Effects of series compensation on spot price power markets
-
Upload
gb-shrestha -
Category
Documents
-
view
215 -
download
0
Transcript of Effects of series compensation on spot price power markets
![Page 1: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/1.jpg)
Effects of series compensation on spot price power markets
G.B. Shrestha*, Wang Feng
Power Market Research Group, School of EEE, S2, Nanyang Technological University, Singapore 639798, Singapore
Received 24 June 2003; revised 9 February 2005; accepted 3 March 2005
Abstract
The operation of a deregulated power market becomes more complex as the generation scheduling is dependent on suppliers’ and
consumers’ bids. With large number of transactions in the power market changing in time, it is more likely for some transmission lines to face
congestion. Series compensation, such as TCSC, with its ability to directly control the power flow can be very helpful to improve the
operation of transmission networks. The effects of TCSC on the operation of a spot price power market are studied in this paper using the
modified IEEE 14-bus system. Optimal Power Flow incorporating TCSC is used to implement the spot price market. Linear bids are used to
model suppliers’ and consumers’ bids. Issues of location and cost of TCSC are discussed. The effects of levels of TCSC compensation on
wide range of system quantities are studied. The effects on the total social benefit, the spot prices, transmission congestion, total generation
and consumption, benefit to individual supplier and consumer etc. are discussed. It is demonstrated that though use of TCSC makes the
system more efficient and augments competition in the market, it is not easy to establish general relationships between the levels of
compensation and various market quantities. Simulation studies like these can be used to assess the effects of TCSC in specific systems.
q 2005 Elsevier Ltd. All rights reserved.
Keywords: TCSC (Thyristor Controlled Series Compensator); Power markets; Spot price; Optimal power flow; TCSC cost
1. Introduction
The main objective of introducing competition in
electricity markets is to make them more efficient. The
basic idea is that if fair and equitable market structures are
established to give all market participants incentives to
maximize their own individual welfare, then the market as a
whole will behave in a manner which maximizes welfare for
everyone in a deregulated power market. A method used to
dispatch generation and load in an economic manner is to
use spot pricing theory. In a competitive market suppliers
and sometimes consumers submit bid curves to the pool
operator who determines the dispatch results to optimise the
system operation. Suppliers are then paid a price according
to their bids and consumers must pay a price according to
their bids.
Transmission network has to be shared by all market
participants, and uncontrollable nature of transmission lines
0142-0615/$ - see front matter q 2005 Elsevier Ltd. All rights reserved.
doi:10.1016/j.ijepes.2005.03.001
* Corresponding author.
E-mail address: [email protected] (G.B. Shrestha).
may limit the competitive bids by sellers and buyers.
Flexible AC Transmission Systems (FATCS) devices,
which can provide direct and flexible control of power
transfer, can be very helpful in the operation of competitive
power markets. Functions of FACTS devices or controllers
include increasing power transfer capacity of transmission
networks and to provide direct control of power flow over
designated transmission routes. With open access to
transmission systems and more delivery transactions due
to competition, transmission lines more likely to operate
near their transmission limits. Many studies have focused on
the implementation of FACTS in electricity market [1–3].
This paper presents simulation studies on the spot price
market incorporating Thyristor Controlled Series Compen-
sation (TCSC) to study the effects of TCSC on various
aspects of electricity market such as the overall social
benefit, spot prices, wheeling fees, transmission loss, etc.
The paper is organized as follows. Section 2 discusses the
spot price market model where linear bid curves have been
used to model the supplier and consumer bids. Modelling of
TCSC devices and modified Optimal Power Flow incorpor-
ating TCSC device is outlined in Section 3. Case studies to
investigate the effects of TCSC on various aspects of system
Electrical Power and Energy Systems 27 (2005) 428–436
www.elsevier.com/locate/ijepes
![Page 2: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/2.jpg)
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436 429
operation are presented in Section 4 followed by con-
clusions in Section 5.
2. Spot price market model
The main objective of introducing competition in power
markets is to make them more efficient. A method adopted
to dispatch generation and load in an economic manner is to
use spot pricing theory. Spot pricing theory was presented
by Schweppe in [4]. Hogan applied the model in
competitive power market [5]. Several recent studies have
been reported which utilize spot price concepts in the
management of power system congestion [16,17].
