ID Task Name Duration Start Finish 1 ZONA-3 115 days 14/04 06/08 2 Start 0 days 14/04 14/04 3 EMPIRE TOWER 99 days 14/04 21/07 4 EMPIRE TOWER AREA PART-1 (A1-A6/B1'-B4) 84 days 14/04 06/07 5 BASEMENT 45 days 14/04 28/05 6 Raft Fondation & Plat 33 days 14/04 16/05 7 Galian Tanah Raft, Fitlift, Sumpit, Perimeter 5 days 14/04 18/04 8 Chemikal Angkur D-wall 7 days 14/04 20/04 9 Potong Pancang 5 days 15/04 19/04 10 Chemikal Angkur Tiang Pancang 7 days 20/04 26/04 11 Pasang Bekisting batako 5 days 15/04 19/04 12 Lean Concrete 5 days 17/04 21/04 13 Pembesian 20 days 22/04 11/05 14 Pasang kaki Ayam 15 days 27/04 11/05 15 Pasang Bekisting Fitlift, Sumpit. 7 days 07/05 13/05 16 Pasang Tenda 5 days 09/05 13/05 17 Pasang Thermocuple + Final Chek List Raft 3 days 11/05 13/05 18 Pengecoran + Floor Hardener 3 days 14/05 16/05 19 Kolom 5 days 24/05 28/05 20 Pembesian 4 days 24/05 27/05 21 Bekisting 4 days 25/05 28/05 22 Pengecoran 4 days 25/05 28/05 23 Shear Wall 5 days 24/05 28/05 24 Pembesian 4 days 24/05 27/05 25 Bekisting 4 days 25/05 28/05 26 Pengecoran 4 days 25/05 28/05 27 LOWER GROUND 11 days 29/05 08/06 28 Plat dan Balok 6 days 29/05 03/06 29 Bekisting 4 days 29/05 01/06 30 Pembesian 4 days 30/05 02/06 31 Pengecoran 1 day 03/06 03/06 32 Kolom 5 days 04/06 08/06 33 Pembesian 4 days 04/06 07/06 34 Bekisting 4 days 05/06 08/06 35 Pengecoran 4 days 05/06 08/06 36 Shear Wall 5 days 04/06 08/06 37 Pembesian 4 days 04/06 07/06 38 Bekisting 4 days 05/06 08/06 39 Pengecoran 4 days 05/06 08/06 40 MEZZANINE P2 11 days 09/06 19/06 41 Plat dan Balok 6 days 09/06 14/06 42 Bekisting 4 days 09/06 12/06 43 Pembesian 4 days 10/06 13/06 44 Pengecoran 1 day 14/06 14/06 14/04 14/04 18/04 14/04 20/04 15/04 19/04 20/04 26/04 15/04 19/04 17/04 21/04 22/04 11/05 27/04 11/05 07/05 13/05 09/05 13/05 11/05 13/05 14/05 16/05 24/05 27/05 25/05 28/05 25/05 28/05 24/05 27/05 25/05 28/05 25/05 28/05 29/05 01/06 30/05 02/06 03/06 03/06 04/06 07/06 05/06 08/06 05/06 08/06 04/06 07/06 05/06 08/06 05/06 08/06 09/06 12/06 10/06 13/06 14/06 14/06 S S M T W T F S S M T W T F S S M T ar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 1 Task Milestone Summary Project Summary Deadline Progress SCHEDULE EMPIRE, VICTORY TOWER PODIUM PODOMORO CITY DELI MEDAN Page 1 Project: EMPIRE Date: 15/04

TAGS:

description

EMPIRE

Transcript of Empire

  • ID Task Name Duration Start Finish

    1 ZONA-3 115 days 14/04 06/082 Start 0 days 14/04 14/043 EMPIRE TOWER 99 days 14/04 21/074 EMPIRE TOWER AREA PART-1 (A1-A6/B1'-B4) 84 days 14/04 06/075 BASEMENT 45 days 14/04 28/056 Raft Fondation & Plat 33 days 14/04 16/057 Galian Tanah Raft, Fitlift, Sumpit, Perimeter 5 days 14/04 18/048 Chemikal Angkur D-wall 7 days 14/04 20/049 Potong Pancang 5 days 15/04 19/04

