Enduring Exit Regime & NTS Risk Management Processes

20
Enduring Exit Regime & NTS Risk Management Processes Offtake Arrangement Workstream – OAD Section I Review Group 316

description

Enduring Exit Regime & NTS Risk Management Processes. Offtake Arrangement Workstream – OAD Section I Review Group 316. Agenda. Enduring Exit Regime & NTS Risk Management Processes - Overview Real-time Network Modelling Tools NTS Risk Management and Constraint Management Next Steps Discussion - PowerPoint PPT Presentation

Transcript of Enduring Exit Regime & NTS Risk Management Processes

Page 1: Enduring Exit Regime & NTS Risk Management Processes

Enduring Exit Regime & NTS Risk Management Processes

Offtake Arrangement Workstream – OAD Section I Review Group 316

Page 2: Enduring Exit Regime & NTS Risk Management Processes

2

Agenda

Enduring Exit Regime & NTS Risk Management Processes - Overview

Real-time Network Modelling Tools

NTS Risk Management and Constraint Management

Next Steps Discussion

Flow Swapping Process

Page 3: Enduring Exit Regime & NTS Risk Management Processes

3

Constraint Forecasting Overview

Telemetry

Physical & Commercial Constraint

Management Tools

DFN Data

OPN Data

On-line Network Modelling & Assessment

Within Day Constraint Management Strategy

Constraint Forecasting & Identification

Page 4: Enduring Exit Regime & NTS Risk Management Processes

4

Risk in the Enduring Regime

Potential risk generated due to Interruptible NTS Offtakes becoming Firm NTS Offtakes

More Offtakes & greater Volatility/System Flexibility

Zero Exit buyback target and 100% exposure to NG with no collar on the costs

No Exit equivalent of an Entry “TFA”. Therefore constraint management must be carried out BEFORE the constraint occurs

Many locations complicates risk analysis and constraint management decisions

Page 5: Enduring Exit Regime & NTS Risk Management Processes

5

Risk in the Enduring Regime

Broadly, there are two main issues that could give rise to an NTS Exit constraint:

1. The flat supply rate is too low to meet the flat demand rate in an area of the network and pressures become critical.

2. The aggregate within day flow variations remove too much linepack and pressures become critical

Scenario 2 is driven by the offtake flow profiles, therefore in order to forecast and mitigate the risk of this scenario day ahead and within-day, good OPN data is essential

Page 6: Enduring Exit Regime & NTS Risk Management Processes

6

Risk Associated with OPN Data

Telemetry

Physical & Commercial Constraint

Management Tools

DFN Data

OPN Data

On-line Network Modelling & Assessment

Within Day Constraint Management Strategy

Constraint Forecasting & Identification

Risk of DELAYED

Constraint ID

Risk of taking inefficient actions

Risk of delays, rendering some tools

useless

Risk of INCORRECT Constraint ID

Delayed or Inaccurate OPN Data

Risk of Increased Constraint

Management Costs

Page 7: Enduring Exit Regime & NTS Risk Management Processes

7

Constraint Management (CM) Tools

There are more tools available and no reactive tools (interruption) to deal with Exit constraints in the Enduring Exit regime, therefore more time required to make efficient constraint management decisions

No constraint management tool will have immediate effect, each of the tools have differing lead times

Delayed constraint identification may leave some constraint management options unavailable/ineffective

Delayed constraint identification is likely to drive up constraint management costs

Page 8: Enduring Exit Regime & NTS Risk Management Processes

8

Potential CM Tools that rely on OPN Data

Offtake Profile Notice (OPN) Rejection OPN data required to run process

Flow-Swapping OPN data required to run process

Offtake Reduction Invitations OPN data required to run process

Restricting within-day Firm Capacity Release Day ahead OPN analysis to identify potential constraints

Constrained Storage Utilisation OPN analysis to identify constraint

Surrendering Daily NTS Exit (Flat) Capacity OPN analysis to identify constraint

Exit Capacity Constraint Management Agreements OPN analysis to identify constraint

Locational Buy Actions OPN analysis to identify constraint

Operating Margins Utilisation OPN analysis to identify constraint

Off-Peak Capacity Management OPN analysis to identify constraint

Page 9: Enduring Exit Regime & NTS Risk Management Processes

9

Benefits of OPN Data Accuracy

Telemetry

Physical & Commercial Constraint

Management Tools

DFN Data

OPN Data

On-line Network Modelling & Assessment

Within Day Constraint Management Strategy

Constraint Forecasting & Identification

Early Constraint ID

Accurate Constraint ID

Accurate & Timely OPN

Data

More certainty of Capacity Availability

Better Gas Quality Forecasting

Increased Efficiency of Compressor Management

Increased Efficiency of OUG & UAG Management

Better FWACV Handling

Flow Forecasting for Maintenance Purposes

Increased Model Accuracy

And more…..

Reduced CM Costs & Risk

Page 10: Enduring Exit Regime & NTS Risk Management Processes

10

Benefits of OPN Data Accuracy

Good within day forecasting will drive down untimely and exaggerated constraint management instances

Better on-line network modelling will help deliver more optimised NTS operation; ultimately reducing NTS operating costs through efficiency savings (compressor costs, Emissions, UAG etc)

Greater certainty of within day capacity availability means more capacity requests will be fulfilled beyond what is obligated.

