Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity...

46
Version No. 003 Electricity Safety (Management) Regulations 2009 S.R. No. 165/2009 Version incorporating amendments as at 1 November 2013 TABLE OF PROVISIONS Regulation Page PART 1—PRELIMINARY 1 1 Objective 1 2 Authorising provisions 1 3 Commencement 1 4 Revocation 1 5 Definitions 2 6 Meaning of access authority system 4 PART 2—SAFETY MANAGEMENT SCHEMES 7 Division 1—Content of electricity safety management scheme 7 7 Person responsible for supply network or installation, or carrying out of electrical work 7 8 Person responsible for electricity safety management scheme 7 9 Scheme description—employer operators 7 10 Scheme description—asset operators and network operators 8 11 Formal safety assessment—asset operators and employer operators 8 12 Exemptions to be specified 9 1

Transcript of Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity...

Page 1: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

Version No. 003

Electricity Safety (Management) Regulations 2009

S.R. No. 165/2009

Version incorporating amendments as at1 November 2013

TABLE OF PROVISIONSRegulation Page

PART 1—PRELIMINARY 1

1 Objective 12 Authorising provisions 13 Commencement 14 Revocation 15 Definitions 26 Meaning of access authority system 4

PART 2—SAFETY MANAGEMENT SCHEMES 7

Division 1—Content of electricity safety management scheme 7

7 Person responsible for supply network or installation, or carrying out of electrical work 7

8 Person responsible for electricity safety management scheme 79 Scheme description—employer operators 710 Scheme description—asset operators and network operators 811 Formal safety assessment—asset operators and employer

operators 812 Exemptions to be specified 9

Division 2—Content of safety management system—asset operators and employer operators 11

13 Safety management system 1114 Safety policy 1115 Standards for works on applicable assets—where there are

published technical standards 1116 Standards for works on applicable assets—where there are

no published technical standards 1217 Technical standards for electrical work 1318 Applicable assets—asset management plan requirements 1419 Requirements in relation to electrical work 15

1

Page 2: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

20 Access authority system 1621 Emergency preparedness 1622 Internal monitoring, auditing and reviewing 1723 Key performance indicators 1824 Incident recording, investigation and reviewing 1825 Competence and training 19

Division 3—Content of safety management system—network operators 20

25A Safety management system—MEC 2025B Safety management system—other network operator 20

PART 3—RECORDS AND REPORTING 21

26 Records 2127 Asset operator and network operator requirements for

reporting of serious electrical incidents 2228 Asset operator and network operator reporting of incidents

other than serious electrical incidents 23

PART 4—GENERAL 25

29 Exemptions from regulation requirements 25═══════════════

ENDNOTES 26

1. General Information 26

2. Table of Amendments 27

3. Explanatory Details 28

2

Page 3: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

Version No. 003

Electricity Safety (Management) Regulations 2009

S.R. No. 165/2009

Version incorporating amendments as at1 November 2013

PART 1—PRELIMINARY

1 Objective

The objective of these Regulations is to provide for the requirements, procedures and other matters relating to the acceptance of electricity safety management schemes.

2 Authorising provisions

These Regulations are made under sections 150 and 157 of the Electricity Safety Act 1998.

3 Commencement

These Regulations come into operation on 13 December 2009.

4 Revocation

The following Regulations are revoked—

(a) the Electricity Safety (Management) Regulations 19991;

(b) the Electricity Safety (Management) (Amendment) Regulations 20012;

(c) the Electricity Safety (Management) (Amendment) Regulations 20033.

1

Page 4: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

5 Definitions

In these Regulations—

access authority system has the meaning given by regulation 6;

applicable asset means—

(a) a supply network owned or operated by an MEC; or

(b) a complex electrical installation;

AS 5577 means Australian Standard AS 5577, "Electricity network safety management systems", as published or amended from time to time;

asset operator means an owner of an electrical installation that has an installed generation capacity of equal to or greater than 1000 kVA who is entitled to submit an electricity safety management scheme under section 116 of the Act;

emergency service means—

(a) the Chief Commissioner of Police;

(b) an ambulance service;

(c) the Country Fire Authority;

(d) the Metropolitan Fire and Emergency Services Board;

(e) the State Emergency Service;

(f) the Department of Sustainability and Environment;

employer operator means—

(a) an employer of electrical workers who is entitled to submit an electricity safety management scheme under section 114 of the Act;

2

r. 5

Reg. 5 def. of AS 5577 inserted by S.R. No. 131/2013 reg. 5(a).

