Emerging Rapid Capping Technology To Mitigate...
-
Upload
truongtram -
Category
Documents
-
view
217 -
download
2
Transcript of Emerging Rapid Capping Technology To Mitigate...
1 © 2016 Halliburton. All rights reserved.
Andy Cuthbert Global Engineering & Technology Manager
Boots & Coots
Guy Fox Senior Product Manager
Boots & Coots
Emerging Rapid Capping Technology To Mitigate Effects of Catastrophic Subsea
Loss of Well Control
2 © 2016 Halliburton. All rights reserved.
“Prevention is Better than Cure”
vulneratam quaerere remedium”
“Melius [est] in tempore occurrere, quam post causam
Loss of Life
Loss of Asset
Environmental Damage, Cost of Clean up
– sea and land
Cost of support services – dispersant,
rig(s), ROV, FPSO, drilling support
Lost Production Revenue
Fines and Compensation Payments
Reputation in the Court of Public Opinion
3 © 2016 Halliburton. All rights reserved.
Uncontrolled release invariably has
potentially catastrophic consequences.
Emergency
response involves
safety, logistic
and risk factors.
Rapid mobilization of equipment.
Time - the most significant factor in
mitigating hydrocarbon escape to surface.
4 © 2016 Halliburton. All rights reserved.
Sequence of Events
Incident
Incident +2 days: ROV site survey
Incident +3 days: Incident Command in place
Incident +17 days: Containment dome, failed due to hydrate formation
Incident +18 days: Junk shot – failed.
Incident +26 days: Relief well spudded.
Incident +39 days: Attempted top kill fails. Move to Top Hat containment.
Incident +84 days: 3 ram capping stack installed.
Incident +87 days: Well successfully capped.
Incident +107 days: Well successfully killed via relief well.
5 © 2016 Halliburton. All rights reserved.
TIME is of the
essence
6 © 2016 Halliburton. All rights reserved.
To fulfil the requirement to plans as mentioned in the fourth subsection, the NORSOK D-010 standard, Chapters 4.8 should be used, with the following additions:
a) the plans should describe the need for and availability of facility(ies) and services,
b) plans for relief well drilling and capping operations that require modifications of facility(ies),
use of additional equipment, vessels or new technology, should detail how this can be mobilised and operative prior
to start-up of the operation that requires this.
For the U.S. Gulf of Mexico (GOM), it is mandatory for Operators conducting subsea drilling
operations to demonstrate access to a subsea capping stack and the necessary expertise and assets
to mobilize and install the stack offshore.
“Evaluate subsea capping stack components that can accommodate weight savings… using gate valves instead of BOP rams... The gate valves can provide the same pressure
rating as BOP rams…benefits associated with the use of gate valves include improved sealing reliability (metal-metal
sealing surface), reduction in weight, and simplified operation, thereby avoiding the need for Subsea Accumulator
Module (SAM) units.
Because of the geographic distances between subsea capping stack storage locations and potential incident sites, it
is recommended that a specific subsea capping stack should be identified prior to the commencement of
operations… and the associated mobilization planning that is conducted to determine the estimated response time.
This process would allow for the assessment of an estimated response time to ensure that it is acceptable… to identify areas for efficiency improvement related to deployment and installation.” Wood Group Kenny Subsea Capping Stack
Technology Requirements Final Report for BSEE: 100124.01-DG-RPT-0004 | Rev 0 | February 2016
The Australian oil and gas industry is committed to having world-class capability to respond
rapidly and effectively to offshore subsea well control incidents. The… industry’s intervention and response capacity, including a capping stack system, will be called on immediately in the event of an offshore
well control incident. Time to mobilize a global capping stack is anticipated to be 9 - 11 days.
7 © 2016 Halliburton. All rights reserved.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
12 day transit at 13.5 knots
No suitable vessels available locally
No suitable vessels available locally
13 day transit at 13.5 knots
No suitable vessels available locally
No suitable vessels available locally
16 day transit at 13.5 knots
1.75 day marine transit
1.75 day marine transit
1.75 day marine transit
CommentTime (Days)
Region SystemPort of
MobType of transport Stage
East
Coast
Canada
Sta
va
ng
er
Airfreight 747
OS
RL
15
k S
tack
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Mob at Storage Location
Vessel Transit to incident Site
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Marine
Airfreight 747
Airfreight AN-124
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Airfreight AN-124
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Re
qu
ire
d
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Ho
ust
on
Re
qu
ire
d
Ho
ust
on
Airfreight 747
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Mexican
Gulf OS
RL
15
k S
tack
Sta
va
ng
er
MarineMob at Storage Location
Vessel Transit to incident Site
Airfreight 747
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Persian
Gulf
OS
RL
10
k S
tack
Sin
ga
po
re
MarineMob at Storage Location
Vessel Transit to incident Site
Airfreight 747
Airfreight AN-124
Mob at Storage Location
Aircraft Transit to incident Site
Mob at Incident dock
Vessel Transit to Incident Site
Re
qu
ire
d
Ho
ust
on
Marine
Mob at Storage Location
Mob at Incident dock
Vessel Transit to Incident Site
7 aircraft w/ staggered arrival / departure / arrival
3 aircraft w/ staggered arrival /departure / arrival
7 aircraft w/ staggered arrival / departure / arrival
3 aircraft w/ staggered arrival /departure / arrival
2 aircraft w / staggered arrival / departure / arrival
2 aircraft w / staggered arrival / departure / arrival
7 aircraft w/ staggered arrival / departure / arrival
3 aircraft w/ staggered arrival /departure / arrival
8 © 2016 Halliburton. All rights reserved.
