EAA483 PT1

download EAA483 PT1

of 44

Transcript of EAA483 PT1

  • 8/3/2019 EAA483 PT1

    1/44

  • 8/3/2019 EAA483 PT1

    2/44

  • 8/3/2019 EAA483 PT1

    3/44

    Types of Residential Buildings

    Flat

    Single

    Storey

    Terrace

    2-3 Storey

    Terrace

    Single

    Storey Semi

    Detached

    Low Cost

    FlatLow Cost

    House

    Cluster

    Detached

    Town

    House

    Service

    Apartment

    Condominiums

    /Apartment

  • 8/3/2019 EAA483 PT1

    4/44

    Commercial Building Sector

    Can be privately funded e.g.shopping mall, office complex

    Owner negotiate the price.

    Government funded e.g.

    Hospital, University Campuses

    Price based on lowest bid or

    design and built.

    Large in nature, required

    expertise.

  • 8/3/2019 EAA483 PT1

    5/44

    Industrial Sector

    Most of these projects are

    privately funded.

    Quality and time are the critical

    aspects in construction and

    designing of this type of

    projects.

    Timely and smooth executionof a project is the main concern

    in this industry.

    Large/complex in nature,

    required many expertise.

  • 8/3/2019 EAA483 PT1

    6/44

    Civil & Highway Sector

    Driven by social/public benefits.Most of these projects are public funded.

    The client are government agencies.

    Quality and time are the critical aspects in

    construction and designing of this type of

    projects.

    Principally, designers of these

    projects are civil engineers. Builder

    are normally the lowest bidcontractors. However, for some

    projects, client will shortlist few

    contractors based on their previous

    project experience, expertise and

    management and financial

    capabilities to complete the project.

  • 8/3/2019 EAA483 PT1

    7/44

  • 8/3/2019 EAA483 PT1

    8/44

    Town

    Planner

    Owner

    ContractorEngineers

    Architect

    Sub-

    Contractor

  • 8/3/2019 EAA483 PT1

    9/44

    Clients Duties

    To frequently consult the

    consultant and contractorTo find a suitable designengineer for the project

    To give approval if any changesare made to the design or

    specification of the project

    To state the specificationof the project To always monitor the progress and

    state their level of satisfaction on work

    done by the contractor

  • 8/3/2019 EAA483 PT1

    10/44

    Professional Players - Characteristics

    Extensive period of training of an intellectual manner, in

    technical/systematic/humanistic way

    Knowledge and skills vital to the well-being of the larger society

    Monopoly or near monopoly on provision of professional services

    Degree of autonomy in the work place,

    choice/judgment/creativity/skills/judgment - sophisticated work not

    entirely routine

    Regulated by ethical standards. Public good as indicated by a code of

    ethics. Acting in ethical/responsible ways as individuals andinstitutions.

  • 8/3/2019 EAA483 PT1

    11/44

    Architect

    To Produce designs by

    referring to clients

    requirementsTo produce constructionplan/drawing

    To plan and overview

    tenders

    To monitor work

    progress

    Timely, to monitor the design to fulfill

    the regulations requirements

    building codes, zoning laws, fire

    regulations, and other ordinances,

    such as easy access by physically

    challenged individuals

    To apply certificate

    of fitness from the

    authority

    To provide pre-design

    services conducting

    feasibility, selecting a

    site, or specifying the

    requirements the

    design must meet

  • 8/3/2019 EAA483 PT1

    12/44

    Civil

    Engineer

    Supervise

    infrastructure works

    according to

    specifications

    Obtain permission for

    machine works, during

    work and guarding work

    for contractors

    Prepare civil and structural

    construction drawing

    Precede structural

    works according to

    specifications of the

    structural drawings

    Explain the flow of workbetween subcontractor and

    main contractor

    Supervise earthwork

    according to

    specifications

    Detail report of work

    progress, supervise

    concrete work and

    do the test report

  • 8/3/2019 EAA483 PT1

    13/44

    M & E

    Engineer

    Detail record of work

    progress and new

    construction work

    progress

    Prepare mechanical and

    electrical construction

    drawing

    Explain the mechanical

    and electrical problems

    Supervise mechanical

    and electrical works and

    ensure it follows the

    design specification

    Get the solution on electricalproblems such as lack of power

    supply

    Explain flow of work

    between subcontractor

    and main contractor

    Discuss with main contractor

    and subcontractor about

    costing building system e.g.

    elevators, escalator, electrical

    system, cooling system

  • 8/3/2019 EAA483 PT1

    14/44

    Builders construct a project according to theapproved drawings drawn by architect & engineer

