ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The...

12
7 th Fram ICT-200 ICT for Collabo Grant A Pub Period Covered: 2010-01 2013-03 Project Coordinator: Hannes Contine Start Date of Project: 2010-01 Website: http://w Revision: 0.97 (dr mework Programme 09.6.1 Safety and Energy Efficiency in Mobili orative Project Agreement No.: 249105 Final Report blishable Summary 1-01 to 3-31 Date of Preparat s Lüttringhaus ental Automotive GmbH 1-01 Duration www.elvire.eu raft) ity tion: 2013-06-28 39 Months

Transcript of ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The...

Page 1: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

7th Framework ProgrammeICT-2009.6.1ICT for Safety and Energy Efficiency in MobilityCollaborative ProjectGrant Agreement No.: 249105

Publishable Summary

Period Covered: 2010-012013-03

Project Coordinator: Hannes LüttringhausContinental Automotive GmbH

Start Date of Project: 2010-01

Website: http://www.elvire.eu

Revision: 0.97 (draft)

Framework Programme 2009.6.1

ICT for Safety and Energy Efficiency in MobilityCollaborative Project Grant Agreement No.: 249105

Final Report Publishable Summary

01-01 to 03-31

Date of Preparation:

Hannes Lüttringhaus Continental Automotive GmbH

01-01 Duration

http://www.elvire.eu

0.97 (draft)

ICT for Safety and Energy Efficiency in Mobility

Date of Preparation: 2013-06-28

39 Months

Page 2: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

Authors ELVIRE CoordinatorELVIRE Project ManagerELVIRE Work Package Leaders

Project Manager Gloria Pellischek

ERPC GmbH Project Coordinator Hannes Lüttringhaus

Daniela Seidel (finances)Continental Automotive GmbH Phone:Fax:Email:

Copyright: ELVIRE Consortium 2013

2010-01-01 to 2011-03-31

©: 2013 ELVIRE Consortium

ELVIRE Coordinator ELVIRE Project Manager ELVIRE Work Package Leaders

Gloria Pellischek ERPC GmbH

Hannes Lüttringhaus Daniela Seidel (finances) Continental Automotive GmbH

Phone: +49 6073 12-5077 Fax: +49 6073 1279-5077 Email: [email protected]

Copyright: ELVIRE Consortium 2013

26.06.2013

2

corporation.com

Page 3: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

Revision History

Version Date

0.1 2013-03-25

0.2 2013-04-03

1.0 2013-07-02

Table of Contents

Revision History................................

Table of Contents ................................

1 Executive Summary ................................

2 Summary Description of the Project Context and Objectives

3 Project Results and Achievements

4 Potential Impact ................................

5 Project Website ................................

6 Contacts ................................

2010-01-01 to 2011-03-31

©: 2013 ELVIRE Consortium

Change

Document Creation

Document Review

Document Release

................................................................................................................................

................................................................................................

................................................................................................

Summary Description of the Project Context and Objectives ................................

Project Results and Achievements ................................................................

................................................................................................

................................................................................................

................................................................................................................................

26.06.2013

3

.................................... 3

................................................................. 3

...................................................... 4

..................................................... 5

............................................................... 7

........................................................... 9

.......................................................... 11

..................................... 11

Page 4: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

1 Executive Summary

The ELVIRE project was the first research project partially funded by the European Commission which took a clostechnical improvements. Since Electrical Vehicles (EVs) are known for their limited driving range the adoption of these new cars was doubtful, although the media enthusiastically reported on this new possibility. The expectation was set, that EVs would soon replace the conventional cars.

However the limited driving range of EVs of about 100 to 150 kilometres needed to be overcome or the users of such cars would experience a phenomenon known as Rwhich is the fear to break down with an empty battery before the destination has been reached. Therefore Range Anxiety was seen as a market limiting factor of EVs.

The 39 months long project looked at solutions to overcome these problems, battery technology and wireless recharging while driving. The technologies investigated and the solutions developed came solely of the area of Information and Communication Technology (ICT).

First of all it was clear from the start, that EVs requsupply services so a Service Provider had to be established, a role which was taken by Better Place in our project. The service provider had to develop a scalable backwould generate services and deainfrastructure and ideally this had to be full coverage. Better Place also filled this role of an infrastructure operator. The required connection to a utility grid was filled by ENDESA and CEA helped with the development of an energy demand prediction system. SAP looked at the possibilities of roaming and developed a clearing house so that vehicles could charge at foreign infrastructure without the need to sign an additional contract.

