EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool By Roy T. Uemura, PMP, P.E., MBA Project...
-
Upload
briana-franklin -
Category
Documents
-
view
214 -
download
0
Transcript of EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool By Roy T. Uemura, PMP, P.E., MBA Project...
EARNED VALUE EARNED VALUE MANAGEMENT SYSTEMMANAGEMENT SYSTEM
AAProject Performance ToolProject Performance Tool
ByBy
Roy T. Uemura, PMP, P.E., MBARoy T. Uemura, PMP, P.E., MBA
Project Management ConsultantProject Management Consultant
Project Professionals, LLCProject Professionals, LLC
How Is Your Project How Is Your Project Doing?Doing?
Ahead of schedule?Ahead of schedule?
Within your approved Budget?Within your approved Budget?
How Is Your Project How Is Your Project Doing?Doing?
What is your cost estimate at What is your cost estimate at completion?completion?
Will you be ahead or behind Will you be ahead or behind the scheduled completion the scheduled completion date?date?
AgendaAgenda1.1. Explanation of Earned Value Explanation of Earned Value
Management (EVM)Management (EVM)2.2. The traditional “Two Dimensional The traditional “Two Dimensional
System” of EvaluationSystem” of Evaluation3.3. EVM “Three Dimensional System” of EVM “Three Dimensional System” of
EvaluationEvaluation4.4. Critical Variables in EVMCritical Variables in EVM5.5. EVM FormulasEVM Formulas6.6. Applying EVM on projectsApplying EVM on projects7.7. Example Example
Earned Value ManagementEarned Value Management
Method for integrating scope, Method for integrating scope, schedule, and resources, for schedule, and resources, for measuring project performance.measuring project performance.
Compares what was planned with Compares what was planned with what was actually spent with what what was actually spent with what was actually “earned”was actually “earned”
Earned Value Earned Value ManagementManagement
Developed in the 1960’s Popular method for reporting and controlling
project in the Department of Defense A common language to report progress and
cost against a project Helps answer the questions:
Are we on schedule? How much did the work we do cost? Are there variances? Based on these trends, how much will it cost by the
end of the project?
Early Warning SystemEarly Warning System
“… “… based on the Project based on the Project Performance PlanPerformance Plan
and Project’s and Project’s Actual PerformanceActual Performance against against
the Plan, the Plan,
1.1. the project will likely take this the project will likely take this much time to finish, and much time to finish, and
2.2. spend this much money.”spend this much money.”
Traditional SystemTraditional System(Two Dimensional)(Two Dimensional)
CostCost:: compares what was planned compares what was planned to be expended versus what was to be expended versus what was actually expendedactually expended
TimeTime:: Compares the date you are Compares the date you are on a project versus when the project on a project versus when the project is to be completedis to be completed
ProductionProduction:: Compares how much Compares how much work was planned to be completed work was planned to be completed versus how much was actually versus how much was actually completed.completed.
Earned ValueEarned Value(Three Dimensional)(Three Dimensional)
1. Actual work that was 1. Actual work that was “earned”“earned”
versusversus
2. Work that was 2. Work that was accomplishedaccomplished
versusversus
3. Work that was 3. Work that was scheduledscheduled to to be accomplishedbe accomplished
Critical Variables to Critical Variables to EV Performance IndicesEV Performance Indices
1.1. Quality of the project baseline Quality of the project baseline planplan
2.2. Actual performance against Actual performance against baseline planbaseline plan
3.3. Management’s determination to Management’s determination to control (change) the final resultscontrol (change) the final results
Project BaselineProject Baseline
Basis of performance measurementBasis of performance measurement Represents technical, cost and Represents technical, cost and
schedule objectives of the projectschedule objectives of the project CashflowsCashflows
Outside MaterialOutside Material Outside Services Outside Services
Scope of WorkScope of Work
The scope of work of entire project The scope of work of entire project must be definedmust be defined
The Work Breakdown Structure The Work Breakdown Structure (WBS) identifies and groups major (WBS) identifies and groups major deliverablesdeliverables
Integrate scope with budget and Integrate scope with budget and schedule.schedule.