    SurveyorsLand SurveyorSite surveying

    Site boundary

    Quantity SurveyorFinancial Management

    Bill of Quantities

    Obtaining Tenders

    Contract Administration

    Account preparation

    Cost monitoring

    ConstructorsResponsible for

    construction activities

    e.g. construction,

    extension, installation,

    repair, maintenance,

    renovation, demolition

    Register with CIDB (Act

    Part VI)

    A person who undertake

    to carry out & complete

    any construction works

    Manage the project &

    subcontracts

    Keep on schedule

    Control costs

    Coordinate project team

    members

    Specialty

    Contractors

    Largest portion of

    construction industry

    Skilled construction

    workers (act 520)

    Have their own specialty

    Hired and work directly

    for main contractor

    Can be award contract

    directly from client

    Nominated subcontractor

  • 8/3/2019 EAA483 PT1

    15/44

    Specialty Contractors

    Metal

    Worker

    Carpenter

    Bricklayer/

    Mason

    Plasterer

    Drain

    Layer

    Welder

    Licensed

    Electrician

    Tiler

    Plumber

    Joiner

    Painter

    Concretor

    Constructor

    plant

    operator

    Bar-bender

  • 8/3/2019 EAA483 PT1

    16/44

    Other ParticipantsThere are two other bodies/agencies that play an important role in

    construction project.

    Town Planner responsibility

    Organised, control and plan for land

    development and land acquisition includingbuildings within an area

    Work, help and encourage the collection,

    maintenance and publishing of statistics,

    bulletin and monograph, related with town

    and suburb planning & methodology

    Carry out other task given by Pihak

    Berkuasa NegeriorJawatankuasa

    Perancang Negeri

    Local Authorities

    Bodies who represent the interests

    of public safety

    To ensure that the design of project

    comply with the required standardsand guidelines

  • 8/3/2019 EAA483 PT1

    17/44

    List of Local Authority Involved in Construction Industry

    No Local Authority Main Role

    (i) BOMBA Fire hydrant approval

    (ii) IWK Sewerage approval

    (iii) DOE EIA, EMP

    (iv) PWD Pilling, earthwork approval, TIA

    (v) DID Drainage System, ESCP

    (vi) Municipal Council Earthwork approval, Building

    (vii) Pejabat Tanah Land acquisition

    (viii) JBA Water reticulation

    (ix) TNB Electrical approval

    (x) TM Cable approval

  • 8/3/2019 EAA483 PT1

    18/44

  • 8/3/2019 EAA483 PT1

    19/44

    Flow of Technical Information

    DEVELOPER/

    OWNERCONSULTANTS CONTRACTOR

    ARCHITECT

    CIVIL &

    STRUCTURAL

    ENGINEER

    MECHANICAL

    ENGINEER

    ELECTRICAL ENG

    QUANTITY

    SURVEYOR

    BUILDING CODE &

    SPECIFICATION

    Needs

    Solutions

    Design

    Drawings

    Construct

    Zoning Permit

    Design &

    Drawings

    Inspection

    Bills of

    Quantity

  • 8/3/2019 EAA483 PT1

    20/44

    Types of Drawings

    TENDER DRAWINGS

    CONTRACT DRAWINGS

    CONSTRUCTION

    DRAWINGS

    AS-BUILT DRAWINGS

    Set of engineering drawings which

    together with the other tender

    documents, bills of quantities,specification, etc., will describe the

    scheme to the contractor so that he can

    workout the price to construct .

    Are for working or building

    purposes and must, therefore,

    represent the engineers lastthough of construction.

    A legally binding contract after

    appointment of contractor. The

    contracts drawings can be the

    same as tender drawings. If

    alternative proposals have been

    accepted, new additional drawings

    will have to be prepared.

    A set of completion drawings.

    Any changes from construction

    drawings will be recorded in as-

    built drawings and these

    represent actual constructiondetails.

  • 8/3/2019 EAA483 PT1

    21/44

    Specification

    Classes of specifications

    i. Construction Specification

    ii. Military or Federal Specification

    iii. Engineering or Equipment Specification

    Contract & Specifications

    i) The connections between a contract and its engineering specifications arein the areas of meeting requirements for durability, safety and necessaryinformation, use of codes and standards and expert assistance.

    ii) The connections between engineering and administrative specifications arein the areas of paperwork directly related to the building (that is, concerningdesign, testing, procedure, records, instructions and manuals).

    iii) The connections between contracts and administrative specifications are inthe areas of contractual provisions related to management of the project and

    terms of payment.