    10 Chemikal Angkur Tiang Pancang 7 days 20/04 26/0411 Pasang Bekisting batako 5 days 15/04 19/0412 Lean Concrete 5 days 17/04 21/0413 Pembesian 20 days 22/04 11/0514 Pasang kaki Ayam 15 days 27/04 11/0515 Pasang Bekisting Fitlift, Sumpit. 7 days 07/05 13/0516 Pasang Tenda 5 days 09/05 13/0517 Pasang Thermocuple + Final Chek List Raft 3 days 11/05 13/0518 Pengecoran + Floor Hardener 3 days 14/05 16/0519 Kolom 5 days 24/05 28/0520 Pembesian 4 days 24/05 27/0521 Bekisting 4 days 25/05 28/0522 Pengecoran 4 days 25/05 28/0523 Shear Wall 5 days 24/05 28/0524 Pembesian 4 days 24/05 27/0525 Bekisting 4 days 25/05 28/0526 Pengecoran 4 days 25/05 28/0527 LOWER GROUND 11 days 29/05 08/0628 Plat dan Balok 6 days 29/05 03/0629 Bekisting 4 days 29/05 01/0630 Pembesian 4 days 30/05 02/0631 Pengecoran 1 day 03/06 03/0632 Kolom 5 days 04/06 08/0633 Pembesian 4 days 04/06 07/0634 Bekisting 4 days 05/06 08/0635 Pengecoran 4 days 05/06 08/0636 Shear Wall 5 days 04/06 08/0637 Pembesian 4 days 04/06 07/0638 Bekisting 4 days 05/06 08/0639 Pengecoran 4 days 05/06 08/0640 MEZZANINE P2 11 days 09/06 19/0641 Plat dan Balok 6 days 09/06 14/0642 Bekisting 4 days 09/06 12/0643 Pembesian 4 days 10/06 13/0644 Pengecoran 1 day 14/06 14/06

