End-cap Closeout Review Stephen Haywood Rutherford Appleton Lab

description

End-cap Closeout Review. Stephen Haywood Rutherford Appleton Lab. Introduction (10’) Support Structure (20’) Services (beyond Disc) (60’) Integration (30’) General (30’). Past Reviews. Support Structure Contract7 Sep 2004 Disc Assembly27 Jun 2005 - PowerPoint PPT Presentation

Transcript of End-cap Closeout Review

Page 1: End-cap     Closeout Review

End-cap Closeout Review

Stephen Haywood Rutherford Appleton Lab

Page 2: End-cap     Closeout Review

End-cap Closeout Review 2Stephen Haywood 7 Dec 2007

Introduction (10’)Support Structure (20’)Services (beyond Disc) (60’) Integration (30’)General (30’)

Page 3: End-cap     Closeout Review

End-cap Closeout Review 3Stephen Haywood 7 Dec 2007

Past Reviews

Support Structure Contract 7 Sep 2004 Disc Assembly 27 Jun 2005 Thermal Enclosures 22 Sep 2006

Page 4: End-cap     Closeout Review

End-cap Closeout Review 4Stephen Haywood 7 Dec 2007

Support Structure Contract

Page 5: End-cap     Closeout Review

End-cap Closeout Review 5Stephen Haywood 7 Dec 2007

Problems Unforeseen problems led to delays and more resources. Organising the contract through CERN proved difficult. Two major failures in FWT of flat Panels associated with Cyanate

Esther – switch to FM73U film adhesive. Serious problems placing Disk Fixation holes in Support Cylinder;

required 6 man-months of RAL effort to rectify. Inappropriate use of 3D models by contractor. Contractual problems with “build to print” design concerning

responsibilities. We were poorly prepared to accept components (expected more

from Contractor; needs to be specified) – needed longer than 3 months.

Metrology can be much harder than envisaged ! Need greater clarity in who pays for what, including Tooling and

excess Materials.

Page 6: End-cap     Closeout Review

End-cap Closeout Review 6Stephen Haywood 7 Dec 2007

Successes Probably correct not to impose penalties. Load-test and Fit-check at company.

Page 7: End-cap     Closeout Review

End-cap Closeout Review 7Stephen Haywood 7 Dec 2007

Disks

Page 8: End-cap     Closeout Review

End-cap Closeout Review 8Stephen Haywood 7 Dec 2007

IssuesMore Engineering effort should be put into Manufacturing processes Assembly Testing

Key design criteria should include Robustness – physical & ESD damage Serviceability, including Repair Scenarios

Secondary physics requirements should not compromise the engineering principles.

Physicists’ requests should be questioned if they have significant cost/time/design implications.

Page 9: End-cap     Closeout Review

End-cap Closeout Review 9Stephen Haywood 7 Dec 2007

Companies should be given QA requirements and acceptance criteria.

Regular checks should be made of series of components and care should be taken to anticipate needs for raw materials.

Prototyping consumes many more raw materials than might be expected.

Need more resources than expected ! (See later)

Page 10: End-cap     Closeout Review

End-cap Closeout Review 10Stephen Haywood 7 Dec 2007

Thermal Enclosure

Page 11: End-cap     Closeout Review

End-cap Closeout Review 11Stephen Haywood 7 Dec 2007

Issues Is a TE needed? What is its role? (Thermal, Gas, Moisture, G&S) Could a single TE be used? Commonality between Barrel & End-cap RAL avoid taking on too much work Do not underestimate work/time/money, especially for trivial things

which are “just a …” Ensure good connection with other aspects of project Think abut G&S earlier on Consider working with CTS/Lola Sound out companies before tendering; engage in R&D Consider acceptance criteria in advance Insist on sensible envelopes Avoid active cooling Cu foil is much more flexible for G&S

Page 12: End-cap     Closeout Review

End-cap Closeout Review 12Stephen Haywood 7 Dec 2007

From Pippa

The hand over of the OTE to Valencia seemed to go smoothly, but the ITE at

CERN seemed to be almost too difficult (mea culpa).

Page 13: End-cap     Closeout Review

End-cap Closeout Review 13Stephen Haywood 7 Dec 2007

Completion Jeff Bizzell – Heater Wiring Jason Tarrant – Cooling Jason Tarrant – Documentation:

SCT End-cap Documents & Drawings – ATL-IS-AN-0009

Abstract

This document is a guide to the many documents and drawings relating to the design of the SCT End-cap. All the documents and drawings in this document are those created by staff of the Science and Technology Facilities Council (STFC) in the UK . This document can be used to locate any relevant information on any part of the SCT End-cap that was produced by STFC.

