Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular...

25
Economic Analysis of the Modular Pebble Bed Reactor These slides present the conclusions of a preliminary study base These slides present the conclusions of a preliminary study base d on d on existing cost data found in existing cost data found in Evaluation of the Gas Turbine Helium Evaluation of the Gas Turbine Helium Reactor Reactor - - DOE DOE - - HTGR HTGR - - 90380 90380 - - Dec. 1993 and compared against an Dec. 1993 and compared against an NEI report issued in 1992 on the economics of alternative option NEI report issued in 1992 on the economics of alternative option s. s. The purpose was to evaluate on a relative scale whether the pebb The purpose was to evaluate on a relative scale whether the pebb le le bed could be competitive. For the purposes of this study the ga bed could be competitive. For the purposes of this study the ga s price s price in 1992 was assumed constant and did not increase. This study w in 1992 was assumed constant and did not increase. This study w ill ill be revised as better data is developed. be revised as better data is developed. June 1998 June 1998 Pebble Bed Reactor Project MIT Nuclear Engineering Department

Transcript of Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular...

Page 1: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Economic Analysis of the Modular Pebble Bed Reactor

These slides present the conclusions of a preliminary study baseThese slides present the conclusions of a preliminary study based on d on existing cost data found in existing cost data found in ““Evaluation of the Gas Turbine Helium Evaluation of the Gas Turbine Helium ReactorReactor”” -- DOEDOE--HTGRHTGR--90380 90380 -- Dec. 1993 and compared against an Dec. 1993 and compared against an NEI report issued in 1992 on the economics of alternative optionNEI report issued in 1992 on the economics of alternative options. s. The purpose was to evaluate on a relative scale whether the pebbThe purpose was to evaluate on a relative scale whether the pebble le bed could be competitive. For the purposes of this study the gabed could be competitive. For the purposes of this study the gas price s price in 1992 was assumed constant and did not increase. This study win 1992 was assumed constant and did not increase. This study will ill be revised as better data is developed.be revised as better data is developed.

June 1998June 1998

Pebble Bed Reactor ProjectMIT Nuclear Engineering Department

Page 2: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Turbine Hall Boundary

Admin

Training

ControlBldg.

MaintenanceParts / Tools

10

9

8

7

6 4 2

5 3 1

0 20 40 60 80 100 120 140 160

0

20

40

60

80

100

Primary island withreactor and IHX

Turbomachinery

Ten-Unit MPBR Plant Layout (Top View)(distances in meters)

Equip AccessHatch

Equip AccessHatch

Equip AccessHatch

Page 3: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Economic Analysis

• Group Goals– determine cost estimate for construction– compare cost estimate with that of existing

technologies– examine financing options– examine economies of scale vs. productivity

Page 4: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

MPBR Cost Estimate

• Capital cost• O&M cost• Fuel cost• Decommissioning cost

Page 5: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Capital Cost

• Cost savings come from:– more factory fabrication, less site work– learning effect from 1st to 10th unit– natural safety features– shorter construction time

• Total capital cost for 1100 MWe plant$2,296 million

Page 6: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Plant Construction

• Construction Plan / Techniques• Plant Physical layout• Construction Model

Page 7: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Construction Plan / Techniques

• Factory Assembly• Existing Technology• Modular Construction Allows:

– Parallel Construction– Ease of Shipment– Rapid Assembly– Streamlined Testing

Page 8: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based
Page 9: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

G r a p h f o r U n i t 12 0 0

1 0 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T im e ( W e e k )

U n it 1 : M o s t L ik e ly

G r a p h f o r U n i t 22 0 0

1 0 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T im e ( W e e k )

U n it 2 : M o s t L ik e ly

G r a p h f o r U n i t 42 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 4 : M o s t L i k e l y

G r a p h f o r U n i t 52 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 5 : M o s t L i k e l y

G r a p h f o r U n i t 62 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 6 : M o s t L i k e l y

G r a p h f o r U n i t 72 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 7 : M o s t L i k e l y

G r a p h f o r U n i t 82 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 8 : M o s t L i k e l y

G r a p h f o r U n i t 92 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 9 : M o s t L i k e l y

G r a p h f o r U n i t 1 02 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 1 0 : M o s t L i k e l y

G r a p h f o r U n i t 32 0 0

1 5 0

1 0 0

5 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T i m e ( W e e k )

U n i t 3 : M o s t L i k e l y

Page 10: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Unit 2

Unit 3

Unit 4

Un it 1 Unit 5

Un it 6

Un it 7

Unit 8

Unit 9

Unit 10

U n it C on stru ction F low p ath

G r a p h f o r In s t a n t a n e o u s W o r k i n P r o g r e s s8 0 0

6 0 0

4 0 0

2 0 0

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T im e (W e e k )

In s ta n ta ne o us W o rk in P ro g re s s : M o s t L ik e ly W e e k

Page 11: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Graph for Income During Construction60,000

30,000

00 40 80 120 160 200 240 280 320 360 400

Time (Week)

Income During Construction : MostLikely

Dollars/Week

Graph for Indirect Construction Expenses4 M

2 M

00 40 80 120 160 200 240 280 320 360 400

Time (Week)

Indirect Construction Expenses : Most Likely Dollars/Week

Graph for hardware cost600 M

300 M

00 40 80 120 160 200 240 280 320 360 400

Time (Week)

hardware cost : Most Likely

G rap h fo r N e t C o n s tru c t io n E x p en se2 B

1 .5 B

1 B

5 0 0 M

00 4 0 8 0 1 2 0 1 6 0 2 0 0 2 4 0 2 8 0 3 2 0 3 6 0 4 0 0

T ime (W e e k )

