Dust Handbook

download Dust Handbook

of 82

Transcript of Dust Handbook

  • 8/8/2019 Dust Handbook

    1/82

    Dust Abatement HandbookAir Quality Department

    March 2010

  • 8/8/2019 Dust Handbook

    2/82

    Dust Abatement Handbook-Introductory Inormation

    i March 2010

    Introductory Information .....................................................................................................................................v

    Introduction ..............................................................................................................................................................vi

    PM-10 Nonattainment Area ..............................................................................................................................vii

    Coverage o Rule 310 ............................................................................................................................................vii

    About this Handbook ........................................................................................................................................viii

    Acknowledgements ...............................................................................................................................................ix

    Document Conventions .......................................................................................................................................ix

    Acronyms ....................................................................................................................................................................x

    Section 1 - Before Starting Work

    Getting Started .....................................................................................................................................................1-1

    Why Rule 310? ..................................................................................................................................................1-1

    Coverage o Rule 310 .....................................................................................................................................1-1

    Whats Not Covered ........................................................................................................................................1-1

    Does Rule 310 Apply? ....................................................................................................................................1-1

    Is a Permit Required? .....................................................................................................................................1-1

    A Few Essentials ...................................................................................................................................................1-2

    Beore Starting Work ......................................................................................................................................1-2

    While Your Permit is Active ..........................................................................................................................1-3

    As Your Project Nears Completion ............................................................................................................1-3

    What Activities Are Covered by Rule 310? ..................................................................................................1-4

    What is Considered a Dust-Generating Activity? ................................................................................1-4

    What Is Required Beore Commencing Work at a Project Site?...........................................................1-5

    Understand Your Obligations .....................................................................................................................1-5

    Section 2 - Dust Control Permit

    The Dust Control Permit and Dust Control Plan .......................................................................................2-1

    Applying or a Permit .....................................................................................................................................2-1

    The Dust Control Plan ....................................................................................................................................2-1

    Fees ......................................................................................................................................................................2-1

    Receiving Your Permit ...................................................................................................................................2-1

    What to Do When Your Permit is about to Expire .................. .................... .................... ................... ...2-1

    The Dust Control Plan (310 402) ..................................................................................................................2-2

    Updating the Dust Control Plan ....................... .................... ................... .................... .................... .........2-2

    Changes Made at the Initiative o the Permit Holder ................. .................... .................... ............2-2

    Table of Contents

  • 8/8/2019 Dust Handbook

    3/82

    Dust Abatement Handbook-Introductory Inormation

    ii March 2010

    Changes Required by the Department ................................................................................................2-2

    How is the Approved Dust Control Plan Used? (310 402) ..................................................................2-3

    Section 3 - Approved Training

    Dust Training (310 309 and 310)................................................................................................................3-1

    What Training is Required? ..........................................................................................................................3-1

    Who Can Provide Training? ..........................................................................................................................3-1

    Certications .....................................................................................................................................................3-1

    Authority to Direct Activities to Comply with Rule 310 ....................................................................3-2

    Section 4 - Permit Signage and Recordkeeping

    Project Inormation Signs (310 308) ...........................................................................................................4-1

    Inormation to Include ..................................................................................................................................4-1

    When to Update the Sign .............................................................................................................................4-1

    Where to Post the Sign ..................................................................................................................................4-1

    Recordkeeping (310 502) ...............................................................................................................................4-2

    What Records are Required? .......................................................................................................................4-2

    Document Retention .....................................................................................................................................4-2

    Section 5 - Accessible Areas

    Areas that are Accessible to the Public ........................................................................................................5-1

    Section 6 - Subcontractor and Block PermitsSubcontractors .....................................................................................................................................................6-1

    Subcontractor Registration .........................................................................................................................6-1

    Subcontractors are Subject to Enorcement .........................................................................................6-1

    Block Permits and Utility Responsibilities (310 404) .......................................................................6-3

    Activity Occurring at Locations Not in the Block Permit.................................................................6-3

    Enorcement ...................................................................................................................................................6-3

    Section 7 -Trackout

    Trackout Rule (310 306) ...................................................................................................................................7-1

    Trackout Clean-up Requirements .............................................................................................................7-1

    The Dierence between Trackout and Staining...................................................................................7-1

    Trackout Controls ............................................................................................................................................7-4

    Controlling and Changing Exits during Construction Phases ......................................................7-5

    Table of Contents

  • 8/8/2019 Dust Handbook

    4/82

    Dust Abatement Handbook-Introductory Inormation

    iii March 2010

    Section 8 - Stabilizing Your Site

    Control and Stabilization (310 304 and 305).........................................................................................8-1

    Pre-disturbance ...............................................................................................................................................8-1

    Work Phases ......................................................................................................................................................8-1

    Operations .........................................................................................................................................................8-1

    Control Measures on Disturbed Areas (no activity or 30 Days or Longer) .................... ............8-2

    Trespass ..............................................................................................................................................................8-2

    Section 9 - Visible Emissions

    Visible Emissions (310 303) ............................................................................................................................9-1

    On-site Visible Emission Opacity Limits ...................................................................................................9-1

    Visible Emissions Beyond the Property Line ..........................................................................................9-1

    High Wind Conditions and Visible Emissions (310 303.2) .................. .................... .................... .........9-3

    Site Operations During High Winds ..........................................................................................................9-3

    Visible Emissions Originating rom Adjacent Lands ............................................................................9-3

    Section 10 - Onsite Operations

    Unpaved Parking Lots (310 304.1) ................... ................... .................... .................... ................... .......... 10-1

    Unpaved Haul and Access Roads (310 304.2 and 305.7) .................... ................... .................... ... 10-2

    Unpaved Roads(310 304.2 and 305.7) .................... ................... .................... .................... ................... 10-3

    Trackout Control Devices (310 306.1) ................... .................... .................... ................... .................... ... 10-4

    Hauling Bulk Marterials (310 305.1-3) ................... .................... .................... ................... .................... ... 10-5

    Moving Bulk Materials ................... ................... .................... .................... ................... .................... .......... 10-5

    Storage Piles, Bulk Material Stacking, Loading and Unloading (310 304.5 and 305.5) ........ 10-6

    Open Storage Piles ................... .................... ................... .................... .................... ................... ................. 10-6

    Managing Open Storage Piles (during active use) ................... .................... .................... ................ 10-6

    Managing Open Storage Piles (inactive) .................. ................... .................... .................... ................ 10-6

    Weed Abatement (310305.8) ................... ................... .................... .................... ................... .................... 10-7

    Section 11-Permit Administration

    When is an Activity Completed? What Do I Need toDo to Close Out a Permit? (310402.c) ................. .................... .................... ................... .................... ... 11-1

    Changes in Ownership o Property .................... ................... .................... .................... ................... .......... 11-2

    Transerring a Permit ................... .................... ................... .................... .................... ................... ................. 11-3

    Changing an Address or an Element o the Dust Control Plan ................... .................... ................ 11-3

    Permit Acreage Increase .................... ................... .................... .................... ................... .................... .......... 11-4

    Permit Renewal ................. .................... ................... .................... .................... ................... .................... .......... 11-4

    Table of Contents

  • 8/8/2019 Dust Handbook

    5/82

    Dust Abatement Handbook-Introductory Inormation

    iv March 2010

    Section 12 - Inspections

    Compliance Warning Signs........................ .................... ................... .................... .................... ................ 12-1

    Specic Warning Signs ................... ................... .................... .................... ................... .................... .......... 12-1

    Inspection Rights ................. .................... .................... ................... .................... .................... ................... ....... 12-2

    Once an Inspection Begins, What Do Inspectors Look For? .................... ................... .................... ... 12-3

    A Permit ................. .................... .................... ................... .................... ................... .................... .................... 12-3

    Completed Records ................. .................... ................... .................... .................... ................... ................. 12-3

    The Approved Dust Control Plan .................... ................... .................... .................... ................... .......... 12-3

    Whether a Dust Control Coordinator is on Site ................... .................... ................... .................... ... 12-3

    Water .................. .................... ................... .................... .................... ................... .................... .................... ... 12-3

    Impacts on Sensitive Groups .................... .................... ................... .................... .................... ................ 12-3