Vehicle Equipment was needed to provide a dashboard integrated communication and service terminal to the EV driver. Since the equipment was meant to be installed in vehicles the car manufacturers Renault and Volkswagen as well as automotive supplier Continental took thwork package, accompanied by ATB from Bremen. The equipment was developed and cars were equipped so that open road tests could be conducted. Lindholmen Science Park verified the system successfully and the final demonstration presented it to the CommuniInterest.

A Business Model was also needed to prove that eself-sustaining business, which is capable to bear it s operational expenses and infrastructure investments.

After the project finished with a successfquestion remains: why are EVs not more successful by now? Where are the cars? Where are the customers? One of the projects conclusions was that Political Power has to set the course for success now. The technolowork, but only if critical mass can be reached soon. Legislation and regulation have to help to give EVs more weight in the market place.

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

Executive Summary

The ELVIRE project was the first research project partially funded by the European Commission which took a close look at the expected new market of e-mobility and its needed technical improvements. Since Electrical Vehicles (EVs) are known for their limited driving range the adoption of these new cars was doubtful, although the media enthusiastically

is new possibility. The expectation was set, that EVs would soon replace the

However the limited driving range of EVs of about 100 to 150 kilometres needed to be overcome or the users of such cars would experience a phenomenon known as Rwhich is the fear to break down with an empty battery before the destination has been reached. Therefore Range Anxiety was seen as a market limiting factor of EVs.

The 39 months long project looked at solutions to overcome these problems, battery technology and wireless recharging while driving. The technologies investigated and the solutions developed came solely of the area of Information and Communication

First of all it was clear from the start, that EVs require new kinds of information and energy supply services so a Service Provider had to be established, a role which was taken by Better Place in our project. The service provider had to develop a scalable back-would generate services and deal with EV user requests. Also there was the need of charge infrastructure and ideally this had to be full coverage. Better Place also filled this role of an infrastructure operator. The required connection to a utility grid was filled by ENDESA and CEA

ped with the development of an energy demand prediction system. SAP looked at the possibilities of roaming and developed a clearing house so that vehicles could charge at foreign infrastructure without the need to sign an additional contract.

ment was needed to provide a dashboard integrated communication and service terminal to the EV driver. Since the equipment was meant to be installed in vehicles the car manufacturers Renault and Volkswagen as well as automotive supplier Continental took thwork package, accompanied by ATB from Bremen. The equipment was developed and cars were equipped so that open road tests could be conducted. Lindholmen Science Park verified the system successfully and the final demonstration presented it to the Communi

A Business Model was also needed to prove that e-mobility also has potential to become a sustaining business, which is capable to bear it s operational expenses and infrastructure

After the project finished with a successful demonstration and dissemination event the question remains: why are EVs not more successful by now? Where are the cars? Where are the customers? One of the projects conclusions was that Political Power has to set the course for success now. The technology is ready for mass deployment, the Business Model would work, but only if critical mass can be reached soon. Legislation and regulation have to help to give EVs more weight in the market place.

26.06.2013

4

The ELVIRE project was the first research project partially funded by the European mobility and its needed

technical improvements. Since Electrical Vehicles (EVs) are known for their limited driving range the adoption of these new cars was doubtful, although the media enthusiastically

is new possibility. The expectation was set, that EVs would soon replace the

However the limited driving range of EVs of about 100 to 150 kilometres needed to be overcome or the users of such cars would experience a phenomenon known as Range Anxiety, which is the fear to break down with an empty battery before the destination has been reached. Therefore Range Anxiety was seen as a market limiting factor of EVs.

The 39 months long project looked at solutions to overcome these problems, excluding battery technology and wireless recharging while driving. The technologies investigated and the solutions developed came solely of the area of Information and Communication

ire new kinds of information and energy supply services so a Service Provider had to be established, a role which was taken by Better

-end system which l with EV user requests. Also there was the need of charge

infrastructure and ideally this had to be full coverage. Better Place also filled this role of an infrastructure operator. The required connection to a utility grid was filled by ENDESA and CEA

ped with the development of an energy demand prediction system. SAP looked at the possibilities of roaming and developed a clearing house so that vehicles could charge at

ment was needed to provide a dashboard integrated communication and service terminal to the EV driver. Since the equipment was meant to be installed in vehicles the car manufacturers Renault and Volkswagen as well as automotive supplier Continental took this work package, accompanied by ATB from Bremen. The equipment was developed and cars were equipped so that open road tests could be conducted. Lindholmen Science Park verified the system successfully and the final demonstration presented it to the Community of

mobility also has potential to become a sustaining business, which is capable to bear it s operational expenses and infrastructure

ul demonstration and dissemination event the question remains: why are EVs not more successful by now? Where are the cars? Where are the customers? One of the projects conclusions was that Political Power has to set the course

gy is ready for mass deployment, the Business Model would work, but only if critical mass can be reached soon. Legislation and regulation have to help to