Reg. 5 def. of asset operator inserted by S.R. No. 131/2013 reg. 5(a).

Reg. 5 def. of employer operator amended by S.R. No. 131/2013 reg. 5(b).

Page 5: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(b) an occupier of specified premises who is entitled to submit an electricity safety management scheme under section 115 of the Act;

MEC means a major electricity company;

network operator means—

(a) an MEC; or

(b) an owner of an electric line that is on land that is not owned or leased by the owner or operator of the electric line and who is entitled to submit an electricity safety management scheme under section 116 of the Act;

published technical standard means a document giving technical information, guidance or advice published by—

(a) Standards Australia; or

(b) Standards New Zealand; or

(c) the British Standards Institute; or

(d) the International Organisation for Standardisation; or

(e) the International Electrotechnical Commission; or

(f) any similar standards organisation within or outside Australia approved by Energy Safe Victoria; or

(g) Energy Safe Victoria;

* * * * *

3

Reg. 5 def. of network operator inserted by S.R. No. 131/2013 reg. 5(a).

r. 5

Reg. 5 def. of relevant asset operator revoked by S.R. No. 131/2013 reg. 5(c).

Page 6: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

scheme operator means an asset operator, employer operator or network operator;

the Act means the Electricity Safety Act 1998.

6 Meaning of access authority systemr. 6

Reg. 6(1) amended by S.R. No. 131/2013 reg. 6(1).

(1) For the purpose of these Regulations, an access authority system is, for a safety management system for an applicable asset of an asset operator, a system—

(a) under which access to, or the carrying out of work on or near, the applicable asset or part of the applicable asset to which the electricity safety management scheme relates is controlled; and

(b) under which an access authority may be issued for the purpose of allowing access to, or the carrying out of work on or near, the applicable asset or part of the applicable asset to which the electricity safety management scheme relates; and

(c) that specifies the positions of the persons who are authorised by the asset operator to issue an access authority and to supervise that access or the carrying out of that work; and

(d) that ensures that persons authorised to issue an access authority, and

persons carrying out that work under an access authority—

(i) are competent to do so; and

4

Reg. 5 def. of scheme operator substituted by S.R. No. 131/2013 reg. 5(d).

Reg. 6(1)(c) amended by S.R. No. 131/2013 reg. 6(2).

Page 7: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(ii) are provided with appropriate training, procedures, tools, equipment and emergency support.

(2) For the purpose of these Regulations, an access authority system is, for a safety management system for electrical work carried out by electrical workers employed by an employer operator, a system—

(a) under which the following is controlled—

(i) access to an electrical installation or electrical equipment while electrical work to which the electricity safety management scheme relates is being carried out on the installation or equipment;

(ii) the carrying out of work near an electrical installation or electrical equipment while electrical work to which the electricity safety management scheme relates is being carried out on the installation or equipment; and

(b) under which an access authority may be issued for the purpose of allowing access to, or the carrying out of work near, an electrical installation or electrical equipment while electrical work to which the electricity safety management scheme relates is being carried out on the installation or equipment; and

(c) that specifies the positions of the persons who are authorised by the employer operator to issue an access authority and to supervise that access or the carrying out of that work; and

(d) that ensures that persons authorised to issue an access authority, and

5

r. 6r. 6

Page 8: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

persons carrying out that work under an access authority—

(i) are competent to do so; and

(ii) are provided with appropriate training, procedures, tools, equipment and emergency support.

__________________

6

r. 6

Page 9: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

PART 2—SAFETY MANAGEMENT SCHEMES

Division 1—Content of electricity safety management scheme

7 Person responsible for supply network or installation, or carrying out of electrical work

An electricity safety management scheme must specify—

(a) in the case of an employer operator, the title of the position and the business address of the person who has ultimate responsibility for the management, control and safe carrying out of electrical work to which the scheme relates;

(b) in the case of an asset operator or a network operator, the title of the position and the business address of the person who has ultimate responsibility for the management, control and safe operation of the applicable asset.