    Subcontractors .................... ................... .................... .................... ................... .................... .................... ... 12-3

    Site Conditions .................... ................... .................... .................... ................... .................... .................... ... 12-3

    Courtesy Inspections ................. .................... ................... .................... .................... ................... .................... 12-4

    Inspection Initiative .................. .................... ................... .................... .................... ................... .................... 12-4

    Section 13 - Enforcement

    Enorcement ................... ................... .................... .................... ................... .................... .................... ............. 13-1

    Ombudsman Review ................. .................... ................... .................... .................... ................... .................... 13-2

    Administrative Hearings ................. .................... .................... ................... .................... .................... ............. 13-2

    Public Records Act Requests ................... .................... .................... ................... .................... .................... ... 13-3

    Section 14 - Test Methods

    Test Methods (Visible Emissions) ................. .................... ................... .................... .................... ................ 14-1

    Determining the Presence o Visible Emissions Crossing a Property Line ........................ ...... 14-1

    Determining Opacity o Fugitive Emissions .................. .................... .................... ................... .......... 14-1

    Test Methods (Soil Stability) ................. .................... ................... .................... .................... ................... ....... 14-2

    Soil Crust Determination (The Drop Ball Test) .................. ................... .................... .................... ...... 14-2

    Standard Test Methods or Laboratory Determinationo Water (Moisture) Content o Soil and Rock by Mass (ASTM D2216 - 05) ................... ...... 14-3

    Determining Silt Content Using ASTM Method C136-06 .................... ................... .................... ... 14-3

    Determining Silt Loading ................. .................... ................... .................... .................... ................... ....... 14-3

    Threshold Friction Velocity .................. ................... .................... .................... ................... .................... ... 14-3Threshold Friction Velocity with Rock Test Method .............................. ................... .................... ... 14-3

    Section 15 - More Helpful Hints

    More Helpul Hints .................. ................... .................... .................... ................... .................... .................... ... 15-1

    Section 16 - Resources

    Resources ................... .................... .................... ................... .................... ................... .................... .................... 16-1

    Table of Contents

  • 8/8/2019 Dust Handbook

    6/82

    Dust Abatement Handbook-Introductory Inormation

    v March 2010

    Appendices

    A Rule 310 Fugitive Dust rom Dust-Generating Operations (revised 1-27-2010)

    B Drat Guidance Document or Issuing Notices o Violation Directly toSubcontractors or to other Non-Permitted Entities Observed ViolatingRule 310 (April 18, 2006)

    C Notice to Comply Interim Policy

    D Frequently Asked Questions

    E Dust Compliance Fact Sheet (Fall 2008)

    F Permit Signage Fact Sheet

    G Gravel Pads Fact Sheet

    H Dust Control Permit Application Package

    I Permit Acreage Increase Request Form

    J Permit Cancellation Request Form

    K Permit Name Change Request Form

    L Dust Control Plan Change Form

    M Parcel Change Notication Form

    N Dust Control Recordkeeping Forms

    Sel Inspection and Control Measure Application

    Employee List o Training Certications

    Subcontractor Registration List

    O Application or Subcontractor Registration

    P Subcontractor Registration Renewal Application

    Q Subcontractor Registration Change Request Form

    Table of Contents

    Most o the above documents are directly linked in this pdversion so you can readily access the document online.

    Only those documents not accessible online are included in the

    Appendices

    http://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_sources/faqs.aspxhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Dust_Control_Brochure.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Project_Sign_Requirements.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Gravel_Pads_Instructions.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Permit_Cancellation_Request.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/NameChange.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/PlanChange.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/ParcelChange.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/resources.aspx#dust_applicationshttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/BlankSampleDailyLogV1.0-25Jun08.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/BlankSampleCertLogV1.0-25Jun08.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/BlankSampleSubcontractorLogV1.0-25Jun08.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/SUB_REG_AppForm.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/SUB_Renewal%20Applicaton.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/CHANGE_REQUEST_FORM_3.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/CHANGE_REQUEST_FORM_3.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/SUB_Renewal%20Applicaton.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/SUB_REG_AppForm.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/BlankSampleSubcontractorLogV1.0-25Jun08.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/BlankSampleCertLogV1.0-25Jun08.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/BlankSampleDailyLogV1.0-25Jun08.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/resources.aspx#dust_applicationshttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/ParcelChange.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/PlanChange.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/NameChange.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Permit_Cancellation_Request.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Gravel_Pads_Instructions.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Project_Sign_Requirements.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/Dust_Control_Brochure.pdfhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_sources/faqs.aspxhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdf
  • 8/8/2019 Dust Handbook

    7/82

    Dust Abatement Handbook-Introductory Inormation

    vi March 2010

    I there is a scene that epitomizes the West in early

    movies and song, it is that o the dusty trail. Cattle

    drives and wagon trains are accompanied by

    prevalent, pervasive dust. I there is anything that

    can be readily created in the West, it is dust.

    Today, dust (also known as particulate matter)

    is an unwelcome and unhealthy eature o poor

    stewardship o our lands. While dust rom disturbed

    lands is predictable, it is also preventable.

    The Maricopa County Air Quality Departments

    (department) Rule 310Fugitive Dust rom Dust-Generating Operations is a comprehensive set o

    regulations that, when properly implemented, will

    dramatically reduce dust emissions and improve

    air quality. The need or improved air quality or

    particulates is urgently important in Maricopa

    County.

    While air quality is oten good to excellent, the

    number o days that do not meet or approach the

    particulate air quality standard established by the

    United States Environmental Protection Agency

    (EPA) are ar too many and leave the region in non-

    attainment. The result o unhealthul air quality

    on ar too many days is the imposition o stringent

    controls designed to curtail and control emissions.

    Rule 310 is a critical element in Maricopa Countys

    strategy to achieve improved air quality, and broad

    compliance with the Rules provisions is essential.

    The department has instituted an aggressive

    program to monitor compliance with the Rule,

    and strict enorcement is leading to reduced dust

    emissions.

    Every approach to improving air quality comes with

    a learning curve. Rule 310 imposes requirements

    and opportunities or interpretation under avariety o scenarios. In developing this handbook,

    the department has reached out to those most

    aected and asked or and received their input. The

    intent o this handbook is to crat a practical guide

    oering a comprehensive overview o how the Rule

    310 is interpreted that will be useul and useda

    document that will become dog-eared and tattered

    through requent reerence.

    Introduction

  • 8/8/2019 Dust Handbook

    8/82

    Dust Abatement Handbook-Introductory Inormation

    vii March 2010

    The PM-10 nonattainment area includes a

    substantial portion o Maricopa County that

    includes most o the metropolitan Phoenix area.

    This area has been deemed a nonattainment

    area or air quality by the EPA and the Arizona

    Department o Environmental Quality (ADEQ).The PM-10 nonattainment area exceeds the

    acceptable national standard or PM-10 pollution

    levels. PM-10 (particulate matter 10 microns, or

    smaller, in diameter) includes dust, soot, and other

    tiny bits o solid material that are released into

    and move around in the air. PM-10 is produced by

    many sources, including exhaust rom cars, trucks,

    buses, and planes; industrial sources like power

    plants; ugitive dust sources like construction,

    mining, and agricultural activities; as well as uel

    combustion like the operation o replaces and

    wood stoves.

    Area A diers rom the PM-10 nonattainment area.

    Within Area A, clean-burning gasoline measures

    (emissions testing; summer and winter uel

    ormulations) are applicable. The boundary has

    been used by many other state statues, rules, and

    PM-10 Nonattainment Area

    PM-10 Nonattainment Area Map showing Area A

    ordinances (such as residential wood-burning) as the

    area o applicability or those respective regulations.

    Coverage of Rule 310

    Although Indian communities are ound within the

    borders o Maricopa County, the department has no

    jurisdiction over them, because they are considered

    sovereign nations.

    This handbook does not apply to developments in Pinal

    County.

    Additionally, normal agricultural practices are under

    the jurisdiction o ADEQ, not Maricopa County.

    Construction activities on agricultural land are subject

    to Rule 310.

    Rule 310 applies to all o Maricopa County regardless

    o whether a site is located in the PM-10 nonattainment

    area or Area A (two related but distinct designations).

