Economics and Engineering in a New Partnership:...

83
Economics and Engineering in a New Partnership: Cost of Service Larry Vogt Director, Rates Mississippi Power Wisconsin Public Utility Institute June 28, 2017 1

Transcript of Economics and Engineering in a New Partnership:...

Economics and Engineering in a New Partnership: Cost of Service

Larry VogtDirector, Rates

Mississippi Power

Wisconsin Public Utility Institute

June 28, 2017

1

The Cost-of-Service Study

A cost-of-service study is a model of utility accounting and financial data which relies on various engineering and economics inputs and concepts to appropriately assign detailed cost elements to the customer groups using the principle of cost causation.

2

Power System Functional Levels

GENERATION ANDSTEP-UP SUBSTATION

TRANSMISSION SUBTRANSMISSION

PRIMARY DISTRIBUTION

DISTRIBUTIONSUBSTATION

TRANSMISSIONSUBSTATION

LINE TRANSFORMERSECONDARY DISTRIBUTIONSERVICE LINE

3

Annual Energy Losses Throughout the T&D System

System Losses:  6.2% < 600 V

12.47 kV

46 kV

115 kV

230 kV

4,662 GWh

1,767 GWh

4,317 GWh

1,824 GWh

533 GWh

538 GWh

0.9%3.2%8.0%

M

M

M

7,024 GWh GENERATION

STEP-UP SUBSTATIONS

EHV TRANSMISSION LINES

TRANSMISSION SUBSTATIONS

HV TRANSMISSION LINES

SUBTRANSMISSION SUBSTATIONS

SUBTRANSMISSION LINES

DISTRIBUTION SUBSTATIONS

PRIMARY LINES

LINE TRANSFORMERS

SECONDARY LINES

SERVICES

4

Cost-of-Service StudyMajor Data Requirements

Accounting and Finance Data

• Investment Items

• O&M Expenses

• Income Taxes

• Revenues

• Cost of Capital

Engineering and Technical Data

• System Load

• T&D System Losses

• Class Load Shapes

• Class Characteristics

• T&D Construction Specs

5

SPECIFICASSIGNMENT

COST-OF-SERVICE STUDY

INVESTMENTDATA

FUNCTIONALIZATIONLEVELIZATION

CLASSIFICATION

CUSTOMERDATA

SYSTEMDATA

DEMANDALLOCATION

CUSTOMERALLOCATION

ENERGYALLOCATION

RES COM IND LGT OTH

EXPENSEDATA

REVENUES INCOMETAXES

6

Cost-of-Service StudyLevel of Detail

Total Company

Wholesale Electric Retail Electric Other Departments

Residential Commercial Industrial Lighting

R R-TOU Sm GS Med GS Lrg GS HLF SL OL

JURISDICTION

CUSTOMER CLASS

RATE CLASS

7

Much about cost of service has changed over the last 40 years!• Computation Capability

Tools Data

• Information Technologies Metering T&D System Mapping

• Legislation and Regulations Filing Requirements Reporting

• Classification and Allocation Methodologies Embedded Cost Approach Marginal Cost Approach

8

Cost-of-Service Study Tools

1971 Cost-of-Service Study

9

Cost-of-Service StudyKey Processes

Functionalization (and Levelization)» Alignment of costs by major system function and voltage level:  Production, Transmission, Distribution, and Customer Services 

Classification» Alignment of functionalized costs by cost‐causation components:  Customer, Demand, and Energy 

Allocation» Assignment of costs to jurisdiction, customer classes, or rate classes

10

COST OF SERVICE:FUNCTIONALIZATION

11

Cost Functionalization

Functionalization is the process of arranging all of the utility's cost elements by the major operational sectors of the utility system:

1. Production2. Transmission3. Distribution4. Customer Accounts5. Customer Assistance (Customer Service and

Informational Expenses)6. Sales

12

FERC Uniform System of AccountsRate Base and Expense Items

100 – 199 Assets and Other Debits – Plant Held for Future Use, CWIP, Accumulated Depreciation, Fuel Stocks, Plant Materials and Supplies, Prepayments, 190 -Accumulated Deferred Income Taxes (ADIT)

200 – 299 Liabilities and Other Credits – Operating Reserves, Customer Deposits and Advances for Construction, Investment Tax Credits (ITC), 281, 282 & 283 -ADIT