Page 5: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

2 Summary Description of the Project Context and Objectives

In the centre of this project stands the development of those Information and Communication Technologies (ICT) and Services that are needed to neutralize the electric vehicle (EV) driver’s "Range Anxiety": the fear to break down due to the vehicle's drivithe same time to cope with the sparse distribution of electrical supply points.

Therefore the objective of “ELVIRE” was to develop an oncommunication & service platform for realistic usecommunication and services. For this purpose the following actions were taken:

� selection representative use

� identification & development of ICT & services needed to comply with t

� development of “prototypes” for on

� Verification of all integrated subproof of concept.

Based on a typical mission of an EV as use case, the projcustomer oriented, open service platform required for the optimum interaction between the user in his vehicle, the service provision layer and an intelligent electricity infrastructure.

ELVIRE was structured into five work p

WP 1000 covering the project administration, legal aspects and dissemination and the inclusion of complementary RTD

WP 2000 defined relevant mission data for the use cases in consideration of technical an commercial aspects

WP 3000 addressed the external ICT for EV service provision, charge infrastructure management and balancing energy demand and supply for the users

WP 4000 developed the EV Communication Device and the OEMboard communication and service platform

WP 5000 conducted usability tests and the overall end

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

Summary Description of the Project Context and Objectives

In the centre of this project stands the development of those Information and Communication Technologies (ICT) and Services that are needed to neutralize the electric vehicle (EV) driver’s "Range Anxiety": the fear to break down due to the vehicle's driving range limitation and at the same time to cope with the sparse distribution of electrical supply points.

Therefore the objective of “ELVIRE” was to develop an on-board electric energy communication & service platform for realistic use-cases including thecommunication and services. For this purpose the following actions were taken:

selection representative use-cases according to realistic scenarios and business

identification & development of ICT & services needed to comply with t

development of “prototypes” for on-board Communication and E

Verification of all integrated sub-systems on prototype level and demonstration of the

Based on a typical mission of an EV as use case, the project’s purpose was to develop a customer oriented, open service platform required for the optimum interaction between the user in his vehicle, the service provision layer and an intelligent electricity infrastructure.

ELVIRE was structured into five work packages, with:

covering the project administration, legal aspects and dissemination and the inclusion of complementary RTD

defined relevant mission data for the use cases in consideration of technical an commercial aspects

the external ICT for EV service provision, charge infrastructure management and balancing energy demand and supply for the users

developed the EV Communication Device and the OEM-neural universal onboard communication and service platform

conducted usability tests and the overall end-to-end system validation

Fig. 1: Project Distribution over 39 months

26.06.2013

5

Summary Description of the Project Context and Objectives

In the centre of this project stands the development of those Information and Communication Technologies (ICT) and Services that are needed to neutralize the electric vehicle (EV) driver’s

ng range limitation and at the same time to cope with the sparse distribution of electrical supply points.

board electric energy cases including the relevant external

communication and services. For this purpose the following actions were taken:

cases according to realistic scenarios and business-models

identification & development of ICT & services needed to comply with the use cases

board Communication and E-energy service unit

systems on prototype level and demonstration of the

ect’s purpose was to develop a customer oriented, open service platform required for the optimum interaction between the user in his vehicle, the service provision layer and an intelligent electricity infrastructure.

covering the project administration, legal aspects and dissemination and the

defined relevant mission data for the use cases in consideration of technical an

the external ICT for EV service provision, charge infrastructure management and balancing energy demand and supply for the users

neural universal on-

end system validation

Page 6: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

The ELVIRE system was developed within the three core RTD work packages.

The ELVIRE system is comprised of a number of subAnxiety the EV users have access to service terminals built into the dashboards of the demo vehicles. These terminals provide reliable informationtrips. There are two principal solutions to the service communication. However, both service terminals obtain their service communication from the same service provider backsystem. The main difference between thcommunicating with the service provider and the other is linking exclusively to an OEM backend which functions as a car access server for the service provision and which also offers telemetry services directly to their customers.

