1 EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background In terms of the Bill of Rights, included in the Constitution of the Republic of South Africa of 1996, everyone has the right to have the environment protected and to live in an environment that is not harmful to human health or well-being. Legal instruments developed to ensure that this right is given effect to, include, inter alia, the EIA regulations promulgated in terms of the ECA and the NEMA. Both sets of EIA regulations, including the amendments thereto, identified activities that may result in substantial negative impacts on the environment. These regulations require(d) that an environmental impact assessment process be followed in respect of these identified activities and applications be submitted to the competent authority for consideration. Commencement with any of the listed activities identified by the legislation set out in Table 1below prior to obtaining authorization from the competent authority is (was) prohibited by the ECA and the NEMA and constitutes(d) an offence. Table 1 EIA Regulations Government Gazette Effective Dates EIA Regulations promulgated in terms of the ECA, Act No 73 of 1989 GNR 1182 & 1183: Government Gazette No 18261, Pretoria, 5 September 1997 08 September 1997 – end of day 09 May 2002. Amendment of the ECA EIA Regulations GNR 670 and GNR 672 of 10 May 2002, Government Gazette No 23401 10 May 2002 – end of day 02 July 2006. 2006 EIA Regulations promulgated in terms of the NEMA, Act No 107 of 1998 GNR 385, 386 and 387 Government Gazette No 28753, Pretoria, 21 April 2006 03 July 2006 – end of day 01 August 2010 2010 EIA Regulations promulgated in terms of the NEMA, Act No 107 of 1998 GNR 543, 544, 545 and 546 Government Gazette No 33306, Pretoria, 18 June 2010 02 August 2010 – end of day 07 December 2014 2014 EIA Regulations promulgated in terms of the NEMA, Act No 107 of 1998 GNR 982, 983, 984 and 985 Government Gazette No 38282, Pretoria, 04 December 2014 08 December 2014 – current

Transcript of EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated...

Page 1: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

1

EIA Listed activities & Time Lines

UPDATED: JANUARY 2015

Background

In terms of the Bill of Rights, included in the Constitution of the Republic of South Africa of 1996, everyone has the right to have the environment protected and to live in an environment that is not harmful to human health or well-being. Legal instruments developed to ensure that this right is given effect to, include, inter alia, the EIA regulations promulgated in terms of the ECA and the NEMA. Both sets of EIA regulations, including the amendments thereto, identified activities that may result in substantial negative impacts on the environment. These regulations require(d) that an environmental impact assessment process be followed in respect of these identified activities and applications be submitted to the competent authority for consideration. Commencement with any of the listed activities identified by the legislation set out in Table 1below prior to obtaining authorization from the competent authority is (was) prohibited by the ECA and the NEMA and constitutes(d) an offence.

Table 1

EIA Regulations

Government Gazette

Effective Dates

EIA Regulations promulgated in terms of the ECA, Act No 73 of 1989

GNR 1182 & 1183: Government Gazette No 18261, Pretoria, 5 September 1997

08 September 1997 – end of day 09 May 2002.

Amendment of the ECA EIA Regulations

GNR 670 and GNR 672 of 10 May 2002, Government Gazette No 23401

10 May 2002 – end of day 02 July 2006.

2006 EIA Regulations promulgated in terms of the NEMA, Act No 107 of 1998

GNR 385, 386 and 387 Government Gazette No 28753, Pretoria, 21 April 2006

03 July 2006 – end of day 01 August 2010

2010 EIA Regulations promulgated in terms of the NEMA, Act No 107 of 1998

GNR 543, 544, 545 and 546 Government Gazette No 33306, Pretoria, 18 June 2010

02 August 2010 – end of day 07 December 2014

2014 EIA Regulations promulgated in terms of the NEMA, Act No 107 of 1998

GNR 982, 983, 984 and 985 Government Gazette No 38282, Pretoria, 04 December 2014

08 December 2014 – current

Page 2: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

2

Application of Document

The following table has been produced in order to enable an EMI to:

Determine whether the activities undertaken by a proponent were listed in terms the previous sets of Regulations (including amendments thereto over time);

To determine the applicable Act & set of regulations

contravened;

To determine the applicable contravention (specific listed activity); and

To ensure that the correct listed activities and Act are applied in any consequent enforcement action.

Listed Activities as from 08 September 2012.

This document was last updated in January 2015.

This document serves as reference and supportive text only and cannot take the place of legal advice in a specific situation governed by legislation.

This document will not take the place of any regulations published by DEA.

Activities must be double-checked and quoted from the relevant Government notices (including amendments thereto), and not from this document.

This document has been developed for EMI Enforcement & S24G purposes.

Page 3: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

3

08 September 1997 – end of day 09 May 2002.

EIA Regulations promulgated in terms of the ECA, Ac t No 73 of 1989 - GNR 1182 & 1183: Government Gazet te No 18261, Pretoria, 5 September 1997

Activity 1(a) The construction or upgrading of facilities for com mercial electricity generation and supply.

Activity 1(b)

The construction or upgrading of nuclear reactors a nd installations for the production, enrichment, re processing and disposal of nuclear fuels and wastes

Activity 1(d)

The construction or upgrading of roads, railways, a irfields and associated structures outside the bord ers of town planning schemes.

Activity 1(e)

The construction or upgrading of- marinas, harbours and all structures below the high-water mark of th e sea.

Activity 1(f)

The construction or upgrading of cableways and asso ciated structures

Activity 1(h)

The construction or upgrading of racing tracks for motor-powered vehicles and horse racing, but not in cluding indoor tracks

Activity 1(m)

The construction or upgrading of public and private resorts and associated infrastructure

Activity 7

The reclamation of land below the high-water mark o f the sea and in inland water including wetlands

05 January 1998 – end of day 09 May 2002.

EIA Regulations promulgated in terms of the ECA, Ac t No 73 of 1989 - GNR 1182 & 1183: Government Gazet te No 18261, Pretoria, 5 September 1997

Activity 1(g) The construction or upgrading of structures associa ted with communication networks, other than telecom munication lines and cables, as well as access roads leading to these structures

Activity 1(o)

The construction or upgrading of buildings and stru ctures for industrial and military manufacturing an d storage of explosives or ammunition or for testin g or disposal of such explosives or ammunition

Activity 3

The concentration of livestock in a confined struct ure for the purpose of mass commercial production

Page 4: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

4

Activity 4

The intensive husbandry of, or importation of, any plant or animal that has been declared a weed or an invasive alien species

Activity 5

The release of any organism outside its natural are a of distribution that is to be used for biological pest control

Activity 6

The genetic modification of any organism with the p urpose of fundamentally changing the inherent chara cteristics of that organism

02 March 1998 – end of day 09 May 2002.

EIA Regulations promulgated in terms of the ECA, Ac t No 73 of 1989 - GNR 1182 & 1183: Government Gazet te No 18261, Pretoria, 5 September 1997

Activity 1(c) The construction or upgrading of transportation rou tes and structures, and manufacturing, storage, han dling or processing facilities for any substance which is dangerous or hazardous and is controlled b y national legislation

Activity 1(i)

The construction or upgrading of canals and channel s, including diversions of the normal flow of water in a river bed and water transfer schemes between water catchments and impoundments

Activity 1(j)

The construction or upgrading of dams, levees and w eirs affecting the flow of a river

Activity 1(k)

The construction or upgrading of reservoirs for pub lic water supply

Activity 1(l)

The construction or upgrading of schemes for the ab straction or utilisation of ground or surface water for bulk supply purposes

Activity 1(n)

The construction or upgrading of sewage treatment p lants and associated infrastructure

Activity 8

The disposal of waste in terms of section 20 of the Environment Conservation Act, 1989

Activity 9

Scheduled processes listed in the Second Schedule t o the Atmospheric Pollution Prevention Act, 1965 (A ct No. 45 of 1965).

Page 5: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

5

01 April 1998 – end of day 09 May 2002.

EIA Regulations promulgated in terms of the ECA, Ac t No 73 of 1989 - GNR 1182 & 1183: Government Gazet te No 18261, Pretoria, 5 September 1997

Activity 2(c) The change of land use from agricultural or undeter mined use to any other land use

Activity 2(d)

The change of land use for grazing to any other for m of agricultural use

Activity 2(e)

The change of land use for use for nature conservat ion or zoned open space to any other land use

10 May 2002 – end of day 02 July 2006.

Amendment of the ECA EIA Regulations promulgated in terms of the ECA, Act No 73 of 1989 - GNR 670 and GNR 672 of 10 May 2002, Government Gazette No 23401

Activity 1(a) The construction, erection or upgrading of faciliti es for commercial electricity generation with an ou tput of at least 10 megawatts and / or infrastructu re for bulk supply

Activity 1(b)

The construction or upgrading of nuclear reactors a nd facilities for the production, enrichment, proce ssing, reprocessing, storage or disposal of nuclear fuels and wastes

Activity 1(c)

The construction or upgrading of transportation rou tes and structures, and manufacturing, storage, han dling or processing facilities with regard to any substance which is dangerous or hazardous and is co ntrolled by national legislation, including: (i) infrastructure, excluding road and rail, fo r the transportation of any such substance; and (ii) manufacturing, storage, handling, treatment or processing facilities for any such substance.

Activity 1(d)

The construction or upgrading of roads, railways, a irfields and associated structures.

Activity 1(e)

The construction or upgrading of marinas, harbours and all structures below the high-water mark of the sea and marinas, harbours and associated structures on inland waters

Activity 1(f)

The construction or upgrading of above ground cable ways and associated structures

Activity 1(g)

The construction or upgrading of structures associa ted with communication networks, including masts, t owers and reflector dishes, marine telecommunication lines and cables and access roads leading to those structures, but not including abo ve ground and underground telecommunication lines and cables and those reflector dishes used ex clusively for domestic purposes

Page 6: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

6

Activity 1(h)

The construction or upgrading of racing tracks for motor-powered vehicles and horse racing, but not in cluding indoor tracks

Activity 1(i)

The construction or upgrading of canals and channel s, including structures causing disturbances to th e flow of water in a river bed, and water transfer schemes between water catchments and impoundments

Activity 1(i)

The construction or upgrading of dams, levees and w eirs affecting the flow of a river

Activity 1(k)

The construction or upgrading of reservoirs for pub lic water supply

Activity 1(l)

The construction or upgrading of schemes for the ab straction or utilisation of ground or surface water for bulk supply purposes

Activity 1(m)

The construction or upgrading of public and private resorts and associated infrastructure

Activity 1(n)

The construction or upgrading of sewage treatment p lants and associated infrastructure

Activity 1(o)

The commenced with the construction or upgrading of buildings and structures for industrial, commercia l and military manufacturing and storage of explosives or ammunition or for testing or disposal of such explosives or ammunition

Activity 2(c)

The change of land use from agricultural or zoned u ndetermined use or an equivalent zoning, to any oth er land use

Activity 2(d)

The change of land use for grazing to any other for m of agricultural use

Activity 2(e)

The change of land use for use for nature conservat ion or zoned open space to any other land use

Activity 3

The concentration of livestock, aquatic organisms, poultry and game in a confined structure for the pu rpose of commercial production, including aquaculture and mariculture

Activity 4

The intensive husbandry of, or importation of, any plant or animal that has been declared a weed or an invasive alien species

Activity 5

The release of any organism outside its natural are a of distribution that is to be used for biological pest control

Activity 6

The genetic modification of any organism with the p urpose of fundamentally changing the inherent chara cteristics of that organism

Activity 7

The reclamation of land, including wetlands, below the high-water mark of the sea, and in inland water s

Activity 8

The disposal of waste as defined in section 20 of t he Act, excluding domestic waste, but including the establishment, expansion, upgrading or closure of

Page 7: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

7

facilities for all waste, ashes and building rubble

Activity 9

Scheduled processes listed in the Second Schedule t o the Atmospheric Pollution Prevention Act, 1965 (A ct No. 45 of 1965).

03 July 2006 – end of day 02 July 2009.

2006 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 385, 386 and 387 Gover nment Gazette No 28753, Pretoria, 21 April 2006

Activity 1(o) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the recycling, re-use, handling, temporary stora ge or treatment of general waste with a throughput capaci ty of 20 cubic metres or more daily average measure d over a period of 30 days, but less than 50 tons daily average measured over a period of 30 days. Activity repealed on 03 July 2009 - refer to the Go vernment Gazette 32369 - From this date included in the NEMWA.

Activity 1(p) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the temporary storage of hazardous waste. Activity repealed on 03 July 2009 - refer to the Go vernment Gazette 32369 - From this date included in the NEMWA.

Activity 1(s) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the treatment of effluent, wastewater or sewage with an annual throughput capacity of more than 2 000 cubic metres but less than 15 000 cubic metres; Activity repealed on 03 July 2009 - refer to the Go vernment Gazette 32369 - From this date included in the NEMWA.

Activity 23 of GNR 386

The decommissioning of existing facilities or infra structure, other than facilities or infrastructure that commenced under an environmental authorisation issued in terms of the Environmental Impact Assessm ent Regulations, 2006 made under section 24(5) of t he Act and published in Government Notice No. R. 385 of 2006, for - d. the disposal of waste; e. the treatment of effluent, wastewater and sewage with an annual throughput capacity of 15 000 cubic metres or more; f. the recycling, handling, temporary storage or tr eatment of general waste with a daily throughput ca pacity of 20 cubic metres or more; or g. the recycling, handling, temporary storage or tr eatment of hazardous waste. Activity repealed on 03 July 2009 - refer to the Go vernment Gazette 32369 - From this date included in the NEMWA.