300 – 399 Intangible, Production, Transmission, Distribution, and General Plant

400 – 459 Income, Retained Earnings, and Operating Revenues – Depreciation Expense, Taxes Other Than Income Taxes, Sales for Resale

500 – 599 Power Production, Transmission, and Distribution O&M Expenses

900 – 949 Customer Accounts, Customer Service and Informational, and Sales O&M, and A&G Expenses

13

New FERC Accounts

In the 2003 to 2005 timeframe, the FERC Uniform System of Accounts was modified by the addition of 56 accounts mostly associated with:

• Asset Retirement Obligations [FASB statement SFAS 143; FERC Order No. 631 - 2003] and

• Regional Transmission and Market Operations [FERC Order No. 668 - 2005]

14

Cost Levelization

Levelization is an aspect of functionalization which recognizes voltage levels:

Transmission: Backbone Transmission (115 kV+)Subtransmission (34.5 kV – 69 kV)

Distribution: Primary (4.16 kV – 23 kV)Secondary (< 600 volts)

15

5

4

3

2

1

Cost-of-Service Levelsof The Power System

5A

5B

< 600 V

12.47 kV

46 kV

115 kV

230 kV

16

Functionalization ofMajor Gross Plant

Production Transmission Distribution

System Level: 1 2 3 4 5FERC Accts (Sub) (Pri) (Sec)310 – 316 Steam Production X320 – 325 Nuclear Production X330 – 336 Hydraulic Production X340 – 346 Other Production X350 – 353 Transmission Subs X X X354 – 359 Transmission Lines X360 – 363 Distribution Subs (Inc. Land) X X364 Poles, Towers & Fixtures X X365 OH Conductors/Devices X X366 UG Conduit X X367 UG Conductors/Devices X X368 Line Transformers X X369 – 370 Services and Meters X371 – 373 Cust. Inst. and St. Lgt. X

GSUs -“Splits”-

17

GSU Transformer

18

115 kV to 12.47 kV Substation

19

115 kV to 46 kV & 12.47 kV Sub

20

Distribution Substation Capacitor Array

21

Single Pole with Multiple Voltage Classes

TRANSMISSION

PRIMARY DISTRIBUTION

SECONDARY DISTRIBUTION

22

Functionalization of Distribution System Devices

360 Land and Land Rights361 Structures362 Station Equipment363 Storage Battery Equipment364 Poles, Towers & Fixtures365 OH Conductors & Devices

Switches Reclosers & Sectionalizers

366 UG Conduit367 UG Conductors & Devices368 Line Transformers

Regulators Capacitors Cutouts Arresters

369 Services370 Meters373 Street Lighting

SUBS

R

N.O.

N.C.

N.C.N.C.

1,500 cKVAR

333-333-33350-50-50

75

15

25 37.5

336.4 MCM AL

4/0

CU

NO. 2 ALC/N

1/0 CU

23

AM/FM Mapping Systems

24

Functionalized Rate Base Summary

Note: $ in Millions Prod Tran Dist Accts Asst Sales

Total Net Plant In Service $617.6 $57.6 $194.9 $2.1 $0.3 $0.1Plant Held For Future Use 1.0CWIP 496.9 32.2 10.1Rate Base Additions:• Fuel Stock 14.3• M&S (Inc. Reactant Stock) 29.5 3.0 6.5 0.1• Prepayments 0.4 0.1 0.1• Cash Working Capital 21.8 1.5 8.3 2.0 0.3 0.1Rate Base Deductions:• Operating Reserves (N/A)• Customer Deposits/Advances 0.1 1.4 0.1• Net ADITs & ITCs 134.8 14.4 44.7 0.4Total Rate Base: $1,304.9 $1,045.7 $79.9 $174.8 $3.7 $0.6 $0.2

25

Functionalized Expenses Summary

Note: $ in Millions Prod Tran Dist Accts Asst Sales

Labor and Associated Expenses:• Operations $37.9 $3.8 $18.9 $6.5 $1.0 $0.4• Maintenance 32.9 1.5 13.4 0.1• A&G 26.6 2.1 9.8 2.6 0.4 0.1Power Expenses:• Fuel 131.5• Purchased Power 7.0• Nonterritorial Sales 30.9

Depreciation Expenses 33.1 4.0 10.9 0.2

Taxes Other Than Income Taxes 3.3 0.6 1.3 5.4

Total Expenses: $324.5 $241.4 $12.0 $54.3 $14.8 $1.4 $0.526

COST OF SERVICE:CLASSIFICATION

27

Cost Classification

Classification assigns the functionalized cost elements to the cost causation components of Customer, Demand, and Energy.