25 (400T) crane vessels available globally
Seven Borealis
Lewek Constellation
Sapura 3000
Seven Polaris
Lewek Champion
HOS Iron Horse
Normand Oceanic
Seven Seas
Seven Waves
Skandi Acergy
Aker Wayfarer
AKOFS Seafarer
Boa Sub C
Ceona Amazon
Construction Support
Vessel 108
Deep Blue
Giant II
Hai Yang Shi You 286
Lewek Connector
Normand Vision
North Sea Atlantic
North Sea Giant
Seven Rio
Skandi Arctic
Lay Vessel North
Ocean 105
9 © 2016 Halliburton. All rights reserved.
10 © 2016 Halliburton. All rights reserved.
CURRENTLY: Heavy, unwieldy ram-based equipment
REQUIRE: Mobility – 40 ton valve-based capping stack
CURRENTLY: Heavy, unwieldy ram-based equipment -weighing
in at 120 tons or more – rapid deployment using readily
available crane capacity, is precluded. Pre-loaded flatbed trucks
require road permits for loads of this weight.
REQUIRE: Mobility – 40 ton capping stack, housed at a
dedicated bonded facility, which means it already has Customs
clearance for shipping. The destination airport CURRENTLY:
Hydraulic ram based system that requires a full subsea
accumulator package, Time taken to rebuild and retest ram-
based capping stack under API RP 53
CURRENTLY: Ram-based system requires a full subsea accumulator package; retest under API RP 53
REQUIRE: Gate valve based system, ROV manipulated, retest under API RP 17W
CURRENTLY: Hydraulic ram based system requires a full subsea accumulator package; time taken to rebuild and retest ram-based capping stack under API RP 53
REQUIRE: Gate valve based system, ROV manipulated, less time to rebuild a modular system and retest under API RP 17W CURRENTLY Air Mobility: +8 x Boeing 747 or +3 x Antonov flights(@ $1mm/flt) REQUIRE: Reduced number of airlifts – maximum two for landing / take off rights and scheduling
CURRENTLY: Limited number of port facilities with loading capability for 250 ton structures REQUIRE: Access to a wider range of ports, especially in remote areas. Crane support for a lighter valve-based device is far less demanding of port facilities.
CURRENTLY: Limited number of port facilities with capacity REQUIRE: Access to a wider range of ports.
GAP Analysis
11 © 2016 Halliburton. All rights reserved.
CURRENTLY: Inherent design restriction with elastomer seals (with a closing time constraint).
REQUIRE: Erosion resistance metal to metal seals vs elastomer sealing element (requires closing time constraint).
CURRENTLY: Elastomer seals (with a closing time constraint). REQUIRE: Erosion resistance metal to metal seals.
CURRENTLY: Restricted vessel of opportunity with crane capacity; Limited number of vessels of opportunity that have 250 ton crane capacity. REQUIRE: Greater access to available vessels by a less demanding crane requirement. Access to software for real time updates of available vessels of opportunity and supplementary equipment as required.
CURRENTLY: Restricted vessel of opportunity. REQUIRE: Greater access to available vessels. CURRENTLY: Weather limits for deploying a 120 ton device overboard REQUIRE: A lighter device that can sustain more extreme sea state conditions, therefore widening the operational weather window.
CURRENTLY: Weather limitations for deployment. REQUIRE: A wider operational weather window. CURRENTLY: No ancillary subsea dispersant support REQUIRED: The means to tie into a subsea manifold for ROV dispersant deployment, as part of the response package.
CURRENTLY: No ancillary subsea dispersant support REQUIRED: Subsea manifold for ROV dispersant deployment.
SPH and CFD support for specific subsea scenarios, metocean conditions and full fluid dynamic interface available for real time capping coordination.
GAP Analysis
12 © 2016 Halliburton. All rights reserved.
Summary – Complete Package
Combination of debris clearance, capping equipment and dispersant deployment:
Truly air Mobile Capping Stack (maximum two aircraft)
BOP Intervention support equipment
Dispersant application support systems
Debris Removal equipment
Containment support equipment
Topside Separation equipment*
Well Kill Equipment
Logistics support
13 © 2016 Halliburton. All rights reserved.
Emerging Rapid Capping Technology To Mitigate Effects of Catastrophic Subsea
Loss of Well Control
Guy Fox Senior Product Manager
Boots & Coots
Andy Cuthbert Global Engineering & Technology Manager
Boots & Coots