    14/04

    14/04 18/0414/04 20/04

    15/04 19/0420/04 26/04

    15/04 19/0417/04 21/04

    22/04 11/0527/04 11/05

    07/05 13/0509/05 13/05

    11/05 13/0514/05 16/05

    24/05 27/0525/05 28/0525/05 28/05

    24/05 27/0525/05 28/0525/05 28/05

    29/05 01/0630/05 02/06

    03/06 03/06

    04/06 07/0605/06 08/0605/06 08/06

    04/06 07/0605/06 08/0605/06 08/06

    09/06 12/0610/06 13/06

    14/06 14/06

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 1

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    45 Kolom 5 days 15/06 19/0646 Pembesian 4 days 15/06 18/0647 Bekisting 4 days 16/06 19/0648 Pengecoran 4 days 16/06 19/0649 Shear Wall 5 days 15/06 19/0650 Pembesian 4 days 15/06 18/0651 Bekisting 4 days 16/06 19/0652 Pengecoran 4 days 16/06 19/0653 MEZZANINE P1 11 days 20/06 30/0654 Plat dan Balok 6 days 20/06 25/0655 Bekisting 4 days 20/06 23/0656 Pembesian 4 days 21/06 24/0657 Pengecoran 1 day 25/06 25/0658 Kolom 5 days 26/06 30/0659 Pembesian 4 days 26/06 29/0660 Bekisting 4 days 27/06 30/0661 Pengecoran 4 days 27/06 30/0662 Shear Wall 5 days 26/06 30/0663 Pembesian 4 days 26/06 29/0664 Bekisting 4 days 27/06 30/0665 Pengecoran 4 days 27/06 30/0666 GROUND FLOOR 6 days 01/07 06/0767 Plat dan Balok 6 days 01/07 06/0768 Bekisting 4 days 01/07 04/0769 Pembesian 4 days 02/07 05/0770 Pengecoran 1 day 06/07 06/0771 Chemikal Angkur D-wall LG-GF 36 days 30/05 04/0772 Bor Dwall 34 days 30/05 02/0773 Install Besi 34 days 01/06 04/0774 EMPIRE TOWER AREA PART-2 (A1-A6/B4-B7') 48 days 28/05 14/0775 BASEMENT 5 days 28/05 01/0676 Kolom 5 days 28/05 01/0677 Pembesian 4 days 28/05 31/0578 Bekisting 4 days 29/05 01/0679 Pengecoran 4 days 29/05 01/0680 Shear Wall 5 days 28/05 01/0681 Pembesian 4 days 28/05 31/0582 Bekisting 4 days 29/05 01/0683 Pengecoran 4 days 29/05 01/0684 LOWER GROUND 12 days 02/06 13/0685 Plat dan Balok 7 days 02/06 08/0686 Bekisting 5 days 02/06 06/0687 Pembesian 5 days 03/06 07/0688 Pengecoran 1 day 08/06 08/06

    15/06 18/0616/06 19/0616/06 19/06

    15/06 18/0616/06 19/0616/06 19/06

    20/06 23/0621/06 24/06

    25/06 25/06

    26/06 29/0627/06 30/0627/06 30/06

    26/06 29/0627/06 30/0627/06 30/06

    01/07 04/0702/07 05/07

    06/07 06/07

    30/05 02/0701/06 04/07

    28/05 31/0529/05 01/0629/05 01/06

    28/05 31/0529/05 01/0629/05 01/06

    02/06 06/0603/06 07/06

    08/06 08/06

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 2

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    89 Kolom 5 days 09/06 13/0690 Pembesian 4 days 09/06 12/0691 Bekisting 4 days 10/06 13/0692 Pengecoran 4 days 10/06 13/0693 Shear Wall 5 days 09/06 13/0694 Pembesian 4 days 09/06 12/0695 Bekisting 4 days 10/06 13/0696 Pengecoran 4 days 10/06 13/0697 MEZZANINE P2 12 days 14/06 25/0698 Plat dan Balok 7 days 14/06 20/0699 Bekisting 5 days 14/06 18/06

    100 Pembesian 5 days 15/06 19/06101 Pengecoran 1 day 20/06 20/06102 Kolom 5 days 21/06 25/06103 Pembesian 4 days 21/06 24/06104 Bekisting 4 days 22/06 25/06105 Pengecoran 4 days 22/06 25/06106 Shear Wall 5 days 21/06 25/06107 Pembesian 4 days 21/06 24/06108 Bekisting 4 days 22/06 25/06109 Pengecoran 4 days 22/06 25/06110 MEZZANINE P1 12 days 26/06 07/07111 Plat dan Balok 7 days 26/06 02/07112 Bekisting 5 days 26/06 30/06113 Pembesian 5 days 27/06 01/07114 Pengecoran 1 day 02/07 02/07115 Kolom 5 days 03/07 07/07116 Pembesian 4 days 03/07 06/07117 Bekisting 4 days 04/07 07/07118 Pengecoran 4 days 04/07 07/07119 Shear Wall 5 days 03/07 07/07120 Pembesian 4 days 03/07 06/07121 Bekisting 4 days 04/07 07/07122 Pengecoran 4 days 04/07 07/07123 GROUND FLOOR 7 days 08/07 14/07124 Plat dan Balok 7 days 08/07 14/07125 Bekisting 5 days 08/07 12/07126 Pembesian 5 days 09/07 13/07127 Pengecoran 1 day 14/07 14/07128 Chemikal Angkur D-wall LG-GF 39 days 03/06 11/07131 TANGGA 31 days 21/06 21/07132 Tangga Basement To LG 7 days 21/06 27/06133 Bekisting 4 days 21/06 24/06134 Pembesian 4 days 23/06 26/06

