EEGS IRKP2 Meeting
ROSA activities in EEGS
Date 24.06.2010
Place Warsaw
EGNOS Extension to Eastern Europe
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 2EEGS-IRKP2 Meeting
Status of ROSA activities in EEGS:
WP2: EGNOS Improvement in Eastern Europe WP3: Regional Feasibility and Integration Studies WP4: Demonstration Activities
CONTENTS
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 3 EEGS-IRKP2 Meeting
WP2: EGNOS improvement in Eastern Europe
Activities: WP2.3 Infrastructure improvements
– ROSA provided one week of RINEX data (1Hz GPS L1/L2) for Romanian reference station(s) (BUCU and BUC1)
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 4 EEGS-IRKP2 Meeting
WP3: REGIONAL FEASIBILITY AND INTEGRATION STUDIES
Activities: WP3.1 GNSS context, RIMS and Service Provision
– Task 2:ROSA will compile the information requested in a document template according to the guidelines and will fill the document for the Romanian case: EEGS-ROSA_ROMS_D8 document
– The document has two parts: • RIMS data collection sheet• GNSS Market Development information
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 5 EEGS-IRKP2 Meeting
WP3: REGIONAL FEASIBILITY AND INTEGRATION STUDIES
Activities: WP3.1 GNSS context, RIMS and Service Provision
– RIMS data collection sheet
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 6 EEGS-IRKP2 Meeting
WP3: REGIONAL FEASIBILITY AND INTEGRATION STUDIES
Activities: WP3.1 GNSS context, RIMS and Service Provision
– RIMS data collection sheet –RIMS location in BucharestFaculty of Land Reclamation and Environmental Engineering
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 7 EEGS-IRKP2 Meeting
WP3: REGIONAL FEASIBILITY AND INTEGRATION STUDIES
Activities: WP3.1 GNSS context, RIMS and Service Provision
– GNSS Market Development information• Air Traffic Service providers interested in GNSS (market analysis
and sizing) • Maritime /Road providers interested in GNSS (market analysis and
sizing) • R&D Companies in GNSS market (market analysis and sizing) • General companies interested in GNSS applications (SBAS data
exploitation, market analysis and sizing,...)
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 8 EEGS-IRKP2 Meeting
WP4: Demonstration Activities
Activities: WP 4.1 Definition and Procurement
– Task 4: ROSA will prepare the demonstrations in Romania with all the necessary preparatory activities which will include as a minimum and as required by the associated demonstrations
WP 4.2 EGNOS Extension Demonstrations – Task 2: ROSA will manage a demonstration in Romania. This
demonstration will show how EGNOS coverage area could cover Romania with an enhanced EGNOS with algorithm modifications and additional RIMS in Romania (the number of RIMS will be an input from the WP 2.3 analyses).
WP 4.4 Demonstrations Results Analyses – Task 2: ROSA will analyze the results of the demonstrations in
Romania at user level.
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 9 EEGS-IRKP2 Meeting
WP4: Demonstration Activities
Activities: WP 4.1 Definition and Procurement
– ROSA will compile the information requested in a document template according to the guidelines and will fill the document for the Romanian demonstrations: EEGS-ROSA_ROMD_D16 document
• Dynamic demonstration• Static demonstration• Waterway demonstration
Objective- comparison between GPS-only signal, signal with magicSBAS and signal with ROMPOS (Romanian Position determination System) DGNSS service
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 10 EEGS-IRKP2 Meeting
WP4: Demonstration ActivitiesActivities: WP 4.1 Definition and Procurement
– Dynamic demonstration
Time Km I nstruction Toward
1h 15 min 103 km 1.Head East on E81/ A1 toward Bucharest
Bucharest
1 min 200 m 2.Turn right to exit the Highway on Bucharest Beltway
Bucharest Beltway2 min 700 m 3.At the roundabout, take the
3rd exit onto the Bucharest Bucharest Beltway20 min 10 km 4.Continue on Bucharest
BeltwayA2 Highway
1 min 170 m 5. Slightly turn right to enter A2 Highway
A2 Highway
1 min 400 m 6.At the roundabout, take the 2nd
exit onto the A2 Highway
Cernavoda
1h 45 min 148 km 7. Head East on A2 Highway Cernavoda
5 min 13:30 8. Exit the Highway
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 11 EEGS-IRKP2 Meeting
WP4: Demonstration ActivitiesActivities: WP 4.1 Definition and Procurement
– Waterway Demonstration
EGNOS Extension to Eastern Europe
Company’s
logo19/04/23 Page 12 EEGS-IRKP2 Meeting
WP4: Demonstration ActivitiesActivities: WP 4.1 Definition and Procurement
– Waterway Demonstration