Earned Value Management

15
Earned Value Management Earned Value Management Pranay Srivastava Pranay Srivastava Mar 2008 Mar 2008 Agenda Earned Value Management EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.

description

Earned

Transcript of Earned Value Management

Page 1: Earned Value Management

Earned Value Management Earned Value Management Pranay Srivastava Pranay Srivastava

Mar 2008Mar 2008

Agenda

� Earned Value Management � EVM Introduction

� Base Data

� Summary Data

� Forecast Data

� EVM in Practice.

Page 2: Earned Value Management

Agenda

� Earned Value Management � EVM Introduction

� Base Data

� Summary Data

� Forecast Data

� EVM in Practice.

EVM History� 1967 DoD Instruction Cost/Schedule

control system criteria

� 1987 PMI recommends EVM

� 1997 DoD Regulation 5000.2R on EVM

� 1998 ANSI/EIA 748 adopts EVM.

Page 3: Earned Value Management

What is EVM� Best practices focusing on process, people & tools for project tracking and control

� Integrates� Technical performance (status of work)

� Schedule performance

� Cost performance

� When used to its full extent, it allows � Measuring performance

� Analyzing variance

� Developing forecasts.

Advantages of EVM

� Easy to understand

� Low overhead

� Integrates cost and schedule

� Based on results

� Simplifies status reporting

� Reliable prediction

� Well proven.

Page 4: Earned Value Management

Disadvantages of EVM

� Doesn’t address critical path

� Deterministic

� Can drive wrong behavior

� Doesn’t account quality

� Can’t handle management reserves

� Doesn’t reveal the cause.

Type Of Data

� Base Data� Data ONLY for the current period

� Summary Data� Derived data based on the base data

� Rolled-up data till date

� Indicates the current health of the project

� Forecast Data� Project forecast/estimate based on summary data.

Page 5: Earned Value Management

Agenda

� Earned Value Management � EVM Introduction

� Base Data

� Summary Data

� Forecast Data

� EVM in Practice.

Base Data

� Total Budget (BAC)� Total planned value for the project

� Planned value (PV)� Estimated effort/cost for all tasks planned to be completed in the period

� Earned value (EV)� Planned effort/cost for all tasks completed during the period.

Page 6: Earned Value Management

Base Data

� Actual Cost (AC)� Actual effort/cost incurred on all tasks completed during the period

� Total Spent (TS)� Actual effort/cost incurred on all tasks to date, regardless of whether the task has been completed or not.

Base Data

� Assume today is 22nd Feb; Task A, B, C, D are complete, E is in-progress, and F not yet started

Total

1025-feb-2008F

3*520-Feb-2008E

131015-Feb-2008D

7510-Feb-2008C

14105-Feb-2008B

551-Feb-2008A

TSACEVPVSchedule DateTask

Page 7: Earned Value Management

Agenda

� Earned Value Management � EVM Introduction

� Base Data

� Summary Data

� Forecast Data

� EVM in Practice.

Summary Data

� Cost Variance (CV)� Difference between Earned Value and Actual Cost i.e. EV – AC

� Cost Performance Index (CPI)� Ratio of Earned Value and Actual Cost (EV/AC)

� <1.0 indicates project will be over budget

� >1.0 indicates project will be under budget

� = 1 indicates project will finish on-budget.

Page 8: Earned Value Management

Summary Data

� Schedule Variance (SV)� Difference between Earned Value and Planned Value i.e. EV – PV

� Schedule Performance Index (SPI)� Ratio of Earned Value and Planned Value (EV/PV)

� <1.0 indicates project will be delayed

� >1.0 indicates project will finish before time

� = 1 indicates project will finish on-time.