The service provider back-end has at its core the control and management centre (CMC), which secures communication and functions as a gateway. Behind the CMC there are several connected subsystems. The charge infrastructure is ravailability levels, the ENFORSE system is predicting energy demand from the field and it forecasts the availability of charge infrastructure. HORST is a system for the realization of roaming between service providers whicgrid communication provides information about actual and planned grid limitations and it allows service providers to warrant higher service levels to their customers.

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

The ELVIRE system was developed within the three core RTD work packages.

Fig. 2: ELVIRE System Diagram

The ELVIRE system is comprised of a number of sub-systems. In order to minimize Range Anxiety the EV users have access to service terminals built into the dashboards of the demo vehicles. These terminals provide reliable information, esp. about the feasibility of driving trips. There are two principal solutions to the service communication. However, both service terminals obtain their service communication from the same service provider backsystem. The main difference between the two communication channels is that one is directly communicating with the service provider and the other is linking exclusively to an OEM backend which functions as a car access server for the service provision and which also offers

irectly to their customers.

end has at its core the control and management centre (CMC), which secures communication and functions as a gateway. Behind the CMC there are several connected subsystems. The charge infrastructure is reporting on current occupancy and availability levels, the ENFORSE system is predicting energy demand from the field and it forecasts the availability of charge infrastructure. HORST is a system for the realization of roaming between service providers which improves infrastructure utilization and the utility grid communication provides information about actual and planned grid limitations and it allows service providers to warrant higher service levels to their customers.

26.06.2013

6

The ELVIRE system was developed within the three core RTD work packages.

systems. In order to minimize Range Anxiety the EV users have access to service terminals built into the dashboards of the demo

, esp. about the feasibility of driving trips. There are two principal solutions to the service communication. However, both service terminals obtain their service communication from the same service provider back-end

e two communication channels is that one is directly communicating with the service provider and the other is linking exclusively to an OEM back-end which functions as a car access server for the service provision and which also offers

end has at its core the control and management centre (CMC), which secures communication and functions as a gateway. Behind the CMC there are several

eporting on current occupancy and availability levels, the ENFORSE system is predicting energy demand from the field and it forecasts the availability of charge infrastructure. HORST is a system for the realization of

h improves infrastructure utilization and the utility grid communication provides information about actual and planned grid limitations and it allows service providers to warrant higher service levels to their customers.

Page 7: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

3 Project Results and Achievements

The main project results in chronological order are:

1. Definition of the use cases which provided a framework for the RTD work packages to further specify their subdriving an EV in a typical day. The

a. “initial activation”, the set

b. “frequent update” which is performed every time a vehicle is switched on and which checks for data updates, i.e. driver vehicle assignments;

c. “planning drive” whiccountermeasures provide remedy;

d. “driving without a plan”, which is a typical scenario for daily commutes;

e. “charging” which requires authentication, etc.

Other use cases dealt with emergencies, drivexceptional situations.

2. Analysis and definition of the “Range Anxiety” phenomenon. Range Anxiety was identified as one of the potential constraints to the marketability of EVs. The cognitive model of Range Anxiety was dindicated that it is dynamic, subjective, temporal, emotional and object oriented. The following strategies were identified to avoid Range Anxiety:

a. availability of reliable information sources for the user which clarify any uncertainty;

b. capability for immediate monitoring;

c. active interference possibilities when a destination is out of reach;

d. ability to double check or drill down information;

e. flexibility of the information

3. Development of the Early Prototype, which was the first running system on the bench with a reduced set of use cases implemented. The Early Prototype enabled first tests, incl. usability testing of the system as presented on the user terminal, that time a PC. The Early Prototype consisted of the following sub

a. Control and Management Centre (CMC), which manages the service provider process and generates service responses to remote requests;

b. Communication Platform (CMP), whichcommunication and authenticates the communication partners;

c. The working interfaces to remote systems such as Utility Energy Management, HORST roaming platform, ENFORSE energy demand prediction and all the connected charge and b

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

Project Results and Achievements

The main project results in chronological order are:

Definition of the use cases which provided a framework for the RTD work packages to further specify their sub-systems. The use cases described the user experience of driving an EV in a typical day. The most prominent included:

“initial activation”, the set-up routine when a car is purchased;

“frequent update” which is performed every time a vehicle is switched on and which checks for data updates, i.e. driver vehicle assignments;

“planning drive” which checks if a planned trip is feasible, and if not, which countermeasures provide remedy;

“driving without a plan”, which is a typical scenario for daily commutes;

“charging” which requires authentication, etc.

