 months or 0.10 percent at 1 year. Addi-tionally, the following interpretations should be made:

(1) Measured expansions greater than 0.10 percent atany age are indications that the aggregate should be regard-edas potentially deleteriously reactive.

(2) Measured expansions greater than 0.05 percent at6 months but less than 0.10 percent at 1 year usuallyindicate that the aggregate is not deleteriously reactive, butin borderline cases, the slope and trend of the length changeversus time curve should be examined for assistance ininterpretation.

(3) If the aggregate contains strained and very finelydivided quartz, but either the content of such particles or thedegree of strain is such that the criteria mentioned previous-ly for strained quartz aggregate are not exceeded, additionalspecial mortar-bar tests should be carried out. In these teststhe mortar bars are made using a nonreactive fine aggregate,but five particles of a size between 12.5 and 19.0 mm (1/2to 3/4 in.), consisting entirely or mostly of the strainedquartz, are inserted into each bar. The bars are stored underconditions of 100 percent RH and a temperature of 60 ° ±5 °C (140 ° ± 10 °F). The aggregate so tested will beconsidered potentially deleteriously reactive if expansion at6 months exceeds 0.025 percent or expansion at 1 yearexceeds 0.04 percent. These special criteria are invokedbecause of the observed slow rate of expansion of concretecontaining reactive strained and very finely divided quartz.

d. Quick-chemical test criteria.A fine or coarseaggregate will be classified potentially deleteriously reactiveor deleteriously reactive if the data point plotted for it fallsto the right of the line on the standard graph accompanyingthe description of the test method.

e. Service record.A fine or coarse aggregate will beclassified as potentially deleteriously reactive when servicerecords establish that excessive expansion due to alkali-silicareaction has occurred in a structure in which the aggregatehas been used. Where service records indicate deleterious

D-4

Page 121: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

reactivity, the aggregate should be so classed, regardless oflaboratory test results. As previously indicated, thelaboratory test methods cannot be absolutely relied on,individually or collectively, to provide an unquestionablypositive indication of potentially excessive expansion.Every effort should be made to obtain prior performancerecords, especially where cements of high-alkali contentshave been used, and especially if exposure conditions havebeen similar to those predicted for the proposed work. Itshould be noted that some reactions occur slowly and takeyears to become evident. Care should be taken on youngerstructures.

f. Blended aggregates.If either the coarse or fineaggregates for a project will be blended from aggregatederived from two or more sources, the combined coarse orfine aggregate, in the proportion intended for use, will beevaluated for potential reactivity. In the petrographicexamination, the estimated amounts of potentiallydeleterious constituents present will be calculated by themethod of weighted averages, using the proposed grading ofthe blended coarse or fine aggregate. For the mortar-bartest, where fine aggregate is to be blended from two ormore sources, each sieve fraction used in the test shall be inproportion to that sieve fraction in the proposed blended fineaggregate. For blended coarse aggregates, the crushedmaterial from which the test mortars are prepared shallinclude all of the rock types occurring in the combinedcoarse aggregate, in the percentages of each size groupanticipated for the combined grading of the projectaggregate. Similar procedures should be used to selectaggregate to be powdered for sample material for use in thequick-chemical test.

g. Application of standard test criteria. It ispreferred that each fine or coarse aggregate be evaluatedbased on a combination of service record, petrographicexamination, mortar-bar, and quick-chemical test results. Ifthe indications disagree, aggregates are to be consideredpotentially deleteriously reactive if so indicated by thefollowing combinations of tests:

(1) Service records and mortar-bar test results.

(2) Service records and petrographic examination.

(3) Mortar-bar test results and quick-chemical testresults.

(4) Petrographic examination and quick-chemical testresults.

(5) If in the absence of mortar-bar test results,

petrographic examination indicates that the aggregate ispotentially deleteriously reactive, but this is not confirmedby either service record or results of the quick-chemical test,the aggregate should not be used until the results of mortar-bar testing can be obtained.

