Earned Value Management theory and its application on practice at CERN and JINR.

37
Earned Value Management theory and its application on practice at CERN and JINR. Dmitry Kekelidze Software Engineer JINR – LIT/ CERN - GS-AIS

description

Earned Value Management theory and its application on practice at CERN and JINR. Dmitry KekelidzeSoftware EngineerJINR – LIT/ CERN - GS-AIS. Agenda. EVMS concepts NICA project EVM web-based application. What is EVM?. EVM is the project management tool. Are we there yet? - PowerPoint PPT Presentation

Transcript of Earned Value Management theory and its application on practice at CERN and JINR.

Page 1: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Earned Value Management theory and

its application on practice at CERN and JINR.

Dmitry KekelidzeSoftware Engineer

JINR – LIT/ CERN - GS-AIS

Page 2: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Agenda

EVMS concepts NICA project EVM web-based application

Page 3: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

What is EVM?

EVM is the project management tool...

Are we there yet?How much longer before we’ve arrived?What can we do about it?

Page 4: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

performance measurementhow am I doing against my baseline plan?

performance managementwhat do I need to do to bring the project in on cost and schedule?

EVM is

Page 5: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Preparation• Research Topic• Decide on Structure

Make Slides• EVM Basics• EVM Advanced• NICA Intro• Conclusion

Finishing up• Trial Presentation• Implement Feedback

Example: making this presentation

Page 6: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Research

Presentation template

EVM Basics

NICA Intro

Conclusion

EVM Advanced

Start slides

Agenda

ReshuffleDry run

Slides ready

cost

time

Project: making the presentation

Page 7: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

What is this mysterious Earned Value ?

What is an honest measure for what is achieved?

Page 8: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Research

Presentation template

EVM Basics

NICA Intro

Conclusion

EVM Advanced

Agenda

ReshuffleDry run

time

costSlides ready

Start slides

Project: making the presentation

Page 9: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Main metrics :PV - Planned Value

The portion of work expected to be completed at a given date, times the authorized budget allocated to carry out that work

EV - Earned Value

The value of completed work expressed in terms of the budget assigned to that work

AC - Actual Cost The costs actually incurred and recorded in accomplishing the work performed

EVM Concepts

Page 10: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

time

Cost

•Are we ahead or behind schedule?•Are you getting value for money?•Did you spend money on the right things?

Achievement

now

How is our project doing?

BudgetPlanned Value

Actual Cost

Earned Value

$

Page 11: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

now time

Underspending but ...

Actual Cost

Planned Value

Earned Value

What happens?

$

Page 12: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

now time

Underspending but ...

Actual Cost

Planned Value

Earned Value

$

What happens ?

Page 13: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

time

AC

PV

EVnow

BAC: Budget At Complete

SV = EV – PVSchedule Variance

CV = EV – ACCost Variance

project end

project start

SV < 0

SV > 0

CV < 0

CV > 0

PMR Project Management Reserve

$EVM Concepts

Page 14: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Earned Value: Cheat Sheet

Schedule Variance SV = EV–PV In currency. Negative means delay

Schedule Performance Index

SPI = EV/PV < 1 means delay

Cost Variance CV = EV-AC In currency. Negative means overcost.

Cost Performance Index

CPI = EV/AC < 1 means overcost

Estimate At Completion

EAC = BAC / CPI Forecast final cost

To Complete Performance Index

TCPIBAC = (BAC-EV)/(BAC-AC)

Can we catch up?