8 Person responsible for electricity safety management scheme

An electricity safety management scheme must specify the title of the position of the person who is responsible for preparation and submission of the scheme.

9 Scheme description—employer operators

(1) An electricity safety management scheme submitted by an employer operator must contain a description of—

(a) the electrical work to which the scheme relates; and

r. 7

Reg. 7(b) amended by S.R. No. 131/2013 reg. 7.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

7

Page 10: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(b) the electrical installation or electrical equipment in relation to which that electrical work is or will be carried out.

(2) The description must provide sufficient information to enable Energy Safe Victoria to—

(a) identify the location, extent and scope of the electrical installation or electrical equipment requiring the electrical work; and

(b) assess the risks associated with the safety of the electrical installation or electrical equipment.

10 Scheme description—asset operators and network operators

(1) An electricity safety management scheme submitted by an asset operator or a network operator must contain a description of the design, construction, operation and maintenance of every applicable asset to which the scheme relates.

(2) The description must provide sufficient information to enable Energy Safe Victoria to identify the location, extent and scope of every applicable asset and to assess the risks associated with the safety of those applicable assets.

11 Formal safety assessment—asset operators and employer operators

(1) An electricity safety management scheme must contain a formal safety assessment relating to, as the case requires—

(a) the carrying out of electrical work for the employer operator; or

(b) the asset operator's applicable asset.

Reg. 10 (Heading) amended by S.R. No. 131/2013 reg. 8(1).

r. 10

Reg. 10(1) amended by S.R. No. 131/2013 reg. 8(2).

Reg. 11 (Heading) amended by S.R. No. 131/2013 reg. 9(1).

Reg. 11(1)(b) amended by S.R. No. 131/2013 reg. 9(2).

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

8

Page 11: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(2) The formal safety assessment must be consistent with the applicable scheme description and must provide—

(a) a description of the methodology used and investigations undertaken for the formal safety assessment; and

(b) an identification of hazards having the potential to cause a serious electrical incident; and

(c) a systematic assessment of the risks associated with, as the case requires—

(i) the electrical work that is carried out in relation to an electrical installation or electrical equipment; or

(ii) the applicable asset—

including the likelihood and consequences of a serious electrical incident; and

(d) a description of technical and other measures undertaken or to be undertaken to reduce those risks as far as practicable.

(3) In this regulation, applicable scheme description means—

(a) for electrical work that is to be carried out, the scheme description required by regulation 9;

(b) for an applicable asset, the scheme description required by regulation 10.

12 Exemptions to be specified

For the purpose of section 117 of the Act, an electricity safety management scheme submitted

r. 12Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

9

Page 12: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

under Division 3 of Part 10 of the Act must specify—

(a) all provisions of the regulations relating to—

(i) the installation and operation of electrical installations; or

(ii) supply networks—

from which the scheme operator seeks to be exempted; and

(b) in the case of a scheme under which a person authorised under the scheme to carry out a class or type of electrical work is to be exempt from compliance with—

(i) any of the regulations relating to the carrying out of that class or type of work; or

(ii) the provisions referred to in section 117(1) of the Act—

all provisions of the regulations relating to the carrying out of that class or type of work and the provisions referred to in that section from which the person seeks to be exempted; and

(c) in the case of a scheme under which a person carrying out a specified class or type of electrical work on the specified premises to which the scheme applies is to be exempt from compliance with—

(i) any of the regulations relating to the carrying out of that class or type of work; or

(ii) the provisions referred to in section 117(2) of the Act—

r. 12Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

10

Page 13: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

all provisions of the regulations relating to the carrying out of that class or type of work and the provisions referred to in that section from which the person seeks to be exempted.

Division 2—Content of safety management system—asset operators and employer operators

13 Safety management system

An electricity safety management scheme for an asset operator or an employer operator must specify a safety management system that complies with this Division to be followed in relation to the safety of, as the case requires—

(a) the electrical work carried out or to be carried out by the persons authorised by the employer operator; or

(b) the design, construction, operation, maintenance and decommissioning of the applicable asset owned or operated by the asset operator.