Performance Measurement Performance Measurement MethodsMethods
Fixed formula by task:Fixed formula by task:
0/100 %, 25/75%, 50/50 %0/100 %, 25/75%, 50/50 % Weighted MilestonesWeighted Milestones
Percent complete based on specific Percent complete based on specific workwork
(milestone) accomplished.(milestone) accomplished. Percent CompletePercent Complete
Increment completed / total Increment completed / total activity or taskactivity or task
Equivalent Completed Units Equivalent Completed Units
Cost Account PlanCost Account Plan
WP# WORK DESCRIPTION EV METHOD JAN FEB MAR APR BAC
1 Design Weighted PV
Milestones AC
EV
2 Site Prep Fixed Formula PV
0/100% AC
EV
3 Install Foundations Equivilent PV
Units AC
EV
4 Construct Building % Compl PV
AC
EV
Project DescriptionProject Description
Installed approximately 14.5 miles Installed approximately 14.5 miles of of transmission line of which about transmission line of which about 4,000 feet was installed 4,000 feet was installed underground.underground.
Installed 93 steel poles: 52 poles Installed 93 steel poles: 52 poles were direct buried and 41 were were direct buried and 41 were mounted on pier foundations.mounted on pier foundations.
Kuilima
Waialua
Visual Progress ReportVisual Progress Report Foundation: Dug Concrete Foundation: Dug Concrete
PouredPoured
Pole Erection: Pole Erection:
Lines Strung:Lines Strung:
Trench: Trench: Conduit Installed:Conduit Installed: Cable Installed:Cable Installed: Trench Covered:Trench Covered:
Kuilima
Waialua
Controlling ChangeControlling Change
Essential: Change Management Essential: Change Management Control System in the Project Plan Control System in the Project Plan prevents incorrect, inappropriate, or prevents incorrect, inappropriate, or unauthorized changes to the project.unauthorized changes to the project.
Inform appropriate stakeholders of Inform appropriate stakeholders of authorized changes to the Baseline authorized changes to the Baseline (scope/quality, schedule, cost)(scope/quality, schedule, cost)
EVM Input Data RequiredEVM Input Data Required
PLANNING PHASEPLANNING PHASE Planned Value (PV)Planned Value (PV) Budget At Completion (BAC)Budget At Completion (BAC) % Complete - Planned% Complete - Planned
EXECUTING & CONTROLLING EXECUTING & CONTROLLING PHASESPHASES
Actual Cost (AC)Actual Cost (AC) % Complete - Actual% Complete - Actual
Calculations from Input Calculations from Input DataData
Earned Value - EVEarned Value - EV Cost Variance - CVCost Variance - CV Schedule Variance - Schedule Variance -
SVSV
Calculations for AnalysisCalculations for Analysis
Cost Performance Index - Cost Performance Index - CPICPI Schedule Performance Index - Schedule Performance Index - SPISPI Budget at Completion - Budget at Completion - BACBAC Estimate to Completion - Estimate to Completion - ETCETC Estimate at Completion - Estimate at Completion - EACEAC To Complete Performance Index - To Complete Performance Index -
TCPITCPI
Primary Data ElementsPrimary Data Elements
PV (Planned Value)PV (Planned Value)
The value of the amount of work that wasThe value of the amount of work that was
planned to be accomplished on a task (or aplanned to be accomplished on a task (or a
project) as of a certain date in the baselineproject) as of a certain date in the baseline
plan. plan.
BAC (Budget at Completion)BAC (Budget at Completion)
Total cost of a task (or project) according toTotal cost of a task (or project) according to
the baseline plan.the baseline plan.
AC (Actual Cost)AC (Actual Cost)
The actual amount of money spent The actual amount of money spent
on a task (or project) as of a certain on a task (or project) as of a certain date.date.