    09/06 12/0610/06 13/0610/06 13/06

    09/06 12/0610/06 13/0610/06 13/06

    14/06 18/0615/06 19/06

    20/06 20/06

    21/06 24/0622/06 25/0622/06 25/06

    21/06 24/0622/06 25/0622/06 25/06

    26/06 30/0627/06 01/07

    02/07 02/07

    03/07 06/0704/07 07/0704/07 07/07

    03/07 06/0704/07 07/0704/07 07/07

    08/07 12/0709/07 13/07

    14/07 14/07

    21/06 24/0623/06 26/06

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 3

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    135 Pengecoran 1 day 27/06 27/06136 Tangga LG To P2 7 days 03/07 09/07137 Bekisting 4 days 03/07 06/07138 Pembesian 4 days 05/07 08/07139 Pengecoran 1 day 09/07 09/07140 Tangga P2 To P1 7 days 13/07 19/07141 Bekisting 4 days 13/07 16/07142 Pembesian 4 days 15/07 18/07143 Pengecoran 1 day 19/07 19/07144 Tangga P1 To GF 7 days 15/07 21/07145 Bekisting 4 days 15/07 18/07146 Pembesian 4 days 17/07 20/07147 Pengecoran 1 day 21/07 21/07148 EMPIRE PODIUM 81 days 14/04 03/07149 BASEMENT 43 days 14/04 26/05150 Plat lantai 38 days 14/04 21/05151 Chemikal Angkur D-wall 10 days 14/04 23/04152 Pembesian 7 days 12/05 18/05153 Pasang Water Stop 5 days 14/05 18/05154 Pengecoran 3 days 19/05 21/05155 Kolom 4 days 22/05 25/05156 Pembesian 3 days 22/05 24/05157 Bekisting 3 days 23/05 25/05158 Pengecoran 3 days 23/05 25/05159 Core Wall 5 days 22/05 26/05160 Pembesian 4 days 22/05 25/05161 Bekisting 4 days 23/05 26/05162 Pengecoran 4 days 23/05 26/05163 LOWER GROUND 11 days 26/05 05/06164 Plat dan Balok 6 days 26/05 31/05165 Bekisting 4 days 26/05 29/05166 Pembesian 4 days 27/05 30/05167 Pengecoran 1 day 31/05 31/05168 Kolom 5 days 01/06 05/06169 Pembesian 4 days 01/06 04/06170 Bekisting 4 days 02/06 05/06171 Pengecoran 4 days 02/06 05/06172 Core Wall 5 days 01/06 05/06173 Pembesian 4 days 01/06 04/06174 Bekisting 4 days 02/06 05/06175 Pengecoran 4 days 02/06 05/06176 MEZZANINE P2 11 days 06/06 16/06177 Plat dan Balok 6 days 06/06 11/06178 Bekisting 4 days 06/06 09/06

