EDUC 6145 Project Management in Education and Training
-
Upload
lisa-teschke -
Category
Documents
-
view
217 -
download
0
Transcript of EDUC 6145 Project Management in Education and Training
-
7/26/2019 EDUC 6145 Project Management in Education and Training
1/19
OUR NATION AND SOCIETY K-2
LETS GO CAMPING
SCHOOLONLINEABCSTREET
APPLETOWN,GEORGIA 12345
MAY 8,2015
-
7/26/2019 EDUC 6145 Project Management in Education and Training
2/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
OR NATIONAL AND SOCIETY
MISSION TO LETS GO CAMPING PROJECT
(The part that is missing is: the Budget to schedule the project.)
The SchoolOnline, an national initiative to develop online digital learning sources (i.e. learning objects (Ertner et al. 2014).
in specific curricular areas for primary and secondary has authorized Jackson Consulting Companys payroll group. The project plan
will be developed by the Project Steering committee. The purpose of this learning activity for k-12 learners is to identify and
understand the difference between their own needs and wants and to think abou the needs and wants of others. The project
includes Project objectives and scope, resources, project control which two teams: one proposing and researching the content for
design briefs and the other do the development work. Also, creating educational learning objects. The learning object will be
developing students understanding of values, sustainability, dimensions of well-being. And they will also have the understanding of
how people contribute to the needs and well-being of the community. Also, how we all contribute to the community in productive
and fair ways. Project Managers- Gordon Anderson, Review Panel, Writing, Design and Development Team. The Organization
Structure of the Our nation and Society Project: (Ertner et al. 2014).
Project Steering Committee:
Four people on this committee
Review Panel (Subject Matter Experts,
School Education experts)
Jeff Parker, Penny Johnston, Tracey Ward
and Scott
Project Manager:
Gordon
Writing Team:
Three People
Design Team
Four People
Development Team
Four People
Design Briefs Design Specifications Learning Objectives
-
7/26/2019 EDUC 6145 Project Management in Education and Training
3/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
The purpose will provide resources that support student to: a) develop understanding about contemporary society as a
springboard for understanding self and others and for examining the contributions needed to bring about preferred futures. b)
Investigate interconnecting social, cultural, ecological and economic systems, political and ethical issues, and alternative worldviews.
c) Develop values, understandings, skills, dispositions and behavior associated with civic decision making and with the principles of
the democratic process, sustainable futures, and social justice. The scope of the project is to design and develop high-quality online
digital content organized around one or more of the following themes: a) geographical, economic, environmental, ethical,
etiological, and political systems, and/or issues. b) The way we are now. c) What we want for the future. It should be noted that all
above be covered in the total body of content developed in the project, but that not all elements need to be present in each
individual learning object. Requirements for technology purpose used simple animations, text and audio. All of the learning objects
will be needed to be develops in Flash for a particular set of end-user specifications. It is also critical to have the interface design
considerations which are clean interface, large drag and drop areas, large font texts, audio instructions and colorful, fun graphics
(Ertner et al. 2014).
-
7/26/2019 EDUC 6145 Project Management in Education and Training
4/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Initial Flowchart for Lets go Camping
Home exterior:
(audio & interpreterinstructions)
Bedroom
(selects items for bag)
Kitchen
(select items for bag)
Shed
(select items for bag)
Packing bag
(items added to bag)
Lets go camping
(Click button when choices are
made)
Set up camp
(Animation)
Play camp Scene
(Animation of implications of choices over
hours/nights/days.)
Change Items
-
7/26/2019 EDUC 6145 Project Management in Education and Training
5/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
The Project Manager, Gordon is hereby authorized to interface with management as required, negotiate for resources,
delegate responsibilities within the framework of the project, and to communicate with all organizations and management, as
required, to ensure successful and timely completion of the project. All specs and specifications for the designs go through Gordon.
The Project Manager is responsible for developing the project plan, monitoring the schedule, cost, and scope of the project during
implementation, and maintaining control over the project by measuring performance and taking corrective action.(Ertner et al.
2014).
(FYI: this was another part that was missing from their project)
The project plan will be submitted and approved in accordance with the milestone schedule below. Upon approval of the
project plan resources will be assigned to the project and work will commence within 5 business days. Gordon, the Project Sponsor
must approve any schedule changes which may impact milestones. A detailed schedule will be included in the project plan. The high
level milestone schedule is:
July 1, 2015Project Plan Complete and Approved by Project Steering Committee and (SME) Review Panel
July 15, 215Payroll Design Completed based on the Writing/Design and Development Team all gets One month each to work ontheir assignments. Once a week all three teams will meet up attend the Workshop for the week, which will be held on Fridays.