In spot price market model, there are three types of
participants: the consumers, the suppliers, and the trans-
mission/distribution operator, who determines the market
price and operates the system. The suppliers and consumers
submit bid curves that define amounts of energy (MW), and
the corresponding price ($/MW-h). These bids of suppliers
are often directly related to the marginal cost curves. The
pool operator treats the submitted bids as the true marginal
cost curves of the suppliers and the true marginal benefit
curves of the consumers and uses the Optimal Power Flow
(OPF) to minimize the total costs in order to determine the
generation dispatch and related spot prices.
Zij= rij +j xij
- j xc Bus-i Bus-j
jB i0 jBj0
(a)
Zij= rij +j xij
Sic Sjc
Bus-i Bus-j
(b)
Fig. 1. TCSC modeling. Transmission line with TCSC. (b) Injection model
of transmission line with TCSC.
2.1. Bid functions
Linear bid functions are used for both the supplier and
the consumer. The minimum price ps,min and the slope ms
specify the generation bid Sp of the suppler. The bid price is
modelled as:
ps Z ps; min CSp
ms
(1a)
then, the generation cost function C(x) is given by:
CðxÞ Z
ðx
0ps;min C
Sp
ms
� �dsp Z ps; minx C
x2
2ms
(1b)
In a traditional market, load is not considered as a variable
because of the inability of utilities to directly or indirectly
control loads. In a spot market, the consumer demand d is a
function of the price pc. The linear demand function may be
mathematically expressed with the slope md as:
d Z dmax Kmdpc (2a)
where, dmax is the maximum demand of the consumer.
Then, the inverse of this demand function can be
expressed as
pc Z pc; max Kd
md
(2b)
where
pc; max Zdmax
md
This inverse demand function represents the marginal
benefit of consuming unit quantity of electricity.
The integral of this function becomes the benefit function
B(x) which is a quadratic formulation:
BðxÞ Z
ðx
0
dmax
md
KD
md
� �dD Z
dmax
md
x K1
2md
x2 (2c)
The loads are considered to maintain constant power
factor. Further details on the bid curves in spot price markets
are given in [6].
3. Optimal power flow (OPF) incorporating TCSCs
Modelling of FACTS devices for various purposes and
approaches and formulations of low flow analysis incorpor-
ating FACTS devices have been reported in recent literature
[18–20], while the issues in OPF in the context of pool
paradigm has been discussed by Gross and Bompard [21].
This section outlines the OPF methodology used in the
studies in Section 4.
3.1. TCSC model
During steady state TCSC can be considered as a
additional reactance—jxc. The value of xc can be adjusted
according to control schemes specified. The simple steady
static model of a transmission line with a TCSC connected
between bus-i and bus-j is shown in Fig. 1(a).
The change in the line flow due to series capacitance
can be represented as a line without series capacitance with
power injected at the receiving and sending ends of the line
as shown in Fig. 1(b). The real power injections at bus-i (Pic)
and bus-j (Pjc) can be expressed as [6].
Pic Z V2i DGij KViVjðDGijcos dij CDBijsin dijÞ (3a)
Pjc Z V2j DGij KViVjðDGij cos dij KDBij sin dijÞ (3b)
![Page 3: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/3.jpg)
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436430
Similarly, the reactive power injections at bus-i (Qic) and
bus-j (Qjc) can be expressed as:
Qic ZKV2i DBij KViVjðDGij sin dij KDBij cos dijÞ (4a)
Qjc ZKV2j DBij CViVjðDGij sin dij CDBij cos dijÞ (4b)
where
DGij Zxcrijðxc K2xijÞ
ðr2ij Cx2
ijÞðr2ij C ðxij KxcÞ
2Þ;
DBij ZKxcðr
2ij Kx2
ij CxcxijÞ
ðr2ij Cx2
ijÞðr2ij C ðxij KxcÞ
2Þ
(5)
These steady Power Injection Model of TCSC is used to
properly modify the parameters of transmission lines with
TCSCs [7] for optimal power flow algorithms in the
following studies.
3.2. TCSC cost
The cost of a multi-module TCSC is represented in the
form of a linear equation as [8].
Cf ;k Z cxc;k
S2max
SB
(6)
where
c is the cost coefficient of TCSC ($/MVA-year); in this
study cZ22,000 $/MVA-year is adopted [9];
Smax is the thermal limits of line where kth FACTS
device is placed (MVA);
SB is the base power (MVA);
xc,k is the kth series capacitive reactance (pu).
The formulation allows the capital cost of TCSC to vary
with the TCSC capacity (MVA). The thermal limit included
in the formulation helps to satisfy the thermal limit of the
transmission line when a TCSC is added to that line.