D-6. Control of Alkali-Silica Aggregate Reactions

Aggregates considered potentially deleteriously reactiveshould not be used in concrete that will be exposed tomoisture in service. If such use is unavoidable, suitableprecautions must be taken to minimize the probability ofharmful internal expansion and cracking. Such precautionsinclude the following:

a. Use of low-alkali cements.If it appears likely thatlow-alkali cement, i.e., cement meeting the optionalrequirement for low-alkali content of ASTM C 150 (CRD-C201) will be available at little or no increase in cost, thisoptional requirement should be invoked and such cementused. However, experience has indicated that such use doesnot provide a complete guarantee that no distress will beexperienced, especially if (a) the structure is a slab on gradeexposed to relatively high temperature and low relativehumidity conditions so that the alkalies become concentratedin the region near the surface, (b) alkali from externalsources can be expected to penetrate the concrete, or(c) alkalies are released internally from certain aggregatecomponents as a result of reaction with cement hydrationproducts.

b. Use of slag or pozzolans.If low-alkali cement isnot available or available only at excessive cost, the use ofa GGBF slag or a mineral admixture such as a pozzolan (flyash, silica fume, or natural pozzolan) (or a blended cementcontaining such a component) is indicated. Thesecomponents effectively absorb hydroxide ions and alkaliions from the concrete pore solutions, thus reducing thedriving force for the deleterious alkali-silica chemicalreaction with aggregate. While blended portland blast-furnace slag cements are not widely available, separatelybatched GGBF slag may be used to provide a GGBF slag-portland-cement concrete highly resistant to alkali-silicaattack. Silica fume added in much smaller percentages thanslag has also been highly effective, although the costinvolved may be high. Some slags, fly ashes, and otherpozzolans provide effective protection against the alkali-silica reaction, some do not. Fly ashes and naturalpozzolans must meet the requirements of ASTM C 618,Table 2A, Supplementary Optional Physical Requirements,Reactivity with Cement Alkalies, to be considered effective.Slag must meet the requirements of ASTM C 989,Appendix X3, to be considered effective. These

D-5

Page 122: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

specifications give criteria for determining the effectivenessof the material. Silica fume should be considered apozzolan for this discussion and should be evaluated perASTM C 618.

c. Determination of the minimum amount of pozzolanor slag to use to control alkali-silica reaction.

(1) The proposed material should be given apreliminary characterization by a combination of physical,chemical, and petrographic methods to assure that it is areasonable candidate material and that it meets theapplicable specifications.

(2) Prepare four mortar mixtures according toASTM C 441 (CRD-C 257). Use the proposed cement orhigh-alkali cement and Pyrex glass as the aggregate on theassumption that if the candidate pozzolan (fly ash, silicafume, or natural pozzolan) or slag will control thiscombination, it will control the actual job materials. Pyrexglass is preferred since its pessimum amount is 100 percent.This avoids the need to conduct tests to determine thepessimum amount of reactive material in the actualaggregate and possible fluctuations in test results due tononuniformity of the aggregate. A control mixture withoutpozzolan or slag should be made.

(3) Test the bars from these mixtures byASTM C 441 (CRD-C 257) for a minimum of 14 days,longer if possible.

(4) Evaluate the expansion data to determine theamount of slag or pozzolan needed to keep expansion fromexceeding the criteria given in the appropriate specifications.

(5) This is the amount to use in the concrete. If maybe necessary to make slight modifications to the intendedconcrete mixture to assure desired workability or strengthgain or other needed properties.

(6) Once a material and its amount to use has beenselected, the continued suitability of this material during theduration of construction should be periodically monitored byselected physical or chemical or petrographic methods or acombination of these. For example, one might use fineness,silica content, or relative amount of glass. Similarmonitoring should be used for the cement. The frequency

of testing and parameters to be used must be determined anddocumented in the concrete materials design memorandum.

