Emerging Strategic Fortune Minerals Limited Metal & Coal ......Binder for iron ore pellets Source:...
Transcript of Emerging Strategic Fortune Minerals Limited Metal & Coal ......Binder for iron ore pellets Source:...
Emerging Strategic Metal & Coal
ProducerFortune Minerals LimitedInvestor Presentation
December 2010TSX-FT
2
FORWARD-LOOKING INFORMATIONThis document contains certain forward-looking information. This forward-looking information includes, ormay be based upon, estimates, forecasts, and statements as to management’s expectations with respect to,among other things, the size and quality of the Company’s mineral resources, progress in development ofmineral properties, timing and cost for placing the Company’s mineral projects into production, costs ofproduction, amount and quality of metal products recoverable from the Company’s mineral resources,demand and market outlook for metals and coal and future metal and coal prices. Forward-lookinginformation is based on the opinions and estimates of management at the date the information is given, andis subject to a variety of risks and uncertainties and other factors that could cause actual events or results todiffer materially from those projected in the forward-looking information. These factors include the inherentrisks involved in the exploration and development of mineral properties, uncertainties with respect to thereceipt or timing of required permits and regulatory approvals, the uncertainties involved in interpretingdrilling results and other geological data, fluctuating metal and coal prices, the possibility of project costoverruns or unanticipated costs and expenses, uncertainties relating to the availability and costs of financingneeded in the future, uncertainties related to metal recoveries and other factors. Mineral resources that arenot mineral reserves do not have demonstrated economic viability. Inferred mineral resources areconsidered too speculative geologically to have economic considerations applied to them that would enablethem to be categorized as mineral reserves. There is no certainty that mineral resources will be convertedinto mineral reserves. Readers are cautioned to not place undue reliance on forward-looking informationbecause it is possible that predictions, forecasts, projections and other forms of forward-looking informationwill not be achieved by the Company. The forward-looking information contained herein is made as of thedate hereof and the Company assumes no responsibility to update them or revise it to reflect new events orcircumstances, except as required by law.
3
FORTUNE MINERALS INVESTMENT HIGHLIGHTS 2 development stage projects in permitting stage:
NICO Gold-Cobalt-Bismuth-Copper Project, NWT & Saskatchewan 4 million equivalent gold ozs, significant cobalt & largest deposit of bismuth in world
Mount Klappan Anthracite Coal Project, British Columbia 2.8 billion tonnes metallurgical coal - One of world’s largest undeveloped deposits
NICO & Mount Klappan, both have: Positive definitive feasibility studies - >$ 1.3 billion NPV’s Successfully test mined – Deposit geometries & grades confirmed Successfully pilot plant processed – Production of high value products confirmed All commodities have significant demand growth
New Mount Klappan definitive feasibility study based on rail transport of coal to port Golden Giant Mine mill purchased & dismantled to reduce NICO CAPEX Sue-Dianne Copper-Silver-Gold deposit, 25 km north of NICO – Future mill feed Experienced board & management team Pursuing partnering options at project level to finance projects
Deloitte & Touche engaged to identify strategic partner for Mount Klappan BNP Paribas engaged to arrange US$ 250 million NICO project financing
Production of specialty metals & coal with minimal equity dilution