    27/06 27/06

    03/07 06/0705/07 08/07

    09/07 09/07

    13/07 16/0715/07 18/07

    19/07 19/07

    15/07 18/0717/07 20/07

    21/07 21/07

    14/04 23/0412/05 18/05

    14/05 18/0519/05 21/05

    22/05 24/0523/05 25/0523/05 25/05

    22/05 25/0523/05 26/0523/05 26/05

    26/05 29/0527/05 30/05

    31/05 31/05

    01/06 04/0602/06 05/0602/06 05/06

    01/06 04/0602/06 05/0602/06 05/06

    06/06 09/06

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 4

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    179 Pembesian 4 days 07/06 10/06180 Pengecoran 1 day 11/06 11/06181 Kolom 5 days 12/06 16/06182 Pembesian 4 days 12/06 15/06183 Bekisting 4 days 13/06 16/06184 Pengecoran 4 days 13/06 16/06185 MEZZANINE P1 11 days 17/06 27/06186 Plat dan Balok 6 days 17/06 22/06187 Bekisting 4 days 17/06 20/06188 Pembesian 4 days 18/06 21/06189 Pengecoran 1 day 22/06 22/06190 Kolom 5 days 23/06 27/06191 Pembesian 4 days 23/06 26/06192 Bekisting 4 days 24/06 27/06193 Pengecoran 4 days 24/06 27/06194 GROUND FLOOR 6 days 28/06 03/07195 Plat dan Balok 6 days 28/06 03/07196 Bekisting 4 days 28/06 01/07197 Pembesian 4 days 29/06 02/07198 Pengecoran 1 day 03/07 03/07199 Chemikal Angkur D-wall LG-GF 36 days 27/05 01/07200 Bor Dwall 35 days 27/05 30/06201 Install Besi 35 days 28/05 01/07202 VICTORY TOWER 115 days 14/04 06/08203 VICTORY TOWER AREA PART-1 (B13-B16'/A1'-A5') 92 days 14/04 14/07204 BASEMENT 53 days 14/04 05/06205 Raft Fondation & Plat 41 days 14/04 24/05206 Galian Tanah Raft, Fitlift, Sumpit, Perimeter 20 days 14/04 03/05207 Potong Pancang 22 days 15/04 06/05208 Chemikal Angkur Tiang Pancang 10 days 07/05 16/05209 Pasang Bekisting batako 22 days 15/04 06/05210 Lean Concrete 22 days 25/04 16/05211 Pembesian 20 days 30/04 19/05212 Pasang kaki Ayam 13 days 05/05 17/05213 Pasang Bekisting Fitlift, Sumpit. 7 days 15/05 21/05214 Pasang Tenda 7 days 15/05 21/05215 Pasang Thermocuple + Final Chek List Raft 3 days 19/05 21/05216 Pengecoran + Floor Hardener 3 days 22/05 24/05217 Kolom 5 days 01/06 05/06218 Pembesian 4 days 01/06 04/06219 Bekisting 4 days 02/06 05/06220 Pengecoran 4 days 02/06 05/06221 Shear Wall 5 days 01/06 05/06222 Pembesian 4 days 01/06 04/06