Other use cases dealt with emergencies, driver exchanges during a trip or other exceptional situations.

Analysis and definition of the “Range Anxiety” phenomenon. Range Anxiety was identified as one of the potential constraints to the marketability of EVs. The cognitive model of Range Anxiety was developed which indicated that it is dynamic, subjective, temporal, emotional and object oriented. The following strategies were identified to avoid Range Anxiety:

availability of reliable information sources for the user which clarify any uncertainty;

capability for immediate monitoring;

active interference possibilities when a destination is out of reach;

ability to double check or drill down information;

flexibility of the information presentation

Development of the Early Prototype, which was the first running system on the bench with a reduced set of use cases implemented. The Early Prototype enabled first tests, incl. usability testing of the system as presented on the user terminal, that time a PC. The Early Prototype consisted of the following sub

Control and Management Centre (CMC), which manages the service provider process and generates service responses to remote requests;

Communication Platform (CMP), which safeguards the backend data communication and authenticates the communication partners;

The working interfaces to remote systems such as Utility Energy Management, HORST roaming platform, ENFORSE energy demand prediction and all the connected charge and battery switch infrastructure.

Fig. 3: Range Anxiety Cognitive Model

26.06.2013

7

Definition of the use cases which provided a framework for the RTD work packages to systems. The use cases described the user experience of

up routine when a car is purchased;

“frequent update” which is performed every time a vehicle is switched on and which checks for data updates, i.e. driver vehicle assignments;

h checks if a planned trip is feasible, and if not, which

“driving without a plan”, which is a typical scenario for daily commutes;

er exchanges during a trip or other

Analysis and definition of the “Range Anxiety” phenomenon. Range Anxiety was identified as one of the potential constraints to the marketability of EVs. The cognitive

Development of the Early Prototype, which was the first running system on the bench with a reduced set of use cases implemented. The Early Prototype enabled first tests, incl. usability testing of the system as presented on the user terminal, which was at that time a PC. The Early Prototype consisted of the following sub-systems:

Control and Management Centre (CMC), which manages the service provider process and generates service responses to remote requests;

safeguards the backend data communication and authenticates the communication partners;

The working interfaces to remote systems such as Utility Energy Management, HORST roaming platform, ENFORSE energy demand prediction and all the

: Range Anxiety Cognitive Model

Page 8: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

d. OEM Back-end for service clearing and telemetry

e. Communication Device (EVCD) for secure data communication in the vehicle;

f. Service Unit, which is the touch screen dashboard, which represents services and provides users with the required information to minimize Range Anxiety. This device contains a navigation map and besides guidance services it also estimates the expected energysumption for a given route considering topography, driving behaviour and vehicle status information. With this information it analyses the feasibility of a planned trip and it also produces suggestions in case of a driving range conflicts i.e. by searfor available energy outlets and offering reservation, etc.

4. Analysis and recommendations regarding a business model for estakeholders along the value chain were interviewed and their views mapped on the so called Business Model Canvaquestion of how to realize a full coverage charge infrastructure, when selling energy to EV users seems not a major revenue opportunity. Generation of value has to reach beyond energy retail. The usage ofparking are of higher value and they could be bundled with energy retail to be offered combined. In addition, battery switch is an interesting option which supports the business model and at the same time fur

5. Development of the Full Prototype which completed the implementation of the remaining use cases. The results of the Early Prototype testing were analysed and improvements were defined and implemented. Also the vehicle onwas now completed and the systems were integrated to their final configuration. The devices were installed into vehicles and embedded software was calibrated to meet car specifications

Fig. 5: ELVIRE HMI in VW Dash

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

end for service clearing and telemetry

Communication Device (EVCD) for secure data communication in the vehicle;

Service Unit, which is the touch screen operated user terminal in the vehicle dashboard, which represents services and provides users with the required information to minimize Range Anxiety. This device contains a navigation map and besides guidance services it also estimates the expected energy con-sumption for a given route considering topography, driving behaviour and vehicle status information. With this information it analyses the feasibility of a planned trip and it also produces suggestions in case of a driving range conflicts i.e. by searching for available energy outlets and offering reservation, etc.

Analysis and recommendations regarding a business model for e-stakeholders along the value chain were interviewed and their views mapped on the so called Business Model Canvas. The derived business model is centred around the question of how to realize a full coverage charge infrastructure, when selling energy to EV users seems not a major revenue opportunity. Generation of value has to reach beyond energy retail. The usage of infrastructure, battery leasing and inner city parking are of higher value and they could be bundled with energy retail to be offered combined. In addition, battery switch is an interesting option which supports the business model and at the same time further reduces Range Anxiety.

