City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Tacoma City Council Study SessionJuly 15, 2008
-
8/14/2019 East Foss Council PP 071508_FINAL
2/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
The Tacoma City Council commissioned astudy to work cooperatively with the Port of
Tacoma and other area businesses to developa transportation corridor in the alignment of theD Street in the East Thea Foss Peninsula areato separate industrial and nonindustrial uses
and to address traffic and related issues amongthe varied interests.
Project Purpose
-
8/14/2019 East Foss Council PP 071508_FINAL
3/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Project Area
-
8/14/2019 East Foss Council PP 071508_FINAL
4/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
To identify possible transportation solutionsfor the East Foss Peninsula that are
consistent with planning efforts, protect andencourage economic development, andfacilitate a transition between co-existing landuses of the East Thea Foss peninsula.
Steering Committee Vision Statement
-
8/14/2019 East Foss Council PP 071508_FINAL
5/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Focus on three primary area wide needs:
Traffic Access, Circulation & FunctionalSeparation
Transitions between mixed-use and industrialuses
Maintain/improve arterials to support existingbusinesses and to help spur new privateinvestments
Steering Committee
-
8/14/2019 East Foss Council PP 071508_FINAL
6/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Study Assumptions
No change to existing zoning
Recommended road projects are not subject to theMurray Morgan bridge funding decisions
Recognize the importance of the transportationlinks between the downtown and the Peninsulaarea
Prepared planning level project cost estimates
Emergency service levels would be unchanged
The E. 11th Street Bridge over the Puyallup River isapproaching its service life
-
8/14/2019 East Foss Council PP 071508_FINAL
7/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Stakeholders / Existing Land Use Zoning
Prominent Landowners / Uses J.M. Martinac* Petrich Marine Dock* Johnnys Dock Valero LP* Simpson Tacoma Kraft Mill* Globe Machinery* Supervalu Supervalu, International Panattoni* Burlington Northern Santa Fe Railroads Colonial Fruit and Produce* Thea Foss Development Authority* Port of Tacoma*
Conoco Phillips Stellar Port Maritime & Industrial NW Detention Center Amtrak Freighthouse Square Tacoma Dome
USF Reddaway
-
8/14/2019 East Foss Council PP 071508_FINAL
8/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Traffic Analysis Scenarios
Two access & circulation scenarios involving theMurray Morgan Bridge and East D Street at SR-509were analyzed as follows:
I. Fully operational Murray Morgan Bridge, D Streetoverpass complete, SR509 ramps to D Street.
II. Vehicle restricted operation of the Murray MorganBridge, D Street overpass complete, and no SR 509ramps to D Street.
-
8/14/2019 East Foss Council PP 071508_FINAL
9/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Current Conditions
East D Street at E. 15th looking South
East F Street at E. 7th looking South
E. 15th Street at St. Paul looking West
East D Street at E. 7th looking North
-
8/14/2019 East Foss Council PP 071508_FINAL
10/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Year 2025 Traffic Level of Service
LOS No Bridge/No Ramps LOS with Bridge/Ramps
Ci f T
-
8/14/2019 East Foss Council PP 071508_FINAL
11/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Future Circulation (No Bridge / No Ramps)
Concept A Extend East D Street Concept B Use Existing Streets
Cit f T
-
8/14/2019 East Foss Council PP 071508_FINAL
12/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor StudyFuture Circulation (Bridge /Ramps)
Concept A Extend East D Street Concept B Use Existing Streets
Cit f T
-
8/14/2019 East Foss Council PP 071508_FINAL
13/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions & Public Opinion
Varied views on separating industrial and mixed-use traffic
Overall support for slip ramps at SR 509 / East D Street
Support for St. Paul Ave/E. F Street at East 11th Streetintersection improvement
Varied opinions on East D Street designs
Business opposition to restriction industrial trafficon East DStreet north of E. 11th Street
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
14/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
15/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions
Projects B & C East D Street & SR 509 Ramps
B
C
Project C only
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
16/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions
Projects D, E and I (No MM Bridge)
D
IE
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
17/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions
Project E (Functioning MM Bridge)
E
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
18/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions
Projects F, G and H:East F Street, East D Street & NewEast 10th Street (No Murray MorganBridge)
H
G
F
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
19/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Solutions
Map # Location Recommendation Cost Estimate
Both Options
A East D / Puyallup Ave. Adjust traffic signal phasing (Grade Separation improvement complete andopen).
$2,000
B East D / SR 509 Construct Half Single Point Urban Interchange at East D St. / SR 509 (Ramps toand from the east) and signal.