3.3. Objective function
The objective function in the spot market is the
maximization of social benefits including the cost of
FACTS devices which can be expressed as:
MaxXi2D
BiðxiÞKXj2G
CjðxjÞKXk2Nc
Cf ;kðxc;kÞ (7)
where xc,k is the kth series compensation device and Nc is the
total number of series compensation devices in the system.
3.4. Operating constraints
All operating constraints of the transmission networks
are to be satisfied.
(i)
Power injection: the net injections of real and reactivepower at each bus should be zero.
Pi Z Vi
XN
jZ1
½Vj½gij cosðdi KdjÞCbij sinðdi KdjÞ��
KPGi CPCi Z 0
Qi Z Vi
XN
jZ1
½Vj½gij sinðdi KdjÞKbij cosðdi KdjÞ��
KQGi CQCi Z 0
(8)
(ii)
Generation limits: the limits on the maximum andminimum outputs of the generators are incorporated as:
Pg; min %Pg%Pg; max Qg; min %Qg%Qg; max g2G (9)
(iii)
Demand limits: the limits on consumers’ maximumand minimum demands are imposed as
Pc; min %Pc%Pc; max Qc; min %Qc %Qc; max c2C
QcZc
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi1 Kpf 2
c
ppfc
!Pc ð10Þ
(iv)
Transmission limits: the limit on the MVA flow on atransmission line in incorporated as:
jSijj2 %S2
ij max (11)
(v)
Voltage limits: voltage limit at each bus is expressed as:Vi; min %Vi%Vi; max; i2N (12)
(vi)
After including TCSC devices, the inequality con-straints will include the limits of these devices, which
means the maximum and minimum values of equival-
ent reactance (xc) [10].
xci; min %xci%xci; max
i2Nc
)TCSC (13)
for all Nc number of TCSCs.
3.5. Solution technique
The Lagrange function of the optimisation problem
incorporating all the constraints in the objective function is
![Page 4: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/4.jpg)
Table 1
OPF results without TCSC
Social benefit ($/h) Generation cost ($/h) Customer benefit ($/h)
1577.3 1417.0 2994.3
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436 431
formed as:
Lð,ÞZXi2D
BiðxiÞKXj2G
CjðxjÞKXk2Nc
Cf ;kðxc;kÞ
KXi2G
miPG; minðPGi; min KPGiÞ
KXi2G
miPG; maxðPGi KPGi; maxÞ
KXi2G
miQG; minðQGi; min KQGiÞ
KXi2G
miQG; maxðQGi KQGi; maxÞ
KXi2D
miPC; minðPCi; min KPCiÞ
KXi2D
miPC; maxðPCi KPCi; maxÞ
KXi2D
miQC; minðQCi; min KQCiÞ
KXi2D
miQC; maxðQCi KQCi; maxÞKXi2N
lipðPiÞ
KXi2N
liQðQiÞKXi2C
lipf Qi K
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi1Kpf 2
i
pf 2i
s!Pi
!
KXi2N
Xj2N
mij; maxðjSijjKSij; maxÞ
KXi2N
Xj2N
mji; maxðjSjijKSji; maxÞ
KXi2N
miv; minðVi; min KViÞKXi2N
miv; maxðVi; max KViÞ
KXi2Nc
mci; minðxci; min KxciÞKXi2Nc
mci; maxðxci; max KxciÞ
Table 2
System operation data without TCSC
Bus no. Voltage Generation
Mag. (pu) Ph. Ang. (deg) P (MW) Q (MVAr)
1 1.100 0.0 95.6 38.8
2 1.089 K2.282 100.0 50.0
3 1.100 K1.111 100.0 40.0
4 1.011 K6.639 – –
5 1.007 K6.681 – –
6 1.035 K9.301 53.0 12.4
7 1.051 K9.661 –
8 1.090 K9.661 0.0 24.0
9 1.037 K11.245 – –
10 1.018 K11.826 – –
11 1.002 K11.663 – –
12 0.993 K10.602 – –
13 1.008 K10.604 – –
14 0.976 K13.118 – –
Total 348.6 165.2
Sequential Quadratic Programming (SQP) method is
used for the solution of the OPF problem, which can provide
all the marginal prices directly. The detailed development of
the solution procedure along with its detailed implemen-
tation process in MATLAB environment is described in
[15].