Primary Data Elements (cont’d)Primary Data Elements (cont’d)
Performance AnalysisPerformance Analysis
EV (Earned Value).EV (Earned Value).
The value of the amount of work The value of the amount of work actually actually
completed on a task (or project) as completed on a task (or project) as of aof a
certain date, according to the certain date, according to the baselinebaseline
plan. plan.
EV = % Actual Complete x EV = % Actual Complete x BACBAC
CV (Cost Variance)CV (Cost Variance)
The difference between the value of workThe difference between the value of work
that was actually completed (EV) on a taskthat was actually completed (EV) on a task
(or project) and the cost that was actually(or project) and the cost that was actually
spend (AC) on the task (or project) as of a spend (AC) on the task (or project) as of a
certain date.certain date.
CV = EV - ACCV = EV - AC
(+$ = spending less than (+$ = spending less than planned)planned)
Performance Analysis (cont’d)Performance Analysis (cont’d)
SV (Schedule Variance)SV (Schedule Variance)
The difference between the value of work The difference between the value of work
that was actually completed (EV) on a taskthat was actually completed (EV) on a task
(or project) and the work that should have(or project) and the work that should have
been done (PV) as of a certain date.been done (PV) as of a certain date.
SV = EV - PVSV = EV - PV
(+$ = Ahead of Schedule)(+$ = Ahead of Schedule)
Performance Analysis (cont’d)Performance Analysis (cont’d)
CPI (Cost Performance Index)CPI (Cost Performance Index)
The ratio of the value of work actuallyThe ratio of the value of work actually
completed (EV) on a task (or project) andcompleted (EV) on a task (or project) and
amount actually spent (AC) on a task (oramount actually spent (AC) on a task (or
project) as of a certain date.project) as of a certain date.
CPI = EV/ACCPI = EV/AC
(>1 = Spending less than (>1 = Spending less than planned)planned)
Performance Analysis (cont’d)Performance Analysis (cont’d)
SPI (Schedule Performance Index)SPI (Schedule Performance Index)
The ratio between the value of work that The ratio between the value of work that waswas
actually completed (EV) on a task (or actually completed (EV) on a task (or project)project)
and the work that should have been doneand the work that should have been done
(PV) as of a certain date.(PV) as of a certain date.
SPI = EV/PVSPI = EV/PV
(>1 = Ahead of Schedule)(>1 = Ahead of Schedule)
Performance Analysis (cont’d)Performance Analysis (cont’d)
Performance Analysis (cont’d)Performance Analysis (cont’d)
ETC (Estimate To Completion)ETC (Estimate To Completion)The forecasted cost of the remaining task The forecasted cost of the remaining task (or project) is calculated by CPI or (or project) is calculated by CPI or CPI x SPICPI x SPI
ETC = Remaining Work / CPIETC = Remaining Work / CPI = (BAC - EV/ CPI= (BAC - EV/ CPI oror ETC = Remaining Work/ (CPI x ETC = Remaining Work/ (CPI x
SPI)SPI) = (BAC - EV/(CPI x SPI)= (BAC - EV/(CPI x SPI)
EAC (Estimate at Completion)EAC (Estimate at Completion)
The value expressed in either dollars or The value expressed in either dollars or hourshours
to represent the projected final cost of workto represent the projected final cost of work
when completed. The EAC equals the when completed. The EAC equals the actualactual
costs (AC) incurred plus the estimated costs (AC) incurred plus the estimated costscosts
to complete the remaining work (ETC). to complete the remaining work (ETC).