  • 8/8/2019 Dust Handbook

    9/82

    Dust Abatement Handbook-Introductory Inormation

    viii March 2010

    The purpose o this handbook is to provide a practical

    guide oering a comprehensive overview o the

    departments policies and interpretations o Rule 310.

    The intent is that this guide will be useul and used.

    The handbook is organized to respond to topical

    questions and it is structured to provide answers to themost commonly encountered compliance challenges.

    The department has also produced the Dust Abatement

    Field Guide for the Construction Industry, a pocket-sized,

    quick reerence designed to provide inormation about

    how to comply with Rule 310 in the eld. While not

    as comprehensive as this handbook, the Field Guide

    is a durable, reliable, and brie summary o the most

    important points that designated site representatives

    and workers in the eld should know about Rule 310.

    Disclaimer

    This Dust Abatement Handbookand the related FieldGuide are provided to assist in better understanding

    the provisions o Maricopa County Air Quality

    Departments Rule 310Fugitive Dust From Dust-

    Generating Operations. The contents o this handbook

    and the Field Guide should not be viewed as the

    denitive statement o the Rule and how to achieve

    compliance. Where the clear language o Rule 310 and

    any ormally issued policy related to Rule 310 conicts

    with this handbook or the Field Guide, Rule 310 and the

    policy will prevail.

    The user o this handbook should clearly understand

    that the discussion contained in this document is notbinding. The Rule itsel should be relied upon or a nal

    determination o compliance. This handbook is not

    intended to serve as an alternative to Rule 310 which

    is, by itsel, the denitive statement o dust-control

    requirements.

    UpdatesThis document is expected to be updated rom time to

    time. I you identiy any area that requires clarication,

    please let us know. Send your comments to

    [email protected]. You may wish to check

    the website rom time to time to see i any revisions are

    posted.

    Where to Find the Full Text of Rule310

    Rule 310 is available online athttp://www.maricopa.

    gov/aq/divisions/planning_analysis/rules/docs/310.

    pd. Rule 310 is also an appendix to this document.

    About this Handbook

    http://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdfhttp://www.maricopa.gov/aq/divisions/planning_analysis/rules/docs/310.pdf
  • 8/8/2019 Dust Handbook

    10/82

    Dust Abatement Handbook-Introductory Inormation

    ix March 2010

    This handbook and the related eld guide were developed in 2009 in a collaborative eort between the regulated community

    and the Maricopa County Air Quality Department. The basic document was developed by an internal working group within the

    Department and review and comment was provided by an external working group. The external working group was comprised

    o members o the regulated community who will rely on the contents o this handbook and eld guide to improve compliance

    with Rule 310. Additional support was provided by Logan Simpson Design, Inc., working under contract with the department.

    Acknowledgements

    External Working Group

    Alisa Schroder, Director o Compliance

    Meritage Homes

    Adam Lebrecht, Environmental Manager

    DL Withers Construction, LC

    Amanda McGinnis, Senior Vice PresidentAssociated General Contractors

    Brian Kasitz, Project Environmental Coordinator

    Kiewit

    Cameron Flower, Senior Environmental ManagerKitchell

    Katea Ravega, Attorney at LawQuarles and Brady

    Nathan White, Environmental ManagerBeazer Homes

    Paul Haggerty, Vice President

    Lennar

    Roger Ferland, Attorney at Law

    Quarles and Brady

    Spencer Kamps, Vice President o Legislative AairsHome Builders Association of Central Arizona

    Internal Working Group

    Dennis Dickerson, Ombudsman

    Ken Hooker, Supervisor

    Monica Perrin, Inspector

    Aaron Jensen, Inspector

    Logan Simpson Design Inc.

    Wayne Colebank, RLA, Principal

    Kevin Boesch, CPESC IT, Senior Permitting SpecialistTrace Baker, Technical Publications/Document

    Development Specialist

    Brian Nething, Graphics Specialist

    Document Conventions

    When a reerence to a period o days is mentioned, it

    will mean calendar days unless otherwise specied.

    It is recommended that this document be printed in

    color to allow all graphical eatures to be seen.

    The reerence to the Control Ofcer in the document

    reers to the Director o the Air Quality Department.

  • 8/8/2019 Dust Handbook

    11/82

    Dust Abatement Handbook-Introductory Inormation

    x March 2010

    Acronyms

    Commonly Used Rule 310-Related Acronyms

    ABC Aggregate Base Course

    ASTM American Society or Testing and Materials

    ATI At the Time o the InspectionCCM Contingency Control Measure

    DCC Dust Control Coordinator

    DCP Dust Control Plan

    DG Decomposed Granite

    HPA High Pollution Advisory

    HPV High Priority Violation

    HT Haul Truck

    NOV Notice o Violation

    NTC Notice to ComplyOAC Order o Abatement by Consent

    PAAP Paved Area Accessible to the Public

    PCR Permit Cancellation Request

    PCM Primary Control Measures

    PM Particulate Matter

    PM-10 Particulate matter whose size is 10 micrometers or smaller (One micrometer is equivalent to 3.93700787 10-5 inches)

    TOCD Trackout Control Device

    TFV Threshold Friction Velocity

    TO TrackoutVE Visible Emissions

    VEE Visible Emissions Evaluation

  • 8/8/2019 Dust Handbook

    12/82

    Section 1 - Before Starting Work

  • 8/8/2019 Dust Handbook

    13/82

    Dust Abatement Handbook-Section 1 Beore Starting Work

    1-1 Marc

    Why Rule 310?

    Because air quality in the greatermetropolitan Phoenix area does notmeet air quality standards or PM-10, it

    is necessary to a have a comprehensiveprogram to control PM-10 air pollution.Maricopa Countys Rule 310 - FugitiveDust rom Dust-Generating Operations,was developed to provide part o thiscomprehensive program.

    Coverage of Rule 310

    Rule 310 is a county-wide rule andcan be enorced in any portion oMaricopa County. Rule 310 also appliesregardless o whether a site is located

    in the PM-10 Nonattainment Areaor Area A (two related but distinctdesignations).

    Rule 310 applies to any constructionactivity that results in soil disturbance.While a ew activities are exempt,a good rule o thumb is to assumethat the activity you are planning iscovered by Rule 310 until you conrmotherwise.

    The ollowing activities are denitelycovered: Land clearing using

    mechanized equipment, earthmoving,weed abatement by discing or blading,excavation, construction, demolition,bulk material handling, storageand or transporation operations,operating outdoor equipment, usingstaging areas, parking areas, haul

    and access roads, disturbing suraceareas associated with a project siteand installing initial landscapingor landscape maintenance usingmechanized equipment.

    Rule 316 - Nonmetallic MineralProcessing is another rule thatapplies a separate set o dust controlrequirements on specic activities.Although many eatures are similar,there are distinct dierences.

    Whats Not Covered?

    Although tribal communities are oundwithin the borders o Maricopa County,the department has no jurisdictionover them because they are legally

    considered sovereign nations. Note:check with tribal governments assome have their own dust controlrequirements.

    This handbook does not apply todevelopments in Pinal County.Additionally, normal agriculturalpractices are under the jurisdictiono the Arizona Department oEnvironmental Quality (ADEQ), notMaricopa County.

    Does Rule 310 Apply?

    I you are engaged in a dust-generatingactivity covered by Rule 310, the rulerequirements apply at all times (24/7).Even if you do not need to have a permit,

    the dust control provisions of Rule 310

    still apply to your project.

    Is a Permit Required?

    The threshold or a permit is based onthe amount o surace area disturbedby a project. I the area disturbed will

    meet or exceed 0.1 acre (4,356 squareeet) then a permit is required.

    Construction activities thattake place on agricultural landsare subject to Rule 310. Forexample, construction o a newood processing warehouse

    on armland would be coveredand a permit required i thesurace area disturbed metor exceeded 0.1 acre. Also,trackout originating romagricultural lands is coveredunder Rule 310 and is subjectto enorcement.

    Getting Started

    Helpful HintI in doubt, ask us. Departmentsta are available to answer yourquestions and a good place tostart is to contact the Desk DutySupervisor at (602) 506-6734.

    A tenth o an acre is a relativelysmall amount o land. Mostcustom home residentialprojects will easily all underthe criteria to have a permit.