Activity 24 of GNR 386

The recommissioning or use of any facility or infra structure, excluding any facility or infrastructure that commenced under an environmental authorisatio n issued in terms of the Environmental Impact Assessm ent Regulations, 2006 made under section 24(5) of t he Act and published in Government Notice No. R. 385 of 2006, after a period of two years from closu re or temporary closure, for -

Page 8: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

8

i. electric ity generation; ii. nuclear reactors and nuclear fuel storage; or iii. facilities for any process or activity, which require permission, authorisation, or further autho risation, in terms of legislation governing the rel ease

of emissions, pollution, effluent or waste prior to the facility being recommissioned.

Activity 25 of GNR 386

The expansion of or changes to existing facilities for any process or activity, which requires an amen dment of an existing permit or license or a new per mit or license in terms of legislation governing the re lease of emissions, pollution, effluent.

Activity 1(f) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the recycling, re-use, handling, temporary stora ge or treatment of general waste with a throughput capaci ty of 50 tons or more daily average measured over a period of 30 days.

Activity 1(g) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the use, recycling, handling, treatment, storage or final disposal of hazardous waste.

Activity 1(o) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the final disposal of general waste covering an area of 100 square metres or more or 200 cubic metres or mo re of airspace.

Activity 1(p) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the treatment of effluent, wastewater or sewage with an annual throughput capacity of 15 000 cubic metres o r more.

Activity 1(q) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the incineration, burning, evaporation, thermal treatment, roasting or heat sterilisation of waste or effluent, including the cremation of human or an imal tissue.

Activity 1(r) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the microbial deactivation, chemical sterilisati on or non-thermal treatment of waste or effluent.

03 July 2006 – end of day 02 July 2009.

2006 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 385, 386 and 387 Govern ment Gazette No 28753, Pretoria, 21 April 2006

Activity 24(c) of GNR 386

The recommissioning or use of any facility or infra structure, excluding any facility or infrastructure that commenced under an environmental authorisatio n issued in terms of the Environmental Impact Assessm ent Regulations, 2006 made under section 24(5) of t he Act and published in Government Notice No. R. 385 of 2006, after a period of two years from closu re or temporary closure, for facilities for any pro cess or activity, which require permission, authori sation, or further authorisation, in terms of legislation g overning the release of emissions, pollution, efflu ent or waste prior to the facility being recommissi oned.

Page 9: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

9

Activity 25 of GNR 386

The expansion of or changes to existing facilities for any process or activity, which requires an amen dment of an existing permit or license or a new per mit or license in terms of legislation governing the re lease of emissions, pollution, effluent.

Activity 1(e) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or any process or activity which requires a permit or license in terms of legislation governing the gener ation or release of emissions, pollution, effluent or waste and which is not identified in Government Notice No. R. 386 of 2006.

03 July 2006 – end of day 08 October 2009.

2006 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 385, 386 and 387 Govern ment Gazette No 28753, Pretoria, 21 April 2006

Activity 1(i) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the extraction or processing of natural gas incl uding gas from landfill sites.

03 July 2009 – end of day 01 August 2010.

2006 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 385, 386 and 387 Govern ment Gazette No 28753, Pretoria, 21 April 2006

Activity 24(c) of GNR 386

The recommissioning or use of any facility or infra structure, excluding any facility or infrastructure that commenced under an environmental authorisatio n issued in terms of the Environmental Impact Assessm ent Regulations, 2006 made under section 24(5) of t he Act and published in Government Notice No. R. 385 of 2006, after a period of two years from closu re or temporary closure, for facilities for any pr ocess or activity, which require permission, author isation, or further authorisation, in terms of legislation g overning the release of emissions, pollution, efflu ent or waste prior to the facility being recommissi oned unless the facility for the process or activity is included in the list of waste management activities published in terms of section 19 of the National Environmental Management: Waste Act, 2008 (Act No. 59 of 2008) in which case the activity is regarded to be excluded from the list”.

Activity 1(e) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or any process or activity which requires a permit or license in terms of legislation governing the gener ation or release of emissions, pollution, effluent or waste and which is not identified in Government Notice No. R. 386 of 2006, or included in the list of waste management activities published in terms of section 19 of the National Environmental Management: Waste Act, 2008 (Act No. 59 of 2008) in which case the activity is regarded to be excluded from the list”.

Page 10: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

10

03 July 2006 – end of day 01 August 2010.

2006 EIA Regulations promulgated in terms of the NE MA, Act No 107 of 1998: GNR 385, 386 and 387 Go vernment Gazette No 28753, Pretoria, 21 April 2006

Activity 1(a) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the generation of electricity where the electric ity output is more than 10 megawatts but less than 20 megawatt s.

Activity 1(b) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the above ground storage of 1 000 tons or more b ut less than 100 000 tons of ore.

Activity 1(c) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the storage of 250 tons or more but less than 1 00 000 tons of coal.

Activity 1(d) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or resorts, lodges, hotels or other tourism and hos pitality facilities in a protected area contemplated in the National Environmental Management: Protected Areas Act, 2003 (Act No. 57 of 2003).

Activity 1(e) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or any purpose where lawns, playing fields or sport s tracks

covering an area of more than three hectares, but l ess than 10 hectares, will be established;

Activity 1(f) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or sport spectator facilities with the capacity to hold 8 000 spectators or more.

Activity 1(g) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the slaughter of animals with a product throughp ut of 10 000 kilograms or more per year.

Activity 1(h) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the the concentration of animals for the purpose of duction in densities that exceed - i. 20 square metres per head of cattle and more tha n 500 head of cattle per facility per year; ii. eight square meters per sheep and more than 1 0 00 sheep per facility per year; iii. eight square metres per pig and more than 250 pigs per facility per year excluding piglets that a re not yet weaned; iv. 30 square metres per crocodile at any level of production, excluding crocodiles younger than 6 mon ths; v. three square metres per head of poultry and more than 250 poultry per facility at any time, excludi ng chicks younger than 20 days; vi. three square metre per rabbit at and more than 250 rabbits per facility at any time; or vii. 100 square metres per ostrich and more than 50 ostriches per facility per year or 2500 square met res per breeding pair.

Activity 1(i) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or aquaculture production, including mariculture an d algae farms, with a product throughput of 10 000 ki lograms or more per year

Activity 1(j) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or agri-industrial purposes, outside areas with an existing land use zoning for industrial purposes, that cover an area of 1 000 square metres or more.

Page 11: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

11

Activity 1(k) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the bulk transportation of sewage and water, inc luding storm water, in pipelines with - i. an internal diameter of 0,36 metres or more; or ii. a peak throughput of 120 litres per second or m ore.

Activity 1(l) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the transmission and distribution of electricity above ground with a capacity of more than 33 kilovolts an d less than 120 kilovolts.

Activity 1(m) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or any purpose in the one in ten year flood line of a river or stream, or within 32 metres from the bank of a rive r or stream where the flood line is unknown, exclud ing purposes associated with existing residential u se, but including - i. canals; ii. channels; iii. bridges; iv. dams; and v. Weirs.

Activity 1(n) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the off-stream storage of water, including dams and reservoirs, with a capacity of 50 000 cubic metres or more, unless such storage falls within the ambit of the activity listed in item 6 of Government Not ice No. R. 387 of 2006.

Activity 1(o) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the recycling, re-use, handling, temporary stora ge or treatment of general waste with a throughput capaci ty of 20 cubic metres or more daily average measure d over a period of 30 days, but less than 50 tons daily average measured over a period of 30 days.

Activity 1(p) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the temporary storage of hazardous waste.

Activity 1(q) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the landing, parking and maintenance of aircraf t including - i. helicopter landing pads, excluding helicopter la nding facilities and stops used exclusively by emer gency services; ii. unpaved aircraft landing strips shorter than 1, 4km; iii. structures for equipment and aircraft storage; iv. structures for maintenance and repair; v. structures for fuelling and fuel storage; and vi. structures for air cargo handling.

Activity 1(r) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the outdoor racing of motor powered vehicles inc luding - (i) motorcars; (ii) trucks; (iii) motorcycles; (iv) quad bikes;

Page 12: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

12

(v) boats; and (vi) jet skis.

Activity 1(s) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the treatment of effluent, wastewater or sewage with an annual throughput capacity of more than 2 000 cubic metres but less than 15 000 cubic metres;

Activity 1(t) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or marinas and the launching of watercraft on inlan d fresh water systems.

Activity 1(u) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or above ground cableways and funiculars.

Activity 1(v) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or advertisements as defined in classes 1(a), 1(b), 1(c), 3(a), 3(b), 3(l) of the South African Manual for Ou tdoor Advertising Control.

Activity 2 of GNR 386

Construction or earth moving activities in the sea or within 100 metres inland of the high-water mark of the sea, in respect of – a) facilities for the storage of material and the m aintenance of vessels; b) fixed or floating jetties and slipways; c) tidal pools; d) embankments; e) stabilising walls; f) buildings; or g) infrastructure.

Activity 3 of GNR 386

The prevention of the free movement of sand, includ ing erosion and accretion, by means of planting veg etation, placing synthetic material on dunes and exposed sand surfaces within a distance of 100 metr es inland of the high-water mark of the sea.

Activity 4 of GNR 386

The dredging, excavation, infilling, removal or mov ing of soil, sand or rock exceeding 5 cubic metres from a river, tidal lagoon, tidal river, lake, in-s tream dam, floodplain or wetland.

Activity 5 of GNR 386

The removal or damaging of indigenous vegetation of more than 10 square metres within a distance of 10 0 metres inland of the high-water mark of the sea.

Activity 6 of GNR 386

The excavation, moving, removal, depositing or comp acting of soil, sand, rock or rubble covering an ar ea exceeding 10 square metres in the sea or within a distance of 100 metres inland of the high-water mar k of the sea.

Activity 7 of GNR 386

The above ground storage of a dangerous good, inclu ding petrol, diesel, liquid petroleum gas or paraff in, in containers with a combined capacity of more than 30 cubic metres but less than 1 000 cubic metr es at any one location or site

Page 13: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

13

Activity 10 of GNR 386

The establishment of cemeteries.

Activity 11 of GNR 386

The decommissioning of a dam where the highest part of the dam wall, as measured from the outside toe of the wall to the highest part of the wall, is 5 metres or higher or where the high-water mark of th e dam covers an area of more than 10 hectares.

Activity 12 of GNR 386

The transformation or removal of indigenous vegetat ion of 3 hectares or more or of any size where the transformation or removal would occur within a critically endangered or an endangered ecosystem li sted in terms of section 52 of the National Environ mental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).

Activity 13 of GNR 386

The abstraction of groundwater at a volume where an y general authorisation issued in terms of the Nati onal Water Act, 1998 (Act No. 36 of 1998) will be exceeded.

Activity 14 of GNR 386

The construction of masts of any material or type a nd of any height, including those used for telecomm unication broadcasting and radio transmission, but excluding - a) masts of 15 metres and lower exclusively used

i. by radio amateurs; or ii. for lighting purposes

b) flag poles; and c) lightning conductor poles.

Activity 15of GNR 386

The construction of a road that is wider than 4 met res or that has a reserve wider than 6 metres, excl uding roads that fall within the ambit of another l isted activity or which are access roads of less than 30 metres long.

Activity 16 of GNR 386

The transformation of undeveloped, vacant or dereli ct land to – a) establish infill development covering an area of 5 hectares or more, but less than 20 hectares; or b) residential, mixed, retail, commercial, industri al or institutional use where such development doe s not constitute infill and where the total area to be

transformed is bigger than 1 hectare.

Activity 17 of GNR 386

Phased activities where any one phase of the activi ty may be below a threshold specified in this Sched ule but where a combination of the phases, includin g expansions or extensions, will exceed a specified t hreshold.

Activity 18 of GNR 386

The subdivision of portions of land 9 hectares or l arger into portions of 5 hectares or less

Activity 19

The development of a new facility or the transforma tion of an existing facility for the conducting of manufacturing processes, warehousing, bottling, packaging, or storage, which, including associated structures or infrastructure, occupies an area of 1 000 square metres or more outside an existing area zoned for industrial purposes.

Page 14: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

14

Activity 20 of GNR 386

The transformation of an area zoned for use as publ ic open space or for a conservation purpose to anot her use.

Activity 21 of GNR 386

The release of genetically modified organisms into the environment in instances where assessment is re quired by the Genetically Modified Organisms Act, 1997 (Act No. 15 of 1997) or the National Environme ntal Management: Biodiversity Act, 2004 (Act No. 10 of 2004).

Activity 22 of GNR 386

The release of any organism outside its natural are a of distribution that is to be used for biological pest control.

Activity 23 of GNR 386

The decommissioning of existing facilities or infra structure, other than facilities or infrastructure that commenced under an environmental authorisation issued in terms of the Environmental Impact Assessm ent Regulations, 2006 made under section 24(5) of t he Act and published in Government Notice No. R. 385 of 2006, for - a) electricity generation; b) nuclear reactors and storage of nuclear fuel; c) industrial activities where the facility or the land on which it is located is contaminated or has the potential to be contaminated by any material wh ich

may place a restriction on the potential to re-use the site for a different purpose;

Activity 24 of GNR 386

The recommissioning or use of any facility or infra structure, excluding any facility or infrastructure that commenced under an environmental authorisatio n issued in terms of the Environmental Impact Assessm ent Regulations, 2006 made under section 24(5) of t he Act and published in Government Notice No. R. 385 of 2006, after a period of two years from closu re or temporary closure, for - a. electricity generation; b. nuclear reactors and nuclear fuel storage; or

Activity 1(a) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the generation of electricity where – i. the electricity output is 20 megawatts or more; or ii. the elements of the facility cover a combined area in excess of 1 hectare;

Activity 1(b) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or nuclear reaction including the production, enric hment, processing, reprocessing, storage or disposal of nu clear fuels, radioactive products and waste.

Activity 1(c) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the above ground storage of a dangerous good, including petrol, diesel, liquid petroleum gas or p araffin, in containers with a combined capacity of 1 000 cubic metres or more at any one location or site including the storage of one or more dangerous good s, in a tank farm

Activity 1(d) of GNR 386

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the refining of gas, oil and petroleum products.

