Elementary School #33
Elementary School #33
• Board approval in 2006• Funding
2002 Bond 2005 Bond
• Location Camino A Lago Meadows
Opening Date – 2014 versus 2015• 2014 Opening Considerations
Construction costs Committee support Enrollment stabilization
• Challenges Alternate location Budgeting considerations New Request For Proposal (RFP) requirements
for Construction Manager (CM) at Risk Compressed timeline
Opening Date – 2014 versus 2015• 2015 Opening Considerations
More time for review and development of school design
More time to ready fixtures and furnishings upon completion
• Challenges More than one move for some
students
Design Options
• Proceed with 2008 design• Review prototypes from approved
architects• Design committee to work with architect
to develop site plans and make recommendations to Board
Questions?