4. Case studies
The modified IEEE 14-bus system [11] has been used to
investigate the effects of TCSC device on market operation
including the social benefit and the benefits of each market
participant. The system diagram is shown in Fig. 2. Bus 1, 2,
3, 6 are the buses where power suppliers G1, G2, G3, G4 are
located. Bus 4, 5, 9–14 are those buses where power
consumers D1–D8 are located. Further details on para-
meters are given in [12]. The generator cost functions and
the consumer benefit functions are given by Eqs. (2) and (5),
respectively. The coefficients of the cost function are
adopted from [13]. Based on the values in [14],
the coefficients of the benefit functions are shown in
Appendix A. The voltage magnitude limits and transmission
line ratings are also shown in Appendix A. In this study, the
load power factor is kept constant at 0.9 (lag).
4.1. System operation without TCSC
The base case of power system operation obtained from
OPF without any TCSC is listed in Tables 1–3. It can been
seen that congestions occurred in line 13, 14, 15, and 16
which implies that although some power consumers did bid
higher price in power markets they cannot access to the
cheaper power due to the transmission limits. This is caused
by the physical characteristics of transmission network.
Long-term congestion may lead to large amount of waste in
Load Spot Price
P (MW) Q (MVAr) P ($/MVAr h) Q ($/MW h)
– – 5.68 0.0
– – 5.80 0.28
– – 5.73 0.28
107.6 52.1 6.50 0.57
116.2 56.3 6.25 0.56
– – 4.95 0.0
– – 7.30 1.02
– – 7.30 0.95
5.0 2.4 7.74 1.28
20.8 10.1 8.54 1.72
20.7 10.5 8.67 1.41
26.0 12.6 9.97 2.27
5.0 2.4 11.29 2.26
29.4 14.2 9.90 2.16
331.7 160.6 – –
![Page 5: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/5.jpg)
Table 4
OPF result with TCSC
Social benefit ($/h) Generation cost ($/h) Customer benefit ($/h)
1595.9 1432.1 3030.9
Table 3
Line flows limited by line ratings
Line (From) bus (To) bus Line rating
(MVA)
Line flow
(MVA)
13 9 10 25 25.0
14 6 11 25 25.0
15 6 12 25 25.0
16 6 13 25 25.0
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436432
social benefits. For pool operator such as ISO, it is necessary
to encourage competition and reduce the waste. FACTS
devices can detour the power through the congested
transmission line and hence enable cheaper power to be
transferred from generators to consumers.
4.2. Locations of TCSCs
Several studies have been reported which investigate the
optimal placement of FACTS devices for various network
purposes [22,23]. In this study, the location of TCSC is
taken as the best when it achieves the maximum total social
benefit. The maximum series capacitive compensation of
TCSC is limited to 70% reactance of the line reactance
where is placed. A trial-and-error method is used to
determine the best location. Since the congestion in the
network occurred on the upper part of the transmission
network, which is composed of two loops, it is reasonable
that TCSC mounted on one of transmission line between
these two loops should be effective. It is found that the best
Table 5
System operation data with TCSC
Bus no. Voltage Generation
Mag. (pu) Ph. Ang. (deg) P (MW) Q (MVAr)
1 1.100 0.0 95.9 39.8
2 1.085 K0.748 100.0 50.0
3 1.095 0.193 100.0 40.0
4 0.994 K6.425 – –
5 0.991 K6.329 – –
6 1.031 K8.245 55.7 12.5
7 1.034 K9.606 –
8 1.073 K9.606 0.0 24.0
9 1.020 K11.273 – –
10 1.000 K11.812 – –
11 1.000 K10.695 – –
12 0.989 K9.541 – –
13 1.004 K9.521 – –
14 0.983 K11.266 – –
Total 351.6 166.3
location for TCSC is on line 17 because it increases the
social benefit most. When multi-TCSC devices are to be
considered, similar heuristic method is adopted to determine
the locations. Line 17 and 13 are deemed the best locations
for two TCSCs and lines 17, 13, and 15 are the best positions
for three TCSCs.
4.3. System operation studies with TCSC
4.3.1. System-wide effects
Operation of the power market is studied with one TCSC
placed on line 17 at different levels of TCSC compensation.
The details of results at 70% compensation are shown in
Tables 4–6. Table 7 lists the value of important system
quantities at different levels of TCSC compensation placed
on the line 17.
It is seen that the social benefit increases gradually from
1577 to 1596 $/h with the increase in the level of
compensation from 0 to 70%. There are the net increases
in social benefit after accounting for the cost of the TCSC
devices, which also increases with the level of compen-
sation to $3/h at 70% compensation. It should be noted that
the increase in social benefit is the combined result of the
changes in the consumer benefit and the generation cost.