Activity 1(h) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the manufacturing, storage or testing of explosi ves, including ammunition, but excluding licensed retail outlets and the legal end use of such explosives.

Activity 1(j) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the bulk transportation of dangerous goods using pipelines, funiculars or conveyors with a throughpu t capacity of 50 tons or 50 cubic metres or more pe r day.

Page 15: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

15

Activity 1(k) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the landing, parking and maintenance of aircraft , excluding unpaved landing strips shorter than 1,4 k ilometres in length, but including – i. airports; ii. runways; iii. waterways; or iv. structures for engine testing.

Activity 1(l) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the transmission and distribution of above groun d electricity with a capacity of 120 kilovolts or mor e.

Activity 1(m) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or marine telecommunications

Activity 1(n) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the transfer of 20 000 cubic metres or more wate r between water catchments or impoundments per day.

Activity 1(s) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or rail transportation, excluding railway lines and sidings in industrial areas and underground railway lines in m ines, but including –

i. railway lines; ii. stations; or iii. shunting yards.

Activity 1(t) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or any purpose where lawns, playing fields or sport s tracks covering an area of 10 hectares or more, will be es tablished.

Activity 2 of GNR 387

Any development activity, including associated stru ctures and infrastructure, where the total area of the developed area is, or is intended to be, 20 hec tares or more.

Activity 3 of GNR 387

The construction of filling stations, including ass ociated structures and infrastructure, or any other facility for the underground storage of a dangerou s good, including petrol, diesel, liquid petroleum ga s or paraffin.

Activity 4 of GNR 387

The extraction of peat.

Activity 5 of GNR 387

The route determination of roads and design of asso ciated physical infrastructure, including roads tha t have not yet been built for which routes have bee n determined before the publication of this notice an d which has not been authorised by a competent auth ority in terms of the Environmental Impact Assessment Regulations, 2006 made under section 24( 5) of the Act and published in Government Notice No . R. 385 of 2006, where – a) it is a national road as defined in section 40 o f the South African National Roads Agency Limited a nd National Roads Act, 1998 (Act No. 7 of 1998); b) it is a road administered by a provincial author ity; c) the road reserve is wider than 30 metres; or d) the road will cater for more than one lane of tr affic in both directions.

Page 16: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

16

Activity 6 of GNR 387

The construction of a dam where the highest part of the dam wall, as measured from the outside toe of the wall to the highest part of the wall, is 5 metr es or higher or where the high-water mark of the dam cove rs an area of 10 hectares or more.

Activity 9 of GNR 387

Construction or earth moving activities in the sea or within 100 metres inland of the high-water mark of the sea, excluding an activity listed in item 2 of Government Notice No. R. 386 of 2006 but including construction or earth moving activities in respect of – a) facilities associated with the arrival and depar ture of vessels and the handling of cargo; b) piers; c) inter- and sub-tidal structures for entrapment o f sand; d) breakwater structures; e) rock revetments and other stabilising structures ; f) coastal marinas; g) coastal harbours; h) structures for draining parts of the sea; i) tunnels; or j) underwater channels.

Activity 10 of GNR 387

Any process or activity identified in terms of sect ion 53(1) of the National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).

09 October 2009 – end of day 01 August 2010.

2006 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 385, 386 and 387 Govern ment Gazette No 28753, Pretoria, 21 April 2006

Activity 1(i) of GNR 387

The construction of facilities or infrastructure, i ncluding associated structures or infrastructure, f or the extraction or processing of natural gas excl uding gas from landfill sites.

Page 17: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

17

02 August 2010 – end of day 07 December 2014

GNR 544: 2010 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 543, 544, 54 5 and 546 Government Gazette No 33306, Pretoria, 10 June 2010

Activity 1 of GNR 544

The construction of facilities or infrastructure fo r the generation of electricity where: (i) the electricity output is more than 10 megaw atts but less than 20 megawatts; or

(ii) the output is 10 megawatts or less but the tot al extent of the facility covers an area in excess of 1 hectare.

Activity 2 of GNR 544

The construction of facilities or infrastructure fo r the storage of ore or coal that requires an atmos pheric emissions license in terms of the National Environmental Management: Air Quality Act (Act No. 39 of 2004).

Activity 3 of GNR 544

The construction of facilities or infrastructure fo r the slaughter of animals with a product throughpu t of: (i) poultry exceeding 50 poultry per day; or (ii) game and red meat exceeding 6 units per day.

Activity 4 of GNR 544

The construction of facilities or infrastructure fo r the concentration of animals for the purpose of c ommercial production in densities that exceed— (i) 20 square metres per large stock unit and more than 500 units, per facility; (ii) 8 square meters per small stock unit and;

a. more than 1 000 units per facility excluding pi gs where (b) will apply; b. more than 250 pigs per facility excluding piglet s that are not yet weaned;

(iii) 30 square metres per crocodile at any level o f production, excluding crocodiles younger than 6 m onths; (iv) 3 square metre per rabbit and more than 500 ra bbits per facility; or (v) 250 square metres per ostrich or emu and more t han 50 ostriches or emus per facility; or 2500 squa re metres per breeding pair. [Corrected by “Correction Notice 1” of 30 July 2010 , GN No. R. 660, and “Correction Notice 2” of 10 De cember 2010, GN No. R. 1159]

Activity 5 of GNR 544

The construction of facilities or infrastructure fo r the concentration of:

(i) more than 1 000 poultry per facility situated w ithin an urban area, excluding chicks younger than 20 days

(ii) more than 5 000 poultry per facility situated outside an urban area, excluding chicks younger tha n 20 days,

Activity 6 of GNR 544

The construction of facilities, infrastructure or s tructures for aquaculture of: (i) finfish, crustaceans, reptiles or amphibians wh ere such facility, infrastructure or structures wil l have a production output exceeding 20 000 kg but less

than 200 000 kg per annum (wet weight); (ii) molluscs where such facility, infrastructure o r structures will have a production output exceedin g 30 000 kg but not exceeding 150 000 kg per annum (wet

weight); (iii) aquatic plants where such facility, infrastru cture or structures will have a production output exceeding 60 000 kg but not exceeding 200 000 kg pe r

annum (wet weight); excluding where the construction of facilities, inf rastructure or structures is for purposes of offsho re cage culture in which case activity 7 in this No tice will apply.

Page 18: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

18

Activity 7 of GNR 544

The construction of facilities, infrastructure or s tructures for aquaculture of offshore cage culture of finfish, crustaceans, reptiles, amphibians, moll uscs and aquatic plants where the facility, infrastructure o r structures will have a production output exceedin g 50 000 kg but not exceeding 100 000 kg per annum (wet weight).

Activity 8 of GNR 544

The construction of a hatchery or agri-industrial i nfrastructure outside industrial complexes where th e development footprint covers an area of 2 000 squ are metres or more.

Activity 9 of GNR 544

The construction of facilities or infrastructure ex ceeding 1000 metres in length for the bulk transpor tation of water, sewage or storm water - (i) with an internal diameter of 0,36 metres or mor e; or (ii) with a peak throughput of 120 litres per secon d or more, excluding where: a. such facilities or infrastructure are for b ulk transportation of water, sewage or storm water or storm water drainage inside a road reserve; or b. where such construction will occur within u rban areas but further than 32 metres from a waterc ourse, measured from the edge of the watercourse.

Activity 10 of GNR 544

The construction of facilities or infrastructure fo r the transmission and distribution of electricity - (i) outside urban areas or industrial complexes wit h a capacity of more than 33 but less than 275 kilo volts; or (ii) inside urban areas or industrial complexes wit h a capacity of 275 kilovolts or more.

Activity 11 of GNR 544

The construction of:

(i) canals; (ii) channels; (iii) bridges; (iv) dams; (v) weirs; (vi) bulk storm water outlet structures; (vii) marinas; (viii) jetties exceeding 50 square metres in size; (ix) slipways exceeding 50 square metres in size; (x) buildings exceeding 50 square metres in size; o r (xi) infrastructure or structures covering 50 squar e metres or more

where such construction occurs within a watercourse or within 32 metres of a watercourse, measured fro m the edge of a watercourse, excluding where such construction will occur behind the development setback line.

Activity 12 of GNR 544

The construction of facilities or infrastructure fo r the off-stream storage of water, including dams a nd reservoirs, with a combined capacity of 50000 cu bic metres or more, unless such storage falls within th e ambit of activity 19 of Notice 545 of 2010;

Activity 13 of GNR 544

The construction of facilities or infrastructure fo r the storage, or for the storage and handling, of a dangerous good, where such storage occurs in containers with a combined capacity of 80 but not e xceeding 500 cubic metres;

Activity 14 of GNR 544

The construction of structures in the coastal publi c property where the development footprint is bigge r than 50 square metres, excluding (i) the construction of structures within existing ports or harbours that will not increase the develo pment footprint or throughput capacity of the port or harbour; (ii) the construction of a port or harbour, in whic h case activity 24 of Notice 545 of 2010 applies; (iii) the construction of temporary structures with in the beach zone where such structures will be dem olished or disassembled after a period not exceedin g 6 weeks.

Page 19: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

19

Activity 15 of GNR 544

The construction of facilities for the desalination of sea water with a design capacity to produce mor e than 100 cubic metres of treated water per day.

Activity 16 of GNR 544

Construction or earth moving activities in the sea, an estuary, or within the littoral active zone or a distance of 100 metres inland of the high-water m ark of the sea or an estuary, whichever is the greater, in respect of – (i) fixed or floating jetties and slipways; (ii) tidal pools; (iii) embankments; (iv) rock revetments or stabilising structures incl uding stabilising walls; (v) buildings of 50 square metres or more; or (vi)infrastructure covering 50 square metres or mor e – but excluding (a) if such construction or earth moving activities will occur behind a development setback line; or (b) where such construction or earth moving activit ies will occur within existing ports or harbours an d the construction or earth moving activities will not increase the development footprint or throughput ca pacity of the port or harbour; (c) where such construction or earth moving activit ies is undertaken for purposes of maintenance of t he facilities mentioned in (i)-(vi) above; or (d) where such construction or earth moving activit ies is related to the construction of a port or har bour, in which case activity 24 of Notice 545 of 20 10 applies.

Activity 17 of GNR 544

The planting of vegetation or placing of any materi al on dunes and exposed sand surfaces, within the l ittoral active zone for the purpose of preventing t he free movement of sand, erosion or accretion, exclud ing where the planting of vegetation or placement o f material relates to restoration and maintenance o f indigenous coastal vegetation or where such plantin g of vegetation or placing of material will occur b ehind a development setback line.

Activity 18 of GNR 544

The infilling or depositing of any material of mor e than 5 cubic metres into, or the dredging, excava tion, removal or moving of soil, sand, shells, shel l grit, pebbles or rock of more than 5 cubic metres from: (i) a watercourse; (ii) the sea; (iii) the seashore; (iv) the littoral active zone, an estuary or a dis tance of 100 metres inland of the high-water mark o f the sea or an estuary, whichever distance is the greater- but excluding where such infilling, depositing , dr edging, excavation, removal or moving; is for maintenance purposes undertaken in accordan ce with a management plan agreed to by the relevant environmental authority; or occurs behind the development setback line. [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]

Activity 21 of GNR 544

The establishment of cemeteries of 2500 square metr es or more in size.

Activity 22 of GNR 544

The construction of a road, outside urban areas, (i) with a reserve wider than 13,5 meters or, (ii) where no reserve exists where the road is wide r than 8 metres, or (iii) for which an environmental authorisation was obtained for the route determination in terms of ac tivity 5 in Government Notice 387 of 2006 or activi ty 18 in Notice 545 of 2010.

Page 20: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

20

Activity 23 of GNR 544

The transformation of undeveloped, vacant or dereli ct land to –

(i) residential, retail, commercial, recreational, industrial or institutional use, inside an urban ar ea, and where the total area to be transformed is 5 hectares or more, but less than 20 hectares, or

(ii) residential, retail, commercial, recreational, industrial or institutional use, outside an urban area and where the total area to be transformed is bigger than 1 hectare but less than 20 hectares; -

except where such transformation takes place – (i) for linear activities; or (ii) for purposes of agriculture or afforestation, in which case Activity 16 of Notice No. R. 545 app lies. [Corrected by “Correction Notice 1” of 30 July 2010 , GN No. R. 660]

Activity 24 of GNR 544

The transformation of land bigger than 1000 square metres in size, to residential, retail, commercial , industrial or institutional use, where, at the ti me of the coming into effect of this Schedule or thereafter s uch land was zoned open space, conservation or had an equivalent zoning. [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]

Activity 25 of GNR 544

The release of genetically modified organisms into the environment, where assessment for such release is required by the Genetically Modified Organisms Act, 1997 (Act No. 15 of 1997) or the National Envi ronmental Management: Biodiversity Act, 2004 (Act N o. 10 of 2004).

Activity 26 of GNR 544

Any process or activity identified in terms of sect ion 53(1) of the National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).

Activity 27 of GNR 544

The decommissioning of existing facilities or infra structure, for - (i) electricity generation with a threshold of more than 10MW; (ii) electricity transmission and distribution with a threshold of more than 132kV; (iii) nuclear reactors and storage of nuclear fuel; (iv) activities, where the facility or the land on which it is located is contaminated ; (v) storage, or storage and handling, of dangerous goods of more than 80 cubic metres; but excluding any facilities or infrastructure that commenced under an environmental authorisation iss ued in terms of the Environmental Impact Assessment Regulations, 2006 made under section 24( 5) of the Act and published in Government Notice No . R. 385 of 2006, or Notice No. 543 of 2010.

