EARLESS, LEGLESS, HOMELESS??
MITIGATION MEASURES THREATENED REPTILES AND GRASSLAND
BOCO ROCK WIND FARM
![Page 2: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/2.jpg)
Presenter: Nick Graham-Higgs, CEnvP, FEIANZ
Director of nghenvironmental
Environmental Representative
Boco Rock Wind Farm
![Page 3: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/3.jpg)
LOCATION: BOCO ROCK WIND FARM
![Page 4: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/4.jpg)
• Monaro Tablelands
• Elevation 900 to 1,100 metres
• 122 turbines, 114 MW
• Predicted capacity 350 GW hrs
• Stage 1 currently under construction comprises 67 turbines
• Boco Rock Wind Farm Pty Ltd is the developer
• GE Energy and Downer EDI consortium constructing stage 1
• Total project cost $361m (AUD)
STATS: BOCO ROCK WIND FARM
![Page 5: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/5.jpg)
• Received approved in 2010
• Large areas of the Endangered Ecological Community - Natural Temperate Grassland
• Provides habitat to the threatened;
Grassland Earless Dragon
Striped Legless lizard
Little Whip Snake
APPROVAL: BOCO ROCK WIND FARM
![Page 6: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/6.jpg)
NATURAL TEMPERATE GRASSLAND
![Page 7: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/7.jpg)
Striped Legless Lizard Grassland Earless Dragon
Little Whip Snake Photos provided by Allison Brunott, Downer
![Page 8: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/8.jpg)
Conditions of approval • Biodiversity offset package • Pre-construction surveys • No ground breaking works November to January • Develop harm minimisation/relocation strategy in consultation
with OEH Reptile Management Plan • Grassland reptiles required pre-construction surveys • Scalping of the top 10-20 cm • Release captured reptiles • Dragons captured in colder months sent to University Canberra
APPROVAL: CONDITIONS
![Page 9: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/9.jpg)
![Page 10: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/10.jpg)
RESULTS
• Project ecologists have captured;
Ten (10) Grassland Earless Dragons
Three (3) Little Whip Snakes
Two (2) Striped Legless Lizards
• 500 workdays by ecologists by completion of the Stage 1
![Page 11: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/11.jpg)
Photo provided by Allison Brunott, Downer
![Page 12: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/12.jpg)
DRIVERS OF EXTINCTION
• Seven (7) of the Grassland Earless Dragons held by University of Canberra
• Australian Research Council ‘drivers of extinction’
• Goal of reducing risk of extinction:
Captive breeding program
Evolutionary relationship between populations
Contribute to a release program?
![Page 13: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/13.jpg)
CHALLENGES
• Scalping following preclearance survey within:
3 weeks, May and November
3 days, February and May
• November to January exclusion of ground breaking works
![Page 14: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/14.jpg)
• Large areas scalped prior exclusion period
• Resulting environmental risks:
Erosion and sediment control
Over-clearing
Weed and pathogen ingress.
Prolonged stockpiling impacting soil health.
ENVIRONMENTAL RISKS
![Page 15: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/15.jpg)
![Page 16: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/16.jpg)
![Page 17: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/17.jpg)
![Page 18: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/18.jpg)
![Page 19: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/19.jpg)
• Minimised extent of clearing
• Prescriptive mitigations measures increased risk of impact
• Reduced harm
• Success of release program unknown
• Providing Dragons to the UC Drivers of Extinction program is a measurable outcome
SUCCESSFUL?
![Page 20: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/20.jpg)
• Prescriptive mitigation measures reduced options
• Additional methods and strategies exist:
Alternative methods to remove habitat
Utilisation of grazing
Provide option of funding research?
ALTERNATIVE APPROACHES
![Page 21: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/21.jpg)
• Mitigation strategies can introduce risk
• Approval conditions and mitigation strategies
Less prescriptive
Adaptive
Objective-orientated
LESSONS LEARNT
![Page 22: EARLESS, LEGLESS, HOMELESS?? - New Zealand Wind Energy ... · • Boco Rock Wind Farm Pty Ltd is the developer • GE Energy and Downer EDI consortium constructing stage 1 • Total](https://reader033.fdocuments.us/reader033/viewer/2022060519/604c923a399c3263ae3aa536/html5/thumbnails/22.jpg)
The author thanks the following people in providing assistance in preparation of this presentation
• Allison Brunott - Environmental Advisor, Downer
• Adrian Oakey, Manager – Boco Rock Wind Farm, CWP Renewables Pty Ltd
• Callan Wharfe, on site ecologist Total Earth Care Pty Ltd,
• Professor Stephen Sarre, University of Canberra
• Brooke Marshall, nghenvironmental
ACKNOWLEDGEMENTS