Consumer benefit is found to increase monotonously from
2994 $/h at 0% compensation to 3031 $/h at 70% compen-
sation, while the generation cost is reduced initially from
1417 $/h at 0% compensation to 1413 $/h at 20% compen-
sation and then gradually increases to 1432 $/h at 70%
compensation. Thus the introduction of TCSC makes the
production of some extra power feasible in the power
market, which is also indicated by: (i) the increase in the
generation output from 349 MW at 0% compensation to
352 MW at 70% compensation, and (ii) the increase in total
consumption from 332 MW at 0% to 335 MW at 70%
compensation.
Load Spot price
pu (MW) pu (MVAr) P ($/MVAr h) Q ($/MW h)
– – 5.70 0.0
– – 5.82 0.26
– – 5.75 0.27
107.7 52.2 6.50 0.57
116.2 56.0 6.27 0.54
– – 5.14 0.0
– – 7.61 1.02
– – 7.61 0.95
5.0 2.4 8.22 1.27
26.8 12.6 8.59 1.30
15.4 7.4 8.99 1.13
25.9 12.6 9.99 2.22
9.2 4.5 10.55 2.30
29.5 14.3 9.96 2.02
334.5 162.0 – –
![Page 6: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/6.jpg)
Table 6
Line flows limited by line ratings
Line (From) bus (To) bus Line rating
(MVA)
Line flow
(MVA)
13 4 9 25 25.0
14 6 11 25 25.0
15 6 12 25 25.0
16 6 13 25 25.0
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436 433
It is apparent that the installation of TCSC produces
benefit that far exceeds its cost for the system conditions
studied. The net benefit may not be so significant during low
levels of load or generation. And studies over extended
periods would be necessary would be necessary if we need
to evaluate the feasibility of FACTS device installation.
Although, the effects of TCSC on different facets of the
market operation may be too complex for analytical
treatment, simulation studies like these can certainly be
helpful in evaluating the likely effects. This study can be
readily extended to evaluate the total benefits for extended
periods of time (a day, a week or longer) by incorporating
system operating data (hourly generation and demand bids)
for the entire period of investigation.
Table 7
Impact of TCSC with different limits on maximum compensation
Compensation of TCSC 0% 10%
Cost of TCSC ($/h) 0 0.4
Social benefit ($/h) 1577 1580
Consumer benefit ($/h) 2994 2996
Generation cost ($/h) 1417 1415
Total generation (MW) 349 348
Total consumption (MW) 332 331
Real power losses (MW) 16.9 17.0
Table 8
Generation output with different TCSC maximum compensation limits
Real power (MW) Compensation of TCSC
Gen Bus 0% 10% 2
G1 Bus 1 95.6 95.5 9
G2 Bus 2 100 100 1
G3 Bus 3 100 100 1
G4 Bus 6 53.0 52.7 5
Table 9
Consumer demands with different TCSC maximum compensation levels
Load demand
(MW)
Compensation of TCSC
0% 10% 20%
Bus 4 107.6 106.7 105.7
Bus 5 116.2 115.6 115.0
Bus 9 5 5 5
Bus 10 20.8 21.7 22.8
Bus 11 21.7 20.8 19.7
Bus 12 26.0 26.0 26.0
Bus 13 5.0 5.0 5.0
Bus 14 29.4 30.5 31.6
4.3.2. Impacts on individual suppliers and consumers
The changes in individual consumer’s demand and
supplier’s output at different level of TCSC compensation
are shown in Tables 8 and 9. Because generator 2 and 3
reached their maximum output limits, their outputs remain
constant unaffected by TCSC. Load demands at bus 9 and
13 are at their minimum limits by 20% compensation.
Demand at bus 13 is increased at higher level of TCSC
compensation while the demand at bus 9 remains at its
minimum value throughout.
In this study, a consumer’s welfare is the amount of benefit
the consumer received from using the power, minus the
expense incurred in purchasing the power. Similarly, a
supplier’s welfare is the amount of revenue received from
selling the power, minus the cost of supplying the power. The
individual welfare of each market participant at different
level of TCSC compensation may be computed and are listed
in Tables 10 and 11. Except those buses where generation or
consumption have reached the limits, the change in welfare
of market participants have the same trend as the changes in
generation and demand shown in Tables 8 and 9.
