ELI begins construction - the next phase of implementation

6
ELI begins construction - the next phase of implementation astimil Růžička, ELI Beamlines Managing Director ague, May 24, 2013

description

ELI begins construction - the next phase of implementation. Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013. Recent progress in ELI Beamlines. Establishment of ELI-DC (April 2013) Contract for building general contractor signed (May 2013) - PowerPoint PPT Presentation

Transcript of ELI begins construction - the next phase of implementation

Page 1: ELI begins construction - the next phase of implementation

ELI begins construction - the next phase of implementation

Vlastimil Růžička, ELI Beamlines Managing DirectorPrague, May 24, 2013

Page 2: ELI begins construction - the next phase of implementation

Establishment of ELI-DC (April 2013)

Contract for building general contractor signed (May 2013)

Contract for delivery of PW class laser close to being concluded (probably June 2013)

Recent progress in ELI Beamlines

Page 3: ELI begins construction - the next phase of implementation

Establishment of ELI-DC

Signature of notarial deed, Brussels, April 11, 2013

Fourth from the left:Robert-Jan Smits, Director-General of DG Research and Innovation

Institute of Physics joins the Association after it being established legally by royal decree (expected May/June 2013)

Page 4: ELI begins construction - the next phase of implementation

Construction pit May-17, 2013 (phase 1, site preparation, contractor: Strabag)

Size: 120 x 60 mDepth: 9 m

General contract signed

General contractor: consortium Metrostav, OHL ŽS, VCES•Laser hall (3 stories bldg., 1 underground), admin.bldg., multifunctional bldg.•To be finished May 2015, total cost 1,4 bil. CZK (VAT excl.)

Page 5: ELI begins construction - the next phase of implementation

Cutting edge 2-PW class 10 Hz repetition rate laser

Based on DPSSL technology

World leading parameters in output power and repetition rate

„Workhorse“ of the ELI Beamlines facility

Supplier: Lawrence Livermore National Laboratory, California, USA

Participation of Czech scientists in the development team

Contract to be signed June 2013

Procurement of PW class laser

Page 6: ELI begins construction - the next phase of implementation

Fyzikální ústav AV ČR, v. v. i.Na Slovance 2182 21 Praha 8

[email protected]

Thank you very much for your attention

[email protected]