EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced...

27
EMC Test Report for David Filmer Limited FLOCKMAN

Transcript of EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced...

Page 1: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC Test Report

for

David Filmer Limited

FLOCKMAN

Page 2: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

UKAS Accredited EU Notified Body

FCC & VCCI Registered BSMI Lab ID: SL2-IN-E-3008

EMC TEST REPORT No. 07R297 CR

Issue#1: 28th August 2007

Tel. +44 (0) 23 8027 1111 Fax. +44 (0) 23 8027 1144

e mail. [email protected] www.hursley-emc.co.uk

Hursley EMC Services Ltd. Unit 16, Brickfield Lane Chandlers Ford Hampshire. UK. SO53 4DP 1871

EMC Test Report

for

David Filmer Limited

FLOCKMAN

Project Engineer: R. P. St John James

Approval Signatory

Approved signatories: S. M. Connolly I. P. Kenney J. A. Jones

The above named are authorised Hursley EMC Services engineers.

Page 3: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 2 of 26

Contents

1.0 OVERVIEW ........................................................................................................................................................3 1.1 INTRODUCTION ..................................................................................................................................................3 1.2 OBJECTIVE .........................................................................................................................................................3 1.3 PRODUCT MODIFICATIONS.................................................................................................................................3 1.4 CONCLUSION .....................................................................................................................................................3 1.5 TEST DEVIATIONS..............................................................................................................................................3 1.6 EMC TEST LAB REFERENCE..............................................................................................................................3 1.7 EMISSIONS CLASS A STATEMENT (ADVISORY) ..................................................................................................3 1.8 TEST SUMMARY.................................................................................................................................................4

2.0 EQUIPMENT & TEST DETAILS.....................................................................................................................5 2.1 GENERAL ...........................................................................................................................................................5 2.2 EUT DESCRIPTION.............................................................................................................................................5 2.3 EUT TEST EXERCISER .......................................................................................................................................6 2.4 EUT TEST CONFIGURATION ..............................................................................................................................6 2.5 EUT SUPPORT....................................................................................................................................................6 2.6 ENVIRONMENTAL TEST CONDITIONS.................................................................................................................7 2.7 EMC TEST EQUIPMENT .....................................................................................................................................7

3.0 EMISSION RESULTS........................................................................................................................................8 3.1 RADIATED DISTURBANCE ..................................................................................................................................8 3.2 CONDUCTED DISTURBANCE.............................................................................................................................10 3.3 MAINS HARMONICS .........................................................................................................................................12 3.4 MAINS VOLTAGE FLICKER...............................................................................................................................13

4.0 IMMUNITY RESULTS....................................................................................................................................14 4.1 PERFORMANCE CRITERIA.................................................................................................................................14 4.2 ELECTROSTATIC DISCHARGE ...........................................................................................................................15 4.3 RADIATED RF INTERFERENCE..........................................................................................................................17 4.4 FAST TRANSIENT BURSTS ................................................................................................................................18 4.5 SURGE..............................................................................................................................................................19 4.6 CONDUCTED RF FIELD.....................................................................................................................................20 4.7 VOLTAGE DIPS & INTERRUPTIONS...................................................................................................................21

5.0 PHOTO LOG.....................................................................................................................................................22

Page 4: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 3 of 26

1.0 OVERVIEW

1.1 Introduction The Equipment Under Test (EUT), as described within this document, was submitted for EMC testing as agreed with the customer.

1.2 Objective The purpose of the test was to measure and report the EUT against limits and methods of the emissions and immunity standards, as requested for and listed in section 1.8 Test Summary.

1.3 Product Modifications None.

1.4 Conclusion The EUT met the emission limits and immunity requirements of the tests defined in section 1.8 Test Summary.

This report relates to the sample tested and may not represent the entire population. It is valid only for the product identified, either in part or in full, to the relevant electromagnetic requirements necessary for compliance with the EMC Directive 2004/108/EC and other national requirements.

1.5 Test Deviations None.

1.6 EMC Test Lab Reference Hursley EMC Services file: 07R297.

1.7 Emissions Class A Statement (advisory) The product and/or the product’s documentation should carry the following warning:

WARNING

This is a Class A product. In a domestic environment this product may cause radio interference in which case the user may be required to take adequate measures.

Page 5: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 4 of 26

1.8 Test Summary The EUT complies with the test standard EN 61326:1997, including amendments A1:1998, A2:2001 & A3:2003, for electrical equipment for measurement control and laboratory use and Table 1 (minimum) immunity tests requirements, to the performance criteria relating to equipment that is used in a continuous unmonitored operation.