4Canada Focus - Operating in mining friendly jurisdictions
PROPERTY INTERESTSPROPERTY INTERESTS
Canada Focus - Operating in mining friendly jurisdictions
5
CorporateInformation
Share Performance
Listing: TSX-FT Share Price: ~$ 1.30 Issued Shares: 105.8 million Fully Diluted: 126.9 million Market Cap: ~$ 135 million Working Capital: $ 8.7 million (Q3- 2010) Total Assets: $ 127.6 million (Q3-2010)
China Mining Resources Group Ltd. ~16% Manulife Global Management US ~ 11% Officer & Director Holdings ~26% (includies China Mining)
As of December 6 2010All values in C$ unless otherwise noted
Analyst Reports
Ownership
David Davidson, Paradigm Capital Michael Fowler, Loewen Ondaatje McCutcheon
6
100% owned by Fortune Minerals
2.8 billion tonne resource – One of world’s largest undeveloped deposits of metallurgical coal
Definitive Feasibility Study demonstrates robust economics
Very well understood geology, with test mining & processing compete
New rail transportation development strategy - Simplifies project – Facilitates scalable expansion
Near term production potential – Low risk permitting – Environmental Assessment initiated
Supply shortages of metallurgical coals – Growing world consumption
Railway sub-grade links mine site with CN mainline & Ridley Terminals
MOUNT KLAPPAN ANTHRACITE COAL PROJECT HIGHLIGHTS
7
Large license area in northwest B.C. (15,866 Ha)
Close proximity to deep water shipping ports
Stewart Port (150km)
Ridley Terminals in Prince Rupert (330km)
Close proximity to Asian markets
Port of Prince Rupert 36 hours closer to Asian ports than other West Coast ports
Mine site straddles railway right-of-way
Track (CN) installed to 150km south of mine
Railway road bed largely complete to mine
Road access from railway subgrade
Feasibility study for railway expansion completed
Support of CN Railway
B.C. Government now revenue sharing with First Nations groups
STRATEGIC LOCATION & INFRASTRUCTURE
8
Mount Klappan Resources (million tonnes)(1) (3)
Lost Fox Metallurgical Coal Reserves (million tonnes)(2) (3)
(1) 2.8 billion tonne resource in all classes - estimates by Marston & Marston Inc. as of February 2007(2) 9.7 Bcm / tonne finished product strip ratio at 1.5 million tonne per year.(3) Richard Marston, PE is the Qualified Person as defined by NI 43-101
Area Measured Indicated Demonstrated Inferred SpeculativeLost Fox 107.9 109.5 217.4 91.5 749.6 Hobbit-Broatch - 13.5 13.5 258.4 753.0 Summit - - - 9.6 508.9 Nass - - - - 201.5 Total 107.9 123.0 230.9 359.5 2,213.0
In Situ Coal Reserves Measured Indicated Total In Situ
85.6 16.1 101.7
10% Ash Product ReservesProven Probable Total Product
51.6 9.2 60.8
MOUNT KLAPPAN RESOURCES & RESERVES
9
ANTHRACITE PRODUCTS & USE
Highest quality coal with very high carbon & energy content Anthracite only 1% of world coal reserves Metallurgical coal with diverse applications
Other products: Blend coal with coking coal for making metallurgical coke Direct coke replacement Heating & cooking briquettes Binder for iron ore pellets
Source: Company Information.
Filter Media US$ 350 / tonne Metallurgical Reductants / charge carbon US$ 350 / tonne Ultra-Low Vol. PCI US$ 175 / tonne Sinter US$ 150 / tonne Power Generation US$ 125 / tonne
10
World anthracite production: ~ 565 million tonnes
China: 483 million tonnes – a net importer of anthracite
Vietnam: 43 million tonnes – reduced exports with plans to utilize all production domestically
Few new high-quality deposits in mining friendly jurisdictions
Increasing demand from end markets for good quality metallurgical coals
China became a net coal importer in 2009, coking coal in 2007 & anthracite in 2004
Japan & South Korea imports increased in 2010 after financial crisis in 2009
Other emerging economies will also be the driving forces for future met. coal demand