$10,962,0001
C East D / East 15th Streets Improve East 15th St. / East D St. to include 10' sidewalk on west side, SBparking lane, 14' SB lane, 12' landscaped median/turn pocket, 14' NB lane.Access management/driveway consolidation where needed. Also improvepedestrian crossings at designated locations. Relocate transit stops/shelters tocrosswalk locations.
$4,771,000
D East D St. Extension (PrivateRoad)2
Extension is on private land and would require the relocation of BNSF rail spur.Extend East D St. south of East 11th St. to link to East 15th St. (10' sidewalk onwest side, SB parking lane, 2 - 11' travel lanes, 6' sidewalk on east side) 3.
$3,354,0001
E E. 11th / E. F St. Realign intersection at East 11th St. and East F St. $682,000
F East F St. Reconstruct East F Street north of East 11th St. $1, 622,000
G East D St. (North of E. 11th St.) Widen East D St. north of East 11th St. (SB parking lane and 2 - 14' lanes, 10'sidewalk on west side.
$1,760,0001
Operational Murray Morgan Bridge
H East 10th St. Add new east-west street (East 10th St.) between East D and East F Streets toinclude one 14' lane each direction and 6' sidewalk on south side.
$620,000
No Murray Morgan Bridge
I East 11th St. Extend East 11th St. west to tie into East D St.; Multi-use trail on north sidelinking to future shoreline esplanade and sidewalk on south side.
$846,0001
Total with Operational Murray Morgan Bridge $23,773,0001
Total with Murray Morgan Bridge closed $23,999,0001
Note 1: The Cost Estimate does not include costs for Permitting, Right of Way, Utility and Agency Agreements, or Bridge removal.
Note 2: The recommendation of this planned Private Road does irrevocably commit the property owner to build the road.
Note3: The roadway cross-section was developed for cost purposes only.
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
20/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Other Recommended Solutions
Pedestrian Links
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
21/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Summary of Key Points
Study area wide need for roadway maintenance
Desire for slip ramps at East D Street to SR 509
Desire to increase economic/redevelopmentopportunities of underutilized parcels
Need for improved arterial design to meet existing uses
Desire to ensure equitable distribution of improvementcosts
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
22/43
City of TacomaEast Thea Foss Waterway Transportation
Corridor Study
Recommended Implementation Strategy
Other Implementation Strategies:
Develop a plan to classify heavy truck arterials and implementheavy truck arterial design standards.
Determine if a shared cost approach (LID or other) would beacceptable to study area businesses and property owners.
As funding allows, adopt the recommended projects into the CitysSix-Year Transportation Program 2008 amendment.
Add all unfunded capital projects to the 2008 ComprehensivePlan/Transportation Element/Project list.
Implement three priority projects:
1. Begin needed street and rail crossing maintenance.
2. Improve the East 11th Street at East F Street/St Paul intersection.
3. Move forward with SR 509 ramp feasibility with WSDOT and BNSF
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
23/43
C y o aco aEast Thea Foss Waterway Transportation
Corridor Study
Factors Affecting Implementation
Competing interests for limited funding
Current economic conditions
Availability of grant funding
Varied opinions on separating traffic
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
24/43
yEast Thea Foss Waterway Transportation
Corridor Study
Recommended Next Steps
Incorporate appropriate sections of traffic study into theS-8 Shoreline Master Plan Regulations.
Implement the recommended three priority projects
Participating entities need to take studyrecommendations back to their boards/commissions
Increase coordination of advanced facility planningbetween the City and the Port of Tacoma.
Facilitate partnerships to share infrastructure costs tomaintain existing uses and to increase economic
development in the study area.
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
25/43
yEast Thea Foss Waterway Transportation
Corridor Study
Questions?
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
26/43
yEast Thea Foss Waterway Transportation
Corridor Study
Intentionally Blank
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
27/43
East Thea Foss Waterway TransportationCorridor Study
Alternative Concept
Gateway, Shared Use Path, Nonmotorized Bridge
City of Tacoma
-
8/14/2019 East Foss Council PP 071508_FINAL
28/43
East Thea Foss Waterway TransportationCorridor Study
Roadway Network
Freeways Interstate 5 Interstate 705 SR 509Principal Arterials Puyallup Avenue
Portland Avenue East 11th Street
Minor Arterials East D Street East 15th Street St. Paul Avenue
Collector Arterials East 26th Street East G Street East L Street East 27th Street Lincoln Avenue
City of TacomaE Th F W T i
-
8/14/2019 East Foss Council PP 071508_FINAL
29/43
East Thea Foss Waterway TransportationCorridor Study
Accidents
Intersection Accidents by Typ
0
5
10
15
20
25
30
35
40
E.26thSt.atE.PortlandAve.
E.DSt.atE.PuyallupAve.
E.GSt. atE.PuyallupAve.
E.LSt.atE.PuyallupAve.
