Dynamic Islanding: Improving Electric Service Reliability with Energy Storage
Emeka OkaforAmerican Electric Power
Nov 2nd, 2010
Funded in part by the Energy Storage Systems Program of the U.S. Department Of Energy through Sandia National Laboratories
![Page 2: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/2.jpg)
2
Project Description
• Outages on distribution system can last several hours.
• Energy Storage Systems can be leveraged to reduce impact of outages.
• Project demonstrates ability of Energy Storage to mitigate outage impact.
• Three 2-MW systems commissioned in 2009.• Demonstrated ability to provide backup power.
![Page 3: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/3.jpg)
2006 - Battery in a Substation for Capital Deferral
Installed 1MW, 7.2 MWh of NASbattery on a feeder to defer building a new substation
Daily Peak Shaving
Tyler Mountain Feeder12 kV bus
North Charleston Feeder
West Washington FeederVoltage Regulator
46kV/12kV Transformer
12/16/20 MVA
46 kV bus
![Page 4: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/4.jpg)
AEP 2006 Project – Performance Data• Scheduled trapezoidal Charge &
Discharge profiles
• Improved the feeder load factor by 5% (from 75% to 80%)
• AC Efficiency 80% - Effectively 90% due to reduced T&D losses( IEEE Transactions on Power Delivery, Vol23, NO.4, Oct 2008, pp2168-73)
+ 1.2 MW Charge
- 1.0 MW Discharge
2007
2006
2008Three Successful
Years of Peak
Shaving
![Page 5: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/5.jpg)
5
New Features in the 2009 Storage Devices:Load Following
• Increase battery life with fewer shallow discharges
• Increase availability for backup power and other valuable services
![Page 6: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/6.jpg)
6
PERCENTAGE OF CUSTOMER OUTAGES THAT MAY BE REDUCED WITH BACKUP POWER.
(AEP OHIO 2008)
0.00%10.00%20.00%30.00%40.00%50.00%60.00%70.00%80.00%90.00%
100.00%
1 2 3 4 5 6 7 8 >8
Hours
Cust
omer
s Res
tore
d
Percentage of Customers restored within 7 hours is
95.34%
Percentage of Customers restored within 7 hours is
95.34%
Assumption: excludes traditional major events and momentary outages.
New Features in the 2009 Storage Devices: Backup Power
![Page 7: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/7.jpg)
7
• 2MW, 14.4 MWh in Bluffton, Ohio
• Two other identical sites in West Virginia and Indiana (2008)
• All with dynamic islanding
2008 Projects – To Improve Service Reliability
![Page 8: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/8.jpg)
8
2MW, 14.4 MWh in Milton, WV
2008 Projects – To Improve Service Reliability
2MW, 14.4 MWh in Churubusco, IN
![Page 9: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/9.jpg)
9
Churubusco, IN:Battery Islanding Zones.
![Page 10: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/10.jpg)
10
System Normal :Grid connected. Battery disconnected.
![Page 11: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/11.jpg)
11
Fault at F8; loss of grid power. All reclosers and switches in the island open.
![Page 12: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/12.jpg)
12
Battery picks up island based on last load information.
![Page 13: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/13.jpg)
13
Grid power restored.
![Page 14: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/14.jpg)
14
Battery disconnected. Load connected back to the grid.
![Page 15: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/15.jpg)
15
Live Islanding Test Information• Test Site : Balls Gap, Milton, WV• Test Date: July 8, 2009• Island Size: 700 customers• Time to island customers: 0.5 to 2 min.• Power Outage Duration: 28 min.• Time to Exit Island: 6 sec. (not Synchronized)• Average Island Load: 0.8 MW
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia
![Page 16: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/16.jpg)
16
Islanding Data – Battery Load & Energy
Islanding period = 28 min
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia
![Page 17: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/17.jpg)
17
Old Islanding Scheme at Milton
![Page 18: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/18.jpg)
18
New Islanding Scheme at Milton
![Page 19: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/19.jpg)
19
Live Islanding Experience• NaS Storage Site : Balls Gap, Milton, WV• Outage Date: Dec 18, 2009• Outage Cause: Heavy snow• Island Size: 25 Customers (small area)• Time to island customers: 2 min.• Power Outage Duration: 2 Days• Time to Exit Island: 6 sec. (not Synchronized)• Average Island Load: 167 kW
![Page 20: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/20.jpg)
20
Lessons Learned
• Islanding automation improvement.
• Design Improvement : Scheme should work with loss of 1-MW string.
• No opportunity at other sites.
![Page 21: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/21.jpg)
21
Battery used for voltage support
![Page 22: Dynamic Islanding: Improving Electric Service Reliability with … · 2011-04-15 · Dynamic Islanding: Improving Electric Service Reliability with Energy Storage Emeka Okafor. American](https://reader031.fdocuments.us/reader031/viewer/2022013020/5ea3dfb894b1c3448357d820/html5/thumbnails/22.jpg)
22
Conclusion
• Successful deployment of energy storage systems.
• Demonstrated “Islanding”.• Automation and Design improvement.• Demonstrated load-following and voltage
support.