    The opacity o dust emissionsrom dust-generatingoperations, as pictured at let,cannot exceed 20%.

  • 8/8/2019 Dust Handbook

    14/82

    Dust Abatement Handbook-Section 1 Beore Starting Work

    1-2 Marc

    What do you need to do to ensurethat a project is in compliance?The ollowing list o important Dosand Donts are intended to providea snapshot o some o the most

    signicant provisions o Rule 310. Thishandbook provides more expansivediscussions on each o these provisionsin later sections.

    Before Starting Work

    3 Understand your projectboundaries, type o work, areaswhere soil will be disturbed, locationso exits and entrances, storageareas, equipment pathsconsidereverything that could potentially

    create dust.

    3 Dont start a project that disturbsgreater than or equal to 0.1 acreuntil you have obtained a dustcontrol permit. Include paths, oottrac areas, and all other areasthat are anticipated to result in soildisturbance, in your calculations todetermine the size o the project.

    3 Plan ahead to ensure you receive yourdust control permit beore you start

    workstart the application processearly. The department may require 14days or review once an application

    is deemed complete. Also, actor intime or postal delivery o the permit.

    3 As part o the permit applicationprocess, you will be required to llout an application which includesthe Dust Control Plan. The approvedpermit and the plan must be on sitebeore you start work.

    3 Read and understand yourapproved Dust Control Plan. Duringpreconstruction meetings inorm allproject workers o Dust Control Planrequirements and ensure a successulproject start-up.

    3 Request a courtesy inspection by anair quality inspector or their presenceat the preconstruction meeting toanswer questions. One courtesyinspection is allowed or eachproject phase (generally, these aredemolition, land development, andvertical construction).

    3 Familiarize yoursel with Rule 310 andthis handbook. The Rule containsimportant details and requirementsthat may not be addressed in thehandbook. Develop a working

    knowledge o the dust controlrequirements and related challenges.

    3 I your project is 1 acre or larger in

    size, your application must identiythe soil texture ound at the site. Thesoil texture is generally ound in asoils report prepared or the projectsite (alternatively, Appendix F o the

    departments rules and regulationscontains a map o soil descriptions).

    3While trackout is prohibited or any

    The department has up to14 days to review a paid,technically complete permitapplication package.This timetable does not include

    postal delivery. Line up a DustControl Coordinator, hydrants,and control equipment tobe used at your site prior tosubmitting the applicationpackage. Consider municipalrequirements, such as backfowprevention devices andobtaining hydrant meters.

    Installing a Gravel Pad

    A Few Essentials

    Helpful HintIdeally, the Dust Control Planshould be lled out by someoneamiliar with controlling dustemissions.

  • 8/8/2019 Dust Handbook

    15/82

    Dust Abatement Handbook-Section 1 Beore Starting Work

    1-3 Marc

    size project, i the project site is 2acres or largeror you will be moving100 yd3 o material per day, establish acontrolled exit with a trackout controldevice.

    3 I your project disturbs an area greaterthan one acre, the site superintendantmust have completed the Basic DustControl Training Class within the pastthree years

    3 I your project disturbs an area veacres or larger, an on-site Dust ControlCoordinator is required. Make sureyou have lined up a certied DustControl Coordinator with a validcertication beore starting work.

    3 Ensure that you are prepared tocontrol dust prior to starting a project.(or example, secure a water sourceand be ready to apply water prior toinitiating soil disturbance).

    3 Post required project inormationsigns when the permit area is veacres or greater.

    While Your Permit is Active

    3Make sure subcontractors have acurrent registration number.

    3 Never allow on-site emissions toexceed 20% opacity.

    3 Actively monitor trackout during thecourse o the workday.

    3 Do not allow any visible dust to cross

    your property line.3 Apply water to control emissionsbeore, during, and ater earthmovingoperations (Note: additional controloptions are available).

    3 I the primary dust control measure isineective, immediately implementthe contingency measure rom yourapproved Dust Control Plan. Whilethe contingenecy measure can beapplied along with the primary

    control measure, use o both,concurrently, is not required.

    3 Document the use o the contingencymeasure in your daily log.

    3 I dust emissions cannot becontrolled, stop work.

    3 Understand and meet stabilizationstandards.

    As Your Project Nears

    Completion

    3 Know when your permit expires andplace the expiration date on yourcalendar along with the date bywhich the permit renewal applicationmust be submitted (be sure toallow enough time or processingand postal delivery). Note: the

    department has up to 14 days toprocess your complete application.I the application is not complete orerrors are present, additional time willbe required to resolve any problems.

    3 Apply or permit cancellation whenwork is completed and ensure thatdisturbed areas within the permit areaare stabilized and meet stabilizationstandards.

    A Few Essentials contd.

    Helpful HintOnce you understand the projectand the obligations o your DustControl Plan, actor dust-controlcosts into your project bid andbudget. Include the cost osignage, training, dust-controlsta, trackout control devices, andall other personnel and materialsused to control dust.

    Provide a Dust Control Plan withbid materials to subcontractors sothey understand what is requiredand can submit accurate bids.

  • 8/8/2019 Dust Handbook

    16/82

    Dust Abatement Handbook-Section 1 Beore Starting Work

    1-4 Marc

    Rule 310 regulates dust emissionsassociated with construction activities.Generally, i the surace o the groundis disturbed in some manner, or i bulkmaterials are moved rom one location

    to another or stockpiled, the potentialexists or ugitive dust emissions.Rule 310 applies to all activities thatmay result in ugitive dust emissionsand a permit is required i the area tobe disturbed is 0.1 acre or more.

    Maricopa County denes disturbanceas a portion o the earths surace ormaterial placed on the earths suracethat has been physically moved,uncovered, destabilized, or otherwisemodied rom its undisturbed nativecondition i the potential or the

    emission o ugitive dust is increasedby the movement, destabilization, ormodication.

    I you are engaged in dust-generatingoperations, no matter how small,you must control those emissionsand comply with Rule 310. I you aredisturbing 0.1 (one-tenth) acre or more,you must comply with Rule 310 andobtain a dust-control permit. One-tentho an acre is just 4,356 t.

    Examples o activities that can disturb0.1 acre include:

    3 parking ve pickup trucks next toeach other on open dirt.

    3

    staging 10 yd o aggregate base.3 driving 360 eet onto undisturbedland.

    What is Considered a

    Dust-Generating Activity?

    A primary dust-generating activity isany operation capable o generatingugitive dust, including but not limitedto, the ollowing:

    3 land clearing, maintenance, andland cleanup using mechanizedequipment.

    3 earthmoving.

    3 weed abatement by discing orblading.

    3 excavating.

    3 construction.

    3 demolition.

    3 bulk material handling (e.g., bulk

    material hauling and/or transporting,bulk material stacking, loading, andunloading operations).

    3 storage and/or transportingoperations (e.g., open storagepiles, bulk material hauling and/ortransporting, bulk material stacking,loading, and unloading operations).

    3 operation o any outdoor equipment.

    3

    operation o motorized machinery.3 establishing and/or using stagingareas, parking areas, material storageareas, or access routes to and rom asite.

    3 establishing and/or using unpavedhaul/access roads to, rom, and withina site.

    3 disturbed surace areas associatedwith a site.

    3 installing or maintaining landscapingwhile using mechanized equipment.

    Remember:

    Disturbed suraces do not haveto be contiguous (connectedto or adjacent to each other)!

    Bulk Material Pile

    What Activities Are Covered by Rule 310?

  • 8/8/2019 Dust Handbook

    17/82

    Dust Abatement Handbook-Section 1 Beore Starting Work

    1-5 Marc

    Be saeget a permit beore doinganything that will disturb the land.

    3 Apply or and receive a permit beoredoing anything that will disturb aslittle as 0.1 acre o land.

    3 Prepare a Dust Control Plan andsubmit it to the department as parto your permit application.

    3 Remember:

    R permit coverage is required oronly those areas in your permitthat will be disturbed, includingthe working area, prep areas, andparking areas. You can add areas asneeded using the Permit AcreageIncrease Request Form.

    R the dust control permit is good orone year (permits or shorter orlonger periods are not available).

    R a dust control permit is noteective until the ee is paid.