Development of the Full Prototype which completed the implementation of the remaining use cases. The results of the Early Prototype testing were analysed and improvements were defined and implemented. Also the vehicle onwas now completed and the systems were integrated to their final configuration. The devices were installed into vehicles and embedded software was calibrated to meet

Fig. 4: Trip Consumption Preview

: ELVIRE HMI in VW Dash Fig. 6: Service Unit and EVCD in Renault Trunk

26.06.2013

8

Communication Device (EVCD) for secure data communication in the vehicle;

operated user terminal in the vehicle dashboard, which represents services and provides users with the required information to minimize Range Anxiety. This device contains a navigation map

-mobility. All stakeholders along the value chain were interviewed and their views mapped on the

s. The derived business model is centred around the question of how to realize a full coverage charge infrastructure, when selling energy to EV users seems not a major revenue opportunity. Generation of value has to reach

infrastructure, battery leasing and inner city parking are of higher value and they could be bundled with energy retail to be offered combined. In addition, battery switch is an interesting option which supports the

ther reduces Range Anxiety.

Development of the Full Prototype which completed the implementation of the remaining use cases. The results of the Early Prototype testing were analysed and improvements were defined and implemented. Also the vehicle on-board equipment was now completed and the systems were integrated to their final configuration. The devices were installed into vehicles and embedded software was calibrated to meet

: Trip Consumption Preview

: Service Unit and EVCD in Renault Trunk

Page 9: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

6. Verification and validation of the full prototype included open road testing with unbiased test subjects. These subjects were driving the demo cars accompanied by test moderators whoIn addition answers to a number of questions were noted and the whole driving was recorded with video cameras. The analysis of the materials showed that 92% of the participants believed that tsystem and the information presented to a large degree.

4 Potential Impact

ELVIRE was at the forefront of the EV related European research projects. It addressed the main technical challenges for a vand unconcerned e-mobility. The project also spent effort on defining a possible business plan which showed e-mobility could actually become a viable business. Over the three year period the public perception about EVs as reflected in the media underwent a transformation. In the beginning the EV was seen as a saviour and the media in a state of hype was producing exaggerated expectations regarding the EV market adoption. Today, three years later tmedia is drawing a different picture by stating that the customers don’t want to buy EVs yet, due to high purchase prices and limited driving range. Batteries are portrayed as not advanced enough. So the former exaggerated expectations could not be met.market in the promised quantities and their production costs and sales prices are much higher than predicted. Also the parallel development of smart grids and renewable energy sources stalled. Germany i.e. reduced the subsidies on downturn of the banking industry which is now followed by financial instabilities in southern Europe is consuming vast amounts of capital. From this point of view the political discussion about investments for the needed energy turnaround towards alternative sources seems no longer opportune.

So the market development of eare just a few EV models coming to the market and the adoption rate has been lowlikely remain low, mainly due to the price barrier and the lack of infrastructure. The perceived range limitation of EVs can be solved with smart ICT solutions as this project successfully demonstrated. Not the battery technology is the limiting EVs in the market is the reason that enot getting up to speed by itself and the car industry is not realising good profit margins then society has only one power left to accelerate the change, political power. At a point in time when the human race understands its impact on the biosphere and needs to take measures to drastically reduce green house gas emissions the governments are asked to take necessary actions, even against interests of some lobby groups. Unfortunately so far not much has happened. The political discussions around these topics always seem to end with the conclusion that our local economy has a still higher priority than global ecology.

ELVIRE has produced a principal solution in terms of technology as well as economy for realising the EV mass market. If governments are not adjusting the general conditions in favour of EVs then the market will not take off until oil prices leave no alternative. Wthat be? The answer is uncertain. Probably the crude oil reserves have to be further exhausted

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

Verification and validation of the full prototype included open road testing with unbiased test subjects. These subjects were driving the demo cars accompanied by test moderators who were tasking them to perform standardised system interactions. In addition answers to a number of questions were noted and the whole driving was recorded with video cameras. The analysis of the materials showed that 92% of the participants believed that the application is a useful tool for EVs. They trusted the system and the information presented to a large degree.