Activity 28 of GNR 544

The expansion of or changes to existing facilities for any process or activity where such expansion or changes to will result in the need for a permit or license in terms of national or provincial legislat ion governing the release of emissions or pollution , excluding where the facility, process or activity is included in the list of waste management activities published in terms of section 19 of the National E nvironmental Management: Waste Act, 2008 (Act No. 5 9 of 2008) in which case that Act will apply. [Corrected by “Correction Notice 1” of 30 July 2010 , GN No. R. 660, and “Correction Notice 2” of 10 De cember 2010, GN No. R. 1159]

Activity 29 of GNR 544

The expansion of facilities for the generation of e lectricity where: (i) the electricity output will be increased by 10 megawatts or more, excluding where such expansion t akes place on the original development footprint; o r (ii) regardless the increased output of the facilit y, the development footprint will be expanded by 1 hectare or more;

Page 21: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

21

Activity 11 of GNR 386

The decommissioning of a dam where the highest part of the dam wall, as measured from the outside toe of the wall to the highest part of the wall, is 5 metres or higher or where the high-water mark of th e dam covers an area of more than 10 hectares.

Activity 30 of GNR 544

The expansion of facilities for the slaughter of an imals where the daily product throughput will be in creased by more than: (i) 50 poultry or (ii) 6 units of red meat and game.

Activity 31 of GNR 544

The expansion of facilities for the concentration o f animals for the purpose of commercial production in densities that will exceed— (i) 20 square metres per large stock unit, where th e expansion will constitute more than 500 additiona l units; (ii) 8 square meters per small stock unit, where th e expansion will constitute more than:

a. 1 000 additional units per facility or more excl uding pigs where (b) will apply; b. 250 additional pigs, excluding piglets that are not yet weaned;

(iii) 30 square metres per crocodile at any level o f production where the expansion will constitute an increase in the level of production, excluding crocodiles younger than 6 months; (iv) 3 square metre per rabbit where the expansion will constitute more than 500 additional rabbits; o r (v) 250 square metres per ostrich or emu where the expansion will constitute more than 50 additional o striches or emus; and (vi) 2500 square metres per breeding pair, where th e facility will be increased by 2500 square metres or more.

Activity 32 of GNR 544

The expansion of facilities for the concentration o f poultry, excluding chicks younger than 20 days, w here the capacity of the facility will be increased by: (i) more than 1 000 poultry where the facility is s ituated within an urban area; or (ii) more than 5 000 poultry per facility situated outside an urban area.

Activity 33of GNR 544

The expansion of facilities, infrastructure or stru ctures for aquaculture of- (i) finfish, crustaceans, reptiles or amphibians, w here the production output of such facility, infra structure or structures will be increased by 20 000 kg (wet weight) or more; (ii) molluscs where the production output of such f acility, infrastructure or structures will be incre ased by 30 000 (wet weight) or more;

(iii) aquatic plants where the production output of such facility, infrastructure or structures will b e increased by 60 000 kg (wet weight) or more.

Activity 34 of GNR 544

The expansion of facilities, infrastructure or stru ctures for aquaculture of offshore cage culture of finfish, crustaceans, reptiles, amphibians, mollusc s and aquatic plants where the production output of such facility, infrastructure or structures will be incr eased by 50 000 kg (wet weight) or more.

Activity 35 of GNR 544

The expansion of facilities for agri-industrial pur poses outside industrial complexes, where the devel opment footprint of the facility will be increased by a 1 000 square metres or more, with the exception of ha tcheries, where activity 36 in this Notice applies.

Activity 36 of GNR 544

The expansion of hatcheries, outside industrial com plexes, where the development footprint of the hatc hery will be increased by 2 000 square metres or more.

Activity 37 GNR 544

The expansion of facilities or infrastructure for t he bulk transportation of water, sewage or storm wa ter where: (a) the facility or infrastructure is expanded by m ore than 1000 metres in length; or (b) where the throughput capacity of the facility o r infrastructure will be increased by 10% or more–

Page 22: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

22

excluding where such expansion: (i) relates to transportation of water, sewage or s torm water within a road reserve; or (ii) where such expansion will occur within urban a reas but further than 32 metres from a watercourse, measured from the edge of the watercourse.

Activity 38 of GNR 544

The expansion of facilities for the transmission an d distribution of electricity where the expanded ca pacity will exceed 275 kilovolts and the developmen t footprint will increase.

Activity 39 of GNR 544

The expansion of (i) canals; (ii) channels; (iii) bridges; (iv) weirs; (v) bulk storm water outlet structures; (vi) marinas; within a watercourse or within 32 metres of a water course, measured from the edge of a watercourse, wh ere such expansion will result in an increased development footprint but excluding where such expa nsion will occur behind the development setback lin e.

Activity 40 of GNR 544

The expansion of

(i) jetties by more than 50 square metres; (ii) slipways by more than 50 square metres; or (iii) buildings by more than 50 square metres

(iv) infrastructure by more than 50 square metres within a watercourse or within 32 metres of a water course, measured from the edge of a watercourse, bu t excluding where such expansion will occur behind the development setback line. We need to add development footprint as per activit y 45 of same notice [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]

Activity 41 of GNR 544

The expansion of facilities or infrastructure for t he off-stream storage of water, including dams and reservoirs, where the combined capacity will be increased by 50000 cubic metres or more.

Activity 42 of GNR 544

The expansion of facilities for the storage, or sto rage and handling, of a dangerous good, where the c apacity of such storage facility will be expanded b y 80 cubic metres or more.

Activity 43 of GNR 544

The expansion of structures in the coastal public p roperty where the development footprint will be inc reased by more than 50 square metres, excluding such expansions within existing ports or harbours w here there would be no increase in the development footprint or throughput capacity of the port or harbour.

Activity 44 of GNR 544

The expansion of facilities for the desalination of sea water where the design capacity will be expand ed to produce an additi onal 100 cubic metres or more of treated water per day.

Page 23: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

23

Activity 45 of GNR 544

The expansion of facilities in the sea, an estuary , or within the littoral active zone or a distance of 100 metres inland of the high-water mark of the sea or an estuary, whichever is the greater, for – (i) fixed or floating jetties and slipways; (ii) tidal pools; (iii) embankments; (iv) rock revetments or stabilising structures incl uding stabilising walls; (v) buildings by more than 50 square metres; (vi) infrastructure by more than 50 square metres; (vii) facilities associated with the arrival and de parture of vessels and the handling of cargo; (viii) piers; (ix) inter- and sub-tidal structures for entrapment of sand; (x) breakwater structures; (xi) coastal marinas; (xii) coastal harbours or ports; (xiii) structures for draining parts of the sea or estuary; (xiv) tunnels; or (xv) underwater channels – where such expansion will result in an increase in the development footprint of such facilities but excluding where such expansion occurs: (a) behind a development setback line; or (b) within existing ports or harbours where there w ill be no increase in the development footprint or throughput capacity of the port or harbour.

Activity 46 of GNR 544

The expansion of cemeteries by an additional 2500 s quare metres or more.

Activity 47 of GNR 544

The widening of a road by more than 6 metres, or th e lengthening of a road by more than 1 kilometre - (i) where the existing reserve is wider than 13,5 m eters; or (ii) where no reserve exists, where the existing ro ad is wider than 8 metres – excluding widening or lengthening occurring inside urban areas.

Activity 48 of GNR 544

The expansion of facilities for the refining, extra ction or processing of gas, oil or petroleum produc ts where the installed capacity of the facility wil l be increased by 50 cubic metres or more per day, exclu ding facilities for the refining, extraction or pro cessing of gas from landfill sites. [Corrected by “Correction Notice 1” of 30 July 2010 , GN No. R. 660]

Activity 49 of GNR 544

The expansion of facilities or infrastructure for t he bulk transportation of dangerous goods: (i) in gas form, outside an industrial complex, by an increased throughput capacity of 700 tons or mor e per day; (ii) in liquid form, outside an industrial complex or zone, by an increased throughput capacity of 50 cubic metres or more per day; or (iii) in solid form, outside an industrial complex or zone, by an increased throughput capacity of 50 tons or more per day.

Page 24: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

24

Activity 50 of GNR 544

The expansion of airports where the development foo tprint will be increased.

Activity 51 of GNR 544

The expansion of facilities or infrastructure for m arine telecommunication where there will be an incr eased development footprint.

Activity 52 of GNR 544

The expansion of facilities or infrastructure for t he transfer of water from and to or between any com bination of the following: (i) water catchments; (ii) water treatment works; or (iii) impoundments; where the capacity will be increased by 50 000 cubi c metres or more per day, but excluding water treat ment works where water is treated for drinking purposes.

Activity 53 of GNR 544

The expansion of railway lines, stations or shuntin g yards where there will be an increased developmen t footprint – excluding: (i) railway lines, shunting yards and railway stati ons in industrial complexes or zones; (ii) underground railway lines in mines; and (iii) additional railway lines within the reserve o f an existing railway line.

Activity 54 of GNR 544

The expansion of an island, anchored platform or an y other permanent structure on or along the sea bed , where the expansion will constitute an increased development footprint.

Activity 55 of GNR 544

The expansion of a dam where: (i) the highest part of the dam wall, as measured f rom the outside toe of the wall to the highest part of the wall, was originally 5 metres or higher and where the height of the wall is increased by 2,5 metres o r more; or (ii) where the high-water mark of the dam will be i ncreased with 10 hectares or more.

Activity 56 of GNR 544

Phased activities for all activities listed in this Schedule, which commenced on or after the effectiv e date of this Schedule, where any one phase of the activity may be below a threshold but where a combi nation of the phases, including expansions or exten sions, will exceed a specified threshold; - excluding the following activities listed in this S chedule: 2; 11(i)-(vii); 16(i)-(iv); 17; 19; 20; 22(i) & 22(iii); 25; 26; 27(iii) & (iv);

Page 25: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

25

28; 39; 45(i)-(iv) & (vii)-(xv); 50; 51; 53; and 54.

GNR 545: 2010 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 543, 544, 54 5 and 546 Government Gazette No 33306, Pretoria, 10 June 2010

Activity 1 of GNR 545

The construction of facilities or infrastructure fo r the generation of electricity where the electrici ty output is 20 megawatts or more.

Activity 2 of GNR 545

The construction of facilities or infrastructure fo r nuclear reaction including energy generation, the production, enrichment, processing, reprocessing, storage or disposal of nuclear fuels, radioactive p roducts and nuclear and radioactive waste.

Activity 3 of GNR 545

The construction of facilities or infrastructure fo r the storage, or storage and handling of a dangero us good, where such storage occurs in containers wi th a combined capacity of more than 500 cubic metres.

Activity 4 of GNR 545

The construction of facilities or infrastructure fo r the refining, extraction or processing of gas, oi l or petroleum products with an installed capacity of 50 cubic metres or more per day, excluding facilities for the refining, extraction or processing of gas f rom landfill sites. [Corrected by “Correction Notice 1” of 30 July 2010 , GN No. R. 660]

Activity 5 of GNR 545

The construction of facilities or infrastructure fo r any process or activity which requires a permit o r license in terms of national or provincial legisl ation governing the generation or release of emissions, p ollution or effluent and which is not identified in Notice No. 544 of 2010 or included in the list of waste management activities published in terms of section 19 of the National Environmental Management: Waste Act, 2008 (Act No. 59 of 2008) in which case that Act will apply.

Activity 6 of GNR 545

The construction of facilities or infrastructure fo r the bulk transportation of dangerous goods - (i) in gas form, outside an industrial complex, usi ng pipelines, exceeding 1000 metres in length, with a throughput capacity of more than 700 tons per d ay; (ii) in liquid form, outside an industrial complex, using pipelines, exceeding 1000 metres in length, with a throughput capacity more than 50 cubic metre s per day; or

(iv) in solid form, outside an industrial complex, using funiculars or conveyors with a throughput cap acity of more than 50 tons day. (v)

Activity 7 of GNR 545

The construction of (i) airports, or (ii) runways or aircraft landing strips longer than 1,4 kilometres.

Activity 8 of GNR 545

The construction of facilities or infrastructure fo r the transmission and distribution of electricity with a capacity of 275 kilovolts or more, outside a n urban area or industrial complex.

Page 26: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

26

Activity 9 of GNR 545

The construction of facilities or infrastructure fo r marine telecommunication.

Activity 10 of GNR 545

The construction of facilities or infrastructure fo r the transfer of 50 000 cubic metres or more water per day, from and to or between any combination of the following: (i) water catchments, (ii) water treatment works; or (iii) impoundments, excluding treatment works where water is to be trea ted for drinking purposes.

Activity 11 of GNR 545

The construction of railway lines, stations or shun ting yards, excluding - (i) railway lines, shunting yards and railway stati ons in industrial complexes or zones; (ii) underground railway lines in a mining area; an d

(iii) additional railway lines within the reserve of an e xisting railway line;

Activity 12 of GNR 545

The construction of facilities, infrastructure or s tructures for aquaculture of - (i) finfish, crustaceans, reptiles or amphibians w here the facility, infrastructure or structures wil l have a production output of 200 000 or more kg pe r annum (live round weight); (ii) molluscs where the facility, infrastructure or structures will have a production output of 150000 or more kg per annum (live round weight); (iii) aquatic plants where the facility, infrastruc ture or structures will have a production output of 200 000 or more kg per annum (live round weight); excluding where the construction of facilities, inf rastructure or structures is for purposes of offsho re cage culture in which case activity 13 in this N otice will apply.

Activity 13 of GNR 545

The construction of facilities, infrastructure or s tructures for aquaculture of offshore cage culture of finfish, crustaceans, reptiles, amphibians, moll uscs and aquatic plants where the facility, infrastructure o r structures will have a production output of 100 0 00 or more kg per annum (live round weight).

