Dynamic Part-Time Shoulder Use Triggers
American Association of State Highway and Transportation Officials Committee on Transportation System Operations
Atlanta, GA
August 27, 2018
![Page 2: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/2.jpg)
2
What is Part-Time Shoulder Use?
![Page 3: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/3.jpg)
What is Part-Time Shoulder Use?
3
• Various names
– Shoulder running
– Hard shoulder running
– Temporary shoulder use
– Part-time shoulder use
• Same meaning: use of the left or right shoulders of an existing roadway for travel during certain hours of the day.
– Transportation Systems Management and Operations (TSMO) strategy for addressing congestion and reliability issues
– Preserves shoulder as shoulder during most hours of day
![Page 4: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/4.jpg)
4
What is Part-Time Shoulder Use? (continued)
• It adds capacity only when needed
• It keeps the shoulder intact for most hours of the day
• Do what is physically and financially possible
– Support decisions with analysis
• A decision to use the shoulder part-time may defer major and costly widening.
Source: Minnesota Department of Transportation
Source: Pace Bus
![Page 5: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/5.jpg)
5
Types of Part-Time Shoulder Use
• Bus-on-Shoulder (BOS) – open only to buses, usually at driver’s discretion
• Static part-time shoulder use – open to passenger vehicles during predetermined hours of operation
• Dynamic part-time shoulder use – open to passenger vehicles based on need and real-time conditions
Shoulder use typically implemented on freeways; but can be applied to arterials
![Page 6: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/6.jpg)
6
Bus On Shoulder (BOS) in Minneapolis-St. Paul
Source: Metro Transit
![Page 7: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/7.jpg)
7
Left-Shoulder Bus on Shoulder (BOS) in Chicago
Source: Pace Bus
![Page 8: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/8.jpg)
8
Bus on Shoulder (BOS) on US 9 Arterial in New Jersey
Source: TCRP Report 151
![Page 9: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/9.jpg)
9
Static Shoulder Use – US 2 in Washington State
Source: Google Maps
![Page 10: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/10.jpg)
10
Static Shoulder Use – I-66 in Virginia (Made Dynamic in 2015)
Dynamic signs over shoulder; but fixed hours of operation.
Source: Virginia Department of Transportation
![Page 11: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/11.jpg)
11
Dynamic Shoulder Use – I-66 in Virginia
Source: Virginia Department of Transportation
Source: Virginia Department of Transportation
![Page 12: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/12.jpg)
12
Shoulder Use on I-70 Mountain Corridor, Colorado
Source: Colorado Department of Transportation
Source: Colorado Department of Transportation
![Page 13: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/13.jpg)
13
Dynamic Shoulder Use – I-35W in Minneapolis
Source: Minnesota Department of Transportation
![Page 14: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/14.jpg)
14
Where is Part-Time Shoulder Use?
There are many international applications as well.
Source: Kittelson & Associates, Inc.
![Page 15: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/15.jpg)
15
2016 Federal Highway Administration (FHWA) Guide
• There is a new resource to assist State DOT’s considering part time shoulder use.
• It is a guide, not a standard, directive or policy.
• Comprehensive– Limited information on
operations: when to open and close shoulder
http://www.ops.fhwa.dot.gov/publications/fhwahop15023/index.htm
![Page 16: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/16.jpg)
16
Current Research: “Triggers” for Dynamic Shoulder Use
![Page 17: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/17.jpg)
17
Project Objectives
• Guide agencies to implement Dynamic Part-Time Shoulder Use (D-PTSU)
• Prepare internal FHWA white paper synthesizing current practices (complete)
– Domestic and International
• Prepare document with “Triggers” for D-PTSU
![Page 18: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/18.jpg)
18
Potential Triggers
• Existing and future traffic performance metrics (e.g. speed, volume, occupancy)
• Air quality and noise impacts and potential benefits
• Facility characteristics, including upstream/ downstream (lane drops, ramps, etc.)
• Typical daily traffic patterns/ composition
• Noise and air quality impacts and the timing of peak noise levels versus when the shoulder might be open to traffic
• Public acceptance, traveler expectations, and avoiding confusion with frequent opening and closing patterns
• Maintenance considerations
• Incident and emergency response scenarios
• Enforcement considerations
• Left vs. right shoulder considerations
• Availability of Advanced Traffic Management (ATM)/Intelligent Transportation System (ITS)
• Safety considerations and the importance of returning a shoulder use lane back to a traditional shoulder when not needed as a traffic management strategy
![Page 19: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/19.jpg)
19
Concept of Operational-Based Trigger
Uncongested Conditions
Predict Breakdown
Open Shoulder*
Prevent Congestion
Historical Data
Predictive Models
Best Practices
Facility-specific needs
* Assuming there are no issues with maintenance, law enforcement, environmental conditions, etc.
![Page 20: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/20.jpg)
20
Levels of D-PTSU
• Low level – D-PTSU with core hours of operation and planned deviations scheduled in advance, such as opening on a weekend, special events, etc.
• Medium level(s)
• High level – D-PTSU purely in response to roadway and traffic conditions
• Increasing real-time responsiveness to traffic
• Increasing agency capabilities/maturity
![Page 21: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/21.jpg)
21
Conceptual Application of Speed-Based Trigger
• Low-level D-PTSU: Use historical data
• High-level D-PTSU: Use real-time data
![Page 22: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/22.jpg)
22
Process to Determine Triggers
![Page 23: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/23.jpg)
23
Initial Outline of Project Report
• Chapter 1: Introduction and Dynamic Shoulder Use Installation Summary.
• Chapter 2: Decision Support Framework for Dynamic Shoulder Use.
• Chapter 3: Considerations for Opening the Shoulder.
• Chapter 4: Considerations for Closing the Shoulder.
• Chapter 5: Maintenance, Incident and Emergency Response, and Other Considerations.
• Appendix A: Fact Sheets for Dynamic Shoulder Installations Worldwide.
![Page 24: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/24.jpg)
24
Project Timeline
• Technical work completed by end of 2018
• Webinar in April 2019
• Publication in mid-2019
![Page 25: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/25.jpg)
25
QUESTIONS?
![Page 26: Dynamic Part-Time Shoulder Use Triggers · What is Part-Time Shoulder Use? 3 • Various names –Shoulder running –Hard shoulder running –Temporary shoulder use –Part-time](https://reader035.fdocuments.us/reader035/viewer/2022063006/5fb6bf403cac6c60fb473677/html5/thumbnails/26.jpg)
26
Contact Information
• Jim Hunt [email protected]
• Greg Jones [email protected]
• Pete Jenior [email protected]
• David Hale [email protected]