Page 11: Enduring Exit Regime & NTS Risk Management Processes

Summary

Page 12: Enduring Exit Regime & NTS Risk Management Processes

12

Summary

The enduring exit regime removes the option of interruption from NTS’s demand management tool kit. As interruption was a close to real time action this both puts more emphasis on;

New exit tools – Of which many use OPN as part of their transaction process. i.e. deviation from prevailing forecast

Forecasting – the use of these tools will need to be assessed at longer lead-times to avoid emergency actions and/or the requirement to curtail exit flows in the first place

More generally optimal NTS operation will ultimately reduce NTS operating costs through efficiency savings (compressor costs, FWACV, UAG etc) through better forward network assessment

Greater certainty of within day capacity availability means we will be able fulfil more capacity requests beyond what is obligated.

Page 13: Enduring Exit Regime & NTS Risk Management Processes

13

Position on Development

National Grid NTS continues to believe that receiving information on an offtake by offtake basis on their expected profile is a basic requirement of the system operator in order to meet its safe, efficient, economic and co-ordinated licence obligations.

National Grid NTS would not however be apposed to any changes to either the OPN format, timing and/or associated restrictions in flow profiles (groups and/or single offtakes) if they can be shown to better facilitate these licence conditions between the TSOs.

Overall, National Grid NTS believes the emphasis of ‘section I’ should be on forecast accuracy of the physical profile notification at all lead-times and not simply adherence to prevailing data in order to define allowed ramp rates based on percentage change.

Page 14: Enduring Exit Regime & NTS Risk Management Processes

14

Next Steps…?

Page 15: Enduring Exit Regime & NTS Risk Management Processes

Flow Swaps – OAD Review

Mike Wassell

Page 16: Enduring Exit Regime & NTS Risk Management Processes

16

Background

National Grid NTS and the DNOs may initiate flow swaps to manage their systems economically and efficiently.

OAD section I 2.4 (refer to final slide)

Where National Grid NTS or the DNO User request a flow swap the aggregate of the revised OPN rates for all Offtakes in the same LDZ / NTS Exit Zone are the same as the prevailing OPN aggregate rates

i.e. the mechanism as detailed under OAD Section i is for 1:1 swap of flow from one offtake to one or more alternative offtakes serving the same LDZ.

From the 1st of Oct 2012 DNO User(s) are subject to exit flat overrun charges and any deemed enduring applications that may result from a chargeable exit flat overrun.

Page 17: Enduring Exit Regime & NTS Risk Management Processes

17

Example of Flow Swap

Exit Point A Exit Point B

Flow 10 Flow 0

Capacity 10 Capacity 5

National Grid request a Flow Swap from NTS/LDZ offtake A to NTS/ LDZ offtake B of 7

Post Flow Swap

Exit Point A Exit Point B

Flow 3 Flow 7

Capacity 10 Capacity 5

Pre Flow Swap

Page 18: Enduring Exit Regime & NTS Risk Management Processes

18

Views sought

Is it felt such a scenario is likely in the enduring regime?

1-in-20 obligation

choice of offtakes to swap flow to on majority of cases

Way forward

is there a case for change to the flow swap rules?

Case for change options ?

Page 19: Enduring Exit Regime & NTS Risk Management Processes

19

NTS Initiated Flow Swap OAD Section I

2.4 Revisions requested by National Grid NTS

2.4.1 National Grid NTS may at any time request a DNO to submit revised Offtake Profile Notices for two or more Offtakes for an LDZ, subject to and in accordance with this paragraph 2.4.

2.4.2 National Grid NTS' request shall specify:

(a) the Offtakes in respect of which such revision is requested;

(b) the times with effect from which the DNO is requested to revise the relevant rates of offtake; and

(c) the revised rates of offtake requested.

2.4.3 Any request by National Grid NTS for the revision of any Offtake Profile Notices shall satisfy the requirement that, for all times in the Day, the aggregate, in respect of all Offtakes (serving the same LDZ) for which such request is made, of the revised rates of offtake requested is the same as the aggregate rates of offtake under the prevailing Offtake Profile Notices at the time the request is made.

2.4.4 To the extent to which the revision by the DNO of any Offtake Profile Notice(s) in compliance with National Grid NTS' request would infringe any of the requirements of this paragraph 2 or TPD Section J4.5.2, National Grid NTS shall be deemed to have waived such other requirements (on the assumption that the DNO submits such revised Offtake Profile Notice(s) within 15 minutes after National Grid NTS' request is made).

Page 20: Enduring Exit Regime & NTS Risk Management Processes

20

NTS Initiated Flow Swap OAD Section I

2.4.5 The DNO shall comply with National Grid NTS' request unless in the DNO's reasonable opinion the safe and efficient operation of the LDZ (consistent with the DNO's obligations to Users under the Transportation Principal Document) would be materially prejudiced by the flow of gas at the relevant Offtakes on the basis of the requested revisions, in which case the DNO shall:

(a) contact and inform National Grid NTS of the position as soon as possible following receipt of National Grid NTS' request; and

(b) cooperate with National Grid NTS and use all reasonable endeavours to agree upon alternative revisions to

Offtake Profile Notices.