    07/06 10/0611/06 11/06

    12/06 15/0613/06 16/0613/06 16/06

    17/06 20/0618/06 21/06

    22/06 22/06

    23/06 26/0624/06 27/0624/06 27/06

    28/06 01/0729/06 02/07

    03/07 03/07

    27/05 30/0628/05 01/07

    14/04 03/0515/04 06/05

    07/05 16/0515/04 06/05

    25/04 16/0530/04 19/05

    05/05 17/0515/05 21/0515/05 21/05

    19/05 21/0522/05 24/05

    01/06 04/0602/06 05/0602/06 05/06

    01/06 04/06

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 5

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    223 Bekisting 4 days 02/06 05/06224 Pengecoran 4 days 02/06 05/06225 LOWER GROUND 11 days 06/06 16/06226 Plat dan Balok 6 days 06/06 11/06227 Bekisting 4 days 06/06 09/06228 Pembesian 4 days 07/06 10/06229 Pengecoran 1 day 11/06 11/06230 Kolom 5 days 12/06 16/06231 Pembesian 4 days 12/06 15/06232 Bekisting 4 days 13/06 16/06233 Pengecoran 4 days 13/06 16/06234 Shear Wall 5 days 12/06 16/06235 Pembesian 4 days 12/06 15/06236 Bekisting 4 days 13/06 16/06237 Pengecoran 4 days 13/06 16/06238 MEZZANINE P2 11 days 17/06 27/06239 Plat dan Balok 6 days 17/06 22/06240 Bekisting 4 days 17/06 20/06241 Pembesian 4 days 18/06 21/06242 Pengecoran 1 day 22/06 22/06243 Kolom 5 days 23/06 27/06244 Pembesian 4 days 23/06 26/06245 Bekisting 4 days 24/06 27/06246 Pengecoran 4 days 24/06 27/06247 Shear Wall 5 days 23/06 27/06248 Pembesian 4 days 23/06 26/06249 Bekisting 4 days 24/06 27/06250 Pengecoran 4 days 24/06 27/06251 MEZZANINE P1 11 days 28/06 08/07252 Plat dan Balok 6 days 28/06 03/07253 Bekisting 4 days 28/06 01/07254 Pembesian 4 days 29/06 02/07255 Pengecoran 1 day 03/07 03/07256 Kolom 5 days 04/07 08/07257 Pembesian 4 days 04/07 07/07258 Bekisting 4 days 05/07 08/07259 Pengecoran 4 days 05/07 08/07260 Shear Wall 5 days 04/07 08/07261 Pembesian 4 days 04/07 07/07262 Bekisting 4 days 05/07 08/07263 Pengecoran 4 days 05/07 08/07264 GROUND FLOOR 6 days 09/07 14/07265 Plat dan Balok 6 days 09/07 14/07266 Bekisting 4 days 09/07 12/07

    02/06 05/0602/06 05/06

    06/06 09/0607/06 10/06

    11/06 11/06

    12/06 15/0613/06 16/0613/06 16/06

    12/06 15/0613/06 16/0613/06 16/06

    17/06 20/0618/06 21/06

    22/06 22/06

    23/06 26/0624/06 27/0624/06 27/06

    23/06 26/0624/06 27/0624/06 27/06

    28/06 01/0729/06 02/07

    03/07 03/07

    04/07 07/0705/07 08/0705/07 08/07

    04/07 07/0705/07 08/0705/07 08/07

    09/07 12/07

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 6

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    267 Pembesian 4 days 10/07 13/07268 Pengecoran 1 day 14/07 14/07269 VICTORY TOWER AREA PART-2 (B13-B10'/A1'-A5') 48 days 06/06 23/07270 BASEMENT 5 days 06/06 10/06271 Kolom 5 days 06/06 10/06272 Pembesian 4 days 06/06 09/06273 Bekisting 4 days 07/06 10/06274 Pengecoran 4 days 07/06 10/06275 Shear Wall 5 days 06/06 10/06276 Pembesian 4 days 06/06 09/06277 Bekisting 4 days 07/06 10/06278 Pengecoran 4 days 07/06 10/06279 LOWER GROUND 12 days 11/06 22/06280 Plat dan Balok 7 days 11/06 17/06281 Bekisting 5 days 11/06 15/06282 Pembesian 5 days 12/06 16/06283 Pengecoran 1 day 17/06 17/06284 Kolom 5 days 18/06 22/06285 Pembesian 4 days 18/06 21/06286 Bekisting 4 days 19/06 22/06287 Pengecoran 4 days 19/06 22/06288 Shear Wall 5 days 18/06 22/06289 Pembesian 4 days 18/06 21/06290 Bekisting 4 days 19/06 22/06291 Pengecoran 4 days 19/06 22/06292 MEZZANINE P2 12 days 23/06 04/07293 Plat dan Balok 7 days 23/06 29/06294 Bekisting 5 days 23/06 27/06295 Pembesian 5 days 24/06 28/06296 Pengecoran 1 day 29/06 29/06297 Kolom 5 days 30/06 04/07298 Pembesian 4 days 30/06 03/07299 Bekisting 4 days 01/07 04/07300 Pengecoran 4 days 01/07 04/07301 Shear Wall 5 days 30/06 04/07302 Pembesian 4 days 30/06 03/07303 Bekisting 4 days 01/07 04/07304 Pengecoran 4 days 01/07 04/07305 MEZZANINE P1 12 days 05/07 16/07306 Plat dan Balok 7 days 05/07 11/07307 Bekisting 5 days 05/07 09/07308 Pembesian 5 days 06/07 10/07309 Pengecoran 1 day 11/07 11/07310 Kolom 5 days 12/07 16/07

