Early Warning System

1
They were slain that had warning, not they that took it. (Adapted from a French proverb.) For further information: MYO NAING, Phone: 076 056 0544, email: [email protected] A qualitative approach and a case-study methodology were used. Data were collected through observation, interviews and document study. Twenty five people were interviewed, three site observations were undertaken, and key pertinent documents and reports were analysed. The unit of analysis is the City of Johannesburg (CoJ) and three municipal entities, i.e. City Power, Johannesburg Water and Pikitup. Three theories are used as a theoretical framework: Ansoff‟s “weak signals theory(1975; 1979); the “four roots of service delivery problems”(Devarajan & Reinikka, 2004); and four essential elements of an EWS(UNISDR, 2005) (Figure 1). (1) To what extent does the weak signals theory contribute to the effectiveness of an M&E system by integrating its approach into an early warning system? Questions It would be hard to apply the Weak Signals Theory to an early warning system for a municipal service delivery process. However, the rational of the theory can still be applied. Findings Early warning signals exist and are noticed by some officials and staff but no mechanism or budget exists to enable the use of that knowledge. Most of the municipal problems are due to _______________ in the areas of structure, systems, planning and resource utilisation. Thus, all of the systems and structure, especially those related to planning „noise‟ need to be consolidated. Training and education programmes need to be tailored to the needs and tasks of staff. There is a need for a more competently drafted legislation that requires an M&E system to serve as an EWS, with clear and explicit guidelines. Discussion A Take Home Message References is, thus, to develop a M&E system that is incorporated with an Early Warning System (EWS) so that it can capacitate municipalities to receive advance information about potential problems, and will enable them to implement the necessary corrective interventions. The current municipal monitoring and evaluation (M&E) system is by legislation compelled to serve as an early warning system (EWS). However, it does not have all the components of an EWS and, as a result, cannot alert key players and stakeholders of developing problematic trends in municipal service delivery processes (Sejeng, 2013; Engela & Ajam, 2010). Introduction Purpose of the study Methodology The existing municipal M&E frameworks have to include an extra section, articulating the direction and guide-lines of how to integrate the EWS components into the framework, and also the budget for this. Also the EWS activities have to be allocated (see Figure 2, 3 and 4 as a sample of EWS model, system and planning). There is no consolidated risk knowledge data-base. There are signals, and people who detect and understand the signals. There is monitoring but no warning or communication. And no action is taken. The response capability has not been developed yet, systematically. Or scan the QR (Quick Response) code for my contact details The study is based on two premises: (3) How can the current M&E system of municipalities be modified and upgraded to integrate the components and characteristics of early warning system in it? (2) To what extent does the current M&E system of municipalities have the characteristics of an early warning system? (1) the current municipal service delivery performance could be improved if the early warning signals of possible problems could be detected early and used to minimise the development of problems and maximise efficiency. Two premises (2) the current municipal M&E systems do not serve as an EWS. Ansoff, I. H. (1975). Managing Strategic Surprise by Response to Weak Signals. In California management Review, Vol. XVII, No. 2. Ansoff, I. H. (1979). Strategic Management. London: Macmillan. Ansoff, I. H. (1984). Implementing Strategic Management. New York: Prentice/Hall. Devarajan, S. & Reinikka, R. (2004). Making Service Work for Poor People. In Journal of African Economies, Vol. 13(1), p. 1142- 1166. Engela, R. & Ajam, T. (2010). Implementing a Government-wide M&E System in South Africa. Washington, DC: The World Bank. Nikander, I. O. (2002). Early Warnings: A Phenomenon in Project Management. Espoo (Finland): Helsinki University of Technology Nikander, I. O. & Eloranta, E. (2001). Project management by early warnings. In International Journal of Project Management Vol. 19, Issue 7, October 2001, p. 385399. Sejeng, T. (2013). Municipal Performance M&E. A presentation presented on 10 April 2013 at the IMFO indaba: Key to sustainable service delivery. UNISDR (United Nations International Strategy for Disaster Reduction) (2005). Hyogo Framework for Action 20052015: building the resilience of nations and communities to disasters. World Conference on Disaster Reduction in Kobe, Japan, 1822 January 2005. United Nations, A/CONF.206/6. Retrieved on February 10, 2014 from http://www.unisdr.org/eng/hfa/hfa.htm. Definition: Early Warning System (EWS) A detection process that alerts key players of developing problematic trends in municipal service delivery processes that can be obviated by taking the necessary corrective interventions at an early stage. Factors affecting municipal service delivery process Normal Proactive Response Legislation: M&E has to serve as an EWS Resource misallocation Expenditure leakages Weak incentive Demand-side failure Any change taking place is preceded by some form of warning. Even on the basis of the initially inexact information some actions can be taken. Response Capability Dissemination & Communication Monitoring & Warning Risk Knowledge Early Warning System Four Essential Elements of an EWS Four Roots of Service Delivery problems Weak Signals Theory Theory to system Problems Figure 1: Conceptual and theoretical framework Environmental trends Internal trends Performance trends Issues Impact? Drop from issues list Signal strength? minor major weak Urgency? Urgency? strong Start a gradual commitment project Start a priority project urgent delayable postponable urgent delayable postponable Source: Ansoff, 1984: 366. Figure 4: Weak Signals Strategic Issue Management decision Continue to monitor Include in next planning cycle Figure 2: An early warning phenomenon in an environment of municipal service delivery process Figure 3: The sub-periods of time available between early warning and full impact of problem Source: Nikander, 2002: 86. The rest of time for the implementation of response Mobilisation time of implementation Planning and negotiation time Decision time Time available Early warning Full impact of problem Possible problems Source: Adopted from Nikander & Eloranta, 2001: 389. Moment of observation Time The time factor Time available Flow of municipal service delivery processes Processing Observer An environment of municipal service delivery processes Decision-makers Responses Decision making Communication Early warning for Municipal Service Delivery Processes Myo Naing Current domain of M&E Concept of EWS Proposed expanded territory of M&E Anticipating & mitigating problems Holding accountability, checking whether or not on the right tracts, & learning WITS SCHOOL OF GOVERNANCE FINDING: Fragmentation FRAGMENTATION Copyright © 2014 Myo Naing All rights reserved. Definition: two premises: EARLY WARNING SYSTEM The M&E concept and framework need to be re-designed to encompass and build-in the concept of the Early Warning System.