    C i b C & S ifi i

  • 8/3/2019 EAA483 PT1

    22/44

    Connection between Contract & Specifications

    Contracts

    Engineering

    Specification

    Contractual Provisions

    Related to Building

    Design

    Paperwork Directly

    Related to the Building

    Administrative

    Contractual Provisions

    Related to Management

    of the Project

  • 8/3/2019 EAA483 PT1

    23/44

    Levels of Specifications in Construction Project

    INDUSTRY & GOVERNMENT

    Facility Requirements

    CONTRACTORS

    Construction Tooling Specifications

    Assembly Specifications

    Material Specifications

    ARCHITECT/ENGINEER

    Construction Specifications

    Equipment Specification

    Material Specifications

    BUILDING MATERIALS SUPPLIERS

    Process Specifications

    Cleaning Specifications

    Material Specifications

    Packaging Specifications

    PART MANUFACTURERS

    Process Specifications

    Cleaning Specifications

    Material Specifications

    Packaging Specifications

    Examination & Shop Test Specifications

  • 8/3/2019 EAA483 PT1

    24/44

    Bills of Quantities

    Nature of Bills

    Comprise a list of items of work which are briefly described

    Provide a measure of the extent of work and allows the work to be pricedThe work included in the item is defined in detail by the rules in the Method of Measurement

    Item description is therefore brief to allow the relevant rules of the method to be identified

    The measurement may be a single item or number, dimension (linear meter, square meter, cubic

    meter), time (hours, weeks) or weight

    Method of Measurement

    BQ required to be prepared using rules in a specified Method of Measurement Standard Methods of

    Measurement are now commonly available and used

    The Method of Measurement will divide the work into categories for building industry, the division is

    usually based on different trades

    Practice in the Building Industry

    The item description simply identifies the extent of the work priced, but the detailed requirements areto be found in the Specification and Drawings

    In Contract Document the specification of the works is included in the Bills of Quantities in the form of

    lengthy preambles

  • 8/3/2019 EAA483 PT1

    25/44

    Functions of BQ

    BQ to serve a

    number of

    functions

    An estimate measure of the

    work for the tendered price, to

    be used to achieve a revised

    contract price once the actual

    quantities of work carried out

    are measured. It is the

    remeasured form of contract.

    A basis to measure the

    value of work

    completed for interim

    payments.

    A breakdown of the

    tendered price, with no

    contractual status, but

    providing information for

    the selection from

    tenderers.

    A schedule of rates (SOR)

    as the contract basis for

    valuing variations in the

    work

  • 8/3/2019 EAA483 PT1

    26/44

    Standard Forms

    The standard Forms of contract normally used for civil engineering adopt the bills of

    quantities for re-measurement. In the building industry, the price is normally a lump

    sum and the bills are intended to be simply a guide to allow the price to be

    determined. All forms use the rates and prices in the bills as a schedule of rates for

    valuation of variations. In Contract Document, Bills of Quantity consists of :

    Preamble to Bill of Quantities

    Bill 1: Preliminary

    Bill 2: Civil & External Works

    Bill 3: Building Works

    Bill 4: Mechanical & Electrical Works

    Bill 5: Prime Cost and Provisional Sum

  • 8/3/2019 EAA483 PT1

    27/44

  • 8/3/2019 EAA483 PT1

    28/44

    Contract Overview

    In construction, contract consists of written agreements signed by the contracting

    parties (mainly an owner and a contractor) which bind them, and it defines

    relationships and obligations. If any one party fails to fulfill their part of the

    agreement, then the other party can seek compensation.

    A contract must involve a consideration or payment. A consideration is defined as an

    act, or promise by one party with another that constitutes the price for which they

    buy the promise of the other. Consideration is governed by three main elements:

    Valuable consideration The act, forbearance or promise must have some economic

    value. Good consideration (such as moral duty) is not sufficient to render a promise

    enforceable.

    Sufficient consideration Consideration must be sufficient but need not be

    adequate. This means that there must be some economic value, but it need not be

    realistic.

    Movement of consideration Consideration must move from the promise. For

    example, if X promises to give Y RM10000 in return for Y placing a contract with Z, Z

    cannot enforce Ys promise, as Z has supplied no consideration for it.

  • 8/3/2019 EAA483 PT1

    29/44

    Contract Overview (cont.)

    A contract should fulfill three functions,

    a) Normal performance A contract should define what is expected from each

    party and how their performance may be allowed to vary under certain

    circumstances within contract.

    a) Sharing of risk As we have seen, contracts involve risk. The seller, especially, is

    exposed to considerable risk. A contract should define how risk is to be shared

    between parties.

    a) Coping with problems We hope that our contracts will work perfectly, but they

    often involve problems. The contract should define how the more predictableproblems are to be dealt with.