Grounding

Drawings

G&S Parts

TD-1011-598 (ATLISES_0095) is the GRP Front Support cover assembly, this calls all piece parts required.

TD-1011-161 to 164 (ATLISES_0101 to 0104) are the 4 sections of Cu-polyimide Support Cylinder ground sheet.

Documents

ATL-IS-EN-0014 ATLAS SCT End-cap Grounding and Shielding, Engineering Implementation

Page 14: End-cap     Closeout Review

End-cap Closeout Review 14Stephen Haywood 7 Dec 2007

This ReviewQuestions: What have we learnt ?

Includes good lessons; Managerial & Technical What could be done better or differently ? What might we want to take forward for the future ?

& Celebration/Thank-you !

Page 15: End-cap     Closeout Review

End-cap Closeout Review 15Stephen Haywood 7 Dec 2007

Support Structure

Page 16: End-cap     Closeout Review

End-cap Closeout Review 16Stephen Haywood 7 Dec 2007

Page 17: End-cap     Closeout Review

End-cap Closeout Review 17Stephen Haywood 7 Dec 2007

Preparatory work: Prototyping … use of Contractors? FEA

Design of Support Structure: Was the concept of a Cylinder and Panels better than a space

frame?

Materials & Construction Techniques: CFRP, Cyanate-Esther adhesives, Korex Edge sealing Testing Support Cylinder bonding

Was RS4 CE film really OK? Unable to undertake FWT test

Contract: Should Support Structures and Disks have been in single Contract,

ensuring good fit?

Page 18: End-cap     Closeout Review

End-cap Closeout Review 18Stephen Haywood 7 Dec 2007

From Patrick

The problem was that PCI was not setup to machine cylinders within the specifications. My experience with the disks was that PCI have made excellent quality disks, but even machining the outer and inner diameter was hard for them. Next time it is better to use PCI or any other composite company where they are good in: making composite structures, and find the right company for machining the parts if high tolerances are required. This was done for the barrel cylinders.

The mistakes in the machining have caused several problems and confusions throughout the project. At the end there was no alternative than to accept, but everything became more difficult: measurements and supports that did not fit and needed modifications

Edge sealing of the composite structures: This should have been done better, at least for the wings. We found several Thermal Enclosure leaks through these aluminium foil closures, and probably still we have leaks through these.

Page 19: End-cap     Closeout Review

End-cap Closeout Review 19Stephen Haywood 7 Dec 2007

Services

Page 20: End-cap     Closeout Review

End-cap Closeout Review 20Stephen Haywood 7 Dec 2007

STFT

Page 21: End-cap     Closeout Review

End-cap Closeout Review 21Stephen Haywood 7 Dec 2007

Page 22: End-cap     Closeout Review

End-cap Closeout Review 22Stephen Haywood 7 Dec 2007

PPF1

Page 23: End-cap     Closeout Review

End-cap Closeout Review 23Stephen Haywood 7 Dec 2007

ServicesCylinder Radial Cryostat

(Cooling ) LMT Opto DCS FSI

Routing & lengths Caused a lot of worry for JT & TW Did we get it right (except for Heaters)

Physical routing of Heater Pad wires Bends Clips Grounding

LMT’s: Al Cu

Page 24: End-cap     Closeout Review

End-cap Closeout Review 24Stephen Haywood 7 Dec 2007

From Pippa

I worry a lot about the mixture of metals we've ended up with, and the problems we had swapping from aluminium to copper C-seals.

The cooling layout has been the most recent headache, since everything had to be redesigned to relocate the heaters. We are fortunate that the C-wheels are not there, otherwise there's no way we'd have fitted everything in.

We have had the problems of dealing with overlength of a lot of the services, but thankfully nearly everything has been long enough. There are just a few heater pad cables that need extensions, due to a design change not getting propagated through.

The routing of cables to PPF1 worked really smoothly for the end cap, and benefitted a lot from adequate prototyping being done in advance. We had a few issues with optimising the way the grounds were brought together at the clamp, but all the horrible complications of different strip back lengths just worked.

Dealing with the fibres as they came off the end cap was also rather easier than for the barrel.