Activity 14 of GNR 545

The construction of an island, anchored platform or any other permanent structure on or along the sea bed excluding construction of facilities, infrastructure or structures for aquaculture purpos es;. [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]

Activity 15 of GNR 545

Physical alteration of undeveloped, vacant or derel ict land for residential, retail, commercial, recre ational, industrial or institutional use where the total area to be transformed is 20 hectares or more; except where such physical alteration takes place f or: (i) linear development activities; or (ii) agriculture or afforestation where activity 16 in this Schedule will apply.

Page 27: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

27

Activity 16 of GNR 545

The physical alteration of virgin soil to agricultu re, or afforestation for the purposes of commercial tree, timber or wood production of 100 hectares or more.

Activity 17 of GNR 545

The extraction or removal of peat or peat soils, in cluding the disturbance of vegetation or soils in a nticipation of the extraction or removal of peat or peat soils.

Activity 18 of GNR 545

The route determination of roads and design of asso ciated physical infrastructure, including roads tha t have not yet been built for which routes have bee n determined before 03 July 2006 and which have not b een authorised by a competent authority in terms of the Environmental Impact Assessment Regulations, 2006 or 2009, made under section 24(5) of the Act and published in Government Notice No. R. 385 of 2006,— (i) it is a national road as defined in section 40 of the South African National Roads Agency Limited and National Roads Act, 1998 (Act No. 7 of 1998); (ii) it is a road administered by a provincial auth ority; (iii) the road reserve is wider than 30 metres; or (iv) the road will cater for more than one lane of traffic in both directions.

Activity 19 of GNR 545

The construction of a dam, where the highest part o f the dam wall, as measured from the outside toe of the wall to the highest part of the wall, is 5 met res or higher or where the high-water mark of the dam cove rs an area of 10 hectares or more.

Activity 24 of GNR 545

Construction or earth moving activities in the sea, an estuary, or within the littoral active zone or a distance of 100 metres inland of the high-water m ark of the sea or an estuary, whichever distance is the gr eater, in respect of: (i) facilities associated with the arrival and depa rture of vessels and the handling of cargo; (ii) piers; (iii) inter- and sub-tidal structures for entrapmen t of sand; (iv) breakwater structures; (v) coastal marinas; (vi) coastal harbours or ports; (vii) structures for reclaiming parts of the sea; (viii) tunnels; or (ix) underwater channels; but excluding — (a) activities listed in activity 16 in Notice 544 of 2010, (b) construction or earth moving activities if suc h construction or earth moving activities will occu r behind a development setback line; (c) where such construction or earth moving activit ies will occur in existing ports or harbours where there will be no increase of the development footpr int or throughput capacity of the port or harbour; or (d) where such construction or earth moving activit ies takes place for maintenance purposes.

Activity 25 of GNR 545

The expansion of facilities for nuclear reaction in cluding energy generation, the production, enrichme nt, processing, reprocessing, storage or disposal o f nuclear fuels, radioactive products and nuclear and radioactive waste.

Activity 26 of GNR 545

Commencing of an activity, which requires an atmosp heric emission license in terms of section 21 of th e National Environmental Management: Air Quality Act, 2004 (Act No. 39 of 2004), except where such c ommencement requires basic assessment in terms of N otice of No. R544 of 2010. [Corrected by “Correction Notice 1” of 30 July 2010 , GN No. R. 660, and “Correction Notice 2” of 10 D ecember 2010, GN No. R. 1159]

Page 28: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

28

GNR 546: 2010 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 543, 544, 54 5 and 546 Government Gazette No 33306, Pretoria, 10 June 2010

Activity 1 of GNR 546

The construction of billboards exceeding 18 square metres in size outside urban or mining areas or out side industrial complexes.

Activity 2 of GNR 546

The construction of reservoirs for bulk water suppl y with a capacity of more than 250 cubic metres.

Activity 3 of GNR 546

The construction of masts or towers of any material or type used for telecommunication broadcasting or radio transmission purposes where the mast: (a) is to be placed on a site not previously used f or this purpose, and (b) will exceed 15 metres in height, but excluding attachments to existing buildings and masts on rooftops.

Activity 4 of GNR 546

The construction of a road wider than 4 metres with a reserve less than 13,5 metres.

Activity 5 of GNR 545

The construction of resorts, lodges or other touris m accommodation facilities that sleep less than 15 people.

Activity 6 of GNR 546

The construction of resorts, lodges or other touris m accommodation facilities that sleep 15 people or more.

Activity 7 of GNR 546

The conversion of existing structures to resorts, l odges or tourism accommodation facilities that slee p 15 people or more.

Activity 8 of GNR 546

The construction of aircraft landing strips and run ways 1.4 kilometres and shorter. [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]

Activity 9 of GNR 546

The construction of above ground cableways and funi culars;

Activity 10 of GNR 546

The construction of facilities or infrastructure fo r the storage, or storage and handling of a dangero us good, where such storage occurs in containers wi th a combined capacity of 30 but not exceeding 80 cubic metres.

Activity 11 of GNR 546

The construction of tracks or routes for the testin g, recreational use or outdoor racing of motor powe red vehicles excluding conversion of existing track s or routes for the testing, recreational use or outdoor racing of motor powered vehicles.

Activity 12 of GNR 546

The clearance of an area of 300 square metres or mo re of vegetation where 75% or more of the vegetativ e cover constitutes indigenous vegetation.

Page 29: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

29

Activity 13 of GNR 546

The clearance of an area of 1 hectare or more of ve getation where 75% or more of the vegetative cover constitutes indigenous vegetation, except where such removal of vegetation is required for: (1) the undertaking of a process or activity includ ed in the list of waste management activities publi shed in terms of section 19 of the National Environ mental Management: Waste Act, 2008 (Act No. 59 of 2008), i n which case the activity is regarded to be exclude d from this list. (2) the undertaking of a linear activity falling be low the thresholds mentioned in Listing Notice 1 in terms of GN No. 544 of 2010.

Activity 14 of GNR 545

The clearance of an area of 5 hectares or more of v egetation where 75% or more of the vegetative cover constitutes indigenous vegetation, except where such removal of vegetation is required for: (1) purposes of agriculture or afforestation inside areas identified in spatial instruments adopted by the competent authority for agriculture or affores tation purposes; (2) the undertaking of a process or activity includ ed in the list of waste management activities publi shed in terms of section 19 of the National Environ mental Management: Waste Act, 2008 (Act No. 59 of 2008) in which case the activity is regarded to be excluded from this list; (3) the undertaking of a linear activity falling be low the thresholds in Notice 544 of 2010.

Activity 15 of GNR 546

The construction of facilities, infrastructure or s tructures of any size for any form of aquaculture.

Activity 16 of GNR 546

The construction of: (i) jetties exceeding 10 square metres in size; (ii) slipways exceeding 10 square metres in size; (iii) buildings with a footprint exceeding 10 squar e metres in size; or (iv) infrastructure covering 10 square metres or mo re where such construction occurs within a watercourse or within 32 metres of a watercourse, measured fro m the edge of a watercourse, excluding where such construction will occur behind the development setb ack line.

Activity 17 of GNR 546

The expansion of reservoirs for bulk water supply w here the capacity will be increased by more than 25 0 cubic metres.

Activity 18 of GNR 546

The expansion of a resort, lodge, hotel and tourism or hospitality facilities where the development fo otprint will be expanded.

Activity 19 of GNR 546

The widening of a road by more than 4 metres, or th e lengthening of a road by more than 1 kilometre.

Activity 20 of GNR 546

The expansion of runways or aircraft landing strips where the expanded runways or aircraft landing str ips will be longer than 1,4 kilometres in length.

Activity 21 of GNR 546

The expansion of above ground cableways and funicul ars where the development footprint will be increas ed.

Activity 22 of GNR 546

The expansion of tracks or routes for the testing, recreational use or outdoor racing of motor powered vehicles excluding conversion of existing tracks o r routes for the testing, recreational use or outdoor racing of motor powered vehicles, where the develo pment footprint will be expanded.

Page 30: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

30

Activity 23 of GNR 546

The expansion of facilities or infrastructure for t he storage, or storage and handling of a dangerous good, where such storage facilities will be expande d by 30 cubic metres or more but less than 80 cubic metr es.

Activity 24 of GNR 546

The expansion of (a) jetties where the jetty will be expanded by 10 square metres in size or more; (b) slipways where the slipway will be expanded by 10 square metres or more; (c) buildings where the buildings will be expanded by 10 square metres or more in size; or (d) infrastructure where the infrastructure will be expanded by 10 square metres or more where such construction occurs within a watercourse or within 32 metres of a watercourse, measured fro m the edge of a watercourse, excluding where such construction will occur behind the development setback line.

Activity 25 of GNR 546

The expansion of facilities, infrastructure or stru ctures of any size for any form of aquaculture.

Activity 26 of GNR 546

Phased activities for all activities listed in this Schedule and as it applies to a specific geographi cal area, which commenced on or after the effective date of this Schedule, where any phase of the activity may be below a threshold but where a combination of the phases, including expansions or extensions, will exceed a specified threshold.

08 December 2014 – current

GNR 983: 2014 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 982, 983, 98 4 and 985 Government Gazette No 38282, Pretoria, 04 December 2014

Activity 1 of GNR

983

The development of facilities or infrastructure for the generation of electricity from a renewable res ource where —

(i) the electricity output is more than 10 megawatt s but less than 20 megawatts; or

(ii) the output is 10 megawatts or less but the tot al extent of the facility covers an area in excess of 1 hectare;

excluding where such development of facilities or i nfrastructure is for photovoltaic installations and occurs within an urban area.

Activity 2 of GNR 983

The development and related operation of facilities or infrastructure for the generation of electricit y from a non -renewable resource where —

(i) the electricity output is more than 10 megawatt s but less than 20 megawatts; or

(ii) the output is 10 megawatts or less but the tot al extent of the facility covers an area in excess of 1 hectare.

Activity 3 of GNR 983

The development and related operation of facilities or infrastructure for the slaughter of animals with a product throughput of—

(i) poultry exceeding 50 poultry per day;

(ii) reptiles, game and red meat exceeding 6 units per day; or

(iii) fish, crustaceans and amphibians with a wet w eight product throughput of 20 000 kg per annum.

Page 31: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

31

Activity 4 of GNR 983

The development and related operation of facilities or infrastructure for the concentration of animals for the purpose of com mercial production in densities

that exceed—

(i) 20 square metres per large stock unit and more than 500 units per facility;

(ii) 8 square meters per small stock unit and;

c. more than 1 000 units per facility excluding pi gs where (b) applies; or

d. more than 250 pigs per facility excluding piglet s that are not yet weaned;

(iii) 30 square metres per crocodile at any level o f production, excluding crocodiles younger than 6 m onths;

(iv) 3 square metre per rabbit and more than 500 ra bbits per facility; or

(v) 250 square metres per ostrich or emu and more t han 50 ostriches or emus per facility.

Activity 5 of GNR 983

The development and related operation of facilities or infrastructure for the concentration of —

(i) more than 1 000 poultry per facility situated w ithin an urban area, excluding chicks younger than 20 days;

(ii) more than 5 000 poultry per facility situated outside an urban area, excluding chicks younger tha n 20 days;

(iii) more than 5000 chicks younger than 20 days pe r facility situated within an urban area; or

(iv) more than 25000 chicks younger than 20 days pe r facility situated outside an urban area.

Activity 6 of GNR 983

The development and related operation of facilities , infrastructure or structures for aquaculture of —

(i) finfish, crustaceans, reptiles or amphibians, w here such facility, infrastructure or structures wi ll have a production output exceeding 20 000 kg per

annum (wet weight);

(ii) molluscs and echinoderms, where such facility , infrastructure or structures will have a producti on output exceeding 30 000 kg per annum (wet

weight); or

(iii) aquatic plants, where such facility, infrastr ucture or structures will have a production output exceeding 60 000 kg per annum (wet weight);

excluding where the development of such facilities, infrastructure or structures is for purposes of se a-based cage culture in which case activity 7 in th is

Notice applies.

Activity 7 of GNR 983

The development and related operation of facilities , infrastructure or structures for aquaculture of s ea-based cage culture of finfish, crustaceans, rept iles,

amphibians, molluscs, echinoderms and aquatic plant s, where the facility, infrastructure or structures will have a production output exceeding 50 000 kg per

annum (wet weight).

Activity 8 of GNR 983

The development and related operation of hatcheries or agri -industrial facilities outside industrial complexes where the development footprint covers an area

of 2 000 square metres or more.

Activity 9 of GNR 983

The development of infrastructure exceeding 1000 me tres in length for the bulk transportation of water or storm water —

(vii) with an internal diameter of 0,36 metres or m ore; or

(viii) with a peak throughput of 120 litres per sec ond or more;

excluding where—

(a) such infrastructure is for bulk transportation of water or storm water or storm water drainage ins ide a road reserve; or

(b) where such development will occur within an urb an area.

Page 32: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

32

Activity 10 of GNR 983

The development and related operation of infrastruc ture exceeding 1000 metres in length for the bulk t ransportation of sewage , effluent, process water, waste

water, return water, industrial discharge or slime s –

(i) with an internal diameter of 0,36 metres or more; or

(ii) with a peak throughput of 120 litres per se cond or more;

excluding where—

(a) such infrastructure is for bulk transportation of sewage, effluent, process water, waste water, re turn water, industrial discharge or slimes inside a

road reserve; or

(b) where such development will occur within an urb an area.

Activity 11 of GNR 983

The development of facilities or infrastructure for the transmission and distribution of electricity —

(i) outside urban areas or industrial complexes wit h a capacity of more than 33 but less than 275 kilo volts; or

(ii) inside urban areas or industrial complexes wit h a capacity of 275 kilovolts or more.

