Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG
description
Transcript of Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG
Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG
By
Peter J H Carnell
Matthew Humphrys
Worldwide Higher Heating Value (HHV) Specifications
0123456789101112
Japan Korea USA UK France Spain
35
34
37
38
36
3940
414243
4445
46
HH
V(M
J/sm
3)
• Spot sales complicated by differences in LNG specification• Lean LNG gives more marketing flexibility
– Easier for user to add LPG than N2
Typical LNG Flowsheet
Transportation Study Results for Conventional Floating LNG (FLNG)
• Based on Qmax LNG Vessels– Length 400m, breadth 80m, displacement 550,000Te
• High Plant Utilisation Rate Required• Need Spare Storage Capacity to allow for loading
delays– LNG Storage Capacity 350,000 m3
– LPG Storage Capacity 80,000 m3
– Condensate Storage Capacity 160,000 m3
Condensate Storage LNG StorageLPG Storage
Liquefaction Plant
Machinery Space
Accommodation
Seawater intake reservoir
Fla
re t
ower
Floating LNG Hull Layout
• Comparable to the Worlds Largest Ship– Knock Nevis; Length 458m - Breadth 69m
• Larger than Very Large Crude Carriers– Length 333m - Breadth 58m
Ship to Ship LNG Transfer Time Log
Operation Duration (Hrs)
Preparation 13
Cargo Transfer 25.8
Dismantling 6.2
Total Duration 45.0
• 2 – 3 day window for transfers• Difficult operation for two huge vessels• LPG & condensate needs additional transfer equipment & operations
Issues with Higher Hydrocarbons (C2+) on FLNG
• LPG marketable, but adds complexity and reduces LNG storage (or increases vessel size)
• LPG system increases fire risk by ~30%
• C2 content of LPG limited to 2% (vapour pressure)
• Excess C2 may exceed fuel gas demand
• C2 –rich fuel gas may exceed NOx emission limit on gas turbine
• ‘Slopping’ on FLNG can create variable Boil Off Gas, hence variable Fuel Gas composition & Wobbe Number– Impact on Fuel Gas burners
Catalytic De-Richment
• Catalytic De-Richment (CDR) converts higher hydrocarbons (ethane up to naphtha) to methane
• Well established technology developed for substitute natural gas (SNG)
• Overall reactions:
4C2H6 + 9H2O 7CH4 + 7H2O + CO2
2C3H8 + 7H2O 5CH4 + 5H2O + CO2
4C4H10 + 19H2O 13CH4 + 13H2O + 3CO2
C5H12 + 6H2O 4CH4 + 4H2O +CO2
LNG Plant with Catalytic De-richment
Catalytic De-richment Reactors & reactions
Typical CDR Operating Conditions*
Component Inlet Kmol/h Exit Kmol/h
CH4 - 175
C2H6 100 -
CO2 - 25
H2O 167 116
Temp 275 °C: Press 30 bara: Steam/Carbon 0.833
* Patented catalyst
Potential Increase in LNG from Heavy Gases
Raw Gas Composition Product Gas Composition
C1
(%)
C2
(%)
C3
(%)
C4
(%)
C1
(%)
Increased C1
%+
100 - - - 100 -
95 5 - - - 9
90 5 3 2 113 26
85 10 5 - 115 35
Catalytic De-Richment
• Catalytic De-Richment (CDR) converts higher hydrocarbons to methane– Increased LNG production– Simplified FLNG design
• Well established technology • Reduces flaring where ethane in excess of fuel
gas demand• Generates constant
Wobbe number fuel gas• Lean LNG gives more marketing
flexibility 0123456789101112
Japan Korea USA UK France Spain
35
34
37
38
36
3940
414243
4445
46
HH
V(M
J/sm
3)
Mercury Distribution
J M C o n f i d e n t i a l
G l o b a l H o t S p o t s f o r M e r c u r y i n O i l a n d G a s R e s e r v e s
Why Must Mercury be Removed?
• Avoid corrosion of equipment using aluminium alloys, copper alloys and some other alloys– LME (liquid metal embrittlement)– Amalgam corrosion
• Process cheaper mercury-distressed crudes
• Avoid emissions to environment• Comply with HSE directives &
protect employees– Feb ’09 UN Environment Programme – World-wide
treaty to limit Hg exposure
LME
2004 Moomba Explosion
Losses:• Caused by LME of aluminium
heat exchanger inlet, by Hg• Leading insurers put the insured
loss at A$320million (USD245 million)
• Energy crisis in NSW & South Australia– Supplies were limited to 30-40%
capacity– Cutbacks by major industrial
customer– Job layoffs
PURASPEC Mercury Removal Technology
• Uses variable valency metal sulphide
Hg + MxSy → MxSy-1 + HgS
• Metal sulphide can be generated in situ from mixed metal oxide (patented co-removal of H2S & Hg)
• Grades for gas and liquid hydrocarbons (LPG, condensate etc)
• Can be used on saturated gas
Full Cradle to Grave Service
• Optimisation of Mercury Removal Unit (MRU) design with customer
• Data sheets and vessel drawings– Low PD radial flow designs possible
• Provision of most suitable absorbent• Supervised loading and discharge• Recycling of spent absorbent
– Absorbents are made from materials compatible with smelters
– Only audited, approved smelters used– Certificate proves environmentally safe disposal
Mercury Distribution – Gas Processing Plant Mercury Survey Results
4%
2%Multiphase
flowSeparation
Cooling/Al Heat
Exchanger
LP Compression
Amine System
Fuel Gas
<10 nanogram / Nm3
inlet specification
Export
Overboard
NGL’s
Separation
ExportRegeneration Medium
Wells
100%
2%
90%
8%
90%
25%
Amine
65%
5%20% 19%
15%
GasOil
NGL’s
WaterGlycol
Amine
Oil Storage/Export
Compression
4%
Waste Water
Molecular Sieve/Glycol Unit
Recommended location of MRU
Typical location of (carbon) MRU
Fit and Forget Technology
• Intervention only required for charging and discharging
• High mercury capacity gives long bed life
• Sharp absorption profile means bed can cope with high excursions in mercury in feed and in the flow rate of feed
FPSO SE ASIA
MRU on FPSO
Oil & Gas Platform Gulf of Thailand
Offshore MRU
Conclusions
• Catalytic De-Richment can be used to increase LNG production – Free up space for LNG storage or reduce size of vessel– Simplifies FLNG design and improves safety– Potentially reduce the need for flaring
• Mercury removal essential– Location upstream of acid gas & water removal
maximises protection of equipment, people and environment