Page 25: End-cap     Closeout Review

End-cap Closeout Review 25Stephen Haywood 7 Dec 2007

And of course the evaporative cooling... more extensive and realistic testing before hand might have found the problems with the control thermocouples with more lead time. This still wouldn't have addressed the unreliability of the heaters and the short to ground.

Page 26: End-cap     Closeout Review

End-cap Closeout Review 26Stephen Haywood 7 Dec 2007

STFT Construction:

Foam & glue CFRP

Accessibility (Sealing) (G&S)

Page 27: End-cap     Closeout Review

End-cap Closeout Review 27Stephen Haywood 7 Dec 2007

From Patrick

What I can recall is that the STFT delivered to Nikhef was of very bad quality. The slots had to be re-machined and repainted with araldite.

Also a mistake was made with rotational and mirror symmetry, which had to be fixed in situ.

I also think NOW that the parts should be been made much more precise to make everything fit much better. At the end most of the following parts needed adjustments to make them fit.

Page 28: End-cap     Closeout Review

End-cap Closeout Review 28Stephen Haywood 7 Dec 2007

Cable TraysRadial Cryostat

Complexity Time (Design & Assembly) & Cost Material Assembly

Page 29: End-cap     Closeout Review

End-cap Closeout Review 29Stephen Haywood 7 Dec 2007

From Patrick

The CCT worked very well as well, except the Ribbon Guides which fitted very difficult on the tabs. Especially at the top it took sometimes more than 1 hour to mount one!! Too reach too far inside and only one hand available.

Mounting the RCT cover is also difficult and dangerous with the too long LMT's and R/O ribbons. Has to fit on too many holes and screws. Need about 4 people in a too small area.

Page 30: End-cap     Closeout Review

End-cap Closeout Review 30Stephen Haywood 7 Dec 2007

PPF1Cooling LMT Opto DCS FSI

Accessibility Interaction with other detectors

Page 31: End-cap     Closeout Review

End-cap Closeout Review 31Stephen Haywood 7 Dec 2007

From Patrick

The PPF1 design did not work out very well in the beginning, also because Jason was too busy with the HEX redesign. Too late and too many problems. At the end all is working, but could have been a lot better.

We should have had proper protection taken into account during the assembly. The electrical PPF1 were too fragile. In ATLAS there is very little respect for somebody else his parts. People leaning against or on PPF1's to reach somewhere. We have really seen non SCT people abusing our PPF1's. Of course this caused many faults, and damages.

Also the Cooling PPF1's are not very well supported. With making the Serto connections too much force is needed and move around. One patch panel has M3 and the other M4 screws, very annoying.

Page 32: End-cap     Closeout Review

End-cap Closeout Review 32Stephen Haywood 7 Dec 2007

From Patrick

The Type II cable clamp should have been wider closing the PPF1 box. This would prevent dirt getting into the box and solve problems we had with routing the R/O ribbons and LMT cooling pipes. LMT cooling should have had a proper patch panel at the ECex1 connector. The pipes coming of the flange were not properly positioned and too stiff to reroute them.

The whole installation and connection testing of LMT's went rather well.

The R/O ribbons below the LMT's should be changed for next time. We had to disconnect & connect R/O ribbons several times when LMT's were already connected. This was rather risky with violating all the rules about bend radii for optical ribbons. The Cu/Kapton foils caused us a lot shorts etc.

Next time some risk analysis / review should be done for PPF1's, and the person designing should be expecting the worst.

Page 33: End-cap     Closeout Review

End-cap Closeout Review 33Stephen Haywood 7 Dec 2007

From Pippa

I'd also emphasise the importance of prototyping and system testing, with as close to final parts as possible. A few examples:

There was a genuine effort to prototype barrel PPB1, but the final cables were stiffer, and it was a real problem to fit 6 of them across the width available. We had to modify the PPB1 brackets on the fly, even though they were partly glued to the cryostat wall, giving few options.

For the end caps, we tried out the real cable in the clamp ahead of time, and were able to redesign it in a calm way, before the cable installation in the pit.

There has been lots of system testing of modules, but in the last round of power supply firmware updates, there were changes made which were OK with shorter test cables, but failed to work when combined with long cables and PP3.