ELVIRE was at the forefront of the EV related European research projects. It addressed the main technical challenges for a vehicle-grid-integration and produced solutions for unlimited

mobility. The project also spent effort on defining a possible business plan mobility could actually become a viable business. Over the three year period

ic perception about EVs as reflected in the media underwent a transformation. In the beginning the EV was seen as a saviour and the media in a state of hype was producing exaggerated expectations regarding the EV market adoption. Today, three years later tmedia is drawing a different picture by stating that the customers don’t want to buy EVs yet, due to high purchase prices and limited driving range. Batteries are portrayed as not advanced enough. So the former exaggerated expectations could not be met. EVs did not come to the market in the promised quantities and their production costs and sales prices are much higher than predicted. Also the parallel development of smart grids and renewable energy sources stalled. Germany i.e. reduced the subsidies on private solar panel installations. The economic downturn of the banking industry which is now followed by financial instabilities in southern Europe is consuming vast amounts of capital. From this point of view the political discussion

r the needed energy turnaround towards alternative sources seems no

So the market development of e-mobility and the introduction of EVs have been slow. There are just a few EV models coming to the market and the adoption rate has been lowlikely remain low, mainly due to the price barrier and the lack of infrastructure. The perceived range limitation of EVs can be solved with smart ICT solutions as this project successfully demonstrated. Not the battery technology is the limiting factor, the missing critical mass of EVs in the market is the reason that e-mobility is not jump started as expected. If the market is not getting up to speed by itself and the car industry is not realising good profit margins then

er left to accelerate the change, political power. At a point in time when the human race understands its impact on the biosphere and needs to take measures to drastically reduce green house gas emissions the governments are asked to take necessary

, even against interests of some lobby groups. Unfortunately so far not much has happened. The political discussions around these topics always seem to end with the conclusion that our local economy has a still higher priority than global ecology.

as produced a principal solution in terms of technology as well as economy for realising the EV mass market. If governments are not adjusting the general conditions in favour of EVs then the market will not take off until oil prices leave no alternative. Wthat be? The answer is uncertain. Probably the crude oil reserves have to be further exhausted

26.06.2013

9

Verification and validation of the full prototype included open road testing with unbiased test subjects. These subjects were driving the demo cars accompanied by

were tasking them to perform standardised system interactions. In addition answers to a number of questions were noted and the whole driving was recorded with video cameras. The analysis of the materials showed that 92% of the

he application is a useful tool for EVs. They trusted the

ELVIRE was at the forefront of the EV related European research projects. It addressed the integration and produced solutions for unlimited

mobility. The project also spent effort on defining a possible business plan mobility could actually become a viable business. Over the three year period

ic perception about EVs as reflected in the media underwent a transformation. In the beginning the EV was seen as a saviour and the media in a state of hype was producing exaggerated expectations regarding the EV market adoption. Today, three years later the media is drawing a different picture by stating that the customers don’t want to buy EVs yet, due to high purchase prices and limited driving range. Batteries are portrayed as not advanced

EVs did not come to the market in the promised quantities and their production costs and sales prices are much higher than predicted. Also the parallel development of smart grids and renewable energy sources

private solar panel installations. The economic downturn of the banking industry which is now followed by financial instabilities in southern Europe is consuming vast amounts of capital. From this point of view the political discussion

r the needed energy turnaround towards alternative sources seems no

mobility and the introduction of EVs have been slow. There are just a few EV models coming to the market and the adoption rate has been low and will likely remain low, mainly due to the price barrier and the lack of infrastructure. The perceived range limitation of EVs can be solved with smart ICT solutions as this project successfully

factor, the missing critical mass of mobility is not jump started as expected. If the market is

not getting up to speed by itself and the car industry is not realising good profit margins then er left to accelerate the change, political power. At a point in time

when the human race understands its impact on the biosphere and needs to take measures to drastically reduce green house gas emissions the governments are asked to take necessary

, even against interests of some lobby groups. Unfortunately so far not much has happened. The political discussions around these topics always seem to end with the conclusion that our local economy has a still higher priority than global ecology.

as produced a principal solution in terms of technology as well as economy for realising the EV mass market. If governments are not adjusting the general conditions in favour of EVs then the market will not take off until oil prices leave no alternative. When will that be? The answer is uncertain. Probably the crude oil reserves have to be further exhausted

Page 10: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

before it takes place. The damage to our global climate system will have worsened by then and future generations will not just struggle with their econo

Tangible impacts of ELVIRE have been slowed in different areas. Since the beginning of the project no Pan-European service providers have been established. Some national activities, were started, but they are not tightly aligned nor interoperable yetto support the dense distribution of charge infrastructure. Car manufacturers are not requested to support battery switch as a solution. So, the impact could have been much higher yet. What remains is the excellent internatioproject and which is continuing in subsequent research projects. The developed technologies will find their individual ways into exploitation, although probably with lesser impacts. As hybrid cars seem to enjoy a better market adoption (by the way: steered through emission legislation) some of the on-board solutions will be likely to be used in this context.