14 Safety policy

A safety management system referred to in regulation 13 must specify—

(a) the safety policy; and

(b) the titles of the positions and the duties of the persons responsible for the implementation of the safety policy.

15 Standards for works on applicable assets—where there are published technical standards

(1) This regulation applies if there are published technical standards that relate to the design,

Pt 2 Div. 2 (Heading) substituted by S.R. No. 131/2013 reg. 10.

Reg. 13 amended by S.R. No. 131/2013 reg. 11(1).

r. 13

Reg. 13(b) amended by S.R. No. 131/2013 reg. 11(2).

Reg. 14 amended by S.R. No. 131/2013 reg. 12.

Reg. 15(1) amended by S.R. No. 131/2013 reg. 13.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

11

Page 14: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

construction, commissioning, installation, operation, maintenance and decommissioning of an applicable asset owned or operated by the asset operator.

(2) A safety management system for the applicable asset must—

(a) list all of the published technical standards that the asset operator will comply with when designing, constructing, commissioning, installing, operating, maintaining and decommissioning the applicable asset; and

(b) if the asset operator chooses not to comply with a particular published technical standard, specify requirements for the design, construction, commissioning, installation, operation, maintenance and decommissioning of the applicable asset—

(i) that will ensure a level of safety in relation to those activities that is at least equal to or greater than the level of safety that would ensue from compliance with that standard; and

(ii) that the asset operator will comply with when carrying out those activities.

(3) If the safety management system complies with subregulation (2)(b), the safety management system must also include an explanation as to why compliance with subregulation (2)(b) was chosen.

16 Standards for works on applicable assets—where there are no published technical standards

r. 16Reg. 16(1) amended by S.R. No. 131/2013 reg. 14.

Reg. 15(2)(a) amended by S.R. No. 131/2013 reg. 13.

Reg. 15(2)(b) amended by S.R. No. 131/2013 reg. 13.

Reg. 15(2)(b)(ii) amended by S.R. No. 131/2013 reg. 13.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

12

Page 15: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(1) This regulation applies if there are no published technical standards that relate to the design, construction, commissioning, installation, operation, maintenance and decommissioning of an applicable asset owned or operated by the asset operator.

(2) A safety management system for the applicable asset must specify requirements for the design, construction, commissioning, installation, operation, maintenance and decommissioning of the applicable asset—

(a) that will ensure the requisite level of safety; and

(b) that the asset operator will comply with when carrying out those activities.

(3) The requisite level of safety is that the design, construction, commissioning, installation, operation, maintenance and decommissioning of the applicable asset—

(a) is adequate to ensure the safety of the public; and

(b) is adequate to minimise the risk of damage to another person's property; and

(c) is adequate to ensure the safety and safe operation of the applicable asset; and

(d) provides an adequate means of automatically isolating the applicable asset or any part of the applicable asset in the event of an emergency; and

(e) provides an adequate means of preventing unauthorised access to the applicable asset by a member of the public.

17 Technical standards for electrical work

Reg. 16(2)(b) amended by S.R. No. 131/2013 reg. 14.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

13

Page 16: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(1) A safety management system for electrical work carried out or to be carried out by persons authorised by an employer operator must—

(a) list every published technical standard that applies to the electrical work; and

(b) if the employer operator chooses not to comply with a particular published technical standard, specify requirements in relation to the carrying out of the electrical work that will ensure a level of safety in the carrying out of the work that is at least equal to or greater than the level of safety that would ensue from compliance with that standard.

(2) If the safety management system complies with subregulation (1)(b), the safety management system must also include an explanation as to why compliance with subregulation (1)(b) was chosen.

18 Applicable assets—asset management plan requirements

A safety management system must specify the asset management plan for an applicable asset by which an asset operator will ensure that the design, construction, commissioning, installation, operation, maintenance and decommissioning of the applicable asset and any modification of the applicable asset—

(a) is adequate to ensure the safety of the public; and

(b) is adequate to minimise the risk of damage to another person's property; and

(c) is adequate to ensure the safety and safe operation of the applicable asset; and

(d) takes into account the results of the formal safety assessment for the applicable asset; and

r. 17

Reg. 18 amended by S.R. No. 131/2013 reg. 15.

r. 18Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

14

Page 17: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(e) meets—

(i) the published technical standards listed in the safety management system in accordance with regulation 15(2)(a); or

(ii) the requirements specified in the safety management system in accordance with regulation 15(2)(b) or 16(2); and

(f) provide adequate means of automatically isolating the applicable asset or any part of the applicable asset in the event of an emergency; and

(g) provide adequate means of preventing unauthorised access by the public to the applicable asset.