N e t C o nstruc tio n E xp e nse : M o st L ik e ly

Page 12: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Construction Model

• Can it be done?• Influence of external factors?• What are vulnerabilities / areas for time and

cost savings?• What is the relationship between

construction time and cash flow?• Sensitivity analysis

Page 13: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Graph for Net Construction Expense2 B

1.499 B

999.7 M

499.55 M

0 40 80 120 160 200 240 280 320 360 400Time (Week)

Net Construction Expense : Most LikelyNet Construction Expense : Unit-4 Hits WaterNet Construction Expense : IntervenorsNet Construction Expense : Module Delay

Graph for Instantaneous Work in Progress800

600

400

200

00 40 80 120 160 200 240 280 320 360 400

Time (Week)

Ins tantaneous W ork in Progres s : M os t Likely W eekIns tantaneous W ork in Progres s : Unit-4 Hits W ater W eekIns tantaneous W ork in Progres s : Intervenors W eekIns tantaneous W ork in Progres s : M odule Delay W eek

0

Page 14: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

MPBR PLANT CAPITAL COST ESTIMATE(MILLIONS OF JAN. 1992 DOLLAR WITHOUT CONTINGENCY)

Account No. Account Description Cost Estimate

20 LAND & LAND RIGHTS 2.521 STRUCTURES & IMPROVEMENTS 19222 REACTOR PLANT EQUIPMENT 62823 TURBINE PLANT EQUIPMENT 31624 ELECTRIC PLANT EQUIPMENT 6425 MISCELLANEOUS PLANT EQUIPMENT 4826 HEAT REJECT. SYSTEM 25

TOTAL DIRECT COSTS 1,275

91 CONSTRUCTION SERVICE 11192 HOME OFFICE ENGR. & SERVICE 6393 FIELD OFFICE SUPV. & SERVICE 5494 OWNERÕS COST 147

TOTAL INDIRECT COST 375

TOTAL BASE CONSTRUCTION COST 1,650CONTINGENCY (M$) 396

TOTAL OVERNIGHT COST 2,046UNIT CAPITAL COST ($/KWe) 1,860AFUDC (M$) 250

TOTAL CAPITAL COST 2296

Page 15: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

O&M Cost

• Simpler design and more compact• Least number of systems and components• Small staff size: 150 personnel• $31.5 million per year

Page 16: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Fuel Cost

• Assumptions:– One fuel pebble will cost $20.00 (‘92$)– One third of the fuel pebble bed is replaced

annually (120,000 per unit per year)– 1.0 mill/kWh for spent fuel disposal and

radioactive waste management• Cost: $32.7 million / year

Page 17: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Decommissioning Cost

• $211 million• Remove all radioactive wastes from site and

all construction material to a level of 3ft below grade.

• Less than 1 mill/kWh levelized busbar cost

Page 18: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

MPBR Busbar Generation Costs (‘92$)Reactor Thermal Power (MWt) 10 x 250Net Efficiency (%) 45.3%Net Electrical Rating (Mwe) 1100Capacity Factor (%) 90

Total Overnight Cost (M$) 2,046Levelized Capital Cost ($/kWe) 1,860Total Capital Cost (M$) 2,296Fixed Charge Rate (%) 9.4730 Year Level Cost (M$/yr):Levelized Capital Cost 217Annual O&M Cost 31.5Level Fuel Cycle Cost 32.7Level Decommissioning Cost 5.4

Revenue Requirement 286.6

Busbar Cost (mill/kWhr):Capital 25.0O&M 3.6Fuel 3.8Decommissioning 0.6

Total 33.0

Page 19: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Financing Construction

• Cost of capital– debt-to-equity ratio– distribution of risk

• Consortium approach– share risk– lower return on investment

Page 20: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Amortization of debt

• Determine annual revenue requirements– debt-to-equity ratio– return on preferred equity– return on common equity– income taxes

Page 21: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Debt Service Coverage

• Ratio of total revenue generated to annual revenue required– depends on amortization length– distribution of risk

• Consortium approach best

Page 22: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Competitive With Gas ?

• Natural Gas 3.4 Cents/kwhr• AP 600 3.62 Cents/kwhr• ALWR 3.8 Cents/kwhr• MPBR 3.3 Cents/kwhr

Levelized Costs (1992 $ Based on NEI Study)

Page 23: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Group Findings

• Low levelized cost– low fuel cost– low O&M cost

• High unit capital cost– low capacity design– high contingency factor (24%)

Page 24: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Future Work

• Determine optimal capital structure• Adjust cost estimate to design changes• Create detailed cash flow statement

Page 25: Economic Analysis of the Modular Pebble Bed Reactorweb.mit.edu/pebble-bed/Economics.pdfModular Pebble Bed Reactor These slides present the conclusions of a preliminary study based

Major MPBR Conclusions• Naturally Safe (Regulatory / Safety Implications)

– Constrained by Fuel Particle failure above 1600oC• Core power density chosen as 3.54 MW/m3

• Fuel pebble manufacturing defects are the most significant source of fission product release

• Economically Competitive– 3.3 cents/kWhr (natural gas = 3.4 cents/kWhr)

• Producing revenue within 3 years (rapid construction)• Low staffing and O&M costs• Factory Assembly

• Societal Acceptance– Proliferation Resistance -- promising, but future work needed– Waste Disposal -- promising, but future work needed