    R a dust control permit and theapproved Dust Control Plan mustbe kept on site at all times. Workcannot begin on the site until theapproved permit is received andonsite.

    R all project workers on your site,including subcontractors, shouldbe amiliar with the plan.

    3 I the site is one acre or greater,a description o the site-specicsoil designations must beprepared. (See Appendix F o theMaricopa county Air Pollution

    Control Rules and Regulations).

    The permit holder is ultimatelyresponsible or ensuring thepermitted site is in complianceat all times to prevent risks to theenvironment and the public, even

    inoncompliance is the result o anaction by an owner, subcontractor, ortrespasser.

    3 The provisions o an approvedDust Control Plan are binding andenorceablei you dont intend toimplement a provision o the plandont include it. Conversely, i youplan to take an action to control dust,ensure that action is included in yourpermit as one o your options.

    3

    The approved Dust Control Planis eective 24/7, including holidays.Thereore, dust must be controlled24/7.

    What Is Required Before Commencing Work at a Project Site?

    Become amiliar with Rule 310and its requirements.Rule 310 is available throughthe departments website at

    www.maricopa.gov/aq/divisions/planning_analysis/

    rules/docs/310-1001.pdf.

    Posted Permit

    Helpful HintAn easy way to ensure thatthe permit and approved DustControl Plan are on site at alltimes is to post a copy o thepermit document to some

    semi-permanent onsite eature.Alternatively, the permit can bekept in a more secure locationonsite. The most importantthing is to ensure that the permit

    can be produced during an

    inspection. While axing thepermit to a ence as shown inthe photo is acceptable, the sitesuperintendant should considerhaving a backup copy handyin case o vandalism or loss othe documents.

    Still need a permit even though

    your existing permit may soon

    expire?

    3 Apply or a new permit at least 14calendar days prior to expiration.Keep in mind:

    3 A new Dust Control Plan must besubmitted.

    3 A new permit number will be

    issued.

    3 The project inormation signshould be updated with the newpermit number.

    year or until the permit is closed outby the department).

    Understand Your

    Obligations

    3 The applicants signature on thedust control permit applicationrepresents a binding agreement

    and obligates the applicant toimplement identied controlmeasures on the permitted areaor the lie o the permit (i.e., one

  • 8/8/2019 Dust Handbook

    18/82

    Section 2 - Dust Control Permit

  • 8/8/2019 Dust Handbook

    19/82

    Dust Abatement Handbook-Section 2 Dust Control Permit

    2-1 This page updated June 30

    Receiving Your Permit

    The completed permit will be sent to

    the applicants address. Allow up to14 days or permit processing plus

    sucient time or delivery byU.S. Postal Service First Class mail.

    What to Do When YourPermit is about to Expire

    Still need a permit even though your

    existing permit may soon expire?

    Apply or a new permit well beore

    your current permit is about to expire.Remember to allow up to 14 days orthe department to review the complete

    application, as well as time or postaldelivery.

    Keep in mind:

    3 a new Dust Control Plan must be

    submitted with the new permit

    application.

    3 only include those areas that are

    still disturbed. Hardscaped and

    landscaped areas do not need to be

    included.

    3 a new permit number will be issued.

    3 the project inormation sign should

    be updated with the new permit

    number.

    Applying for a Permit

    The dust control permit application

    package, which contains instructionsor lling out the permit application

    orms as well as the Dust ControlPlan associated with the dust controlpermit, is located online on the

    departments website at http://www.maricopa.gov/aq/divisions/

    compliance/dust/docs/pd/DustControlPermitApplicationPackage.

    pd.

    Completed applications should besubmitted, along with payment o the

    ee, to:

    One Stop Shop

    501 North 44th Street, Suite 200Phoenix, Arizona 85008

    Include the appropriate ee or your

    dust control permit application.The completed application can besubmitted to the One Stop Shop in

    person or by mail with payment bycheck or money order. A credit card or

    cash may be used or payment i theapplication is submitted in person at

    the One Stop Shop location.

    The Dust Control PlanThe Dust Control Plan is completed bythe applicant and submitted as parto the permit application. The Dust

    Control Plan is an integral part o thepermit and is efective upon approval

    o the permit. Given its importance,consider having the Dust Control Plan

    completed by someone amiliar with

    dust-generating operations.

    Fees

    Basic ees or a dust control permit(permit valid or one year) are

    calculated on the basis o the totaldisturbed acreage (Note: this is a newee structure that went into efect on

    July 1, 2010). Fees are establishedaccording to the ollowing schedule:

    3 a late ee o $100 is required or any

    application submitted in response to

    a violation.

    The ee or a block permit is $2,000.

    Make checks payable to Maricopa

    County Air Quality Department orMCAQD.

    Permitting Administrative Process

    The Dust Control Permit and Dust Control Plan

    The applicant

    completes permit

    application, including

    the Dust Control Plan,

    and submits the

    application with the

    appropriate fee

    payment.

    The One Stop Shop

    receives the

    application, confirms

    fee payment, and

    determines if the

    application is

    complete.

    The Department

    conducts a

    technical review of

    the application

    and Dust Control

    Plan within 14

    days after

    submittal.

    The approved

    permit and Dust

    Control Plan are

    received at the

    project site and

    approved

    dust-generating

    activities can begin.

    The Control Officer

    rejects the

    application and

    contacts the permit

    applicant with

    instructions. Return

    to Step 3

    The Control Officer

    approves the

    permit and sendsthe approved

    permit and Dust

    Control Plan to the

    permit applicant.

    Step 1 Step 2 Step 3 Step 4 Step 5

    $795

    $1,325

    $3,855

    $6,425

    $9,635

    $15,415

    0.1 to less than one acre

    One acre to less than ten

    acres

    Ten acres to less than 50acres

    50 acres to less than 100acres

    100 acres to less than 500

    acres

    500 acres or greater

    http://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdfhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/DustControlPermitApplicationPackage.pdf
  • 8/8/2019 Dust Handbook

    20/82

    Dust Abatement Handbook-Section 2 Dust Control Permit

    2-2 Marc

    Helpful HintAllow at least 14 days or theDepartment to approve revisionsto the Dust Control Plan. You

    must ollow your existing,approved permit and plan until

    you have received notice rom thedepartment that your changes

    have been approved.

    permit holder requiring revisions to theDust Control Plan. The permit holdermust submit required revisions within

    3 working days o receipt o thenotice. I more than 3 working days

    are needed, the permit holder canrequest an extension. Even though

    the extension is available, it is notguaranteed that the extension will be

    granted. In any event, compliance withRule 310 is expected immediately.

    The Dust Control Plan is submitted aspart o the permit application.

    The department reviews each Dust

    Control Plan or completeness andtechnical accuracy.

    Updating the Dust

    Control PlanThe approved Dust Control Plan

    can be revised at the initiative othe permit holder oras directed by

    the department.

    Revisions to the Dust Control Plan arenot efective at time o submittalthey

    must be approved by the departmentbeore becoming efective. Changes

    to the Dust Control Plan required bythe departments control ocer mustbe submitted within 3 working days o

    receipt o the control ocers directive.

    Changes Made at the Initiative

    of the Permit HolderThe permit holder may request changes

    to the Dust Control Plan or:

    3 changes in acreage.

    3 changes in the designated Dust

    Control Coordinator and/or his or her

    contact inormation.

    3 substantive changes in operations.

    3 any change requested by the Dust

    Control Coordinator or designated

    site representative.

    3 changes to primary or contingency

    control measures

    Changes Required by the

    DepartmentAt times, dust emissions may continue

    to occur even i the control measurescontained in the Dust Control Planare ollowed. When this occurs, the

    department will issue a notice to the

    The Dust Control Plan (310 402)

    Helpful HintOPEN YOUR MAIL - otendocuments will have a deadline

    or action date included. Dontmiss critical deadlines by ailing to

    open mail rom the departmentimmediately.