Activity 12 of GNR 983

The development of —

(i) canals exceeding 100 square metres in size;

(ii) channels exceeding 100 square metres in size;

(iii) bridges exceeding 100 square metres in size;

(iv) dams, where the dam, including infrastructure and water surface area, exceeds 100 square metres in si ze;

(v) weirs, where the weir, including infrastructure an d water surface area, exceeds 100 square metres in size;

(vi) bulk storm water outlet structures exceeding 100 s quare metres in size;

(vii) marinas exceeding 100 square metres in size;

(viii) jetties exceeding 100 square metres in size;

(ix) slipways exceeding 100 square metres in size;

(x) buildings exceeding 100 square metres in size;

(xi) boardwalks exceeding 100 square metres in size; or

(xii) infrastructure or structures with a physical footp rint of 100 square metres or more;

where such development occurs—

(a) within a watercourse;

(b) in front of a development setback; or

(c) if no development setback exists, within 32 met res of a watercourse, measured from the edge of a w atercourse; —

excluding—

(aa) the development of infrastructure or structure s within existing ports or harbours that will not i ncrease the development footprint of the port or

harbour;

(bb) where such development activities are related to the development of a port or harbour, in which c ase activity 26 in Listing Notice 2 of 2014 applies ;

(cc) activities listed in activity 14 in Listing No tice 2 of 2014 or activity 14 in Listing Notice 3 o f 2014, in which case that activity applies;

Page 33: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

33

(dd) where such development occurs within an urban area; or

(ee) where such development occurs within existing roads or road reserves.

Activity 13 of GNR 983 The development of facilities or infrastructure fo r the off-stream storage of water, including dams a nd reservoirs, with a combined capacity of 50000 cu bic

metres or more, unless such storage falls within th e ambit of activity 16 in Listing Notice 2 of 2014.

Activity 14 of GNR 983 The development of facilities or infrastructure, fo r the storage, or for the storage and handling, of a dangerous good, where such storage occurs in cont ainers

with a combined capacity of 80 cubic metres or more but not exceeding 500 cubic metres.

Activity 15 of GNR 983

The development of structures in the coastal publi c property where the development footprint is bigge r than 50 square metres , excluding —

(i) the development of structures within existing p orts or harbours that will not increase the develop ment footprint of the port or harbour;

(ii) the development of a port or harbour, in which case activity 26 in Listing Notice 2 of 2014 appli es;

(iii) the development of temporary structures withi n the beach zone where such structures will be remo ved within 6 weeks of the commencement of

development and where indigenous vegetation will n ot be cleared; or

(iv) activities listed in activity 14 in Listing No tice 2 of 2014, in which case that activity applies .

Activity 16 of GNR 983 The development and related operation of facilities for the desalination of water with a design capaci ty to produce more than 100 cubic metres of treated water

per day.

Activity 17 of GNR 983

Development —

(i) in the sea;

(ii) in an estuary;

(iii) within the littoral active zone;

(iv) in front of a development setback; or

(v) if no development setback exists, within a distanc e of 100 metres inland of the high-water mark of th e sea or an estuary, whichever is the greater;

in respect of—

(a) fixed or floating jetties and slipways;

(b) tidal pools;

(c) embankments;

(d) rock revetments or stabilising structures inclu ding stabilising walls;

(e) buildings of 50 square metres or more; or

(f) infrastructure with a development footprint of 50 square metres or more —

but excluding—

(aa) the development of infrastructure and structur es within existing ports or harbours that will not increase the development footprint of the port or

harbour;

Page 34: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

34

(bb) where such development is related to the developmen t of a port or harbour, in which case activity 26 i n Listing Notice 2 of 2 014 applies;

(cc) the development of temporary infrastructure or structures where such structures will be removed w ithin 6 weeks of the commencement of

development and where indigenous vegetation will n ot be cleared; or

(dd) where such development occurs within an urban area.

Activity 18 of GNR 983

The planting of vegetation or placing of any materi al on dunes or exposed sand surfaces of more than 1 0 square metres, within the littoral active zone, for the

purpose of preventing the free movement of sand, er osion or accretion, excluding where —

(i) the planting of vegetation or placement of mate rial relates to restoration and maintenance of indi genous coastal vegetation undertaken in

accordance with a maintenance management plan; or

(ii) such planting of vegetation or placing of mate rial will occur behind a development setback.

Activity 19 of GNR 983

The infilling or depositing of any material of mor e than 5 cubic metres into, or the dredging, excava tion, removal or moving of soil, sand, sh ells, shell grit,

pebbles or rock of more than 5 cubic metres from—

(i) a watercourse;

(ii) the seashore; or

(iii) the littoral active zone, an estuary or a dis tance of 100 metres inland of the high-water mark o f the sea or an estuary, whichever distance is the

greater—

but excluding where such infilling, depositing , dr edging, excavation, removal or moving— (a) will occur behind a development setback;

(b) is for maintenance purposes undertaken in ac cordance with a maintenance management plan; or

(c) falls within the ambit of activity 21 in this Notice, in which case that activity applies.

Activity 20 of GNR 983

Any activity including the operation of that activi ty which requires a prospecting right in terms of section 16 of the Min eral and Petroleum Resources

Development Act, 2002 (Act No. 28 of 2002), includi ng associated infrastructure, structures and earthw orks, directly related to prospecting of a mineral

resource, including activities for which an exempti on has been issued in terms of section 106 of the M ineral and Petroleum Resources Development Act, 200 2

(Act No. 28 of 2002).

Activity 21 of GNR 983

Any activity including the operation of that activi ty which requires a mining permit in terms of secti on 27 of the Mineral an d Petroleum Resources Development

Act, 2002 (Act No. 28 of 2002), including associate d infrastructure, structures and earthworks directl y related to the extraction of a mineral resource, including

activities for which an exemption has been issued i n terms of section 106 of the Mineral and Petroleum Resources Development Act, 2002 (Act No. 28 of 200 2).

Activity 22 of GNR 983

The decommissioning of any activity requiring –

(i) a closure certificate in terms of section 43 of the Mineral and Petroleum Resources Development Ac t, 2002 (Act No. 28 of 2002); or

(ii) a prospecting right, mining right, mining perm it, production right or exploration right, where th e throughput of the activity has reduced by 90% or more

over a period of 5 years excluding where the compet ent authority has in writing agreed that such reduc tion in throughput does not constitute closure.

Page 35: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

35

Activity 23 of GNR 983

The development of cemeteries of 2500 square metres or more in size.

Activity 24 of GNR 983

The development of —

(i) a road for which an environmental authorisation was obtained for the route determination in terms of activity 5 in Government Notice 387 of 2006 or

activity 18 in Government Notice 545 of 2010; or

(ii) a road with a reserve wider than 13,5 meters, or where no reserve exists where the road is wider than 8 metres;

but excluding—

(a) roads which are identified and included in acti vity 27 in Listing Notice 2 of 2014; or

(b) roads where the entire road falls within an urb an area.

Activity 25 of GNR 983

The development and related operation of facilities or infrastructure for the treatment of effluent, w astewater or sewage wit h a daily throughput capacity of

more than 2000 cubic metres but less than 15000 cub ic metres.

Activity 26 of GNR 983

Residentia l, retail, recreational, tourism, commercial or ins titutional developments of 1000 square metres or mo re, on land previously used for mining or heavy

industrial purposes; —

excluding —

(i) where such land has been remediated in terms of part 8 of the National Environmental Management: W aste Act, 2008 (Act No. 59 of 2008) in which case

the National Environmental Management: Waste Act, 2 008 applies; or

(ii) where an environmental authorisation has been obtained for the decommissioning of such a mine or industry in terms of this Notice or any previous

NEMA notice; or

(iii) where a closure certificate has been issued i n terms of section 43 of the Mineral and Petroleum Resources Development Act, 2002 (Act No. 28 of 2002 )

for such land.

Activity 27 of GNR 983

The clearance of an area of 1 hectares or more, but less than 20 hectares of indigenous vegetation, except where su ch clearance of indigen ous vegetation is

required for—

(i) the undertaking of a linear activity; or

(ii) maintenance purposes undertaken in accordance with a maintenance management plan.

Activity 28 of GNR 983

Residential, mixed, retail, commercial, industrial or institutional developments where such land was u sed for agriculture or afforestation on or after 01 April

1998 and where such development:

(i) will occur inside an urban area, where the tota l land to be developed is bigger than 5 hectares; o r

(ii) will occur outside an urban area, where the to tal land to be developed is bigger than 1 hectare;

excluding where such land has already been develope d for residential, mixed, retail, commercial, indus trial or institutional purposes.

Page 36: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

36

Activity 29 of GNR 983

The release of genetically modified organisms into the environment, where assessment for such release is required by the Gene tically Modified Organisms

Act, 1997 (Act No. 15 of 1997) or the National Envi ronmental Management: Biodiversity Act, 2004 (Act N o. 10 of 2004).

Activity 30 of GNR 983 Any process or activity identified in terms of sect ion 53(1) of the National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).

Activity 31 of GNR 983

The decommissioning of existing facilities, structu res or infrastructure for —

(i) any development and related operation activity or activities listed in this Notice, Listing Notice 2 of 2014 or Listing Notice 3 of 2014;

(ii) any expansion and related operation activity o r activities listed in this Notice, Listing Notice 2 of 2014 or Listing Notice 3 of 2014;

(iii) any development and related operation activit y or activities and expansion and related operation activity or activities listed in this Notice, List ing

Notice 2 of 2014 or Listing Notice 3 of 2014;

(iv) any phased activity or activities for developm ent and related operation activity or expansion or related operation activities listed in this Notice or

Listing Notice 3 of 2014; or

(v) any activity regardless the time the activity w as commenced with, where such activity:

(a) is similarly listed to an activity in (i), (ii), ( iii), or (iv) above; and

(b) is still in operation or development is still in p rogress;

excluding where—

(aa) activity 22 of this notice applies; or

(bb) the decommissioning is covered by part 8 of th e National Environmental Management: Waste Act, 200 8 (Act No. 59 of 2008) in which case the National

Environmental Management: Waste Act, 2008 applies.

Activity 32 of GNR 983

The continuation of any development where the environme ntal authorisation has lapsed and where the continu ation of the developmen t, after the date the

environmental authorisation has lapsed will meet th e threshold of any activity or activities listed in this Notice, Listing Notice 2 of 2014, or Listing Notice 3 or

Listing Notice 4 of 2014.

Activity 33 of GNR 983 The underground gasification of 300 kilograms or mo re coal per day, including any associated operation .

Activity 34 of GNR 983

The expansion or changes to existing facilities for any process or activity where such expansion or ch anges will result in th e need for a permit or licence or an

amended permit or licence in terms of national or p rovincial legislation governing the release of emis sions or pollution, excluding—

(i) where the facility, process or activity is incl uded in the list of waste management activities pub lished in terms of section 19 of the National

Environmental Management: Waste Act, 2008 (Act No. 59 of 2008) in which case the National Environmenta l Management: Waste Act, 2008 applies; or

(ii) the expansion of or changes to existing facili ties for the treatment of effluent, wastewater or s ewage where the capacity will be increased by less than

15 000 cubic metres per day.

Page 37: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

37

Activity 35 of GNR 983

The expansion of residential, retail, recreational, tourism, commercial or institutional developments on land previously used for mining or heavy industrial

purposes, where the increased development footprint will exceed 1000 square meters;

excluding—

(i) where such land has been remediated in terms of part 8 of the National Environmental Management: W aste Act, 2008 (Act No. 59 of 2008) in which case

the National Environmental Management: Waste Act, 2 008 applies; or

(ii) where an environmental authorisation has been obtained for the decommissioning of such a mine or industry in terms of this Notice or any previous

NEMA notice; or

(iii) where a closure certificate has been issued i n terms of section 43 of the Mineral and Petroleum Resources Development Act, 2002 (Act No. 28 of 2002 )

for such land.

Activity 36 of GNR 983

The expansion of facilities or structures for the g eneration of electricity from a renewable resource where —

(i) the electricity output will be increased by 10 megawatts or more, excluding where such expansion t akes place on the original development footprint; o r

(ii) regardless the increased output of the facilit y, the development footprint will be expanded by 1 hectare or more;

excluding where such expansion of facilities or str uctures is for photovoltaic installations and occur s within an urban area.

Activity 37 of GNR 983

The expansion and related operation of facilities for the generation of electricity fro m a non -renewable resource where —

(i) the electricity output will be increased by 10 megawatts or more, excluding where such expansion t akes place on the original development footprint;

or

(ii) regardless the increased output of the facilit y, the development footprint will be expanded by 1 hectare or more.

Activity 38 of GNR 983

The expansion and related operation of facilities f or the slaughter of animals where the daily product throughput will be inc reased by more than —

(i) 50 poultry;

(ii) 6 units of reptiles, red meat and game; or

(iii) 20 000 kg wet weight per annum of fish, crust aceans and amphibians.

Activity 39 of GNR 983

The expansion and related operation of facilities f or the concentration of animals for the purpose of commercial production in densities that will exceed —

(i) 20 square metres per large stock unit, where th e expansion will constitute more than 500 additiona l units;

(ii) 8 square meters per small stock unit, where th e expansion will constitute more than;

(a) 1 000 additional units per facility or more exc luding pigs where (b) applies; or

(b) 250 additional pigs, excluding piglets that are not yet weaned;

(iii) 30 square metres per crocodile at any level o f production where the expansion will constitute an increase in the level of production, excluding

crocodiles younger than 6 months;

(iv) 3 square metre per rabbit where the expansion will constitute more than 500 additional rabbits; o r

(v) 250 square metres per ostrich or emu where the expansion will constitute more than 50 additional o striches or emus.

Page 38: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

38

Activity 40 of GNR 983

The expansion and related operation of facilities for the concentration of po ultry, excluding chicks younger than 20 days, where the capacity of the fa cility will

be increased by—

(iv) more than 1 000 poultry where the facility is situated within an urban area; or

(v) more than 5 000 poultry per facility situated o utside an urban area.