Although, the generation at bus 2 and 3 hit their
maximum limits (100 MW), their individual welfare keeps
20% 40% 60% 70%
0.9 1.7 2.6 3.0
1584 1590 1594 1596
2997 3012 3025 3031
1413 1421 1429 1432
348 350 351 352
331 332 334 335
17.1 17.2 17.1 17.1
0% 40% 60% 70%
5.5 95.4 95.8 95.9
00 100 100 100
00 100 100 100
2.3 54.1 55.2 55.7
40% 60% 70%
106.4 107.3 107.8
115.1 115.4 115.6
5 5 5
24.8 25.6 26.1
17.1 16.0 15.4
25.9 25.9 25.9
5.7 8.1 9.2
32.4 30.5 29.5
![Page 7: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/7.jpg)
Table 11
Consumer welfare ($/h) with different TCSC compensation levels
Bus No Compensation of TCSC
0% 10% 20% 40% 60% 70%
Bus 4 203.5 201.7 199.9 202.6 202.9 203.2
Bus 5 233.8 233.0 232.2 232.4 231.1 230.6
Bus 9 K14.0 K14.3 K14.6 K16.3 K16.3 K16.3
Bus 10 23.8 25.2 26.8 26.6 26.5 26.6
Bus 11 21.9 20.8 19.4 14.7 12.8 12.0
Bus 12 40.7 41.0 41.2 40.3 40.1 39.9
Bus 13 3.1 3.7 4.4 7.1 10.2 11.8
Bus 14 46.3 49.1 52.1 51.2 46.7 44.5
Table 10
Generator welfare ($/h) with different TCSC compensation levels
Bus no. Compensation of TCSC
0% 10% 20% 40% 60% 70%
Bus 1 223.8 223.5 223.3 222.9 224.6 225.3
Bus 2 128.9 129.1 129.3 128.3 130.1 130.8
Bus 3 84.3 84.4 84.6 83.6 85.6 86.4
Bus 6 104.6 103.1 101.6 108.8 113.2 115.2
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436434
changing at different TCSC compensation levels. This is
due to the change in spot prices incurred. The negative value
for the consumer welfare at bus 9 is due to the minimum
load demand limit. If this constraint is removed by setting
this minimum limits to zero, the study results show that the
load demand at bus 9 reduces to zero.
Thus, it is seen that the benefits to individual supplier and
consumer are not uniformly distributed and some participants
may actually face reduction in their welfare/profit. Although
TCSC will always provide overall benefit to the system as a
whole, some market participants benefit more and others
benefit less. It is reasonable that those who benefit more should
bear the cost of FACTS devices in proportion to their benefit.
This concept is being considered for further investigation.
4.3.3. Effects on spot prices
The spot prices at generator buses and load buses with the
levels of TCSC compensation are shown in Figs. 3 and 4,
2
3
2
45
6 78
91011
12 13 14
G3
G2
G4
G5
G1
13
45 6
7
89
10 11
12
1318
14
15 16
1719 20
D1 D2 D3
1
Fig. 2. Modified IEEE 14-bus system diagram.
respectively. The general effect of TCSC on spot prices that it
reduces the higher spot prices and increases the lower spot
prices towards the mean value becomes apparent from these
figures. The highest spot price at bus 13 is reduced most thus
reducing the load demand at this bus. Similarly, the lowest
spot price at bus 6 is raised most thus increasing the generator
output at bus 6.
It may be worth noticing that before 20% compensation
of TCSC, the power transfer is redistributed throughout the
transmission network so as to make loads at bus 10 and 14
increase. That contributes to the increase of social benefit
although the total generation and the consumption decrease
and the total real power losses increase. After 20%
compensation level, the transmission line 17 (between
bus 9 and bus 14) and transmission line 11 (between bus 4
and bus 9) reach their maximum transfer limits and line 13
became un-congested. It drives the spot price at bus 9 and 14
0 10 20 30 40 50 60 70 804.8
5.0
5.2
5.4
5.6
5.8
bus1bus2bus3bus6
Rea
l Pow
er S
pot P
rice
(U
S$/W
M-h
r)
TCSC Compensation level
Fig. 3. Spot prices at generator buses at different level of TCSC
compensation.
![Page 8: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/8.jpg)
0 10 20 30 40 50 60 70 806
7
8
9
10
11
bus4 bus5 bus9 bus10 bus11 bus12 bus13 bus14
Rea
l Pow
er S
pot P
rice
(U
S$/M
W-h
r)
TCSC Compensation level
Fig. 4. Spot prices at load buses at different level of TCSC compensation.