    10/07 13/0714/07 14/07

    06/06 09/0607/06 10/0607/06 10/06

    06/06 09/0607/06 10/0607/06 10/06

    11/06 15/0612/06 16/06

    17/06 17/06

    18/06 21/0619/06 22/0619/06 22/06

    18/06 21/0619/06 22/0619/06 22/06

    23/06 27/0624/06 28/06

    29/06 29/06

    30/06 03/0701/07 04/0701/07 04/07

    30/06 03/0701/07 04/0701/07 04/07

    05/07 09/0706/07 10/07

    11/07 11/07

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 7

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    311 Pembesian 4 days 12/07 15/07312 Bekisting 4 days 13/07 16/07313 Pengecoran 4 days 13/07 16/07314 Shear Wall 5 days 12/07 16/07315 Pembesian 4 days 12/07 15/07316 Bekisting 4 days 13/07 16/07317 Pengecoran 4 days 13/07 16/07318 GROUND FLOOR 7 days 17/07 23/07319 Plat dan Balok 7 days 17/07 23/07320 Bekisting 5 days 17/07 21/07321 Pembesian 5 days 18/07 22/07322 Pengecoran 1 day 23/07 23/07323 TANGGA 33 days 05/07 06/08324 Tangga Basement To LG 7 days 05/07 11/07325 Bekisting 4 days 05/07 08/07326 Pembesian 4 days 07/07 10/07327 Pengecoran 1 day 11/07 11/07328 Tangga LG To P2 7 days 17/07 23/07329 Bekisting 4 days 17/07 20/07330 Pembesian 4 days 19/07 22/07331 Pengecoran 1 day 23/07 23/07332 Tangga P2 To P1 7 days 24/07 30/07333 Bekisting 4 days 24/07 27/07334 Pembesian 4 days 26/07 29/07335 Pengecoran 1 day 30/07 30/07336 Tangga P1 To GF 7 days 31/07 06/08337 Bekisting 4 days 31/07 03/08338 Pembesian 4 days 02/08 05/08339 Pengecoran 1 day 06/08 06/08340 VICTORY PODIUM 56 days 17/05 11/07341 BASEMENT 17 days 17/05 02/06342 Plat lantai 13 days 17/05 29/05343 Chemikal Angkur D-wall 7 days 17/05 23/05344 Pembesian 7 days 20/05 26/05345 Pasang Water Stop 5 days 22/05 26/05346 Pengecoran 3 days 27/05 29/05347 Kolom 4 days 30/05 02/06348 Pembesian 3 days 30/05 01/06349 Bekisting 3 days 31/05 02/06350 Pengecoran 3 days 31/05 02/06351 LOWER GROUND 11 days 03/06 13/06352 Plat dan Balok 6 days 03/06 08/06353 Bekisting 4 days 03/06 06/06354 Pembesian 4 days 04/06 07/06