The EUT met the emission test requirements of the following standards:

Description General Standard Referenced Standard Radiated disturbance

Conducted disturbance, ac port

EN 61326:1997 inc A1:1998, A2:2001

& A3:2003 CISPR 22:1993, Class A

Mains harmonics - EN 61000-3-2:2000

Mains voltage flicker - EN 61000-3-3:1995

The EUT met the immunity test requirements of the following standards:

Description General Standard Referenced Standard Electrostatic discharge EN 61000-4-2:1995

Radiated RF interference EN 61000-4-3:1996

Fast transient bursts EN 61000-4-4:1995

Surge EN 61000-4-5:1995

Conducted RF field EN 61000-4-6:1996

Voltage dips and interruptions

EN 61326:1997 inc A1:1998, A2:2001

& A3:2003

EN 61000-4-11:1994 The uncertainty measurement for each test has been included to support a level of confidence of approximately 95%.

Page 6: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 5 of 26

2.0 EQUIPMENT & TEST DETAILS

2.1 General Product (EUT): FLOCKMAN Serial number: 001 (designated by Hursley EMC Services)

Product build level: Production sample

Product manufacturer: David Filmer Limited

Customer: Mr D Filmer David Filmer Limited Wascelyn Brent Knoll Somerset TA9 4DT +44 (0) 1278 760760

Test commissioned by: Mr D Filmer

Date EUT received: 3rd August 2007

Test date(s): 3rd – 6th August 2007

EMC measurement site(s): Hursley EMC Services Limited • Unit 16, Brickfield Lane, Chandlers Ford, Hampshire • Hursley Park, Winchester, Hampshire

2.2 EUT Description FLOCKMAN is an Automated control system for poultry production. Extract from customer’s literature: FLOCKMAN has been designed for the individual broiler grower to give similar benefits to the old more sophisticated product FLOCKMAN that is aimed primarily at the larger integrated broiler company. Although it controls lighting programs (with dawn/dusk dimming), whole cereal inclusion and automatic meal-time feeding for each day, it needs no computers nor automatic feed or bird weighers. Once started at the beginning if the crop, it needs no further input from the grower until after the house is empty, when it is stopped.

Page 7: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 6 of 26

2.3 EUT Test Exerciser The volt free contact for Auger Cereal turns on once every 60 seconds for 10 seconds, a mains powered light bulb was connected to this input to indicate the contact was opening and closing. The display (LCD) cycles indicating Target Cereal Feed (15.0%) followed by actual feed (15.0 to 15.3%) then “Light off Pans On”, this repeated every 10 seconds.

2.4 EUT Test Configuration

2.5 EUT Support Balluf Proximity Sensor, s/n EMC002

HEMCS light and breakout box, s/n EMC003

Mains

EUT

Proximity Sensor

Mains

HEMCS Breakout

box

Lamp

Page 8: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 7 of 26

2.6 Environmental Test Conditions Temperature 23-24º Celsius

Relative Humidity 42-50%

Atmospheric Pressure 1000-1020 millibars

2.7 EMC Test Equipment

#ID Manufacturer Type Serial Nø Description Calibration status

003 Rohde Schwarz ESH-3 872994/027 Test receiver 9kHz-30MHz Calibrated 006 HP 8568B 2841A04350 Spectrum analyser Calibrated 013 Chase CB/6121A 1012 yel Bilog Internal 030 KeyTek MZ-15/EC 9205380 ESD Minizap /pink Calibrated 050 HP 8447D 1937A02341 Pre-amp 30-1000MHz Calibrated 066 Voltech PM3000A 7652 Harmonics & flicker analyser Calibrated 066a Voltech IEC 555 AM77/7652 Reference Z for 066 Calibrated 068 EM CWS500C 1001-07 Conducted immunity simulator Calibrated 068a EM ATT6/75 1001-11 6dB 75W attenuator Calibrated 092 Schwarzbeck VULB 9163 232 (grey) 30-3000MHz Trilog antenna Calibrated 117 KeyTek EMC Pro 9711274 Immunity tester Calibrated 118 KeyTek Pro CCL 9711291 Capacitive clamp Calibrated 120 Kalmus 7250LC-CE 8672-1 RF Power amp & pulse opt. Internal 125 Rohde Schwarz SMHU 828875/018 Signal generator 0.1-4230MHz Calibrated 145 Bird 4421/4022 4624/0103 Power meter & probe (145a) Calibrated 147 Rohde Schwarz ESH3 Z5 846695/011 AMN - single phase Calibrated 158 Rohde Schwarz ESH3Z2 357881052 Pulse Limiter Calibrated 166 Oregon Sci BA-888 - Electronic barometer Calibrated 235 MEB M3 13-214 3W 16A CDN Calibrated 241 Rohde Schwarz ESVP 879962/049 Test receiver 30-1300MHz Calibrated

Note: ‘Calibration status’ means that the instrument is certified with a UKAS or traceable calibration certificate. ‘Internal’ denotes regular internal calibration against HEMCS procedures.