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436 435
higher and spot price at bus 10 lower, compared to those
cases at other compensation levels of TCSC. Thus, it is not
easy to establish precise relationships between the spot
prices and the levels of compensation. Simulation studies
like this would be necessary to view such impacts.
5. Conclusions
Simulation studies on the effects of TCSC on the
operation of spot price power market have been presented
in this paper using a modified IEEE 14-bus system.
A suitable formulation of TCSC cost is established and
Table A-1
Generator data
Gen.No. Bus no. P (MW) Q (MVar)
Max. Min. Max.
1 1 100 20 40
2 2 500 100 50
3 3 500 100 40
4 6 100 20 24
5 8 – – 24
Generation costZC2P2G CC1PG CC0. Note: generator 5 at bus 8 supplies reactiv
Table A-2
Demand data
Demand no. Bus no. pf (lag) P (MW) Q
Max. Min. M
1 4 0.9 200 50 20
2 5 0.9 200 50 20
3 9 0.9 100 5 20
4 10 0.9 100 5 20
5 11 0.9 100 5 20
6 12 0.9 100 5 20
7 13 0.9 100 5 20
8 14 0.9 100 5 20
Consumer benefitZC2P2D CC1PD CC0
included in the objective function. Heuristic method has
been used to determine the locations of TCSC devices with
the objective to maximize the social benefit. It is seen that
with its ability to redistribute power flow in the network,
TCSC can influence the loads and generation at different
buses to achieve significant increase in the social benefit.
Inclusion of TCSC makes the spot price at generator
buses and load buses move towards the average value. In
this way, the impact of TCSC is to enhance total benefit and
reduce the waste of social benefit.
TCSC may affect the welfare gained by individual
participant in different way. Because the use of TCSC
influences the spot price at different buses differently, some
participants benefit more and some benefit less.
Though, the use of TCSC in a market can make it more
efficient, it is not easy to establish direct relationships
between the amount of compensation and various market
quantities. However, simulation can be used to assess the
impacts of TCSC on the desired quantities. The increase in
benefits from using TCSC may not be very high at low
levels of demand and generation. Simulation studies over
extended periods of time would be necessary to evaluate the
overall benefit over long periods of time to evaluate the
actual feasibility of TCSC in an actual system.
Appendix A
Modified IEEE 14-bus System Data. Tables A-1–A-4.
Cost coefficients
Min. C2 C1 C0
K40 0.0245 1 0
K40 0.0351 1 0
K40 0.0389 1 0
K6 0.0372 1 0
K6 – – –
e power only.
(MVar) Cost coefficients
ax. Min. C2 C1 C0
0 K200 K0.015 10 0
0 K200 K0.015 10 0
0 K200 K0.010 5 0
0 K200 K0.015 10 0
0 K200 K0.015 10 0
0 K200 K0.018 12 0
0 K200 K0.018 12 0
0 K200 K0.018 12 0
![Page 9: Effects of series compensation on spot price power markets](https://reader035.fdocuments.us/reader035/viewer/2022080101/57501dd51a28ab877e8d979b/html5/thumbnails/9.jpg)
Table A-4
Modified IEEE 14-bus system line rating
Line (From) bus (To) bus Line rating
(MVA)
1 1 2 292.41
2 2 3 292.41
3 2 4 292.41
4 1 5 292.41
5 2 5 292.41
6 3 4 292.41
7 4 5 292.41
8 5 6 42.25
9 4 7 42.25
10 7 8 25.0
11 4 9 16.0
12 7 9 42.25
13 9 10 25.0
14 6 11 25.0
15 6 12 25.0
16 6 13 25.0
17 9 14 25.0
18 10 11 25.0
19 12 13 25.0
20 13 14 25.0
Table A-3
Bus data
Bus no. Max. voltage
magnitude (pu)
Min. voltage
magnitude (pu)
1–14 1.1 0.97
G.B. Shrestha, W. Feng / Electrical Power and Energy Systems 27 (2005) 428–436436
References
[1] Coates D. ‘FACTS: a transmission utility perspective’, flexible AC
transmission systems—the FACTS (Ref. No. 1998/500). IEE
Colloquium; 1998. 2/1–7.
[2] Baldick R, Kahn E. ‘Contract paths phase-shifters and efficient
electricity trade’. IEEE Transactions on Power Systems, vol. 2, no. 12;
1997. pp. 749–55.
[3] Foss AM. ‘FACTS opportunities in England and Wales’, flexible AC
transmission systems (FACTS)—the key to increased utilisation of
power systems. IEE Colloquium on (Digest No. 1994/005); 1994. pp.
