![Page 1: ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013.](https://reader030.fdocuments.us/reader030/viewer/2022032804/56649e4c5503460f94b41215/html5/thumbnails/1.jpg)
ELI begins construction - the next phase of implementation
Vlastimil Růžička, ELI Beamlines Managing DirectorPrague, May 24, 2013
![Page 2: ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013.](https://reader030.fdocuments.us/reader030/viewer/2022032804/56649e4c5503460f94b41215/html5/thumbnails/2.jpg)
Establishment of ELI-DC (April 2013)
Contract for building general contractor signed (May 2013)
Contract for delivery of PW class laser close to being concluded (probably June 2013)
Recent progress in ELI Beamlines
![Page 3: ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013.](https://reader030.fdocuments.us/reader030/viewer/2022032804/56649e4c5503460f94b41215/html5/thumbnails/3.jpg)
Establishment of ELI-DC
Signature of notarial deed, Brussels, April 11, 2013
Fourth from the left:Robert-Jan Smits, Director-General of DG Research and Innovation
Institute of Physics joins the Association after it being established legally by royal decree (expected May/June 2013)
![Page 4: ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013.](https://reader030.fdocuments.us/reader030/viewer/2022032804/56649e4c5503460f94b41215/html5/thumbnails/4.jpg)
Construction pit May-17, 2013 (phase 1, site preparation, contractor: Strabag)
Size: 120 x 60 mDepth: 9 m
General contract signed
General contractor: consortium Metrostav, OHL ŽS, VCES•Laser hall (3 stories bldg., 1 underground), admin.bldg., multifunctional bldg.•To be finished May 2015, total cost 1,4 bil. CZK (VAT excl.)
![Page 5: ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013.](https://reader030.fdocuments.us/reader030/viewer/2022032804/56649e4c5503460f94b41215/html5/thumbnails/5.jpg)
Cutting edge 2-PW class 10 Hz repetition rate laser
Based on DPSSL technology
World leading parameters in output power and repetition rate
„Workhorse“ of the ELI Beamlines facility
Supplier: Lawrence Livermore National Laboratory, California, USA
Participation of Czech scientists in the development team
Contract to be signed June 2013
Procurement of PW class laser
![Page 6: ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013.](https://reader030.fdocuments.us/reader030/viewer/2022032804/56649e4c5503460f94b41215/html5/thumbnails/6.jpg)
Fyzikální ústav AV ČR, v. v. i.Na Slovance 2182 21 Praha 8
Thank you very much for your attention