The potential impacts are remaining true. The technology developed in ELVIRE is ready for utilization and it would help to make an impact in many areas, such as: competitiveness of the European industry, CO2 emission reduction, energy security and personal data security. Of course the entire consortium is wishing that the EV market is accelerating nevertheless athat the project results will also produce monetary results soon.

Fig. 7: Political Power is needed to give EVs more weight

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

before it takes place. The damage to our global climate system will have worsened by then and future generations will not just struggle with their economies.

Tangible impacts of ELVIRE have been slowed in different areas. Since the beginning of the European service providers have been established. Some national activities,

were started, but they are not tightly aligned nor interoperable yet. Political will is not formed to support the dense distribution of charge infrastructure. Car manufacturers are not requested to support battery switch as a solution. So, the impact could have been much higher yet. What remains is the excellent international collaboration which took place in this project and which is continuing in subsequent research projects. The developed technologies will find their individual ways into exploitation, although probably with lesser impacts. As

better market adoption (by the way: steered through emission board solutions will be likely to be used in this context.

The potential impacts are remaining true. The technology developed in ELVIRE is ready for would help to make an impact in many areas, such as: competitiveness of the

European industry, CO2 emission reduction, energy security and personal data security. Of course the entire consortium is wishing that the EV market is accelerating nevertheless athat the project results will also produce monetary results soon.

: Political Power is needed to give EVs more weight

26.06.2013

10

before it takes place. The damage to our global climate system will have worsened by then

Tangible impacts of ELVIRE have been slowed in different areas. Since the beginning of the European service providers have been established. Some national activities,

. Political will is not formed to support the dense distribution of charge infrastructure. Car manufacturers are not requested to support battery switch as a solution. So, the impact could have been much

nal collaboration which took place in this project and which is continuing in subsequent research projects. The developed technologies will find their individual ways into exploitation, although probably with lesser impacts. As

better market adoption (by the way: steered through emission board solutions will be likely to be used in this context.

The potential impacts are remaining true. The technology developed in ELVIRE is ready for would help to make an impact in many areas, such as: competitiveness of the

European industry, CO2 emission reduction, energy security and personal data security. Of course the entire consortium is wishing that the EV market is accelerating nevertheless and

Page 11: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

5 Project Website

The address of the project public website is

This website contains all formal data regarding the project and the consortium. It also provides a high level description of the project purpose, structure and outcomes. More importantly, is allows open access to the public deliverables of the project, the scientific &technical publications as well as the released communication materials. More generally, dissemination activities are listed and related documents (slides, posters, papers) are available for download.

6 Contacts

Project Coordinator

Hannes Lüttringhaus

Business Development ManagerInterior Electronics SolutionsContinental Automotive GmbHVDO-Strasse 1 64832 Babenhausen Germany

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

The address of the project public website is http://www.elvire.eu/

contains all formal data regarding the project and the consortium. It also provides a high level description of the project purpose, structure and outcomes. More importantly, is allows open access to the public deliverables of the project, the scientific &technical publications as well as the released communication materials. More generally, dissemination activities are listed and related documents (slides, posters, papers) are available

Public Interface

Business Development Manager Interior Electronics Solutions Continental Automotive GmbH

Carole Sentein

Commissariat à l’Énergie Atomiqueet aux Énergies AlternativesCentre de Saclay - DRT/LIST/DCPoint courrier 72 91191 Gif-sur-Yvette CedexFrance Email : [email protected]

26.06.2013

11

contains all formal data regarding the project and the consortium. It also provides a high level description of the project purpose, structure and outcomes. More importantly, is allows open access to the public deliverables of the project, the scientific & technical publications as well as the released communication materials. More generally, dissemination activities are listed and related documents (slides, posters, papers) are available

Commissariat à l’Énergie Atomique et aux Énergies Alternatives

DRT/LIST/DCSI

Yvette Cedex

Page 12: ELVIRE Final Publishable Summary V1 - CORDIS...Final Project Report Summary 1 Executive Summary The ELVIRE project was the first research project partially funded by the European Commission

Final Project Report Summary

2010-01-01 to 2013-03-31

©: 2013 ELVIRE Consortium

12