EAC = AC + ETCEAC = AC + ETC
Performance Analysis (cont’d)Performance Analysis (cont’d)
Performance Analysis (cont’d)Performance Analysis (cont’d)Ranges of Estimate at Ranges of Estimate at
CompletionCompletionHigh-End Projection (Cumulative CPI x SPI)High-End Projection (Cumulative CPI x SPI)
EAC = AC + (BAC - EV) / (CPI x SPI)EAC = AC + (BAC - EV) / (CPI x SPI)
In-Between Projection (80% CPI x 20% SPI)In-Between Projection (80% CPI x 20% SPI)
EAC = AC + (BAC - EV) / (0.8 CPI x EAC = AC + (BAC - EV) / (0.8 CPI x 0.2 SPI)0.2 SPI)
Low-End Projection (Cumulative CPI)Low-End Projection (Cumulative CPI)
EAC = AC + (BAC - EV) / CPIEAC = AC + (BAC - EV) / CPI
To Complete Performance IndexTo Complete Performance IndexTCPI: Project performance which must beTCPI: Project performance which must beachieved on all remaining work in order toachieved on all remaining work in order tomeet the financial goal by managementmeet the financial goal by management
TCPI = Work Remaining / Funds TCPI = Work Remaining / Funds RemainingRemaining
= = (Total Budget - Earned (Total Budget - Earned value) value)
(BAC - Actual Costs)(BAC - Actual Costs)
= = (BAC - EV)(BAC - EV) (BAC - AC)(BAC - AC)
PMP ExamPMP Exam
Estimate At Completion Estimate At Completion (EAC)(EAC)
EAC = EAC = BACBAC CPICPIEstimate to Complete Estimate to Complete
(ETC)(ETC) ETC = EAC - ACETC = EAC - AC
Rita Mulcahy, PMP Exam Prep 5Rita Mulcahy, PMP Exam Prep 5thth Edition (2005) Edition (2005)
ExampleExample
Time: 4Time: 4thth month of 10 month month of 10 month scheduleschedule
Budget at Completion: BAC = Budget at Completion: BAC = $10,000$10,000
Planned Value: PV = $4,000Planned Value: PV = $4,000 Actual Cost: AC = $3,800Actual Cost: AC = $3,800 Actual % Complete: 36%Actual % Complete: 36% Earned Value: Earned Value:
EV = 0.36 x $10,000 = $3,600EV = 0.36 x $10,000 = $3,600
Time
3
BAC$10,000
$5,000
1 6 7
AC = $3,800
EV = $3,600
Status Date
PV = $4,000
Earned Value Analysis
2 4 5 8 9 10
Traditional AnalysisTraditional AnalysisCost Variance:= Planned Expenditure - Cost Variance:= Planned Expenditure -
Actual CostActual CostCV = PV - ACCV = PV - ACCV = $4,000 - $3,800 = $200 (under spent CV = $4,000 - $3,800 = $200 (under spent
by $200)by $200)Earned Value AnalysisEarned Value AnalysisCV = EV - ACCV = EV - ACCV = $3,600 - $3,800 = -$200 (spending CV = $3,600 - $3,800 = -$200 (spending
more than planned for work performed)more than planned for work performed)SV = EV - PVSV = EV - PVSV = $3,600 - $4,000 = -$400 (less work SV = $3,600 - $4,000 = -$400 (less work
was done than planned)was done than planned)
Performance AnalysisPerformance Analysis
Performance AnalysisPerformance Analysis
Cost Performance Index (CPI)Cost Performance Index (CPI)CPI = EV / ACCPI = EV / ACCPI = $3,600/$3,800 = 0.95 (<1, for CPI = $3,600/$3,800 = 0.95 (<1, for
every $1 spent, only $0.95 in every $1 spent, only $0.95 in physical work was done)physical work was done)
Schedule Performance Index (SPI)Schedule Performance Index (SPI)SPI = EV / PVSPI = EV / PVSPI = $3,600 / $4,000 = 0.9 (<1, for SPI = $3,600 / $4,000 = 0.9 (<1, for
every $1 of physical work planned, every $1 of physical work planned, only $0.9 was done)only $0.9 was done)
Performance AnalysisPerformance Analysis