Page 9: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 8 of 26

3.0 EMISSION RESULTS

3.1 Radiated Disturbance

3.1.1 Data A profile scan was taken at a distance of three metres on eight azimuths of the EUT in both the vertical and horizontal polarities of the antenna in a semi-anechoic chamber.

Using the data obtained from the chamber profile-scan as an engineering guide, the EUT was then transferred onto the turntable in the Open Area Test Site. The antenna was positioned at a distance of ten metres from the periphery of the EUT. Radiated emissions were then systematically maximised by revolving the EUT and adjusting the antenna in polarity and height. The highest emissions are presented here.

Emission frequency

(MHz)

Antenna polarity

Measured quasi-peak value

(dBµV/m)

Class A specified quasi-peak limit

(dBµV/m) Status

40.245 Vertical 16.9 40 Pass 46.750 Vertical 21.4 40 Pass 53.448 Vertical 16.4 40 Pass 54.405 Vertical 21.7 40 Pass 55.931 Vertical 17.3 40 Pass 121.154 Vertical 16.1 40 Pass 177.687 Vertical 21.7 40 Pass 194.177 Vertical 16.9 40 Pass 230.861 Horizontal 22.8 47 Pass 626.428 Vertical 29.3 47 Pass

Uncertainty of measurement: +/-4.2dBµV for a 95% confidence level.

The measurements reported are the highest emissions relative to the CISPR 22 Class A limits and take into account the antenna and cable loss factors. Measurements made according to the CISPR 22 test standard and Hursley EMC Services test procedure RAD-01.

TEST ENGINEER: Stephen Connolly

Page 10: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 9 of 26

3.1.2 Profile

Peak trace profile with quasi-peak values ( )

Final Measurement

30 40 50 60 70 100 200 300 400 500 600 800 10000

10

20

30

40

50

60

70

80

Frequency MHz

dB µ

volts

CISPR A

07FF297(03)_01 2007/08/06 Customer :DAVID FILMER LIMITEDNormalized to:10m

Page 11: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 10 of 26

3.2 Conducted Disturbance

3.2.1 Data

A filtered 230V/50Hz supply was fed to the EUT via a 50Ω/50µH Artificial Mains Network (AMN). The AMN was bonded to a conductive ground plane. Line and neutral phases and each power supply were measured separately.

A spectrum analyser was set to scan between 0.15MHz and 30MHz to record the peak emission profiles. The worst-case peaks were then measured using an average and/or quasi-peak receiver and compared to the CISPR 22 Class A limits. The worst-case results from both power supplies are shown here.

MAINS - NEUTRAL

Frequency (MHz)

Quasi-peak value (dBµV)

Average value (dBµV) Status

Measured Class A Limit

Measured Class A Limit

12.010 33.4 73.0 32.2 60.0 Pass 13.956 39.1 73.0 37.6 60.0 Pass 14.741 38.4 73.0 36.4 60.0 Pass

MAINS - LINE

Frequency (MHz)

Quasi-peak value (dBµV)

Average value (dBµV) Status

Measured Class A Limit

Measured Class A Limit

0.154 20.2 79.0 17.2 66.0 Pass 0.302 25.3 79.0 20.3 66.0 Pass

14.357 32.6 73.0 24.9 60.0 Pass

Uncertainty of measurement: +/-3.22dBµV for a 95% confidence level.

Measurements made according to the CISPR 22 test standard and Hursley EMC Services test procedure CON-02.

TEST ENGINEER: Rob St John James

Page 12: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 11 of 26

3.2.2 Profile

Shown here is the mains-neutral plot.

Conducted Emissions

07CE0297_02 2007/08/03 Customer :DAVID FILMER LIMITED

0.1 0.2 0.3 0.4 0.7 1 2 3 4 5 6 10 20 300

10

20

30

40

50

60

70

80

90

100

Frequency MHz

dB a

bove

1 m

icro

v olt/

m

CISPR "A" QP

CISPR "A" Av

Page 13: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 12 of 26

3.3 Mains Harmonics

Uncertainty of measurement: +/-5.8% for a 95% confidence level. Measurements made according to the EN 61000-3-2 standard and Hursley EMC Services procedure HAR-01.