Page 34: End-cap     Closeout Review

End-cap Closeout Review 34Stephen Haywood 7 Dec 2007

Cooling Use of CuNi X0

Bending Connectors

Were we right to design our own? Accessibility of Connectors Flexibility for connection HEX

Design Communications (CERN, RAL, QMW) Manufacture Soldering problems

Tony Feedback

Page 35: End-cap     Closeout Review

End-cap Closeout Review 35Stephen Haywood 7 Dec 2007

AssemblySealing Use of Foils & Membranes (Cu-Polyimide)

Adhesives Araldite 2011 Techsil Templflex

Page 36: End-cap     Closeout Review

End-cap Closeout Review 36Stephen Haywood 7 Dec 2007

From Patrick

Parts received at CERN:

Most of the parts we received at CERN did not fit and needed modifications. The last known are the metal N2 pipes which did not fit into the Elbow adapters. We had to re-machine all the pipe ends to make everything fit. Another example are holes in the Heater Pad CCT with were we have 7.5mm holes while M3 screws needed to be used. I think at the end we spend a couple of man years modifying parts here at CERN.

Parts we received at CERN for an assembly we often received in different batches. We did not have a good system at CERN to receive and storage parts so often parts were lost for some time. Also due to time pressure, the parts were usually not taken out of there boxes until we needed them and then we found assemblies not complete or parts would not fit, causing the next crises.

Often parts we received still needed some way of assembly: for example soldering of some copper pipes for the N2 system. This would have been a lot easier for us if these had already been soldered and there are several other issues where this was the case.

Page 37: End-cap     Closeout Review

End-cap Closeout Review 37Stephen Haywood 7 Dec 2007

From Patrick

The SCT had a particular problem that all most all of our manpower at CERN was travelling. If parts are shipped to CERN these should be shipped complete, assembled and checked before shipping. Do not ask people at CERN to fill in the blanks. If you for what ever reason want to ship parts to CERN not assembled also deliver the right manpower to prepare the parts at CERN as soon as they arrive.

We should have invested from day 1 much more in storage and cupboards at CERN and should have given some sort of priority to checking parts as soon as they arrive.

We were never very good in checking and approving drawings, which caused a lot of problems.

Page 38: End-cap     Closeout Review

End-cap Closeout Review 38Stephen Haywood 7 Dec 2007

From Patrick

During the assembly of the EC the services TPPF1's should have been positioned at there final location and moved inward for transport only.

The too long LMT's and ribbons caused several problems and cables are now under tension, which may cause us some problems in the future.

The HEX assemblies should have been part of the assembly and testing in NIKHEF/Liverpool or at least in SR1. Only simple pipe connections should be allowed next time during installation. I know this has a big history with Marco, but next time we should not allow this to happen again.

The Thermal enclosure should be sealed in SR1. This we should have never allowed to happen.

Page 39: End-cap     Closeout Review

End-cap Closeout Review 39Stephen Haywood 7 Dec 2007

From Pippa

I think that having a design that didn't allow closing of the thermal enclosure in SR1 was a big mistake. I do realise that this may have been the only solution consistent with the envelopes originally imposed. But the detector has been in the pit for months now without being finally closed at the end, which is risky. It's also an interim problem for installation and testing, in that we can't run cooling at all until the entire plumbing installation is finished. The space constraints also pushed us to use lots of specially designed non-standard connections, which was tricky, and in the end forced some things with the installation sequence that were a problem for the schedule.

Techsil... pah!

Page 40: End-cap     Closeout Review

End-cap Closeout Review 40Stephen Haywood 7 Dec 2007

Grounding & Shielding

Page 41: End-cap     Closeout Review

End-cap Closeout Review 41Stephen Haywood 7 Dec 2007

Schematic

Page 42: End-cap     Closeout Review

End-cap Closeout Review 42Stephen Haywood 7 Dec 2007

Design Retrospective Ground all metallic parts

Groundsheet on Support Cylinder Membranes

Tabs STFT

Small foils Connections

Soldering Silver-loaded epoxy Finger-stock

Quench forces

Page 43: End-cap     Closeout Review

End-cap Closeout Review 43Stephen Haywood 7 Dec 2007

From Patrick

Using the Segmented Plate as our grounding ring was a very bad idea. because also others use these plates to mount parts this has caused a lot of problems. If we would get a short now it can be a million things and we cannot systematically disconnect parts any more to find the short, which is a big concern. So lets hope this does not happen!