Indian crude steel production expected to increase from 72.8 million tonnes to 124 million tonnes by 2010 & 293 million tonnes by 2020
Brazilian crude steel production expected to increase from 26.5 million tonnes to 103 million tonnes by 2030
An insufficient supply of met. coals to meet anticipated further global demand
VERY ATTRACTIVE MARKET DYNAMICS FOR ANTHRACITE / PCI
PCI produced from Mount Klappan will be very high-quality & priced at the upper range of PCI prices
11
November 2010 DFS update to 2005 & 2008 DFS
Based on railway transport of coal from mine to Ridley Coal Terminal in Prince Rupert
Initial production from Lost Fox deposit open pit mine, wash plant & site infrastructure
60.8 Mt of product coal reserves – 20+ yrs production (only 3.6% of global resource)
Production of 3 Mtpa clean coal
Premium ultra-low volatile PCI product
Can diversify product mix to produce premium products (charge carbon) & sinter
2010 DEFINITIVE FEASIBILITY STUDY (DFS) – OVERVIEW
BASE CASEUltra-Low Volatile PCI
US$175 / tonne (C$1 = US$ 0.95)
PRE-TAX AFTER TAX
IRR 25.4% 20.7%
NPV (8%) C$ 1,027.8 Million C$ 667.4 Million
Capital (Years 1-4) C$ 768.4 Million
Pre-Tax NPV (8%)In billions
$0.5 $1.0
$1.6 $2.2
$2.7 $3.3
$3.8
$-$0.5 $1.0 $1.5 $2.0 $2.5 $3.0 $3.5 $4.0 $4.5
$150 / t $175 / t $200 / t $225 / t $250 / t $275 / t $300 / t
12
EXISTING & PROPOSED RAIL TRANSPORTATION CN Main Line (green) extends between Prince George & Prince Rupert CN operates on the red shaded part of Dease Lake Line - $ 175 million upgrade for unit trains Orange shaded part of Dease Lake Line – track removed 2 years ago Blue shaded part of Dease Lake Line has railway roadbed already constructed Bright green 22 km part of Dease Lake Line – Requires construction of roadbed & 3 bridges Cost of 150 km extension to Mount Klappan estimated at $ 142.8 million – Total $ 317.8 million
Existing railway right-of-way & road bed
13
Ice-free, deepwater port capable of handling full Capesize vessels ~US$ 10/tonne reduction in ocean freight
World Class coal & bulk materials handling facility with 16 Mtpa capacity
Serviced by Provincial highway & CN Rail Main Line
Significant capacity: Currently only handling ~50% of design capacity
36 hours closer to Asian ports than port of Vancouver
Opportunities for shared cargos & blending with other metallurgical coals
RIDLEY COAL TERMINAL IN PRINCE RUPERT
14
DFS reserves only represents 3.6% of total resource
Simultaneous development of the Hobbit Broatch deposit or more rapid mining of the Lost Fox deposit would produce improved economics
Rail transportation allows for higher annual production than 3 Mtpa
Current resource only identified to 300 meters – Additional coal seams identified at depth
Increased resource potential – Marston has recommended a 4 phase drilling program
BC Government is extending the electrical grid & connection would lower power costs & enable use of lower cost mining equipment
Lease to purchase of mobile equipment fleet would result in lower upfront Capex & increased IRR
Project finance debt & off-take / trade financing expected to enhance IRR
SIGNIFIANT UPSIDE POTENTIAL BEYOND 2010 DFS
A total resource of 2.8 billion tonnes, rail directly to the mine site, & no port capacity issues allows for a very large, scalable project – potentially 6 Mtpa +
15
One of world’s largest undeveloped deposits with 2.8 billion tonne resource
Robust economics – DFS shows pre-tax NPV of $1 billion & IRR of 25.4% mining just 3.6% of total resource
Updated DFS with railway development option recently completed – Simpler & scalable transportation with superior port option
Project scalable beyond 3 Mtpa – potential for 6 Mtpa + & improved economics
Low risk permitting – Government support, no impacted fish habitats & rail subgrade is already in place