Page 15: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

now time

EAC$

Estimated Cost at Completion

Page 16: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Benefits of EVM

Requires development of integrated baselineResults in better project definition and planning

Early identification of trends and problems Accurate picture of project status

Cost, schedule, and technicalsegregation of schedule and cost variances

Projection of final costs Project control by the team

Enables project manager to make informed decisions based on facts

Results in successful projectsOn time, on cost

Page 17: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Example: software development

Requirement

Architecture

Design

Code

Testing

100h

100h

100h

200h

100h

Page 18: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Task Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Status at end of Month 5

Requirements(100h) S------F Complete,

Spent 100h

Architecture(100h) S----PF --F Complete,

Spent 120h

Design(100h) PS-S-PF --F Complete,

Spent 125h

Code (200h) PS----S- -----PF 25% Complete,

Spent 70h

Testing(100h) PS---PF Not yet started

Example: execution plan

Page 19: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

At the end of Month 5, what is?

Calculation Answer

PV 100 + 100 + 100 + 200 500h

EV 100 + 100 + 100 + 50 350h

AC 100 + 120 + 125 + 70 415h

BAC 100 + 100 + 100 + 200 + 100 600hCV 350 - 415 -65h

CPI 350 / 415 84%

SV 350 - 500 -150h

SPI 35,000 / 50,000 70%

IEAC 600/0.84 711h

TCPI (600-350)/(600-415) 135%

Page 20: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

PMBOK

Page 21: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

WBS: Work Breakdown Structure, hierarchical list of all the activities to be performed to complete the project.

Workunits: The “Leaves” of the WBS tree. Activity small in size/duration, under responsibility of one person.

Workunits use Resources (money, people) to produce Deliverables

Terminology

Page 22: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Where can EVM be Applied?

EVM suitable for projects that have:• Clear definition of work scope• Project schedule range from a few months to

many years• Small to very large cost

Page 23: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

• Technically complex and demanding,i.e. that cannot be fully specified in the front-end phase;

• Long makespan: economic effects like inflation• Involving many contributors, contractors, suppliers...

i.e. many activities that are outsourced, result-oriented.

What is a large-scale project?

Page 24: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Agenda

EVMS concepts NICA project EVM web-based application

Page 25: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

NICA

Page 26: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Is NICA large-scale project?

NICA

Work planned for period from year 2012 till 2017 Estimated cost is more than 100M $ Tasks to complete:

• General Infrastructure• Accelerator• MPD Detector

All the work have to be well coordinated

Page 27: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

LHC Accelerator and Detectors

Page 28: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Project audit of 2001

18% overspend announcement … only

Technical Coordinator → “the project is behind

schedule” Project Administrator → “the project is under-running” LHC Team: not is position to demonstrate that the

project could be completed within allocated budget!

Member States asked the LHC Project Management to set up

a formal Project Control System

Page 29: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

EVM-based project control system

Deliverable-oriented physical progress monitoring

Interfaced to accounting systems,

to get accurate information on actual costs

Excel spreadsheets to interact with DBs

Web-based

The key requirements

Page 30: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Why a D-O EVMS?

Activitycompleted?

Progress 90%!

An activity of the project

Activitynot startedProgress 0%

Activityhalf-way

Progress 50%Activity

almost doneProgress 90%

90%-syndrome

Page 31: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Outcome of EVM experience…

Re-established trust• Cost and Schedule Review Committee:

‘world class’• CERN management was formally

congratulated by Member States• Further overruns were discussed in the

context of proven project control.

Project culture at CERN and cost awareness of project engineers have improved.

Page 32: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Agenda

EVMS concepts NICA project EVM web-based application

Page 33: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Data Definition

WBS Workunits

Resources Personnel Material

Deliverables

• Web interface• Excel files

Page 34: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Collaborative tool

Reminders for progress reporting

Page 35: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Dynamic Reports

Crosstab to drill drown through the WBS structure (or other dimension…)

PV, EV, AC Charts at every WBS level

Page 36: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.

Conclusion

Objectively measures performance of the project as it moves from project initiation through project closure.

Provides early warning of potential project adverse performance.

Shows Opportunity associated with positive schedule variance.

Enables the management of risk associated with underwriting or insuring against negative schedule variance.

Provides a means to forecast future performance based upon past performance.

Page 37: Earned Value Management theory  and  its  application on practice  at  CERN and JINR.