» Customer-related costs – fixed costs which are independent of load or energy requirements.

» Demand-related costs – fixed costs which are dependent on kW requirements.

» Energy-related costs – variable costs which are dependent on kWh requirements.

28

5

4

3

2

1

Cost-of-Service Levelsof The Power System

5A

5B

< 600 V

12.47 kV

46 kV

115 kV

230 kV

ENERGYDEMAND

DEMAND

DEMAND

DEMANDCUSTOMER

DEMANDCUSTOMER

29

Classification of Production Plant

In general, production plant is considered to be a demand-related cost component since plant is built to provide capacity to meet peak loading conditions.

However, some cost allocation methods treat a portion of production plant costs as being energy related on the basis that energy requirements are a determinant of production plant. Subsequently that portion of cost is allocated on the basis of average demand or energy.

30

Classification of Production Expenses

Steam Production O&M FERC Method NARUC MethodOperation Demand Energy Demand Energy500 Supervision and Engineering All -- Labor* Labor*

501 Fuel and Fuel Handling -- All -- All

502 Steam Expenses All -- Labor Materials

503 Steam From Other Sources -- All -- All

504 Steam Transferred - Credit -- All -- All

505 Electric Expenses All -- Labor Materials

506 Miscellaneous Steam Expenses All -- All --

507 Rents All -- All --

509 Allowances -- All -- All

Maintenance

510 Supervision and Engineering -- All Labor* Labor*

511 Structures All -- All --

512 Boilers -- All -- All

513 Electric Plant -- All -- All

514 Miscellaneous Steam Plant All -- -- All

* Allocation between Energy and Demand based on labor subtotal of underlying accounts. 31

Classification of Transmission Plant and O&M Expenses

In general transmission plant and its associated O&M expenses are considered to be demand-related costs.

32

Classification of Distribution Plant

Demand Customer

Distribution Substations X

Primary Lines* X X

Line Transformers* X X

Secondary Lines* X X

Other Line Equipment X X

Service Lines X

Meters X

* Minimum Distribution System facilities.

33

COST OF SERVICE:ALLOCATION

34

Cost Allocation

Allocation is the process whereby the customer, demand, and energy cost components, developed in the classification of costs step, are apportioned to customer groups: rate classes, customer classes, and/or jurisdictions.

Direct assignment of costs are made when possible, e.g., ornamental poles and fixtures assigned directly to the lighting class.

35

Major Cost Allocators

Energy Cost Allocator – Developed on the basis of customers’ kWh energy usage.

Demand Cost Allocator – Developed on the basis of customers’ kW loads.

Customer Cost Allocator – Developed on the basis of numbers of customers.

36

Allocation Factors

An allocator is a series of ratios which sum to 100% of total. For example, the production level energy allocator is based on the kWh output of the generators.

Res Com Ind TotalAllocation Factor:GWh at Level 1 4,662 1,824 538 7,024

0.6637 0.2597 0.0766 1.0

37

Expansion of Energy Sales at Meters to the Production Level

< 600 V

12.47 kV

46 kV

115 kV

230 kV

4,662 GWh

1,767 GWh

4,317 GWh

1,824 GWh

533 GWh

538 GWh

0.9%3.2%8.0%

System Losses: 6.2%

M

M

M

7,024 GWh

38

Expansion of Peak Demands at Meters to the Production Level

< 600 V

12.47 kV

46 kV

115 kV

230 kV

1,199 MW

253 MW

1,085 MW

264 MW

53 MW

54 MW

1.9%4.3%10.5%

System Losses: 9.1%

M

M

M

1,517 MW

39

8,760 Hourly System Loads

40

Peak Day System Load Shape

-

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Res Sm Com Lg Com Sm Ind Lg Ind 41

Demand Allocation in the1960s and 1970s

The literature of the time focused on three main methods of demand cost allocation:• Peak Responsibility• Noncoincident Peak• Average and Excess Demand (AKA Greene’s formula)