Estimate To Complete (ETC)Estimate To Complete (ETC)
ETC = (BAC - EV) / CPIETC = (BAC - EV) / CPI
ETC = (BAC - EV) / (CPI x ETC = (BAC - EV) / (CPI x SPI)SPI)
Performance AnalysisPerformance Analysis
Estimate At Completion (EAC)Estimate At Completion (EAC)
EAC = AC + [(BAC - EV)/(CPI x SPI)]EAC = AC + [(BAC - EV)/(CPI x SPI)] = 3,800 + [(10,000 – 3,600) / = 3,800 + [(10,000 – 3,600) /
(0.95 x 0.90)](0.95 x 0.90)] = $11,285 (high end)= $11,285 (high end)
EAC = AC + [(BAC - EV) / CPI] EAC = AC + [(BAC - EV) / CPI] = 3,800 + (10,000 – 3,600) / = 3,800 + (10,000 – 3,600) /
0.950.95 = $10,537 (low end)= $10,537 (low end)
Performance AnalysisPerformance Analysis
To Complete Performance Index To Complete Performance Index (TCPI)(TCPI)
TCPI = (BAC - EV) / (BAC - AC)TCPI = (BAC - EV) / (BAC - AC)
TCPI = ($10,000 - $3,600) / ($10,000 TCPI = ($10,000 - $3,600) / ($10,000 - $3,800)- $3,800)
TCPI = $6,400 / $6,200TCPI = $6,400 / $6,200
TCPI = 1.03TCPI = 1.03
Analyzing Data for TrendsAnalyzing Data for Trends
$0
($5)
($10)
($15)
($20
$5
$10
Cost Variance
Schedule Variance
Earned Value AnalysisEarned Value Analysis
CPI
SPI
EAC ($7.5 M)
EAC $9.5 M
Time
Baseline BudgetCPI & SPI = 1
1.0
Performance ReportPerformance Report
Actual Cost Baseline Actual % Compl Earned Value P lanned P lanned % Planned Value
(AC) (BAC) % Wt. % Compl by Wt (EV) % Compl Compl by Wt (PV)
Total - Manage $96,533 $185,243 1.8% 66.7% 1.2% $126,051 66.7% 1.2%
Total - Engineer $422,574 $38,438 0.4% 100% 0.4% $38,438 100% 0.4%
Total - Construct $3,575,578 $9,969,624 97.8% 43.0% 42.1% $4,294,051 68.5% 67.0%
Grand Total $4,094,685 $10,193,305 100.0% 43.7% $4,458,540 68.6% $4,531,495
EARNED VALUE ANALYSIS:
Schedule Variance (SV) = (EV) - (PV) = -$72,955 (1.7 % behind schedule)
Cost Variance (CV) = (EV) - (AC) = $363,855 (spending 8.1% less than w ork performed)
Schedule Perform Index (SPI) = (EV) / (PV) = 0.98 (Progressing only 98% of the rate originally planned)
Cost Performance Index (CPI) = (EV) / (AC) = 1.09 (Getting 9% more w ork done than the planned cost )
Estimate at Completion (EAC) = AC+[(Tot Budget-EV)/(CPI*SPI)] = $9,447,623To Complete Perf Index (TCPI) = (Tot Budget - EV)/Funds Remain = 0.94
Float and Management ReservesFloat and Management Reserves
The project manager should control The project manager should control contingency reserve and schedule floatcontingency reserve and schedule float
The work at hand expands to fill The work at hand expands to fill the time availablethe time available
Expenditures will rise to meet the Expenditures will rise to meet the budget.budget.
The remaining “management The remaining “management reserves” should be added to EAC reserves” should be added to EAC until such time when the reserve is until such time when the reserve is no longer needed.no longer needed.
Earned Value Management Earned Value Management SystemSystem
Performance ManagementPerformance Management Accurate Baseline EstimateAccurate Baseline Estimate Measure Performance against Measure Performance against
the Planthe Plan Analyze variances to PlanAnalyze variances to Plan Assess impacts to Overall Assess impacts to Overall
PlanPlan Identify corrective actionsIdentify corrective actions Implement the corrective Implement the corrective
actionsactions
Questions?Questions?