East avenue PD&E STUDY | EVALUATION MATRIX

1
East avenue PD&E STUDY | EVALUATION MATRIX Addresses capacity needs and provides acceptable Level of Service in 2045 Yes Enhances roadway safety Yes Number of Parcels Impacted 106 Residential Relocations 24 Business Relocations 6 Historical, Archeological or Section 4(f) Sites Affected Medium Wetlands Impacted (Acres) Low Floodplains Impacted (Acres) 4.78 Impacts to Threatened and Endangered Species Low Potential Impacts from Noise Low 5 High Risk Sites 4 Medium Risk Sites Potential Impacts to Utilities Relocations to electric, water, sewer, communications Preliminary Design $3,150,000 Preliminary Right of Way $53,300,000 Preliminary Construction Cost $35,291,490 Total Preliminary Cost $91,741,000 Physical Resource Effects Potential Contamination Sites (within 500') Cost Estimate ($ million) Impact potential: Low Project Goals Social and Economic Effects Cultural Resource Effects Natural Resource Effects

Transcript of East avenue PD&E STUDY | EVALUATION MATRIX

East avenue PD&E STUDY | EVALUATION MATRIX

Addresses capacity needs and provides acceptable Level of Service in 2045 YesEnhances roadway safety Yes

Number of Parcels Impacted 106Residential Relocations 24Business Relocations 6

Historical, Archeological or Section 4(f) Sites Affected Medium

Wetlands Impacted (Acres) LowFloodplains Impacted (Acres) 4.78Impacts to Threatened and Endangered Species Low

Potential Impacts from Noise Low5 High Risk Sites

4 Medium Risk SitesPotential Impacts to Utilities Relocations to electric, water, sewer, communications

Preliminary Design $3,150,000 Preliminary Right of Way $53,300,000 Preliminary Construction Cost $35,291,490 Total Preliminary Cost $91,741,000

Physical Resource Effects

Potential Contamination Sites (within 500')

Cost Estimate ($ million)

Impact potential: Low

Project Goals

Social and Economic Effects

Cultural Resource Effects

Natural Resource Effects