EDM Fast Start PresentationWBS 11 – Assembly and Commissioning
Vince Cianciolo, Paul HuffmanMay 23, 2006
![Page 2: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/2.jpg)
EDM Fast Start, WBS11 2
Schedule Overview
• Fully tested B-shield
• Fully tested CV/liquifier and coil pkg.
• Fully tested insert• Fully tested 3He system
• Assemble/commission B shield
• Assemble/commission coil package into CV
• Assemble/commission insert in CV
• Assemble/commission 3He system in CV
• Re-install B shield upper half • Mate neutronics • Commissioning run• CD4/data collection :-)
![Page 3: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/3.jpg)
EDM Fast Start, WBS11 3
Significant Planning Assumptions • Internal cryostat components arrive fully tested at cryostat assembly site
– Measurement cell insert– 3He injection and purification system– Coil package– All related DAQ components
• This is hugely important. The full apparatus will require 6-8 weeks for a cooldown cycle and this dominates cost and schedule. As much as possible testing must be done prior to assembly, in parallel and in smaller cryogenic vessels.
• Require ability to test 3He transport w/o external shield– Otherwise grossly inflates cooldown/warmup cycle time, and mandates lots of
handling for delicate shield pieces.• M&S costs included in estimates for various subsystems (not in this WBS)
– Rails and other infrastructure equipment– Helium– Tools
• NCSU is the cryostat assembly site– Cost totally dominated by technician support (nearly 4 FTE years)
• >$300k labor savings if done at NCSU• Balances against shipping, disassembly, re-assembly, extra infrastructure
– Assembly requires continuous presence and expertise of the cryostat team for ~ 2 years• Probably significantly longer if apparatus and team not geographically close
![Page 4: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/4.jpg)
EDM Fast Start, WBS11 4
Gantt ChartDuration – 38 months
Test coil pkg in CV (NCSU)
Test insert in CV (NCSU)
Test 3He system in CV (NCSU)
B-shield installation (FNPB)
Test entire apparatus at FNPB
Schedule dominated by repeated cooldown/testing cycles
![Page 5: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/5.jpg)
EDM Fast Start, WBS11 5
Milestones
Subsystem inputs
Assembly and commissioning deliverables
![Page 6: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/6.jpg)
EDM Fast Start, WBS11 6
Critical Path
• Cryostat vessel• Whichever subsystem will be the first to
install– Seemingly the coil package
• Not the B-shield, which is only needed more than two years after the start of coil package assembly into the cryostat.
![Page 7: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/7.jpg)
EDM Fast Start, WBS11 7
Schedule Risks/Uncertainties
• Cost and schedule is totally dominated by the number of cooldown cycles required for successful commissioning:– 3 for coil package– 4 for insert– 3 for 3He components– 3 for integrated tests– 2 for commissioning run w/ beam, B-shield
• These estimates (sorry!) really are WAGs because it is impossible to know how long it is going to take to diagnose a problem.
![Page 8: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/8.jpg)
EDM Fast Start, WBS11 8
Areas of Interface - Everything
• DAQ• Neutronics and Shielding• Cryostat• Insert• 3He Components• Coil package and shielding• Infrastructure
![Page 9: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/9.jpg)
EDM Fast Start, WBS11 9
Technical (Scope) Issues• Is your scope well defined (yes/no)? Is it
documented? Yes and no.– We have carefully constructed this WBS so that
it only involves assembly and commissioning of fully-tested parts.
• Important that this is understood and agreed to by other subsystems.
– Also, our model currently assumes that external subsystem labor is free or costed by the corresponding subsystem.
• If this is not correct it needs to be fixed.
![Page 10: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/10.jpg)
EDM Fast Start, WBS11 10
Cost Estimates• Work package spreadsheets not complete.• Cost estimate is entirely labor.• Dominated by NCSU and ORNL technician
time:– ORNL – ~2 FTE-years = $400k– NCSU - ~4 FTE-years = $450k– Shipping - $36k
• Pre-contingency estimates.• These estimates (sorry!) really are WAGs
because it is impossible to know how long it is going to take to diagnose a problem.
![Page 11: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/11.jpg)
EDM Fast Start, WBS11 11
Staffing Plans• NCSU (from D. Haase talk)
– People - 5 NC State physics faculty, TUNL technical support (Engineers and electronics techs)
– Key skills - cryogenics design, implementation and testing– Recruitments - need 1 postdoc and 2 cryo technicians– Issue - funding for recruitments
• ORNL– Technicians w/ cryogenic expertise needed– Issue: not currently on staff– Issue: Need to come to grips with operational model for
the experiment, i.e., will ORNL assume general responsibility w/ relatively little involvement by collaborating scientists (“J-Lab model”) or will there be substantial, on-site presence of collaborating scientists (“RHIC model”).
![Page 12: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/12.jpg)
EDM Fast Start, WBS11 12
Procurement Planning• We have structured this WBS element so
that there are no material purchases.
![Page 13: EDM Fast Start Presentation WBS 11 – Assembly and Commissioning](https://reader035.fdocuments.us/reader035/viewer/2022062721/56813727550346895d9eb3aa/html5/thumbnails/13.jpg)
EDM Fast Start, WBS11 13
Issues
• The “62% Rule” is not always applicable:– Hourly rate for NCSU technicians assumes 52*40
hours/year (unlike ORNL, and presumably LANL) in which vacation time is built into overhead.
• To correctly cost things they should be entered as 71.4% or their hourly rate should be upped.
– Another example is an intermittent resource, like a couple of electricians who work for a couple of weeks on the project.
• ORNL, NCSU technician/engineer burdened rates in the spreadsheets are not correct.
• I started this WBS in a fresh file. I didn’t realize it was using a 5-day calendar (apparently now the MSP default). So fractions are not currently consistent with 62% rule.