TEST ENGINEER: Andy Jones

Page 14: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 13 of 26

3.4 Mains Voltage Flicker

Uncertainty of measurement: +/-3.8% for a 95% confidence level. Measurements made according to the EN 61000-3-3 standard and Hursley EMC Services procedure FLK-01.

For voltage changes caused by manual switching, the equipment is deemed to comply without further testing if the maximum RMS input current including inrush current is evaluated over each 10mS half-period between zero-crossings does not exceed 20 amps, and the supply current after inrush is within a variation band of 1.5 amps.

Inrush current measurements were made in real time and the product state was altered and the load current unmonitored and the inrush was less than 20 amps and the variation was less than 1.4 amps therefore it complies without testing.

TEST ENGINEER: Andy Jones

Page 15: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 14 of 26

4.0 IMMUNITY RESULTS

4.1 Performance Criteria

General performance criteria for immunity testing are defined below:-

Criterion A During testing normal performance within the specification limits.

Criterion B During testing, temporary degradation, or loss of function or performance which is self-recovering.

Criterion C During testing, temporary degradation, or loss of function or performance that requires operator intervention or system reset occurs.

Criterion D Degradation or loss of function, which is not recoverable due to damage to equipment, components, software, or to loss of data.

The test standard (EN 61326:1997 / A1/A2/A3) requires the “manufacturer” to produce a ‘functional description and a definition of performance criteria’ applicable to these EMC tests. The customer has defined “Unacceptable performance criteria” as a deviation of more than +/-1% for the analogue resistor values and the reference value. Other failure conditions are determined by interpretation using the experience of the laboratory EMC engineers.

Monitoring of EUT performance whilst under test

Radiated immunity: Remote monitoring of the product in the anechoic chamber using a video camera focused on the EUT display and a fibre-optic linked video monitor situated in the control room.

All other tests: Visual monitoring of the EUT display and light one zero volt contact to verify correct function and status.

Page 16: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 15 of 26

4.2 Electrostatic Discharge TEST METHOD

EN 61000-4-2 REFERENCING PROCEDURE: ESD-03

TEST DETAILS Test severity, contact discharge Test severity, air discharge

±4.0 kV, 50 strikes per point. Total of 200 strikes (minimum). ±8.0 kV, 10 strikes for each selected point

Exerciser program during test

Referencing section 2.3

Specified test criterion

Criterion ‘B’ (continuous unmonitored operation)

EUT performance criterion

Criterion ‘A’

RESULTS

Contact, Indirect SPECIFIED VOLTS REFERENCE PLANE @ 10CM STATUS

± 4.0 kV Horizontal and vertical; front, rear and sides PASS

Contact, Direct to EUT SPECIFIED VOLTS TEST POINTS STATUS

± 2.0 & 4.0 kV • All sides of chassis • Ready/not ready indicator housings PASS

Air Discharge (Insulating, Slots & Apertures) SPECIFIED VOLTS TEST POINTS STATUS

± 2.0, 4.0 & 8.0 kV • Interface cable insulation • LCD screen and bezel • Keypad and switches

PASS

UNCERTAINTY: It has been demonstrated that the ESD simulator met the specified requirements in the standard with at least a 95% confidence.

COMMENT: Contact discharge to the front panel caused the display information to corrupt; the bottom line would be copied onto the top line and would stay there until the CE/C button was pressed. Otherwise the test routine operated normally.

TEST ENGINEER: Andy James

Page 17: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 16 of 26

4.2.1.1 Electrostatic Discharge, Test Points

Contact discharge Air discharge

Page 18: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 17 of 26

4.3 Radiated RF Interference TEST METHOD

EN 61000-4-3 REFERENCING PROCEDURE: RES-02

TEST DETAILS Test severity levels

• 3.0 V/m • 80% amplitude modulation, 80 to 1000 MHz • 1% Steps, 3s dwell

Exerciser program during test

Referencing section 2.3

Specified test criterion

Criterion ‘A’ (continuous unmonitored operation)

EUT performance criterion

Criterion ‘A’

RESULTS

TEST POINTS ANTENNA POLARITIES FIELD LEVEL SWEPT FREQUENCY STATUS

Front Horizontal & vertical 3.0 V/m PASS Side, left Horizontal & vertical 3.0 V/m PASS Side, right Horizontal & vertical 3.0 V/m PASS Rear Horizontal & vertical 3.0 V/m PASS

UNCERTAINTY: The field level has been applied at level higher than that specified to give a greater confidence that the EUT meets the specified level.

COMMENT: The EUT met the specified test criterion.