42

Comparison of Allocators1-CP / NCP / A&E / Energy

22%

24%

26%

28%

30%

32%

34%

36%

38%

RES GS LP

1‐CPNCPA&EEnergy

4346% 53% 73%

24%

26%

28%

30%

32%

34%

36%

38%

40%

RES GS LP

1‐CP3‐CP4‐CP12‐CP

Comparison of Allocators1-CP / 3-CP / 4-CP / 12-CP

4446% 53% 73%

Coincidence of Load

45

Demand Allocation Approach Considering Coincidence of Load

-

5 0

1 0 0

1 5 0

2 0 0

2 5 0

-

2 0 0

4 0 0

6 0 0

8 0 0

1 , 0 0 0

1 , 2 0 0

1 , 4 0 0

1 , 6 0 0

1 , 8 0 0

0

5

1 0

1 5

2 0

2 5

3 0

3 5

4 0k W

M W

M WS Y S T E M

C O M M E R C I A L C L A S S

C O M M E R C I A L C U S T O M E R

S Y S T E MP E A K

C L A S S P E A KN C P

C U S T O M E RP E A K

C L A S SC P

46

FERC Methods for Production and Transmission Allocation

FERC believes that the majority of utilities plan their systems to meet their 12 monthly peaks.

FERC precedent is to use a 12-CP demand allocation method when the system demand shape is relatively flat.

FERC allows utilities to file other allocation methods if they can demonstrate that these alternatives reflect their system planning.

47

System Peak Demands

48

FERC Demand Test Measurements

MAX

12-CP

4-CP3-CP

MIN

3 OFF PK 3 OFF PK4 OFF PK 4 OFF PK

MW

49

FERC Demand Test 1

On Peak—Off Peak Test: Compare (a) the average of the monthly system peaks during the on-peak period (e.g., 3-CP or 4-CP) as a percentage of the annual system peak (MAX) to (b) the average of the monthly system peaks during the off-peak period (e.g., 3 OFF PK or 4 OFF PK) as a percentage of the annual system peak.

• A smaller difference (≤ 19%) supports a 12-CP method.

• A larger difference supports some method other than 12-CP.

50

FERC Demand Test 2

Low Peak—High Peak Test: Compute the ratio of the lowest monthly peak (MIN) to the highest monthly peak (MAX) during the annual test period.

• A higher percentage (≥ 66%) supports a 12-CP method.

• A smaller percentage supports some method other than 12-CP.

51

FERC Demand Test 3

Average Peak—High Peak Test: Compute the ratio of the average monthly peaks (12-CP) to the highest monthly peak (MAX) during the annual test period.

• A higher percentage (≥ 81%) supports a 12-CP method.

• A smaller percentage supports some method other than 12-CP.

52

FERC Demand Test 4

Off Peak > On Peak Test: Determine if any monthly off-peak demands exceed any of the on-peak demands during the annual test period.

• A “YES” supports a 12-CP method.• A “NO” supports some method other than

12-CP.

Several years need to be evaluated to determine if such an occurrence could be expected to occur on a frequent basis.

53

FERC Demand Test Results

Test 13-CP: Δ% = 12.3%4-CP: Δ% = 12.0%Test 2MIN/MAX = 75%Test 312-CP/MAX = 87.2%Test 43-CP: YES4-CP: YES

MW

54

Demand Test Results12 Year Averages

Test 13-CP: Δ% = 15.3%4-CP: Δ% = 14.4%Test 2MIN/MAX = 68.6%Test 312-CP/MAX = 85.6%Test 43-CP: 3 YES; 7 NO4-CP: 7 YES; 3 NO

MW

55

Electric Utility Rate Design Study

• A nationwide effort by EPRI, EEI, APPA, and NRECA for NARUC to study and advance ratemaking in costing, rate design, metering, and other relevant topics.

• Reports were published during the period of 1977 to 1981.