19 Requirements in relation to electrical work

A safety management system for the carrying out of electrical work must specify the means by which an employer operator will ensure that the electrical work—

(a) is adequate for the safe operation of the electrical installation or electrical equipment in relation to which electrical work is carried out; and

(b) takes into account the results of the formal safety assessment for the scheme; and

(c) meets—

(i) the published technical standards listed in the safety management system in accordance with regulation 17(1)(a); or

(ii) the requirements specified in the safety management system in accordance with regulation 17(1)(b); and

(d) is carried out by the persons authorised to carry out the work.

r. 19Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

15

Page 18: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

20 Access authority systemr. 20

Reg. 20(1) amended by S.R. No. 131/2013 reg. 16.

(1) The safety management system for an electricity safety management scheme submitted by an asset operator must specify—

(a) the applicable asset or part of the applicable asset for which an access authority system needs to be established; and

(b) the access authority system that is to apply in respect of—

(i) the operation or maintenance of the applicable asset or the part of the applicable asset; or

(ii) work that is to be carried out on or near the applicable asset or part of the applicable asset.

(2) The safety management system for an electricity safety management scheme submitted under section 115 of the Act must specify—

(a) the electrical work carried out or to be carried out on or near an electrical installation or electrical equipment at the premises to which the scheme applies for which an access authority system needs to be established; and

(b) the access authority system that is to apply to that work.

21 Emergency preparedness

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

16

Page 19: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(1) A safety management system must specify a response plan designed to address all reasonably foreseeable emergencies which have been identified through the formal safety assessment.

(2) The response plan must—

(a) ensure the safety of the public; and

(b) minimise the risk of damage to another person's property; and

(c) specify a system for communications between the asset operator or employer operator (as the case requires) and any other person who may be affected by an emergency referred to in subregulation (1); and

(d) in the case of an asset operator, specify the means by which the asset operator will ensure the continued safety of the relevant applicable asset and its operation; or

(e) in the case of an employer operator, specify the means by which the employer operator will ensure the continued safety of electrical work being carried out on electrical installations and electrical equipment.

22 Internal monitoring, auditing and reviewingReg. 22(1) amended by S.R. No. 131/2013 reg. 18.r. 22

(1) A safety management system must specify the means by which the asset operator or the employer operator will—

(a) monitor and audit the implementation of the safety policies and procedures specified in the safety management system; and

Reg. 21(2)(c) amended by S.R. No. 131/2013 reg. 17(1).

Reg. 21(2)(d) amended by S.R. No. 131/2013 reg. 17(2).

Reg. 21(2)(e) amended by S.R. No. 131/2013 reg. 17(3).

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

17

Page 20: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(b) review the adequacy of those policies and procedures.

(2) A safety management system must specify the means to be used to ensure—

(a) regular and systematic identification of deficiencies in those policies and procedures and in their implementation; and

(b) systematic improvement in those policies and procedures and in their implementation.

23 Key performance indicators

A safety management system must specify—

(a) the key performance indicators to be used to determine the asset operator's or the employer operator's level of compliance with the electricity safety management scheme, the relevant provisions of the Act and the regulations made under the Act; and

(b) the process to be adopted to analyse the key performance indicators and to ensure that appropriate action is taken to improve compliance if required.

24 Incident recording, investigation and reviewing

A safety management system must specify—

(a) the means to be used for recording and investigating serious electrical incidents involving, as the case requires—

(i) an asset operator's applicable asset; or

r. 23

Reg. 23(a) amended by S.R. No. 131/2013 reg. 19.

Reg. 24(a)(i) amended by S.R. No. 131/2013 reg. 20.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

18

Page 21: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(ii) electrical work carried out by an electrical worker employed or engaged by an employer operator; and

(b) the management systems to be used for reviewing and taking action on the information so recorded or arising from those investigations.