Significant work already competed - $86 million spent
Test mining & processing compete
Engineering largely complete
Environmental work very advanced
Near-term production potential
Deloitte & Touche engaged to help Fortune identify financial partner to help develop project
Confidentiality agreements executed with tier 1 companies
Expect shortlist of bidders in New Year
RECAP OF MOUNT KLAPPAN INVESTMENT CASE
16
NICO GOLD-COBALT-BISMUTH-COPPER PROJECT HIGHLIGHTS 100% Ownership – No 3rd party royalties Mine & mill in NWT
Open pit & underground mine & concentrator Saskatchewan Metals Processing Plant (SMPP)
Vertically integrated hydrometallurgical facility to produce gold doré, cobalt & copper cathodes & bismuth cathode or ingot
$ 92 million work completed to date, includes: $ 20 million test mining $ 7 million process pilot plants Aboriginal participation in all site programs
2007 positive feasibility study & 2008 update 32.3% Pre-tax IRR Pre-tax $ 361 million 8% NPV Significant recent improvements not included
31 Million tonne reserve – 4 Million eq gold ozs Golden Giant (Hemlo) buildings & equipment
purchased & dismantled to reduce CAPEX Environmental Assessments in progress for mine &
SMPP permittingTest mining 2006/2007
17
MINE LOCATION & INFRASTRUCTURE
5,140 Ha lease in southern NWT
Winter access roads
New all-weather road planned by governments to Hwy (135 km)
$18 million in place for stage 1 –realignment, bridges & roadbed
Engineering & environmental work underway
450 km from railway at Hay River for transport of concentrates to SMPP
160 km from City of Yellowknife
50 km from Town of Whati
22 km from Snare Hydro
Settled land claim with Tlicho Government
18
NICO MINERAL RESERVESUnderground Mineral Reserves Tonnes Au (g/t) Co (%) Bi (%) Cu (%)
Proven 1,403,000 2.23 0.16 0.22 0.04
Probable 767,000 2.92 0.17 0.19 0.03
Total 2,170,000 2.47 0.16 0.21 0.03
Reserve estimate by P&E Mining Consultants Inc., Eugene Puritch, P.Eng. & Fred Brown, CPG PrSciNat, Qualified Persons as defined by NI-43-101
Open Pit Mineral Reserves Tonnes Au (g/t) Co (%) Bi (%) Cu (%)Proven 15,019,000 0.85 0.12 0.16 0.04
Probable 13,797,000 0.71 0.12 0.15 0.03
Total 28,816,000 0.79 0.12 0.15 0.04
Combined Mineral Reserves Tonnes Au (g/t) Co (%) Bi (%) Cu (%)Proven 16,422,000 0.97 0.12 0.16 0.04
Probable 14,564,000 0.83 0.12 0.15 0.03
Total 30,986,000 0.91 0.12 0.16 0.04
Contained Metal 907,000 ounces
82 million pounds
109 million pounds
27 million pounds
19
DIVERSIFIED EXPOSURE TO GOLD & SPECIALTY METALS Gold: Largest source of revenue in first yr of operation – Counter cyclical hedge
Cobalt: Significant demand growth - Principal sources in politically unstable countries World consumption: ~70,000T ~ 6% annual growth Metallurgical markets: high strength alloys, cutting tools, cemented carbides &
magnets Chemical markets: lithium ion & nickel metal hydride batteries, catalysts,
agriculture & pigments Key growth areas: batteries for electronic devices & hybrid / electric vehicles,
catalysts for petroleum refining, turbines LME: Initiated trading in 2010 – Futures market
20
DIVERSIFIED EXPOSURE TO GOLD & SPECIALTY METALS Bismuth: Largest deposit in world – China principal source – supply concerns
World consumption: ~15,000T Traditional markets – fusible alloys, cosmetics, chemicals, ointments, medicines,
lubricants, electronics & flame retardants New markets – Super conductors, CD’S & auto anti-corrosion Environmentally safe (non-toxic) replacement for lead in: solder (plumbing &
electronics), hot-dip galvanizing, plumbing brasses, ceramic glazes, ammunition, radiation shielding, paint pigments & free cutting steel
MCP Group – LOI with World’s largest processor to purchase all production Copper: By-product of cobalt processing
World Consumption: ~ 18 million T Principal Markets: electronics / wire, pipe, brasses & other alloys, & coinage
