Earthworks quantities (GRD Part 3 Chpt. 8)
Transcript of Earthworks quantities (GRD Part 3 Chpt. 8)
1
Earthworks quantities (GRD Part 3 Chpt. 8)
2
• Process of excavating existing land to a suitable level so that pavement construction can commence
• Earthworks normally consist of both cuts and fills• Aim is to minimise earthwork quantities• Seek to achieve a balance in cut and fill quantities
Earthworks
2
3
• On urban projects or rural works on flat terrain difficult to obtain a balance
• In rolling terrain earthwork balance is more readily achieved after making adjustments for:– stripping– depth of top soil removed– removal of unsuitable road construction materials– use of materials for pavement– photogrammetric bias– compaction and bulking factors
• Information to provide the adjustment factors can be obtained from geotechnical investigations
Earthwork balance
4
• E Easy digging - loose free running soils e.g. sands, fine gravels.
• M Medium - denser cohesive soils e.g. clayey gravel, low PI clays
• M-H Medium to hard – e.g. broken rock, wet heavy clay, gravel with boulders
• H Hard - material requiring blasting and hard high PI clays
Excavation of material – ease of digging
3
5
Excavation increases the volume of material. It is therefore necessary to use a bulking factor to determine the volume of material that will be created by excavation.
Bulking factor is defined as:
Bulking factor = volume after excavation/volume before excavation
Shrinkage factor is defined for the compaction of a soil at its final destination:
Shrinkage factor = volume after compaction/volume before excavation
Bulking/compaction of excavated material
6Bulking and shrinkage factors (Part 7 Table 4.1)
Material Loose volumeCompacted
volume
Solid rock 1.60 1.25
75%/25% rock/soil mixture
1.45 1.20
50%/50% rock/soilmixture
1.35 1.10
25%/75% rock/soil mixture
1.25 1.05
Granitic sand and gravel
1.10 0.90
Dune sand 1.15 0.95
Sandy clay 1.25 0.93
Expansive clay (basaltic)
1.45 0.90
Topsoil 1.45 0.95
4
7
• Using average end area method
Estimating earthwork quantities
natural surface
natural surface
A1
A2
Volume = (A1+A2)* L
2
L
8
• For a cut or fill on horizontal ground
Earthwork calculations
Assuming a cut such as the one above, the cross sectional area is given by:
Area = h.2b + 2nh²/2 = h(2b + n.h)
Note: Actual volumes may vary from estimates by 5 – 10%
5
9
• For a cut or fill on sloping ground
Earthworks calculations
Assuming a cut such as the one above, the cross-sectional area is found firstly by calculating WL and WG:
WL = S(b+nh)/(S+n)WG = S(b+nh)/(S-n)
Area = ½(h + b/n)(WL + WG) - b²/n
10
Mass haul diagram
-100,000.0
-80,000.0
-60,000.0
-40,000.0
-20,000.0
0.0
20,000.0
40,000.0
60,000.0
0.0 300.0 600.0 900.0 1,200.0 1,500.0 1,800.0
Chainage
Vo
lum
es
m3
Mass haul
Mass haul diagrams
The mass haul diagram is simply a plot of cumulative volume against chainage. Areas below the line represent net fill and areas above the line represent net waste. The following points are worth noting:
– a rising curve indicates an increasing volume (cut)
– a maximum point on the curve represents the end of a cut
– a falling curve represents a decreasing volume (fill)
– a minimum point represents the end of a fill
– areas at the end of the diagram represent a waste or a deficit.
6
11
Earthwork Balance
-10.0
-5.0
0.0
5.0
10.015.0
20.0
25.0
30.0
35.0
40.0
0.0 200.0 400.0 600.0 800.0 1,000.0 1,200.0 1,400.0 1,600.0
Chainage
Le
ve
ls
Ground levelRoad level
Mass haul diagram example
Mass haul diagram
-100,000.0
-80,000.0
-60,000.0
-40,000.0
-20,000.0
0.0
20,000.0
40,000.0
60,000.0
0.0 300.0 600.0 900.0 1,200.0 1,500.0 1,800.0
Chainage
Volu
mes
m3
Mass haul
12Questions?