  • 8/3/2019 EAA483 PT1

    30/44

    Contract Overview (cont.)

    For a contract to be valid,

    There must be an intention to create legal relationships

    The contract must be legal

    It must not be contrary to public interest

    It may be written or verbal

    It may be signed or sealed

    The parties must have the capacity to contract

  • 8/3/2019 EAA483 PT1

    31/44

    Types of ConstructionContract

  • 8/3/2019 EAA483 PT1

    32/44

    Types of Construction Contract

    Lump Sum

    Concession

    Design &

    BuiltCost Plus

    Unit PriceConstruction

    Contract

  • 8/3/2019 EAA483 PT1

    33/44

    Lump Sum Contracts

    Suitable if the scope and schedule of the project are sufficiently defined to allow

    the consulting engineer to estimate project costs e.g. building type projects.

    Required detailed planning and design prepared complete plans and specification

    for tender documents. Clearly define scope of work desired, the specification and

    level of quality desired.

    Need to appoint architect & consultants to prepare the drawing and specifications.

    After plans have been finalized and approved by the client, then the tender will be

    opened for bidding.

  • 8/3/2019 EAA483 PT1

    34/44

    Lump Sum Contracts (cont.)

    Lump sum contract can be implemented in three different ways,

    i. Lump Sum through Drawings This contract is normally for the project that requires

    early completion. The drawings provided is not very detail for contractors to get an

    accurate measurement for cost estimating. Thus, contractors are liable to a greater

    risk.

    ii. Lump Sum through Drawings and Bill of Quantity (BQ) - This contract is typically for

    projects valued more than RM1 million. Contractors are able to estimate the project

    cost accurately with the help of BQ provided together with the drawings. This

    contract also facilitates the client in making progress payment and can clearly justify

    any variation order or additional order placed by them.

    iii. Lump Sum through Drawings and Price Rate Schedule This contract is normally for

    projects which do not have enough time for document preparation. Price of the

    project is quoted by the contractor. Sometimes, this contract is used for maintenancejobs of buildings. It can be categorized into two types of contract or Firm Price

    Contract.

  • 8/3/2019 EAA483 PT1

    35/44

    Lump Sum Contracts (cont.)

    Selection of contractor will be made by the owner.

    A specific Lump Sum price is determined through competitive bidding by two ormore contractors.

    The contractor with the lowest bid price would normally be awarded the contract.

    If the lowest bid proposal received is within the construction budget then theLump Sum contract can begin.

    However, if the lowest bid proposal is over the budget, then it may be necessary toconduct Value Engineering process calling the selected bidder and consultants to ameeting Tender Evaluation Meeting the price will be adjusted & recalculated until

    the project cost within the budget.

  • 8/3/2019 EAA483 PT1

    36/44

    Unit Price Contracts

    Unit price contracts are used for work where it is impossible to calculate the exact quantity ofmaterials that will be required. This kind of contract is based on estimated quantities of itemsincluded in the project and their unit prices. The final price of the project is dependent on thequantities needed to carry out the project.

    For example, the consultant estimated that 1 million cubic meters of earth needs to be moved.However, both owner and contractor know that after the earthwork has been completed, the earththat has been moved will not exactly be 1 million cubic meters as estimated by consultant. The exactquantity will vary upon completion.

    The owner needs to tell the contractor the estimated quantity before the work starts and paythem the exact measured quantity after the work is completed.

    Generally, this is contract is suitable for construction and supplier projects where different types ofitems, but not their quantity, can be accurately identified in the contract documents.

    Heavy or highway works are the best projects to use this kind of contract.

  • 8/3/2019 EAA483 PT1

    37/44

    Cost Plus Contracts

    Used in situations that make it difficult or impossible for either owner or contractor

    to predict their costs during the negotiation, tender and award process. Technically, it is

    favored where the scope of the work is indeterminate or highly uncertain and kinds of

    labor, material and equipment needed are also uncertain

    The most common form of cost plus contract is Cost Plus a Fixed Fee and Cost Plus a

    Percentage. However, between the common two forms, most owners prefer to choose

    Cost Plus Fixed Fee because it limits the profit amount for the contractor, thereby

    removing any incentive for the contractor to produce poor quality work

    Cost Plus a Percentage contracts are suitable for a very difficult situation such as

    when the time to complete the work is uncertain, but some incentive to maintain

    productivity are needed. Under this arrangement complete records of all time and

    materials spent by contractor on the work must be maintained for future reference.