21
UNDERGROUND TEST MINING & PILOT PLANT PROCESSING
Mining conditions, geometry & grades for deposit confirmed
Environmental impacts assessed
Portal, decline ramp & 2 mine levels established with ventilation raise to surface
~$20 million pre-production development completed
Large sample collected for $7 million pilot plant tests
Proved process flow sheet
Verified production of higher value metal products
Increase in metal recoveries over feasibility study
Tangible demonstration of successful project to governments & communities
Reduced project risk
22
GOLDEN GIANT MINE (HEMLO) MILL, ONTARIO Buildings, equipment & spare parts acquired from Newmont Canada Relocation to NICO for significant reduction in CAPEX & project risk No environmental liability for Hemlo site Dismantling & removal completed for net cash cost of ~$18 million
Includes ~$3.5 million in revenue from sale of surplus equipment, gold & scrap Demonstration of project execution on budget & schedule
23
Micon, Met-Chem, Golder, SGS Lakefield & metallurgical & engineering experts Open pit mine with underground mining contribution in yrs 1 & 2
Maximize gold recovery & high grades during initial production Simple flotation to produce high value concentrate
High concentration ratio – 3.8% sulphide fraction contains the valuable metals Vertically integrated hydrometallurgical plant to produce high value metal products Results:
Pre-tax IRR 32.3% Pre-tax C$361 million 8% NPV Pre-production CAPEX C$213 million Cash Cost US$1.41/lb Co (1)(2)
Cash Cost US $259/oz Au equivalent (2)
April 2008 metal price sensitivity increases IRR to 97.2% & NPV (8%) to $1.5 billion(3)
Significant recent project improvements not included in feasibility study results
2008 DEFINITIVE FEASIBILITY STUDY (DFS) UPDATE
(1) Net of credits for gold and bismuth sales
(2) Base Case metal prices of US$750/oz Au, US$20/lb Co, US$10/lb Bi and US$/C$ 0.97
(3) April 2008 metal prices of US$900/oz Au, US$50/lb Co, US$16/lb Bi and US$/C$ 0.97
24
43% increase in reserves to 31 Mt – 18 Yr mine life - Excludes results of 2010 drilling 16% production rate increase to 4,650 tpd New more efficient mine plan - Eliminated underground backfilling – More underground mill feed Identification of low strip starter pit – Eliminates pre-stripping Co-disposal of waste rock & tails – Reduces dam structures & reclamation costs Commodity price assumptions higher:
Gold US$ 900/oz Cobalt US$ 20/lb Bismuth US$ 10/lb Copper US$ 2.75/lb
Improved recoveries from pilot plant: Gold 56-84%, Averages 72% - Confirmed Cobalt 83% - Formerly 81% Bismuth 70% - Formerly 58% Copper 52% - Now included
Higher value metal products: Gold Doré Cobalt 99.8% cathode Bismuth 99.5% cathode or 99.9% ingot – Feasibility study assumed concentrate Copper 99.99% cathode – Not included in feasibility study
Hydrometallurgical process plant relocated to Saskatoon Lower OPEX (~$7 million/yr) – Mitigates CAPEX increase (~$30 million)
POST-DEFINITIVE FEASIBILITY STUDY IMPROVEMENTS
25
Hydrometallurgical plant to process NICO concentrates to high value metal products
Agreement to purchase lands near Saskatoon Located on CN Rail line Close to Trans-Canada Hwy Inexpensive power (5.7 cents/kWh) Close to natural gas & water Close to reagent sources Skilled worker / engineer pool – 85 employees
High concentration ratio of NICO ores produces only 180 tonnes of concentrate / day for delivery to SMPP
SMPP CAPEX ~ $225 million
SASKATCHEWAN METAL PROCESSING PLANT (SMPP)
NICO
Saskatoon
CN Rail Canadian Route Map
26
2010 NICO DRILL PROGRAM 37 new drill holes completed in 2010 to extend deposit & better delineate limits
Particular emphasis on extending gold-rich central core to depth Drilling very successful in expanding deposit & intersecting high-grade gold intervals:.