56

Public Utility Regulatory Policy Act PURPA – 1978 COSS Standards

SEC 111 (d)(1) Cost of Service.—Rates charged by any electric utility forproviding electric service to each class of electric consumers shall bedesigned, to the maximum extent practicable, to reflect the costs of electricservice to such class, as determined under section 115 (a).SEC. 115 (a) Cost of Service. . . . methods shall to the maximum extentpracticable—

(1) permit identification of differences in cost-incurrence, for each such class ofelectric consumers, attributable to daily and seasonal time of use of service and(2) permit identification of differences in cost-incurrence attributable todifferences in customer, demand, and energy components of costs. . . .methods . . . shall take into account the extent to which total costs to an electricutility are likely to change if—

(A) additional capacity is added to meet peak demand relative to basedemand; and(B) additional kilowatt-hours of electric energy are delivered to electricconsumers.

57

Marginal Energy Cost

• Marginal Energy Cost Approaches• Production dispatch model• Historic incremental heat rates applied to a

projected period

• Time-differentiated costs – seasonal and daily rating periods

58

Marginal Capacity Cost

• Reliability Indicators• Generation reserve margins• Loss of load probability

• Marginal Capacity Cost Approaches• Long-run cost view: Peaker Deferral – typically

based on a CT peaker• Short-run cost view: Resource Expansion Plan –

base plan vs. incremental/decremental load forecast plan

• Time-differentiated costs – seasonal and daily rating periods

59

Generation Fleet – BIP Functions

60

B-I-P ProductionAllocation Method

61

B-I-P ProductionAllocation Method

Base:31.46%

Intermediate:33.06%

Peak:35.48%

62

Equivalent Peaker Production Allocation Method

• The total cost of all CT generators in rate base is classified as 100% demand related.

• The rate base of each of the other generator types is classified between demand and energy-related cost components using the ratio of the unit cost of a new CT to the unit cost of a new (technology specific) generator. For example, the rate base of an existing 1,000 MW CC is $900,000,000 or $900/kW. An equivalent new CC is $1,150/kW, while a new CT is $725/kW.

Demand Component[$725/kW ÷ $1,150/kW] × $900,000,000 = $567,391,130 (63%)

Energy Component$900,000,000 - $567,391,130 = $332,608,870 (37%)

63

Peak Day Class Load Shapes

-

100

200

300

400

500

600

700

800

900

1,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Res Sm Com Lg Com Sm Ind Lg Ind64

Load Research

EXAMPLE: DETERMINE THERESIDENTIAL CLASS LOAD ATTHE TIME OF SYSTEM PEAK.

POPULATION

SAMPLEGOAL: DETERMINE AVERAGE LOAD PER CUSTOMER FROM AREPRESENTATIVE SAMPLE

EXPAND SAMPLETO POPULATION

ESTABLISHOBJECTIVES

SAMPLE DESIGNAND SELECTION

DATA COLLECTIONAND PROCESSING

DATA ANALYSISAND APPLICATIONS

RECORDED DATA

65

CFR § 290.403 : PURPA Load Research Requirements For COS

(b) Accuracy level.  . . . For loads during peak hours, sampling procedures must be designed with a statistically expected accuracy of plus or minus 10 percent at the 90 percent confidence level.

(c) Frequency of load research.  If load data are required to be collected on a sample metered basis, such research need not be conducted more frequently than once every five years for any utility that had total sales of electric energy less than 1 billion kilowatt‐hours annually . . . Load research need not be conducted more frequently than once every four years for all other utilities.

66

Sample Statistics

Mean Per Unit

Standard Deviation

Accuracye.g., ±10%

Confidence Intervale.g., 90%

n

iiY

nY

1

1

1

2

n

YYS i

Y

nSY Y 645.1

Y67

Population Characteristics

RATE CUSTOMERS ANNUAL SALES DEMANDCLASS NUMBER % MWh % MW %

RES 222,418 87.87 2,696,736 43.31 620 42.64COM 18,944 7.48 163,872 2.63 46 3.16MGS 8,710 3.44 1,316,612 21.14 257 17.68LGS 120 0.05 341,666 5.49 60 4.13IND 30 0.01 805,588 12.94 122 8.39HLF 4 - 863,562 13.87 105 7.22OTH 2,909 1.15 38,617 0.62 244 16.78