  • 8/8/2019 Dust Handbook

    21/82

    Dust Abatement Handbook-Section 2 Dust Control Permit

    2-3 Marc

    Z.1 Operations

    P C Apply water (Fill out Category I, Water on pp. 37-41)

    P C Pave (Choose one of the following): Beginning of Project* During Project* End of Project**Must specify additional primary control measure(s) that will be in place prior to paving

    P C Limit vehicle trips to no more than 20 per day per road AND limit vehicle speeds to no more than 15 m.p.h. In thespace provided, list the ed access areas/haul roads each day (includingnumber of employee v water trucks) and a description of how vehiclespeeds will be restricted to no more than 15 m.p.h.:

    maximum number of vehicle trips on the unpavehicles, earthmoving equipment, haul trucks and

    C Cease operations, NOTE: This option CANNOT be considered aprimary

    P C Other:

    Or, explain why this sub-category and its control measures are not applicable

    How is the Approved Dust Control Plan Used (310 402)

    From the departments perspective, the approved Dust Control Plan is a

    contract between the permit holder and the departmentits terms areenorceable, even against subcontractors working on a site. The measures

    included in the Dust Control Plan are the measures that inspectors will expectyou to apply to your site.

    Primary controls listed in the plan are to be used rst. Contingency measuresare to be used when the primary controls are not efectively controlling dustemissions.

    I primary controls or contingency measures dont result in efective

    control, the approved Dust Control Plan must be revised. The obligation isclearly on the permit holder to control dust emissions. I emissions cannot

    be adequately controlled using all available measures, the project will be inviolation o Rule 310 and subject to enorcement by the department.

    This orm has been correctly flled out.

    P= Primary Control Measure

    The rst approach you

    implement to control dust

    emissions

    C= Contingency ControlMeasure

    The backup strategy to be

    used when the primary control

    measure is not efectively

    controlling dust emissions

    This orm has been incorrectly flled out.

    Z.1 Operations

    P C Apply water (Fill out Category I, Water on pp. 37-41)

    P C Pave (Choose one of the following): Beginning of Project* During Project* End of Project**Must specify additional primary control measure(s) that will be in place prior to paving

    P C Limit vehicle trips to no more than 20 per day per road AND limit vehicle speeds to no more than 15 m.p.h. In thspace provided, list the maximum number of vehicle trips on the unpaved access areas/haul roads each day (includingnumber of employee vehicles, earthmoving equipment, haul trucks and water trucks) and a description of how vehicspeeds will be restricted to no more than 15 m.p.h.:

    C Cease operations, NOTE: This option CANNOT be considered a primarycontrol measure.

    P C Other:

    Or, explain why this sub-category and its control measures are not applicable

    In this example, the

    orm at right is incorrect

    because ceasing

    operations has been

    marked as a primary

    control measure - a

    choice which is not

    allowed.

  • 8/8/2019 Dust Handbook

    22/82

    Section 3 - Approved Training

  • 8/8/2019 Dust Handbook

    23/82

    Dust Abatement Handbook-Section 3 Approved Training

    3-1 March 2010

    What Training is

    Required?

    Rule 310 requires certain personnel at

    a permitted site to receive training ondust control and emission reduction

    strategies. The level o required

    training and which personnel must

    be trained depends on the amount o

    acreage disturbed within the permitted

    area. The table below shows who must

    be trained and the level o training

    required by size o the disturbed area.

    Who Can Provide Training?

    The department has established an

    approved training program to certiyindividuals who have successully

    completed required training. Training

    must be given by a trainer who has

    been approved by the department.

    A list o approved trainers is available

    on the departments website at

    www.maricopa.gov/aq/divisions/

    compliance/dust/dust_control_

    training/deault.aspx.

    Trainer ProgramInterested in becoming a trainer?

    Contact the department or inormation

    on the process.

    Certifcations

    There are two levels o certication:

    basic and comprehensive.

    Basic CertifcationTo earn basic certication, individualsmust complete the three-hour training

    course. As indicated in the table,

    water truck and water haul drivers are

    required to earn basic certication.

    On projects that disturb more than 1.0

    acre, the permit holder must designate

    a site representative who has earned

    basic certication.

    In addition, a Dust Control Block Permit

    holder is required to have at least one

    individual who has received the basicdust training certication on those sites

    on which there is greater than one acre

    o surace disturbance.

    Employees required to have the basic

    dust training must renew their training

    certication once every three years.

    Dust Training (310 309 and 310)

    Dust Control Coordinators:

    Arerequiredonprojects

    that disturb ve or more

    acres

    Musthaveearnedthe

    comprehensive certication

    Mustbeidentifedin

    the dust control permit

    application (Part 2, Question

    #5)

    Mustbeonsiteduringdust-

    generating activities.

    Training Requirements By Disturbed Areas

    Comprehensive CertifcationComprehensive training is a six-hour

    training that covers dust control

    measures in detail. Individualswho complete this training earn

    comprehensive certication and

    may be designated as a Dust Control

    Coordinator.

    On projects that disturb 5 or more

    acres, the permit holder must identiy

    a certied Dust Control Coordinator

    who must be present at all times during

    primary dust-generating activities.

    A Dust Control Coordinator must

    complete the comprehensive training

    program once every three years.

    Note: Comprehensive training includes

    basic certifcation.

    Helpul HintThe need or the Dust Control

    Coordinator to be onsite during

    dust-generating activities cannot

    be over emphasized. Experience

    has shown that violations oten

    result when the Dust Control

    Coordinator is not available to

    oversee operations.

    Training Requirements by Disturbed Area Acreage*

    Personnel

    WaterTruck/

    WaterHaul

    Driver

    (Basic

    certifcation

    3-hourcourse)

    Site

    Representative

    (Basic

    certiication

    3-hourcourse)

    DustControl

    Coordinator**

    (Comprehensive

    certifcation

    6-hourcourse)

    Disturb 0.1 acre X

    Disturb 1.0-4.99 acres X X

    Disturb 5.0 acres X X

    *Areas o disturbance may include parking, staging, and stockpiling areas, aswell as driving over previously disturbed areas.

    **The permit holder must give the Dust Control Coordinator authority to actto control dust. Permit holders who do not provide this authority can receivean NOV. Dust Control Coordinators who accept work without the authorityto act to control dust can lose their certifcation.

    Visible Emission Certifcation

    Certication o Dust Control

    Coordinators is not required

    but is strongly recommended.

    http://www.maricopa.gov/aq/divisions/compliance/dust/dust_control_training/default.aspxhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_control_training/default.aspxhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_control_training/default.aspxhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_control_training/default.aspxhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_control_training/default.aspxhttp://www.maricopa.gov/aq/divisions/compliance/dust/dust_control_training/default.aspx
  • 8/8/2019 Dust Handbook

    24/82

    Dust Abatement Handbook-Section 3 Approved Training

    3-2 March 2010

    Dust Training (310 309 and 310) (contd)

    Authority to DirectActivities to Comply withRule 310

    To receive a dust control permit,the permit holder must name a

    site representative or Dust Control

    Coordinator who has the level o

    training required based on the area

    disturbed by the project (see table on

    page 3-1). I a site representative or

    Dust Control Coordinator is required

    based on the size o the project, he or

    she must be given the authority to act

    to control dust by the permit holder.

    This means the site representative or

    Dust Control Coordinator must be able

    to direct actions within an area coveredby a permit to ensure compliance

    with Rule 310including ceasing

    operations, i necessary, to ensure that

    dust is not generated.

    Helpul HintCourtesy inspections and

    industry presentations given

    by department staf represent

    another opportunity or training.I you organize an event such as

    a gathering o your rms project

    superintendants, it is possible to

    schedule an inspector to provide a

    presentation on aspects o

    Rule 310.

    Note: industry presentations

    are ree o charge but do not

    take the place o ormal training

    certications.

    Only approved trainers can provide certifed dust control training

    The departments director

    has the authority to suspendor revoke the Basic or

    Comprehensive Dust Control

    certication or cause. For

    cause means:

    3 inappropriate ethical activities

    or conduct associated with the

    dust control program or

    3 repeated ailure to ollow

    training requirements

    Remember:

    3 trained site representatives are

    required on projects that disturb 1.0-

    4.99 acres; must be designated on the

    dust control permit; and must havebasic certication.

    3 dust Control Coordinators are

    required on projects that disturb ve

    or more acres, must be designated

    on the dust control permit, and must

    have certication or attending the

    Comprehensive Dust Control training.

