Department of Transportationand Public Works (DTPW)
Corridor WorkshopsApril 10 – 12, 2018
East-West Corridor Rapid Transit Project
#MiamiSMARTplan www.miamismartplan.com
Meeting Purpose
Project Identification
Project Scope
Project Process
Project Overview
Tier 1 Alternatives
Project Schedule
Public Engagement
2
East-West Corridor Rapid Transit Project
Identify ViableAlternatives
Identify ViableAlternatives
Present Tier 1Alternatives
Present Tier 1Alternatives
Selected as one of the sixSMART Plan Rapid Transit
Corridors
Major East-West Connection
High levels of traffic congestion
Need to serve major regionaleconomic engines
3
Project IdentificationEast-West Corridor Rapid Transit Project
What?What?
Where?Where?
How toAccess?How toAccess?
Rapid Transit Modes
Corridor Alignment
Station Locations and Types
4
Project ScopeEast-West Corridor Rapid Transit Project
5
Project ProcessEast-West Corridor Rapid Transit Project
ProjectDevelopment
andEnvironment(PD&E) Study
ProjectDevelopment
andEnvironment(PD&E) Study
Part of the process for complying with the NationalEnvironmental Policy Act (NEPA) of 1969 as mandated bythe U.S. Environmental Protection Agency (EPA) inaddition to Federal and State laws and regulations
State process for complying with NEPA requirements
Evaluation criteria allows for the project to be eligible forFederal and State funding
Public outreach is an essential and vital component ofthe process
Project Elements
6
Project ProcessEast-West Corridor Rapid Transit Project
Review of allexisting corridorconditions
DataCollection
EngineeringAnalysis
EnvironmentalEvaluations
Public Involvement
Developalternatives thatmeet the projectgoals
Identify potentialimpacts to social,natural, andphysicalenvironments
Continuous outreach and coordination with communityand stakeholders
Study Process - Milestones
Project Initiation
Elected Officials/Agency and Public Kick-Off Meetings
Environmental and Engineering Analysis
Corridor Public Workshops/Viable Alternatives
Alternatives Public Workshops/Recommended Alternative
Federal Environmental Class of Action Determination (NEPA)
Public Hearing/Selection of Locally Preferred Alternative (LPA)
FTA Acceptance into Project Development
Final Environmental and Engineering Documents
Publ
icEn
gage
men
t
We are here
7
Project ProcessEast-West Corridor Rapid Transit Project
PreviousMeetings
Project Overview
East-WestMultimodal
Corridor StudyInitiated
19921992 19981998
Federal TransitAdministration
Record ofDecision
SR 836Mainline
Constructionbegins
20122012 20172017
SR 836/SR 826Interchange
Improvementscompleted
20152015
AirportLinkOpens for
Service
8
East-West Corridor Rapid Transit Project
East-West Multimodal Corridor – Record of DecisionEast-West Multimodal Corridor – Record of Decision
Project Overview
9
East-West Corridor Rapid Transit Project
20192019
SR 836 ExpressRoutes(DTPW)
Project Overview
10
East-West Corridor Rapid Transit Project
836 Mainline and87th Ave.Interchange- In Construction
Dolphin StationPark & Ride- In Construction
Widening from57th Ave. to NW17th Ave.-In Construction
SR 836/I-95InterchangeImprovements- In DB Procurement
SR 836 SouthwestExtension “KendallParkway”- In PD&E
SR 836 HEFTRamps- In DBProcurement
XT (Express Technology) lanes
2019and beyond
2019and beyond
Major Projects onSR 836 by MDX
Project Overview
11
East-West Corridor Rapid Transit ProjectKick-Off Meetings – June 2017
Project Overview
12
East-West Corridor Rapid Transit ProjectKick-Off Meetings – Feedback
Project LimitsConsider including options north of SR 826
ModeConsider modes other than Metrorail (Heavy Transit Rail –
HRT)
AlignmentsConsider options other than NW 7th Street from 57th Avenue
to 62nd Avenue
Project Overview
13
East-West Corridor Rapid Transit ProjectUpdated Project
New ModesNew Modes
Project Overview
14
East-West Corridor Rapid Transit ProjectUpdated Project
New ProjectLimits
New ProjectLimits
NewAlignments
NewAlignments
Study Process
15
Project OverviewEast-West Corridor Rapid Transit Project
Locally PreferredAlternative
Locally PreferredAlternative
AlternativesIdentification
Tier 1Initial
AlternativesNo-Build
Potential BuildAlternatives
Tier 2Viable
AlternativesNo-Build
3 Build Alternatives
Tier 3Recommended
AlternativeNo-Build
1 Build Alternative
ViableAlternatives
No-Build3 Build Alternatives
RecommendedAlternative
No-Build1 Build Alternative
Publ
icIn
volv
emen
t
Study Process
16
Tier 1 AlternativesEast-West Corridor Rapid Transit ProjectAlternativesConsidered
Public HearingSelection of
LocallyPreferred
AlternativeSpring2019
Kick-offMeetingsSummer
2017
CorridorWorkshops
Spring2018
AlternativesWorkshops
Fall2018
17
Project ScheduleEast-West Corridor Rapid Transit Project
Your feedbackis important!
18
For more information:
Public Engagement
Karla Damian, DTPW Public Information OfficerPh.: 786-469-5420Email: [email protected]
Marie-Elsie Dowell, PE Consultant Project ManagerPh.: 305-514-3125Email: [email protected]
Ann Pope, Consultant Public Information Officer (PIO)Ph.: 305-321-6011Email: [email protected]
#MiamiSMARTplan [email protected] www.miamiSMARTPLAN.com
East-West Corridor Rapid Transit Project