TOT 253,135 6,226,653 1,454

68

Load Research Sample Sizes

RATE 1979 1981 1983 1985 1987

RES 150 252 240 240 210COM - 30 80 300 350MGS - 120 160 160 160LGS/IND 6 50 70 77 85HLF 4 4 4 4 4

TOT 160 456 554 781 809

69

COS Load Research Metering

70

COST OF SERVICE:Study Summarization

71

RR = R + T + EWHERE

RR = REVENUE REQUIREMENTR = RETURN (NET INCOME) = RB × r

RB = NET RATE BASEr = WEIGHTED COST OF CAPITAL

T = INCOME TAXESE = OPERATING EXPENSES

Rate of Return Realization

72

ROR = [Revenue – Taxes – Expenses] ÷ RB

Cost-of-Service Study ResultsSMALL

TOTAL RESIDENTIAL COMMERCIAL

OPERATING REVENUES $ 471,450,356 $175,069,700 $ 70,431,660

OPERATING EXPENSES $ 324,494,642 $133,908,169 $40,413,912

OPERATING INCOME $ 146,955,714 $41,161,531 $ 30,017,748

INCOME TAXES $ 39,027,651 $ 7,909,932 $ 9,422,796

NET OPERATING INCOME $ 107,928,063 $ 33,251,599 $ 20,594,952

RATE BASE $ 1,304,942,001 $565,704,937 $ 165,747,023

RATE OF RETURN:ROI 8.47% 5.88% 12.42%

ROE 9.37% 3.93% 18.81%

73

Initial PURPA Reporting Requirements (circa 1978)

74

Larry Vogt

Q&A

75

Appendix Materials

76

Classification of Production Expenses

Nuclear Production O&M FERC Method NARUC MethodOperation Demand Energy Demand Energy517 Supervision and Engineering All -- Labor* Labor*

518 Fuel -- All -- All

519 Coolants and Water All -- Labor Materials

520 Steam Expenses All -- Labor Materials

521 Steam From Other Sources All -- -- All

522 Steam Transferred - Credit All -- -- All

523 Electric Expenses All -- Labor Materials

524 Miscellaneous Nuclear Expenses All -- All --

525 Rents All -- All --

Maintenance

528 Supervision and Engineering -- All Labor* Labor*

529 Structures All -- All --

530 Reactor Plant Equipment -- All -- All

531 Electric Plant -- All -- All

532 Miscellaneous Nuclear Plant -- All -- All

* Allocation between Energy and Demand based on labor subtotal of underlying accounts. 77

Classification of Production Expenses

Hydraulic Production O&M FERC Method NARUC MethodOperation Demand Energy Demand Energy535 Supervision and Engineering All -- Labor* Labor*536 Water for Power All -- All --537 Hydraulic Expenses All -- All --538 Electric Expenses All -- Labor Materials 539 Miscellaneous Hydraulic Expenses All -- All --540 Rents All -- All --

Maintenance541 Supervision and Engineering All -- Labor* Labor*542 Structures All -- All --543 Reservoirs, Dams, and Waterways All -- All --544 Electric Plant -- All -- All545 Miscellaneous Hydraulic Plant All -- -- All

* Allocation between Energy and Demand based on labor subtotal of underlying accounts. 78

Classification of Production Expenses

Other Production O&M FERC Method NARUC MethodOperation Demand Energy Demand Energy546 Supervision and Engineering All -- All --547 Fuel -- All -- All548 Generation Expenses All -- All --549 Miscellaneous Hydraulic Expenses All -- All --550 Rents All -- All --

Maintenance551 Supervision and Engineering All -- All --552 Structures All -- All --553 Generating and Electric plant All -- All --554 Miscellaneous Other Plant All -- All --

Other Power Supply O&M555 Purchased Power Demand Energy Demand Energy 556 System Control and Load Dispatching All -- All --557 Other Expenses All -- All --

Example comparison (millions): $30.5 $189.7 $60.8 $159.3 79

FERC Demand Test 1

MAX

12-CP

4-CP3-CP

MIN

3 OFF PK 3 OFF PK4 OFF PK 4 OFF PK

MW

Y%

X%Δ% = X% - Y%

80

FERC Demand Test 2

MAX

12-CP

4-CP3-CP

MIN

3 OFF PK 3 OFF PK4 OFF PK 4 OFF PK

MW

81

FERC Demand Test 3

MAX

12-CP

4-CP3-CP

MIN

3 OFF PK 3 OFF PK4 OFF PK 4 OFF PK

MW

82

FERC Demand Test 4

MAX

12-CP

4-CP3-CP

MIN

3 OFF PK 3 OFF PK4 OFF PK 4 OFF PK

MW

83