Eliminating High Risk Work at Hanford · 2015-10-06 · (August) All 242-Z glove boxes removed...
Transcript of Eliminating High Risk Work at Hanford · 2015-10-06 · (August) All 242-Z glove boxes removed...
www.energy.gov/EM 1
Eliminating High Risk Work at Hanford
John CiucciPresident and CEO
CH2M HILL Plateau Remediation Company
September 29, 2015
www.energy.gov/EM 2
www.energy.gov/EM 3
Project Overview
• 2008-2018 (contract option period granted)
• Approximately 1,378 employees (547
bargaining unit)
• Voluntary Protection Program Star of
Excellence
• More than $2.2 billion to small businesses
contract-to-date
• Current Project Scope:
• Sludge Treatment Project
• Groundwater Treatment Program
• Cesium/Strontium Storage
• Waste and fuels management
• Plutonium Finishing Plant closure (PFP)
www.energy.gov/EM 4
Sludge Treatment Project
www.energy.gov/EM 5
Site-Wide Groundwater Treatment
0.5 0.5
0.8
1
1.4
1.8
2.1
0.50.6
0.9
1.2
1.8 1.9
2.3
2009 2010 2011 2012 2013 2014 2015
Billi
on
Ga
llo
ns
Goal Actual Gallons Treated
Accelerating Cleanup by Consistently Beating Groundwater Goals
www.energy.gov/EM 6
Managing Cesium/Strontium Capsules
www.energy.gov/EM 7
Waste Management
www.energy.gov/EM 8
Demolition of PFP
www.energy.gov/EM 9
PFP: Monumental Challenge
238 Glove Boxes 196 Pencil Tank Units
24,000 feet of Asbestos38 Filter Boxes7,100 feet of Process Vacuum Piping
www.energy.gov/EM 10
PFP: Significant Progress Made
238 Glove Boxes 196 Pencil Tank Units
24,000 feet of Asbestos38 Filter Boxes7,100 feet of Process Vacuum Piping
48%
Complete
www.energy.gov/EM 11
PFP: Significant Progress Made
238 Glove Boxes 196 Pencil Tank Units
24,000 feet of Asbestos38 Filter Boxes7,100 feet of Process Vacuum Piping
48%
Complete
66%
Complete
www.energy.gov/EM 12
PFP: Significant Progress Made
238 Glove Boxes 196 Pencil Tank Units
24,000 feet of Asbestos38 Filter Boxes7,100 feet of Process Vacuum Piping
48%
Complete
92%
Complete
66%
Complete
www.energy.gov/EM 13
PFP: Significant Progress Made
238 Glove Boxes 196 Pencil Tank Units
24,000 feet of Asbestos38 Filter Boxes7,100 feet of Process Vacuum Piping
48%
Complete
92%
Complete
66%
Complete
4 Remaining
www.energy.gov/EM 14
PFP: Significant Progress Made
238 Glove Boxes 196 Pencil Tank Units
24,000 feet of Asbestos38 Filter Boxes7,100 feet of Process Vacuum Piping
Complete
48%
Complete
92%
Complete
66%
Complete
4 Remaining
www.energy.gov/EM 15
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 16
April: McCluskey Glove Box Removed
RISK:
Deploying new PPE in
hazardous
environment
MITIGATION:
Employee-driven
research and training
www.energy.gov/EM 17
April: McCluskey Glove Box Removed
www.energy.gov/EM 18
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 19
April: Last Pencil Tank Removed
AFTER:
All pencil tanks gone; debris on canyon floor to be
removed
BEFORE:
52 pencil tanks/196 pencil tank units
www.energy.gov/EM 20
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 21
June: In-Situ Glove Box Size Reduction Starts
MITIGATION:
Improved airflow and wipe downs, additional fixative
and PPE, extra padding on obstacles and PPE
RISK:
Cross contamination during doffing24,000,000 DPM/cm2 – 333,000 DAC
www.energy.gov/EM 22
June: In-Situ Glove Box Size Reduction Starts
www.energy.gov/EM 23
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 24
June: External Demolition Review Panel
Non-CHPRC Participants:
Jennifer Meszaros, DNFSB
Farid Bamdad, DNFSB
David Cleaves, DNFSB
Pat Fox , DNFSB
Tom Teynor, DOE-RL
Margo Voogd, DOE-RL
John Silko, DOE-RL
Don Rack, DOE (EM-42)
Hoss Brown, ICP
Ray Geimer, West Valley
Dave Lowe, CH2M Corporate
John Fulton, CH2M Corporate
Kurt Kehler, CH2M Corporate
www.energy.gov/EM 25
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 26
July: PRF Canyon Entries Began
RISK:
Supplied air90,000,000 DPM/cm2 – 33,000 DAC
MITIGATION:
• Increased ventilation
• Improved radiological work controls
• Increased fixative use
www.energy.gov/EM 27
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 28
August: All 242-Z Glove Boxes Removed
www.energy.gov/EM 29
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 30
PFP: Path to Demolition
2015
(April) Last pencil
tank removed
(June) In-situ glove box
size reduction starts
(June) External demolition
review panel
(August) All 242-Z glove
boxes removed
(July) PRF canyon
entries began(April) McCluskey
glove box removed
(November) DSA for
demolition implemented
(November) In-situ glove
box size reduction complete
www.energy.gov/EM 31
PFP: Path to Demolition
2016
(March) 236-Z
demolition starts
(April) 242-Z demolition
starts
(June) 234-5Z
demolition starts
(July) 291-Z demolition
starts
www.energy.gov/EM 32
PFP: Path to Demolition
www.energy.gov/EM 33
PFP: Path to Demolition
www.energy.gov/EM 34
PFP: Removing a Significant Risk
www.energy.gov/EM 35
PFP: Removing a Significant Risk
www.energy.gov/EM 36
PFP: Removing a Significant Risk