25 Competence and training

(1) The safety management system for an electricity safety management scheme submitted by an asset operator must specify the work and staffing systems required for the safe design, construction, operation, maintenance and decommissioning of the asset operator's applicable asset to ensure that—

(a) the minimum level of qualifications, skill and competence that is required to perform those activities is established; and

(b) only persons with the appropriate qualifications, skills and competence are assigned to perform those activities; and

(c) any training necessary for persons assigned to perform those activities is provided.

(2) The safety management system for an electricity safety management scheme submitted by an employer operator must specify the work and staffing systems used in carrying out the electrical work to which the scheme relates to ensure that—

(a) the minimum level of qualifications, skill and competence that is required for the

Reg. 25(1) amended by S.R. No. 131/2013 reg. 21.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

19

Page 22: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

carrying out of the electrical work is established; and

(b) only persons with the qualifications, skills and competence appropriate to the work are assigned to carry out that work; and

(c) any training necessary for persons assigned to carry out the work is provided.

Division 3—Content of safety management system—network operators

25A Safety management system—MEC

For the purpose of section 99(2)(b) of the Act, the electricity safety management scheme for a supply network of an MEC must specify a safety management system that complies with AS 5577.

25B Safety management system—other network operator

(1) This regulation applies to a network operator who submits an electricity safety management scheme under section 116 of the Act.

(2) For the purpose of section 116(2)(b) of the Act, the electricity safety management scheme must specify a safety management system that complies with AS 5577.

__________________

r. 25

Pt 2 Div. 3 (Heading and regs 25A, 25B) inserted by S.R. No. 131/2013 reg. 22.

Reg. 25A inserted by S.R. No. 131/2013 reg. 22.

r. 25A

Reg. 25B inserted by S.R. No. 131/2013 reg. 22.

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

20

Page 23: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

PART 3—RECORDS AND REPORTING

26 Records

(1) An accepted ESMS operator must, in accordance with this regulation, establish and maintain a system for keeping records relating to its accepted ESMS.

Penalty:20 penalty units.

(2) The records required to be kept under subregulation (1) are—

(a) the accepted ESMS; and

(b) any revisions of the accepted ESMS; and

(c) any written audit reports of the accepted ESMS; and

(d) any reports of investigations of incidents involving—

(i) in the case of an employer operator, the carrying out of electrical work;

(ii) in the case of an MEC, the MEC's supply network; and

(e) a copy of each report given by the accepted ESMS operator to Energy Safe Victoria; and

(f) in the case of an employer operator, a register of the names and qualifications of persons nominated to carry out electrical work under the accepted ESMS.

(3) The records must be kept—

(a) at the address nominated by the accepted ESMS operator in the accepted ESMS; and

(b) in a manner that makes their retrieval reasonably practicable; and

r. 26Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

21

Page 24: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(c) in a secure manner; and

(d) for the period of 7 years after the creation of the record.

27 Asset operator and network operator requirements for reporting of serious electrical incidents

(1) For the purpose of section 142(1) and (2) of the Act, an electricity supplier that is an asset operator or a network operator must report a serious electrical incident in the form of a statistical summary on a quarterly basis.

(2) Despite subregulation (1), for the purpose of section 142(1) and (2) of the Act, an electricity supplier that is an asset operator or a network operator must report a serious electrical incident as soon as practicable after it occurs if the incident—

(a) causes the death of or injury to a person; or

(b) causes significant property damage; or

(c) causes significant disruption to the community; or

(d) involves a transmission line; or

(e) involves an imminent risk of electrocution.

(3) The report of a serious electrical incident to which subregulation (2) applies must specify, to the extent that the information is available to the asset operator or the network operator—

(a) the nature of the incident; and

(b) where and when the incident occurred; and

(c) particulars of any person involved in the incident; and

Reg. 27 (Heading) amended by S.R. No. 131/2013 reg. 23(1).

r. 27

Reg. 27(1) amended by S.R. No. 131/2013 reg. 23(2).

Reg. 27(2) amended by S.R. No. 131/2013 reg. 23(2).

Reg. 27(3) amended by S.R. No. 131/2013 reg. 23(3).

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

22

Page 25: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(d) whether any emergency service attended the incident.

