EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation...
-
Upload
horatio-conley -
Category
Documents
-
view
222 -
download
0
Transcript of EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation...
![Page 1: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/1.jpg)
EE and SE Installation
Wolfgang Funk - CERN CMS11/9/2002 1
1.) Introduction2.) Installation scenario3.) SE schedule, manpower, cost estimates 4.) EE schedule, manpower, cost estimates 5.) Conclusion
![Page 2: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/2.jpg)
Introduction:
Wolfgang Funk - CERN CMS11/9/2002 2
SE (preShower Endcap)• Each SE is a donut-shaped disk of 2.5 tons • SEs have to be installed before beampipe in ’06 according to V33• SEs arrive fully tested at SX5• Preliminary installation of SE on EE Dummies to debug
EE (Ecal Endcap)• Each EE consists of 2 Dees• Each Dee is a half-disk of 12 tons (incl. frame), installation after beampipe possible• Dees arrive fully tested and in up-right position at SX5 after test mounting at assembly area
HE = HCAL Endcap, HF = HCAL Forward
![Page 3: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/3.jpg)
EE and SE:
Wolfgang Funk - CERN CMS11/9/2002 3
EESE
![Page 4: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/4.jpg)
EE Dummy Mounting
Wolfgang Funk - CERN CMS11/9/2002 4
Raisers
EE platform
![Page 5: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/5.jpg)
EE Platform
Wolfgang Funk - CERN CMS11/9/2002 5
SE table
![Page 6: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/6.jpg)
SE and its Support Frame
Wolfgang Funk - CERN CMS11/9/2002 6
![Page 7: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/7.jpg)
SE Preliminary Installation
Parking positionof SE
Wolfgang Funk - CERN CMS11/9/2002 7
Dummy EE
![Page 8: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/8.jpg)
EE+ Lowering
Wolfgang Funk - CERN CMS11/9/2002 8
Second shaft
![Page 9: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/9.jpg)
EE Final Installation
Wolfgang Funk - CERN CMS11/9/2002 9
SE in parking position
![Page 10: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/10.jpg)
SE Final Installation
Wolfgang Funk - CERN CMS11/9/2002 10
EE
SE
![Page 11: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/11.jpg)
Wolfgang Funk - CERN CMS11/9/2002 11
• Dates: Jun. 06 (12 working days) for SE+ and SE- • Mechanical installation: 1day/SE • Electrical installation and testing: ~week/SE• Manpower: point 5 Support Team, technicians, engineers and physicists from collaboration institutes (3+3) (no hired manpower needed)• Installation tools: 2 frames and 1 lifting gear <40K schematic drawings existing SE table is part of EE platform HF raisers (time to build up raisertower: 2h)
Schedule, Manpower and Cost Estimates (SE):
![Page 12: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/12.jpg)
Wolfgang Funk - CERN CMS11/9/2002 12
• Services from patch panels onwards: cabling link person cooling link person 40 patch panels /SE per patch panel: 2 LV cables, 1 HV cable, 1 DCS cable inside cooled cable trays cable trays used as well for EE services 10 fiber cables/SE, 4 cooling pipes/SE
Manpower for cabling from CMS cabling team Cabling already done in 2004/2005
Schedule, Manpower andCost Estimates (SE)(2):
![Page 13: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/13.jpg)
Wolfgang Funk - CERN CMS11/9/2002 13
• Dates: Jan. 07 (2 months) for EE+ and EE-• Mechanical, electrical installation including testing: 2 weeks/EE• ’’Flying’’ test system: (used for EB, as well) with cooling, HV, LV and fibers connected to patch panels (2/Dee)• Manpower: point 5 Support Team, technicians, engineers and physicists from collaboration institutes (3+3) (no hired manpower needed)• Installation tools: 4 Dummy Dees: ~100K (study underway) EE platform(s): (2X) 100K (drawings existing) HF raisers, Airpads are standard CMS• If Dees are late: SE stays on Dummy EE, LHC shutdown period (2 months summer 07) could be used to install EE- or both (EE+, EE-)
Schedule, Manpower and Cost Estimates (EE):
![Page 14: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/14.jpg)
Wolfgang Funk - CERN CMS11/9/2002 14
• Services from patch panels onwards: cabling link person cooling link person 4 patch panels /Dee per patch panel: 1 cooling pipe, 34 LV cables, 4 HV cables, 3 fiber cables, DCS cables inside cooled cable trays cable trays used as well for SE services
Manpower for cabling from CMS cabling team Cabling already done in 2004/2005
Schedule, Manpower andCost Estimates (EE)(2):
![Page 15: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/15.jpg)
Conclusion:
Wolfgang Funk - CERN CMS11/9/2002 15
• Costs are accounted in costbook• Installation is using only point 5 Support Team and institutional manpower (no hired manpower needed)• Contingency plan exists• Production drawings of installation tools have to be made• Start of tooling production 2003 after EDR • All tooling submitted for approval to TIS
![Page 16: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/16.jpg)
EE Platform (2)
Wolfgang Funk - CERN CMS11/9/2002 16
![Page 17: EE and SE Installation Wolfgang Funk - CERN CMS 11/9/20021 1.) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.](https://reader036.fdocuments.us/reader036/viewer/2022062518/56649ea35503460f94ba6fbd/html5/thumbnails/17.jpg)
ManpowerInstallation
Costs
EB
point 5 Support Team, technicians, engineers and
physicists from collaboration institutes (3+3) (no hired
manpower needed)
500kTransport frames and
rotation cage
EE ’’200 (300)kDummy EEs and
platform(s)
SE ’’<40k
Frames and lifting gear
Manpower and Project Costs for Installation in SX5/UX5
Costs for cables and cabling in costbook, cabling done by general cabling team
Wolfgang Funk - CERN CMS11/9/2002 17