Oct 21, 2015Revise and final closing of the project before trial
Oct 22-Oct 2, 2015Testing Completed by students from grade k-2
Oct 5Oct 9, 2015Beta Testing Completed
Oct 12- Oct 16, 2015Implementation Completed
Oct 23, 2015One, Payroll Cycle Complete and Project Completion
The budget for the Payroll project is $441,840. It is to be funded through the FY2015 SchoolONline Technology Budget.
20 Staff: Paid 28.00 per hour/work 8 hours a day for 83 days = $371,840
Technology materials: 70,000
-
7/26/2019 EDUC 6145 Project Management in Education and Training
6/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
SCHOOLONLINE ACCEPTANCE
Approved by the Project Sponsor:
__________________________________________ Date: ___________________
Johnny Appleseed
SchoolOnline Project Manager
-
7/26/2019 EDUC 6145 Project Management in Education and Training
7/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Resources:
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning,
scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.
Statement of project scope, including a summary of what will and will not be included in the scope of this project:
The particular approach they will be taken is pedagogical approach to maintain on the project mission. The preferred
pedagogies are provide multiple representations of reality and the complexity of the real world. Present authentic tasks that encourage
conceptualization. It was determine that the learning objectives should be pretty flexible where it allows the student or small group
could use it without direct instruction from the teacher. The main key, for keeping learning object small which would give them the
limited of choices. Due to the timeline where SchoolONline will establish the design work which will take three months to maintain
everyone on the same page. Workshop sessions will bring the writers and the development every two weeks to clarify expectations
between the team members. This will be run by Gordon who is the PM as well, since everything must go through Gordon anyways.
The scope of the project is to design and develop high -quality online digital content organized around on or more of the following
themes: a) geographical, economic environmental, ethical, etiological, and political systems, and/or issues. b) The way we are now. c)
What we want for the future. It should be note that all above be covered in the total body of content developed in the project but that
not all elements need to be present in each individuals learning object. Requirements for technology purpose used simple animations,
text and audio. All of the learning objects will be need to be develops in Flash for a particular set of end-user specifications. (Ertner
et al. 2014).
Project Purpose (revised from SOW)
Theres been a few slight changes from the SOW, which is the title is to be changes from Mission to Mars to Lets Go Camping. Due
to the fact it has the impact of identifying the needs for survival and the things we want that occur within a reality situation. The
budget had to change due to an oversight, allowing the writers to write the program in three month period, plus adding
Project Objectives (revised from SOW)
-
7/26/2019 EDUC 6145 Project Management in Education and Training
8/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
The purpose will provide resources that support student to: a) develop understanding about contemporary society as a springboard for understanding self
and others and for examining the contributions needed to bring about preferred futures. b) Investigate interconnecting social, cultural,
ecological and economic systems, political and ethical issues, and alternative worldviews. c) Develop values, understandings, skills, dispositions and behaviorassociated with civic decision making and with principles of the democratic process, sustainable futures, and social justice.(Ertner et al. 2014).
Assumptions (revised from SOW)
Stakeholder list and descriptions (For each key stakeholder or stakeholder group, briefly explain their role in the project, and whyand when they should be included or consulted during the project.) (Ertner et al. 2014).
Project Steering committee/review PanelScott Allen, Penny Johnson, Jeff Parker, Tracey Ward
Setting policies and procedures for addressing resources priorities and conflicts
Creating and maintaining labor and financial information systems Providing facilities and equipment to support the performance of project work. Defining the limits of managers decision-making authority. Writing team completes 32 drafts, narrow down to the top two per person
Project manager: Gordon
Describe objectives, schedule and resource budgets. Ensuring a clear, feasible project plan for how everyone will reach performance target. Review all sign off coming and going according to plan. If any drastic changes Creating and sustaining a focused and committed team. Selecting or creating a teams operating practices and procedures.
Managing the accomplishment of objectives, within the tiem and budget targets. Monitoring performance against plans and dealing any problems that arise Controlling project changes. Report on project activities Keeping clients informed and committed Contributing to team members performance appraisals
Writing Team: SchoolONline(Time frame-One Month)Prepare (Design briefs)
32 draft briefs to determine with the ideas the Review Panel to determine the develop further. After revision and determine which draft will beused continue to prepare with the contents.
-
7/26/2019 EDUC 6145 Project Management in Education and Training
9/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Design Team: SchoolONline(Time frame-One Month)Designs specifications- learning objectives used simple animation, text and audio.FYI: SchoolsONline: Avoid using full-color graphics and video due to increase of file size
All learning objectives will be needed to be developed in Flash for particular set of end=user specifications
Development Team: SchoolONline(Time frame-One Month)Learning Objectives: initial flowchart for Lets Go Camping
Home exterior
(audio instructions)
Kitchen(Select items for bag)
Bedroom(Select items for bag)
Shed(Select items for bag)
Packing bag
(items added to bag)
Lets go Camping
(click button when choices are made)
Set up Camp
(animation)
Play camp scene
(Animation of implications of choices over hours/nights and days)
Change items
-
7/26/2019 EDUC 6145 Project Management in Education and Training
10/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Additionally, include a brief rationale statement in which you identify the case study on which your project is based, and a summaryof any assumptions you made or information you filled in for the case study to complete this document.
