East Fork of Fountain Creek Mandatory Pre Bid Meeting
description
Transcript of East Fork of Fountain Creek Mandatory Pre Bid Meeting
14 May 2013
Aerial of Flood Insurance Rate Map (FIRM)
East Fork of
Fountain Creek
Aerial View of Existing Creeks
April 11, 2013
Photos looking North – Upstream
April 11, 2013
Confluence of Main Stem and East Fork of Fountain Creek
South of the Confluence of
Fountain Creek
Administrative NotesBid Opening will be 3:00 PM,
Thursday 30 May 2013 at City HallBid Bonds requiredPlease include completed CDOT
Forms 605, 606 and 621CDOT funded projectDBE & OJT Goal = zeroDavis Bacon wages not required
Substantial completion by 30 Sep 2013
All RFI’s should be in writing and sent via e-mail to: [email protected] or [email protected]
Staging area – TBD and negotiated between the Contractor and property owner
Channel Fill and ReclamationWithin the Easement:
Per plans and specsCity Engineering Specs (Title 7;
Section 7.5.2.1. Utility Mains – available on line)
95% Modified Proctor (ASTM D-1557) unless otherwise directed
Contractor is responsible for all QC & soils testing
City may do some QA testing
Outside the Easement:Will require special attentionSee supplemental plans
Alternative Pipe MaterialsProposals will be evaluated
separatelyDecision to use alternative pipe
materials will be collaboratively evaluated and approved by the City, the property owner and CDOT
Must include:Recent experience with similar
72” and 84” pipe diametersCrew shall also have recent
experience with large diameter pipe installations (i.e. Project Superintendent, Foreman, etc.)
Provide referencesProvide QC plan
Trail Ridge Apartments – Grading Plan