51.3m averaging 2.2 g/t Au & 0.11% Co, including 3m averaging 15.59 g/t Au, 0.46% Co, 0.05% Bi & 0.20% Cu in NICO 10-300;
8.00m averaging 4.74 g/t Au & 0.16% Bi, including 1m grading 35 g/t Au in NICO 10-325; 3.38m averaging 11.59 g/t Au, 0.37% Co, 0.16% Bi & 0.14% Cu, including 1.67m averaging 20.04
g/t Au, 0.36% Co, 0.24% Bi & 0.13% Cu in NICO 10-324; 5.00m averaging 4.84 g/t Au, including 2.5m averaging 9.21 g/t Au in NICO 10-327; 20.1m averaging 0.38% Co & 0.37% Bi in NICO 10-292
27
Average Annual Metal Production: Gold: yrs 1&2 of mine life: ~66,400 ozs, yrs 3-18 of mine life: ~31,500 ozs Cobalt: ~3.4 million lbs (1,550 tonnes) Bismuth: ~ 3.65 million lbs (1,650 tonnes) Copper: ~ 770,000 lbs (350 tonnes)
Average revenue: ~$100/T, $170 million/yr Revenues higher in early years of production
Average cost: ~$60/T, $102 million/yr Improvements increase project revenues – CAPEX will be higher Front End Engineering & Design Studies by Aker Solutions & other engineering companies
Revised capital & operating costs Q1 2011 BNP Paribas engaged to arrange US$ 250 million for project financing
Indicative term sheet with 70:30 debt equity split Environmental Assessments for mine & SMPP in progress for permitting Production targeted in 2013 Examining options for Fortune’s contribution to project financing
Off-take relationships, minority partners, gold or cobalt sales, equity
CURRENT STATUS OF NICO PROJECT
28
STRATEGY FOR SHAREHOLDER VALUE RECOGNITION Market Capitalization: ~$ 135 Million:
undervalues 2 major projects with feasibility NPV’s collectively > $ 1.3 Billion, $ 8.7 million working capital & ~$ 40 million(1) in Hemlo equipment
Joint venture Mount Klappan with strategic partner: Deloitte engaged to find development partner Simplifies corporate focus, values project, resolves financing challenges & brings financial
& marketing expertise Permitting initiated for potential production in 2014
Development of NICO: BNP Paribas engaged to arrange US$ 250 million project debt facility Indicative term sheet 70:30 debt to equity with credit for capital already spent Options for 30% equity share - Strategic minority partner, equity, forward metal sales In permitting for planned production in 2013
JV Strategy minimizes future equity dilution Investor recognition of Fortune’s world class Canadian development assets with minimal
equity dilution
(1) Company estimate of value to NICO Project
29
DirectorsGeorge Doumet, MSc, MBA Chairman, Director Chemical Engineer – President & CEO, Federal White Cement
Robin Goad, MSc, Pgeo President & CEO, Director Geologist - 29 yrs mining & exploration experience
David Knight, BA, LLB Secretary, Director Partner, Macleod Dixon specializing in securities & mining law
James Excell, BASc Director Metallurgical Engineer – 35 yrs mining experience BHP-Billiton
William Breukelman, BASc, MBA, Peng Director Chemical Engineer – Chairman, Gedex
Mahendra Naik, B Comm, CA Director CFO Fundeco - Founding director & former CFO, IAMGOLD
James Currie, BSc (Hons), PEng Director Mining Engineer – Executive Vice President & COO, New Gold
The Honorable Carl L. Clouter
Shou Wu (Grant) Chen, MSc, MBA
Director
Director
Commercial pilot - former owner of charter airline in NWT
Geologist – Deputy Chairman & CEO, China Mining Resources Group
ManagementJulian Kemp, BBA, CA VP Finance & CFO Chartered Accountant – 22 yrs mining financial experience
Thomas Rinaldi, BSc VP Operations Mining Engineer – 27+ yrs engineering & operations experience
Michael Samuels, BEng
Jared Orynik, BSc, PEng
Director Technical Services
Senior Metallurgist
Chemical Engineer – 15+ yrs experience in mineral process industry
Metallurgical Engineer – 7 yrs experience with Teck
Dr. Richard Schryer, PhD
Adam Jean, HBA, CA
Director Regulatory & Environmental AffairsController
Aquatic Scientist – 21 yrs experience in mine permitting & environmental assessmentsChartered Accountant previously with Ernst & Young
James Mucklow, MESc, PEng
Pat Moloney, BSc, Bed
Manager Env.& Community
Manager Human Resources
Geological Engineer – 21 yrs geological & environmental experience
12 yrs human resources experience
Emerging Strategic Metal & Coal
ProducerFor further information, please contact:
Robin Goad, President & Chief Executive OfficerLindsay Simmons, Investor Relations Coordinator
140 Fullarton Street, Suite 1902London, Ontario, Canada
N6A 5P2Tel. (519) 858-8188Fax. (519) 858-8155
E-mail. [email protected]. www.fortuneminerals.com
TSX-FT