  • 8/3/2019 EAA483 PT1

    38/44

    Cost Plus Contracts (cont.)

    The Cost Plus Contract may be specified as,

    Cost + Fixed Percentage Contract

    Cost + Fixed Fee Contract

    Cost + Fixed Fee with Guaranteed Maximum Price Contract Compensation is

    based on a fixed sum of money. The total project cost will not exceed an agreedupper limit.

    Cost + Fixed Fee with Bonus Contract Compensation is based on a fixed sumof money. A bonus is given if the project finish below budget, ahead of schedule,etc.

    Cost + Fixed Fee with Guaranteed Maximum Price and Bonus Contract Compensation is based on a fixed sum of money. The total project cost will notexceed an agreed upper limit and a bonus is given if the project is finished below

    budget, ahead of schedule etc.

    Cost + Fixed Fee with Agreement for Sharing Any Cost Savings Contract Compensation is based on a fixed sum of money. Any cost savings are shared withthe buyer and the contractor.

  • 8/3/2019 EAA483 PT1

    39/44

    Design and Build Contracts

    In the design and build contracts a contractor is responsible for both the design and

    construction of the project. This is the latest method being used in construction project.

    It is also the fastest method for designing and building a project.

  • 8/3/2019 EAA483 PT1

    40/44

    Design and Build Contracts

    Design & Build

    Contracts

    Advantages Disadvantages

    Single point responsibility

    easier to manage

    Client/Design and Build Contractor are

    in direct contract

    Clients financial commitment

    known from the outset

    Greater integration between design and

    construction and improved build ability

    The Design and Build Contractor has more

    control over the project delivery process

    Reduce variance

    Competition remains

    There is little scope for the client to

    make changes without substantial

    costs to the client

    The clients agent has to

    ensure the specification is met

    Performance standards are left

    to the contractor

  • 8/3/2019 EAA483 PT1

    41/44

    Concession Contracts

    The definition of the concession contract:

    A project based on the granting of a concession by a Principal, usually by a

    government to the Promoter, sometimes known as the Concessionaire, who

    is responsible for the construction, financing , operation and maintenance ofa facility over the period of the concession before finally transferring the

    facility at no cost to the Principal, a fully operational facility. During

    concession period the promoter owns and operates the facility and collects

    revenues in order to repay the financing and investment costs, maintain and

    operate the facility and make a margin of profit.

  • 8/3/2019 EAA483 PT1

    42/44

    Concession Contracts

    Concession

    Contracts

    BTO build,

    transfer, operate

    DBOT design, built,

    operate, transfer

    BOL build, operate,

    lease

    BOO build,

    own, operate

    FBOOT finance, build,

    own, operate, transfer

    BOT build,

    operate, transfer

    BOT build, operate,

    transfer

    BRT built,

    rent, transfer

    BOOST built, own,

    operate, subsidies,

    transfer

    BOD build,

    operate, deliver

    DBOM design, build,operate, maintain

  • 8/3/2019 EAA483 PT1

    43/44

    Concession Contracts

    Supply

    Contract

    Promoter

    Operators

    Users

    Investors

    Lender

    Suppliers

    Loan

    Agreement

    Shareholder

    Agreement

    Operation

    Contract

    Off-take

    Contract

    Concession

    Agreement

    Construction

    Contract

    Principal

    Constructors

  • 8/3/2019 EAA483 PT1

    44/44

    Summary of Contract Types

    No Contract Application Advantage Disadvantage1 Lump Sum Most widely used. Suitable for

    project that have sufficient

    information on scope and

    schedule.

    Fair and secure to all

    parties

    Consume a lot of time

    during the design and

    pricing stage.

    2 Unit Price For a project that is impossible to

    calculate the exact quantity of

    materials or works.

    Flexible contractual

    arrangement.

    Project may go over

    budget after job

    completed.

    3 Cost Plus Used in situations that make it

    difficult or impossible for either

    the owner or contractor to predict

    their costs during the negotiation,

    tender and award process.

    Contractors may gain

    more profits because it

    does not provide cost

    control

    High risk because a lot of

    variable are uncertain.

    4 Design & Build The fastest method for designing

    and building a project

    Faster and single point

    responsibility easier

    to manage by owner.

    Performance standards

    are left to the contractor.

    5 Concession For a project based on the

    granting of a concession by a

    Principal to Promoter, who is

    responsible for most of the work.

    Single point

    responsible. Facilitate

    government in building

    and maintaining

    facilities.

    Complicated, time

    consuming and

    expensive.