    3 permit holders who do not give site

    representatives and Dust Control

    Coordinators authority to act are

    subject to enorcement underRule 310.

    3 a Notice o Violation can be issued i

    a Dust Control Coordinator does not

    have ull authority to ensure that dust

    control measures are implemented

    on site.Helpul HintMaintain a legible photocopy

    o the certication card or each

    trained personnel member in a

    le or binder located onsite so

    that it is accessible during aninspection.

    o the project but there are additional

    permitted, yet undisturbed, phases

    waiting to be developed.

    In this scenario, a Dust Control

    Coordinator would be required onsite

    unless the undisturbed phases were

    clearly identied in the dust control

    permit, as well as the Dust Control

    Plan, and the undisturbed area on

    the project site was clearly marked

    with access restricted to those project

    phases not yet active.

    When ewer than ve acres o land (in

    all phases o the project) remain to

    be disturbed, then the Dust Control

    Coordinator requirement would no

    longer apply i previously disturbed

    areas have been stabilized and notice

    o stabilization has been provided to

    the department.

    A Dust Control Coordinator is required

    whenever the disturbed area reaches

    or exceeds ve acres. In some

    instances, a permit area may develop

    such that ewer than ve acres odisturbed surace remain in one phase

  • 8/8/2019 Dust Handbook

    25/82

    Section 4 - Permit Signage and Recordkeeping

  • 8/8/2019 Dust Handbook

    26/82

    Dust Abatement Handbook-Section 4 Permit Signage and Recordkeeping

    4-1 March

    Project Information Signs (Rule 310 308)

    Information to Include

    For sites permitted at ve acres or more,

    the project inormation sign must

    contain the inormation shown below

    (using text size o at least our inches)and be placed at the main entrance o

    the site:

    3 project name.

    3 permit holders name.

    3 current dust control permit number.

    3 name and local phone number o

    person(s) responsible or dust control.

    In addition, your sign must include the

    ollowing text:

    Dust Complaints?Call Maricopa County Air Quality

    Department

    (602) 372-2703

    Should the ocial complaint phone

    number ever change, the department

    will send a notice to all permit holders

    providing the new number.

    When to Update the Sign

    You must change your project

    inormation sign to refect changes to

    the dust control permit or Dust Control

    Plan, such as:

    3 a new contact name or phone

    number.

    3 a change in the project name.

    3 a new permit number.

    Where to Post the Sign

    The main entrance to a site is that

    which would normally be used by

    employees and subcontractors when

    gaining site access. As a projectmatures, an additional entrance may be

    established.

    The purpose o the signage

    requirement is to provide the

    public with inormation about the

    permit status o the project, and the

    sign should be posted where that

    inormation is most prominently

    observed by members o the public.

    The project sign requirement is based

    on the original acreage permitted. A

    sign is still required even i a project isreduced to under ve acres.

    Permit Sign Example

    ACME ESTATES, AZ123 DEVELOPMENT

    PERMIT NUMBER 144501

    CONTACT: ANITA PERMIT (602) 000-000

    DUST COMPLAINTS?CALL THE MARICOPA COUNTY

    AIR QUALITY DEPARTMENT

    (602) 372-2703

    Helpful HintDont orget to change the project

    inormation sign to refect

    changes in your permit.

    For example:

    changes to the project name

    or permit holder name

    a new permit number

    contact inormation or the

    projects responsible ocial

    Helpful HintTo avoid uncertainty when

    multiple entrances are used, a

    permit holder is encouraged to

    place signs at each site accesspoint, especially where another

    project entrance is more visible

    to the public. However, only one

    sign is required by Rule 310.

    I only one sign is posted, it

    should be placed at the location

    that would be viewed by

    members o the public as the

    main entrance to the site.

  • 8/8/2019 Dust Handbook

    27/82

    Dust Abatement Handbook-Section 4 Permit Signage and Recordkeeping

    4-2 March

    What Records are

    Required?

    3 The dust control permit and all

    updates (must be on site).

    3 The Dust Control Plan and all updates

    (must be on site).

    3 Dust control logs documenting dust

    control measures used each day (must

    be available within 48 hours).

    Each day a self-inspecon by the

    permit holder must be conducted

    with notes taken to document

    observaons. This is an importantdocument and can be used to

    show that site condions have

    been carefully controlled. Crical

    informaon that is required by

    Rule 310 includes:

    3 observations o damp and crusted

    soil.

    3 trackout conditions and actions taken

    to clean up trackout.

    3 daily water usage (note how water is

    applied, how oten, and the amount -

    a rough approximation is acceptable).

    3 dust suppressant application.

    3 when street sweeping occurred.

    3maintenance o trackout controls

    (what kind and when installed).

    3 what kind and when contingency

    measures in the Dust Control Plan

    were used.

    3 what subcontractors were on site,

    include registration numbers.

    3 a list o employees who have

    completed dust control training,

    the date o the class, and the name

    o the company or person who did

    the training. Keep copies o training

    certicates on le.

    3 all supporting documentation (e.g.,

    street sweeping or water truck

    receipts).

    3 types and results o all test methods

    conducted.

    Document Retention

    Records must be retained consistent

    with the following meframes and

    whichever is longer will apply:

    3 two years rom the date the record

    was initiated, as long as operations

    are ongoing. For example, a ve-year

    project only needs a two-year record

    log.

    3

    all records must be retained orsix months ollowing termination o

    site operations.

    Recordkeeping

    (Rule 310 502)

    Helpful Hints3While no exact ormat is prescribed or recordkeeping, a three-ring binder is recommended or paperrecords.

    3 Electronic recordkeeping, used by some permit holders, is a valid orm o recordkeeping.

    3 A scanned copy o the Dust Control Permit accessible on a computer is an acceptable way to maintain an

    on site copy.

    Water Meter

  • 8/8/2019 Dust Handbook

    28/82

    http://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/CompletedSampleDailyLogV1.0-25Jun08.pdf
  • 8/8/2019 Dust Handbook

    29/82

    Section 5 - Accessible Areas

  • 8/8/2019 Dust Handbook

    30/82

    Dust Abatement Handbook-Section 5 Accessible Areas

    5-1 March 2010

    Areas that are Accessible to the Public

    The denition o areas accessible to

    the public is any paved parking lot

    or paved roadway that can be entered

    or used or public travel primarily

    or purposes unrelated to the dust

    generating operation. To determinewhether an area meets this denition,

    consider the ollowing:

    3 any paved area with local non-

    construction trac is considered

    accessible to the public.

    3 to ensure that an area is closed to

    the public it must be clearly posted

    (i.e., by using a sign that states

    Construction Trac Only). Any

    place on a site where the area under

    construction and the area open to the

    public is indistinct will be considered

    an area accessible to the public.

    sidewalks are considered paved areas

    accessible to the public, unless they

    are barricaded or marked of with

    signage. Trackout on sidewalks will

    not be included in the cumulative

    distance trackout calculation;however, trackout on sidewalks

    must be removed by the end o the

    workday.

    3 parking lots, including those in

    strip malls and churches, are always

    considered areas accessible to the

    public unless marked otherwise with

    signage to restrict public access.

    The use o signs/barricades/ropes/

    ences can help to dene a controlled

    area. While the use o yellow ropeor tape to separate the area is notrequired, it has practical value in

    ensuring that the area is seen to be

    separate rom other areas where the

    public has ready access.

    Helpful HintThe public is considered to have

    access to any paved area on your

    site unless access is clearly and

    efectively restricted. A sign and

    physical restrictions (e.g., rope

    barriers, cones) may be needed to

    ensure that the public will avoid

    an area.

    Signage restricting access to paved area

    Helpful HintTrackout extending rom your

    project onto paved areas of site is

    a common violation.

    I an area is restricted and trackout

    is present, it will not be cited as a

    trackout violation.

  • 8/8/2019 Dust Handbook

    31/82

    Section 6 - Working on Other Sites

  • 8/8/2019 Dust Handbook

    32/82

    Dust Abatement Handbook-Section 6 Subcontractors and Block Permits

    6-1 March

    Subcontractors

    Subcontractor

    Registration

    Subcontractors are hired by a permit

    holder to perorm various tasks on aconstruction site. The department

    requires that subcontractors accessing

    sites covered by a dust control permit

    obtain registration. This applies to

    any subcontractor engaged in dust-

    generating activities (e.g., driving on

    roads, landscaping, carpentry, etc.)