(7) It is desirable to approximate the actualenvironmental conditions during the laboratory testing. Ifthere is a significant source of alkali from the environment,it may affect the control provided by the pozzolan or slagand could necessitate the use of nonreactive aggregate.

d. Decreasing the availability of water.Concretesbatched at low w/c have only a limited supply of internalwater needed to cause the alkali-silica reaction product gelto swell, and the permeability of such concretes to outsidewater is also reduced. Thus, the deleterious consequencesof the alkali-silica reaction may be slowed downsignificantly. Experience has also indicated that whenconcrete dries sufficiently that the relative humidity in thepores of the concrete falls below and remains below 80percent, no adverse expansion occurs. However, thechemical reaction is not necessarily precluded, andsubsequent rewetting may produce rapid and seriousexpansions.

e. The sandgravel problem.So-called sandgravelaggregates derived from river-transported deposits along thePlatte, Republican, Laramie, and several other rivers in theGreat Plains states (notably Kansas, Nebraska, Colorado,Wyoming, and to a lesser extent Iowa and Missouri) causecharacteristic problems in concrete. In part, thesedifficulties are due to the poor grading of these materials,but alkali-aggregate reactivity is associated with glassyvolcanic components in the western part of the region andopal combined with lesser amounts of volcanic glass to theeast. Neither the use of low-alkali cements nor the use ofpozzolans have completely succeeded in controlling theproblem. Accordingly, aggregates from these sourcesshould be avoided if economically feasible to do so. If thisis not feasible, replacement of at least 45 percent of theaggregate with crushed limestone appears to be an effectiveremedy when combined with the use of low-alkali cement.

f. Decreasing the amount of reactive aggregate.Itmay be economical to use some proportion of local reactiveaggregate with the rest being more expensive importednonreactive aggregate, rather than use all importedaggregates. The proportion of reactive aggregates that cansafely be used must be carefully investigated.

D-6

Page 123: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

Appendix EAlkali-Carbonate Rock Reactions

E-1. General Statement.

The results of studies that have been reported indicate thatfour types of alkali-carbonate rock reaction may berecognized in concrete. A thorough review of researchthrough 1964 is contained in paragraph E-4 of this manual(Highway Research Board 1964).* It is possible that futurework will show that some of these are merely differentmanifestations of the same reaction, shown by differentrocks under a variety of circumstances. The four types ofreactions are discussed in the following subparagraphs:

a. Reactions involving nondolomitic carbonate rocks.Some rocks which contain little or no dolomite may bereactive (Mather et al. 1963; Buck 1965). The reaction ischaracterized by reaction rims which are visible along theborders of cross sections of aggregate particles. Etchingthese cross-sectional surfaces with dilute hydrochloric acidreveals that the rims are "negative" rims, i.e. the reactionrim zone dissolves more rapidly than the interior of theparticle. The evidence to date indicates that the reaction isnot harmful to concrete and may even be beneficial.

b. Reactions involving dolomite or highly dolomiticcarbonate rocks. The reaction of dolomite or highlydolomitic aggregate particles in concrete has been reported(Tynes et al. 1966). The reaction was characterized byvisible reaction rims on cross sections of the aggregateparticles. When these cross-sectional areas of aggregateparticles were etched with acid, the rimmed area dissolvedat the same rate as the nonrimmed area. No evidence wasreported that this reaction was damaging to concrete.

c. Reactions involving impure dolomitic rocks.Therocks of this group have a characteristic texture andcomposition. The texture is such that larger crystals ofdolomite are scattered in and surrounded by a fine-grainedmatrix of calcite and clay. The rock consists of substantialamounts of dolomite and calcite in the carbonate portion,with significant amounts of acid-insoluble residue consistinglargely of clay. Two reactions have been reported withrocks of this sort, as follows:

(1) Dedolomitization reaction. This reaction isbelieved to have produced harmful expansion of concrete(Hadley 1961). Magnesium hydroxide, brucite (Mg (OH)2),

* References cited in this appendix are given in Appendix Aof this EM.

is formed by this reaction; its presence in concrete whichhas expanded and which contains carbonate aggregate of theindicated texture and composition is strong evidence thatthis reaction has taken place.