Summary Data - Emerging Trend

� Why required� SV/SPI are measure of work scope not time

� At end of project, SV = 0 & SPI = 1

� Time Based Schedule Variance� Difference between Planned Time and Actual Time

� SV(t) = Planned Time – Actual Time

� Time Based Schedule Performance Index� Ratio of Planned Time and actual Time

� SPI(t) = Planned Time / Actual Time

Page 9: Earned Value Management

Summary Data

� Assume today is 22nd Feb; Task A, B, C, D are complete; E is in-progress, F not yet started

Total

10F

3*5E

1310D

75C

1410B

55A

SPISVCPICVTSACEVPVTask

Agenda

� Earned Value Management � EVM Introduction

� Base Data

� Summary Data

� Forecast Data

� EVM in Practice.

Page 10: Earned Value Management

Forecast Data

� Estimate To Complete (ETC)� Estimated effort/cost to complete all pending scheduled tasks

� Project ETC� Team's estimate of effort/cost required to complete all scheduled tasks (valid when earlier estimations are no longer valid)

� Statistical ETC� ETC = (BAC – EV) assuming similar variance will not occur in future

� ETC = (BAC-EV)/CPI assuming similar variance will occur in future.

Forecast Data

� Estimate At Completion (EAC)� Estimated effort/cost incurred to complete all scheduled tasks

� Project EAC� Team's estimate of total effort/cost to complete all scheduled tasks

� Project EAC = Total Spent + Project ETC

� Statistical EAC� EAC = Actual Cost + (BAC-EV)

� EAC = Actual Cost + (BAC-EV)/CPI.

Page 11: Earned Value Management

Forecast Data - Emerging Trend

� Future cost performance is assumed to be same as past 3 periods cost performance

� EAC = AC + ( BAC - EV)/ ((EVi+EVj+EVk)/ACi+ACj+ACk)

� Future cost performance is assumed to be also influenced by schedule performance

� EAC = AC + ( BAC - EV)/ (CPI*SPI)

� Future cost performance is assumed to be influenced by both cost & schedule performance in some ratio (x,y)

� EAC = AC + ( BAC - EV)/ (x CPI + y SPI)

Forecast Data - Emerging Trend

� Time Estimate At Completion (EACT)� Approx time incurred to complete all scheduled tasks

� An emerging trend in EVM that uses time-based measure of schedule as an alternative or supplement to traditional work-based measure

� Statistical EACT� EACT = BAC/SPIat current trend.

Page 12: Earned Value Management

Forecast Data

� Variance At Completion (VAC)� Forecasted variance between Total Budget and Estimate At Completion

� Project VAC� Team's forecasts of difference between budgeted and actual cost for all tasks

� Project VAC = Total Budget - Project EAC

� Statistical VAC� Statistical VAC = Total Budget - Statistical EAC.

Forecast Data

� To Complete Performance Index (TCPI)� Forecasts how efficient the project team needs to be to complete the project on budget

� TCPI = (Total Budget – Earned Value)

_________________________

(Total Budget – Actual Cost)

Page 13: Earned Value Management

Forecast Data

� Assume today is 22nd Feb; Task A, B, C, D are complete; E is in-progress, F not yet started

Total

10F

3*5E

1310D

75C

1410B

55A

TCPI

VACEACETCSPICPIACPVTask

Agenda

� Earned Value Management � EVM Introduction

� Base Data

� Summary Data

� Forecast Data

� EVM in Practice.

Page 14: Earned Value Management

Steps in using EVM

Develop

task level

Budget

Record task

level usage

Analyze &

Forecast

performance

Measure

physical

progress

Take

corrective

action

Report

performance

� Are we ahead/behind schedule?� Schedule Variance

� How efficiently are we using time?� Schedule Performance Index

� When are we likely to finish work?� Time Estimate at Completion.

How EVM helps in Time management?

Page 15: Earned Value Management

� Are we under/over budget?� Cost Variance

� How efficiently are we using resource?� Cost Performance Index

� What is the project likely to cost?� Estimate At Completion

� What will the remaining work cost?� Estimate To Complete

� How much under/over budget will we be at end of project?� Variance At Completion.

How EVM helps in Cost management?