Activity 41 of GNR 983

The expansion and related operation of facilities, infrastructure or structures for aquaculture of —

(i) finfish, crustaceans, reptiles or amphibians, wher e the annual production output of such facility, i nfrastructure or structures will be increased by 20

000 kg (wet weight) or more;

(ii) molluscs and echinoderms where the annual producti on output of such facility, infrastructure or struc tures will be increased by 30 000 kg (wet

weight) or more; or

(iii) aquatic plants where the annual production output of such facility, infrastructure or structures will be increased by 60 000 kg (wet weight) or more;

excluding where the expansion of facilities, infras tructure or structures is for purposes of sea-based cage culture in which case activity 42 in this Not ice will

applies.

Activity 42 of GNR 983

The expansion and related operation of facilities, infrastructure or structures for aquaculture of sea-based cage culture of finfish, crustaceans, reptile s,

amphibians, molluscs, echinoderms and aquatic plant s where the annual production output of such facili ty, infrastructure or structures will be increased by 50

000 kg (wet weight) or more.

Activity 43 of GNR 983

The expansion and related operation of hatcheries o r agri-industrial facilities outside industrial com plexes, where the development footprint of the hatc heries

or agri-industrial facilities will be increased by 2 000 square metres or more.

Activity 44 of GNR 983

The expansion of cemeteries by 2500 square metres o r more.

Activity 45 of GNR 983

The expansion of infrastructure for the bulk transp ortation of water or storm water where the existing infrastructure —

(i) has an internal diameter of 0,36 metres or more; o r

(ii) has a peak throughput of 120 litres per second or more; and

(a) where the facility or infrastructure is expande d by more than 1000 metres in length; or

(b) where the throughput capacity of the facility o r infrastructure will be increased by 10% or more;

excluding where such expansion—

(aa) relates to transportation of water or storm wa ter within a road reserve; or

(bb) will occur within an urban area.

Activity 46 of GNR 983

The expansion and related operation of infrastructu re for the bulk transportation of sewage, effluent, process water, waste w ater, return water, industrial

discharge or slimes where the existing infrastructu re—

(i) has an internal diameter of 0,36 metres or more; o r

(ii) has a peak throughput of 120 litres per second or more; and

Page 39: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

39

(a) where the facility or infrastructure is expanded by more than 1000 metres in length; or

(b) where the throughput capacity of the facility o r infrastructure will be increased by 10% or more;

excluding where such expansion—

(aa) relates to transportation of sewage, effluent , process water, waste water, return water, industr ial discharge or slimes within a road reserve; or

(bb) will occur within an urban area.

Activity 47 of GNR 983

The expansion of facilities or infrastructure for t he transmission and distribution of electricity whe re the expanded capacit y will exceed 275 kilovolts and the

development footprint will increase.

Activity 48 of GNR 983

The expansion of —

(i) canals where the canal is expanded by 100 squar e metres or more in size ;

(ii) channels where the channel is expanded by 100 square metres or more in size ;

(iii) bridges where the bridge is expanded by 100 s quare metres or more in size;

(iv) dams, where the dam, including infrastructure and water surface area, is expanded by 100 square m etres or more in size;

(v) weirs, where the weir, including infrastructure and water surface area, is expanded by 100 square metres or more in size;

(vi) bulk storm water outlet structures where the b ulk storm water outlet structure is expanded by 100 square metres or more in size; or

(vii) marinas where the marina is expanded by 100 s quare metres or more in size;

where such expansion or expansion and related opera tion occurs—

(a) within a watercourse;

(b) in front of a development setback; or

(c) if no development setback exists, within 32 met res of a watercourse, measured from the edge of a w atercourse;

excluding—

(aa) the expansion of infrastructure or structu res within existing ports or harbours that will not increase the development footprint of the port or harbour;

(bb) where such expansion activities are related to the development of a port or harbour, in which cas e activity 26 in Listing Notice 2 of 2014 applies;

(cc) activities listed in activity 14 in Listing No tice 2 of 2014 or activity 14 in Listing Notice 3 o f 2014, in which case that activity applies;

(dd) where such expansion occurs within an urba n area; or

(ee) where such expansion occurs within existing ro ads or road reserves.

Activity 49 of GNR 983

The expansion of –

(i) jetties by more than 100 square metres;

(ii) slipways by more than 100 square metres;

(iii) buildings by more than 100 square metres;

(iv) boardwalks by more than 100 square metres; or

(v) infrastructure or structures where the physical footprint is expanded by 100 square metres or more ;

Page 40: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

40

where such expansion or expansion and related opera tion occurs—

(a) within a watercourse;

(b) in front of a development setback; or

(c) if no development setback exists, within 32 met res of a watercourse, measured from the edge of a w atercourse;

excluding—

(aa) the expansion of infrastructure or structu res within existing ports or harbours that will not increase the development footprint of the port or harbour;

(bb where such expansion activities are relate d to the development of a port or harbour, in which case activity 26 in Listing Notice 2 of 2014 appli es;

(cc) activities listed in activity 14 in Listing No tice 2 of 2014 or activity 14 in Listing Notice 3 o f 2014, in which case that activity applies;

(dd) where such expansion occurs within an urba n area; or

(ee) where such expansion occurs within existin g roads or road reserves.

Activity 50 of GNR 983

The expansion of facilities or infrastructure for t he off -stream storage of water, including dams and reservo irs, where the combined capacity will be increased

by 50000 cubic metres or more.

Activity 51 of GNR 983

The expansion of facilities for the storage, or sto rage and handling, of a dangerous good, where the c apacity of such storage facility will be expanded b y more

than 80 cubic metres.

Activity 52 of GNR 983

The expansion of structures in the coastal public p roperty where the development footprint will be inc reased by more than 50 square metres, excluding suc h

expansions within existing ports or harbours where there will be no increase in the development footpr int of the port or harbour and excluding activities listed

in activity 23 in Listing Notice 3 of 2014, in whic h case that activity applies.

Activity 53 of GNR 983

The expansion and related operation of facilities f or the desalination of water where the design capac ity will be expanded to produce an additional 100 c ubic

metres or more of treated water per day.

Activity 54 of GNR 983

The expansion of facilities —

(i) in the sea;

(ii) in an estuary;

(iii) within the littoral active zone;

(iv) in front of a development setback; or

(v) if no development setback exists, within a dist ance of 100 metres inland of the high-water mark of the sea or an estuary, whichever is the greater;

in respect of—

(a) fixed or floating jetties and slipways;

(b) tidal pools;

(c) embankments;

(d) rock revetments or stabilising structures inclu ding stabilising walls;

(e) buildings where the building is expanded by 50 square metres or more; or

Page 41: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

41

(f) infrastructure where the development footprint is e xpanded by 50 square metres or more,

but excluding—

(aa) the expansion of infrastructure or structures within existing ports or harbours that will not inc rease the development footprint of the port or

harbour; or

(bb) where such expansion occurs within an urban ar ea.

Activity 55 of GNR 983

Expansion—

(i) in the sea;

(ii) in an estuary;

(iii) within the littoral active zone;

(iv) in front of a development setback; or

(v) if no development setback exists, within a dist ance of 100 metres inland of the high-water mark of the sea or an estuary, whichever is the greater;

in respect of —

(a) facilities associated with the arrival and depa rture of vessels and the handling of cargo;

(b) piers;

(c) inter- and sub-tidal structures for entrapment of sand;

(d) breakwater structures;

(e) coastal marinas;

(f) coastal harbours or ports;

(g) tunnels; or

(h) underwater channels;

but excluding the expansion of infrastructure or st ructures within existing ports or harbours that wil l not increase the development footprint of the por t or

harbour.

Activity 56 of GNR 983 The widening of a road by more than 6 metres, or th e lengthening of a road by more than 1 kilometre—

(i) where the existing reserve is wider than 13,5 m eters; or

(ii) where no reserve exists, where the existing ro ad is wider than 8 metres;

excluding where widening or lengthening occur insid e urban areas.

Page 42: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

42

Activity 57 of GNR 983

The expansion and related operation of facilities o r infrastructure for the treatment of effluent, was tewater or sewage where the capacity will be increa sed by

15000 cubic metres or more per day and the developm ent footprint will increase by 1000 square meters o r more.

Activity 58 of GNR 983 The increase of the amount of coal gasified undergr ound, where any such increase exceeds 300 kg per da y, including any associated operation.,.

Activity 59 of GNR 983

The expansion and related operation of facilities o r infrastructure for the refining, extraction or pr ocessing of gas, oil or petroleum products where th e

installed capacity of the facility will be increase d by 50 cubic metres or more per day, excluding fac ilities for the refining, extraction or processing of gas from

landfill sites.

Activity 60 of GNR 983

The expansion and related operation of facilities o r infrastructure for the bulk transportation of dan gerous goods —

(i) in gas form, outside an industrial complex, by an increased throughput capacity of 700 tons or mor e per day;

(ii) in liquid form, outside an industrial complex or zone, by an increased throughput capacity of 50 cubic metres or more per day; or

(iii) in solid form, outside an industrial complex or zone, by an increased throughput capacity of 50 tons or more per day.

Activity 61 of GNR 983 The expansion of airports where the development foo tprint will be increased.

Activity 62 of GNR 983 The expansion of facilities or infrastructure for m arine telecommunication where there will be an incr eased development footprint.

Activity 63 of GNR 983

The expansion of facilities or infrastructure for t he transfer of water from and to or between any com bination of the following—

(i) water catchments;

(ii) water treatment works; or

(iii) impoundments;

where the capacity will be increased by 50 000 cubi c metres or more per day, but excluding water treat ment works where water is treated for drinking

purposes.

Activity 64 of GNR 983

The expansion of railway lines, stations or shuntin g yards where there will be an increased developmen t footprint, excluding—

(i) railway lines, shunting yards and railway stati ons in industrial complexes or zones;

(ii) underground railway lines in mines; or

(iii) additional railway lines within the railway l ine reserve.

Activity 65 of GNR 983

The expansion and related operation of an island, a nchored platform or any other permanent structure o n or along the sea bed, where the expansion will

constitute an increased development footprint, excl uding expansion of facilities, infrastructure or st ructures for aquaculture purposes;

Activity 66 of GNR 983

The expansion of a dam where —

(i) the highest part of the dam wall, as measured f rom the outside toe of the wall to the highest part of the wall, was originally 5 metres or higher and

where the height of the wall is increased by 2,5 me tres or more; or

(ii) where the high-water mark of the dam will be i ncreased with 10 hectares or more.

Page 43: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

43

Activity 67 of GNR 983

Phased activities for all activities—

i. listed in this Notice, which commenced on or aft er the effective date of this Notice; or

ii. similarly listed in any of the previous NEMA no tices, which commenced on or after the effective da te of such previous NEMA Notices;

where any phase of the activity may be below a thre shold but where a combination of the phases, includ ing expansions or extensions, will exceed a specifi ed

threshold;

excluding the following activities listed in this N otice—

17(i)(a-d);

17(ii)(a-d);

17(iii)(a-d);

17(iv)(a-d);

17(v)(a-d);

20;

21;

22;

24(i);

29;

30;

31;

32;

34;

54(i)(a-d);

54(ii)(a-d);

54(iii)(a-d);

54(iv)(a-d);

54(v)(a-d);

55;

61;

62;

64; and

65.

Page 44: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

44

GNR 984: 2014 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 982, 983, 98 4 and 985 Government Gazette No 38282, Pretoria, 04 December 2014

Activity 1 of GNR

984

The development of facilities or infrastructure for the generation of electricity from a renewable res ource where the electricity output is 20 megawatts or more,

excluding where such development of facilities or i nfrastructure is for photovoltaic installations and occurs within an urban area.

Activity 2 of GNR 984

The development and related operation of facilities or infrastructure for the generation of electricit y from a non-renewable resource where the electrici ty output

is 20 megawatts or more.

Activity 3 of GNR 984

The development and related operation of facilities or infrastructure for nuclear reaction including e nergy generation, the production, enrichment, proce ssing,

reprocessing, storage or disposal of nuclear fuels, radioactive products, nuclear waste or radioactive waste.

Activity 4 of GNR 984

The development of facilities or infrastructure, fo r the storage, or storage and handling of a dangero us good, where such storage occurs in containers wi th a

combined capacity of more than 500 cubic metres.

Activity 5 of GNR 984

The development and related operation of facilities or infrastructu re for the refining, extraction or processing of ga s, oil or petroleum pro ducts with an

installed capacity of 50 cubic metres or more per d ay, excluding—

(i) facilities for the refining, extraction or proc essing of gas from landfill sites; or

(ii) the primary processing of a petroleum resource in which case activity 22 in this Notice applies.

Activity 6 of GNR 984

The development of facilities or infrastructure for any process or activity which requires a permit or licence in terms of national or provincial legisla tion

governing the generation or release of emissions, p ollution or effluent, excluding ─

(i) activities which are identified and included in Listing Notice 1 of 2014;

(ii) activities which are included in the list of w aste management activities published in terms of se ction 19 of the National Environmental Management:

Waste Act, 2008 (Act No. 59 of 2008) in which case the National Environmental Management: Waste Act, 2 008 applies; or

(iii) the development of facilities or infrastructu re for the treatment of effluent, wastewater or sew age where such facilities have a daily throughput

capacity of 2000 cubic metres or less.

Activity 7 of GNR 984

The development and related operation of facilities or infrastructure for the bulk transportation of d angerous goods ─

(i) in gas form, outside an industrial complex, usi ng pipelines, exceeding 1000 metres in length, with a throughput capacity of more than 700 tons per

day;

(ii) in liquid form, outside an industrial complex, using pipelines, exceeding 1000 metres in length, with a throughput capacity of more than 50 cubic

metres per day; or

(iii) in solid form, outside an industrial complex, using funiculars or conveyors with a throughput ca pacity of more than 50 tons day.

Activity 8 of GNR 984

The development of—

(i) airports, or

(ii) runways or aircraft landing strips longer than 1,4 kilometres.