description

A research poster, on early warning system for municipal service delivery processes

Transcript of Early Warning System

Page 1: Early Warning System

They were slain that had warning, not they that took it. (Adapted from a French proverb.) For further information: MYO NAING, Phone: 076 056 0544, email: [email protected]

A qualitative approach and a case-study

methodology were used. Data were collected

through observation, interviews and

document study. Twenty five people were

interviewed, three site observations were

undertaken, and key pertinent documents

and reports were analysed.

The unit of analysis is the City of

Johannesburg (CoJ) and three municipal

entities, i.e. City Power, Johannesburg Water

and Pikitup.

Three theories are used as a theoretical

framework: Ansoff‟s “weak signals theory”

(1975; 1979); the “four roots of service

delivery problems”(Devarajan & Reinikka,

2004); and “four essential elements of an

EWS” (UNISDR, 2005) (Figure 1).

(1) To what extent does

the weak signals theory

contribute to the

effectiveness of an M&E

system by integrating

its approach into an

early warning system?

QuestionsIt would be hard to apply the Weak

Signals Theory to an early warning

system for a municipal service delivery

process. However, the rational of the

theory can still be applied.

FindingsEarly warning signals exist and are noticed by some

officials and staff but no mechanism or budget exists

to enable the use of that knowledge.

Most of the municipal problems are due to

_______________ in the areas of structure, systems,

planning and resource utilisation. Thus, all of the

systems and structure, especially those related to

planning „noise‟ need to be consolidated.

Training and education programmes need to be

tailored to the needs and tasks of staff.

There is a need for a more competently drafted

legislation that requires an M&E system to serve as an

EWS, with clear and explicit guidelines.

Discussion A Take Home Message

References

is, thus, to develop a M&E system that is

incorporated with an Early Warning System

(EWS) so that it can capacitate municipalities

to receive advance information about

potential problems, and will enable them to

implement the necessary corrective

interventions.

The current municipal monitoring and

evaluation (M&E) system is by legislation

compelled to serve as an early warning system

(EWS).

However, it does not have all the components

of an EWS and, as a result, cannot alert key

players and stakeholders of developing

problematic trends in municipal service

delivery processes (Sejeng, 2013; Engela &

Ajam, 2010).

Introduction Purpose of the study

Methodology

The existing municipal M&E frameworks

have to include an extra section,

articulating the direction and guide-lines

of how to integrate the EWS components

into the framework, and also the budget

for this. Also the EWS activities have to

be allocated (see Figure 2, 3 and 4 as a

sample of EWS model, system and

planning).

There is no consolidated risk knowledge

data-base. There are signals, and people

who detect and understand the signals.