(2) Rim-silicification reaction. This reaction is notdefinitely known to be damaging to concrete, although thereare some data which suggest that a retardation in the rate ofstrength development in concrete is associated with itsoccurrence. The reaction is characterized by enrichment ofsilica in the borders of reacted particles (Bisque and Lemish1958). This is seen as a positive or raised border at theedge of cross sections of reacted particles after they havebeen etched in dilute hydrochloric acid. Reaction rims maybe visible before the concrete surfaces are etched.Fortunately, carbonate rocks that contain dolomite, calcite,and insoluble material in the proportions that cause eitherthe dedolomitization or rim-silicification reactions arerelatively rare in nature as major constituents of the wholeproduct of an aggregate source.

E-2. Criteria for Recognition of PotentiallyHarmfully Reactive Carbonate Rocks

These criteria serve to indicate those dolomitic carbonaterocks capable of producing the dedolomitization or rim-silicification reaction. Since the reactions generated bysome highly dolomitic or by some nondolomitic carbonaterocks are not known to be harmful to concrete, no attemptis made to provide guides for recognition of these rocks atthis time.

a. Petrographic examination.When petrographicexaminations are made according to ASTM C 295 (CRD-C127) of quarried carbonate rock or of natural gravelscontaining carbonate-rock particles, adequate dataconcerning texture, calcite-dolomite ratio, the amount andnature of the acid-insoluble residue, or some combination ofthese parameters will be obtained to recognize potentiallyreactive rock. Rocks associated with observed expansivededolomitization have been characterized by fine-grain size(generally 50 micrometres or less) with the dolomite largelypresent as small, nearly euhedral crystals generally scatteredin a finer-grained matrix in which the calcite isdisseminated. The tendency to expansion, other thingsbeing equal, appears to increase with increasing clay contentfrom about 5 to 25 percent by weight of the rock, and alsoappears to increase as the calcite-dolomite ratio of thecarbonate portion approaches 1:1.

b. Testing. Samples of rock recognized as potentiallyreactive by petrographic examination will be tested forlength change during storage in alkali solution in accordance

E-1

Page 124: (ENG. CIVIL) Standard Practice for Concrete for Civil Works Structures [US Army Corps of Engineer

EM 1110-2-20001 Feb 94

with ASTM C 586 (CRD-C 146). Rock characterized byexpansion of 0.1 percent or more by or during 84 days oftest by ASTM C 586 should be classified as potentialreactive.

c. Service record.If adequate reliable data areavailable to demonstrate that concrete structures containingthe same aggregate have exhibited deleterious reactions, theaggregate should be classified as potentially reactive on thebasis of its service record.

E-3. Control of Alkali-Carbonate Reaction

The application of engineering judgment will be required inmaking the final decision as to which rocks are to beclassified as innocuous and which are to be classified aspotentially reactive. Once a rock has been classified aspotentially reactive, the action to be taken should be asindicated in the following subparagraphs.

a. Reactive aggregate.Avoid use of aggregate ofrock classified as potentially reactive by appropriateprocedures such as selective quarrying.

b. Other control methods.If it is not feasible toavoid the use of rock classified as potentially reactive, thenspecify the use of low-alkali cement and pozzolan, the useof the minimum aggregate size that is economically feasible,and dilution so that the amount of potentially reactive rockdoes not exceed 20 percent of the coarse or fine aggregateor 15 percent of the total if reactive material is present inboth.

c. Aggregate source.If it is not practical to enforceconditions in subparagraphs a or b, then the aggregatesource that contains potentially reactive rock shall not beindicated as a source from which acceptable aggregate maybe produced.

E-2