Page 45: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

45

Activity 9 of GNR 984

The development of facilities or infrastructure for the transmission and distribution of electricity w ith a capacity of 275 kilovolts or more, outside an urban area

or industrial complex.

Activity 1 0 of GNR 984

The development of facilities or infrastructure for marine telecommunication.

Activity 1 1 of GNR 984

The development of facilities or infrastructure for the transfer of 50 000 cubic metres or more water per day, from and to or between any combination of the

following —

(i) water catchments;

(ii) water treatment works; or

(iii) impoundments;

excluding treatment works where water is to be trea ted for drinking purposes.

Activity 1 2 of GNR 984 The development of railway lines, stations or shunt ing yards excluding —

(i) railway lines, shunting yards and railway stati ons in industrial complexes or zones;

(ii) underground railway lines in a mining area; or

(iii) additional railway lines within the railway l ine reserve.

Activity 1 3 of GNR 984

The physical alteration of virgin soil to agricultu re, or afforestation for the purposes of commercial tree, timber or wood production of 100 hectares or more.

Activity 1 4 of GNR 984

The development and related operation of—

(i) an island;

(ii) anchored platform; or

(iii) any other structure or infrastructure on, bel ow or along the sea bed;

excluding —

(a) development of facilities, infrastructure or st ructures for aquaculture purposes; or

(b) the development of temporary structures or infr astructure where such structures will be removed wi thin 6 weeks of the commencement of

development and where indigenous vegetation will n ot be cleared.

Activity 1 5 of GNR 984

The clearance of an area of 20 hectares or more of indigenous vegetation, excluding where such clearan ce of indigenous vegeta tion is required for —

(iii) the undertaking of a linear activity; or

(iv) maintenance purposes undertaken in accordance with a maintenance management plan.

Page 46: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

46

Activity 1 6 of GNR 984 The development of a dam where the highest part of the dam wall, as measured from the outside toe of t he wall to the highest part of the wall, is 5 metre s or

higher or where the high-water mark of the dam cove rs an area of 10 hectares or more.

Activity 1 7 of GNR 984

Any activity including the operation of that activi ty which requires a mining right as contemplated in section 22 of the Mineral and Petroleum Resources

Development Act, 2002 (Act No. 28 of 2002), includi ng associated infrastructure, structures and earthw orks, directly related to the extraction of a miner al

resource, including activities for which an exempti on has been issued in terms of section 106 of the M ineral and Petroleum Resources Development Act, 200 2

(Act No. 28 of 2002).

Activity 1 8 of GNR 984 Any activity including the operation of that activi ty which requires an exploration right as contempla ted in section 79 of the Mineral and Petroleum Reso urces

Development Act, 2002 (Act No. 28 of 2002), includi ng associated infrastructure, structures and earthw orks.

Activity 1 9 of GNR 984

The removal and disposal of minerals contemplated i n terms of section 20 of the Mineral and Petroleum Resources Development Act, 2002 (Act No. 28 of 2002 ),

including associated infrastructure, structures and earthworks, directly related to prospecting of a m ineral resource, including activities for which an

exemption has been issued in terms of section 106 o f the Mineral and Petroleum Resources Development A ct, 2002 (Act No. 28 of 2002).

Activity 20 of GNR 984

Any activity including the operation of that activi ty which requires a production right as contemplate d in section 83 of the Mineral and Petroleum Resour ces

Development Act, 2002 (Act No. 28 of 2002), includi ng associated infrastructure, structures and earthw orks, directly related to the primary processing o f a

petroleum resource.

Activity 21 of GNR 984

Any activity including the operation of that activi ty associated with the primary processing of a mine ral resource including winning, reduction, extracti on,

classifying, concentrating, crushing, screening and washing but excluding the smelting, beneficiation, refining, calcining or gasification of the mineral

resource in which case activity 6 in this Notice ap plies.

Activity 22 of GNR 984

Any activity including the operation of that activi ty associated with the primary processing of a petr oleum resource including winning, extraction, class ifying,

concentrating, water removal, but excluding the ref ining of gas, oil or petroleum products in which ca se activity 5 in this Notice applies.

Activity 23 of GNR 984

The reclamation of an island or parts of the sea.

Activity 24 of GNR 984 The extraction or removal of peat or peat soils, in cluding the disturbance of vegetation or soils in a nticipation of the extraction or removal of peat or peat soils,

but excluding where such extraction or removal is f or the rehabilitation of wetlands in accordance wit h a maintenance management plan.

Activity 25 of GNR 984 The development and related operation of facilities or infrastructure for the treatment of effluent, w astewater or sewage with a daily throughput capacit y of

15000 cubic metres or more.

Activity 26 of GNR 984

Development--

(vi) in the sea;

(vii) in an estuary;

(viii) within the littoral active zone;

(ix) in front of a development setback; or

(x) if no development setback exists, within a dist ance of 100 metres inland of the high-water mark of the sea or an estuary, whichever is the greater;

Page 47: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

47

in respect of —

(c) facilities associated with the arrival and depa rture of vessels and the handling of cargo;

(d) piers;

(e) inter- and sub-tidal structures for entrapment of sand;

(f) breakwater structures;

(g) coastal marinas;

(h) coastal harbours or ports;

(i) tunnels; or

(j) underwater channels;

but excluding the development of structures within existing ports or harbours that will not increase t he development footprint of the port or harbour.

Activity 27 of GNR 984

The development of —

(i) a national road as defined in section 40 of the South African National Roads Agency Limited and Na tional Roads Act, 1998 (Act No. 7 of 1998);

(ii) a road administered by a provincial authority;

(iii) a road with a reserve wider than 30 metres; o r

(iv) a road catering for more than one lane of traf fic in both directions;

but excluding the development and related operation of a road for which an environmental authorisation was obtained for the route determination in terms of

activity 5 in Government Notice 387 of 2006 or acti vity 18 in Government Notice 545 of 2010, in which case activity 24 in Listing Notice 1 of 2014 applie s.

Activity 28 of GNR 984

Commencing of an activity, which requires an atmosp heric emission license in terms of section 21 of th e National Environmental Management: Air Quality Ac t,

2004 (Act No. 39 of 2004), excluding —

(i) activities which are identified and included in Listing Notice 1 of 2014;

(ii) activities which are included in the list of w aste management activities published in terms of se ction 19 of the National Environmental Management:

Waste Act, 2008 (Act No. 59 of 2008) in which case the National Environmental Management: Waste Act, 2 008 applies; or

(iii) the development of facilities or infrastructu re for the treatment of effluent, wastewater or sew age where such facilities have a daily throughput

capacity of 2000 cubic metres or less.

Activity 29 of GNR 984

The expansion and related operation of facilities f or nuclear reaction including energy generation, th e production, enrichment, processing, reprocessing,

storage or disposal of nuclear fuels, radioactive p roducts, nuclear waste or radioactive waste.

Page 48: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

48

GNR 985: 2014 Regulations promulgated in terms of the NEMA, Act No 107 of 1998: GNR 982, 983, 98 4 and 985 Government Gazette No 38282, Pretoria, 04 December 2014

Activity 1 of GNR

985 The development of billboards exceeding 18 square m etres in size outside urban areas, mining areas or industrial complexes.

Activity 2 of GNR 985

The development of reservoirs for bulk water supply with a capacity of more than 250 cubic metres.

Activity 3 of GNR 985

The development of masts or towers of any material or type used for telecommunication broadcasting or radio transmission purposes where the mast or

tower—

(a) is to be placed on a site not previously used f or this purpose; and

(b) will exceed 15 metres in height—

but excluding attachments to existing buildings and masts on rooftops.

Activity 4 of GNR 985

The development of a road wider than 4 metres with a reserve less than 13,5 metres.

Activity 5 of GNR 985

The development of resorts, lodges, hotels and tour ism or hospitality facilities that sleep less than 15 people.

Activity 6 of GNR 985

The development of resorts, lodges, hotels and tour ism or hospitality facilities that sleeps 15 people or more.

Activity 7 of GNR 985

The development of aircraft landing strips and runw ays 1.4 kilometres and shorter.

Activity 8 of GNR 985

The development and related operation of above grou nd cableways and funiculars.

Activity 9 of GNR 985

The development and related operation of zip- lines or foefie-slides exceeding 100 metres in length.

Activity 1 0 of GNR 985

The development of facilities or infrastructure for the storage, or storage and handling of a dangerou s good, where such storage occurs in containers wit h a

combined capacity of 30 but not exceeding 80 cubic metres.

Activity 1 1 of GNR 985

The development of tracks or routes for the testing , recreational use or outdoor racing of motor power ed vehicles excluding conversion of existing tracks or

routes for the testing, recreational use or outdoor racing of motor powered vehicles.

Activity 1 2 of GNR 985

The clearance of an area of 300 square metres or mo re of indigenous vegetation except where such clear ance of indigenous vegetation is required for

maintenance purposes undertaken in accordance with a maintenance management plan.

Activity 1 3 of GNR 985

The development and related operation of facilities of any size for any form of aquaculture.

Activity 1 4 of GNR 985

The development of—

(i) canals exceeding 10 square metres in size ;

(ii) channels exceeding 10 square metres in size;

(iii) bridges exceeding 10 square metres in size;

Page 49: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

49

(iv) dams, where the dam, including infrastructure and w ater surface area exceeds 10 square metres in size;

(v) weirs, where the weir, including infrastructure and water surface area exceeds 10 square metres in size;

(vi) bulk storm water outlet structures exceeding 10 square metres in size;

(vii) marinas exceeding 10 square metres in size;

(viii) jetties exceeding 10 square metres in size;

(ix) slipways exceeding 10 square metres in size;

(x) buildings exceeding 10 square metres in size;

(xi) boardwalks exceeding 10 square metres in size; or

(xii) infrastructure or structures with a physical footprint of 10 square metres or more;

where such development occurs—

(a) within a watercourse;

(b) in front of a development setback; or

(c) if no development setback has been adopted, wit hin 32 metres of a watercourse, measured from the e dge of a watercourse;

excluding the development of infrastructure or stru ctures within existing ports or harbours that will not increase the development footprint of the port or

harbour.

Activity 1 5 of GNR 985

The transformation of land bigger than 1000 square metres in size, to residential, retail, commercial , industrial or institutional use, where, such land was

zoned open space, conservation or had an equivalent zoning, on or after 02 August 2010.

Activity 1 6 of GNR 985

The expansion of reservoirs for bulk water supply w here the capacity will be increased by more than 25 0 cubic metres.

Activity 1 7 of GNR 985

The expansion of a resort, lodge, hotel and tourism or hospitality facilities where the development fo otprint will be expanded.

Activity 1 8 of GNR 985

The widening of a road by more than 4 metres, or th e lengthening of a road by more than 1 kilometre.

Activity 1 9 of GNR 985

The expansion of runways or aircraft landing strips where the expanded runways or aircraft landing str ips will be longer than 1,4 kilometres in length.

Activity 20 of GNR 985

The expansion and related operation of above ground cableways and funiculars where the development foo tprint will be increased.

Activity 21 of GNR 985

The expansion of tracks or routes for the testing, recreational use or outdoor racing of motor powered vehicles excluding conversion of existing tracks o r

routes for the testing, recreational use or outdoor racing of motor powered vehicles, where the develo pment footprint will be expanded.

Activity 22 of GNR 985

The expansion of facilities or infrastructure for t he storage, or storage and handling of a dangerous good, where such storage facilities or infrastructu re will be

expanded by 30 cubic metres or more but no more tha n 80 cubic metres.

Activity 23 of GNR 985

The expansion of—

(i) canals where the canal is expanded by 10 square metres or more in size;

(ii) channels where the channel is expanded by 10 square metres or more in size;

Page 50: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

50

(iii) bridges where the bridge is expanded by 10 square m etres or more in size;

(iv) dams where the dam is expanded by 10 square me tres or more in size;

(v) weirs where the weir is expanded by 10 square m etres or more in size;

(vi) bulk storm water outlet structures where the s tructure is expanded by 10 square metres or more in size;

(vii) marinas where the marina is expanded by 10 s quare metres or more in size;

(viii) jetties where the jetty is expanded by 10 s quare metres or more in size;

(ix) slipways where the slipway is expanded by 10 s quare metres or more in size;

(x) buildings where the building is expanded by 10 square metres or more in size;

(xi) boardwalks where the boardwalk is expanded by 10 square metres or more in size; or

(xii) infrastructure or structures where the physi cal footprint is expanded by 10 square metres or mo re;

where such development occurs—

(a) within a watercourse;

(b) in front of a development setback adopted in th e prescribed manner; or

(c) if no development setback has been adopted, wit hin 32 metres of a watercourse, measured from the e dge of a watercourse;

excluding the expansion of infrastructure or struct ures within existing ports or harbours that will no t increase the development footprint of the port or harbour.

Activity 24 of GNR 985 The expansion and related operation of facilities o f any size for any form of aquaculture.

Activity 25 of GNR 985 The expansion and related operation of zip- lines o r foefie-slides, where the zip- line or foefie-slid e is expanded by 100 metres in length or more.

Phased activities for all activities—

i. listed in this Notice and as it applies to a spe cific geographical area, which commenced on or afte r the effective date of this Notice; or

ii. similarly listed in in any of the previous NEMA notices, and as it applies to a specific geographi cal area, which commenced on or after the effective

date of such previous NEMA Notices—

iii.

where any phase of the activity may be below a thre shold but where a combination of the phases, includ ing expansions or extensions, will exceed a specifi ed

threshold; —

excluding the following activities listed in this N otice—7;

8;

Page 51: EIA Listed activities & Time Lines - PULAscreening.pula.co.za/Activities and Timelines - _ updated January... · EIA Listed activities & Time Lines UPDATED: JANUARY 2015 Background

51

11;

13;

17;

20;

21; and

24.