There is monitoring but no warning or

communication. And no action is taken.

The response capability has not been

developed yet, systematically.

Or scan the QR (Quick Response) code for my contact details

The study is based on two premises:

(3) How can the current

M&E system of

municipalities be

modified and upgraded

to integrate the

components and

characteristics of early

warning system in it?

(2) To what extent does the

current M&E system of

municipalities have the

characteristics of an

early warning system?

(1) the current municipal service delivery

performance could be improved if the

early warning signals of possible problems

could be detected early and used to

minimise the development of problems

and maximise efficiency.

Two premises

(2) the current municipal M&E systems do not

serve as an EWS.

Ansoff, I. H. (1975). Managing Strategic

Surprise by Response to Weak Signals. In

California management Review, Vol. XVII,

No. 2.

Ansoff, I. H. (1979). Strategic Management.

London: Macmillan.

Ansoff, I. H. (1984). Implementing Strategic

Management. New York: Prentice/Hall.

Devarajan, S. & Reinikka, R. (2004). Making

Service Work for Poor People. In Journal of

African Economies, Vol. 13(1), p. 1142-

1166.

Engela, R. & Ajam, T. (2010). Implementing a

Government-wide M&E System in South

Africa. Washington, DC: The World Bank.

Nikander, I. O. (2002). Early Warnings: A

Phenomenon in Project Management. Espoo

(Finland): Helsinki University of Technology

Nikander, I. O. & Eloranta, E. (2001). Project

management by early warnings. In

International Journal of Project

Management Vol. 19, Issue 7, October

2001, p. 385–399.

Sejeng, T. (2013). Municipal Performance

M&E. A presentation presented on 10 April

2013 at the IMFO indaba: Key to sustainable

service delivery.

UNISDR (United Nations International Strategy

for Disaster Reduction) (2005). Hyogo

Framework for Action 2005–2015: building

the resilience of nations and communities

to disasters. World Conference on Disaster

Reduction in Kobe, Japan, 18–22 January

2005. United Nations, A/CONF.206/6.

Retrieved on February 10, 2014 from

http://www.unisdr.org/eng/hfa/hfa.htm.

Definition: Early Warning System (EWS)

A detection process that alerts key players

of developing problematic trends in

municipal service delivery processes that

can be obviated by taking the necessary

corrective interventions at an early stage.

Factors affecting municipal service delivery process

Normal Proactive

Response

Legislation: M&E has to serve as an EWS

Resource misallocation

Expenditure leakages

Weak incentive

Demand-side failure

Any change taking place is preceded by some form of warning. Even on the basis of the initially inexact information some actions can be taken.

Response Capability

Dissemination & Communication

Monitoring & Warning

Risk Knowledge

Early Warning System

Four Essential Elements of an EWS

Four Roots of Service Delivery problems

Weak Signals Theory

Theory to system

Problems

Figure 1: Conceptual and theoretical framework

Environmental trends

Internaltrends

Performancetrends

Issues

Impact?

Drop from issues

list

Signal strength?

minor

major

weak

Urgency?Urgency?

strong

Start a gradual commitment project

Start a priority project

urgent

delayable

postponable

urgentdelayable

postponable

Source: Ansoff, 1984: 366.

Figure 4: Weak Signals Strategic Issue Management decision

Continue to monitor

Include in next planning cycle

Figure 2: An early warning phenomenon in an environment of municipal service delivery process

Figure 3: The sub-periods of time available between early warning and full impact of problem

Source: Nikander, 2002: 86.The rest of time for the

implementation of responseMobilisation time of

implementationPlanning and

negotiation timeDecision

time

Time availableEarly warning

Full impact of problem

Possible problems

Source: Adopted from Nikander & Eloranta, 2001: 389.

Moment of observation Time

The time factorTime available

Flow of municipal service delivery processes

Processing

Observer

An environment of municipal service delivery processes

Decision-makers

Responses

Decision making

Communication

Early warning

for Municipal Service Delivery ProcessesMyo

Naing

Current domain of M&EConcept

of EWS

Proposed expanded territory of M&E

Anticipating& mitigating

problems

Holding accountability,

checking whether or not on the right tracts, &

learning

WITS SCHOOL OFGOVERNANCE

FINDING: Fragmentation

FRAGMENTATION

Copyright © 2014 Myo Naing All rights reserved.

Definition:

two premises:

EARLY WARNING SYSTEM

The M&E concept and framework need to be

re-designed to encompass and build-in the

concept of the Early Warning System.