The case study the project is based on is Designing Learning Objects for Primary Learners. There was a lot of revision that had to be done
due to the project is for primary learners. At the same time we had to keep the file small based on the objectives and SchoolsONline did notwant to use full color graphic video due to it will increase the file size. So there were some limitations of what the team wanted to use. Also
since the Writing, and Development Team had the project for three months we want to keep the remainder of the team involved so we could
all maintain on the same page. So throughout this time there will be workshop sessions, to prevent any issues that may arise and preventing
from starting back to square one. This allows the communication among the team where everyone could be involved and revise as we go
establishing the program.
Resources:
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning,
scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.
-
7/26/2019 EDUC 6145 Project Management in Education and Training
11/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Effort/Duration
Table:
Phase, Activity,
Or Task:
Resource: 4
people
Project Steering
Committee
Effort
Resource:
4 people
Review
Panel Team
Effort:
Resources:
1 people
Project
Manager
Effort:
Resource: 3 people
Proposing/Research
/Writing Team-
Design Briefs
Effort
Resource:
4 people
Design Team-
Design
SpecificationsEffort:
Resources:
4 people
Development
Team- (Scarlet
Media)Learning
Objectives
Effort:
Resource:
Client
Reviewer:
Student
Trail
Duration:
Determine
specific
Objectives for
software
4 hours =16
hours
4 hours=16
hours
2 hours 4 hours=16
hours
50 hours
Create Briefs 4 hours=16
hours
4 hours 64 hours (8 days/ 8
hours)=192 hours
212
hours
Discusscontent for
briefs
32 hours (8hours/ 4
days)=128 hours
4 hours=16hours
2 hours 146hours
Determine
Specs for
technology
16 hours(8
hours/2
days)=64 hours
4 hours (2
hours/2
days)
16 hours(8
hours/2
days)=64
hours
132
hours
Develop full
design
48 hours ( 8
hours/6
days)
480 hours (8
hours/60
days)=1920
hours
1968
hours
Workshop with
the
Development
Team
120 hours (2
hours/60
days)=480
hours
60 hours(1
hour/60
days)
120 hours (2
hours/60 days)=360
hours
900
hours
Final Trial of
the
Software/DVD
1 hour (with
ten
students)
1 hour
Total: 208 hours 528 hours 120 hours 552 hours 64 hours 1936 hours 1 hour 3409
hours
-
7/26/2019 EDUC 6145 Project Management in Education and Training
12/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Project Schedule: September October November December
Determine Specific
Objectives for
Software
Create Briefs
Discuss content
for Briefs
Determine Specs
for Technology
Develop full
Design
Workshop with
the DevelopmentTeam
Final Trail for
DVD/Software
-
7/26/2019 EDUC 6145 Project Management in Education and Training
13/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Cost Estimation WorksheetActivity Duration Project (4)
people
SteeringCommittee
57.00/hour
Review
Panel
(4 People)44.00/hour
Project
Manager
(1 person)45.00/hour
Writing
Team
(3 people)50.00/hour
Design
Team
(4 people)100.00/hour
Development
Team:
(4 people)Scarlet
media:
60.00/hour
Client
Reviewer:
(5students)
Free DVD
Misc.