E.MSt.atE.PuyallupAve.
E.McKinleyAve.atE.PuyallupAve.
E.15thSt.atE.St .PaulAve.
E.St.PaulAve.atE.11thSt.
E.PortlandAve. atE.PuyallupAve.
E.PortlandAve. atE.LincolnAve.
E.PortlandAve. atE.St.PaulAve.
Intersection Location
AccidentNu
mber2004-2006
Pedestrian
Other
Backing
Head On
Parked Vehicle/ Fixed Object
Sideswipe/ Lane Change
Right Angle/ Broadside
Approach Turn
Rear End
City of TacomaE t Th F W t T t ti
-
8/14/2019 East Foss Council PP 071508_FINAL
30/43
East Thea Foss Waterway TransportationCorridor Study
Freight
Truck Routes Portland Avenue Puyallup Avenue East D Street St. Paul Avenue East 11th Street
Rail Facilities BNSF/ UPRR Tacoma Rail Mountain Division BNSF Log Yards UP Tacoma Yards
City of TacomaE t Th F W t T t ti
-
8/14/2019 East Foss Council PP 071508_FINAL
31/43
East Thea Foss Waterway TransportationCorridor Study
Non-Motorized Facilities
Pedestrian Gaps / Barriers Portland Avenue (N. of St. Paul) Portland Ave (West side), S. of SR 509 St. Paul near 11th and 15th D St. north of Puyallup (in progress) D / F Streets north of 11 th Street 25th Street East of J Street 26th Street East of G Street
Bicycle Gaps / Barriers Puyallup Avenue D Street (North of SR 509)
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
32/43
East Thea Foss Waterway TransportationCorridor Study
Transit
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
33/43
East Thea Foss Waterway TransportationCorridor Study
Current Planned Projects
Bridge Projects East D Street Overpass East 11th Street Bridge Lincoln Avenue Bridge Puyallup River Bridge I-5 / McKinley Avenue Bridge I-5 / L Street Bridge I-5 Puyallup River Bridge
Road / Interchange Projects Portland Avenue Overlay Lincoln Avenue Overlay I-5 / Portland Avenue Interchange
Transit Projects Bus PLUS within Peninsula New Trunk Route from Lakewood to
Tacoma Dome
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
34/43
East Thea Foss Waterway TransportationCorridor StudyCurrent Planned Projects
(Unfunded)Road / Interchange Projects
East D Street Slip Ramps East C Street Extension I-5 HOV Direct Access near TacomaDome East L Street SignalsNon-Motorized Projects East 11th Street Trail
St. Paul Avenue Trail Portland Avenue Trail East 25th Street Trail SR 509 Trail Waterfront Esplanade Puyallup Avenue Bike Lanes East D Street Bike Lanes (over I-5) East G Street Bike Lanes (over (I-5) East 26th Street/River Road Bike Lanes Improved pedestrian facilities on PuyallupAvenue, East C St., East 26th St. East C Street connection to waterwayTransit Projects Light Rail to Seattle
Downtown Circulator Tacoma Dome Multi-Modal Station
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
35/43
East Thea Foss Waterway TransportationCorridor StudyArea A Options (No Bridge / No
Ramps)
East D or F Street Extension Use Existing Streets
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
36/43
East Thea Foss Waterway TransportationCorridor StudyArea B Options (No Bridge / No
Ramps)
East D Street / 15th
Street Boulevard East D Street / 15th
IndustrialRoad
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
37/43
East Thea Foss Waterway TransportationCorridor StudyArea C Options (No Bridge / No
Ramps)
East D Street Boulevard East D Street Industrial Road
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
38/43
East Thea Foss Waterway TransportationCorridor StudyArea D Options (No Bridge / No
Ramps)
East D Street Boulevard East D Street Industrial Road
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
39/43
East Thea Foss Waterway TransportationCorridor Study
East D or F Street Extension East D and F Streets
Area A Options (Operational Bridge / SR509 Ramps)
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
40/43
East Thea Foss Waterway TransportationCorridor StudyArea A Options (Operational Bridge /
SR 509 Ramps)
Use Existing Streets
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
41/43
East Thea Foss Waterway TransportationCorridor StudyArea B Options (Operational Bridge /
SR 509 Ramps)
East D Street / 15
th
Street Boulevard East D Street / 15th
IndustrialRoad
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
42/43
y pCorridor StudyArea C Options (Operational Bridge /
SR 509 Ramps)
East D Street Boulevard East D Street Industrial Road
City of TacomaEast Thea Foss Waterway Transportation
-
8/14/2019 East Foss Council PP 071508_FINAL
43/43
y pCorridor Study
East D Street Boulevard East D Street Industrial Road
Area D Options (Operational Bridge /SR 509 Ramps)