Page 44: End-cap     Closeout Review

End-cap Closeout Review 44Stephen Haywood 7 Dec 2007

Integration

Page 45: End-cap     Closeout Review

End-cap Closeout Review 45Stephen Haywood 7 Dec 2007

Fit Rear Support Panel (Wing) Transfer to Cantilever Stand (CLS) Transfer loads to CLS with Rear Support Yoke and PPF1 & TPP

Support Yoke Insert ITE , using ITE Carriage Fit Link Plate Add OTE, using OTE Mounting Frame Insert into TRT Add Front Support Panel (Wing) with Bridge Support System Add Mechanisms and support from RailsAlso PPF1 & TPP to TRT Arms Shim Adjustment Stands Not needed? Transportation Lock System Services Support Ring

Page 46: End-cap     Closeout Review

End-cap Closeout Review 46Stephen Haywood 7 Dec 2007

Issues

Did we anticipate all requirements?(Eg. Split Front Support was anticipated right from beginning)

Was Tooling optimal and fit-for-purpose?

Page 47: End-cap     Closeout Review

End-cap Closeout Review 47Stephen Haywood 7 Dec 2007

From Patrick

Orange cantilever stand: Wrong paint was used. When using alcohol to clean the paint was removed, so we were not really able to properly clean.

The "front transfer plates" were not very flat ~ 5mm. I still believe that this is why EC-C. For EC-C this plate was mounted and stressed several parts and when removed, changed something on the EC. I still believe that this is one of the causes why we have bigger leaks in the thermal enclosure than on EC-A. On Side A the "front transfer plate" was re-worked and made flat to be well within 0.5mm.

Integration: I have never liked the way the EC was supported on the cantilever stand. Also the transfer from the assembly frame to the cantilever stand and from the cantilever stand to the EC trolley we should do differently next time. The EC should have been supported in a kinematic way.

With the tooling provided we did not have any precise control over what we were doing. Moving the EC onto the EC trolley we ended up 2mm away from what we aimed and had a twist. At the end this was accepted as more or less a good position. For Side A we had to make special to lift the EC in the frame and reposition the EC at the front. It was too difficult and time consuming to make tooling to reposition the EC at the rear.

At the end everything turned out to be ok, but it wasn't easy.

Page 48: End-cap     Closeout Review

End-cap Closeout Review 48Stephen Haywood 7 Dec 2007

From Patrick

A private comment on building detectors. You may not want to use this or word it differently:

A lot of problems with building the EC's was on the manpower involved and specifically on EC-C. The detector should be built by technicians and not by physicists or engineers. I think most of the time people not "qualified" were working on the EC. When doing these difficult projects people with the right skills are absolutely needed. I also see this general change in institutes where mechanical departments are reduced or even cancelled and I think this is very bad. We need the best technicians to make the best detectors: i.e. fix all the problems that we cause.

Also engineers should be much more involved in building detectors, especially the parts that are designed. If this does not happen the engineer will not learn from his mistakes.

One annoying thing I had with EC-C is that people were always too much in a hurry. At the end this resulted in much more problems and delays. I also believe that EC-C was shipped too early too CERN. People travelling to CERN are not very efficient in working hours and EC-C had enough problems which could have been solved in Liverpool. This would have saved a lot of time.

Page 49: End-cap     Closeout Review

End-cap Closeout Review 49Stephen Haywood 7 Dec 2007

From Patrick

The trap we always fall into is accepting parts that we know are wrong, but due to time pressure we accept them. This causes many more problems, than solving the original problem.

Page 50: End-cap     Closeout Review

End-cap Closeout Review 50Stephen Haywood 7 Dec 2007

GeneralInterfaces & Communication CERN Nikhef Valencia Ned for G&S

RAL Organisation Proj Man: Debbie Stephen Dept: Debbie Eddie Mike Senior Engineer to replace Debbie? Additional Engineer to support Jason?

Page 51: End-cap     Closeout Review

End-cap Closeout Review 51Stephen Haywood 7 Dec 2007

SchedulingMost things took longer than expected – never enough time/people

Use of MS Project Did we get level of detail right? Need to schedule time for

Admin Holidays Contingency

Difficulty of individuals undertaking multiple parallel tasks Time for Prototyping

Should we have been more involved at CERN, especially post Integration?

Note: Jeff is still helping with wiring.