    Registrations are good or one year

    rom the date the registration is

    approved/issued.

    While the permit holder is responsible

    or all site activities that may resultin a violation o the provisions o

    Rule 310, subcontractors may, under

    certain circumstances, also be held

    accountable.

    Displaying Subcontractor

    Registration NumbersAnyone who enters an area that

    is subject to a Rule 310 dust

    control permit must obtain and a

    subcontractor registration number

    and ollow the requirements o each

    projects dust control permit and Dust

    Control Plan.

    The subcontractor registration number

    must be displayed on a jobsite. Methods o

    displaying the subcontractor number may

    include:

    3 a sign at the project entrance.

    3 painting it on a vehicle.

    3 a paper sign axed to the vehicle or

    equipment.

    3 a magnet sign axed to the vehicle, e.g.,

    on the door or bumper.

    3 a rear view mirror hanger.

    Subcontractors are

    Subject to Enforcement

    A subcontractor is required to abide by the

    provisions o the dust control permit and

    Rule 310 and subcontractors will be cited or

    violations o Rule 310. Potential violations

    may include:

    3 not using a trackout control device.

    3 grading when opacity exceeds 20%.

    3 loading/unloading when opacity exceeds

    20%.

    Subcontractor registration number located on vehicle bumper

    3wet utility/dry utility installation

    when opacity exceeds 20%.

    3 removal o barricades to avoid use

    a trackout control.

    3

    untarped trucks exiting a site ontopaved areas accessible to the publi

    3 truck reeboard limit exceeded and

    spillage while crossing a public are

    roadway.

    3 creating visible emissions beyond

    property lines.

    While a subcontractor will be held

    responsible or their compliance

    with Rule 310, the responsibility o

    the permit holder and the actions o

    a subcontractor can be dicult toseparate. Factors that will be taken i

    account in determining which party

    responsible include, but are not limit

    to whether the:

    3 subcontractor was inormed o the

    obligations by the permit holder.

    3 subcontractors actions can be clea

    documented.

    3 subcontractor acted in disregard o

    established site protocols.

    3 subcontractors actions were

    observed by a department inspecto

    3 subcontractor can be readily

    identied.

    Subcontractors will be heldaccountable or their violations i thesubcontractor can be easily identieandthe permit holder has establisheappropriate ugitive dust controls. Inaccordance with the departmentssubcontractor policy (dated April 18,

    2006, and included in the appendiceit should be noted that the permitholder will be cited or a violationcaused by a subcontractor unless theinspector can conrm that the permholder did not cause or contribute tothe violation by a subcontractor andthat a subcontractor ignored contro

    put in place by the permit holder.

    The need or clear documentation

    o a violation by a subcontractor

  • 8/8/2019 Dust Handbook

    33/82

    Dust Abatement Handbook-Section 6 Subcontractors and Block Permits

    6-2 March

    Subcontractors (contd)

    Subcontractor registration

    is not required for the

    following activities:

    3 lunch trucks or ood vendors

    3 waste management trucks

    3 vendor/supplier delivery

    trucks (except import, export

    and stacking operations and

    operations using ancillarymotorized equipment, such as

    a orklit)

    3 regulatory agencies

    A permit holder cannot delegate primary obligations of the

    permit to a subcontractor to avoid compliance responsibility.A permit holder may secure a subcontractor to perorm activities within

    a permit area that are considered to be primary permit obligations. For

    example, a subcontractor may be hired to install or maintain a trackout

    control device. In the event that a violation occurs (or example, the trackout

    control device is ound to be improperly maintained such that it is no longer

    efectively controlling trackout) and the violation is due to the inaction or

    untimely action o the subcontractor, the permit holder is responsible or

    compliance and subject to the penalties authorized by law. The permit

    holder is responsible for ensuring that onsite operations are being conductedin compliance with the permit. This obligation cannot be transferred to a

    subcontractor.

    Note: utilities are not considered to be subcontractors when operating under

    their own block permit.

    is essential to avoid the issuance o

    an NOV to the permit holder. For

    example, a subcontractor who has

    removed a barricade to avoid going

    over a trackout control device would

    be issued a NOV. The inspector wouldhave to observe the violation occurring

    in order to issue the NOV to the

    subcontractor. In the above scenario,

    i the subcontractor was not observed

    and the surace was no longer stable as

    a result o the subcontractors actions,

    then the permit holder would be

    issued a violation or unstabilized soil

    (assuming the soil ailed the applicable

    stability standard).

    Ultimately, a permit holder is responsible

    or all activity that occurs within a

    permitted areaincluding activities

    that are perormed by subcontractors.

    While the permit holder is responsible

    or the actions o subcontractors and

    ensuring they conorm to department

    rules when acting on their behal,

    the department reserves the right to

    pursue enorcement action against the

    subcontractor and/or the permit holder

    depending on the circumstances and

    available evidence.

    Helpful HintsAlthough not required by the

    rule, subcontractors are encour-

    aged to have their employees

    complete the comprehensive

    dust control training (six-hour

    course).

    Coordinate with the department

    to schedule a dust control

    presentation.

    Permit holders are encouraged

    to ensure that their contractual

    agreements with subcontractors

    include:

    3 provisions or the

    subcontractors to conduct theiractivities in a manner that is in

    compliance with department

    rules.

    3 provisions that hold the

    subcontractor liable or

    any penalties issued by the

    department that may be the

    result o subcontractor activity.

    Helpful HintsIt is also helpul to review the

    approved Dust Control Plan, aswell as the controls that have been

    established, with subcontractors

    prior to starting work.

    Clear communication with

    subcontractors and active

    monitoring o their on-site activity

    can be efective methods to avoid

    creating conditions that could

    result in the issuance o an NOV.

    A courtesy inspection could

    be held in conjunction with a

    meeting where subcontractors areinvited.

    The departments website

    contains a useul set o Frequently

    Asked Questions about

    subcontractor registration at

    http://www.maricopa.gov/aq/

    divisions/compliance/dust/

    subcontractorRegistration.aspx

    http://http//www.maricopa.gov/aq/divisions/compliance/dust/subcontractorRegistration.aspxhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/subcontractorRegistration.aspxhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/subcontractorRegistration.aspxhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/subcontractorRegistration.aspxhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/subcontractorRegistration.aspxhttp://http//www.maricopa.gov/aq/divisions/compliance/dust/subcontractorRegistration.aspx
  • 8/8/2019 Dust Handbook

    34/82

    Dust Abatement Handbook-Section 6 Subcontractors and Block Permits

    6-3 March

    The purpose o the block permit is to

    allow municipalities, governmental

    agencies, and utilities to conduct

    similar activities at multiple sites across

    the county. Covered activities include

    routine operation and maintenanceo urban inrastructure, as well as

    the expansion or extension o that

    inrastructure such as roads, utilities

    (e.g., pipelines and electric substations)

    and other public rights-o-way. This

    category o permit can only be issued

    to municipalities, governmental

    agencies, and utilities. While the

    permit is held by the authorized block

    permit holder, subcontractors to the

    authorized permit holder may operate

    under the cover o the permit as would

    the employees o the permit holder.The block permit will apply to those

    locations that are listed in the permit

    application. To conduct work at a

    location not listed in the application,

    the block permit holder must notiy

    the department o the intent to work

    in a new location at least three days

    in advance o the planned activity.

    The notice must include inormation

    describing the location and the

    anticipated start date o the work.

    New construction o inrastructurethat is not an extension o an existing

    system must be covered under a new

    dust control permit.

    Activity Occurring at

    Locations Not in the Block

    PermitFor any project not listed in the DustControl Block Permit application, the

    applicant is required to notiy the

    department at least three working days

    in advance o initiating the activity.

    Similarly, at new subdivisions or

    commercial developments, a utility

    will operate under its block permit and

    is required to notiy the department

    o its intention to work on a specic

    property. As with other areas, a block

    permit holder is required to provide

    the department with noticationo its intent to operate at a location

    not previously identied in its block

    permit. Notication must be provided

    in writing and with three working days

    advance notice.

    EnforcementThe permit holder retains responsibility