Cost
Total
Cost
Determine
specific
objectives for
software
50 hours 16 hour=
612.00
16 hour=
704.00
2 hours =
90.00
16 hours=
960.00
194,308
Create Briefs 212
hours
16 hours=
704.00
4 hours =
180.00
64 hours=
3200.00
4084.00
DiscussContent for
briefs
146hours
128 hours=7296.00
16 hours=704.00
2 hours=90.00
8090.00
Determine
specs for
technology
132
hours
64.00
hours=
3648.00
4 hours=
180.00
64 hours
6400.00
10228.00
Develop full
design
768
hours
48 hours=
2160.00
1620 hours=
97,200.00
99,360.00
Workshop
with the
developmentteam
1350
hours
480 hours=
27,360.00
480 hours=
21,120.00
60 hours=
2700
360 hours=
18,000.00
69,180.00
Final Trial of
the
software/DVD
1 hour 0 0
Technology
Licenses
1 item 1000.00 1000.00
Total: 2659
hours
38,916.00 23,232.00 5400.00 21,200.00 6400.00 98,160.00 0.00 1000.00 194,308
-
7/26/2019 EDUC 6145 Project Management in Education and Training
14/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Responsibility/AccountabilityPhase Person Jeff Penny Tracey Gordon SchoolsONline Scarlet Media
Determine specific Objectives forThe software
AP IP IP ISP p p
Create Briefs I I I ISP A
Discuss content for Briefs IP IP IP IS A
Determine specs for
Technology materials
IA I I ISP I I
Develop full Design ISP AP
Workshop with the Development
Team
ARP RP RP SPR RP RP
Final Trail of the DVD/Software R AR AR SPR R R
P= Participate A= Accountable R = Review I=Input Required S=Sign-Off Required
-
7/26/2019 EDUC 6145 Project Management in Education and Training
15/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Project Communication PlannerWho
(Receiver)
What Information When
(How Often)
How
(form/Medium)
Who Creates & Publishes
Project Steering Committee
Review Panel Team
Project Manager
Development Team
Determine specific
Objectives for
The software
4 hours /2 days Form Project Steering
committee
Review Panel Team
Project Manager
Proposing/Research/Writing
Team
Create Briefs 8 hours/8 days Form/Medium Review Panel Team
Project Steering Committee
Review Panel Team
Project Manager
Discuss content for Briefs 8 hours/4 days Form/Medium Review Panel Team
Project Steering TeamProject Manager
Design Team
Determine specs forTechnology materials
8 hours/2 days Form Design Team
Project Manager
Development Team
Develop full Design 8 hours/ 6 days Form/Medium Development Team
Review Panel Team
Project Manager
Proposing/Research/Writing
Team
Workshop with the
Development
Team
2 hours/ 60 days Medium Review Panel Team
Project Steering TeamReview Panel Team
Client Reviewer Students
Trail
Final Trail of theDVD/Software
One day- 1 hour Form/Medium Review Panel Team
-
7/26/2019 EDUC 6145 Project Management in Education and Training
16/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Worksheet: Sign-Off Form (Project Phase)
I have reviewed the following deliverables as of the date identify below. The objectives and briefs specific for the software and age appropriate students Based on the spec for the full design was successful The workshop was a success.
I have found these deliverables to meet with my approval, with the following exceptions:
In order to determine the specs for the technology, so revision in order to meet the objectives and briefs. The workshop was a success except a few minors that needs to be address, with the team participating during this session
needs to mandated to prevent future delay within the process.
I hereby give my approval to proceed with the evolution of these deliverables to the next state of development in order to meet the
project objectives in a timely fashion.
I understand that any changes (additions, deletions, or modifications) to the fundamental structure, underlying design, or the specificfeatures of these deliverables might result in
Of the completion date for these deliverables Additional resource requirements Addititioanl costs
______Gordon Anderson_________________________________ (Signature) Date:___May 20, 2015_______________Gordon Anderson, PM
-
7/26/2019 EDUC 6145 Project Management in Education and Training
17/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Worksheet: Project Sign-Off (Entire Project)
Project Name: Lets Go Camping Upgrade
I have reviewed the following finished deliverables as of the date identify below: Specific objectives align with the briefs Tehcnology Specs with full design development
I have found these finished deliverables to meet with my approval, with the following exceptions: During the final Trial the project steering committee and review committee are to give their input based on their observations.
For each of the divlerables that are named above as exceptions, we will proceed as follows with the following remedies within
the time frames specified:
During the final trial allow the two committees at least one hour to determine their inputs.
__Gordon Anderson_____________ (Signature) Date: ___June 20, 2015_______Gordon Anderson, PM
-
7/26/2019 EDUC 6145 Project Management in Education and Training
18/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com
Resources:Greer, M. (2010). The Project management Minimalist: Just Enough PM to Rock Your Projects![E-book]. Retrieved from:https://class.waldenu.edu/webapps/blackboard/content/listContent.jsp?course_id=_8624934_1&content_id=_25624458_1
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008).Project management: Planning,scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.
Time,F (n/a). Chron-How much does a Project Manager make Hourly. Retrieved from http://work.chron.com/much-project-manager-make-hourly-7628.html
https://class.waldenu.edu/webapps/blackboard/content/listContent.jsp?course_id=_8624934_1&content_id=_25624458_1https://class.waldenu.edu/webapps/blackboard/content/listContent.jsp?course_id=_8624934_1&content_id=_25624458_1https://class.waldenu.edu/webapps/blackboard/content/listContent.jsp?course_id=_8624934_1&content_id=_25624458_1 -
7/26/2019 EDUC 6145 Project Management in Education and Training
19/19
Our National and Society
Lets go Camping SchoolONlinehttp://SchoolONline.com