    12/07 15/0713/07 16/0713/07 16/07

    12/07 15/0713/07 16/0713/07 16/07

    17/07 21/0718/07 22/07

    23/07 23/07

    05/07 08/0707/07 10/07

    11/07 11/07

    17/07 20/0719/07 22/07

    23/07 23/07

    24/07 27/0726/07 29/07

    30/07 30/07

    31/07 03/0802/08 05/08

    06/08 06/08

    17/05 23/0520/05 26/05

    22/05 26/0527/05 29/05

    30/05 01/0631/05 02/0631/05 02/06

    03/06 06/0604/06 07/06

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 8

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    355 Pengecoran 1 day 08/06 08/06356 Kolom 5 days 09/06 13/06357 Pembesian 4 days 09/06 12/06358 Bekisting 4 days 10/06 13/06359 Pengecoran 4 days 10/06 13/06360 MEZZANINE P2 11 days 14/06 24/06361 Plat dan Balok 6 days 14/06 19/06362 Bekisting 4 days 14/06 17/06363 Pembesian 4 days 15/06 18/06364 Pengecoran 1 day 19/06 19/06365 Kolom 5 days 20/06 24/06366 Pembesian 4 days 20/06 23/06367 Bekisting 4 days 21/06 24/06368 Pengecoran 4 days 21/06 24/06369 Core Wall / Dinding 5 days 20/06 24/06370 Pembesian 4 days 20/06 23/06371 Bekisting 4 days 21/06 24/06372 Pengecoran 4 days 21/06 24/06373 MEZZANINE P1 11 days 25/06 05/07374 Plat dan Balok 6 days 25/06 30/06375 Bekisting 4 days 25/06 28/06376 Pembesian 4 days 26/06 29/06377 Pengecoran 1 day 30/06 30/06378 Kolom 5 days 01/07 05/07379 Pembesian 4 days 01/07 04/07380 Bekisting 4 days 02/07 05/07381 Pengecoran 4 days 02/07 05/07382 Core Wall / Dinding 5 days 01/07 05/07383 Pembesian 4 days 01/07 04/07384 Bekisting 4 days 02/07 05/07385 Pengecoran 4 days 02/07 05/07386 GROUND FLOOR 6 days 06/07 11/07387 Plat dan Balok 6 days 06/07 11/07388 Bekisting 4 days 06/07 09/07389 Pembesian 4 days 07/07 10/07390 Pengecoran 1 day 11/07 11/07391 Chemikal Angkur D-wall LG-GF 36 days 04/06 09/07392 Bor Dwall 35 days 04/06 08/07393 Install Besi 35 days 05/06 09/07394 RAMP 36 days 30/06 04/08395 Ramp Basement To LG 7 days 30/06 06/07396 Bekisting 4 days 30/06 03/07397 Pembesian 4 days 02/07 05/07398 Pengecoran 1 day 06/07 06/07

    08/06 08/06

    09/06 12/0610/06 13/0610/06 13/06

    14/06 17/0615/06 18/06

    19/06 19/06

    20/06 23/0621/06 24/0621/06 24/06

    20/06 23/0621/06 24/0621/06 24/06

    25/06 28/0626/06 29/06

    30/06 30/06

    01/07 04/0702/07 05/0702/07 05/07

    01/07 04/0702/07 05/0702/07 05/07

    06/07 09/0707/07 10/07

    11/07 11/07

    04/06 08/0705/06 09/07

    30/06 03/0702/07 05/07

    06/07 06/07

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 9

    Project: EMPIREDate: 15/04

  • ID Task Name Duration Start Finish

    399 Ramp LG To P2 7 days 12/07 18/07400 Bekisting 4 days 12/07 15/07401 Pembesian 4 days 14/07 17/07402 Pengecoran 1 day 18/07 18/07403 Ramp P2 To P1 7 days 22/07 28/07404 Bekisting 4 days 22/07 25/07405 Pembesian 4 days 24/07 27/07406 Pengecoran 1 day 28/07 28/07407 Ramp P1 To GF 7 days 29/07 04/08408 Bekisting 4 days 29/07 01/08409 Pembesian 4 days 31/07 03/08410 Pengecoran 1 day 04/08 04/08

    12/07 15/0714/07 17/07

    18/07 18/07

    22/07 25/0724/07 27/07

    28/07 28/07

    29/07 01/0831/07 03/08

    04/08 04/08

    S S M T W T F S S M T W T F S S M T23 Mar '15 13 Apr '15 04 May '15 25 May '15 15 Jun '15 06 Jul '15 27 Jul '15 17 Aug '15

    Task Milestone Summary Project Summary Deadline Progress

    SCHEDULE EMPIRE, VICTORY TOWER PODIUMPODOMORO CITY DELI MEDAN

    Page 10

    Project: EMPIREDate: 15/04