(4) For the purpose of section 142(1) and (2) of the Act, an electricity supplier that is an asset operator or a network operator must in relation to a serious electrical incident for which the operator has reported under subregulation (2) report the following information as soon as practicable after the operator becomes aware of the information—

(a) the cause of the incident; and

(b) if an emergency service attended the incident, what action was required to be taken by the emergency service; and

(c) what remedial actions (if any) were taken by the asset operator or the network operator; and

(d) what actions are proposed by the relevant asset operator to prevent a repetition of the incident.

(5) In subregulation (2)—

transmission line means an electric line with a nominal voltage of more than 66 000 volts.

28 Asset operator and network operator reporting of incidents other than serious electrical incidents

(1) An electricity supplier that is an asset operator or a network operator must report to Energy Safe Victoria on a quarterly basis all specified electrical incidents in the form of a statistical summary.

Penalty:20 penalty units.

Reg. 27(4) amended by S.R. No. 131/2013 reg. 23(2).

Reg. 27(4)(c) amended by S.R. No. 131/2013 reg. 23(3).

r. 28

Reg. 28 (Heading) amended by S.R. No. 131/2013 reg. 24(1).

Reg. 28(1) amended by S.R. No. 131/2013 reg. 24(2).

Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

23

Page 26: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

(2) In subregulation (1)—

specified electrical incident means an electrical incident (other than a serious electrical incident) that resulted in—

(a) an electric shock from—

(i) the operator's supply network; or

(ii) an electrical installation supplied electricity by the operator's supply network; or

(b) a fire originating from the operator's supply network; or

(c) a part of the operator's supply network becoming dislodged from its supporting structure.

__________________

r. 28Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

24

Page 27: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

PART 4—GENERAL

29 Exemptions from regulation requirements

(1) Energy Safe Victoria may, on the application of the scheme operator, exempt an electricity safety management scheme from any of the requirements of these Regulations.

(2) An exemption under subregulation (1) may be subject to conditions (if any) specified by Energy Safe Victoria.

(3) An application must be in writing and state—

(a) the name, address and telephone number of the applicant; and

(b) the exemption requested; and

(c) the reasons for applying for the exemption. ═══════════════

r. 29Part 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

25

Page 28: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

ENDNOTES

1. General InformationThe Electricity Safety (Management) Regulations 2009, S.R. No. 165/2009 were made on 8 December 2009 by the Governor in Council under sections 150 and 157 of the Electricity Safety Act 1998, No. 25/1998 and came into operation on 13 December 2009: regulation 3.

The Electricity Safety (Management) Regulations 2009 will sunset 10 years after the day of making on 8 December 2019 (see section 5 of the Subordinate Legislation Act 1994).

EndnotesPart 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

26

Page 29: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

2. Table of AmendmentsThis Version incorporates amendments made to the Electricity Safety (Management) Regulations 2009 by statutory rules, subordinate instruments and Acts.

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

Electricity Safety (Management) Amendment Regulations 2013, S.R. No. 131/2013Date of Making: 29.10.13Date of Commencement: 1.11.13: reg. 3

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

EndnotesPart 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

27

Page 30: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

3. Explanatory Details

EndnotesPart 2—Safety Management Schemes

Electricity Safety (Management) Regulations 2009S.R. No. 165/2009

28

Page 31: Electricity Safety (Management) Regulations 2009FILE/09-165sr003.docx  · Web viewElectricity Safety (Management) Regulations 2009. ... an electrical installation or electrical equipment

1 Reg. 4(a): S.R. No. 140/1999. Reprint No. 1 incorporating amendments as at 18 September 2007. Reprinted to S.R. No. 149/2003.2 Reg. 4(b): S.R. No. 8/2001.3 Reg. 4(c): S.R. No. 149/2003.

——Table of Applied, Adopted or Incorporated Matter

The following table of applied, adopted or incorporated matter was included in S.R. No. 131/2013 in accordance with the requirements of regulation 5 of the Subordinate Legislation Regulations 2004.

Statutory rule provision

Title of applied, adopted or incorporated document

Matter in applied, adopted or incorporated document

Regulation 22, which inserts new Division 3 of Part 2 into the Electricity Safety (Management) Regulations 2009

AS 5577, "Electricity network safety management systems" published 12 April 2013 by Standards Australia

The whole