Page 52: End-cap     Closeout Review

End-cap Closeout Review 52Stephen Haywood 7 Dec 2007

Manpower Never enough Would have benefitted from separate Manager & Engineer

Eg. Difficult to manage contractors and do work Importance of getting good people Avoid loosing key people until work really finished (Eg. Ian) If Manpower “envelope” is constant, front-load effort to allow for

problemsNot ideal for Dept planning; cost of keeping a large team in light of delays and changes

Page 53: End-cap     Closeout Review

End-cap Closeout Review 53Stephen Haywood 7 Dec 2007

RAL SupportWorkshops

Metrology

SSTD Workshop (John Spencer)

Contractors: Designers (John, Steve, Alan, Tommy) Technicians (Cooling Lab)

Lab space: Clean Rooms

Needed much more space than anticpated Cooling Lab R12 Metrology Stuart’s area

Page 54: End-cap     Closeout Review

End-cap Closeout Review 54Stephen Haywood 7 Dec 2007

Cost Consistently underestimated by factors of 2-3* Initial inquiries gave false expectations or expected savings did not

materialise “Cheap” materials turned out to be less cheap, eg. Airex Bits and bobs can add up Cost of effort in labour-intensive work adds to total cost (Cooling

pipes, Stiffeners, Membranes)

* The exception was the Support Structures which cost 0.6 M$, while we feared they could be >>1 M$

Page 55: End-cap     Closeout Review

End-cap Closeout Review 55Stephen Haywood 7 Dec 2007

Financial Control I struggled to follow costs in Famis Identification of expenditure in Famis often obscure; lots of junk Would have helped to subdivide FK36000 – I could not understand

how much we had spent on Discs, TE etc Engineers spent money without communicating (did try to control

this several times) Bits and bobs add up

I failed to understand budget and contingencies (from Janet) Janet seemed to understand the bottom line and have significant

contingencies Despite my lack of control, it seems miraculous there was not a net

overspend on the ATLAS Eng In future, prepare very carefully before embarking on project and

consider parallel system (personal spreadsheets) to track

Page 56: End-cap     Closeout Review

End-cap Closeout Review 56Stephen Haywood 7 Dec 2007

ExpenditureExpenditure Budget

Discs 416 353

Structures [1] 341

TE [2] 41 86

Services 185 57

Ass/Integration [3] 50 50

Total 1033

[1] UK paid 20% ie £61k of £317k PCI Contract

[2] We only supplied parts and paid for some tooling, we did not build OTEs or ITEs or Rear TE Pads

[3] Estimates – not updated, but probably in budget

Uncertainty due to difficulty of assessing and I have not revisited … ultimately bottom line from Famis

Page 57: End-cap     Closeout Review

End-cap Closeout Review 57Stephen Haywood 7 Dec 2007

From Disk Review:

One needs far greater resources (money, time, effort) than is often guessed (take first estimate and increase by factor of 2 to 3 (?).

What is expected to be trivial at an early stage in the design often can prove more complicated when considered towards then end of the design phase, when there may be many constraints.

From Patrick:

For time, money and manpower you should next time take into account at least a factor 2.

Page 58: End-cap     Closeout Review

End-cap Closeout Review 58Stephen Haywood 7 Dec 2007

Other ThingsDocumentation Pro-E & Intralink EDMS CDD

Reviews Internal CERN (FDR, PRR, regular meetings)

Page 59: End-cap     Closeout Review

End-cap Closeout Review 59Stephen Haywood 7 Dec 2007

From Patrick

At the end I am satisfied with what we have achieved, but we have certainly not chosen the easiest way. The result could have been better if more qualified people (technicians) would have been based at CERN for the last two years.

The last two years have been difficult for people travelling a lot to CERN, especially for their personal lives. Next time an attempt should be made to get more people based at CERN.

Page 60: End-cap     Closeout Review

End-cap Closeout Review 60Stephen Haywood 7 Dec 2007

ATLAS SCT EC Eng Team @ RALWorkshop TD PPD

Alan Austin Paul Barclay Richard Apsimon

Geoff Burton Steve Butterworth Lewis Batchelor

Eamonn Capocci Mike Curtis-Rous Jeff Bizzell

Colin Dabinett Peter Ford Stephen Haywood

Mike Harris Debbie Greenfield Richard Holt

Cyril Locket John Matheson Mike Tyndel

Graham Rolfe Craig McWaters

Chris Nelson

John Noviss

Brian Smith

Jason Tarrant

Steve Temple

Ian Wilmut

Page 61: End-cap     Closeout Review

End-cap Closeout Review 61Stephen Haywood 7 Dec 2007

Well done&

Thank you

… the drinks are on me