7/1–8.
[4] Schweppe FC, Caramanis MC, Tabors RD, Bohn RE. Spot pricing of
electricity. Boston: Kluwer Academic Publishers; 1988.
[5] Hogan WW. Contract networks for electric power transmission.
J Regul Econom 1992;4(3):211–42.
[6] Feng W, Shrestha GB. Impacts of TCPAR on spot price power system
operation in competitive power markets. The fifth international power
engineering conference. vol. 2 2001 p. 592–7.
[7] Singh SN, David AK. Congestion management by optimising FACTS
device location. International conference on electric utility deregula-
tion and restructuring and power technologies 2000.
[8] de Oliveira EJ, Lima JWM, Pereira JLR. Flexible AC transmission
system devices: allocation and transmission pricing. Int J Electrical
Power Energ Syst 1999;21:111–8.
[9] Griffin J, Atanackovic D, Galiana FD. A study of the impact of
FACTS on the secure-economic operation of power systems. 12th
power systems computation conference. Dresden 1996 p. 1077–82.
[10] Feng W, Shrestha GB. Allocation of TCSC devices to optimize total
transmission capacity in a competitive power market. Power
Engineering Society Winter Meeting, 2001 IEEE, vol. 2; 2001. pp.
587–93.
[11] Fang RS, David AK. Optimal dispatch under transmission contracts.
IEEE Trans Power Syst 1999;14(2):732–7.
[12] Freris LL, Sasson AM. Investigation on the load flow problem.
Proceedings of IEE. vol. 115 1968 pp. 1459–70.
[13] Srivastava SC, Verma RK. Impact of FACTS devices on transmission
pricing in a de-regulated electricity market. Proceeding of inter-
national conference on electric utility deregulation and restructuring
and power technologies, City University, London 2000 pp. 642–48.
[14] Weber JD, Overbye TJ, DeMarco C. Modeling of consumer benefit in
the optimal power flow. Decision Support Syst 1999;24(3–4):279–96.
[15] Feng W. Effects of TCSC and TCPAR on the operation of competitive
power markets. Master’s thesis presented to School of EEE, Nanyang
Technological University, Singapore; 2001.
[16] Gan D, Bourcier DV. Locational market power screening and
congestion management: experience and suggestions. IEEE Trans
Power Syst 2002;17(1):180–5.
[17] Aguado JA, Quintana VH, Madrigal M, Rosehart WD. Coordinated
spot market for congestion management of inter-regional electricity
markets. IEEE Trans Power Syst 2004;19(1):180–7.
[18] Kazemi A, Badrzadeh B. Modeling and simulation of SVC and TCSC
to study their limits on maximum loadability point. Int J Electrical
Power Energ Syst 2004;26(8):619–26.
[19] Xiao Y, Song YH, Sun YZ. Power flow control approach to power
systems with embedded FACTS devices. IEEE Trans on Power Syst
2002;17(4):943–50.
[20] Mhaskar UP, Mote AB, Kulkarni AM. A new formulation for load
flow solution of power systems with series FACTS devices. IEEE
Trans Power Syst 2003;18(4):1307–15.
[21] Gross G, Bompard E. Optimal power flow application issues in the
Pool paradigm. Int J Electr Power Energ Syst 2004;26(10):787–96.
[22] Lee K-H. Optimal siting of TCSC for reducing congestion cost by
using shadow prices. Int J Electr Power Energ Syst 2002;24(8):
647–53.
[23] Zuwei YU, Lusan D. Optimal placement of FACTS devices in
deregulated systems considering line losses. Int J Electr Power Energ
Syst 2004;26(10):813–9.
G.B. Shrestha (IEEE S-88, M-90, SM-92) received B.E. (Honours) degree
in Electrical Engineering from Jadavpur University (India) in 1975, MBA
from University of Hawaii in 1985, MS in Electrical Power Engineering
from RPI in 1986, and PhD in Electrical Engineering from Virginia Tech in
1990. Presently he is an Assoc. Prof. at Nanyang Technological University,
Singapore. His main area of interest is power system operation and
planning.
Wang Feng (IEEE S-99) obtained his B.E. from Hohai University,
Nanjing, China in 1994. After working for several years as a development
engineer for EMS (Energy Management System) and DTS (Dispatch
Training Simulator) in Nanjing Automation Research Institute (NARI), he
is pursuing his postgraduate degree at Nanyang Technological University,
Singapore.