TEST ENGINEER: Stephen Connolly

Page 19: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 18 of 26

4.4 Fast Transient Bursts TEST METHOD

EN 61000-4-4 REFERENCING PROCEDURE: FTB-01

TEST DETAILS Test severity

+/- 1.0kV AC Mains Port

5/50ns Tr/Td 5kHz Repetition Rate

Exerciser program during test

Referencing section 2.3

Specified test criterion

Criterion ‘B’ (continuous unmonitored operation)

EUT performance criterion

Criterion ‘A’

RESULTS

Direct Injection

PORT TEST VOLTAGE STATUS AC power port and “volt free contact” port +/- 1 kV PASS

UNCERTAINTY: It has been demonstrated that the transient simulator met the specified requirements in the standard with at least a 95% confidence.

COMMENT: When the transients were applied to the proximity sensor cable, the LCD display would change, sometimes to dart squares, sometimes to the main menu. Pressing the CE/C button cleared the fault. Otherwise the test routine operated normally.

TEST ENGINEER: Andy Jones

Page 20: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 19 of 26

4.5 Surge TEST METHOD

EN 61000-4-5 REFERENCING PROCEDURE: SUR-02

TEST DETAILS Test severity level

• +/- 0.5kV Line to Line • +/- 1kV Line to Earth Phase Angles: 0, 90, 270 degrees 1.2/50us Tr/Td 60s event intervals

Exerciser program during test

Referencing section 2.3

Specified test criterion

Criterion ‘B’ (continuous unmonitored operation)

EUT performance criterion

Criterion ‘A’

RESULTS TEST VOLTAGES COUPLING MODES STATUS

+500V Line to Line (AC port and “volt free contact” port) PASS -500V Line to Line (AC port and “volt free contact” port) PASS

+1kV Line to Earth (AC port and “volt free contact” port) PASS -1kV Line to Earth (AC port and “volt free contact” port) PASS

UNCERTAINTY: It has been demonstrated that the surge simulator met the specified requirements in the standard with at least a 95% confidence.

COMMENT: No performance degradation was observed. The EUT met the specified test criterion.

TEST ENGINEER: Andy Jones

Page 21: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 20 of 26

4.6 Conducted RF Field TEST METHOD

EN 61000-4-6 REFERENCING PROCEDURE: CES-02

TEST DETAILS Test severity level

3.0V rms, 80% amplitude modulation 0.15 to 80 MHz

Exerciser program during test

Referencing section 2.3

Specified test criterion

Criterion ‘A’ (continuous unmonitored operation)

EUT performance criterion

Criterion ‘A’

RESULTS TEST VOLTAGE TEST POINTS COUPLING METHOD STATUS

3.0V AC port and “volt free contact” port CDN PASS

UNCERTAINTY: It has been demonstrated that the conducted immunity simulator met the specified requirements in the standard with at least a 95% confidence.

COMMENT: No performance degradation was observed. The EUT met the specified test criterion.

TEST ENGINEER: Stephen Connolly

Page 22: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 21 of 26

4.7 Voltage Dips & Interruptions TEST METHOD

EN 61000-4-11 REFERENCING PROCEDURE: PLD-01

TEST DETAILS Test severity level

• Dips – 100% reduction for 20ms • Voltage shift @ zero phase crossing

Exerciser program during test

Referencing section 2.3

Specified test criterion

Criterion ‘B’ (continuous unmonitored operation)

EUT performance criterion

Criterion ‘A’

RESULTS – RF COMMON MODE TEST SPECIFICATION TEST POINTS STATUS

-100% x 20ms AC port and “volt free contact” port) (200V / 50Hz) PASS

UNCERTAINTY: It has been demonstrated that the power line disturbance simulator met the specified requirements in the standard with at least a 95% confidence.

COMMENT: The EUT met the specified test criterion.

TEST ENGINEER: Andy Jones

Page 23: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 22 of 26

5.0 PHOTO LOG Emissions:

Radiated disturbance

Page 24: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 23 of 26

Photo Log (continued)

Emissions:

Conducted disturbance

Page 25: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 24 of 26

Photo Log (continued)

Immunity:

Conducted RF field

Page 26: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 25 of 26

Photo Log (continued)

Immunity:

Fast transient bursts, surge and PLD

Page 27: EMC Test Report EMCS FLOCKMAN CR.pdf · EMC TEST REPORT 07R297 CR This report may not be reproduced other than in full Issue#1: 28th August 2007 Page 3 of 26 1.0 OVERVIEW 1.1 Introduction

EMC TEST REPORT 07R297 CR

This report may not be reproduced other than in full Issue#1: 28th August 2007

Page 26 of 26

Photo Log (continued)

Immunity:

Radiated RF interference